Foothills Technical Advisory Committee Meeting #4 – Agenda Page 1 of 3
Foothills Technical Advisory Committee
Meeting #4 – Technical Coordination Update & Next Steps
Oct 7, 2026, from 1:00 pm – 2:00pm I Hosted via Zoom
PUBLIC VIEWING & COMMENTS
Members of the public can use the following URL link to register in advance to view the meeting:
https://us06web.zoom.us/webinar/register/WN_dW142QE4TEuEU_8Ogq9OAA
Members of the public who wish to send comments regarding issues being addressed by the Lake Oswego Foothills
District Technical Advisory Committee (“Foothills TAC”) are requested to email their comments to
csiquina@ci.oswego.or.us, with “Foothills TAC” in the subject line.
MEETING PURPOSE
Summarize how engagement and summer technical coordination informed refinement of the preliminary
development concepts, introduce the Key Moves that will define the forthcoming Schematic Plan, and prepare for
more detailed focus meetings that will test feasibility and identify the requirements, processes, and potential
adjustments needed to carry the Key Moves into the Preferred Plan.
AGENDA
1. Welcome and Meeting Purpose — 5 minutes
Review the meeting purpose, distributed materials, and intended outcomes
2. Summer Technical Coordination and Early Findings — 15 minutes
Summarize the principal findings from summer technical coordination.
3. Key Moves Defining the Schematic Plan — 10 minutes
Introduce the Key Moves that emerged from refinement of the preliminary concepts through community
engagement, policy direction, and technical coordination.
4. Upcoming Analysis and Coordination— 10 minutes
Review the proposed topics, general sequencing, anticipated participants, and intended outcomes.
5. Focused Technical Meetings Discussion— 15 minutes
Review the Focus Meeting Matrix and gather TAC input on meeting topics, participants, work products,
sequencing, and coordination needs.
6. Next Steps — 5 minutes
Summarize TAC input, identify additional focused technical meetings immediate actions, and confirm how
focused-meeting findings will be documented and reported to the full TAC
______________________________________________________________________________________________
Foothills Technical Advisory Committee Meeting #4 – Agenda Page 2 of 3
FOOTHILLS FOCUS MEETINGS MATRIX
The summary Focus Meetings matrix identifies the technical questions, participants, expected work products, and
sequencing for focused review needed to refine the Schematic Plan and support development of the Preferred
Plan.
Sequence and Focus
Meeting Primary Review Topics and Participants Expected Technical Findings and
Coordination
1
PGE Substation and
Electrical
Infrastructure
Substation relocation feasibility; conflict with the
Grand Connection and Foothills Road realignment;
overhead-line effects on the B Avenue bridge;
property and easement needs; WWTP electrical-
service requirements; and relocation responsibilities,
process, information, and timing.
Participants PGE; City Public Works and
Engineering; WWTP project team; APEX; FFF
Document affected facilities and evaluate whether
relocation or consolidation appears technically
feasible; and identify the process, responsibilities,
and requirements needed to evaluate and
potentially advance relocation.
Dependencies and coordination Begin early.
Findings potentially affect the Grand Connection,
Foothills Road, B Avenue bridge, WWTP
coordination, and development parcels.
2A
State Street and North
Portal
State Street restriping and added parking; A Avenue
recommendations; TIA findings; ODOT access
requirements; preferred North Portal between D and
E Avenues; Terwilliger Alternative; intersection
operations; and implementation triggers.
Participants ODOT; City Transportation and Public
Works; APEX; FFF
Evaluate the recommended State Street and
North Portal concepts and document the
operational and regulatory considerations for
pedestrian and traffic calming enhancements.
Identify required traffic analysis, design criteria,
approval processes, and needed refinements.
Dependencies and coordination Use current
TIA findings. Coordinate with street-network
review and property, access, and grade analysis
for the preferred North Portal between D and E
Avenues and the Terwilliger Alternative.
2B
Railroad Crossings
and Trolley Interface
B Avenue Primary Crossing Concept; A Avenue
Optional Supplemental Connection; trolley-
maintenance driveway and barn access; rail
clearance; accessible grades and landings; rail and
trolley operations; depot and boarding-area interface;
emergency access; construction phasing; and PGE-
line conflicts.
Participants City; rail owner or operator; Willamette
Shore Trolley representatives; ODOT as applicable;
PGE; APEX; FFF
Evaluate the feasibility of the B Avenue Primary
Crossing Concept and A Avenue Optional
Supplemental Connection. Document agency and
operator requirements, information needs, review
processes, and necessary technical refinements.
Dependencies and coordination Coordinate
with PGE findings, State Street crossings, the
future Anchor project, Lake-to-Riverfront Trail,
Curlicue Trail, trolley-maintenance access, and
adjacent property redevelopment.
3
Street Network and
Municipal Operations
Grand Connection; Foothills Road realignment; South
Portal; preferred North Portal between D and E
Avenues; Terwilliger Alternative; street sections;
utilities; loading; solid waste; and maintenance.
Review WWTP service, delivery, controlled access,
large-vehicle turning, and emergency-access
requirements. Review fire-apparatus access,
secondary emergency access, fire lanes, aerial
access, plaza and festival-street closures, and
emergency access during phased development.
Participants City Public Works, Transportation,
Engineering, Fire, and Planning; WWTP project
team; APEX; FFF
Document municipal, WWTP-access
requirements. Identify refinements to street
alignments.
Dependencies and coordination Build from
PGE, ODOT, and crossing coordination. Identify
requirements and considerations for subsequent
grading, utility, property, and development-parcel
refinement.
______________________________________________________________________________________________
Foothills Technical Advisory Committee Meeting #4 – Agenda Page 3 of 3
Foothills Focus Meeting Matrix continued.
Sequence and Focus
Meeting Primary Review Topics and Participants Expected Technical Findings and
Coordination
4
Parks, Trails, and
Natural Resources
Lake-to-Riverfront Trail; Plaza Park; River Greenway;
Curlique Trail; North Portal trail; Tryon Creek bridge
and northern trails; habitat; park operations and
programming; parking and ownership and
maintenance; event servicing; and emergency
access during normal operations and special events.
Participants Parks and Recreation; Natural
Resources; Tryon Creek Watershed Council; Metro
or regional partners as appropriate; Public Works;
Fire as needed; FFF
Review the proposed trail alignments and
intended park functions. Document environmental,
ownership, operational, maintenance, emergency-
access, and permitting considerations and needed
refinements.
Dependencies and coordination Coordinate
with crossing and street alignments. Findings
inform floodplain, habitat, emergency-access,
property, and phasing review.
5
Floodplain, Grading,
and Infrastructure
Phasing
Floodplain considerations and compensatory
measures; finished-floor elevations; street and utility
grades; stormwater; Plaza Park and riverfront
impacts; continuity of WWTP access and operations;
and sequencing of the new WWTP, demolition of the
existing facility, public improvements, and private
redevelopment.
Participants City Public Works and Engineering;
APEX; floodplain and civil specialists; Planning;
Parks; WWTP project team; FFF
Identify the technical basis for a planning-level
grading, floodplain, utility, stormwater, and
infrastructure-phasing strategy, including the
sequence needed to maintain WWTP operations
and emergency access.
Dependencies and coordination Use the
refined street, trail, park, and WWTP framework.
Findings may require changes to development
parcels, capacity, access, property needs, and
improvement sequencing.
6
Development
Capacity, Housing,
and Urban Renewal
Development yield and building scale; parking;
affordable housing allocation; market feasibility;
property strategy; property acquisition and
easements; interface with WWTP noise, odor, and
service operations; infrastructure costs; tax-increment
revenue; public and private responsibilities;
development triggers; and development and public-
improvement phasing.
Participants Planning; Economic Development;
Housing; Urban Renewal; Finance; market or
economic consultant; WWTP project team as
needed; FFF
Test the planning-level development scenario and
housing assumptions.
Dependencies and coordination Use access,
infrastructure, floodplain, property, operational,
and cost findings. Reevaluate development
capacity, public-improvement responsibilities,
revenue, and phasing as technical assumptions
change.
Property and implementation coordination- Each focus meeting will identify associated property acquisitions,
easements, and consider public and private responsibilities, sequencing requirements, preliminary cost
responsibilities, potential funding considerations, and implementation triggers. The project team will consolidate
these findings after the technical concepts have been evaluated and may review them through a follow-up
implementation workshop.