HomeMy WebLinkAboutApproved Minutes - 2002-08-19I.
II.
III
IV
CALL TO ORDER
City of Lake Oswego
Development Review Commission Minutes
August 49, 2002
Chair Sheila Ostly called the Development Review Commission meeting of August 19,
2002 to order at 7:20 p.m. in the Council Chambers of City Hall at 380 A Avenue, Lake
Oswego, Oregon.
ROLL CALL
Commissioners present were Chair Ostly and Commissioners Nan Binkley, Julie
Morales and Bill Tierney. Commissioners Dave Powers, Krystyna Stadnik and Gary
Fagelman were excused.
Staff present were Hamid Pishvaie, Development Review Manager; Elizabeth Jacob,
Associate Planner; Evan Boone, Deputy City Attorney; and Debbie Groves and Jean
Hall, Senior Secretaries.
APPROVAL OF MINUTES
Mr. Tierney moved for approval of the Minutes of March 18, 2002. Ms. Binkley
seconded the motion and it passed with Ms. Ostly, Ms. Binkley, Ms. Morales and Mr.
Tierney voting yes. Mr. Powers, Ms. Stadnik and Mr. Fagelman were not present.
There were no votes against.
Mr. Tierney moved for approval of the Minutes of June 17, 2002. Ms. Ostly
seconded the motion and it passed with Mr. Tierney and Ms. Ostly voting yes. Ms.
Binkley and Ms. Morales abstained from the vote. Mr. Powers, Ms. Stadnik and Mr.
Fagelman were not present. There were no votes against.
PUBLIC HEARING
LU 02-0012, a request by Mountain West Investment Corp. for approval of Conditional
Use and Development Review Permits in order to construct a 64 -unit special use
housing development for assisted living residents. The proposal includes a 3,400
square foot ground floor retail space on B Avenue, a small public park on B Avenue on
the west side of the alley, a plaza at the corner of 2nd Street and B Avenue, and 33 off-
street parking spaces along the alley. Also, 15 trees are proposed to be removed.
City of Lake Oswego Development Review Commission Page 1 of 9
Minutes of August 19, 2002
The property is located at the northwest corner of 2nd Street & B Avenue, Tax Lots
02000, 02100, 02200 of Tax Map 21E 03DD. The hearing had been continued from the
June 17, 2002 agenda. Staff coordinator is Liz Jacob, Associate Planner.
Chair Ostly opened the public hearing and explained the procedures and time limits to
be followed. She asked the Commissioners to report any ex parte conflicts, site visits,
biases and conflicts of interest. All Commissioners present reported that they had
visited the site. Ms. Ostly, Ms. Binkley and Ms. Morales recalled they had heard
previous applications for development of the site. No one challenged any
Commissioner's right to hear the application.
Elizabeth Jacob, Associate Planner, presented the staff report (see Planning Division
Staff Report dated June 7, 2002; LU 02-0012 Staff Report Addendum dated August 9,
2002; and Addendum No. 2 dated August 30, 2002). She pointed out that Exhibit F12
had been submitted on the day of the hearing. She clarified that the application was
considered a new application even though multiple approvals for a conditional use for a
portion of the site had been granted and expired between 1993 and 1998. She explained
that the original site had recently been expanded through purchases of adjacent lots on
the east and west sides of the alleyway. She advised that because the site was located
within the East End Commercial (EC) Zone, the Downtown Redevelopment Design
District, and the First Addition Neighborhood (FAN), the development was to serve as a
transitional area between residential and commercial uses. She pointed out surrounding
development included adjacent apartment uses, a three -to -four story office building and
small retail uses. She advised that the application was subject to Conditional Use
criteria and Zoning Code and Development Standards. She advised that assisted living
use was a listed conditional use in the EC Zone, and Conditional Use criteria required
the applicant to demonstrate that the proposed use was reasonably compatible with
other uses in the vicinity. She advised that the proposed Major Development was to
conform to Comprehensive Plan Policies, which included FAN Plan Policies.
Ms. Jacob focused her presentation on conditional use criteria, compliance with Special
Use Housing standards and compliance with Downtown Design District Guidelines.
She observed that the plan met zoning requirements related to applicable lot coverage,
Floor Area Ratio and height standards. She anticipated that the local infrastructure
could accommodate the proposed use. She noted the developer planned to improve the
adjacent alleyway and Second Street and install sidewalks along B Avenue. She
advised that the plan provided for sufficient landscaping and open space. She
concluded that the staff found the development satisfied the Comprehensive Plan, FAN,
Special Use Housing requirements and the Planned Development Overlay. She
reported that the staff found the proposal complied with FAN policies that called for a
transitional area of high density housing between commercial and single-family
residential land uses and would limit noise, traffic and parking impacts in the
neighborhood. She noted there would be onsite parking spaces off the alleyway and
additional street parking would be available to serve retail customers. She pointed out
that the traffic study showed the proposed use was a low -traffic generating use. She
City of Lake Oswego Development Review Commission Page 2 of 9
Minutes of August 19, 2002
noted the applicant proposed a "No Through Traffic" sign for the alleyway that would
require drivers to exit to B Avenue, rather than drive toward the neighborhood. She
advised that Comprehensive Plan Policies and Downtown Design District Guidelines
required street trees and the applicant proposed to remove 15 trees, plant new trees, and
save one special Japanese maple tree. She observed they planned to create a pedestrian -
friendly pocket park on the west side of the alley and install terraced landscaping and a
plaza at the corner of Second Street and B Avenue. She explained that Downtown
District Design Guidelines called for a "village" look. She related that the applicant
had responded to the Guidelines and concerns of the staff, the two nearby neighborhood
associations, and the Downtown Business Association by reducing the scale of the
project near the residential areas, using natural and residential architectural elements
and refashioning a "storefront" look for retail uses along B Avenue. She observed that
the slope of the site challenged the design process. She recalled the applicant had
eliminated two units in order to raise the interior height of the retail space and create
more storefront window area. She reported that the staff believed the modification of
the building design that pulled the development back from residential use to the north
and raised the center of the development presented a better balance than was shown in
the original design. She said this change eliminated the need to request an exception for
storefront appearance. She said the staff agreed with the applicant's request for an
exception that would allow them to use heavy composition roofing instead of the tile or
slate materials called for in Downtown District Design Guidelines. She said the staff
had observed that the roof system was already intricate, it would be difficult to see roof
material from the street, and tile roofing would require a different type of construction
that could require more height than that which was proposed. She reported that the
applicant wanted an exception from the Downtown Design District prohibition against
building signage in order to erect a facility -identifying sign at the main entry. She
advised that the proposed awning signs or blade signs under the awnings in front of the
retail uses would comply with Sign Code provisions for the Downtown area.
Ms. Jacob pointed out that Exhibit F12 showed a change in drainage plans that would
move facilities further away from the significant Japanese lace -leaf maple. She
explained the applicant was requesting to be allowed to cut two additional trees in order
to increase the sidewalk width to meet the Code's 8 -foot minimum width requirement
on the west side of the alley where they had originally proposed a 5 -foot wide sidewalk.
She recalled that the applicant had originally intended to attempt to save the two trees,
even though they were not in good health. She said the staff recommended a condition
that called for 3 -inch instead of 2 -inch mitigation trees. She concluded that the staff
recommended approval of the application because the applicant had shown it met
Conditional Use criteria and Special Use Housing requirements (to be close to services
and shopping).
During questioning by the Commissioners, the staff confirmed that the area of the park
had been included in required open space and landscaped area calculations; that it was
not unusual for a new subdivision to locate the open space across a street or alleyway,
as long as the area of the park could not be conveyed separately in a future real estate
City of Lake Oswego Development Review Commission Page 3 of 9
Minutes of August 19, 2002
transaction; and that the park area was to be dedicated to the City for a public park. Ms.
Binkley wondered if the presence of the pocket park eliminated space that could
otherwise be used for retail. The staff advised there was no requirement that the site
feature a specific percentage of retail space, and they pointed out that Rossman Park
was also within the EC Zone. They also confirmed that no interior building plans had
been submitted and that although the applicant's arborist believed the newly modified
drainage plans would protect the Japanese maple tree, the staff had not had an
opportunity to confirm that.
Mr. Boone recalled that the applicant had requested a continuance from the date the
application was originally scheduled to be heard, and he reported that the staff found
the supplemental application filed by the applicant to be sufficiently different from the
original application that the 120 -day time period was to be restarted as of July 29, 2002.
Applicant
Edward Sullivan, 222 SW Columbia, Ste 1400, Portland, Oregon, 97201, testified
on behalf of the applicant. He said the applicant agreed with the staff report and would
accept the conditions recommended by the staff. He explained that the applicant's team
had delayed the hearing in order to listen to all interested parties and then revised their
proposal to earn the support of the parties. He said the applicant had made their best
effort to make the development consistent with Lake Oswego style and compatible with
the neighborhood. He emphasized that the application demonstrated the proposal met
every one of the City's design and conditional use standards. He cautioned the
Commissioners to focus on the issue of whether or not the use complied with the Code
and not stereotyped characterizations of site users' shopping habits. He advised that
there were federal and state laws that protected the proposed use.
Kelley O. Hamilton, Chairman, Mountain West Investment Corporation, 245
Commercial Street, #200, Salem, Oregon, 97301, explained that his firm developed
assisted living facilities that provided a housing type that served senior citizens who
were still mobile but felt isolated in their own home. He explained that the applicant
had selected the City of Lake Oswego and zip code 97034 for the development because
the 2000 Census showed that one in nine City residents were over 65 years of age, and
one in 18.5 residents were at least 75 years old, and his firm had found those residents
were underserved within the City.
Ben Settecase, Proiect Manager, Mountain West Investment Corporation, 245
Commercial Street, #200, Salem, Oregon, 97301, recalled the history of the site and
the proposal. He noted the current site included the area where a senior housing project
had been approved by the DRC three times in the past, plus two recently purchased
adjacent parcels. He noted the design included elements and materials that reflected
Lake Oswego style. He related how the applicant had revised their proposal several
times and asked for a continuance of the previously scheduled hearing in order to
respond to different concerns of the First Addition Neighborhood (FAN), the
City of Lake Oswego Development Review Commission Page 4 of 9
Minutes of August 19, 2002
Downtown Business Association and City staff. He recalled their concerns related to
parking, a weak storefront presence along B Avenue, the number of units proposed for
the facility and the impact of the height of the building on the neighborhood. He related
that although a FAN representative had agreed the applicant could eliminate retail uses
in order to include more living units, the staff had advised the applicant to include retail
space, and the local business association had asked for a stronger storefront presence.
He pointed out the current proposal included retail use, 66 living units, and better
defined entries. He noted the current plan eliminated two second floor living units in
order to accommodate taller retail ceilings. He said the current plan featured 57,000
square feet, 64 assisted living units and 3,400 square feet of retail space.
Tom Armstrong, Winterbrook Planning, 310 SW Fourth Avenue, #1000, Portland,
Oregon, 97204, testified that the proposal met the City's standards and criteria. He
pointed out how the design flowed from a corner public plaza that featured a significant
Japanese maple tree and how the retail space was separated from the residential space.
He explained that the applicant proposed to install a seven -foot wide sidewalk on 2nd
Street, except in the area where the walk had to be narrower in order to avoid impact on
the Japanese maple tree. He noted the landscape plan showed 53 trees that would
buffer the development, and the building had been stepped back at the north end and
most of its height had been relocated to the center of the development. He pointed out
the site sloped toward the corner of 2nd Street and B Avenue. He explained that the
applicant's team had not submitted an interior floor plan because they had focused on
presenting the exterior of the building at the hearing. He advised the development
featured more landscaped open space (34%) than the 20% currently required for Special
Use Housing and he specified that the site was to include two public spaces at the
pocket park and corner plaza. He said the development would serve as a transition
between the neighborhood and Downtown and would provide retail stores along B
Avenue that would enhance the area's pedestrian/shopping environment. During
questioning by the Commissioners, he pointed out examples of the proposed materials
on the material board. Mr. Armstrong and landscape architect, Bob Foster, 431 Ash
Street, Lake Oswego, 97034, explained the applicant planned to dedicate the pocket
park to the City and also to install and dedicate a pedestal in the plaza to display City
sculpture.
Greg Elmore, Mountain West Investment Corporation, 245 Commercial Street,
#200, Salem, Oregon, 97301, clarified that the alleyway sloped downward toward the
corner of 2nd Street and B Avenue (see revised plans in Exhibit 18 of the August 9,
2002 Addendum). He also clarified that the facility's administrative offices and
common living areas were behind a portion of the storefront and an arched entry area at
the corner plaza. He explained that the main entry would feature stucco -covered
columns with a stone base and there were to be residential units and a balcony area on
top of it (see Exhibit E19). He said the kitchen and commercial laundry would be
below ground level. He emphasized that the B Avenue wing had been designed on the
slope down to the corner of 2nd and B Avenue. He pointed out where the plan had been
revised to lower the building at its north end and move two units toward the center of
City of Lake Oswego Development Review Commission Page 5 of 9
Minutes of August 19, 2002
the development and over the entry (see Exhibit E20). He clarified that tiny windows
and vents in the gable ends indicated space used for vaulted ceilings and did not
accommodate an additional floor level. He confirmed that all mechanical units were to
be on the rooftop (see Exhibit E20 and floor plans in Exhibit E19). He confirmed for
Ms. Binkley that the gables would not appear to be "chopped off' from some
perspectives, as they appeared on the Block 136 development. He clarified the building
would feature shingles on the third floor, on all gabled areas, and as design elements
above rock on the lower level. He clarified that the samples of cultured stone on the
material board were smaller sized samples and some would be larger. He clarified the
chimney shown in the west elevation would serve the commercial kitchen, state
regulations prohibited fireplaces in the units, and common areas would feature vented
fireplaces that did not require exterior chimneys. He pointed out the location of the
main electrical facility in Exhibit E17 and he clarified the electrical meter (or perhaps
two meters) for the facility would be as close to the alley as possible for drive-by
reading. Mr. Pishvaie advised that all meters were required to be screened and the staff
would revise the conditions of approval to reflect that requirement. Mr. Elmore referred
to Exhibit E18 and clarified that window trim and vertical corner boards would be 4
inches wide and fascia boards would be 8 inches wide. He confirmed the west alleyway
entry elevation would feature stucco finish. Ms. Binkley commented that the stucco
exacerbated the large scale of that portion of the building and she noted the materials
board did not include an example of the stucco.
Proponents
John V. Pinson, 570 7th Street, Lake Oswego, 97034, testified that he had constructed
a five -unit row house development near the corner of 2nd Street and C Avenue that
featured a wide age range of residents. He opined that the applicant's project provided
a sensible transition between residential and commercial uses. He explained that he
knew several residents who had been forced to leave the City because they had not been
able to find assisted living housing within the City.
Mr. Boone advised the Commissioners that the issue of public need had already been
addressed when the City Council adopted zoning for the site.
Will Denecke, 2665 SW Glen Eagles Road, Lake Oswego, 97034, testified that the
site was a sensible location for the proposed pedestrian -oriented mixed use (see his
letter in Exhibit G104). He noted the neighborhood would benefit from the fact that
the proposed use would not generate a high level of traffic. He anticipated that the
development would create more retail uses and housing in the neighborhood.
Mr. Boone advised the Commissioners that because the proposed use was a conditional
use that was to be allowed somewhere in the zone, the issue to be considered was
whether the proposed site was an appropriate location within the zone for the use and
any impacts it would have on the neighborhood. He also advised that one criterion for
Special Use Housing was access to commercial facilities.
City of Lake Oswego Development Review Commission Page 6 of 9
Minutes of August 19, 2002
Rita Haines, 5049-D Foothills Road, Lake Oswego, 97034, recalled her experience as
a senior real estate sales specialist. She advised that the City was not served by a
sufficient amount of senior housing.
Opposition
James Bolland, Chair, First Addition Neighborhood, 804 Stn Street, Lake Oswego,
97034, asked that the hearing be continued to allow representatives from FAN and the
Evergreen Neighborhood Association an opportunity to study the most recent revisions
of the applicant's proposal and to prepare testimony for a future hearing. He read an
August 19, 2002 letter from the Downtown Business Association into the record (see
Exhibit G200). The letter stated that the business owners had not received a notice of
the hearing or a copy of the LU 02-0012 Staff Report Addendum. It stated that the
Association was opposed to the project because the proposed use was incompatible with
Lake Oswego redevelopment goals and the issues of the design of the retail storefronts
and pedestrian access to the core areas had not been fully addressed.
The Commissioners acknowledged Mr. Bolland's request for a continuance and decided
to continue to hear testimony at the meeting.
Mr. Bolland corrected the staff report by clarifying that the previous development that
had been approved for the site was not an assisted living facility, but a senior
independent living facility. He also clarified that he had not recommended that the
applicant delay the previous hearing, but had only recommended to the applicant's
representative that they needed to invite comments from the Evergreen Neighborhood
Association as well as FAN, and that could most likely not be accomplished in time for
that hearing.
Norma Petersen, 890 F Avenue, Lake Oswego, 97034, observed that residents were
leaving the City because of the cost of living in Lake Oswego and that the applicant's
facility would be an expensive place to live. She stated the proposed facility would be
incompatible with FAN and the surrounding business community due to its size and
density, which exceeded all other FAN residential and business structures. She said the
proposal disregarded the FAN Plan to preserve neighborhood character. She
anticipated that residents of the new facility would need to be driven to shopping and
services, which would increase traffic and parking problems in the area. She questioned
whether there was sufficient parking for employees and visitors. She submitted a
signed petition for the record (see Statement of Testimony in Exhibit G201).
Rebuttal
Mr. Sullivan observed the applicant had submitted most of their materials to the record
at least two months prior to the hearing and the opponents had had sufficient
opportunity to prepare testimony. He suggested that if the Commissioners continued
City of Lake Oswego Development Review Commission Page 7 of 9
Minutes of August 19, 2002
the hearing, it would be fairer to the applicant for them to limit the continued hearing to
written testimony and the applicant's response.
The Commissioners generally agreed that it was best to allow oral testimony at the next
hearing in order to adequately hear testimony related to design issues and because of the
significance of the project. Mr. Sullivan encouraged the Commissioners to provide a
taped record of the hearing to the absent Commissioners before the next hearing. Mr.
Tierney observed that the staff reports had been available to all parties well in advance
of the hearing, but he said he believed that it was important to allow additional oral
testimony at the next hearing. The Commissioners listed issues to be addressed at the
next hearing. Ms. Ostly and Ms. Binkley indicated they desired to see a better design
for the main entry. Ms. Binkley noted the proposed entry seemed massive and seemed
to project over the street and the proposed materials were inappropriate. She also
opined the window walled storefront seemed too commercial for retail use. She asked
for an up-to-date floor plan and a stucco sample. She suggested the applicant consider
an alternative material to stucco. Ms. Morales asked for a roof plan and she also voiced
her desire to see a floor plan and a model that would show massing. Mr. Tierney asked
for specific color samples.
Ms. Binkley moved to continue LU 02-0012 to September 4, 2002. Ms. Morales
seconded the motion and it passed with Ms. Ostly, Ms. Binkley, Ms. Morales and Mr.
Tierney voting yes. Mr. Powers, Ms. Stadnik and Mr. Fagelman were not present.
There were no votes against.
V. FINDINGS, CONCLUSIONS AND ORDER
LU 02-0025, a request by Gramor Oregon, Inc
The staff reported they had added two conditions - B8 and B10 - to specify the canopy
sign was to be installed on top of the canopy and to clarify that secondary signage types
did not include awnings.
Ms. Morales moved for approval of LU 02-0025, Findims, Conclusions and Order.
Mr. Tierney seconded the motion and it passed with Ms. Ostly, Ms. Binkley, Ms.
Morales and Mr. Tierney voting yes. Mr. Powers, Ms. Stadnik and Mr. Fagelman were
not present. There were no votes against.
VI. GENERAL PLANNING
Boones Ferry Road/Lake Grove Main Street Plan Committee
The Commissioners designated Mr. Fagelman as their representative on the Committee.
Request for continuance of a hearing
City of Lake Oswego Development Review Commission Page 8 of 9
Minutes of August 19, 2002
Mr. Boone clarified that anyone was allowed to request a continuance at the first
evidentiary hearing.
VII. ADJOURNMENT
There being no further business before the Commission, Chair Ostly adjourned the
meeting at 9:40 p.m.
Respectfully submitted,
Jean Hall
Senior Secretary
L:\dre\minutes\08-19-02.doc
City of Lake Oswego Development Review Commission Page 9 of 9
Minutes of August 19, 2002