Subject: 2020 Wastewater Collection System Rehabilitation Project: Work Order 277
Meeting Date: May 5, 2020 Staff Member: Stefan Broadus, P.E.
Department: Engineering
Action Required Advisory Board/Commission Recommendation
Z Motion ❑ Approval
❑ Public Hearing ❑ Denial
❑ Ordinance ❑ None Forwarded
❑ Resolution Z Not Applicable
❑ Information Only Comments:
❑ Council Direction
Z Consent Agenda
Staff Recommendation: Award a Public Improvement Contract
Recommended Language for Motion: Move to Award a Public Improvement Contract with
Moore Excavation, Inc. for construction of the 2020 Wastewater Collection System
Rehabilitation Project, Work Order 277, in the amount of$1,309,035.50.
Project/ Issue Relates To:
❑X Council Goals/Priorities ❑X Adopted Master Plan(s) ❑Not Applicable
BACKGROUND
On September 4, 2018, Council authorized the execution of a personal services contract (PSC)
with Wallis Engineering to provide engineering and project management services for
wastewater collection infrastructure rehabilitation. City Council and City staff have identified
investing in our infrastructure as a long-term priority in order to prolong the life of the City's
assets. The PSC was executed, and Wallis Engineering has been providing those engineering
and construction management services. The PSC is for multiple rehabilitation projects over
several years. The first project was for rehabilitation of the wastewater collection
infrastructure in Wembley Park Road; which was completed in January 2020. The second
rehabilitation project is the Work Order 277 —2020 Wastewater Collection System
503.635.0215 380 A Avenue PO BOX 369 Lake Oswego, OR 97034 www.lakeoswego.city
Page 2
Rehabilitation Project, which is the subject of this Council Report. This wastewater collection
system rehabilitation project is funded in the most recent Capital Improvement Plan dated June
4, 2019.
DISCUSSION
This project will rehabilitate approximately 2100 linear feet of sanitary sewer by lining the
existing pipeline with Cured In Place Pipe (CIPP), rehabilitating approximately 1500 linear feet
of sanitary sewer by hydraulically ramming a bursting head through the old pipe and pulling in a
new High Density Polyethylene (HDPE) pipe behind as replacement pipe, replacing
approximately 1500 linear feet of sanitary sewer pipeline by open cut trenching, and
rehabilitating several miscellaneous accessories such as laterals and manholes. The composite
project is comprised of 15 individual project areas distributed around the City of Lake Oswego.
This project was advertised on March 30th. Bids were opened on April 23rd with 3 proposals
received as listed in the table below. Construction is expected to begin in May and to be
completed in late 2020.
Bid Company Amount Bid
1 Moore Excavation, Inc. $1,309,035.50
2 Emery & Sons Construction Group, LLC $1,466,644.00
3 K&R Plumbing Construction Co., Inc. $1,604,235.00
FISCAL NOTE
This project is budgeted from the Wastewater fund.
Funding FY 2018-19 FY 2019-20 FY 2020-21 Total
Source
Wastewater $127,714 $1,400,000 $500,000 $2,027,714
RECOMMENDATION
Authorize the City Manager to sign a public improvement contract with Moore Excavation, Inc.
in the amount of$1,309,035.50 for construction of the 2020 Wastewater Collection System
Rehabilitation Project: Work Order 277.