HomeMy WebLinkAboutAgenda Item - 2026-10-07 - Number 1.0 - Foothills TAC Meeting 4 Slides - Schematic PlanningLAKE OSWEGO FOOTHILLS -TAC MEETING #4 –OCTOBER 7, 2026
Foothills District Framework Plan
Technical Advisory Committee Meeting
Technical Coordination Update
& Next Steps
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
•Welcome and Meeting Purpose— 5 minutes
•Summer Technical Meeting Coordination— 15 minutes
•Key Moves Defining the Plan Refinement— 10 minutes
•Upcoming Analysis & Coordination— 10 minutes
•Focused Technical Meeting Discussion— 15 minutes
•Next Steps — 5 minutes
Agenda
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Outcomes:
1.Summarize the principal findings from TAC #3 and summer technical coordination.
2.Introduce the Key Moves that now define the Schematic Planning-level framework which emerged from the broader
engagement, planning, and technical coordination process.
3.Review the proposed focus meetings that will examine the Key Moves at a greater level of technical detail.
4.Gather TAC input on participation, work products, sequencing, and coordination.
Meeting Purpose and Outcomes
Purpose:
▪Summarize the issues identified through summer technical coordination, introduce the Key Moves as the current
schematic planning-level framework, and preview the additional analysis and coordination needed before
development of the Preferred Plan.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Where We Left Off
•Big Idea and three
preliminary concepts
•TAC Mtg #3 and
additional meetings
Project Progression
Where We Are Now
•Schematic planning-
level framework and
Key Moves
•Infrastructure/environ-
mental analysis, costs,
and development
feasibility underway
Where We Are Going
•Focused technical
coordination
•Refinement into the
Preferred Plan
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
TAC Mtg. #3 - Big Ideas & Preliminary Concepts
North
Portal
WWTP
South
Portal
Park
Edge
State
Street
Edge
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
TAC Mtg. #3 Takeaways:
Considerations Carried Forward
1 . The Grand Connection
2. Foothills Road retained for WWTP access
3. Commercial activity and storefronts
4. Public space to complement the park
5 . Need for northern access
North
Portal
WWTP
South
Portal
Park
Edge
State
Street
Edge
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
TAC Mtg. #3 Takeaways:
Issues Requiring Further Coordination
1 . State Street and rail crossings
2. North Portal alignment and phasing
3. Tryon Creek fish passage and trail access
4. Plaza Park design and program
5 . Development and WWTP operations
“TAC Meeting #3 helped us identify the common ideas worth carrying forward and the questions that could not be resolved through a general concept discussion. Coordination during the summer allowed us to explore those questions directly with the agencies, departments, and operators responsible for the affected facilities.”
North
Portal
WWTP
South
Portal
Park
Edge
State
Street
Edge
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Summer Technical Coordination
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
▪State Street Design Considerations- ODOT transportation planning
▪Willamette Shore Line Rail Right-of-Way -Metro & TriMet
▪Willamette Shore Line Trolley Operations- Metro & TriMet, City staff
▪PGE Substation and Electrical Infrastructure- Portland General Electric
▪Tryon Creek and Highway 43 Fish Passage Project Status - Tryon Creek Watershed
Council
▪Waste Water Treatment Plant Access- City Public Works
▪Foothills Park, Trails and Public Space- City Parks and Recreation staff
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
STATE STREET AND ODOT
Special Transportation Area and
Blueprint for Urban Design the
basis for evaluating context-
sensitive improvements..
Proposed changes require
design-exception, and ODOT
review.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
RAIL AND TROLLEY
OPERATIONS
Maintain rail corridor
clearance and vehicle access
to the trolley building
Existing grades support aB
Avenue grade-separated
walking and biking connection.
Trolley
Bldg
Trolley
Stop
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
PGE INFRASTRUCTURE
S ubstations and overhead
transmission lines constrain
streets, and crossings.
Consolidation is apossible
consideration requires
substantial property, technical
review, time, and cost.
Powerlines
Substation
Substation
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
TRYON CREEK AND NORTH
ACCESS
C oordinate fish passage,
highway, rail, trail, and
access improvements.
The North Portal still requires
separate review of geometry,
property needs, funding, and
approvals.
Interjurisdictional coordination
adds time and complexity but
may result in positive outcomes
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
WASTEWATER TREATMENT
PLANT ACCESS
Maintain existing Foothills
Road grade and alignment
with access at three locations
Foothills Road provides service
access to WWTP and future
development
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Technical Meetings & Findings
Early coordination identified the conditions that informed concept refinement and the issues requiring further technical work .
These findings informed which ideas moved forward into the Schematic Plan Key Moves and established the questions for focused technical
coordination.
“These conversations did not resolve every issue or approve a final design. They helped us understand which ideas could continue, what conditions would need to be addressed, and where more detailed technical coordination would be required. That information informed refinement of the preliminary concepts into the Schematic Plan Key Moves.”
PARKS, TRAILS, AND
PUBLIC SPACE
A plaza can complement
Foothills Park as an urban
threshold
Planning must address
accessibility, operations,
maintenance, programming, and
flood recovery.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
1. Build the Grand Connection
Create the signature multimodal street and view
corridor that extends Downtown through the
redevelopment area to Foothills Park and the
riverfront.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
2. Create a New Front Door at State Street
Strengthen the State Street edge between A and B
Avenues with active storefronts, enhanced pedestrian
crossings, and a visible invitation into Foothill with
elevated rail crossings at A Ave and B Ave
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
3. Create a Plaza Park at the Riverfront
Terminate the Grand Connection at a flexible public
destination framed by storefronts and development
and integrated with Foothills Park.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
4. Frame the Public Realm with Development
Organize housing and focused ground-floor retail
along the Grand Connection and Plaza Park. New
buildings create active street edges and help screen
the WWTP from primary public spaces.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
5. Connect the Lake to the River
Extend the Lake Trail from Millennium Plaza Park
across State Street and the railroad corridor, then
through Foothills to the riverfront.
Lakewood Bay
Willamette River`
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
6. Enhance the South Portal
Improve the existing southern connection as a
welcoming multimodal gateway and complete
the district loop.
Lakewood Bay
Willamette River`
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
7. Establish the North Portal
Evaluate alternatives impacts on access, State
Street/HWY 43 operations, rail/property impacts
cost and environmental considerations.
Lakewood Bay
Willamette River`
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
The Key Moves: Defining the Schematic Plan
Enabling Conditions
Wastewater treatment plant coordination
Floodplain infrastructure and phasing strategy
Lakewood Bay
Willamette River`
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Draft Evaluation Criteria
Project Objectives
•Remove Barriers to Development
•Improve Access & Connectivity
•Support Affordable & Diverse
Housing
•Encourage High-Quality Design
and Public Spaces
•Fund Critical Infrastructure
Through Urban Renewal
Analysis Underway
Traffic Impacts and
Operations
•Test State Street,
intersections, access, and
North Portal implications.
•Identify operational
considerations and
potential implementation
triggers.
Infrastructure Costs
and Phasing
•Utility upgrades,
relocations, and
extensions identified
•Prepared planning-level
costs for new, realigned,
and modified streets.
•Evaluating grading,
floodplain, and phasing
Development
Feasibility
•Test development capacity,
housing assumptions,
parking, and urban-renewal
revenue.
•Identify potential
development program based
on financial models.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Focused Technical Meetings
1 EARLY CONSTRAINTS
1 PGE Substation and
Electrical Infrastructure
Participants
PGE; Public Works and
Engineering;
Expected finding
Facility and easement
constraints; relocation
feasibility, process,
responsibilities, and
timing
2 ACCESS AND
CROSSINGS
2A State Street and
North Portal
Participants
ODOT; Transportation and Public
Works;
Expected finding
Traffic and design criteria; approval
needs; North Portal refinements and
implementation triggers
2B Railroad Crossings
and Trolley Interface
Participants
City; rail and trolley representatives;
ODOT; PGE; APEX; FFF
Expected finding
Clearance, grade, access, operating,
construction, and approval
requirements
3 DISTRI C T CIRCULATION
& PUBLIC REALM
3 Street Network and
Municipal Operations
Participants
Public Works; Transp; Engrg ; Fire;
Planning; WWTP
Expected finding
Street, utility, service,
emergency-access, and WWTP
operating requirements
4 Parks, Trails and
Natural Resources
Participants
Parks; Nat.Res.; TCWC; Public
Works; regional partners;
Expected finding
Trail and park standards; ownership,
maint., access, habitat, &permitting
needs
4 I NFRASTRUCTURE &
DEV. FEASIBILITY
5 Floodplain /Grading and
Infrastructure Phasing
Participants
Public Works and Engr.; Planning;
Parks; WWTP;
Exp ected finding
Planning-level grading,
floodplain, stormwater, utility,
and phasing strategy
6 Development Capacity,
Housing and Urban
Renewal
Participants
Plng; Ec.Dev.; Housing; Urban
Renewal; Finance; EcoNW
Expected finding
Test devel. capacity, affordability,
infrastructure costs, TIF revenue, and
phasing
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
1 EARLY CONSTRAINTS
1 PGE Substation and
Electrical Infrastructure
Participants
PGE; Public Works and
Engineering; APEX; FFF
Expected finding
Facility and easement
constraints; relocation
feasibility, process,
responsibilities, and
timing
Focused Technical Meetings
Plan direction >>>>>
•Future road
realignment conflicts
with the existing
substation.
•B Avenue bridge may
affect electrical lines
serving Downtown.
Desired finding>>>>>
•Define the pathway and
information needed to
preserve the Grand
Connection and
advance the B Avenue
bridge while
accommodating
essential electrical
infrastructure.
What we know>>>>>
•Substation consolidation
may be possible but
requires PGE
investigation
•Existing Foothills Road
can remain until the
ultimate realignment is
implemented.
•Transmission lines are
expected to remain
overhead; a lateral may
be impacted by a trail
bridge.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Focused Technical Meetings
2 ACCESS AND
CROSSINGS
2A State Street and
North Portal
Participants
ODOT; Transportation and Public
Works; APEX; FFF
Expected finding
Traffic and design criteria; approval
needs; North Portal refinements and
implementation triggers
2B Railroad Crossings
and Trolley Interface
Participants
City; ODOT Transportation/rail and
trolley representatives;; PGE;
Ex pected finding
Clearance, grade, access, operating,
construction, and approval
requirements
Plan direction >>>>>
•Enhance the pedestrian
& business environment
on State Street
•Advance the D–E
Avenue North Portal
Alignment and retain
the Terwilliger
Alternative for technical
comparison.
•Provide walking and
bicycling connections
across State Street and
the rail corridor.
What we know>>>>>
•Future traffic under
current zoning and the
Schematic Plan
development scenario.
•Intersection volume-to-
capacity, delay, level of
service, and queueing.
•Potential mitigation
measures and
implications for North
Portal need, and
location.
Desired finding>>>>>
•Define a viable highway
and rail coordination
pathway for improving
State Street crossings,
advancing the B Avenue
connection, and
identifying the North
Portal alignment that
should inform the
Preferred Plan.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Focused Technical Meetings
3 DISTRICT CIRCULATION &
PUBLIC REALM
3 Street Network and
Municipal Operations
Participants
Public Works; Transp; Engrg ; Fire;
Planning; WWTP; APEX; FFF
Expected finding
Street, utility, service, emergency-
access, and WWTP operating
requirements
4 Parks, Trails and
Natural Resources
Participants
Parks; Nat.Res.; TCWC; Public Works;
regional partners;
Expected finding
Trail and park standards; ownership,
maint., access, habitat, &permitting
needs
Plan direction >>>>>
•Establish a connected
street framework.
•Retain Foothills Road
as a service street.
•Create an integrated
lake-to-riverfront,
north–south, and
riverfront trail
network.
•Plan for a Plaza Park
and Festival Street.
What we know>>>>>
•Schematic street
sections, circulation,
emergency access,
WWTP access, utilities,
cost, and phasing.
•Trail alignments, and
accessibility, and
grading considerations.
•Plaza programming,
and design integration
with Foothills Park
Desired finding>>>>>
•Identify the requirements
and refinements needed
for the street network to
function safely through
phased redevelopment
and the support or
refinement of trail,
bikeway, and Plaza
Park improvements
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Focused Technical Meetings
4 I NFRASTRUCTURE &
DEVELOPMENT
FEASIBILITY
5 Floodplain /Grading and
Infrastructure Phasing
Participants
Public Works and Engr.; APEX;
specialists; Planning; Parks; WWTP;
Exp ected finding
Planning-level grading,
floodplain, stormwater, utility,
and phasing strategy
6 Development Capacity,
Housing and Urban
Renewal
Participants
Plng; Ec.Dev.; Housing; Urban
Renewal; Finance; EcoNW
Expected finding
Test devel. capacity, affordability,
infrastructure costs, TIF revenue, and
phasing
Plan direction >>>>>
•Coordinate streets,
utilities, grades,
floodplain conditions,
parking, and
development parcels.
•Test a planning-level
development
capacity.
•Plan for phased
infrastructure and
redevelopment while
preserving the district
framework.
What we know>>>>>
•Utility, roadway,
grading, floodplain, and
infrastructure &
probable cost
•Building typology,
parking, market-
feasibility, and
absorption analysis.
•Affordable-housing
assumptions.
•Public-investment
required, and potential
feasibility gaps.
Desired finding>>>>>
•Establish coordinated
infrastructure,
development, housing,
cost, and revenue
assumptions to refine the
Schematic Plan and
determine an
implementable pathway
to the Preferred Plan.
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Overall Project Schedule
Nov 2, 2026
Feb 1, 2027
Apr 1, 2027
Jun14, 2027
Sep 15, 2027
Dec 31, 2027
Preferred Plan Schematic & Analysis Summaries
Draft Framework Plan
Final Framework Plan & Adoption
Initial Draft Amendments
Post Plan Amendments Ready for Adoption
Adoption of Post Plan Amendments
LAKE OSWEGO FOOTHILLS - TAC MEETING #4 –OCTOBER 7, 2026
Upcoming Schedule
•Focused Technical Meetings Oct -Nov
• CAC Meeting #8 Oct 13
•City Council Study Session – Schematic Design Oct 20
•Planning Commission Work Session – Schematic Design Oct 26
•Preferred Plan Refinement Nov -Dec