Loading...
HomeMy WebLinkAboutAgenda Item - 2026-05-19 - Number 05.8 - Willamette River Greenway Trail Construction Contract Award 5.8 COUNCIL REPORT V -w 0 GREGO\--" Subject: Willamette River Greenway Trail Construction Contract Award Meeting Date: May 19, 2026 Staff Member: Kyra Haggart, Project Manager Report Date: May 8, 2026 Department: Parks & Recreation Action Required Advisory Board/Commission Recommendation ❑ Motion ❑ Approval ❑ Public Hearing ❑ Denial ❑ Ordinance ❑ None Forwarded ❑ Resolution , ❑X Not Applicable ❑ Information Only Comments: ❑ Council Direction ❑X Consent Agenda Staff Recommendation: Authorize the City Manager to sign a contract with Daybreak Construction for an amount of$688,000 for construction of Work Orders 357 & 370 Willamette River Greenway Trail. Recommended Language for Motion: Move to authorize the City Manager to sign a contract with Daybreak Construction for an amount of$688,000 for construction of Work Orders 357 ❑ 370 Willamette River Greenway Trail. Issue before Council (Highlight Policy Question): ❑X Council Goals/Priorities ❑Adopted Master Plan(s) ❑Not Applicable EXECUTIVE SUMMARY On March 31, 2026, City Council approved the funding plan for the Willamette River Greenway Trail project. Ten bids for construction were received and opened on April 28, 2026, with the successful bidder identified as Daybreak Construction with a bid amount of$688,000. Staff recommend that Council authorize the City Manager to sign a contract with Daybreak Construction in an amount of$688,000 for construction of the Willamette River Greenway Trail. Respect. Fv PI'en e Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 2 BACKGROUND This project will fill a critical gap in the Willamette River Greenway Trail through Lake Oswego and will complete the connection between three of Lake Oswego's riverfront parks: Foothills Park, Roehr Park, and George Rogers Park. With this missing gap filled, Lake Oswego will offer a continuous 2.25-mile stretch of regional multi-use pathway along the Willamette River that provides recreational opportunities, improves access to nature close to homes, and enhances safe walking and biking connections between the riverfront and downtown Lake Oswego. The City has been planning to complete this trail connection since at least 1994, when the project appeared as a recommendation in the City's Comprehensive Plan. This recommendation was carried forward into the 2013 update of the Comprehensive Plan, which is still serving Lake Oswego today. Recommendations to complete this project also appeared in the 2001 Open Space Plan, the 2002 George Rogers Park Master Plan, and the 2003 Trails and Pathways Master Plan. In 2012, the project was identified as a need in Parks Plan 2025, and it also appeared as a pathway project in the 2014 Transportation System Plan. Most recently it was identified as a top priority in the recent update of the City's Park and Recreation System Plan (Parks Plan 2040) adopted by City Council on June 3, 2025. Parks & Recreation staff began working with a consulting team in 2023 to develop a conceptual design and a planning-level cost estimate for the trail. The design and the associated estimated project costs were refined over the next several years. In March 2026, City Council approved the funding plan for the project. Bidding for the project's construction was advertised on April 8, 2026, and 10 bids were received and opened on April 28, 2026. Staff evaluated each bid received and determined that nine of the bids were responsive and responsible. Bids were evaluated based on the scoring criteria identified in the request for bids and staff identified Daybreak Construction as the successful responsible bidder. Staff issued a Notice of Intent to Award letter to bidders on April 30, 2026. In accordance with Subsection 00130.15 of the General Conditions, bidders had seven calendar days from the date of this notice to submit to the City a written protest of the intended award. The protest period closed on May 7, 2026, and no protests were received. FISCAL IMPACT Construction costs for this project were originally estimated at approximately $1,400,000, including a 20% contingency. This estimate was based on recent project costs from 2025 with an added escalation factor for 2026 construction that was consistent with year-over-year escalation rates seen over the past several years. Bids for the construction of this project came in lower than anticipated, with the apparent successful bid submitted by Daybreak Construction at $688,000. Including the $688,000 contract with Daybreak Construction, an added 20% contingency, and construction of a portion of the project's fencing that will be contracted separately by the City, construction is currently estimated at $860,000. The approved funding plan, which covers the total project estimate of$1,760,000 presented to Council in March 2026, allocates $240,000 of City Park Development fund dollars and $300,000 of Parks System Development Charge (SDC) fees to this project. Of the remaining estimated Respect. c . �!e Trust - , 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 3 $1,220,000 needed, approximately $1,140,000 is funded through Lake Oswego's Metro Local Share dollars, and $80,000 is being provided through a grant from the Mt. Hood Territory 2026 Strategic Investment Program. Metro approved Lake Oswego's Local Share request for this project on March 31, 2026, and the Intergovernmental Agreement between Metro and Lake Oswego is being finalized. Although the bids for construction came in lower than anticipated, staff recommend keeping the approved funding plan in place as additional contingency to address any significant issues or unknowns that could arise during the construction process. If the project comes in under budget, remaining Park Development dollars and SDCs can be used towards future parks projects identified in the CIP, and remaining funds from Metro's Local Share program can be reallocated towards the other projects on the Local Share project list that was approved by Council in April 2024. Potential projects include the West Waluga Neighborhood Connector Trails and the Luscher Farm Access & Parking projects. RECOMMENDATION Authorize the City Manager to sign a contract with Daybreak Construction for an amount of $688,000 for construction of Work Orders 357 & 370 Willamette River Greenway Trail. Respect. F-. P!'P„ Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY