HomeMy WebLinkAbout2021-2027 CIP Funding PlanFUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 1
…..…..………...…………...Projected…..…..………………….…
Parks and Open Space
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
Adult Community Center WO 295 Bonds 2,000,000 2,000,000
Luscher Farm Access Bonds 1,000,000 1,000,000
Municipal Golf Course WO 306 Bonds 3,000,000 3,000,000
Rassekh Park Development WO 307 Bonds 800,000 4,000,000 4,800,000
RecreaƟ on/AquaƟ cs Center WO 305 Bonds 5,000,000 10,000,000 14,000,000 29,000,000
Stevens Meadow and Cooks BuƩ e Parking
(Stevens Homestead)
General 400,000 400,000
Total 12,200,000 14,000,000 14,000,000 0 0 0 40,200,000
Parks and Open Space
Unfunded
AthleƟ c Fields (ArƟ fi cial Turf) SDC/Bond 1,000,000
Bryant Woods/Canal Acres/River Run 1 & 2 SDC/Bond 2,700,000
Land AcquisiƟ on/Natural Areas and Parks SDC/Bond 3,000,000
Luscher Farm Trails Gen/SDC/
Tourism
250,000
Luscher Environmental Classroom SDC/Bond 1,500,000
Luscher Urban Agriculture Expansion SDC/Bond 1,500,000
Miscellaneous Water Dependent FaciliƟ es General 739,000
Neighborhood Parks General/SDC 2,600,000
Parks Structures Replacement General/Bond 1,000,000
Pilkington Park SDC 1,400,000
Skatepark SDC/Bond 1,465,000
Sport Court RenovaƟ on General/ Bonds 500,000
Southwood Park Subdivision General/SDC 402,000
Tryon Cove Park SDC/Bond 2,000,000
Total 0 0 0 0 0 0 20,056,000
…..…..………...…………...Projected…..…..………………….…
Pavement PreservaƟ on (Streets & Overlays)
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27
Total
Funded/Projected
Annual Pavement Management Program Street 2,000,000 200,000 2,000,000 2,000,000 6,200,000
Blue Heron Rd RehabilitaƟ on & Drainage Im-
provements
Street 303,000 910,000 1,213,000
Cameo Ct. Rd ReconstrucƟ on LID WO 284 Street 221,000 221,000
Citywide Annual Paving 2021/22 WO 300 Street 3,200,000 3,200,000
Citywide Annual Paving 22/23 Street 2,400,000 3,100,000 5,500,000
Citywide Pavement PreventaƟ ve Maintenance Street 100,000 400,000 500,000
Firwood Rd Upgrade: Boones Ferry Rd to Waluga
Dr
Street 250,000 250,000
Lakeview Blvd St & Drainage Improvements Street 1,000,000 4,275,000 825,000 6,100,000
Total 5,921,000 3,500,000 3,303,000 5,385,000 2,825,000 2,250,000 23,184,000
FUNDING PLAN SUMMARY
2 City of Lake Oswego Capital Improvement Plan 2021-2027
Bridges
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded
Blue Heron Bay at South Shore Blvd Bridge
Replacement (BR006)
Street 2,367,000
Lakewood Bay at North Shore Rd (BR001) Street 2,605,000
Oswego Canal Bridge at Bryant Rd (BR010) Street 3,920,000
Springbrook Creek at Summit Dr (BR009) Street 10,112,000
SPRR Overpass, Summit Dr Clackamas County
Bridge (BR015)
Street 2,003,000
West Bay at South Shore Blvd (BR005) Street 3,126,000
Total 0 0 0 0 0 0 24,133,000
…..…..………...…………...Projected…..…..………………….…
Roadway Improvements (Other Infrastructure
Improvements)
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
Boones Ferry Rd Phase 1 LORA 2,050,000 2,050,000
Total 2,050,000 0 00002,050,000
Roadway Improvements (Other Infrastructure
Improvements)
Unfunded
3rd & 4th St ReconstrucƟ on: A Ave to B Ave (TSP
228)
LORA/St 2,894,000
A Ave Enhancements: 4th St to 6th St (TSP 229) Street 1,391,000
Astor Ave Upgrade: Washington Ct to Harrington
(TSP 57)
Street 1,890,000
B Ave/1st St IntersecƟ on Improvements (TSP 108) Street 3,000,000
B Ave Improvements: State to 2nd St (porƟ on of
North Anchor TSP 225)
LORA/St/Dev 1,596,000
B Ave Phase 1 (Foothills Project) (TSP 136) SDC/Dev 3,997,000
B Ave Phase 2 (Foothills Project) (TSP 136) SDC/Dev 2,247,000
B Ave Improvements: 2nd to 5th St (TSP 226) LORA 3,390,000
Baleine St Upgrade: Allison to Inverurie (TSP 55) Street 1,951,000
Pavement PreservaƟ on (Streets & Overlays)
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded
Boca Raton Dr Roadway Improvements Street 2,333,000
First AddiƟ on Roadway & Drainage Improve-
ments-Group 1
Street 2,260,000
First AddiƟ on Roadway & Drainage Improve-
ments-Group 2
Street 3,486,000
Meadows Rd Pavement RehabilitaƟ on Project Street 5,628,000
Total 0 0 0 0 0 0 13,707,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 3
Foothills Rd Phase 1: A to B Avenues (Foothills
Project) (TSP133)
SDC/Dev 3,636,000
Foothills Rd Phase 2: North of B Avenue (TSP 134) SDC/Dev 2,067,000
Hallmark Dr FesƟ val St (TSP 152) Street 1,180,000
Inverurie Rd Upgrade: Carman to Wash Ct./Lake
Forest (TSP 56)
Street 6,350,000
Kerr Parkway/Boones Ferry Rd/Country Club Dr
IntersecƟ on Improvements (TSP 109)
Street 218,000
Lake Forest Blvd Upgrade: Boones Ferry Rd via
Washington Ct to Carman Dr (TSP 52)
Street 4,529,000
Lakeview Blvd Truck RestricƟ on (TSP 304) Street 347,000
Lakeview Blvd/65th Ave/McEwan Rd Improve-
ments (TSP 301)
Street 3,100,000
Lake Grove Public Parking Areas (TSP 172) Street/LORA 9,210,000
Lake Oswego Transit Center: 5th St Reconstruc-
Ɵ on A Ave to B Ave (TSP 102)
Street 1,581,000
MercanƟ le Dr/Boones Ferry Rd IntersecƟ on
Improvements (TSP 138)
Street 23,000
MercanƟ le Dr Upgrades: Boones Ferry Rd to Kruse
Way (TSP 156)
Street 20,000
Monroe Parkway: Greenridge Dr to Boones Ferry
Rd (TSP 121)
Street 22,000
North Portal: Foothills Rd Upgrade Phase 2 D and
E Avenues (TSP 135)
Street 2,186,000
Oakridge Rd Improvements: Quarry Rd to Boones
Ferry Rd (TSP 160)
Street 962,000
Quarry Rd-Galewood: IntersecƟ on Improvements
(TSP 155)
Street 37,000
Seville Ave Sidewalk: Lake Forest to Roosevelt
(TSP 51)
Street 2,112,000
Tryon Creek Bridge and Culvert Replacement (TSP
231)
Street/Grant 2,191,000
Westview Dr: Driver Feedback Sign Street 40,000
West Sunset Extension Signal to Upper Dr (TSP
230)
Street 1,746,000
Total 0 0 000092,965,000
…..…..………...…………...Projected…..…..………………….…
IntersecƟ ons
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
Jean/Pilkington IntersecƟ on Improvements (TSP
62) (WO 273)
SDC 1,098,000 1,098,000
Total 1,098,000 0 0 0 0 0 1,098,000
Roadway Improvements (Other Infrastructure
Improvements)
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded (cont.
Bergis Rd Realignment (TSP 223) Street 2,417,000
Boones Ferry Rd Improvements Phase 2 (1.2) LORA 26,500,000
Carmen/Lake Forest IntersecƟ on Geometry Im-
provement (TSP 70)
Street 135,000
FUNDING PLAN SUMMARY
4 City of Lake Oswego Capital Improvement Plan 2021-2027
…..…..………...…………...Projected…..…..………………….…
Pathways
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
ADA Sidewalk Ramp Retrofi t Program Street 100,000 100,000 100,000 100,000 100,000 100,000 600,000
Boca Ratan Pathway - Bonniebrae Drive to Atwa-
ter Rd Street 150,000 400,000 550,000
Douglas Way Pathway - Hallmark to Boones Ferry
Rd Street 75,000 175,000 250,000
Douglas Way Pathway - Quarry Rd to Hallmark Dr Street 125,000 525,000 650,000
Future School Related Priority Pathways Street 500,000 500,000 500,000 500,000 2,000,000
Hallinan Street Pathway - Hemlock Street to
Cherry Lane Street 125,000 375,000 500,000
Lanewood Street Pathway - Boones Ferry Rd to
Twin Fir Rd Street 100,000 250,000 350,000
Third Street Curb Ramps WO 313 Street 45,000 45,000
Total 720,000 1,825,000 600,000 600,000 600,000 600,000 4,945,000
IntersecƟ ons
Funding
Source 2021-22 2022-23 2023-24 024-25 2025-26 2026-27 Total
Unfunded
6 Corner IntersecƟ on Alignment Improvements
(TSP 54)
Street 1,255,000
65th Ave/McEwan Rd IntersecƟ on Improvement
(TSP 302)
Street 488,000
A Ave/8th Signal Improvements (TSP 66) Street 71,000
Bangy/Bonita Signal Interconnect (TSP 72) Street 69,000
Boones Ferry Rd/Knaus Rd Signal InstallaƟ on Street 1,392,000
Boones Ferry Rd at MercanƟ le Pedestrian Cross-
walk Signal
Street 110,000
Boones Ferry Rd Signal Interconnect: I-5 to Bryant
(TSP 71)
Street 326,000
Bryant Rd/Childs Rd Signal InstallaƟ on (TSP 68) Street 727,000
Bryant Rd/Lakeview Blvd IntersecƟ on Improve-
ment
Street 614,000
Carman Dr/Bonita Rd/Waluga Dr Signal Installa-
Ɵ on
Street 2,327,000
Goodall Rd/Country Club/Uplands Dr Signal Instal-
laƟ on
Street 3,647,000
Hwy 43/McVey Ave IntersecƟ on Improvements
(TSP 111)
Street 45,000
Hwy 43/Terwilliger IntersecƟ on Improvements
(TSP 110)
Street 45,000
Jean Rd/Jean Way IntersecƟ on Improvement (TSP
303)
Street 238,000
Staff ord Rd/Bergis Rd Signal InstallaƟ on (TSP 141) Street 1,304,000
Total 0 0 0 0 0 0 12,658,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 5
Pathways 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded
Funding
Source
10th Street Sidewalk: E Ave to G Ave (TSP 215) Street 442,000
Ash St Sidewalk & Pathway: Erickson to O’Brien St
(TSP 176)
Street 653,000
Atwater Rd Sidewalks: Knaus Rd to Boca Ratan Dr
(TSP 213)
Street 820,000
B Ave Sidewalk: 9th St to 10th St (TSP 218) Street 29,000
Barton Rd Pathway: Riven Dell Rd to Childs Rd
(TSP 184)
Street 1,213,000
Bergis Rd/Cornell Pathway: Bergis Farm Dr/Cornell
St to exisƟ ng path (TSP 100)
Street 738,000
Berwick Rd Pathway: Berwick Ct to Ellis Ave (TSP
44)
Street 47,000
Boones Ferry Rd Pathway: Washington Ct to Pilk-
ington Rd (TSP 132)
Street 164,000
Burma Rd Sidewalks: Bangy Rd to Carman Dr (TSP
199)
Street 965,000
C Ave Sidewalk: 10th St to Country Club (TSP 219) Street 558,000
Canyon Dr Neighborhood Pathway: Dellwood to
South Shore (TSP 4)
Street 716,000
Centerwood St Sidewalk: Red Leaf to city limit
(TSP 84)
Street 138,000
Childs Rd (east) Pathway: Staff ord to 35th (TSP 97) Street 4,386,000
Childs Rd (west) Pathway: Canal Rd to Sycamore
Ave (TSP 7)
Street 503,000
Cloverleaf Dr Sidewalk: Banyan to Fernwood Dr
(TSP 53)
Street 417,000
Crest Dr Pathway: Prestwick Rd to Ridgecrest (TSP
207)
Street 627,000
Daniel Way Sidewalk: Kruse Woods Pl to Carman
Dr (TSP 9)
Street 254,000
Dellwood Dr Pathway: Canyon Dr to Fernwood Cir
(TSP #183)
Street 156,000
Depot Street Pathway: Lakeview Blvd to Bridge-
port to Milwaukie Regional Trail (TSP 188)
Street 210,000
Douglas Way Pathway Entrance: Barricade Replac-
ing DelineaƟ on Poles
Street 35,000
E Ave Pathway: 4th to 10th (TSP 10) Street 691,000
E Ave Sidewalk: State to 1st (TSP 58) Street 172,000
Erickson St Sidewalk: Maple St to Laurel St. (TSP
178)
Street 676,000
Evergreen Rd Pathway: 4th to 10th (TSP 45) Street 227,000
F Ave Pathway: 10th St to ACC (TSP 216) Street 480,000
Fernwood Circle Pathway: Fernwood Dr to Fern-
wood Dr (TSP 48)
Street 508,000
FUNDING PLAN SUMMARY
6 City of Lake Oswego Capital Improvement Plan 2021-2027
Pathways
Funding
Sourc 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded (cont.)
Fernwood Dr: South Shore to Marjorie (TSP 11) Street 1,126,000
Fir Ridge Rd Sidewalk: Twin Fir to Wembley Park
Rd (TSP 12)
Street 144,000
Fosberg Rd Pathway: Melrose to Carman (TSP 81) Street 300,000
G Ave Pathway: 4th to 2nd St (TSP 217) Street 353,000
Glen Eagles Pl Pathway: Wembley Park Rd to Glen
Eagles Rd (TSP 205)
Street 221,000
Glen Eagles Rd Pathway: Wembley Park Rd to
Prestwick (TSP 204)
Street 802,000
Glenmorrie Dr (West) Pathway: Green Bluff to
Hwy 43 (TSP 99)
Street 295,000
Glenmorrie Dr (West) Sidewalk: Cherry Ln to
Green Bluff Dr (TSP 174)
Street 992,000
Goodall Rd Pathway: Knaus to Country Club (TSP
15)
Street 1,088,000
Green Bluff Pathway: Wayside to Glenmorrie Dr
(TSP 98)
Street 1,871,000
Greentree Rd Sidewalk: Fernwood to Westview
(TSP 16)
Street 889,000
Harvey Way-MercanƟ le Dr Pathway ConnecƟ on
(TSP 165)
Street 441,000
Hemlock St Sidewalk: Parrish to Cornell (TSP 179) Street 670,000
Hillside Dr Sidewalk: Palisades Crest Dr to Fern-
wood Cir (TSP 47)
Street 235,000
Hwy 43 Buff ered Pathway: Public Storage to
Briarwood (TSP 74)
Street 2,733,000
Kelok Pathway: South Shore to Bryant Rd (TSP 17) Street 2,067,000
Kerr Pkwy (north) Pathway: PCC to Multnomah.
Co line (TSP 73)
Street 2,127,000
Knaus Rd Pathway: Boones Ferry Rd to Country
Club Rd (TSP 19)
Street 5,699,000
Kruse Way Enhanced Sidewalk: MercanƟ le Dr to
Boones Ferry Rd (TSP 153)
Street 512,000
Kruse Way Pathway: Galewood Pathway Connec-
Ɵ on (TSP 164)
Street 79,000
Lake Forest Dr Pathway: Ellis Ave to Berwick Rd
(TSP 43)
Street 224,000
Lake Oswego to TualaƟ n Trail (TSP 144) Street 3,259,000
Lakeview Boulevard Pathway: Bryant Rd to South
Shore Blvd (TSP 124)
Street 743,000
Lakeview Blvd Pathway: Jean Rd to 65th Ave (TSP
75)
Street 735,000
Lakeview Blvd Pathway: Summit Dr to Iron Mtn
Blvd (TSP 20)
Street 2,029,000
Lakewood Rd Sidewalk: North Shore to Lake
Oswego Swim Park (TSP 221)
Street 411,000
Lanewood-Lake Grove Ave Pathway ConnecƟ on
(TSP 163)
Street 259,000
Lee St Sidewalk: Hemlock St to Aspen Park/Pali-
sades 2 Resv (TSP 180)
Street 386,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 7
Pathways
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded (cont.)
Library to ACC Pathway (TSP 23) Street 400,000
LO-Tigard/Bridgeport-to-Milwaukie Trail Connec-
Ɵ on (TSP 145)
Street 1,793,000
Maple St Sidewalks: Erickson to GRP Trail (TSP
177)
Street 472,000
Marjorie Ave Pathway: Fernwood Dr to Cloverleaf
Dr (TSP 182)
Street 149,000
McNary Parkway Pathway: Kerr Parkway to
Churchill Downs (TSP 120)
Street 583,000
Meadowlark Lane Sidewalk: Overlook Dr to Ridge
Pointe Dr (TSP 24)
Street 313,000
MercanƟ le Dr Sidewalk: Hallmark to Boones Fry
Rd. (TSP 25)
Street 347,000
Mossy Brae Rd Pathway: River Run Park to Staf-
ford Rd. (TSP 185)
Street 3,303,000
North Shore Pathway: Cabana Ln to Hwy 43 (TSP
220)
Street 1,419,000
Oak St Pathway: McVey to Palisades Terrace Dr
(TSP 26)
Street 168,000
Oakridge Rd Sidewalk: Bonaire to Waluga Rd (TSP
159)
Street 1,584,000
O’Brien St Sidewalk & Pathway: Ash St. to Hallinan
Open Space (TSP 175)
Street 309,000
Palisades Crest Dr Neighborhood Sidewalk: Hill-
side Dr to Cook’s BuƩ e Park (TSP 27)
Street 191,000
Pilkington Rd Pathway: Pilkington Park/Dawn St to
Childs Rd (TSP 90)
Street 116,000
Prestwick Rd Pathway: Glen Eagles Rd to Crest Dr
(TSP 206)
Street 368,000
Quarry Rd Sidewalk: Oakridge to Boones Ferry Rd
(TSP 158)
Street 142,000
Red Leaf St Sidewalk: Pilkington to Tualata (TSP
82)
Street 126,000
River-to-River Trail (TSP 94) Street 7,369,000
Roosevelt Ave Sidewalk: Washington Ct to Har-
rington (TSP 50)
Street 1,790,000
South Shore Blvd Pathway: Lakeview to McVey
(TSP 88)
Street 8,379,000
Staff ord Rd Pathway: Rosemont to Childs (TSP 96) Street 3,024,000
Sunningdale Rd Sidewalks: Andrews Rd to 10th St
(TSP 214)
Street 415,000
Thoma Rd Sidewalk & Pathway: Knaus Rd to LO
High School (TSP 209)
Street 396,000
Timberline Drive Sidewalk: Knaus Rd to Bon-
niebrae Dr (TSP 29)
Street 593,000
Touchstone Rd Pathway: Kerr Parkway to Carman
Drive (TSP 130)
Street 53,000
FUNDING PLAN SUMMARY
8 City of Lake Oswego Capital Improvement Plan 2021-2027
…..…..………...…………...Projected…..…..………………….…
Bicycle Pedestrian Pathways
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded
5th St at A Ave Crossing: RRFB Retrofi t Street 18,000
65th Ave Bike Lanes, Sidewalks: Lakeview Blvd to
Childs Rd (TSP 131)
Street 2,628,000
Bonita Rd Sidewalks/Bike Lanes: Bangy Rd to Car-
man Dr (TSP 80)
Street 4,515,000
Boones Ferry Rd Bike Lanes: Country Club to
northern city limits (TSP 36)
Street 1,290,000
Boƫ celli Bike Lanes ReconstrucƟ on: Melrose to
Touchstone (TSP 93.1)
Street 1,863,000
Boƫ celli Bike Lane: Melrose to Touchstone (TSP
93.2)
Street 23,000
Bridgeport to Milwaukie Regional Trail Connec-
Ɵ on: Upper Dr to Bridgeport to Milwaukie Re-
gional Trail (TSP 194)
Street 315,000
Bryant Rd Bike Lanes and Pathway - Boones Ferry
Rd to Childs Rd (TSP 37)
Street 1,297,000
Carman Dr Sidewalks & Bike Lanes: Kruse Way to
I-5 (TSP 5)
Street 480,000
Pathways
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded (cont.)
Treetop Ln Sidewalk: Overlook Dr to Fernwood
Dr (TSP 46)
Street 228,000
Tualata Sidewalk: Red Leaf to Jean Rd (TSP 83) Street 602,000
Twin Fir Rd Pathway: Upper Drive & Boones Ferry
Rd (TSP 30)
Street 2,335,000
Uplands Dr Pathway: Ridgecrest Rd to Wembley
Park Rd (TSP 208)
Street 376,000
Waluga Dr Pathway: Oakridge to Madrona (TSP
#31)
Street 366,000
Washington Court Pathway: Queens Park Rd to
Lake Forest Blvd (TSP 32)
Street 637,000
Westlake Dr Sidewalk: Kruse Way to Amberwood
Circle (TSP 85)
Street 574,000
Westview Dr Sidewalk: Greentree Rd to South
Shore (TSP 33)
Street 1,148,000
WillameƩ e Greenway Trail: WillameƩ e Shore Line
(Trolley) Trail (TSP 95)
Street 6,046,000
WillameƩ e River Greenway Trail: Foothills Park to
Tryon Cove Park (TSP 87)
Street 1,556,000
WillameƩ e River Greenway Trail:
George Rogers Park to Riverbend Condos (TSP 86)
Street 401,000
WillameƩ e River Greenway Trail: Roehr Park
Pathway Repair/Upgrade (TSP 28)
Street 318,000
WillameƩ e Steps (TSP 137) Street 2,778,000
Total 0 0 000094,525,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 9
…..…..………...…………...Projected…..…..………………….…
Water
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
2021-2022 Water DistribuƟ on RehabilitaƟ on: WO
315
Water 570,000 570,000
AlƟ tudes Valves for Reservoir Balance: (S-09) Water 50,000 320,000 370,000
Annual Water RehabilitaƟ on Program Water 105,000 300,000 1,000,000 500,000 1,250,000 500,000 3,655,000
Bergis Water Reservoir Replacement: (S-07) Water 875,000 1,775,000 2,650,000
City View/Bergis Pressure Zone-Fire Flow Im-
provements: (F-04)
Water 250,000 250,000
City View/Bergis Pressure Zone-Pipe Resiliency
Improvements: (R-05)
Water 435,000 875,000 1,310,000
Filter Covers at the Water Treatment Plant Water 500,000 500,000
Bicycle Pedestrian Pathways
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Unfunded (cont.)
Cornell at McVey: Enhance Pedestrian Crossing Street 63,000
Hwy 43 Bike Lanes: Terwilliger to Oak St (TSP 38) Street 988,000
Iron Mtn/Lakeview Blvd to Fairway Rd (Elements
of TSP 39)
Street 125,000
Jean Rd Bike Lanes, Sidewalks: Jean Way to Pilk-
ington Rd (TSP 118)
Street 248,000
Jeff erson Pkwy Bike lanes and Pathways: Mt Jef-
ferson Terr to McNary Pkwy (TSP 123)
Street 322,000
McNary Pkwy Bike Lanes: Jeff erson Pkwy to Kerr
Pkwy (TSP 125)
Street 1,968,000
Meadow Ave Pathway: Meadows Dr to Carman
Dr (TSP 201)
Street 126,000
Melrose Bike Lanes: Westlake to Boƫ celli (TSP 92) Street 30,000
Oswego Canal Trail: Bryant Rd to Childs Rd. (TSP
186)
Street 860,000
Overlook Dr Bike Lanes: Meadowlark Ln to Staf-
ford Rd (TSP 126)
Street 1,140,000
Parkview Dr Bike Lanes: Westlake Drive to Fosberg
Rd (TSP 128)
Street 1,506,000
Pilkington Rd Bike Lanes and Sidewalks: Willow to
Boones Ferry (TSP 76)
Street 413,000
Pilkington Bike Lanes and Sidewalks: Willow Rd to
Jean Rd (TSP 122)
Street 853,000
Royce Way Bike Lanes: Bryant Rd to Westview Rd
(TSP 127)
Street 33,000
Staff ord Rd Bike Lane: South Shore to Overlook
(TSP 91)
Street 3,621,000
Terwilliger Bike Lanes: Hwy 43 to city limits/Cas-
tleridge Ln. (TSP 104)
Street 2,196,000
Total 0 0 0 0 0 0 26,921,000
FUNDING PLAN SUMMARY
10 City of Lake Oswego Capital Improvement Plan 2021-2027
Water
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded (cont.)
Forest Highlands Pressure Zone-Pipe Resiliency
Improvements: (F-03) (R-02)
Water 950,000 1,905,000 2,855,000
McNary Pressure Zone-Fire Flow Improvements:
(F-02)
Water 1,150,000 1,150,000
McVey Pump StaƟ on Upgrades: (P-01) Water 500,000 1,210,000 1,710,000
Pipe Capacity Improvements: (D-02) Water 835,000 1,675,000 2,510,000
Pipe Capacity Improvements: (D-03) Water 685,000 1,375,000 2,060,000
Ridge Point Water Main RehabilitaƟ on: WO 314 Water 75,000 75,000
Seismic and Structural Upgrades to Water Storage
Reservoirs: S-10)
Water 225,000 445,000 670,000
Seismic, Structural, Electrical and Mechanical
Upgrades to Water Pump StaƟ ons: (P-06) (P-04)
Water 295,000 590,000 885,000
Seismic Upgrades and Re-painƟ ng to Cooks BuƩ e
and Palisades No. 1 Water Storage Reservoirs:
(S-05) (S-06)
Water 360,000 715,000 1,075,000
Summit Pressure Zone - Fire Flow Improvements:
(F-01)
Water 535,000 535,000
Telemetry & CommunicaƟ on Upgrades: (M-04)
WO 301
Water 400,000 100,000 500,000
Touchstone Pump StaƟ on Upgrade: (P-05) Water 140,000 745,000 885,000
Trolley StaƟ on Water Reuse DemonstraƟ on
Project
Water 55,000 55,000
Waluga Pressure Zone Pipe Resiliency Improve-
ments: (R-01)
Water 645,000 1,290,000 1,935,000
Water Quality Monitoring System Improvements:
(M-05)
Water 300,000 300,000
Total 2,000,000 4,385,000 8,030,000 4,765,000 4,890,000 2,435,000 26,505,000
Water
Unfunded
Add Sixth Pump at the Water Treatment Plant:
(P-03)
Water 900,000
Backup Power at RIPs and WTP Water 1,000,000
Filter Media Replacement at the Water Treatment
Plant
Water 1,030,000
Knaus Pressure Zone-Pipe Resiliency Improve-
ments: (R-04)
Water 1,828,000
Palisades Pressure Zone; Pipe Resiliency Improve-
ments: (R-03)
Water 3,042,000
pH Control for OpƟ mizaƟ on at WTP Water 500,000
Pipe Capacity Improvements: (D-04) Water 229,000
Pipe Capacity Improvements: (D-05) Water 2,711,000
Southside Reservoir No. 2: (S-04) Water 5,198,000
Waluga Pressure Zone-Pipe Resiliency Improve-
ments: (R-06)
Water 4,658,000
Waluga Pressure Zone-Pipe Resiliency Improve-
ments: (R-07)
Water 2,158,000
Total 0 0 0 0 0 0 23,254,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 11
…..…..………...…………...Projected…..…..………………….…
Stormwater
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
Annual Small Projects, Catch Basins, & UIC
Retrofi ts
Stormwater 240,000 240,000 240,000 240,000 240,000 240,000 1,440,000
Bayberry/Rye/Andrews Rd Drainage Improve-
ments
Stormwater 250,000 650,000 900,000
Blue Heron Rd Drainage Improvements Stormwater 250,000 500,000 750,000
Daniel Way Roadway and Channel StabilizaƟ on
Project
Stormwater 125,000 375,000 500,000
Dolph Court/Country Club Culvert Crossing Stormwater 185,000 500,000 685,000
Firwood Rd Upgrade: Boones Ferry Rd to
Waluga Dr
Stormwater 100,000 100,000
Fosberg Rd Drainage Improvements WO 288 Stormwater 1,000,000 1,000,000
Goodall Rd Drainage Improvement Project Stormwater 200,000 200,000 400,000
Jean Rd UIC Retrofi t Stormwater 70,000 70,000
Lakeview Blvd Street & Drainage Improvements Stormwater 375,000 825,000 1,200,000
Redfern Ave Drainage Improvements Stormwater 200,000 460,000 660,000
Upper Drive Drainage Improvements, West of
Bryant Rd
Stormwater 150,000 450,000 600,000
Total 1,435,000 815,000 1,525,000 2,165,000 1,525,000 840,000 8,305,000
Stormwater
Unfunded
5th Street & Lake Bay Ct Drainage Improve-
ments
Stormwater 450,000
Ash St ODOT Hwy 43 Stormwater 150,000
Bickner St to McVey Ave Stormwater Replace-
ment
Stormwater 842,000
Cedar Court Drainage Improvements Stormwater 286,000
Chandler Rd Drainage Improvements Stormwater 535,000
Cherry Crest DetenƟ on - Water Quality Treat-
ment Facility
Stormwater 794,000
Churchill Downs Drainage Improvements Stormwater 68,000
Douglas Circle Drainage Improvements Stormwater 550,000
Eena Rd Drainage Improvements Stormwater 312,000
Elizabeth Gress Park - Sediment Control/Res-
toraƟ on
Stormwater 292,000
Foothills/A Ave Drainage Improvements Stormwater 1,179,000
Lakeview Blvd Drainage Improvements - West
of Jean Rd
Stormwater 950,000
Lower Boones Ferry Rd - Lake Grove UGB Stormwater 4,081,000
Melrose St Tributary RehabilitaƟ on Stormwater 342,000
Preakness Ct Water Quality/DetenƟ on Stormwater 181,000
Regional Stormwater Facility-Bergis/Staff ord Rd Stormwater 896,000
Regional Water Quality Facility Retrofi t Stormwater 506,000
Sediment Basin EvaluaƟ on and Retrofi ts Stormwater 521,000
Sher Lane Drainage Improvements Stormwater 450,000
Southwood Park DetenƟ on Stormwater 174,000
Sunbrook Dr Drainage Improvements Stormwater 310,000
Tanglewood Dr Water Quality/DetenƟ on Stormwater 181,000
Touchstone Dr Drainage Improvements Stormwater 115,000
Total 0 0 0 0 0 0 14,165,000
FUNDING PLAN SUMMARY
12 City of Lake Oswego Capital Improvement Plan 2021-2027
…..…..………...…………...Projected…..…..………………….…
Sewer
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
2022 Wastewater RehabilitaƟ on Sewer 1,500,000 1,500,000
Blue Heron Trunk ( T-BH-1) Sewer 500,000 1,000,000 1,500,000
Blue Heron Trunk ( T-BH-2) WO 298 Sewer 325,000 825,000 1,675,000 35,000 2,860,000
Canal Trunk (T-CAN-1 & P-CAN-1) Sewer 500,000 1,000,000 1,500,000
Downtown Trunk 1 (T-DWN-2) Sewer 150,000 150,000 700,000 1,000,000
East Mountain Park Trunk (T-EMP-2 & T-EMP-3) Sewer 175,000 1,390,000 1,565,000
Foothills Rd Interceptor (T-L1-1) Sewer 225,000 3,100,000 6,075,000 9,400,000
Forest Highlands Trunk 1 (T-FH-1) Sewer 550,000 1,700,000 2,250,000
I/I ReducƟ on Program Priority A Projects (G-3) Sewer 500,000 500,000 1,250,000 1,250,000 500,000 4,000,000
Lakewood Trunk (T-LW-1) Sewer 75,000 155,000 230,000
Lake Oswego Interceptor Sewer (LOIS) Manhole
Repairs and Upgrades
Sewer 1,000,000 125,000 2,250,000 300,000 3,675,000
McVey Trunk (T-MCV-1 & T-MCV-2) Sewer 500,000 1,500,000 2,000,000
South Shore 2 Wastewater RehabilitaƟ on WO 303 Sewer 1,450,000 1,450,000
South Shore Trunk (T-SS-1) Sewer 100,000 220,000 320,000
System Wide RehabilitaƟ on (OperaƟ ons) Sewer 500,000 1,500,000 500,000 1,500,000 500,000 4,500,000
Total 4,350,000 3,105,000 8,250,000 6,055,00011,200,000 4,790,000 37,750,000
Sewer
Unfunded
Downtown Trunk 3 & 4 (T-DWN-3 & T-DWN-4) Sewer 170,000
East Mountain Park Trunk (T-EMP-1) Sewer 350,000
Flow Tracking Data (PS-6) Sewer 365,000
Foothills Rd Pump StaƟ on (PS-4) Sewer 9,400,000
I/I ReducƟ on Program Priority B Projects (G-3) Sewer 25,378,000
L5 Basin Trunk (T-L5-1) Sewer 52,000
New Canal Basin Pump StaƟ on (PS-7) Sewer 1,350,000
Other Pipeline Repair Projects for Major Collectors
(P-1)
Sewer 4,810,000
Rebuild LiŌ StaƟ on and Pressure Mains Sewer 1,000,000
Relocate Storm and Sanitary Sewer Mains Sewer 1,461,000
Riverfront Trunk 2 (T-RF-2) Sewer 535,000
South Lake Trunk (T-SL-1) Sewer 127,000
Southwood Trunk (P-SW-1) Sewer 567,000
West Mountain Park Trunk (T-WMP-1) Sewer 650,000
WillameƩ e Rd Pump StaƟ on (PS-3) Sewer 1,102,000
Total 0 0 0 0 0 0 47,317,000
FUNDING PLAN SUMMARY
City of Lake Oswego Capital Improvement Plan 2021-2027 13
…..…..………...…………...Projected…..…..………………….…
Large Capital Equipment
Funding
Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
5-Yard Dump Truck Street 300,000 300,000
Backhoe Street 170,000 170,000
Fire Engine General 750,000 750,000
Loader Water 150,000 150,000
Street Sweeper Stormwater 285,000 285,000
Van with Closed-Circuit Television Equipment Wastewater 240,000 240,000
Total 1,035,000 0 450,000 170,000 240,000 0 1,895,000
Total Funded for FY 2021-22 32,309,000
27,630,000
147,432,000
Total Funded for FY 2022-23
Total Funded for FY 2021-2022 -2026-2027
Total Unfunded for FY 2021-2022 - 2026-2027 369,701,000
…..…..………...…………...Projected…..…..………………….…
FaciliƟ es/Other Funding Source 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 Total
Funded/Projected
City Hall General 1,500,000 1,500,000
Total 1,500,000 0 0 0 0 0 1,500,000
FUNDING PLAN SUMMARY
14 City of Lake Oswego Capital Improvement Plan 2021-2027