HomeMy WebLinkAboutAgenda Item - 2026-01-20 - Number 06.2 - WO 363, Carman Drive Sidewalk 6.2 oti� E*P4_ COUNCIL REPORT v AN o OREGO� Subject: Award a Public Improvement Contract for the construction of Work Order 363 Carman Drive Sidewalk Project. Meeting Date: January 20, 2026 Staff Member: Mort Anoushiravani, PE Assistant City Engineer Report Date:January 9, 2026 Heike Shipton, PE Senior Associate Engineer Department: Public Works - Engineering Action Required Advisory Board/Commission Recommendation ❑X Motion ❑ Approval ❑ Public Hearing ❑ Denial ❑ Ordinance ❑ None Forwarded ❑ Resolution ❑X Not Applicable ❑ Information Only Comments: ❑ Council Direction ❑X Consent Agenda Staff Recommendation: Award a Public Improvement Contract. Recommended Language for Motion: Move to authorize the City Manager to sign a Public Improvement Contract with Faison Construction, Inc. in the amount of$1,206,095.11 for the construction of Work Order 363 Carman Drive Sidewalk Project. Project/ Issue Relates To: Adopted Capital Improvement Plan (CIP) project and Council Goals for prioritizing pathway projects. Issue before Council (Highlight Policy Question): ❑X Council Goals/Priorities ZAdopted Master Plan(s) ❑Not Applicable BACKGROUND The 2024 Group 2 Pathways project (Work Order 337) is identified as an important component in the City's Transportation System Plan (TSP) and is funded under the current Capital Respect. Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO,OR 97034 WWW.LAKEOSWEGO.CITY Page 2 Improvement Plan (CIP). The four locations included in the Project were recommended by the Transportation Advisory Board (TAB). These locations are: 1. Carman Drive, from Waluga Drive to Quarry Road 2. Pilkington Road, from Boones Ferry Road to Lakeview Boulevard 3. Tree Top Lane, from Overlook Drive to Fernwood Drive 4. Meadowlark Lane, from Overlook Drive to Ridge Pointe Drive. These four pathways were chosen to provide safer routes to school and increase overall pedestrian accessibility. On February 20, 2024, the City Council awarded a public services contract to Harper Houf Peterson Righellis, Inc for Engineering Services for the Group 2 Pathways project in the amount of$896,884. Extensive outreach and engagement with the public and impacted residents occurred throughout the design phase, including three in-person open houses and community meetings, one digital open house, online surveys, and face-to-face meetings with residents. To deliver the projects in the most efficient way, the construction contract for the sidewalks along Tree Top Lane and Meadowlark Lane were combined into a single bid package under Work Order 362 and constructed in 2025. The Pilkington Project is pending right-of-way resolution, and has been separated out from Carmen. Moving forward, the construction work for the Carman Drive Sidewalk project will be executed under Work Order 363. DISCUSSION Project design was completed in November 2025, and the construction project was advertised for bid on December 3, 2025. The engineers' estimate of probable construction costs was $1,650,000. Sealed bids were opened on December 23, 2025, and the following bids were received: Cost GFE Total Rank Contractor Bid Points Points Points 1 Faison Construction, Inc $1,206,095 90 10 100 2 Wickwire $1,298,908 83.57 8 91.57 3 Pacific Ex $1,355,000 80.11 8 88.11 4 Daybreak Construction $1,370,000 79.23 10 89.23 5 Moore Ex $1,375,380 78.92 7 85.92 6 SLE $1,394,000 77.87 2 79.87 7 Turney1 $1,425,990.25 76.12 1 77.12 Respect. Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO,OR 97034 WWW.LAKEOSWEGO.CITY Page 3 8 Titan Utilities $1,444,514 75.15 10 85.15 9 Nutter Corp $1,458,625 74.42 3 77.42 10 Kodiak Pacific $1,489,131 72.89 5 77.89 11 Lyda Ex $1,492,935 72.71 4 76.71 12 MJ Hughes $1,497,818.60 72.47 4 76.47 13 North Cascade Ex $1,515,183 71.64 4 75.64 14 Kerr Contractors $1,667,928. 65.08 3 68.08 15 Emery & Sons $1,685,058 64.42 3 67.42 16 Subcom2 Incomplete n/a n/a n/a 1 Disqualified.Did not submit First Tier Disclosure 2 Disqualified.Did not submit Bid Schedule This procurement included the City's Good Faith Effort (GFE) Requirements, e.g., COBID solicitation. Work is expected to begin in late February or March, with an anticipated completion date in mid-summer 2026. FISCAL IMPACT The project is currently funded from the Street Fund in the adopted 2025/26 to 2028/29 Capital Improvement Plan (CIP). RECOMMENDATION Authorize the City Manager to sign a Public Improvement Contract with Faison Construction, Inc. in the amount of$1,206,095.11 for the construction of WO 363 Carman Drive Sidewalk Project. Respect. Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO,OR 97034 WWW.LAKEOSWEGO.CITY