Agenda Item - 2026-10-13 - Number 06.1 - Lake Oswego Wastewater Treatment Facility
6.1 d os� COUNCIL REPORT c V O GREGO\--" Subject: Project Authorization for the Lake Oswego Wastewater Treatment Facility and Associated Sewer Rate Adoption. Meeting Date: 10/13/2026 Staff Member: Stefan Broadus, PE Director of Special Projects Report Date: 10/2/2026 Department: Public Works - Engineering Action Required Advisory Board/Commission Recommendation ❑X Motion ❑ Approval ❑ Public Hearing ❑ Denial ❑ Ordinance ❑ None Forwarded ❑ Resolution ❑X Not Applicable ❑ Information Only Comments: ❑ Council Direction ❑ Consent Agenda Staff Recommendation: Authorize the execution of the Design-Build-Operate-Maintain Contract and Sewer Rate Adjustment. Recommended Language for Motion: Move to (1) authorize the City Manager to sign a Design-Build-Operate-Maintain Contract with Jacobs Project Management Company for the Lake Oswego Wastewater Facility project and (2) adopt Resolution 26-55 directing staff to proceed with the 28% sewer rate adjustment schedule ("Option 1"), effective July 1, 2027. Project/ Issue Relates To: Collaborate with the City of Portland to make a financially and environmentally responsible long-term investment in a wastewater treatment facility. Issue before Council (Highlight Policy Question): ❑X Council Goals/Priorities ❑Adopted Master Plan(s) ❑Not Applicable Respect er, Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 2 BACKGROUND The project history to date is thoroughly described in the September 1, 2026 Council Report and omitted from this report for brevity, but the highlights are as follows: - Tryon Creek Wastewater Treatment Plant (TCWTP) was built in 1964 and is owned and operated by the City of Portland. - The plant is reaching the end of its useful life and needs to be replaced. - In 2017, the City of Lake Oswego and City of Portland began planning a replacement facility on an adjacent site. - From 2018 through 2023, Lake Oswego was delivering this project utilizing a Design-Build- Finance-Operate-Maintain (DBFOM) model. - In 2024, the City decided to compensate the DBFOM Contractor (Epcor) for their services performed to date, but to not execute the Project Agreement to construct and operate the facility. - The City pivoted to a Design-Build-Operate-Maintain (DBOM) delivery method seeking "market-driven, competitive pricing" and increase the confidence that the costs were "reflective of current market conditions." - The DBOM procurement process yielded Jacobs as the DBOM contractor and they provided a Technical and Cost Proposal in April of 2026. - The technical proposal includes preliminary designs of a facility that features traditional treatment technology, meets or exceeds water quality requirements, is energy efficient, meets the highest seismic design criteria, features robust odor control systems, and is expandable for future capabilities including sustainability efforts. DISCUSSION Price Proposal Components The Jacobs Best and Final Offer (BAFO) for the LOWWTF includes several elements detailing the costs and timing for construction and operating the facility. These various line items are shown in the table below. These numbers represent the total cost of the facility, but not the amount obligated solely to Lake Oswego. The costs of the facility are shared proportionately based on flow between Lake Oswego and Portland as prescribed by the intergovernmental agreement authorized by Council on December 16, 2025. More details can be found in that Council Report. Component Cost 1. Fixed Design-Build Price $372,621,065 2. Owner-Controlled Account TBD 3. Year 1 Annual Operation & Maintenance Charge $4,994,178 4. Annualized Major Repair& Replacement Schedule $600,767 5. Inflation Index Factor Index-Linked 6. Solids Handling $508 per dry ton 7. Guaranteed Maximum Energy Utilization Flow-based Formula Respect. Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 3 1. Fixed Design-Build Price: This is the price to advance the preliminary design concept to a complete set of engineering plans and specifications, and then permit, construct, and commission (startup) the designed facility. (Note that previous reports showed a fixed design-build price of $369m. In the negotiations with Jacobs, it was determined that approximately $3m worth of line items that were previously carried in the owner- controlled account would be more accurately and appropriately managed within the fixed design-build price. Specifically, these are items in which the risk is more difficult to objectively quantify and document and therefore better for the Contractor to hold those items within the fixed design-build price locking in amount for the City. The overall project total anticipated cost has not changed as a result of this change. Similarly, the sewer rate model is unaffected by this change.) 2. Owner-Controlled Account: This line item is an amount to help the City manage impacts after contract execution from owner-driven scope changes, unforeseen site conditions, and cost escalation of materials. Carrying these funds outside of the base contract gives the City more control of cost variances and reduces risk premium. The cost of escalation of materials has been estimated at about $12.5m. This amount plus the typical cost of unforeseen change orders on a project of this scale have been incorporated into the sewer rate model. 3. Year 1 Annual Operation & Maintenance (O&M) Charge: The annual O&M charge is the price to operate the facility in the first year after construction is complete. The Inflation Index Factor is used to determine the annual O&M charge for subsequent years though the end of the contract term. (Note: The amount shown in the table above has been slightly decreased from the previous report due to negotiations.) 4. Annualized Major Repair & Replacement (MR&R) Schedule: The MR&R schedule in this contract serves as the long-term roadmap and financial mechanism for preserving asset integrity and operational performance over the multi-decade lifecycle of this facility. The MR&R schedule identifies, projects, and schedules the major overhaul, rehabilitation, or complete replacement of capital assets (such as pumps, blowers, and filters) that reach the end of their useful service life during the operating term. By tying these anticipated costs to a City-managed reserve, the schedule ensures that the facility is handed back at the end of the contract term in an excellent condition. 5. Inflation Index Factor:This factor is used in the formula to calculate the escalated Annual O&M Charge after the first year of operating the facility. The Annual O&M Charge is a factor of labor rates, maintenance of machinery and equipment, industrial chemicals and other consumables, and the trucking of solids. The City's owner's advisor, Carollo Engineering, has developed a custom composite of indices that proportionately reflect these factors.This weighted composite index will be used in the formula to determine the Annual O&M Charge in year 2 and beyond through the end of the 10 year O&M term. Respect. Excellence. Trust. Service 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 4 6. Solids Handling: Biosolids are the byproduct of the conventional activated sludge wastewater treatment process that will be utilized by this facility. The biosolids will be hauled to the City of Portland's Columbia Blvd Wastewater Treatment Plant where it will be treated in preparation for secondary, beneficial use. The amount of solids generated is difficult to predict and dependent on the flow characteristics coming into the plant, which can be highly variable. The City will pay a unit price of solids hauling per dry ton as opposed to an annual fee. Paying by the unit price for the actual volume hauled eliminates overly conservative predictive pricing from the Contractor. 7. Guaranteed Maximum Energy Utilization (GMEU): Electricity use is also a function of the flow coming to the plant, which is highly variable. This contract manages electricity as a pass-through cost from Jacobs, which means that the City will only pay for the actual electricity used in the facility up to the amount specified in the GMEU.The Contractor will pay for any electricity usage above that amount. Value Engineering & Price Validation Efforts The initial cost proposal received was higher than anticipated. The project team carefully reviewed the proposal and began negotiating the terms and conditions with the Contractor. The goals of this efforts were to (1) find areas where the cost could be reduced with acceptable consequences and (2) validate that the cost ultimately presented for approval was reasonable and appropriate for the scope of work being performed. This effort was described at length in the September 1, 2026 Council Report for this project and is summarized below: - Shifted to a shorter operations and maintenance contract term. - Performed a detailed line item cost review. - Compared recent costs of similar wastewater facilities. - Considered regional utility infrastructure challenges. - Searched for additional external funding. Resolution 26-55: Utility Rate Unfortunately, the City's sewer utility fund does not have nearly enough money to pay for the project with the existing balance. As with almost every public infrastructure project of similar scale, the LOWWTF must be financed. The previously acquired WIFIA loan from the EPA in the amount of $123.5m as well as traditional municipal bonds are public financing tools with favorable terms for the City. With that said, the targeted utility rate schedule will not generate sufficient revenue to pay the debt service (interest and principal payments) of the loan and bonds. Utility rates must be increased to pay off the financing. The City's detailed sewer rate model has been utilized to identify the minimal utility rate schedule to adequately manage the City's wastewater utility including paying off this project as well as maintaining and rehabilitating the collections system (pipes and pump stations) that conveys the flow from all of the individual services locations to the new treatment plant. Respect. Excellence. Trust. Service. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 5 There are two rate increase options to consider for funding this project: 1. Option 1 - Single Year Increase: the sewer rate model has found that a rate increase of 28% is necessary to keep the sewer utility fund in good standing. This rate increase would be effective July 1, 2027. Once implemented, the utility rate schedule can return to the targeted rate of 3.9% annually. 2. Option 2 - Multi Year Increase: alternatively, a lower rate increase of 8% per year is possible to make minimum payments, but would need to be repeated annually for 10 years before finally returning to the targeted rate of 3.9%annually.This schedule reduces the initial rate increase from any one year to the next, but ultimately requires the rate to be higher than the larger, single year increase. See the graph below to see how these two rate schedules compare. The rates shown are based on typical use for a single-family home as described in the Lake Oswego Master Fees and Charges booklet. Lake Oswego - Sewer Utility Rate Scenarios $25u 3.9% Option 2: 8%/yr for 10 Years $200 Option 1: / 28%One-Time Rate Increase $150 ��� 3.90/0 \o„,„ � — % 000 $100 $50 $- 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 — Respect Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 6 Option 1 would cost about $19.37 more per month in 2027 than compared to Option 2 for the typical single family home in Lake Oswego. That difference begins to shrink every year and in 2032, Option 2 becomes more expensive. This trend continues over time and by 2038, Option 2 is expected to cost about $37 more per month than Option 1 for the typical home. See the chart below. Lake Oswego Sewer Rate - Option 1 vs 2 -- $15.83 $11.82 $7.28 $2.16 $(3.59) $(10) $(10.03) $(20) $(17.22) $(30) $(25.24) $(34.16) $(40) $(35.49) $(36.88) $(50) 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 Respect ,---- Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 7 This same data set can also be presented in terms of the total Lake Oswego utility bill. Since these two options are independent of the other utilities including in the utility bill (water, stormwater, and street maintenance), the difference is unchanged from the previous chart, but this frames the values in the context of the average monthly bill. See below. ■ Option 1:28%One-Time Rate Increase $369.72 - ■ Option 2:8%/yr for 10 Years $332.85 $350 ■ 1 - $300 $278.66 $275.07 $215.72 $250 $235.08 $200 L $150 • 2026 2027 2028 2029 2030 21)21 ""2') 2033 2034 2025 202E 2027 7022 While both options presented are financially viable means to finance the project, they each have benefits and drawbacks. The primary benefits of Option 1 are lower long-term financial impact on the community and a reduction in the amount of interest paid for the project. At the prior Council meeting on September 1, 2026, the City Council expressed a preference for Option 1 and is thus recommended in Resolution 26-55 included in this item. — Respect. F el'e Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 8 Public Outreach The initial planning for this project began more than five years ago and included several public meetings and open houses with the community. Most recently, the project team updated the FAQs on the project webpage and hosted three information sessions to describe the need and purpose of the project as well as the rate increase options Council is considering. Notices and information about the information sessions were provided using multiple Hello LO articles, LODown e-newsletter articles, project webpage, email, multiple social media posts, and the City website. At the information sessions, community members were provided an opportunity to ask questions they may have to the project team members as well as express any preferences or concerns regarding the sewer rate options. Due to limited attendance, general themes and consensus are likely not statistically significant to represent opinions of the entire community. The two virtual information sessions were recorded and are available on YouTube. FISCAL IMPACT Cost Proposal The Jacobs Cost Proposal includes the cost to design and construct the facility as well as the various elements of operating it including the primary operating fee, solids handling, electricity pass-through, and major repairs and replacement of equipment. The capital construction fee is specified as $372,621,065. The annual operations charge is $4,994,178. Funding Sources The City will use System Development Charges (SDCs) and existing wastewater utility fund balances to pay towards the capital construction cost. However, these funds have insufficient balance to pay the entire amount as incurred. Instead, the project will need to be financed by drawing on the WIFIA loan ($123.5 Million) secured in September of 2025 as well as municipal bonds. To pay the debt service for this financing, the City will utilize a combination of proportionate payments from the City of Portland and utility billing. The project's funding plan is summarized in the table below. As discussed above, the existing utility rates are insufficient to cover the debt service payments. Raising the wastewater utility rate is necessary to pay for the project. Funding Source Type i Primary Purpose WIFIA Loan Financing Capital Construction Payment Municipal Bonds Financing Capital Construction Payments System Development Charges Existing Balance Capital Construction Payments LO Sewer Fund Balance Existing Balance Capital Construction Payments Portland Cost Share Payments Revenue Debt Service Payments, Operations Fee LO Utility Billing Revenue Debt Service Payments, Operations Fee Respect. .. .> ';,, Trust. 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY Page 9 Financial Oversight The project team recognizes that this project is an enormous investment for the City and ensuring the best value is achieved on public funds is of utmost importance. The project team plans to return to Council monthly to provide a project status update including a financial overview of total expenses to date and a summary of additional costs incurred. Construction Management Services In addition to the cost of capital construction shown in the Jacobs Cost proposal,the project team anticipates awarding a contract for construction management services for the approximate amount of$10,000,000.This contract could be an amendment to an existing professional services contract of the project or via a new procurement. This amount has been factored into the utility rate model and would not require an additional increase beyond the two scenarios described previously in this report. The project team anticipates presenting this construction management contract for council approval at an upcoming session. RECOMMENDATION Move to (1) authorize the City Manager to sign a Design-Build-Operate-Maintain Contract with Jacobs Project Management Company for the Lake Oswego Wastewater Facility project and (2) adopt Resolution 26-55 directing staff to proceed with the 28% sewer rate adjustment schedule ("Option 1"), effective July 1, 2027. Alternatively, if the City elects not to proceed with this project, the existing Tryon Creek Wastewater Plant would continue to be managed by the City of Portland. Lake Oswego sewer rates would not need to be raised immediately. However, the costs and frequency of major repairs of the aging plant components will increase significantly.The eventual cost to replace the plant in its current location will exceed the cost proposed for the LOWWTF.Accordingly,the Lake Oswego sewer rates will need to be increased greater than what is being proposed in the two scenarios under consideration. This path is not recommended by the project team considering the long-term financial impact on the community as well as the deferment of the non-monetary benefits this project realizes. ATTACHMENTS 1. Jacobs Best and Final Offer for the LOWWTF, 10/5/2026. 2. DBOM Agreement for the Design, Construction, Operation, and Maintenance of the Lake Oswego Wastewater Treatment Plant. 3. Resolution 26-55. Respect. Excellence. Trust. Service 503-635-0215 380 A AVENUE PO BOX 369 LAKE OSWEGO, OR 97034 WWW.LAKEOSWEGO.CITY ATTACHMENT 1 TABLE OF CONTENTS Contents A. BAFO Proposal Overview and Narrative 2 B. DB Price Modifications 2 1. Scope Changes 2 2. Escalation Increase 2 3. Jacobs Reductions 3 4. City Escalation Allowance 4 C. O&M Price Modifications 4 1. Escalation 4 2. Obsolescence Risk 4 3. Major R&R 4 4. O&M Staffing 4 5. Adjustment of Annual O&M Charge/MR&R allocation 5 6. Guaranteed Maximum Energy Utilization (GMEU) 6 7. Inflation Index 6 D. BAFO Documentation 8 1. Proposal Cost Submittal Form 8 2. DBOM Agreement 8 3. Technical Memoranda and Drawings 11 4. Project CPM Schedule 11 Attachment 1 — Escalation Buildup Detail 11 Attachment 2— DBOM Agreement and Appendices 11 Attachment 3—Technical Memoranda and Drawings 11 Attachment 4— Project CPM Schedule 11 Attachment 5— Draft Commissioning Plan 11 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY A. BAFO PROPOSAL OVERVIEW AND NARRATIVE We are pleased to submit our Best and Final Offer(BAFO) Proposal for the Lake Oswego Wastewater Treatment Facility(LOWWTF) Design-Build-Operate-Maintain (DBOM) Project. The purpose of this document is to provide reviewers with a summary and explanation of the revised DBOM pricing. The subsequent sections describe the basis for changes from our original proposal, as well as document the basis for our revised DBOM Proposal. B. DB PRICE MODIFICATIONS Exhibit 1 summarizes our original DB and BAFO Pricing, along with the basis for changes—primarily related to delay in contract award. Jacobs original proposal was valid through July 6, 2026. This BAFO is updated and valid through November 16, 2026. Exhibit 1 -DB Price Comparison Original Proposal Change Basis BAFO $367,377,807 Fixed DB Price ($1,710,949) Scope Changes $9,954,207 Escalation Increase Jacobs Reductions $372,621,065 $15,000,000 Subcontractor Risk ($18,000,000) (GC, Fee, Contingency, (unallocated) Subcontractor Risk) Escalation Risk City $11,400,000 (unallocated) ($900,000) Allowance/Escalation $10,500,000 Bucket increase $393,777,807 TOTAL ($10,656,742) TOTAL $383,121,065 1. SCOPE CHANGES Scope changes to the base project are limited to two items: • The City opts to carry the contract for third-party inspections.Therefore, Jacobs has removed the cost for that effort ($1,910,949)from our BAFO pricing. • The City opts to include a main-tie-tie-main configuration for the main electrical gear. Jacobs has added $200,000 to our BAFO pricing to accommodate this change. 2. ESCALATION INCREASE We engaged several key equipment vendors to assess market conditions and pricing trends over the preceding four months, given ongoing volatility in commodity markets. Overall, impacts were limited, with a few notable exceptions: • Vendors whose products are heavily dependent on resin-based materials reported significant cost increases driven by recent global market conditions. Specifically, the grit concentrator and polymer aging tank pricing was adjusted given significant recent impacts. • The disc filter and RDT manufacturers noted increases in commodity-related costs. 121 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY Across approximately$27 million of process equipment purchase agreements, the cumulative pricing impact was less than 2%. To further mitigate escalation concerns, the DBOM Contractor has elected to assume the risk of future process equipment price increases, and associated process equipment escalation has been removed from the escalation log. We reviewed pricing from approximately 20 major subcontractors to evaluate current pricing conditions and potential escalation risks. Key findings included: • Subcontractors generally identified rebar, miscellaneous metals, and certain piping materials as the areas most affected by recent market volatility. Conversely, pricing for cast-in-place concrete, precast concrete, and drilled pier concrete has remained relatively stable. • Based on current market conditions, Tapani's pricing was adjusted to reflect increases in rebar, fuel, and select piping materials. The most significant adjustment was an approximately$1.0 million increase in installed rebar costs. Most other pricing elements experienced minimal change.The escalation log has been updated accordingly. • Christensen provided updated electrical pricing reflecting continued escalation in electrical equipment markets. Electrical gear costs increased by approximately$800,000, and their subcontract value was adjusted to reflect current market pricing. • Labor cost increases were significant for both Tapani and Harder. Tapani reported wage increases in several crafts that increased its composite labor rate by approximately 5% between March and July, resulting in an estimated $600,000 cost impact. Harder's prior pricing was based on assumptions made while union labor negotiations were ongoing. Final negotiated wage increases exceeded initial assumptions by approximately 12%, accounting for the majority of Harder's pricing adjustment. To provide pricing certainty moving forward, Jacobs will assume the risk of future labor rate increases, and labor escalation has been removed from the escalation register. 3. JACOBS REDUCTIONS Subsequent to submitting our Price Proposal in April, Jacobs provided extensive supporting detail to enable the City to conduct a comprehensive, line-item review of project costs. Although the City generally found our overall costs to be reasonable, several individual line items were identified as being on the higher end of expectations. Taking this feedback seriously and in the spirit of the constructive and good-faith negotiations with the City,Jacobs has implemented a 12%reduction in contingency and Jacobs-related project costs, reducing in an overall project cost reduction of nearly 5%. LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY 4. CITY ESCALATION ALLOWANCE A full escalation buildup detail is included in Attachment 1.We have refined this list to reflect an appropriate risk allocation between the City and Jacobs, with an eye towards balancing administrative simplicity with opportunity for owner savings. For those items that Jacobs can influence escalation cost via multiple factors (e.g. design modifications, design and construction approaches, etc.)we have included these within our BAFO pricing. For those items over which Jacobs has limited control(e.g. material costs), we have included these within the City Escalation Allowance bucket. C. O&M PRICE MODIFICATIONS At the request of the City,we submitted contract pricing for a 10-year term on June 11, 2026. This offering provides significant advantages as compared to the 20- and 30-year pricing presented in our original Price Proposal.The following documents the basis for changes from our original Price Proposal 1. ESCALATION Because increases in O&M pricing due to escalation are addressed within the DBOM Agreement through escalation indices, there is no change to our O&M pricing as a result of the delay to project start. December 2025 indices continue to serve as the basis for our pricing. 2. OBSOLESCENCE RISK Our proposal contemplates Jacobs managing and incurring the costs associated with equipment obsolescence for this 10-year term period. 3. MAJOR R&R The Major R&R scheduled for the first 10 years is significantly lower than the 30-year average, reducing the associated contract value from $79.2M to $9.2M, with approximately 2/3 of the 10- year major repair and replacement activity timed in year 10. Under the 30-year proposal, our average annual maintenance cost reflected 6.1% of our total equipment costs, installed -well within the expected industry range for this life cycle period. Since the 10-year proposal does not extend beyond the full life cycle of much of the equipment, the cost is reduced markedly. 4. O&M STAFFING Our team has considered staffing levels and is confident that our approach provides the appropriate level of resources to ensure reliable, proactive performance and maintenance of the City's assets while aligning with industry-standard staffing levels (Exhibit 2).We take seriously our role as the City's representative, safeguarding public health and protecting the community's investment in this vital infrastructure. 141 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY Exhibit 2-O&M Staffing benchmarking comparison 35 30 • Salem,OR 25 Hillsboro,OR• N • 45 Clark County,WA• 20 Vancouver,WA• E Z Tucscon,AZ • = 15 • Gresham,OR ti= Spokane,WA .••• Eugene,OR co Woonsocket,RI • LOWWTF Z Lincoln,CA • 06 10 • 0 • Portland,OR(Tryon Creek) • • Wilsonville,OR 5 Hood River,OR The Dalles,OR 0 0 5 10 15 20 25 30 Design Capacity(mgd) 5. ADJUSTMENT OF ANNUAL O&M CHARGE/MR&R ALLOCATION As part of ongoing contract negotiation discussions, the team identified a misalignment in how Jacobs'costs were allocated between the Ordinary Operations and Maintenance Charge and the Annual Capital Maintenance Charge as compared to how the DBOM Agreement envisioned that allocation.We have realigned our costs for consistency with the DBOM Agreement, as shown in Exhibit 3. This reallocation does not change the total O&M cost. Exhibits 3 and 4 highlights pricing revisions to reflect this reallocation. Exhibit 3—O&M Price Comparison 30-year 10-year BAFO (10-year term w/ Term Term MR&R reallocation) Ordinary Operation and Maintenance $5,308,000 $4,670,000 $4,994,178 Component Major MR&R Component (10-yr total) $79,225,109 $9,249,446 $6,007,668 Sludge Trucking Cost (per dry ton) $508 $508 $508 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY Exhibit 4- MR&R Schedule Revisions Original Price Proposal BAFO Price Proposal Asset Grouping Yrs 1-5 Yrs 6-10 Yrs 1-5 Yrs 6-10 Pumps 264,367 1,694,138 0 1,541,916 _ Blowers 60,174 305,493 0 0 Screens 120,473 484,009 0 484,009 Grit 98,896 379,537 68,306 379,537 Aeration 40,814 102,035 0 0 Clarifiers 203,949 509,872 203,949 509,872 Disk Filters 226,324 1,028,671 212,921 1,028,670 _ UV Disinfection 141,239 294,504 0 160,521 _ HVAC 29,143 239,283 0 0 RDTs 74,949 292,948 _ 0 263,394 _ Odor 83,811 108,240 83,811 83,811 Valves 0 97,200 0 0 Gates 0 274,251 0 0 Piping 0 0 0 0 VFDs 0 614,405 0 308,729 Electrical Gear 174,675 437,257 55,000 270,000 _ Generators 67,036 201,108 0 201,108 _ LCPs 0 0 0 0 PLCs 40,633 234,323 0 30,293 _ Network SCADA 18,836 59,532 0 27,021 Tanks 0 0 0 0 Buildings 52,035 146,885 0 94,800 Structures 0 0 0 0 Site 0 48,403 0 0 TOTALS 1,697,352 7,552,094 623,987 5,383,681 6. GUARANTEED MAXIMUM ENERGY UTILIZATION(GMEU) The City requested a modification to the structure of the GMEU to be tied to influent flows and loads as compared to a static value, based on project design criteria. Jacobs proposes utilization of the following relationship, upon which our BAFO is based: 145 x Average Annual BOD (lb/d)+ 166,944 x Average Annual Flow(MGD) + 2,003,317 7. INFLATION INDEX The City requested a basket of indices to account for inflation. We propose the following relationship and definitions: 161 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY "Index-Linked" means, with respect to an amount expressly identified as being subject to adjustment, that the amount is adjusted as of each July 1 commencing July 1, 2027 by: Index-LinkedN = (0.572 x(ECI-TCN/ECI-TCN_,) + 0.316 x(PPI-GMEN/PPI-GMEN_,) + (0.054 x (PPI-ICN/PPI-ICN_,) + (0.004 x(PPI-WCN/PPI-WCN1) + (0.014 x(PPI-TTLN/PPI-TTLN_,) + 0.01632) x Index-LinkedN_, Where, N =the period from the immediately preceding June to the previous June, (except that for the initial July 1, 2027 adjustment, it will be for June 2027 to December, 2025) N-1 =the same calendar period one year earlier "Inflation Index" is a weighted blend of indices and means the amount determined as follows: [Inflation Index= (0.572 x ECI-TC) + (0.316 x PPI-GPME) + (0.054 x PPI-IC) + (0.044 x PPI-WC) + (0.014 x PPI-TTL) + 0.01632 Where, ECI-TC = Employment Cost Index(ECI), total compensation for private industry workers in the utilities industry, for the 2nd quarter of the calendar year, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: CIU20144000000001 (with the value reported for: (a)the 2nd quarter of each calendar year being used for purposes of clause (1) of the definition of"Index-Linked, and (b) the 1St quarter of 2026 being used for purposes of clause (2) of the definition of"Index-Linked). PPI-GPME = Producer Price Index(PPI), general purpose machinery and equipment, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: WPS114. PPI-IC= Producer Price Index(PPI), industrial chemicals, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: WPU061. PPI-WC = Producer Price Index(PPI), solid waste collection, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: PCU562111562111. PPI-TTL= Producer Price Index(PPI), truck, truck trailer and RV leasing, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID:WPU442102.] I 7 I LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY D. BAFO DOCUMENTATION 1. PROPOSAL COST SUBMITTAL FORM Exhibit 5, consistent with the Cost Submittal Form line items documented in the RFP, summarizes our BAFO Price Proposal. Exhibit 4-BAFO Proposal Cost Submittal Form Item RFP Description Value # Section 2 _ 4.1 Fixed Design-Build Price-Project Option 2 _ $372,621,065(1) 7 4.3 Year 1 Annual Operation and Maintenance Charge $5,056,000 -Project Option 2, 10-year Term 10 4.4 Guaranteed Maximum Energy Utilization—Project Refer to Item C.6 above Option 2 11 4.5 Inflation Index Factor Refer to Item C.7 above 12 4.6 Major Repair and Replacement Refer to Item C.5 above 13 4.1 Maximum Drawdown Schedule To be finalized prior to Contract Award 14 4.33 Sludge Trucking Cost $508 per Dry Ton (1) Value does not include City's Escalation Allowance 2. DBOM AGREEMENT We appreciate the diligent efforts on the part of the City to drive contract discussions to resolution over the past several months. We believe we have navigated the bulk of the outstanding items to successful resolution. Attachment 2 includes the current, marked-up version of the DBOM Agreement and associated Appendices upon which our BAFO Proposal is based,with the status of items which have not been confirmed to be closed noted in Exhibit 5.These documents reflect work by both Parties to introduce additional clarity and modify the terms of the DBOM Agreement to enhance Project value. While the City and Jacobs are in agreement on the bulk of these revisions, there are a few items that are not yet fully resolved.These are documented below. Exhibit 5-Outstanding DBOM Agreement Items Article Description Markup Status Action Agreement 1 Indices Captured in markup City to review and acceptor comment 5.2 Access to TCWTP Site Captured in markup City to review and acceptor (C, D) comment 8.9 Access to TCWTP Site Captured in markup City to review and acceptor comment 9.3 (H) Deductions for Odor No change, subject to City to review and accept or Citations acceptance of Jacobs other comment comments related to odor I 8 I LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY Article Description Markup Status Action 9.3 (L) Deductions for No change, subject to City to review and accept or Sustained Odor acceptance of Jacobs other comment Conditions comments related to odor 9.3 (M) City Termination Rights No changes here. Issue City to review and accept or based on Failure to captured in markups to comment Meet Odor Guarantee Agreement Article 21.1.A 9.4 Guaranteed Maximum Not captured in markup; City to review and acceptor Energy Consumption described in Item C.6 above comment; revise Agreement 9.6 (E) Sludge and Scum Off- Captured in markup City to review and accept or loading comment 11 Contract Term and Not captured in markup City to prepare draft language. Extensions Jacobs' understanding is that renewal terms are negotiable upon extension(s) and that sufficient time will be incorporated to allow for implementation of End of Term requirements. 11.6 Capital Modifications Not captured in markup City to prepare draft language. (F) for Future Nutrient Jacobs understands Nutrient Removal Removal will be implemented implementation at a future date and managed as a Capital Modification 17.5 Requisitions against Captured in markup Jacobs refined markup to (E) MRR Account reflect intent 21.1.A DBOM Contractor Captured in markup City to review and accept or Events of Default comment Defined Appendices 1.1 (d) Easements Not captured in markup City needs to add description of easements for completeness, and address ROW vacation on SW corner of Project Site (not addressed in Jacobs BAFO). 1, Design-Build Project Captured in markup City to review and acceptor Att. 1A Site Plan comment 1, Operations and Captured in markup City to review and accept or Att. 1B Maintenance Project comment Site Plan 4 Codes and Standards Captured in markup City to review and accept or comment I 191 LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY Article Description Markup Status Action 4.1(m) Cybersecurity Not captured in markup. City to review and acceptor Jacobs proposed language comment; revise Agreement is captured in TM 8. 4.5 Sludge requirements Captured in markup City to review and acceptor (a, b) comment 4.10 Cut/Fill requirements Captured in markup City to review and acceptor comment 4.11 Codes and Standards Captured in markup City to review and accept or comment 7.5.7 Traffic Control Not captured in markup. City to comment on whether Parameters Jacobs approach is Jacobs'approach is documented in Price acceptable; revise Agreement Proposal and is inconsistent accordingly. with current language. 8 Commissioning Captured in markups to City to review and acceptor (acceptability to BES) Attachment 5 - comment Commissioning Plan 11.3.1 Odor Control Standard Captured in markup City to review and accept or comment 11.3.3 Odor Test Protocols Captured in markup City to review and accept or comment 11.3.4 Odor Tests Captured in markup City to review and accept or comment 13.3 Determination of an Captured in markup City to review and acceptor Odor Incident for comment Purposes of the Odor Guarantee 13.4.2 Sludge and Scum Captured in markup City to review and accept or comment 13.4.3 Sampling Captured in markup City to review and accept or comment 13.4.4 Reporting Captured in markup City to review and acceptor comment 14 Service Fee Calculation Captured in markup City to review and acceptor comment 19 Approved Captured in markup City to review and accept or Subcontractors comment I -1oI LAKE OSWEGO WWTF DBOM BAFO PRICING SUMMARY 3. TECHNICAL MEMORANDA AND DRAWINGS Technical Memoranda and Drawings are included for completeness as Attachment 3. Given the limited changes in scope, these have not been updated since submission of our Technical Proposal on April 2, 2026. However, we have updated our Assumptions, Clarifications, Discussions and Inclusions (ACDC) and incorporated into the Technical Memoranda as TM 8.This TM serves to provide additional clarity related to our BAFO. 4. PROJECT CPM SCHEDULE Attachment 4 includes the full project CPM. Given our significant reduction in project contingency, we have added 30 days of float between our Acceptance Date and Scheduled Acceptance Date, which is the point of time when Liquidated Damages would be assessed. ATTACHMENT 1 —ESCALATION BUILDUP DETAIL ATTACHMENT 2-DBOM AGREEMENT AND APPENDICES ATTACHMENT 3-TECHNICAL MEMORANDA AND DRAWINGS ATTACHMENT4-PROJECTCPM SCHEDULE ATTACHMENT 5-DRAFT COMMISSIONING PLAN *41 I I11I ATTACHMENT 2 Execution Version DBOM AGREEMENT FOR THE DESIGN, CONSTRUCTION, OPERATION AND MAINTENANCE OF THE LAKE OSWEGO WASTEWATER TREATMENT FACILITY between CITY OF LAKE OSWEGO, OREGON and JACOBS PROJECT MANAGEMENT CO. Dated [ ], 2026 3935946.13 043463 [This Page Intentionally Left Blank] 2 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents TABLE OF CONTENTS Page ARTICLE 1 DEFINITIONS AND INTERPRETATION Section 1.1. DEFINITIONS 3 Section 1.2. INTERPRETATION 27 (A) Plurality 27 (B) Persons 27 (C) Headings 27 (D) References Hereto 27 (E) References to Days and Time of Day 27 (F) References to Including 28 (G) References to Statutes 28 (H) References to Governmental Bodies 28 (I) References to Business Days 28 (J) References to Documents and Standards 28 (K) References to All Reasonable Efforts 28 (L) Entire DBOM Agreement 28 (M) Counterparts and Delivery by Electronic Mail 28 (N) Governing Law 28 (O) Severability 28 (P) Drafting Responsibility 29 (Q) Interpolation 29 (R) Accounting and Financial Terms 29 (S) Currency in U.S. Dollars 29 (T) Applicability, Stringency and Consistency of Contract Standards 29 (U) Obligations to Provide Assistance 29 (V) Third-Party Rights 29 (W) Causing Performance 29 (X) Defined Terms 29 (Y) Acting Reasonably and in Good Faith; Discretion 30 ARTICLE 2 REPRESENTATIONS AND WARRANTIES Section 2.1. REPRESENTATIONS AND WARRANTIES OF THE CITY 31 (A) Existence and Powers 31 (B) Due Authorization 31 (C) No Conflict 31 (D) No Approvals Required 31 (E) No Litigation 31 Section 2.2. REPRESENTATIONS AND WARRANTIES OF THE DBOM CONTRACTOR 31 (A) Existence and Powers 31 (B) Due Authorization and Binding Obligation 32 (C) No Conflict 32 (D) No Approvals Required 32 (E) No Litigation Affecting the DBOM Contractor 32 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (F) No Litigation Affecting the Subcontractors 32 (G) Intellectual Property 33 (H) Information Supplied by the DBOM Contractor 33 (I) DBOM Contractor Reviews 33 (J) Compliance with Applicable Law Generally 33 Section 2.3. CONTINUING ACCURACY OF DBOM CONTRACTOR REPRESENTATIONS AND WARRANTIES 33 ARTICLE 3 TERM Section 3.1. EFFECTIVE DATE AND TERM 34 (A) Initial Term 34 (B) Renewal Term 34 (C) Accrued Rights 35 Section 3.2. SURVIVAL 35 ARTICLE 4 PROJECT SERVICES GENERALLY Section 4.1. GENERAL RESPONSIBILITIES OF THE PARTIES 36 (A) DBOM Contractor 36 (B) City 36 (C) Party Bearing Cost of Performance 36 Section 4.2. DESIGN-BUILD WORK PERSONNEL 36 (A) Staffing Requirements 36 (B) Design-Build Project Manager 36 Section 4.3. OPERATION AND MAINTENANCE SERVICES PERSONNEL 37 (A) Staffing Requirements 37 (B) Operation and Maintenance Supervisor 37 Section 4.4. KEY INDIVIDUALS 38 Section 4.5. COMPLIANCE WITH APPLICABLE LAW 38 (A) Compliance Obligation 38 (B) Governmental Approvals 38 (C) Registration, Licensing and Certification Requirements 38 (D) Investigations of Non-Compliance 38 (E) Fines, Penalties and Remediation 39 (F) Tax Compliance 39 (G) Water Infrastructure Finance and Innovation Act (WIFIA) 40 Section 4.6. TCWTP OUTFALL OBLIGATIONS AND CONDITION RISK 40 (A) DBOM Contractor TCWTP Outfall Obligations 40 (B) Condition of the TCWTP Outfall 40 Section 4.7. RESTRICTIONS ON CITY-DIRECTED DESIGN AND CONSTRUCTION REQUIREMENT CHANGES, CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES 41 Section 4.8. GOOD DESIGN-BUILD PRACTICE AND GOOD OPERATION AND MAINTENANCE PRACTICE 41 Section 4.9. FINANCIAL BOOKS AND RECORDS 42 (A) Recordkeeping Requirements 42 (B) Inspection, Audit and Adjustment 42 Section 4.10. DELIVERY OF DOCUMENTS 43 (A) DBOM Contractor 43 (B) City 43 ii 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents Section 4.11. CITY PAYMENT OBLIGATIONS GENERALLY 43 ARTICLE 5 DESIGN AND CONSTRUCTION Section 5.1. DESIGN-BUILD WORK GENERALLY 44 (A) Commencement and Prosecution of Design-Build Work 44 (B) DBOM Contractor Control of the Design-Build Work; No City Responsibility 44 (C) Materials, Labor and Services 45 (D) Project Sequencing, Schedule and Reports 45 (E) Design and Construction Requirements 45 (F) Standards of Workmanship and Materials 45 (G) Technical Standards and Codes 45 (H) Deliverable Material 46 (I) Payment of Costs 46 (J) Quality Assurance and Quality Control 46 (K) Naming and Signs 46 (L) Laydown Areas 46 (M) Maintenance of the Project Site 47 (N) Title and Risk of Loss 47 (O) Encumbrances 47 (P) Compliance with Easements and Limits; Surveying 47 (Q) Utilities 47 (R) Relocation of Existing Utilities 47 (S) Software Programming 47 (T) Demolition Work 47 (U) Notice of Default 47 (V) Plantings along Foothills Road 48 Section 5.2. ACCESS TO AND SUITABILITY OF THE PROJECT SITE 48 (A) Familiarity with the Project Site 48 (B) Access to Project Site 48 (C) Access to TCWTP Site 48 Section 5.3. [RESERVED] 48 Section 5.4. DIFFERING SITE CONDITIONS 48 (A) Further Investigations and Protection of Utilities 48 (B) DBOM Contractor Responsibility for Site Conditions 49 (C) Discovery of Differing Site Conditions 49 (D) Relief for Differing Site Conditions 49 Section 5.5. REGULATED SITE CONDITIONS 49 (A) DBOM Contractor Responsibilities 49 (B) Cultural Resources 50 (C) Endangered Species 50 (D) Encountering of Hazardous Substances 50 (E) Uncontrollable Circumstance Relief 50 (F) Generator Liability 50 Section 5.6. DESIGN-BUILD GOVERNMENTAL APPROVALS 51 (A) Generally 51 (B) Limited Permitting Assistance by the City 51 (C) DBOM Contractor Assumption of Permitting Risk for Design-Build Work 51 (D) Relief for Delays in the Issuance of DBOM Contractor Managed Governmental Approvals Caused by Governmental Bodies 51 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (E) Exception to DBOM Contractor Assumption of Permitting Risk with Respect to the NPDES Permit 52 (F) DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals 52 (G) Relief for Delays in the Issuance of City Managed Governmental Approvals Caused by Governmental Bodies 53 Section 5.7. DBOM CONTRACTOR DESIGN- GENERAL 53 (A) Design Considerations 53 (B) City Review and Comment on Design Documents 53 (C) Documents at the Project Site 54 (D) Ownership of Design and Intellectual Property 54 Section 5.8. DBOM CONTRACTOR DESIGN- REQUIREMENTS 54 Section 5.9. SECONDARY TECHNICAL CRITERIA 54 (A) Relation to Design and Construction Requirements 54 (B) Permissible Variations 55 Section 5.10. CHANGES TO DESIGN AND CONSTRUCTION REQUIREMENTS GENERALLY 55 Section 5.11. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES MADE AT DBOM CONTRACTOR REQUEST 55 Section 5.12. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES, REPAIRS AND REPLACEMENTS REQUIRED DUE TO RELIEF EVENTS OCCURRING PRIOR TO THE ACCEPTANCE DATE 56 Section 5.13. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES MADE AT CITY DIRECTION 56 Section 5.14. CONSTRUCTION PRACTICE, SAFETY AND SECURITY 57 (A) Means and Methods 57 (B) Safety and Security 57 Section 5.15. CONSTRUCTION MONITORING, OBSERVATIONS, TESTING AND UNCOVERING OF WORK 58 (A) Observation and Design Review Program 58 (B) DBOM Contractor Tests and Inspections 59 (C) City Tests, Observations and Inspections 59 (D) Certificates and Reports 59 (E) Notice of Covering Design-Build Work 59 (F) Meetings and Design-Build Work Review 60 (G) City's Third Party Oversight 60 Section 5.16. CORRECTION OF DESIGN-BUILD WORK 60 (A) Correction of Non-Conforming Design-Build Work 60 (B) Election to Accept Non-Conforming Design-Build Work 60 (C) Relation to Other Obligations 60 Section 5.17. WARRANTIES OF DESIGN-BUILD WORK 60 Section 5.18. COMMISSIONING 60 Section 5.19. SUBSTANTIAL COMPLETION 61 (A) Conditions to Substantial Completion 61 (B) Notice of Substantial Completion 62 ARTICLE 6 ACCEPTANCE Section 6.1. ACCEPTANCE TESTING 63 (A) Submittal of Acceptance Test Plan 63 (B) Acceptance Test Plan 63 (C) Notice of Commencement of the Acceptance Tests 63 (D) Conditions to Commencement of the Acceptance Tests 63 iv 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (E) Conduct of the Acceptance Tests 63 (F) Acceptance Test Report 64 Section 6.2. ACCEPTANCE CONDITIONS 64 Section 6.3. ACCEPTANCE CERTIFICATE 65 (A) Generally 65 (B) Certificate Issuance 65 (C) Deficiencies 65 (D) Effect of Issuance 65 (E) Matters Not Affected By Certificate Issuance 65 (F) Disputes Regarding Acceptance Determination 66 Section 6.4. PUNCH LIST ITEMS 66 (A) Punch List 66 (B) Minimal Impact on Project Operations 66 (C) Waiver of Acceptance Requirements 66 (D) Rectification of Punch List Items 66 (E) Failure to Rectify Punch List Items 67 Section 6.5. SCHEDULED ACCEPTANCE DATE AND LONGSTOP DATE 67 (A) Scheduled Acceptance Date Defined 67 (B) Longstop Date Defined 67 (C) Extension for Relief Events 67 Section 6.6. FAILURE TO ACHIEVE ACCEPTANCE BY THE SCHEDULED ACCEPTANCE DATE 67 (A) Delay Liquidated Damages 67 (B) Re-Testing 67 (C) No City Contribution Payments for Acceptance Prior to Acceptance Date 68 Section 6.7. FAILURE TO ACHIEVE ACCEPTANCE BY THE LONGSTOP DATE 68 Section 6.8. FINAL COMPLETION 68 (A) Requirements 68 (B) Obligation to Achieve Final Completion; Punch List Items 69 ARTICLE 7 PAYMENT FOR THE DESIGN-BUILD WORK Section 7.1. PROJECT DESIGN AND CONSTRUCTION COSTS AND FINANCING 70 Section 7.2. PAYMENT FOR DESIGN-BUILD WORK GENERALLY 70 (A) Design-Build Price 70 (B) Limitation on Payments for Costs of the Design-Build Work 70 (C) No Service Fee Payment Prior to Acceptance 70 Section 7.3. DESIGN-BUILD PRICE 70 (A) Fixed Design-Build Price 70 (B) Fixed Design-Build Price Adjustments 71 Section 7.4. [RESERVED] 74 Section 7.5. PAYMENT PROCEDURE 74 (A) Progress Payments 74 (B) Draft Requisitions 74 (C) Construction Disbursement Procedure 74 (D) Disbursement Dispute Procedures 75 (E) Retainage 76 Section 7.6. PERMISSIBLE WITHHOLDINGS 76 Section 7.7. FINAL REQUISITION AND PAYMENT 77 (A) Final Requisition for Design-Build Price 77 (B) Final Payment of Design-Build Price 77 v 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents ARTICLE 8 OPERATION AND MANAGEMENT Section 8.1. DBOM CONTRACTOR OBLIGATIONS GENERALLY 78 (A) Commencement of Operations 78 (B) Scope 78 (C) Quality Assurance and Quality Control 78 (D) No-Nuisance Covenant 78 (E) Emergency Orders and Directives 78 Section 8.2. SERVICE COORDINATION 78 (A) Communications and Meetings 78 (B) Complaints and Inquiries 79 Section 8.3. OPERATION AND MAINTENANCE MANUAL AND OPERATION AND MAINTENANCE PLAN 79 (A) DBOM Contractor Responsibility 79 (B) Supplements for Capital Modifications 79 Section 8.4. STAFFING AND PERSONNEL 80 (A) Staffing 80 (B) Training 80 Section 8.5. TRAINING OF CITY PERSONNEL 80 (A) Permanent Operations 80 (B) Compensation 80 Section 8.6. UTILITIES DURING THE OPERATION AND MAINTENANCE PERIOD 81 (A) Arrangement of Utilities 81 (B) Generation and Utilization of Project Site Solar Panels 81 Section 8.7. SAFETY AND SECURITY 81 (A) Safety 81 (B) Project Security 82 Section 8.8. OPERATING GOVERNMENTAL APPROVALS 82 (A) Applications and Submittals 82 (B) Data and Information 82 (C) Non-Compliance and Enforcement 83 (D) Reports to Governmental Bodies 83 (E) Potential Regulatory Change 83 (F) DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals 83 Section 8.9. CITY AND PORTLAND ACCESS TO THE PROJECT 84 Section 8.10. OPERATING DATA AND PROJECT RECORDS 84 (A) Computerized Information System 84 (B) Sampling, Testing and Laboratory Work 84 (C) Availability of Operating Data and Project Records to the City 84 (D) Record Documents 85 Section 8.11. PERIODIC REPORTS 85 (A) Monthly and Quarterly Operations 85 (B) Annual Operation and Maintenance Reports 85 (C) Default Reports 85 (D) Permit Communications and Reports 85 Section 8.12. EMERGENCIES 85 (A) Emergency Plan 85 (B) Emergency Action 85 Section 8.13. DOCUMENTS AND REPORTS 86 (A) Plans, Programs, Reports and Documents 86 (B) Default Reports 86 Section 8.14. DISPOSAL OF SURPLUS EQUIPMENT 86 vi 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents Section 8.15. ENFORCEMENT OF PROJECT WARRANTIES 86 ARTICLE 9 PERFORMANCE Section 9.1. PROJECT PERFORMANCE GENERALLY 87 (A) Reliance 87 (B) Curtailments and Shutdowns 87 (C) Limitations on DBOM Contractor Rights 87 (D) Timing of Applicability of Performance Guarantees 87 Section 9.2. EFFLUENT GUARANTEE 87 (A) Generally 87 (B) Deductions for Failure to Comply with the Effluent Guarantee 87 (C) Indemnity for Loss-and-Expense from Non-Complying Effluent 87 (D) Change in Law Event Affecting Effluent 88 Section 9.3. ODOR GUARANTEE 88 (A) Applicable Law Limits 88 (B) Contract Limits 88 (C) Odor Control Practices Report 88 (D) Preventing Recurrence of Violations 88 (E) Odor Incident 89 (F) Sustained Odor Condition 89 (G) Citations for Odor Incidents 89 (H) Deductions for Odor Citations 89 (I) City Monitoring 89 (J) Disregarding Prior Odor Citations 90 (K) Sustained Odor Condition Determination 90 (L) Deductions for Sustained Odor Condition Determination 90 (M) City Termination Rights Based on Failure to Meet Odor Guarantee 90 (N) Concurrent Odor Incidents and Sustained Odor Conditions 90 (O) Number of Odor Citations and Sustained Odor Condition Determinations 90 Section 9.4. ELECTRICITY CONSUMPTION GUARANTEE 91 (A) Guaranteed Maximum Electricity Consumption Calculation 91 (B) Deductions for Excess Electricity Consumption 91 (C) Guaranteed Maximum Electricity Consumption Based on Total Project Consumption 91 (D) Electricity Usage Benchmarking Program 91 Section 9.5. NOISE GUARANTEE 91 Section 9.6. MANAGEMENT OF RESIDUALS 91 (A) General Obligations 91 (B) Sludge and Scum Processing 92 (C) On-Site Storage and Loading 92 (D) Sludge and Scum Transportation and Off-Loading 92 (E) Transportation and Disposal of Grit and Screenings 92 (F) Residuals Transportation and Spills 92 (G) Sludge and Scum Information and Reporting 93 (H) Hazardous Substances 93 (I) Title to Residuals 93 (J) Failure to Comply with the Residuals Management Guarantee 93 (K) Company Rolling Stock and Labor 93 (L) Transportation Vehicle Loading and Operation 94 (M) Authorized Truck Routes 94 vii 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents Section 9.7. UPSETS AND NONCOMPLIANT INFLUENT AFFECTING DBOM CONTRACTOR COMPLIANCE WITH PERFORMANCE GUARANTEES 94 (A) Relief Generally 94 (B) Response Measures to Upsets 94 (C) Service Fee Impact 94 Section 9.8. TESTING, METERING AND WEIGHING 94 (A) Testing 94 (B) Metering and Weighing 94 Section 9.9. RELEASES, LEAKS AND SPILLS 95 (A) Unauthorized Releases Prohibited 95 (B) Notification and Reporting 95 (C) Cleanup and Costs 95 (D) Indemnification 95 Section 9.10. CITY REMEDIES FOR NON-COMPLIANCE WITH PERFORMANCE GUARANTEES 95 (A) Remedies 95 (B) Performance Testing 96 Section 9.11. ADMINISTRATIVE SANCTIONS 96 (A) Compliance Failures 96 (B) Deductions 97 ARTICLE 10 MAINTENANCE, REPAIR AND REPLACEMENT Section 10.1. MAINTENANCE, REPAIR AND REPLACEMENT GENERALLY 98 (A) Ordinary Maintenance 98 (B) Repair and Maintenance of the Grounds of the Project Site 98 (C) Major Maintenance, Repair and Replacement by the DBOM Contractor 98 Section 10.2. MAJOR MAINTENANCE, REPAIR AND REPLACEMENT SCHEDULE 99 (A) Major Maintenance, Repair and Replacement Schedule 99 (B) Major Maintenance, Repair and Replacement Schedule Adjustments 99 Section 10.3. PROJECT EVALUATION 99 (A) Initial and Final Valuation of Vehicles, Rolling Stock, Spare Parts and Consumables 99 (B) Baseline Project Record 100 (C) Final Evaluation of the Project 100 (D) Required Condition of Project Structures at the End of the Term 100 (E) Required Condition of Project Equipment at the End of the Term 100 (F) Required Condition of Capital Modifications at the End of the Term 101 (G) Exit Testing 101 (H) Termination Letter of Credit 102 (I) Disputes 102 Section 10.4. PERIODIC MAINTENANCE INSPECTIONS 102 (A) Annual Maintenance Inspection 102 (B) Full-Scale Inspections 102 (C) Remediation 103 (D) Unscheduled Inspections 103 Section 10.5. COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM 103 viii 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents ARTICLE 11 CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES Section 11.1. CAPITAL MODIFICATIONS GENERALLY 105 (A) City Approval 105 (B) Small-Scale Capital Modifications 105 (C) Conditioned Approvals 105 (D) Responsibility for Costs 105 (E) No DBOM Contractor Ownership 105 Section 11.2. CAPITAL MODIFICATIONS AT DBOM CONTRACTOR REQUEST 105 Section 11.3. CAPITAL MODIFICATIONS ARISING FROM REPAIRS AND REPLACEMENTS OR REQUIRED TO REMEDY A DBOM CONTRACTOR FAULT 106 Section 11.4. CAPITAL MODIFICATIONS, REPAIRS AND REPLACEMENTS REQUIRED DUE TO RELIEF EVENTS OCCURRING FOLLOWING THE ACCEPTANCE DATE 106 Section 11.5. CAPITAL MODIFICATIONS AT CITY DIRECTION 107 Section 11.6. PRIMARY PROCEDURE FOR IMPLEMENTING CAPITAL MODIFICATIONS 107 (A) Primary Implementation Procedure 107 (B) Initial Assessment 107 (C) DBOM Contractor Conceptual Plan and City Review 107 (D) DBOM Contractor Implementation Proposal 108 (E) Negotiation and Finalization of DBOM Contractor Implementation Proposal 109 (F) Implementation Procedures 110 (G) Nutrient Removal Capital Modifications 110 Section 11.7. ALTERNATIVE PROCEDURES FOR IMPLEMENTING CAPITAL MODIFICATIONS 110 Section 11.8. OPERATION AND MAINTENANCE SERVICES CHANGES 110 (A) Generally 110 (B) DBOM Contractor Operation and Maintenance Services Change Report 110 (C) Valuation of Operation and Maintenance Services Changes 112 (D) Justification and Supporting Documentation 113 (E) Agreement on an Operation and Maintenance Services Change 113 (F) Operation and Maintenance Services Change Certificate 113 (G) Disagreement on Operation and Maintenance Services Change Report 114 (H) Responsibility and Payment for Operation and Maintenance Services Changes 114 (I) Cost Savings 114 (J) Operation and Maintenance Services Changes at DBOM Contractor Request 114 Section 11.9. FINANCING CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES 115 (A) Financing Responsibilities 115 (B) Third Party Borrowing or Financing 115 ARTICLE 12 CONTRACTING AND LABOR PRACTICES Section 12.1. USE OF SUBCONTRACTORS 116 ix 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (A) Subcontractors 116 (B) Use of Subcontractors and Key Individuals 116 (C) Restricted Persons 116 (D) Oregon Construction Contractors Board 116 Section 12.2. SUBCONTRACTS 116 (A) Terms and Actions 116 (B) Indemnity for Claims 116 (C) Assignability 116 (D) DBOM Contractor Payment Requirements in General 116 (E) Subcontractor Timely Payment Requirements 117 (F) Right to File a Complaint with the Oregon Construction Contractors Board 117 Section 12.3. MATERIAL CONTRACTS 117 (A) City Consents 117 (B) Timeframe for Consents 117 (C) Costs of Request for Consent 118 Section 12.4. REPLACEMENT MATERIAL CONTRACTS 118 Section 12.5. EQUITY, INCLUSION AND DIVERSITY SUBCONTRACTING REQUIREMENTS 118 Section 12.6. DESIGN-BUILD WORK LABOR AND WAGE REQUIREMENTS 118 (A) Payment of Prevailing Wages; Recordkeeping Requirements 118 (B) Public Works Bond to Assume Payment of Prevailing Wages 119 Section 12.7. LABOR RELATIONS AND DISPUTES 119 (A) Labor Relations 119 (B) Labor Disputes 119 Section 12.8. OVERTIME 119 (A) Employee Overtime Requirements 119 (B) Overtime Notice Requirements 120 Section 12.9. OTHER LABOR REQUIREMENTS 120 (A) Prohibition of Discriminatory Wage Rates Based on Sex 120 (B) Compensation Discussion Prohibitions Restricted 120 Section 12.10. WORKERS' COMPENSATION 120 Section 12.11. EMPLOYEE HEALTH REQUIREMENTS 120 (A) Employee Drug Testing Program 120 (B) Payment of Medical Care 120 ARTICLE 13 INSURANCE, DAMAGE AND DESTRUCTION Section 13.1. INSURANCE 121 (A) Required Insurance 121 (B) Subcontractors 121 (C) Compliance with Insurer Requirements 121 (D) DBOM Contractor Failure to Provide Insurance Coverage 121 (E) Reductions for Insurance Proceeds and Insurance Receivables 121 (F) Property Insurance Proceeds 122 Section 13.2. LOSS, DAMAGE OR DESTRUCTION TO THE PROJECT AND PRIVATE PROPERTY 122 (A) Protection and Repair of the Project 122 (B) Repair of City and Private Property 122 (C) Damage or Destruction from Uninsurable Force Majeure Events 122 (D) Damage or Destruction from Other Relief Events 122 (E) Damage or Destruction from Insurable Force Majeure Events 122 (F) Other Third-Party Payments 123 x 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (G) DBOM Contractor Cost Responsibility 123 Section 13.3. DBOM AGREEMENT NOT AFFECTED BY DAMAGE OR DESTRUCTION 123 ARTICLE 14 RELIEF EVENT PROCEDURES Section 14.1. RELIEF EVENTS GENERALLY 124 (A) Extent of Relief Available to the DBOM Contractor 124 (B) Mitigation Given Effect 124 (C) Applicable Law Compliance 124 Section 14.2. PROCEDURES UPON THE OCCURRENCE OF A RELIEF EVENT 124 (A) Notice and Written Report 124 (B) Updates 124 (C) Submittal of Relief Request 125 (D) Burden of Proof and Mitigation 125 (E) Resumption of Performance 125 (F) City Response 125 (G) Agreement or Dispute 125 Section 14.3. RELEASE 125 ARTICLE 15 FORCE MAJEURE EVENTS Section 15.1. INSURABLE FORCE MAJEURE EVENTS 126 (A) DBOM Contractor Reinstatement 126 (B) Schedule Relief 126 (C) Performance Relief 126 (D) No Compensation Relief 126 (E) Application of Property and Builder's Risk Insurance Proceeds Available for Repair, Replacement or Restoration 126 (F) Insurance Deductibles and Exceedances 127 (G) City Remedies and Termination Right 127 Section 15.2. UNINSURABLE FORCE MAJEURE EVENTS 127 (A) DBOM Contractor Reinstatement 127 (B) Schedule Relief 127 (C) Performance Relief 127 (D) Compensation Relief 127 (E) Disaster Relief Funds 128 (F) Termination Rights 128 Section 15.3. DBOM CONTRACTOR'S OBLIGATIONS UPON MATERIAL DAMAGE OR DESTRUCTION 128 (A) Draft Reinstatement Plan 128 (B) City Responsibilities 128 (C) Reinstatement Plan 128 (D) Reinstatement Plan Details 129 Section 15.4. STANDARDS OF REPLACEMENT, REPAIR OR RECONSTRUCTION 129 Section 15.5. AVAILABILITY OF INSURANCE FOR UNINSURABLE FORCE MAJEURE EVENTS 129 (A) Additional Insurance 129 (B) Additionally Insured Risk to Constitute an Insurable Force Majeure Event; Qualifications 130 Section 15.6. UNAVAILABILITY OF INSURANCE FOR INSURABLE FORCE MAJEURE EVENTS OR FOR THIRD-PARTY LIABILITY 130 xi 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (A) Insurance Unavailability Event 130 (B) Termination by City 130 (C) Continuance of DBOM Agreement 130 (D) Subrogation 131 (E) City Right to Purchase Replacement Insurance Coverage 131 Section 15.7. CONTINUING ATTEMPTS TO OBTAIN INSURANCE 131 ARTICLE 16 CHANGE IN LAW EVENTS AND OTHER RELIEF EVENTS Section 16.1. CHANGE IN LAW EVENTS 132 (A) Schedule Relief 132 (B) Performance Relief 132 (C) Compensation Relief 132 Section 16.2. DISCRIMINATORY OR SPECIFIED CHANGES IN TAX LAW 132 Section 16.3. OTHER RELIEF EVENTS 133 (A) Schedule Relief 133 (B) Performance Relief 133 (C) Compensation Relief 133 Section 16.4. TERMINATION FOR EXTENDED RELIEF EVENTS 133 (A) Termination Right 133 ARTICLE 17 SERVICE FEE AND OTHER PAYMENTS Section 17.1. SERVICE FEE GENERALLY 134 (A) Service Fee Payment Obligation 134 (B) Limitation on Payments 134 Section 17.2. SERVICE FEE FORMULA 134 Section 17.3. OPERATION AND MAINTENANCE CHARGE 134 (A) Generally 134 (B) Ordinary Operation and Maintenance Component 134 (C) Pass-Through Electricity Component 134 (D) Sludge Transportation to Columbia Boulevard 135 Section 17.4. REIMBURSABLE COSTS CHARGE 135 Section 17.5. ANNUAL CAPITAL MAINTENANCE CHARGE 135 (A) Generally 135 (B) Annual Capital Maintenance Charge 135 (C) Annual Adjustment to the Annual Capital Maintenance Charge 135 (D) MRR Account 135 (E) Requisitions Against MRR Account 135 (F) Carryover and Insufficiency of MRR Account Funds 136 (G) Amounts Remaining in MRR Account 136 (H) No Limitation on DBOM Contractor Obligations 136 Section 17.6. DEDUCTIONS CREDIT 137 Section 17.7. EXTRAORDINARY ITEMS 137 Section 17.8. BILLING AND PAYMENT 138 (A) Installments 138 (B) Invoicing and Service Fee Payment Due Date 138 (C) Late Service Fee Payments 139 Section 17.9. ESTIMATES AND ADJUSTMENTS 139 (A) First and Last Billing Periods 139 (B) Annual Service Fee Estimate for City Budgeting Purposes 139 xii 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents Section 17.10. ANNUAL SETTLEMENT 139 Section 17.11. SALES TAXES 140 Section 17.12. CITY'S RIGHT OF SET OFF 140 Section 17.13. BILLING STATEMENT DISPUTES 140 Section 17.14. PRIVATE BUSINESS USE RESTRICTIONS 140 (A) Payments to DBOM Contractor 140 (B) Review of Adjustments to the Service Fee 140 ARTICLE 18 SECURITY FOR PERFORMANCE Section 18.1. PARENT COMPANY GUARANTOR 142 (A) Parent Company Guaranty Agreement 142 (B) Reports and Notifications Concerning the Financial Condition of the Parent Company Guarantor 142 (C) Material Adverse Change to the Financial Condition of the Parent Company Guarantor 142 (D) Credit Enhancement Upon a Material Adverse Change 143 (E) City Termination Rights Associated with the Financial Condition of the Parent Company Guarantor 143 Section 18.2. PAYMENT AND PERFORMANCE BONDS 143 Section 18.3. OPERATION AND MAINTENANCE LETTER OF CREDIT 144 Section 18.4. ADDITIONAL SECURITY FOR PROJECT SERVICES 144 Section 18.5. COSTS OF PROVIDING SECURITY FOR PERFORMANCE 144 ARTICLE 19 DISPUTE RESOLUTION Section 19.1. FORUM FOR DISPUTE RESOLUTION 145 Section 19.2. NON-BINDING MEDIATION GENERALLY 145 (A) Rights to Request and Decline 145 (B) Procedure 145 (C) Non-Binding Effect 145 (D) Relation to Judicial Legal Proceedings 145 Section 19.3. BINDING ARBITRATION FOR CERTAIN SMALLER CLAIMS 145 ARTICLE 20 REMEDIES OF THE PARTIES AND CITY STEP-IN RIGHTS Section 20.1. REMEDIES FOR BREACH 147 Section 20.2. CITY LIQUIDATED DAMAGES RIGHTS 147 (A) City Liquidated Damages Rights Defined 147 (B) Sole Remedy; Exceptions 147 Section 20.3. CITY'S TEMPORARY STEP-IN RIGHTS DURING THE OPERATION AND MAINTENANCE PERIOD 148 Section 20.4. CITY'S RECTIFICATION RIGHTS 148 Section 20.5. NOTICE OF CAPITAL MODIFICATION 149 Section 20.6. NO EFFECT ON PROJECT SERVICES 149 Section 20.7. ALLOCATION OF COSTS AND PROVISION OF RELIEF FOR CITY'S EXERCISE OF STEP-IN RIGHTS 149 Section 20.8. NO WAIVER OF REMEDIES 149 Section 20.9. EXERCISE OF REMEDIES 150 xiii 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (A) Remedies Exclusive 150 (B) Similar Rights and Remedies 150 (C) Single or Partial Exercise of Remedies 150 Section 20.10. NO DUPLICATIVE RECOVERY OR CLAIMS OUTSIDE CONTRACT 150 Section 20.11. NO SPECIAL, CONSEQUENTIAL OR PUNITIVE DAMAGES 150 ARTICLE 21 DBOM CONTRACTOR EVENTS OF DEFAULT Section 21.1. DBOM CONTRACTOR EVENTS OF DEFAULT 151 (A) DBOM Contractor Events of Default Defined 151 (B) DBOM Contractor Remediable Breach Defined 152 (C) DBOM Contractor Bankruptcy-Related Event Defined 153 Section 21.2. NOTIFICATION BY THE DBOM CONTRACTOR 154 Section 21.3. DBOM CONTRACTOR REMEDIABLE BREACH CURE AND REMEDIAL PROGRAM 154 (A) Notice and Remedy or Remedial Program 154 (B) City Acceptance or Non-Acceptance 154 (C) Remediable Program Limited to DBOM Contractor Remediable Breaches 154 Section 21.4. CITY TERMINATION RIGHT 155 (A) Termination Right 155 (B) Relief Events Affecting Performance of Remedial Program 155 ARTICLE 22 CITY EVENTS OF DEFAULT Section 22.1. CITY EVENTS OF DEFAULT 156 Section 22.2. DBOM CONTRACTOR OPTIONS UPON CITY EVENT OF DEFAULT 156 Section 22.3. EFFECT OF TERMINATION 156 ARTICLE 23 TERMINATION Section 23.1. EXCLUSIVE RIGHTS OF TERMINATION 158 (A) Termination of this DBOM Agreement 158 (B) Exclusive Termination Rights 158 Section 23.2. TERMINATION 158 (A) City Termination Rights 158 (B) DBOM Contractor Termination Rights 158 (C) Termination Upon Total Constructive Loss 158 (D) Extent of Termination Rights 159 (E) Termination Date 159 (F) Termination Payments 159 (G) Settlement of Subcontracts 160 (H) Payment of Amounts Due as a Result of Termination 160 (I) Consideration for Convenience Termination Amount 161 (J) Continued Performance 161 (K) Completion or Continuance by City 161 Section 23.3. TRANSFER TO THE CITY OF ASSETS, CONTRACTS AND DOCUMENTS 161 (A) Transfer Responsibilities 161 xiv 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents (B) No Additional Compensation 163 (C) Use of Design Documents Following Termination During the Design-Build Period 163 Section 23.4. TRANSITIONAL ARRANGEMENTS 163 (A) DBOM Contractor Transitional Obligations 163 (B) Equitable Relief 164 Section 23.5. DBOM CONTRACTOR TO COOPERATE 164 Section 23.6. LIMITATION ON DBOM CONTRACTOR LIABILITY 164 (A) Initial Stated Monetary Limitation 164 (B) Delay Liquidated Damages Sub-Limit 164 (C) Stated Monetary Limitation Following First Calendar Year After Acceptance Date through the End of the Term 165 Section 23.7. APPLICABILITY AND INTERPRETATION OF THE LIMITATIONS ON LIABILITY 165 ARTICLE 24 ASSIGNMENT AND CHANGE IN CONTROL Section 24.1. LIMITATION ON ASSIGNMENT BY THE DBOM CONTRACTOR 166 Section 24.2. LIMITATION ON CHANGE IN CONTROL 166 (A) Change in Control Defined 166 (B) Limitations 166 Section 24.3. FACTORS THE CITY MAY CONSIDER 167 Section 24.4. LIMITATION ON ASSIGNMENT BY THE CITY 167 Section 24.5. COSTS OF REQUEST FOR CONSENT 167 ARTICLE 25 INDEMNIFICATION Section 25.1. DBOM CONTRACTOR'S OBLIGATION TO INDEMNIFY 169 Section 25.2. INDEMNIFICATION PROCEDURES 169 (A) Notice 169 (B) DBOM Contractor Right to Dispute Claim 170 (C) Conflicts of Interest 170 (D) Rights and Duties of the Parties 170 (E) City Indemnitee Rights to Conduct Defense 170 (F) Transfer of Conduct of Claim to City Indemnitee 170 (G) Infringement of Intellectual Property Rights 170 ARTICLE 26 MISCELLANEOUS PROVISIONS Section 26.1. OWNERSHIP OF THE PROJECT AND ENVIRONMENTAL ATTRIBUTES; NO LEASE 172 (A) Project Ownership 172 (B) Environmental Attributes Ownership 172 Section 26.2. RELATIONSHIP OF THE PARTIES 172 Section 26.3. [RESERVED] 172 Section 26.4. DBOM CONTRACTOR PERSONS 172 Section 26.5. RISK OF ADVERSE TAX OR ACCOUNTING TREATMENT 173 Section 26.6. NEGOTIATED LUMP SUM PRICING OF ADDITIONAL WORK 173 xv 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents Section 26.7. COST SUBSTANTIATION OF ADDITIONAL WORK NOT SUBJECT TO LUMP SUM PRICE NEGOTIATION 174 (A) Cost Substantiation Generally 174 (B) Costs Requiring Cost Substantiation 174 (C) Cost Substantiation Certificate 174 (D) Evidence of Costs Incurred 175 (E) Mark-Ups 175 Section 26.8. INTEREST ON OVERDUE AMOUNTS 175 Section 26.9. ALL CITY PAYMENT OBLIGATIONS SUBJECT TO APPROPRIATION 175 Section 26.10. GENERAL DUTY TO MITIGATE 175 (A) Mitigation by the DBOM Contractor 175 (B) Mitigation by the City 175 Section 26.11. BUSINESS AND COMMERCIAL OPPORTUNITIES 176 Section 26.12. DBOM AGREEMENT ADMINISTRATION 176 (A) Authority of City Representative 176 (B) Operation and Maintenance Notices 176 (C) Administrative Communications 176 (D) Contract Administration Memoranda 176 (E) Procedure 177 (F) Effect 177 Section 26.13. DBOM AGREEMENT AMENDMENTS 177 (A) Amendments Generally 177 (B) DBOM Agreement Amendments and Contract Administration Memoranda 177 Section 26.14. CITY APPROVALS AND CONSENTS 177 Section 26.15. REFERENCE DOCUMENTS 178 Section 26.16. ACTIONS OF THE CITY IN THEIR GOVERNMENTAL CAPACITY 178 Section 26.17. CONFIDENTIALITY 178 (A) Confidential Information 178 (B) Exceptions 179 (C) Security Plan 179 (D) Public Communications of Confidential Information 179 (E) Equitable Relief 179 Section 26.18. COMPLIANCE WITH MATERIAL AGREEMENTS 179 Section 26.19. BINDING EFFECT 179 Section 26.20. CONSENTS 180 Section 26.21. NOTICES 180 (A) Procedure 180 (B) City Notice Address 180 (C) DBOM Contractor Notice Address 180 Section 26.22. NOTICE OF LITIGATION 181 Section 26.23. FURTHER ASSURANCES 181 xvi 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Table of Contents TRANSACTION FORMS TRANSACTION FORM A PARENT COMPANY GUARANTY AGREEMENT APPENDICES APPENDIX 1 SITE-RELATED INFORMATION ATTACHMENT 1A DESIGN-BUILD PROJECT SITE PLAN ATTACHMENT 1B OPERATIONS AND MAINTENANCE PROJECT SITE PLAN APPENDIX 2 GOVERNMENTAL APPROVALS ATTACHMENT 2A EXPECTED DESIGN-BUILD GOVERNMENTAL APPROVALS ATTACHMENT 2B EXPECTED OPERATIONS GOVERNMENTAL APPROVALS APPENDIX 3 CERTAIN FEDERAL REQUIREMENTS ATTACHMENT 3A DAVIS-BACON ACT WAGE DETERMINATIONS APPENDIX 4 DESIGN AND CONSTRUCTION REQUIREMENTS APPENDIX 5 SECONDARY TECHNICAL CRITERIA APPENDIX 6 DESIGN-BUILD WORK REVIEW PROCEDURES APPENDIX 7 GENERAL DESIGN-BUILD WORK REQUIREMENTS ATTACHMENT 7A PROJECT SCHEDULE APPENDIX 8 COMMISSIONING AND ACCEPTANCE TESTING ATTACHMENT 8A PRELIMINARY COMMISSIONING PLAN ATTACHMENT 8B PRELIMINARY ACCEPTANCE TEST PLAN APPENDIX 9 DESIGN-BUILD WORK SCHEDULE OF VALUES AND MAXIMUM DRAWDOWN SCHEDULES ATTACHMENT 9A DESIGN-BUILD PRICE SCHEDULE OF VALUES ATTACHMENT 9B DESIGN-BUILD PRICE MAXIMUM DRAWDOWN SCHEDULE APPENDIX 10 OPERATION AND MAINTENANCE REQUIREMENTS ATTACHMENT 10A PRELIMINARY OPERATION AND MAINTENANCE PLAN ATTACHMENT 10B MAJOR MAINTENANCE, REPAIR AND REPLACEMENT SCHEDULE APPENDIX 11 ODOR CONTROL STANDARD AND ODOR CONTROL PLAN APPENDIX 12 INSURANCE REQUIREMENTS ATTACHMENT 12A OWNER CONTROLLED INSURANCE PROGRAM REQUIREMENTS APPENDIX 13 PERFORMANCE GUARANTEES AND DEDUCTIONS APPENDIX 14 EXAMPLE CALCULATION OF SERVICE FEE APPENDIX 15 PROJECT FACILITIES EVALUATION PROTOCOL APPENDIX 16 EXIT TESTING APPENDIX 17 REFERENCE DOCUMENTS APPENDIX 18 REPORTS AND RECORDS APPENDIX 19 DBOM CONTRACTOR AND SUBCONTRACTORS INFORMATION ATTACHMENT 19A KEY INDIVIDUALS RESUMES APPENDIX 20 PUBLIC COMMUNICATIONS APPENDIX 21 DESIGN-BUILD QUALITY MANAGEMENT PLAN APPENDIX 22 EQUIPMENT AND MATERIALS SUBJECT TO COST ADJUSTMENT xvii 3935946.13 043463 DBOM AGREEMENT FOR THE DESIGN, CONSTRUCTION, OPERATION AND MAINTENANCE OF THE LAKE OSWEGO WASTEWATER TREATMENT FACILITY THIS DBOM AGREEMENT FOR THE DESIGN, CONSTRUCTION, OPERATION AND MAINTENANCE OF THE LAKE OSWEGO WASTEWATER TREATMENT FACILITY is entered into on [ ], 2026, between City of Lake Oswego, Oregon (the "City"), and Jacobs Project Management Co. a corporation organized and existing under the laws of the State of Delaware, including its permitted successors and assigns (the "DBOM Contractor"). RECITALS WHEREAS, the City is currently a customer of the City of Portland's Tryon Creek Wastewater Treatment Plant; WHEREAS, the City of Portland has determined that the aging Tryon Creek Wastewater Treatment Plant will require significant capital expenditures in order to continue to provide service in accordance with all governmental approvals; WHEREAS, the City has determined that it would be beneficial for the City to develop a new wastewater treatment facility which will provide service to the City and portions of the City of Portland; WHEREAS, the City has further determined that it would be in the City's interest to contract with a private entity to design, construct, commission, acceptance test, operate, maintain and obtain certain governmental approvals for a new wastewater treatment facility(the "Project"); WHEREAS, the City made findings and adopted Resolution No. 24-19 pursuant to ORS 279C.335(2) and OAR 137-49-0130, -0620, -0610, -0640, -0645, -0650 and -0660 which provides the City with the Authority to procure the Project on a design, build, operate and maintain basis; WHEREAS, pursuant to such authority, the City issued a request for qualifications on July 19, 2024, in order to short-list the design-build-operate-maintain entities who would receive the request for proposals; WHEREAS, on July 29, 2025, the City issued a request for proposals for the Project; WHEREAS, in November, 2025, negotiations were initiated with the DBOM Contractor, which negotiations have concluded with this DBOM Agreement; WHEREAS, on October 13, 2026, the City's Council authorized the execution and delivery of this DBOM Agreement in Resolution [ ]; WHEREAS, Jacobs Engineering Group Inc. will guarantee the performance of the obligations of the DBOM Agreement pursuant to a guaranty agreement executed concurrently herewith; 1 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Recitals WHEREAS, the Project will be designed, permitted, constructed, commissioned, acceptance tested, operated and maintained by the DBOM Contractor pursuant to the terms of this DBOM Agreement including the Appendices attached hereto; and WHEREAS, the City desires to receive, and the DBOM Contractor desires to provide design, permitting, construction commissioning, testing, operation and maintenance services as described herein under the terms of this DBOM Agreement. NOW THEREFORE, in consideration of the mutual covenants herein contained and other good and valuable consideration, the receipt and sufficiency of which are hereby expressly acknowledged, the parties hereto, intending to be legally bound, covenant and agree as follows: 3935946.13 043463 ARTICLE 1 DEFINITIONS AND INTERPRETATION Section 1.1. DEFINITIONS. As used in this DBOM Agreement, the following capitalized terms have the meanings set forth below. Certain words and expressions are defined within the Appendices hereto, and such definitions shall apply, unless the context otherwise requires, in all other parts of this DBOM Agreement whether or not this Article contains a cross-reference to such definitions. "Acceptance" means satisfaction of the Acceptance Conditions by the DBOM Contractor and issuance of the Acceptance Certificate by the City. "Acceptance Certificate" means a certificate delivered by the City in accordance with Section 6.3 (Acceptance Certificate). "Acceptance Conditions" has the meaning set forth in Section 6.2 (Acceptance Conditions). "Acceptance Date" means the date on which Acceptance of the Project occurs or is deemed to have occurred under Article 6 (Acceptance). "Acceptance Standards" means the standards for Acceptance as set forth in Appendix 8 (Commissioning and Acceptance Testing). "Acceptance Test Plan"means the sub plan within the Commissioning Plan that describes the testing protocols, procedures and processes for the performance of the Acceptance Tests prepared by the DBOM Contractor and approved by the City in accordance with Appendix 8 (Commissioning and Acceptance Testing). "Acceptance Tests" means the tests required for Acceptance, as more particularly described in Article 6 (Acceptance) and Appendix 8 (Commissioning and Acceptance Testing). "Additional Renewal Term" has the meaning set forth in subsection 3.1(B) (Renewal Term). "Affiliate" in respect of a person means any other person that, directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such first person, where "control" means, with respect to the relationship between or among two or more persons, the possession, directly or indirectly or as trustee, personal representative or executor, of the power to direct or cause the direction of the affairs or management of a person, whether through the ownership of voting securities, as trustee, personal representative or executor, by statute, contract, credit arrangement or otherwise, including the ownership, directly or indirectly, of securities having the power to elect a majority of the board of directors or similar body governing the affairs of such person. "Annual Capital Maintenance Charge" has the meaning set forth in subsection 17.5(B) (Annual Capital Maintenance Charge). 3 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "Appendix" means any of the Appendices and, as applicable, any schedules and attachments thereto, that are appended to this DBOM Agreement and identified as such in the Table of Contents. "Applicable Law" means: (1) Any federal, State or local law, statute, code or regulation; (2) Any formally adopted and generally applicable rule, requirement, determination, standard, policy, implementation schedule, or other order of any Governmental Body having appropriate jurisdiction; and (3) Any Governmental Approval, in each case having the force of law and applicable from time to time to the Project or the DBOM Contractor or any Subcontractor. "Avoidable Costs" when used in relation to an event or circumstance, means all costs and expenditures which: (1) Are saved or avoided as a result of, or in responding to, the event or circumstance or its effects; or (2) If the DBOM Contractor acted reasonably and in accordance with this DBOM Agreement (including subsection 26.10(A) (Mitigation by the DBOM Contractor)) would have been saved or avoided as a result of, or in responding to, the event or circumstance or its effects. "Bankruptcy Law" means the United States Bankruptcy Code, 11 U.S.C. 101 et seq., as amended from time to time and any successor statute thereto. "Bankruptcy Law" also includes (1) any similar state law relating to bankruptcy, insolvency, the rights and remedies of creditors, the appointment of receivers or the liquidation of companies and estates that are unable to pay their debts when due, and (2) in the event the Parent Company Guarantor is incorporated or otherwise organized under the laws of a jurisdiction other than the United States, any similar insolvency or bankruptcy code applicable under the laws of such jurisdiction. "Baseline Groundwater Data Report" means the Baseline Groundwater Data report by WSP USA Environment & Infrastructure Inc., dated September 26, 2022. "Baseline Project Record" has the meaning set forth in subsection 10.3(B) (Baseline Project Record). "Billing Period" means each month of a Contract Year except that: (1) The first Billing Period of the first Contract Year shall begin on the Acceptance Date and shall continue to the last day of the month, in which the Acceptance Date occurs, and (2) The last Billing Period of the last Contract Year shall end on the last day of the Term. Any computation made on the basis of a Billing Period shall be adjusted on a pro rata basis to take into account any Billing Period of less than the actual number of days in the month to which such Billing Period relates. 4 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "Business Day" means a day other than a Saturday, Sunday, or an official City holiday. "Capital Modification" means any material change to any part of the physical assets constituting the Project occurring after the Acceptance Date other than a previously contemplated Major Maintenance, Repair and Replacement included in the Major Maintenance, Repair and Replacement Schedule, including the alteration, addition, demolition or extension of the physical assets constituting the Project or the installation of new structures, equipment, systems or technology. "CERCLA" means the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. 9601 et seq., and applicable regulations promulgated thereunder, each as amended from time to time. "Change in Control" has the meaning set forth in subsection 24.2(A) (Change in Control Defined). "Change in Law Event" means the coming into effect of: (1) Any Applicable Law enacted, promulgated or issued (as applicable) after the Effective Date; (2) Any modification (including repeal) of any Applicable Law existing on the Effective Date that comes into effect after the Effective Date; or (3) A binding change after the Effective Date in the judicial interpretation of any Applicable Law. compliance with which, in accordance with the Contract Standards, materially expands the scope or materially interferes with, delays or increases the cost of performing the Project Services. It is specifically understood, however, that none of the following shall constitute a "Change in Law Event": (1) Any law, statute, code or regulation that has been enacted or adopted on or before the Effective Date to take effect after the Effective Date; (2) The denial, delay in issuance of, or imposition of any term or condition in connection with, any Governmental Approval required for the Project Services, except as and to the extent set forth in subsection 5.6(D) (Relief for Delays in the Issuance of Governmental Approvals Caused by Governmental Bodies) and subsection 5.6(E) (Exception to DBOM Contractor Assumption of Permitting Risk with Respect to the NPDES Permit); (3) A change in the nature or severity of the actions typically taken by a Governmental Body to enforce compliance with Applicable Law which was in effect as of the Effective Date; (4) Any increase in any fines or penalties provided for under Applicable Law in effect as of the Effective Date; (5) Any new, or modification to an existing, Applicable Law that affects generally applicable working or administrative conditions, working or administrative requirements or working or administrative standards that is not specific to the 5 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation wastewater or other similar critical infrastructure industry or the Project (except that the DBOM Contractor shall be entitled to relief on account of new, or modifications to, Applicable Law regarding payment of prevailing wages for labor performing Operation and Maintenance Services); (6) Any act, event or circumstance that would otherwise constitute a Change in Law Event but that does not change the requirements imposed on the DBOM Contractor by the Contract Standards in effect as of the Effective Date; or (7) Any change in Tax law (except that the DBOM Contractor shall be entitled to relief on account of(a) a Discriminatory Change in Tax Law or a Specified Change in Tax Law as and to the extent provided in Section 16.2 (Discriminatory or Specified Changes in Tax Law), or (b) a change in duties, levies, imports or tariffs imposed by the United States on imported goods). "Change Order" means a written order signed by the City and the DBOM Contractor prior to the Acceptance Date, making a Design and Construction Requirement Change. A Change Order shall be deemed to constitute a DBOM Agreement Amendment. "City" means the City of Lake Oswego, Oregon. "City Event of Default" has the meaning set forth in Section 22.1 (City Events of Default). "City Fault" means: (1) A breach by the City of any of its obligations (other than payment obligations) under this DBOM Agreement; (2) A breach of any representation or warranty by the City under this DBOM Agreement; (3) Willful misconduct of the City or any employee, contractor, representative, advisor or agent of the City in each case acting as such; or (4) A negligent act or omission of the City or any employee, contractor, representative, advisor or agent of the City in each case acting as such. "City Indemnitee" means: (1) The City; or (2) Any representative, agent or advisor (including legal, technical and financial advisors) of the City or any manager, official, employee, contractor or subcontractor (of any tier) thereof, in any such person's capacity as a provider of services directly or indirectly to the City in connection with the Project, other than the DBOM Contractor or Subcontractors. "City Managed Governmental Approvals" means those Governmental Approvals for which the City is the application manager and is responsible for obtaining as designated in Appendix 2 (Governmental Approvals). "City Property" means any structures, improvements, equipment, fire alarm systems,valves, pumping systems,wastewater and water mains, hydrants, hydrant connections, 6 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation duct lines, lamps, lampposts, monuments, sidewalks, curbs, trees, lawns, roadways, utilities or any other systems, fixtures, or real or personal property owned, leased, operated, maintained, or occupied by the City. "City Representative" means the individual specified in writing by the City as the representative of the City from time to time for all purposes of this DBOM Agreement. "CMMS" has the meaning set forth in Section 10.5 (Computerized Maintenance Management System). "Commissioning" means the start-up, initial operations and commissioning of the Project Facilities, including tuning and adjusting systems, subsystems and equipment, in order to achieve stable operating conditions in preparation for the Acceptance Tests, as further described in Appendix 8 (Commissioning and Acceptance Testing). "Commissioning Plan" means the plan for the Commissioning of the Project Facilities prepared pursuant to Appendix 8 (Commissioning and Acceptance Testing). "Confidential Information" means information of a party that the party has designated as confidential and which is supplied, or to which access is granted, to or on behalf of the other party (whether before or after the Effective Date), either in writing, or in any other form, directly or indirectly pursuant to discussions with the other party and includes all analyses, compilations, studies and other documents whether prepared by or on behalf of a party which contain or otherwise reflect or are derived from such designated information. "Contract Administration Memorandum" has the meaning set forth in Section 26.12 (DBOM Agreement Administration). "Contract Standards" means the standards, terms, conditions, methods, techniques and practices imposed or required by: (1) Applicable Law; (2) The Design and Construction Requirements; (3) Good Design-Build Practice; (4) The Operation and Maintenance Requirements; (5) Good Operation and Maintenance Practice; (6) The Design-Build Plans; (7) The Operation and Maintenance Plan and the Operation and Maintenance Manual; (8) Applicable written equipment manufacturers'specifications; (9) Applicable Insurance Requirements; (10) The Acceptance Standards and Performance Guarantees; and (11) Any other standard, term, condition or requirement explicitly provided in this DBOM Agreement to be observed by the DBOM Contractor. 7 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation Subsection 1.2(T) (Applicability, Stringency and Consistency of Contract Standards) shall govern issues of interpretation related to the applicability, consistency and stringency of the Contract Standards. "Contract Year" means each of: (1) The period from the Acceptance Date to the next June 30th; (2) Each subsequent period of 12 calendar months commencing on July 1st; and (3) The period from July 1st in the year in which this DBOM Agreement expires or is terminated (for whatever reason) to and including the Termination Date. Any computation made on the basis of a Contract Year shall be adjusted on a pro rata basis to take into account any Contract Year of less than 365 or 366 days, whichever is applicable. "Cost Substantiation" has the meaning described in Section 26.7 (Cost Substantiation of Additional Work Not Subject to Lump Sum Price Negotiation). "DBOM Agreement" means this DBOM Agreement, and includes the Transaction Forms, Appendices and Reference Documents (as applicable). "DBOM Agreement Amendment" has the meaning set forth in Section 26.13 (DBOM Agreement Amendments). "DBOM Contractor" means Jacobs Project Management Co., a corporation organized and existing under the laws of the State of Delaware,which is registered to do business in and is in good standing in the State, and its permitted successors and assigns. "DBOM Contractor Bankruptcy-Related Event" has the meaning set forth in subsection 21.1(C) (DBOM Contractor Bankruptcy-Related Event Defined). "DBOM Contractor Event of Default" has the meaning set forth in subsection 21.1(A) (DBOM Contractor Events of Default Defined). "DBOM Contractor Fault" means: (1) A breach by the DBOM Contractor of any of its obligations (other than payment obligations) under this DBOM Agreement; (2) A breach of any representation or warranty made by the DBOM Contractor under this DBOM Agreement; (3) Willful misconduct of the DBOM Contractor or any DBOM Contractor Person; or (4) A negligent act or omission of the DBOM Contractor or a DBOM Contractor Person. "DBOM Contractor Hazardous Substances" means the presence of Hazardous Substances in, on or under the Project Site (including presence in air, surface water, groundwater, soils or subsurface strata) which is introduced to the Project Site by and caused 8 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation by or attributable to any acts or omissions of the DBOM Contractor or any DBOM Contractor Person. "DBOM Contractor Managed Governmental Approvals" means those Governmental Approvals for which the DBOM Contractor is the application manager and is responsible for obtaining as designated in Appendix 2 (Governmental Approvals). "DBOM Contractor Person" means: (1) Any director, officer, employee or agent of the DBOM Contractor in each case acting as such; or (2) Any Subcontractor and any representative, advisor (including any legal and financial advisor) of the DBOM Contractor, in any such person's capacity as a provider of services directly or indirectly to the DBOM Contractor in connection with the Project. "DBOM Contractor Remediable Breach" has the meaning set forth in subsection 21.1(B) (DBOM Contractor Remediable Breach Defined). "DBOM Contractor Representative" means the individual specified in writing by the DBOM Contractor as the representative of the DBOM Contractor from time to time for all purposes of this DBOM Agreement. "DBOM Contractor Required Insurance" means the Required Insurance to be obtained by the DBOM Contractor, as specified in Appendix 12 (Insurance Requirements). "Deductions" means those deductions from the otherwise applicable Service Fee that the City is explicitly permitted to take pursuant to this DBOM Agreement as offsets on account of any failure to meet any Performance Guarantee. "Deductions Credit" has the meaning set forth in Section 17.6 (Deductions Credit). "Deliverable Material" has the meaning set forth in subsection 5.1(H) (Deliverable Material). "Design and Construction Requirement Change"means a change in the Design and Construction Requirements made by a Change Order: (1) As a result of a DBOM Contractor request agreed to by the City pursuant to Section 5.11 (Design and Construction Requirement Changes Made at DBOM Contractor Request); (2) On account of Relief Events pursuant to Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date); or (3) At the direction of the City pursuant to Section 5.13 (Design and Construction Requirement Changes Made at City Direction). "Design and Construction Requirements" means the requirements for the design, construction and performance of the Project as set forth in Appendix 4 (Design and Construction Requirements) (as may be modified from time to time in accordance with the 9 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DI3()IVI Agreement Definitions and Interpretation provisions of Article 5 (Design and Construction)), Appendix 6 (Design-Build Work Review Procedures), Appendix 7 (General Design-Build Work Requirements) and Appendix 8 (Commissioning and Acceptance Testing), and as construed in accordance with the provisions of subsection 1.2(T) (Applicability, Stringency and Consistency of Contract Standards). "Design-Build Governmental Approvals" means all Governmental Approvals required from time to time during the Design-Build Period for the commencement and continuance of the Design-Build Work. "Design-Build Period" means the period from and including the Effective Date through the Acceptance Date. "Design-Build Plans" means the Communication Plan as described in Appendix 20 (Public Communications), the Emergency Response Plan as described in Appendix 7 (General Design-Build Work Requirements) as well as the Commissioning Plan, the Acceptance Test Plan, the Design-Build Quality Management Plan, the Health and Safety Plan, the Equity, Inclusion and Diversity Subcontracting Plan (to the extent required by the City's WIFIA loan agreement) and any other plans required to be provided by the DBOM Contractor relating to Design-Build Work. "Design-Build Price" means the sum of the Fixed Design-Build Price and the Fixed Design-Build Price Adjustments. "Design-Build Price Maximum Drawdown Schedule" means the schedule of maximum monthly payments of the Design-Build Price attached as Attachment 9B (Design-Build Price Maximum Drawdown Schedule) to Appendix 9 (Design-Build Work Schedule of Values and Maximum Drawdown Schedule). "Design-Build Price Schedule of Values" means the schedule of values attached as Attachment 9A (Design-Build Price Schedule of Values) to Appendix 9 (Design-Build Work Schedule of Values and Maximum Drawdown Schedule). "Design-Build Project Manager" has the meaning set forth in subsection 4.2(B) (Design-Build Project Manager). "Design-Build Quality Management Plan" means the DBOM Contractor's plan for quality assurance and quality control in implementing the Design-Build Work set forth in Appendix 22 (Design-Build Quality Management Plan). "Design-Build Work" means everything required to be furnished and done for and relating to the design, construction, commissioning and acceptance of the Project Facilities by the DBOM Contractor pursuant to this DBOM Agreement during the Design-Build Period. "Design-Build Work Notice to Proceed" has the meaning set forth in subsection 5.1(A) (Commencement and Prosecution of Design-Build Work). "Design-Build Work NTP Date" means the date on which the Design-Build Work Notice to Proceed is issued by the City in accordance with subsection 5.1(A) (Commencement and Prosecution of Design-Build Work). "Design Documents" means the DBOM Contractor's plans, drawings, shop drawings, record drawings, specifications, sketches, graphic representations, calculations, electronic files and other design documents prepared in connection with the Design-Build Work. 10 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation "Differing Site Conditions" means (a) actual subsurface or latent physical subsurface conditions at the Project Site that differ materially from those indicated in the Reference Documents, or (b) unknown physical subsurface conditions at the Project Site of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character required herein; provided, however, that the term "Differing Site Conditions" excludes conditions of which the DBOM Contractor had actual or constructive knowledge as of the Contract Date (including by review of the Reference Documents as well as conditions that should have been reasonably evident from the location, topography and nature of the Project Site). "Discriminatory Change in Tax Law" means a Change in Law Event which results in the imposition of Taxes or a change in Taxes and which specifically applies to discriminate against: (1) The Project or the DBOM Contractor with respect to the Project and not other projects or persons; or (2) Other similar projects delivered through design-build-operate or performance-based infrastructure delivery methods, or another delivery method similar to them and not other projects. "Dispute" means any disagreement, failure to agree or other dispute between the City and the DBOM Contractor arising out of or in connection with this DBOM Agreement, including in respect of the interpretation, breach, performance, validity or termination of this DBOM Agreement, whether in the law of contract or any other area of law. "Dispute Resolution Procedure" means the Dispute resolution procedures set forth in Article 19 (Dispute Resolution); "Effective Date"means the date this DBOM Agreement is executed and delivered by the parties hereto. "Effluent" means all treated wastewater discharged from the Project Facilities. "Effluent Guarantee" has the meaning set forth in subsection 9.2(A) (Generally). "Encumbrance" means any Lien, lease, mortgage, security interest, claim, charge, judgment, judicial award, attachment or encumbrance of any kind with respect to the Project. "Exit Test Procedures and Standards" means the test procedures and standards regarding the Project to be conducted by the DBOM Contractor prior to the Termination Date, as set forth in Appendix 16 (Exit Testing). "Extended Relief Event" has the meaning set forth in Section 16.4 (Termination for Extended Relief Events). "Extraordinary Item" has the meaning set forth in Section 17.7 (Extraordinary Items). "Fees and Costs" means reasonable fees and expenses of employees, attorneys, architects, engineers, expert witnesses, contractors, consultants and other persons, and costs of transcripts, printing of briefs and records on appeal, copying and other reimbursed expenses, 11 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation and expenses reasonably incurred in connection with investigating, preparing for, defending or otherwise appropriately responding to any Legal Proceeding. "Final Completion" means completion of the Design-Build Work in compliance with the Design and Construction Requirements and satisfaction of the requirements of subsection 6.8(A) (Requirements). "Fitch" means Fitch Ratings, Inc., or any of its successors and assigns. If such corporation is dissolved or liquidated or no longer performs the functions of a securities rating agency, "Fitch" shall be deemed to refer to any other nationally-recognized securities rating agency designated by the City. "Fixed Design-Build Price" has the meaning specified in subsection 7.3(A) (Fixed Design-Build Price). "Fixed Design-Build Price Adjustments" has the meaning specified in subsection 7.3(B) (Fixed Design-Build Price Adjustments). "Force Majeure Event" means the occurrence of: (1) Landslides, underground movement, earthquakes, tidal waves, fires, tornadoes, hurricanes, floods, windstorm, hail and lightning; (2) Certified acts of terrorism as defined by the Terrorism Risk Insurance Act (TRIA) occurring during any period in which TRIA or a substantially identical federal law is in effect; (3) Pressure waves caused by aircraft or other aerial devices traveling at supersonic speeds; (4) Unusually severe and abnormal climactic conditions (as compared with the most recent rolling ten-year average weather statistics compiled by the United States National Oceanic and Atmospheric Administration for the time of year and locality of the Project Site) and other acts of God not described in item (1) above; (5) Terrorism arising from nuclear, biological or chemical materials, or any act which would constitute a certified act of terrorism (as defined by the Terrorism Risk Insurance Act) occurring during any period in which TRIA or a substantially identical federal law is not in effect; (6) War, civil war, armed conflict, riot, insurrection, civil commotion or disturbance (including armed violence and hostage taking), blockades, embargoes, sabotage and related causes; (7) Nuclear explosion or nuclear, radioactive, chemical or biological contamination; or (8) Epidemics, pandemics or quarantine, or health orders issued by a Governmental Body relating thereto (other than COVID-19, except to the extent conditions relating to COVID-19 materially deteriorate from the conditions that existed on the Effective Date); the response to which, in accordance with the Contract Standards, materially expands the scope or materially interferes with, delays, or increases the cost of performing the Project Services, 12 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation except to the extent that such event or circumstance arises from or is contributed to, directly or indirectly, by any DBOM Contractor Fault. "GAAP"means generally accepted accounting principles in effect and consistently applied in the United States (including the accounting recommendations published in the Handbook of the American Institute of Certified Public Accountants). "Good Design-Build Practice" means those methods, techniques, standards and practices which, at the time they are to be employed and in light of the circumstances known or reasonably believed to exist at such time, are generally recognized and accepted as good practice in the delivery of wastewater plants serving purposes similar to the Project on a design-build basis as observed in the State, as such practices exist as of the Effective Date and, only in circumstances described in Section 4.8 (Good Design-Build Practice and Good Operation and Maintenance Practice), as such practices evolve over the Term. "Good Operation and Maintenance Practice" means the methods, techniques, standards and practices which, at the time they are to be employed and in light of the circumstances known or reasonably believed to exist at such time, are generally recognized and accepted as good operation, maintenance, repair, replacement and management practices for wastewater plants serving purposes similar to the Project as observed in the State, as such practices exist as of the Effective Date and as such practices evolve over the Term, except in circumstances described in Section 4.8 (Good Design-Build Practice and Good Operation and Maintenance Practice). "Governmental Approvals" means all permits, licenses, authorizations, consents, certifications, exemptions, rulings, entitlements and approvals issued by a Governmental Body of whatever kind and however described which are required under Applicable Law to be obtained or maintained by any person with respect to the Project Services. "Governmental Body" means any federal, State, regional or local legislative, executive, judicial or other governmental board, department, agency, authority, commission, administration, court or other body (including the City and its Development Review Commission, acting in its governmental capacity other than as a party to this DBOM Agreement), or any official thereof, having jurisdiction in any way over or in respect of any aspect of the performance of this DBOM Agreement or the Project. "Grit and Screenings" means grit and screenings generated at the Wastewater Treatment Facility other than Sludge and Scum. "Guaranteed Maximum Electricity Consumption" has the meaning set forth in subsection 9.4(A) (Guaranteed Maximum Electricity Consumption Calculation). "Hazardous Substance" means any hazardous waste, hazardous product, contaminant, toxic substance, deleterious substance, dangerous goods, pollutant, waste, reportable substance, and any other substance, in respect of which the storage, manufacture, handling, disposal, treatment, generation,use, transport, remediation or release into or presence in the environment is prohibited, controlled or regulated under Applicable Law pertaining to the environment, including "hazardous substances" as defined under CERCLA and "hazardous waste" as defined under RCRA. "Health and Safety Plan" has the meaning set forth in subsection 5.14(B) (Safety and Security). 13 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "Income Tax" means any Tax imposed on the income or gross or net receipts (including the Oregon Corporate Activity Tax established in ORS Chapter 317A) of a person by any federal, State or local Governmental Body. "Index-Linked" means, with respect to an amount expressly identified as being subject to adjustment, that the amount is adjusted as of each July 1 commencing July 1, 2027, by multiplying it by the amount determined as follows: Index-LinkedN = (0.572 x (ECI-TCN/ECI-TCN_1) + 0.316 x (PPI-GPMEN/PPI-GPMEN_1) + 0.054 x (PPI-ICN/PPI-ICN_1) + 0.044 x (PPI-WCN/PPI-WCN_1) + 0.014 x (PPI-T1'LN/PPI-TTLN_ 1) + 0.01632) x Index-LinkedN_1 Where N =The period from the immediately preceding June to the previous June (except that for the initial July 1, 2027 adjustment, it will be for June 2027 to December 2025). N-1 = The same annual period one year earlier. ECI-TC = Employment Cost Index (ECI), total compensation for private industry workers in the utilities industry, for the 2nd quarter of the calendar year, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: CIU2014400000000I. PPI-GPME = Producer Price Index (PPI), general purpose machinery and equipment, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: WPS 114. PPI-IC = Producer Price Index (PPI), industrial chemicals, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: WPU061. PPI-WC = Producer Price Index (PPI), solid waste collection, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: PCU562111562111. PPI-TTL = Producer Price Index (PPI), truck, truck trailer and RV leasing, as reported by the Bureau of Labor Statistics of the US Department of Labor in the CPI Detailed Report Series ID: WPU442102. If any such index in its present form becomes unavailable, such index shall be replaced by a similar index as may be agreed to by the parties, acting reasonably. "Influent" means all flows reaching the Wastewater Treatment Facility through the City's wastewater collection and conveyance system. "Initial Renewal Term" has the meaning set forth in subsection 3.1(B) (Renewal Term). "Initial Term" has the meaning set forth in subsection 3.1(A) (Initial Term). "Insurable Force Majeure Event" means the occurrence of any of the events or circumstances set forth in items (1), (2) or (3) of the definition of Force Majeure Event. 14 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "Insurance Proceeds" means the amounts received by a person in respect of a claim made under any policy of insurance required to be maintained under this DBOM Agreement. "Insurance Receivables" means Insurance Proceeds which a person is entitled to receive but which have not yet been received. "Insurance Requirement" means any rule, regulation, code, or requirement issued by any insurer that has issued a policy of Required Insurance under this DBOM Agreement, as in effect during the Term, compliance with which is a condition to the effectiveness of such policy. "Insurance Unavailability Event" has the meaning set forth in subsection 15.6(A) (Insurance Unavailability Event). "Intellectual Property" means any or all of the following and all rights, arising out of or associated therewith: (1) National, international and foreign patents, and applications therefor and all reissues, divisions, renewals, extensions, provisionals, continuations and continuations-in-part thereof; (2) Inventions (whether patentable or not), invention disclosures, improvements, trade secrets, proprietary information, know-how, technology, technical data and customer lists, product formulations and specifications, and all documentation relating to any of the foregoing throughout the world; (3) Copyrights, copyright registrations and applications therefor, and all other rights corresponding thereto throughout the world; (4) Industrial designs and any registrations and applications therefor throughout the world; (5) Rights in any internet uniform resource locators (URLs), domain names, trade names, logos, slogans, designs, common law trademarks and service marks, trademark and service mark registrations and applications therefor throughout the world; (6) Databases and data collections and all rights therein throughout the world; (7) Moral and economic rights of authors and inventors, however denominated, throughout the world; and (8) Any similar or equivalent rights to any of the foregoing anywhere in the world. "Key Individuals" has the meaning set forth in Appendix 19 (DBOM Contractor and Subcontractors Information). "Legal Proceeding" means every action, suit, litigation, arbitration, administrative proceeding, and other legal or equitable proceeding having a bearing upon this DBOM Agreement, and all appeals therefrom. 15 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()10 Agreement I)efinitions and Interpretation "Lien" means any and every lien against the Project or against any monies due or to become due from the City to the DBOM Contractor under this DBOM Agreement, for or on account of the Project Services, including mechanics', materialmen's, laborers'and lenders'liens. "Liquidated Damages Right" has the meaning set forth in subsection 20.2(A) (City Liquidated Damages Rights Defined). "Longstop Date" has the meaning set forth in Section 6.5 (Scheduled Acceptance Date and Longstop Date). "Loss-and-Expense" means, and is limited to, any and all actual loss, liability, forfeiture, obligation, damage, fine, penalty,judgment, deposit, charge, assessment, Tax, cost or expense relating to third-party claims for which the DBOM Contractor is obligated to indemnify the City hereunder, including all Fees and Costs. "Major Maintenance, Repair and Replacement" means any renewal, repair or replacement of the machinery, equipment, structures or improvements constituting a part of the Project and included in the Major Maintenance, Repair and Replacement Schedule. "Major Maintenance, Repair and Replacement Schedule" has the meaning set forth in subsection 10.2(A) (Major Maintenance, Repair and Replacement Schedule). "Material Adverse Change" has the meaning specified in subsection 18.1(C) (Material Adverse Change to the Financial Condition of the Parent Company Guarantor). "Material Contract" means (1) any agreement between the DBOM Contractor and an Affiliate of the DBOM Contractor related to the services to be performed under this DBOM Agreement, (2) a Subcontract for Design-Build Work in excess of $5,000,0000, or (3) a Subcontract for Operation and Maintenance Services that is exclusively for the Project in excess of 10% of the Operation and Maintenance Charge. "Mediator" means any person serving as a mediator of disputes hereunder pursuant to Section 19.2 (Non-Binding Mediation Generally). "Monthly Progress Report" has the meaning specified in subsection 5.1(D) (Project Sequencing, Schedule and Reports). "Moody's" means Moody's Investors Service, Inc. or any of its successors and assigns. If such corporation shall be dissolved or liquidated or shall no longer perform the functions of a securities rating agency, "Moody's"shall be deemed to refer to any other nationally- recognized securities rating agency designated by the City. "MRR Account" has the meaning set forth in subsection 17.5(D) (MRR Account). "Non-Binding Mediation" means the voluntary system of dispute resolution established by Section 19.2 (Non-Binding Mediation Generally) for addressing disputes arising under this DBOM Agreement. "Noncompliant Influent" means (1) Influent containing Toxic Substances or a Hazardous Substance, or (2) Influent in excess of those values set forth in Section 2 (Influent Flows and Loadings) of Appendix 4 (Design and Construction Requirements). 16 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "NPDES Permit" means the National Pollutant Discharge Elimination System Governmental Approval issued by ODEQ for the Project including any renewals, revisions, modifications or amendments thereto. "ODEQ" means the Oregon Department of Environmental Quality. "Odor Citation" has the meaning specified in subsection 9.3(G) (Citations for Odor Incidents). "Odor Guarantee" has the meaning specified in subsection 9.3(B) (Contract Limits). "Odor Incident" has the meaning specified in subsection 9.3(E) (Odor Incident). "Operation and Maintenance Charge" has the meaning set forth in Section 17.3 (Operation and Maintenance Charge). "Operation and Maintenance Letter of Credit" has the meaning set forth in Section 18.3 (Operation and Maintenance Letter of Credit). "Operation and Maintenance Manual" means the manual and related computer programs prepared by the DBOM Contractor containing detailed standard operating and maintenance procedures and other specific instructions, policies, directives, routines, schedules and other matters relating to the Operation and Maintenance Services, developed and maintained in accordance with Section 8.3 (Operation and Maintenance Manual and Operation and Maintenance Plan). "Operation and Maintenance Notice" means a notice given by one party to the other hereunder relating to routine operational matters arising under this DBOM Agreement following the Acceptance Date specifically required hereunder to be given as an "Operation and Maintenance Notice". "Operation and Maintenance Period" means the period between the Acceptance Date and the Termination Date. "Operation and Maintenance Plan" means the plan to be prepared by the DBOM Contractor in accordance with Appendix 10 (Operation and Maintenance Requirements) and approved by the City that documents all protocols, procedures and systems the DBOM Contractor will implement in order to operate and maintain the Project Facilities in accordance with this DBOM Agreement. "Operation and Maintenance Requirements" means the requirements for operation and maintenance of the Project Facilities, as set forth in this DBOM Agreement, including Appendix 10 (Operation and Maintenance Requirements), Appendix 11 (Odor Control Standard and Odor Control Plan), Appendix 13 (Performance Guarantees and Deductions) and the final Operation and Maintenance Plan and final Operation and Maintenance Manual. "Operation and Maintenance Services" means everything required to be furnished and done for and relating to the operation and maintenance of the Project Facilities by the DBOM Contractor pursuant to this DBOM Agreement during the Operation and Maintenance Period. "Operation and Maintenance Services Change" means a change, including an addition, deletion, alteration, substitution or modification, to the DBOM Contractor's Operation 17 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efiniticais and Interpretation and Maintenance Services obligations under this DBOM Agreement, made pursuant to Section 11.8 (Operation and Maintenance Services Changes). "Operation and Maintenance Services Change Certificate" means a certificate issued by the City describing and authorizing an Operation and Maintenance Services Change, the value or method of valuation of the Operation and Maintenance Services Change, and the adjustment, if any, to the Service Fee associated with the Operation and Maintenance Services Change. "Operation and Maintenance Services Change Report" has the meaning set forth in subsection 11.8(B) (DBOM Contractor Operation and Maintenance Services Change Report). "Operation and Maintenance Supervisor" has the meaning set forth in subsection 4.3(B) (Operation and Maintenance Supervisor). "Other Relief Event" means the occurrence of any of the following events or circumstances: (1) A defect, flaw, error, inoperability, inadequacy or other condition or aspect of the design or condition of the TCWTP Outfall, as and to the extent provided in subsection 4.6(B) (Condition of the TCWTP Outfall); (2) Delay in the issuance of the Design-Build Work Notice to Proceed, as and to the extent provided in subsection 5.1(A) (Commencement and Prosecution of Design- Build Work); (3) The existence of a Differing Site Condition, as and to the extent provided in subsection Section 5.4(D) (Relief for Differing Site Conditions); (4) The existence of a Regulated Site Condition, as and to the extent provided in Section 5.5 (Regulated Site Conditions); (5) A delay by a Governmental Body in issuing a Governmental Approval required for the performance of the Design-Build Work and satisfaction of all Acceptance Conditions, as and to the extent provided in subsection 5.6(D) (Relief for Delays in the Issuance of DBOM Contractor Managed Governmental Approvals Caused by Governmental Bodies) and/or subsection 5.6(G) (Relief for Delays in the Issuance of City Managed Governmental Approvals Caused by Governmental Bodies); (6) The imposition of any unanticipated term or condition contained in the NPDES Permit, as and to the extent set forth in subsection 5.6(E) (Exception to DBOM Contractor Assumption of Permitting Risk with Respect to the NPDES Permit); (7) Compliance by the DBOM Contractor, pursuant to subsection 8.12(B) (Emergency Action) or otherwise, with an order or direction by police, fire officials or any comparable public authority having the legal authority to make such order or give such direction; (8) The failure of the Columbia Boulevard Wastewater Treatment Facility to accept Sludge and Scum meeting the requirements set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements), as and to the extent provided in subsection 9.6(D) (Sludge and Scum Transportation and Off-Loading); 18 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation (9) The receipt of Noncompliant Influent or the occurrence of an Upset at the Project Facilities, each to the extent provided in Section 9.7 (Upsets and Noncompliant Influent Affecting DBOM Contractor Compliance with Performance Guarantees); (10) An official or unofficial strike, lockout, work rule or other labor dispute by: (a) public sector employees, or (b) private sector employees (other than employees of the DBOM Contractor or a Subcontractor) (i) which (x) is regional or national in nature and affects the construction or wastewater treatment industry generally or (y) takes place at a facility manufacturing materials or equipment for the Project and is not directed at the Project, and (ii) which event lasts for more than 10 days; (10) Any Encumbrance, or any placement or enforcement of any Encumbrance, including any Encumbrance placed on record after the date of the Effective Date on the Project Site or the Project Facilities that materially adversely impacts the party, not consented to in writing by, or arising out of any action or agreement entered into by, the party adversely affected thereby; (11) The preemption, confiscation, diversion, destruction or other interference in possession or performance of materials or services by a Governmental Body in connection with any condemnation or other taking by eminent domain of any material portion of the Project; (12) The failure (including delays)of any Governmental Body or Utility company having operational jurisdiction in the area in which the Project is located to provide and maintain Utilities to the Project that are required to perform this DBOM Agreement; (13) Physical damage to the Project by a City Indemnitee; (14) Physical damage to the Project by Portland to the extent such damage occurred as a result of Portland's access to the Project pursuant to Section 8.9 (City and Portland Access to the Project) or any unreasonable act of prevention, hindrance, obstruction, or other unreasonable non-cooperation by Portland in its capacity as owner of TCWTP prior to transfer of TCWTP to the City; (15) The demolition and remediation of TCWTP by the City, or any third-party, but solely as it relates to the DBOM Contractor's ability to comply with the Odor Guarantee; (16) Any act of prevention, hindrance, obstruction, or other non-cooperation by a third party or the City or any defect or non-compliance with Applicable Law or the Contract Standards, in carrying out a Capital Modification, as contemplated by Section 11.7 (Alternative Procedures for Implementing Capital Modifications); (17) Any other event that, under a specific provision of this DBOM Agreement, expressly constitutes an Other Relief Event or expressly provides for price or schedule relief, including: (a) the requirement that the Project comply with the Build America Buy America Act in connection with any WIFIA loan obtained by the City as part of its financing structure for the Project as provided in subsection 4.5(G) (Water Infrastructure Finance and Innovation Act (WIFIA)); 19 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation (b) events referred to in Section 4.7 (Restrictions on City-Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes); (c) a direction by the City to comply with revised professional and technical standards as provided in subsection 5.1(G) (Technical Standards and Codes); or (d) a delay caused by City-directed testing, inspections and uncovering as provided in subsection 5.15(E) (Notice of Covering Design-Build Work); (18) The release of any Influent-based Hazardous Substances, other than DBOM Contractor Hazardous Substances, on or into the Project Site at any time after the date of the Final Price Submittal which must be removed; (19) Any Hazardous Substances found in Residuals, as and to the extent provided in subsection 9.6(H) (Hazardous Substances); (20) Cyber-attacks from persons or entities other than employees of the DBOM Contractor or its Affiliates; and (21) A City Fault; the response to which or compliance with which, in accordance with the Contract Standards, materially expands the scope or materially interferes with, delays, or increases the cost of performing the Project Services, except to the extent such event or circumstance arises from or is contributed to, directly or indirectly, by any DBOM Contractor Fault. "Overdue Rate" has the meaning set forth in Section 26.8 (Interest on Overdue Amounts). "P&P Bonds" has the meaning set forth in Section 18.2 (Payment and Performance Bonds). "Parent Company Guarantor" means Jacobs Engineering Group Inc., a corporation organized and existing under the laws of the State of Delaware, and its successors and assigns permitted under the Parent Company Guaranty Agreement. "Parent Company Guaranty Agreement" or "Parent Company Guaranty" means the guaranty agreement entered into concurrently with this DBOM Agreement from the Parent Company Guarantor to the City in the form set forth in Transaction Form A (Parent Company Guaranty Agreement), as the same may be amended from time to time in accordance therewith. "Performance Guarantees" means the guarantees of performance made by the DBOM Contractor specifically set forth in Article 9 (Performance), including any administrative sanctions described therein and in Appendix 13 (Performance Guarantees and Deductions). "Permitted Encumbrances" means, as of any particular time, any one or more of the following: (1) Encumbrances for Utility charges, taxes, rates and assessments not yet delinquent or, if delinquent, the validity of which is being contested diligently and in good 20 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation faith by the DBOM Contractor and against which the DBOM Contractor has established appropriate reserves in accordance with GAAP; (2) Any encumbrance arising out of any judgment rendered which is being contested diligently and in good faith by the DBOM Contractor, the execution of which has been stayed or against which a bond or bonds in the aggregate principal amount equal to such judgments shall have been posted with a financially-sound insurer and which does not have a material and adverse effect on the ability of the DBOM Contractor to construct the Project or operate the Project; (3) Any encumbrance arising in the ordinary course of business imposed by law dealing with materialmen's, mechanics', workmen's, repairmen's, warehousemen's, landlords', vendors' or carriers' encumbrances created by law, or deposits or pledges which are not yet due or, if due, the validity of which is being contested diligently and in good faith by the DBOM Contractor and against which the DBOM Contractor has established appropriate reserves; (4) Servitudes, licenses, easements, encumbrances, restrictions, rights-of- way and rights in the nature of easements or similar charges which shall not in the aggregate materially and adversely impair the construction of the Project or operation of the Project by the DBOM Contractor; (5) Applicable zoning and building bylaws and ordinances, municipal bylaws and regulations, and restrictive covenants, which do not materially interfere with the construction of the Project and operation of the Project by the DBOM Contractor; (6) Encumbrances which are created on or before the Effective Date; (7) Encumbrances which are created by a Change in Law Event on or after the Effective Date; (8) Any encumbrance created by an act or omission by any Governmental Body or with respect to which the City has given its consent; and (9) Any servitudes, licenses, easements, restrictions, rights-of-way, rights and encumbrances specifically identified in Appendix 1 (Site-Related Information). "Portland" means the City of Portland, Oregon. "Project" means the Project Facilities, the TCWTP Outfall and the Project Site, and includes the performance of the Project Services with respect thereto. "Project Equipment" means all manufactured equipment, systems, property or assets, whether or not constituting personal property or fixtures, constituting part of the Project. "Project Facilities"means (1)the new Wastewater Treatment Facility and related structures and equipment to be constructed, operated and maintained by the DBOM Contractor on the Project Site pursuant to this DBOM Agreement, including all Utility connections, roads, parking lots, landscaping and other Project Site improvements connected to or related to the new Wastewater Treatment Facility and related structures, (2) the influent conveyance system from the City's collection system to the Wastewater Treatment Facility, and (3) the effluent conveyance system from the Wastewater Treatment Facility to the TCWTP Outfall; as shown in Attachment 1A (Design-Build Project Site Plan) of Appendix 1 (Site-Related Information) during the Design- 21 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3010 Agreement I)efinitions and Interpretation Build Period and in Attachment 1B (Operations and Maintenance Project Site Plan) of Appendix 1 (Site-Related Information) during the Operations and Maintenance Period. "Project Intellectual Property"means the Intellectual Property which is created, brought into existence, acquired, licensed or used by the DBOM Contractor, any Subcontractor or any other third party, directly or indirectly, for the purposes of the Project Services. "Project Schedule" has the meaning set forth in Appendix 7 (Design-Build Work Review Procedures). "Project Services" means the Design-Build Work and the Operation and Maintenance Services. "Project Site" means the real property described in Appendix 1 (Site-Related Information) on which the Project Facilities are to be constructed by the DBOM Contractor. "Project Structures" means all structures, buildings, roofing systems, concrete tanks and metal tanks, tank covers and above- and below-ground pipes constituting part of the Project other than Project Equipment. "Punch List" has the meaning set forth in subsection 6.4(A) (Punch List). "Punch List Items" means any defects, deficiencies and items of outstanding work that would not materially impair the performance of the Operation and Maintenance Services and could be rectified with minimal interference to the occupancy, use and lawful operation of the Project. "Qualified Commercial Bank" means a reputable domestic or foreign commercial bank: (1) That has a minimum capital surplus of at least $1,000,000,000; (2) Whose long-term debt has at least two of the following ratings: "A3/A" or higher by Moody's, "A" or higher by Standard & Poor's, and "A" or higher by Fitch; and (3) Which maintains a banking office, branch or agency in the United States. "Qualified Insurer" means an insurer that: (1) Is allowed legally to do business in the State and acceptable to the City, acting reasonably; and (2) Has a Best's Financial Strength Rating of"A-" or better, and a Financial Size Category of"Class VII" or better in the latest evaluation of A.M. Best Company, Inc., or a comparable rating from any other nationally-recognized rating agency, unless the City grants specific approval for an exception. "Qualified Residuals Disposal Facility" means a lawful land application site, a sewage sludge incinerator, a sanitary landfill or other lawfully authorized disposal facility for non-hazardous waste which: (1) does not appear on any federal or state list of sites, including the National Priority List or the CERCLIS list under CERCLA, which list is maintained for the purpose of designating landfills or other sites which are reasonably expected to require remediation on account of the release or threat of release of Hazardous Substances; (2) is being operated at the time of disposal in accordance with Applicable Law, as evidenced by the absence 22 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation of any regulatory sanctions or any significant enforcement actions with respect to material environmental matters; (3) if the disposal site is a landfill, has fully funded, bonded or otherwise secured legally required reserves for closure and remediation according to available information; (4) does not otherwise unreasonably expose the City to any material risk as a "generator" or "transporter" of waste under CERCLA or any similar law, or to any material risk under product liability, tort, environmental impairment or any similar law, notwithstanding the indemnities provided by the DBOM Contractor hereunder; (5) has committed by written agreement of the owner or operator to receive Residuals originating at the Project Facilities; and (6) is located in the United States. "Rating Agencies" means Moody's, Standard & Poor's and Fitch, as applicable. "RCRA" means the Resource Conservation and Recovery Act, 42 U.S.C.A. 6901 et seq., and applicable regulations promulgated thereunder, each as amended from time to time. "Reference Documents" means those documents listed as Reference Documents in Appendix 17 (Reference Documents). "Regulated Site Condition" means, and is limited to, (1) Surface or subsurface structures, materials, properties or conditions having historical, cultural, archaeological, religious or similar significance; (2) Any wetlands or habitat of an endangered or protected species as provided in Applicable Law; (3) The presence anywhere in, on or under the Project Site on the Effective Date of wells or underground storage tanks for the storage of Hazardous Substances; and (4) The presence of Hazardous Substances (other than DBOM Contractor Hazardous Substances) in, on or under the Project Site (including presence in air, surface water, groundwater, soils or subsurface strata). "Reimbursable Costs Charge" has the meaning set forth in Section 17.4 (Reimbursable Costs Charge). "Reinstatement Plan" has the meaning set forth in subsection 15.3(C) (Reinstatement Plan). "Reinstatement Works" has the meaning set forth in subsection 15.3(A) (Draft Reinstatement Plan). "Relief Event" means: (1) An Insurable Force Majeure Event; (2) An Uninsurable Force Majeure Event; (3) A Change in Law Event; or (4) An Other Relief Event. "Renewal Term" has the meaning set forth in subsection 3.1(B) (Renewal Term). 23 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation "Required Design-Build Period Insurance" means the insurance required to be maintained by the DBOM Contractor during the Design-Build Period as specified in Section 2 (Insurance During the Design-Build Period) of Appendix 12 (Insurance Requirements). "Required Insurance" means the Required Design-Build Period Insurance and the Required Operation and Maintenance Period Insurance to be provided by the DBOM Contractor. "Required Operation and Maintenance Period Insurance" means the insurance required to be maintained by the DBOM Contractor during the Operation and Maintenance Period as specified in Section 3 (Insurance During the Operation and Maintenance Period) of Appendix 12 (Insurance Requirements). "Requisition" means a written requisition submitted by the Design-Builder requesting payment of the Design-Build Price hereunder in the form approved by the City, together with such supporting documentation as required by Section 7.5 (Payment Procedure). "Residuals" means (1) Sludge and Scum and (2) Grit and Screenings. "Residuals Management Guarantee" has the meaning set forth in subsection 9.6(A) (General Obligations). "Restricted Person"means any person who (or any member of a group of persons acting together, any one of which): (1) Is debarred, suspended, or otherwise disqualified from federal, State, or City contracting for any services similar in nature to the Design-Build Work or the Operation and Maintenance Services; (2) Was or is subject to any material claim of the United States, State, or City in any proceedings (including regulatory proceedings) which have been concluded or are pending at the time at which the determination of whether the person falls within this definition is being made, and which (in respect of any such pending claim, if it were to be successful) would, in the City's view, in either case, be reasonably likely to materially affect the ability of the DBOM Contractor to perform its obligations under this DBOM Agreement; (3) In the case of an individual, he or she (or in the case of a legal entity, any of the members of the board of directors or its senior executive managers) has been sentenced to imprisonment or otherwise given a custodial sentence for any criminal offense (other than minor traffic offences or misdemeanors) less than 5 years prior to the date at which the determination of whether the person falls within this definition is being made; (4) Has, directly or indirectly, its principal or controlling office in a country that is subject to any economic or political sanctions imposed by the United States for reasons other than its trade or economic policies; (5) Has as its primary business the illegal manufacture, sale, distribution or promotion of narcotic substances or arms, or is or has been involved in terrorism; or (6) Has as its primary business the acquisition of distressed assets or investments in companies or organizations which are or are believed to be insolvent or in a financial standstill situation or potentially insolvent. 24 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "RFP" means the City's Request for Proposals for the Lake Oswego Wastewater Treatment Facility, issued on July 29, 2025. "Scheduled Acceptance Date" has the meaning set forth in Section 6.5 (Scheduled Acceptance Date and Longstop Date), and includes extensions for Relief Events as provided in subsection 6.5(C) (Extension for Relief Events). "Secondary Technical Criteria" means the design requirements as set forth in Appendix 5 (Secondary Technical Criteria). "Security Instruments" means the P&P Bonds and the Parent Company Guaranty Agreement. "Service Fee" means the fee to be paid by the City to the DBOM Contractor as compensation for the DBOM Contractor's performance of the Operation and Maintenance Services, calculated in accordance with Article 17 (Service Fee and Other Payments). "Sludge and Scum" means any (1) solid, semi-solid or liquid residue, byproduct or other waste streams removed during the treatment of Influent by the Wastewater Treatment Facility and (2) floatable material, including grease; excluding Grit and Screenings. "Small-Scale Capital Modification" means a Capital Modification requested by the DBOM Contractor, and not required as a result of Relief Events or directed by the City, which has a cost of less than $50,000 (Index-Linked) as a single scope of work. "Specified Change in Tax Law" means a Change in Law Event which results in a new Tax imposed by the United States, the State or the City and paid by the DBOM Contractor or any Subcontractors with respect to the performance of the Project Services, including any value added Taxes or sales Taxes. New Taxes shall not include any Taxes based on or measured by net income or gross receipts; any unincorporated business, payroll, franchise or employment Tax; or any Taxes imposed by a foreign government or any of their agencies. "Standard &Poor's" means Standard 8s Poor's Financial Services LLC, a division of The S&P Global Inc., or any of its successors and assigns. If such corporation shall be dissolved or liquidated or shall no longer perform the functions of a securities rating agency, "Standard & Poor's" shall be deemed to refer to any other nationally-recognized securities rating agency designated by the City. "State" means the State of Oregon. "Subcontract" means any contract entered into by the DBOM Contractor or a subcontractor of the DBOM Contractor of any tier, with one or more persons in connection with the carrying out of the DBOM Contractor's obligations under this DBOM Agreement, whether for the furnishing of labor, materials, equipment, supplies, services or otherwise. "Subcontractor" means any person that enters into a Subcontract. "Substantial Completion" has the meaning set forth in Section 5.19 (Substantial Completion). "Sustained Odor Condition" has the meaning specified in subsection 9.3(F) (Sustained Odor Condition). 25 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 DBOM Agreement Definitions and Interpretation "Tax" means, from time to time, all taxes, surtaxes, duties, levies, imposts, rates, payments, assessments, withholdings, dues and other charges of any nature imposed by any Governmental Body, together with all fines, interest, penalties on or in respect of, or in lieu of or for non-collection of, those taxes, surtaxes, duties, levies, imposts, rates, payments, assessments, withholdings, dues and other charges. "TCWTP" means the existing Tryon Creek Wastewater Treatment Plant owned and operated by Portland. "TCWTP Outfall" means the outfall, pipes and equipment currently used for the TCWTP and intended to be used for the Project upon and following Acceptance. "TCWTP Site" means the real property owned by the City of Portland that the TCWTP is built upon as of the Effective Date. "Term" has the meaning set forth in subsection 3.1(A) (Initial Term). "Termination Date" means the last day of the Term resulting from either a termination or expiration under this DBOM Agreement. "Termination for Convenience" has the meaning specified in subsection 23.2(A)(1) (City Termination Rights). "Termination Letter of Credit" has the meaning set forth in subsection 10.3(H) (Termination Letter of Credit). "Termination LOC Amount" has the meaning set forth in subsection 10.3(H) (Termination Letter of Credit). "Terrorism Risk Insurance Act" or"TRIA" means the Terrorism Risk Insurance Act of 2002. "Total Constructive Loss" means the occurrence of damage or destruction to all or substantially all of the Project. "Toxic Substance" means any toxic, hazardous, chemical, industrial, explosive, flammable, volatile, reactive, corrosive or radioactive waste, material or substance which, alone or in combination with other substances, is contained in sufficiently high concentrations or volumes in Influent so as: (1) to cause a material and adverse effect on the operation of the Project and the performance of the Operation and Maintenance Services (including any substance or combination of substances contained in the Influent in a sufficiently high concentration so as to interfere with the biological processes necessary for the removal of the organic and chemical contents of the Influent required to meet the Effluent Guarantee); (2) to endanger human health or safety; or (3) to cause Effluent or Residuals to become a Hazardous Substance, if any such result could not reasonably have been avoided by the management of the Project in accordance with the Contract Standards. "Transaction Form" means any of the Transaction Forms appended to this DBOM Agreement and identified as such in the Table of Contents. 26 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation "Tryon Creek Interceptor" means the interceptor sewer line that collects and transports sewage from parts of Portland to the TCWTP, a portion of which is located on the Project Site. "Uninsurable Force Majeure Event" means the occurrence of any of the events or circumstances set forth in items (4), (5), (6), (7), or (8) of the definition of Force Majeure Event. "Upset" has the meaning given such term in the Clean Water Act (formally referred to as the Federal Water Pollution Control Act), 33 U.S.C. §1251 et seq., and applicable regulations promulgated thereunder, each as amended from time to time. "Utilities" means any and all utility services and installations whatsoever (including gas, water, sewer, electricity, telephone, and telecommunications), and all piping, wiring, conduit, and other fixtures of every kind whatsoever related thereto or used in connection therewith. "Wastewater Treatment Facility"means the new Wastewater Treatment Facility and related structures and equipment to be constructed, operated and maintained by the DBOM Contractor on the Project Site pursuant to this DBOM Agreement, including all Utility connections, roads, parking lots, landscaping and other Project Site improvements connected to or related to the new replacement Wastewater Treatment Facility and related structures. "Willamette Interceptor" means the interceptor sewer line that collects and transports sewage from parts of Portland and Clackamas County to the TCWTP, a portion of which is located on the Project Site. Section 1.2. INTERPRETATION. This DBOM Agreement shall be interpreted according to the following provisions, except to the extent the context or the express provisions of this DBOM Agreement otherwise require. (A) Plurality. Words importing the singular number mean and include the plural number and vice versa. (B) Persons. Words importing persons include individuals, legal personal representatives, firms, companies, associations, joint ventures, general partnerships, limited partnerships, limited liability partnerships, limited liability companies, trusts, business trusts, corporations, governmental bodies, and other legal entities. (C) Headings. The table of contents and any headings preceding the text of the Articles, Sections and subsections of this DBOM Agreement shall be solely for convenience of reference and shall not affect its meaning, construction or effect. (D) References Hereto. The terms "hereby", "hereof', "herein", "hereunder" and any similar terms refer to this DBOM Agreement. (E) References to Days and Time of Day. All references to days herein are references to calendar days, unless otherwise indicated, such as by reference to Business Days. Each reference to time of day is a reference to Pacific Standard time or Pacific Daylight Saving time, as the case may be. Time is of the essence in this DBOM Agreement. 27 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation (F) References to Including. The words "include", "includes" and "including" are to be construed as meaning "include without limitation", "includes without limitation" and "including without limitation", respectively. (G) References to Statutes. Each reference to a statute or statutory provision includes any statute or statutory provision which amends, extends, consolidates or replaces the statute or statutory provision or which has been amended, extended, consolidated or replaced by the statute or statutory provision and includes any orders, regulations, by-laws, ordinances, codes of practice or instruments made under the relevant statute. (H) References to Governmental Bodies. Each reference to a Governmental Body is deemed to include a reference to any successor to such Governmental Body or any organization or legal entity or organizations or entities which has or have taken over the functions or responsibilities of such Governmental Body. (I) References to Business Days. If the time for doing an act falls or expires on a day that is not a Business Day, the time for doing such act shall be extended to the next Business Day. (J) References to Documents and Standards. Each reference to an agreement, document, standard, principle or other instrument includes a reference to that agreement, document, standard, principle or instrument as amended, supplemented, substituted, novated or assigned. (K) References to All Reasonable Efforts. The expression "all reasonable efforts" and expressions of like import, when used in connection with an obligation of either party, means taking in good faith and with due diligence all commercially reasonable steps to achieve the objective and to perform the obligation, including doing all that can reasonably be done in the circumstances taking into account each party's obligations hereunder to mitigate delays and additional costs to the other party, and in any event taking no less steps and efforts than those that would be taken by a commercially reasonable and prudent person in comparable circumstances but where the whole of the benefit of the obligation and where all the results of taking such steps and efforts accrued solely to that person's own benefit. (L) Entire DBOM Agreement. This DBOM Agreement, contains the entire agreement between the parties hereto with respect to the transactions contemplated by this DBOM Agreement. Without limiting the generality of the foregoing, this DBOM Agreement, shall completely and fully supersede all other understandings and agreements among the parties with respect to such transactions. (M) Counterparts and Delivery by Electronic Mail. This DBOM Agreement may be executed in any number of original counterparts. All such counterparts shall constitute but one and the same DBOM Agreement. Any party may deliver an executed copy of this DBOM Agreement by electronic mail and such counterpart shall be deemed effective upon receipt, but that party will promptly deliver via mail or courier to the other parties an originally executed copy of this DBOM Agreement. (N) Governing Law. This DBOM Agreement shall be governed by and construed in accordance with the applicable laws of the State. (O) Severability. Each provision of this DBOM Agreement shall be valid and enforceable to the fullest extent permitted by law. If any provision of this DBOM Agreement is held to be invalid, unenforceable or illegal to any extent, such provision shall be severed and such invalidity, unenforceability or illegality shall not prejudice or affect the validity, enforceability and legality of the remaining provisions of this DBOM Agreement. If any such 28 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation provision of this DBOM Agreement is held to be invalid, unenforceable or illegal, the parties will promptly endeavor in good faith to negotiate new provisions to eliminate such invalidity, unenforceability or illegality and to restore this DBOM Agreement as nearly as possible to its original intent and effect. (P) Drafting Responsibility. The parties waive the application of any rule of law which otherwise would be applicable in connection with the construction of this DBOM Agreement to the effect that ambiguous or conflicting terms or provisions should be construed against the party who (or whose counsel) prepared the executed agreement or any earlier draft of the same. (Q) Interpolation. If any calculation hereunder is to be made by reference to a chart or table of values, and the reference calculation falls between two stated values, the calculation shall be made on the basis of linear interpolation. (R) Accounting and Financial Terms. All accounting and financial terms used herein are, unless otherwise indicated, to be interpreted and applied in accordance with GAAP. (S) Currency in U.S. Dollars. All references to dollar amounts are in United States of America currency. All payments required to be made by either party hereunder shall be made in lawful money of the United States of America. (T) Applicability, Stringency and Consistency of Contract Standards. Where more than one Contract Standard applies to any particular performance obligation of the DBOM Contractor hereunder, each such applicable Contract Standard shall be complied with. In the event there are different levels of stringency among such applicable Contract Standards, the most stringent of the applicable Contract Standards shall govern. Any reference in this DBOM Agreement to materials, equipment, systems or supplies (whether such references are in lists, notes, specifications, schedules, or otherwise) shall be construed to require the DBOM Contractor to furnish the same, at minimum, in accordance with the grades and standards therefor indicated in this DBOM Agreement. (U) Obligations to Provide Assistance. The obligations of a party to cooperate with, to assist or provide assistance to the other party hereunder shall be construed as an obligation to use the party's personnel resources to the extent reasonably available in the context of performance of their normal duties, and not to incur material additional overtime or third- party expense unless requested and reimbursed by the assisted party. Any failure of a party entitled to assistance hereunder to perform an obligation under this DBOM Agreement shall not be excused on account of any failure of the party obligated to provide assistance. (V) Third-Party Rights. This DBOM Agreement is exclusively for the benefit of the City and the DBOM Contractor and shall not provide any third parties (with the sole exceptions of the rights of any third-party City Indemnitees as provided in Section 25.1 (DBOM Contractor's Obligation to Indemnify)) with any remedy, claim, liability, reimbursement, cause of action or other rights. (W) Causing Performance. A party shall itself perform, or shall cause to be performed, subject to any limitations specifically imposed hereby with respect to Subcontractors or otherwise, the obligations affirmatively undertaken by such party under this DBOM Agreement. (X) Defined Terms. The definitions set forth in Section 1.1 (Definitions) shall control in the event of any conflict with any definitions used in the recitals hereto. 29 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 1 I)I3()IVI Agreement I)efinitions and Interpretation (Y) Acting Reasonably and in Good Faith; Discretion. Each party shall act reasonably and in good faith in the exercise of its rights hereunder, except where a party has the right to act in its "discretion" by the express terms hereof. When a party has "discretion", it means that party has the sole, absolute and unfettered discretion, with no requirement to act reasonably or provide reasons unless specifically required under the provisions of this DBOM Agreement. When a party does not have"discretion"it means that the party shall act reasonably. 30 3935946.13 043463 ARTICLE 2 REPRESENTATIONS AND WARRANTIES Section 2.1. REPRESENTATIONS AND WARRANTIES OF THE CITY. The City represents and warrants, as of the Effective Date, that: (A) Existence and Powers. The City is a political subdivision duly organized and existing under and by virtue of the laws of the State and has full legal right, power and authority to execute, deliver and perform its obligations under this DBOM Agreement. (B) Due Authorization. This DBOM Agreement has been duly authorized, executed and delivered by the City, and constitutes a legal, valid and binding obligation of the City, enforceable against the City in accordance with its terms, except to the extent that its enforceability may be limited by bankruptcy, insolvency or other similar laws affecting creditors' rights from time to time in effect and equitable principles of general application. (C) No Conflict. To the best of its knowledge, neither the execution and delivery by the City of this DBOM Agreement nor the performance by the City of its obligations in connection with the transactions contemplated hereby or the fulfillment by the City of the terms or conditions hereof: (1) Conflicts with, violates or results in a breach of any constitution, law or governmental regulation applicable to the City; or (2) Conflicts with, violates or results in a material breach of any term or condition of any order,judgment or decree, or any contract, agreement or instrument, to which the City is a party or by which the City or any of its properties or assets are bound, or constitutes a material default under any of the foregoing. (D) No Approvals Required. No approval, authorization, order or consent of, or declaration, registration or filing with, any Governmental Body or referendum of voters is required for the valid execution and delivery by the City of this DBOM Agreement or the performance by the City of its payment or other obligations hereunder except otherwise as such have been duly obtained or made. (E) No Litigation. Except as disclosed in writing to the DBOM Contractor, to the best of its knowledge, there is no Legal Proceeding before or by any Governmental Body pending or overtly threatened or publicly announced against the City, in which an unfavorable decision, ruling or finding could reasonably be expected to have a material and adverse effect on the execution and delivery of this DBOM Agreement by the City or the validity, legality or enforceability of this DBOM Agreement against the City, or any other agreement or instrument entered into by the City in connection with the transactions contemplated hereby or on the ability of the City to perform its obligations hereunder or under any such other agreement or instrument. Section 2.2. REPRESENTATIONS AND WARRANTIES OF THE DBOM CONTRACTOR. The DBOM Contractor represents and warrants, as of the Effective Date, that: (A) Existence and Powers. The DBOM Contractor is a corporation duly organized, validly existing and in good standing under the laws of the State of Delaware, and has 31 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 2 DBOM Agreement Representations and Warranties the authority to do business in the State and in any other state in which it conducts its activities, with the full legal right, power and authority to enter into and perform its obligations under this DBOM Agreement. (B) Due Authorization and Binding Obligation. This DBOM Agreement has been duly authorized, executed and delivered by all necessary action of the DBOM Contractor and constitutes a legal,valid and binding obligation of the DBOM Contractor, enforceable against the DBOM Contractor in accordance with its terms, except to the extent that its enforceability may be limited by bankruptcy, insolvency or other similar laws affecting creditors' rights from time to time in effect and equitable principles of general application. (C) No Conflict. To the best of its knowledge, neither the execution nor delivery by the DBOM Contractor of this DBOM Agreement nor the performance by the DBOM Contractor of its obligations in connection with the transactions contemplated hereby or the fulfillment by the DBOM Contractor of the terms or conditions hereof: (1) Conflicts with, violates or results in a breach of any constitution, law, governmental regulation, by-laws or certificates of incorporation applicable to the DBOM Contractor; or (2) Conflicts with, violates or results in a material breach of any order, judgment or decree, or any contract, agreement or instrument to which the DBOM Contractor or any of its Affiliates is a party or by which the DBOM Contractor or any of its Affiliates or any of its properties or assets are bound, or constitutes a default under any of the foregoing. (D) No Approvals Required. No approval, authorization, order or consent of, or declaration, registration or filing with, any Governmental Body is required for the valid execution and delivery of this DBOM Agreement or the performance by the DBOM Contractor of its obligations hereunder except as such have been duly obtained or made. (E) No Litigation Affecting the DBOM Contractor. Except as disclosed in writing to the City, to the best of its knowledge, there is no Legal Proceeding, at law or in equity, before or by any court or Governmental Body pending or, to the best of the DBOM Contractor's knowledge, overtly threatened or publicly announced against the DBOM Contractor or any of its Affiliates, in which an unfavorable decision, ruling or finding could reasonably be expected to have a material and adverse effect on the execution and delivery of this DBOM Agreement by the DBOM Contractor or the validity, legality or enforceability of this DBOM Agreement against the DBOM Contractor, or any other agreement or instrument entered into by the DBOM Contractor in connection with the transactions contemplated hereby, or on the ability of the DBOM Contractor to perform its obligations hereunder or under any such other agreement or instrument. (F) No Litigation Affecting the Subcontractors. Except as disclosed in writing to the City, to the best of its knowledge, there is no Legal Proceeding, at law or in equity, before or by any court or Governmental Body pending or, to the best of the DBOM Contractor's knowledge, overtly threatened or publicly announced against any Subcontractor identified in Appendix 19 (DBOM Contractor and Subcontractors Information), in which an unfavorable decision, ruling or finding could reasonably be expected to have a material and adverse effect on the execution and delivery of any Subcontract by the respective Subcontractor or the validity, legality or enforceability of any Subcontract against the Subcontractor that is party to the Subcontract, or on the ability of any such Subcontractor to perform its obligations under its respective Subcontract. 32 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 2 DBOM Agreement Representations and Warranties (G) Intellectual Property. The DBOM Contractor owns, or has express rights to use, all Intellectual Property necessary for design, construction, operation and maintenance of the Project without any known material conflict with the rights of others. (H) Information Supplied by the DBOM Contractor. The information supplied and representations and warranties made by the DBOM Contractor in all submittals made in response to the RFP and in all post-proposal submittals, with respect to the DBOM Contractor (and to the DBOM Contractor's knowledge, all information supplied in such submittals with respect to the Subcontractors and the Parent Company Guarantor) are true, correct and complete in all material respects. (I) DBOM Contractor Reviews. The DBOM Contractor has carefully reviewed the whole of this DBOM Agreement and has taken all steps it considers reasonably necessary to satisfy itself that nothing contained herein inhibits or prevents the DBOM Contractor from performing and completing the Project in accordance with the Contract Standards. (J) Compliance with Applicable Law Generally. The DBOM Contractor is in compliance in all material respects with Applicable Law pertaining to the DBOM Contractor's business and services. In addition and as required by ORS 305.385, the DBOM Contractor, under penalty of perjury, is to the best of its knowledge not in violation of any tax laws identified in ORS 305.380 and ORS 317A.100-317A.161. Section 2.3. CONTINUING ACCURACY OF DBOM CONTRACTOR REPRESENTATIONS AND WARRANTIES. During the Term, the DBOM Contractor shall not take any action, or omit to perform any act, that results in a representation and warranty made in subsection Section 2.2(A) (Existence and Powers), subsection Section 2.2(G) (Intellectual Property), and subsection Section 2.2(J) (Compliance with Applicable Law Generally) becoming untrue. The DBOM Contractor shall promptly notify the City if any such representation and warranty becomes untrue. From time to time, the DBOM Contractor shall provide the City, upon the City's request, with information reasonably requested by the City to substantiate the continuing accuracy of these representations and warranties. 33 3935946.13 043463 ARTICLE 3 TERM Section 3.1. EFFECTIVE DATE AND TERM. (A) Initial Term. This DBOM Agreement shall become effective on the Effective Date, and will continue in effect until the tenth anniversary of the Acceptance Date (the "Initial Term") or, if renewed as provided in subsection (B) (Renewal Term) of this Section, this DBOM Agreement will remain effective until the last day of the Renewal Term (the Initial Term and any Renewal Term being referred to herein as the "Term"). If this DBOM Agreement is earlier terminated by either party in accordance with their respective termination rights under Article 23 (Termination), however, the Term shall be deemed to have ended as of the date of such termination. (B) Renewal Term. To the extent permitted by Applicable Law, the Term of this DBOM Agreement may be renewed and extended for an initial 10 year renewal term and an additional 10 year renewal term (the first such renewal being the "Initial Renewal Term", the second such renewal term being the "Additional Renewal Term" and each such renewal term individually or in the aggregate being a "Renewal Term"), in each case, upon the mutual agreement of the City and the DBOM Contractor. The terms and conditions governing the Renewal Term shall be subject to the good faith negotiations of the parties. Either party may elect to discontinue negotiations, in which case the DBOM Agreement shall terminate on the expiration date. (1) City of Notice of Intent for Renewal Term. The City shall, not later than 720 days prior to the expiration of the Initial Term or the Initial Renewal Term, as applicable, give the DBOM Contractor written notice of its intent whether or not to exercise its renewal option pursuant to this subsection. (2) DBOM Contractor Notice of Intent and Proposal for Renewal Term. The DBOM Contractor shall, not later than seven days after receipt of the City's notice given pursuant to Item (1) of this subsection, notify the City in writing of its intentions with respect to the renewal and extension of this DBOM Agreement. In the event the DBOM Contractor notifies the City that it also intends to exercise its renewal option pursuant to this subsection, the DBOM Contractor shall, no later than 90 days after receipt of the City's notice given pursuant to Item (1) of this subsection, provide the City with a formal written proposal of the terms and conditions governing the Renewal Term, including: (a) A proposed new Operation and Maintenance Charge, including the base ordinary operation and maintenance component and the Sludge transportation component, to replace the amounts set forth in Section 17.3 (Operation and Maintenance Charge) during the applicable Renewal Term; (b) A new Major Maintenance, Repair and Replacement Schedule with proposed annual costs for Major Maintenance, Repair and Replacement for purposes of determining the Annual Capital Maintenance Charge for each Contract Year in accordance with Section 17.5 (Annual Capital Maintenance Charge) during the applicable Renewal Term; and (c) Any other terms and conditions governing the Renewal Term as agreed upon by the parties to be set forth in the DBOM Contractor's proposal. 34 3935946.13 043463 DBOM Agreement Howard City Circuit Courthouse Article 3 -Term If each party intends to renew and extend this DBOM Agreement pursuant to this subsection, following delivery of the DBOM Contractor's proposal pursuant to Item (2) of this subsection, the parties shall promptly and in good faith negotiate the terms and conditions governing the Renewal Term and, if agreement is reached, execute a DBOM Agreement Amendment reflecting such agreed upon terms and conditions prior to expiration of the Initial Term or the Initial Renewal Term, as applicable. In the event the parties have not yet entered into a DBOM Agreement Amendment by the date that is 360 days prior to the expiration of the Initial Term or the Initial Renewal Term, as applicable, or such later date as may be agreed upon by the parties, the parties may agree to a one-year extension of the Term on the same terms and conditions in effect prior to its expiration in order to provide additional time for the parties to negotiate the terms and conditions governing the Renewal Term. (C) Accrued Rights. No termination of this DBOM Agreement shall: (1) Limit or otherwise affect the respective rights and obligations of the parties hereto accrued prior to the date of such termination; or (2) Preclude either party from impleading the other party in any Legal Proceeding originated by a third-party as to any matter occurring during the Term. Section 3.2. SURVIVAL. Notwithstanding any other provision of this DBOM Agreement, the following provisions hereof will survive the expiration or any earlier termination of this DBOM Agreement: (1) Section 4.9 (Financial Books and Records); (2) Article 19 (Dispute Resolution); (3) Article 21 (DBOM Contractor Events of Default); (4) Article 22 (City Events of Default); (5) Article 23 (Termination), as applicable to the obligations of the parties following the Termination Date; (6) Article 25 (Indemnification); (7) Section 26.17 (Confidentiality); and (8) Section 2.2 (Professional Protective Indemnity) and Section 2.3 (Professional Liability) of Appendix 12 (Insurance Requirements), to the extent the 10- year extended reporting or discovery"tail" period provided therein has not expired on the Termination Date; together with any provisions necessary to give effect to the above provisions. 35 3935946.13 043463 ARTICLE 4 PROJECT SERVICES GENERALLY Section 4.1. GENERAL RESPONSIBILITIES OF THE PARTIES. (A) DBOM Contractor. The DBOM Contractor shall, subject to the terms and conditions of this DBOM Agreement design, construct, operate and maintain the Project. (B) City. The City shall, subject to the terms and conditions of this DBOM Agreement, pay the Design-Build Price, the Service Fee and the other amounts required to be paid by the City hereunder to the DBOM Contractor for the performance of the Project Services. (C) Party Bearing Cost of Performance. All obligations undertaken by each party hereto shall be performed at the cost of the party undertaking the obligation or responsibility, unless the other party has explicitly agreed herein to bear all or a portion of the cost either directly, by reimbursement to the other party or through an adjustment to the Design- Build Price or the Service Fee, as applicable. Section 4.2. DESIGN-BUILD WORK PERSONNEL. (A) Staffing Requirements. The DBOM Contractor shall enforce discipline and good order during the Design-Build Period among the personnel performing the Design-Build Work. All persons engaged by the DBOM Contractor for Design-Build Work shall have requisite skills for the tasks assigned. The DBOM Contractor shall employ or cause its subcontractors to employ or engage and compensate engineers and other consultants to perform all engineering and other services required for the Design-Build Work. All firms and personnel performing Design-Build Work, including Subcontractor firms and personnel, shall meet the licensing and certification requirements imposed by Applicable Law. (B) Design-Build Project Manager. The DBOM Contractor shall designate from time to time an employee of the DBOM Contractor as the DBOM Contractor's construction manager (the "Design-Build Project Manager"), who shall be present on the Project Site with any necessary assistants on a full-time basis when the DBOM Contractor or any Subcontractor is performing the Design-Build Work. The Design-Build Project Manager shall be appropriately trained, experienced and knowledgeable in all aspects of the Design-Build Work so as to knowledgeably interact and communicate with the City and all Subcontractors regarding the Project and appropriately oversee the day-to-day performance of the Design-Build Work. The Design-Build Project Manager shall, among other things: (1) Be familiar with the Design-Build Work and all requirements of this DBOM Agreement; (2) Coordinate the Design-Build Work and give the Design-Build Work regular and careful attention and supervision; (3) Maintain a daily status log of the Design-Build Work; and (4) Attend all construction progress meetings with the City, as required by Appendix 6 (Design-Build Work Review Procedures). The DBOM Contractor shall keep the City continuously informed of all business telephone, mobile telephone, e-mail addresses and other means by which the Design-Build Project Manager may be contacted. The Design-Build Project Manager (or their designee with equal authority to 36 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally bind and represent the DBOM Contractor) shall be available to be contacted by the City on a continuous 24-hours per day, seven days per week, 365 days per year basis for emergency response, information, coordination or any other purpose hereunder. The initial Design-Build Manager shall be the person set forth in Appendix 19 (DBOM Contractor and Subcontractor Information). Section 4.3. OPERATION AND MAINTENANCE SERVICES PERSONNEL. (A) Staffing Requirements. The DBOM Contractor shall staff the Project during the Operation and Maintenance Period in accordance with the Contract Standards with qualified personnel who meet the licensing and certification requirements of Applicable Law. The DBOM Contractor shall discipline or replace, as appropriate, any employee of the DBOM Contractor or any Subcontractor engaging in unlawful, unruly, or offensive conduct. The DBOM Contractor shall notify the City of any material change in staffing levels and positions from time to time, and shall not make any such material change if the new staffing level would adversely affect the ability of the DBOM Contractor to provide the Operation and Maintenance Services in accordance with the Contract Standards. (B) Operation and Maintenance Supervisor. The DBOM Contractor shall appoint a full-time supervisor of the Project during the Operation and Maintenance Period (the "Operation and Maintenance Supervisor") who shall be licensed, trained, experienced and proficient in the management and operation of wastewater plants comparable to the Project, shall be appropriately certified under Applicable Law (unless otherwise agreed upon by the City as long as there is an operations staff member assigned to the Project that is appropriately licensed under Applicable Law), and whose sole employment responsibility shall be managing the DBOM Contractor's performance of the Operation and Maintenance Services. The DBOM Contractor acknowledges that the performance of the individual serving from time to time as the Operation and Maintenance Supervisor will have a material bearing on the quality of service provided hereunder, and that effective cooperation between the City and the Operation and Maintenance Supervisor will be essential to effectuating the intent and purposes of this DBOM Agreement. Accordingly, not fewer than 15 days prior to the date on which any candidate for Operation and Maintenance Supervisor from time to time during the Term is proposed by the DBOM Contractor to assume managerial responsibility for the Project, the DBOM Contractor shall: (1) Provide the City with a comprehensive resume of the candidate's licenses, training, experience, skills and approach to management and customer relations; and (2) Afford the City an opportunity to interview the candidate with respect to such matters. The City shall have the right to disapprove the hiring of the proposed candidate, which right of disapproval shall not be exercised unreasonably. The City shall provide notice of its approval or disapproval within 15 days following the interview, together with a reasonably detailed written explanation of the grounds of any disapproval. Failure of the City to deliver such notice within such 15-day period shall be deemed an approval of the proposed Operation and Maintenance Supervisor by the City. The initial Operation and Maintenance Supervisor, a Key Individual identified in Appendix 19 (DBOM Contractor and Subcontractor Information), shall not be replaced, unless otherwise approved by the City in its discretion, for a period of three years from the Acceptance Date, absent death, disability, retirement, resignation or cessation of employment with the DBOM Contractor. The DBOM Contractor shall replace the Operation and Maintenance Supervisor at the request of the City, after notice and a reasonable opportunity for corrective action, in the event the City reasonably determines that an unworkable relationship has developed between the Operation and Maintenance Supervisor and the City. 37 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally Section 4.4. KEY INDIVIDUALS. Attached as Appendix 19 (DBOM Contractor and Subcontractors Information) is a list of persons (the "Key Individuals") that the DBOM Contractor shall utilize in undertaking the Project Services. With respect to each of the Key Individuals: (1) The DBOM Contractor, while the Key Individuals remain within its employment or the employment of a Subcontractor, shall deploy the Key Individuals to perform the duties for the Project Services described in Appendix 19 (DBOM Contractor and Subcontractors Information); and (2) If for any reason a Key Individual resigns, retires, dies, becomes disabled, receives maternity, parental or sick leave, is promoted or is terminated for cause, then the DBOM Contractor shall retain a replacement with equivalent expertise and experience to the unavailable Key Individual satisfactory to the City acting reasonably, and the DBOM Contractor shall not replace such Key Individual without the City's consent, acting reasonably. (3) The City shall have the right to disapprove the hiring of any proposed replacement Key Individual, which right of disapproval shall not be exercised unreasonably. The City shall provide notice of its approval or disapproval within 15 days following receipt of the resume of the proposed replacement Key Individual, together with a reasonably detailed written explanation of the grounds of any disapproval. Failure of the City to deliver such notice within such 15-day period shall be deemed an approval of the proposed replacement Key Individual by the City. Section 4.5. COMPLIANCE WITH APPLICABLE LAW. (A) Compliance Obligation. The DBOM Contractor shall perform the Project Services in accordance with Applicable Law, and shall cause all Subcontractors to comply with Applicable Law. (B) Governmental Approvals. The DBOM Contractor shall make all filings, applications and reports necessary to be made in order to obtain and maintain all DBOM Contractor Managed Governmental Approvals required for the performance of the Project Services, and assist the City in obtaining the City Managed Governmental Approvals as and to the extent provided in subsections 5.6(F) (DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals) and Section 8.8(F) (DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals), and shall comply with the terms of all Governmental Approvals. (C) Registration, Licensing and Certification Requirements. The DBOM Contractor shall ensure that all persons performing the Project Services, including all Subcontractors, comply with all registration, licensing and certification requirements imposed by Applicable Law. Without limiting the generality of the foregoing, in the event the DBOM Contractor or a Subcontractor performs any asbestos abatement work it shall be licensed in accordance with ORS 468A.710. (D) Investigations of Non-Compliance. In connection with any actual or alleged event of material non-compliance with Applicable Law in the performance of the Project Services, the DBOM Contractor shall, in addition to any other duties which Applicable Law may impose: 38 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally (1) Fully and promptly respond to all inquiries, investigations, inspections, and examinations undertaken by any Governmental Body; (2) Attend all meetings and hearings with respect to the Project required by any Governmental Body; (3) Provide all corrective action plans, reports, submittals and documentation required by any Governmental Body, and shall provide copies of any such plan, report, submittal or other documentation to the City; and (4) Promptly upon receipt thereof, provide the City with a true, correct and complete copy of any written notice of violation or non-compliance with Applicable Law, and true and accurate transcripts of any oral notice of non-compliance with Applicable Law, issued or given by any Governmental Body. The DBOM Contractor shall furnish the City with a prompt written notice describing the occurrence of any event or the existence of any circumstance which does or may result in any such notice of violation or non-compliance to the extent the DBOM Contractor has knowledge of any such event or circumstance, and of any Legal Proceeding alleging such non-compliance. To the greatest extent practicable, the DBOM Contractor shall provide the City an opportunity to review and comment on any proposed DBOM Contractor response to any non-compliance with Applicable Law hereunder prior to its implementing such response. (E) Fines, Penalties and Remediation. Except to the extent excused by Relief Events, in the event that the DBOM Contractor or any Subcontractor fails at any time to comply with Applicable Law with respect to the Project Services, the DBOM Contractor shall: (1) Promptly correct such failure and resume compliance with Applicable Law; (2) Pay any resulting fines, assessments, levies, impositions, penalties or other charges; (3) Indemnify, defend and hold harmless the City and the City Indemnitees in accordance with Section 25.1 (DBOM Contractor's Obligation to Indemnify) from any Loss-and-Expense resulting therefrom; (4) Make all changes in performing the Project Services which are necessary to assure that the failure of compliance with Applicable Law will not recur; and (5) Comply with any corrective action plan filed with or mandated by any Governmental Body in order to remedy a failure of the DBOM Contractor or any Subcontractor to comply with Applicable Law. (F) Tax Compliance. The DBOM Contractor represents and warrants that it has complied, and will continue to comply throughout the Term of this DBOM Agreement and any extensions, with all Tax laws of the State or any political subdivision of the State, including ORS 305.620 and ORS chapters 316, 317, 317A and 318. The DBOM Contractor further represents and warrants that it will require all Subcontractors to similarly comply with all Tax laws of the State or any political subdivision of the State, including ORS 305.620 and ORS Chapters 316, 317, 317A and 318. Any violation of this subsection shall constitute a DBOM Contractor Event of Default pursuant to subsection 21.1(A)(5) (DBOM Contractor Events of Default Defined). 39 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally (G) Water Infrastructure Finance and Innovation Act (WIFIA). The DBOM Contractor acknowledges that the City intends to utilize a WIFIA loan as part of its financing structure. The DBOM Contractor hereby acknowledges that the utilization of a WIFIA loan is predicated on complying during the Design-Build Period with Davis-Bacon Act wage requirements, the Disadvantaged Business Enterprise Program, Build America Buy America Act ("BABAA") and American Iron and Steel requirements, all as more particularly described in Appendix 3 (Certain Federal Requirements). The DBOM Contractor represents and warrants that the costs of the federal programs more particularly described in Appendix 3 (Certain Federal Requirements)) are incorporated into the Fixed Design-Build Price as of the Effective Date; except that, the costs of compliance with BABAA have not been incorporated based upon the WIFIA program's waiver of BABAA requirements for WIFIA-financed projects that have initiated design planning prior to May 14, 2022, and if BABAA compliance is required it shall constitute an Other Relief Event, and the DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures). Any change or addition to applicable federal project funding requirements after the Effective Date shall constitute a Change in Law Event. Section 4.6. TCWTP OUTFALL OBLIGATIONS AND CONDITION RISK. (A) DBOM Contractor TCWTP Outfall Obligations. The DBOM Contractor acknowledges that: (1) the DBOM Contractor's agents and representatives have observed and are generally familiar with the TCWTP Outfall, its design, and its physical condition relevant to the obligations of the DBOM Contractor pursuant to this DBOM Agreement; and (2) the DBOM Contractor shall tie-in to the TCWTP Outfall as part of the Design-Build Work so that the TCWTP Outfall will be incorporated into the Project and utilized to discharge Effluent. During the Operation and Maintenance Period, if requested by the City, the DBOM Contractor will perform periodic inspection and modeling required for the TCWTP Outfall pursuant to the NPDES Permit after the parties enter into a DBOM Agreement Amendment authorizing the performance of such services and the compensation therefor. The DBOM Contractor shall be responsible for performing all Operation and Maintenance Services with respect to the effluent conveyance system (including the outfall junction box at the interconnection point as shown in the Design Documents) it designs and constructs from the Wastewater Treatment Facility to the TCWTP Outfall; provided, however, the DBOM Contractor does not have any maintenance, repair and replacement obligations with respect to the TCWTP Outfall under this DBOM Agreement. (B) Condition of the TCWTP Outfall. The City shall have all maintenance, repair and replacement obligations with respect to the TCWTP Outfall under this DBOM Agreement and shall be responsible for the performance of periodic inspection and modeling required for the TCWTP Outfall pursuant to the NPDES Permit unless the parties agree that the DBOM Contractor will perform such inspection and modeling pursuant to a DBOM Agreement Amendment. The City assumes the risk of the adequacy and sufficiency of the design of the TCWTP Outfall and the existing condition of the TCWTP Outfall as such design or condition may affect the ability of the DBOM Contractor to comply with Applicable Law, perform the Design- Build Work or the Operation and Maintenance Services (including compliance with the Performance Guarantees) or perform any of its other obligations hereunder upon the schedule and for the compensation provided for herein. It shall constitute an Other Relief Event, and the DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures), in the event that any defect, flaw, error, inoperability, inadequacy or other condition or aspect of the design or condition of the TCWTP Outfall (1) prevents, delays or otherwise interferes with the ability of the DBOM Contractor to perform the Design-Build Work or achieve Acceptance in accordance with this DBOM Agreement, or (2) interferes with the ability of the DBOM Contractor to perform or otherwise increases the costs of the DBOM Contractor in performing the Operation and Maintenance Services (including compliance with the Performance Guarantees) in accordance with the Contract Standards. 40 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally Section 4.7. RESTRICTIONS ON CITY-DIRECTED DESIGN AND CONSTRUCTION REQUIREMENT CHANGES, CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES. The City shall not at any time during the Term require, and the DBOM Contractor may refuse to implement, a Change Order (relating to a City-directed Design and Construction Requirement Change or a Design and Construction Requirement Change made due to a Relief Event), a Capital Modification or an Operation and Maintenance Services Change which: (1) Would be contrary to Applicable Law; (2) Would render any policy of Required Insurance void or voidable unless the City agrees to provide replacement insurance or other security reasonably satisfactory to the DBOM Contractor; (3) Would cause the revocation of any Governmental Approval required for the DBOM Contractor to perform its obligations under this DBOM Agreement, and such Governmental Approval would not, using reasonable efforts, be capable of amendment or renewal; (4) Would require a new Governmental Approval for the DBOM Contractor to perform its obligations under this DBOM Agreement, which Governmental Approval would not, using reasonable efforts by the DBOM Contractor or the City, as applicable, be obtainable; (5) Would result in rework to the Design-Build Work in excess of $20,000, unless the adverse effects of such a Change Order on the Design-Build Work or the Operation and Maintenance Services Change (as the case may be) are compensated by the City or the City has agreed to pay the DBOM Contractor on a Cost Substantiation basis pending resolution of, or instead of proceeding to, dispute resolution; (6) Is not documented or evidenced in writing by either a Contract Administration Memorandum, a DBOM Agreement Amendment or a Change Order; provided, however that changes less than $20,000 in the aggregate may be addressed in the field during the Design-Build Period; (7) If the requested change could not be implemented without creating an immediate and serious threat to the health or safety of any person, any property, the environment or the reputation, integrity of, or public confidence in, the Project and any related operations; (8) Would not be feasible, or the DBOM Contractor would not, using commercially reasonable efforts, be able to implement within the time specified; or (9) Would negatively impact the ability of the DBOM Contractor to achieve the Performance Guarantees unless the City agrees to amend the Performance Guarantees or provide compensation relief so that the DBOM Contractor's ability to comply, or cost to comply, would no longer be negatively impacted. Section 4.8. GOOD DESIGN-BUILD PRACTICE AND GOOD OPERATION AND MAINTENANCE PRACTICE. Good Design-Build Practice and Good Operation and Maintenance Practice shall be utilized hereunder, among other things, to implement and in no event to displace or lessen 41 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally the stringency of the Contract Standards. In the event that, over the course of the Term, Good Design-Build Practice or Good Operation and Maintenance Practice evolves after the Effective Date the DBOM Contractor shall utilize such Design-Build Practice or Good Operation and Maintenance Practice in providing the services required under this DBOM Agreement. Section 4.9. FINANCIAL BOOKS AND RECORDS. (A) Recordkeeping Requirements. The DBOM Contractor shall prepare and maintain proper, accurate, current and complete financial books and records regarding the Project Services, including all books of account, bills, vouchers, invoices, personnel rate sheets, cost estimates and bid computations and analyses, purchase orders, time books, daily job diaries and reports, correspondence, and any other documents showing all acts and transactions in connection with or relating to or arising by reason of the Project Services, this DBOM Agreement, any Subcontract or any transactions in which the City has or may have a financial or other material interest hereunder, in each case to the extent required to determine the costs of Design and Construction Requirement Changes, Relief Event costs, or other changes in or additions to the Design-Build Price or the Service Fee for which the City is or may be responsible under this DBOM Agreement. The DBOM Contractor shall produce such financial books and records for examination and copying for all such purposes within 14 days following receipt of a written request by the City. All such information upon delivery to the City shall be presented in a format that will enable an independent auditor to perform a review of the information in accordance with GAAP. The DBOM Contractor shall not be required to provide the City any income statement showing profit or loss, but recognizes that profit and loss information may become discernible to the City through the Cost Substantiation process or otherwise upon the delivery of financial records for the purposes hereof.The DBOM Contractor shall keep and maintain all such financial books and records with respect to each Contract Year until at least the seventh anniversary of the last day of each such Contract Year, or such longer period during which any Legal Proceeding with respect to the Project may be pending. In the event the DBOM Contractor fails to prepare or maintain any financial books, records or accounts as required under this Section, the DBOM Contractor shall not be entitled to any requested payments or adjustments to the extent such failure prevented verification or Cost Substantiation as required by this DBOM Agreement. (B) Inspection,Audit and Adjustment. The City shall have the right to perform or commission an inspection or independent audit of the financial information required to be kept under subsection (A) of this Section. The City shall give the DBOM Contractor reasonable advance notice (at least 10 Business Days) prior to any such audit, and such audit shall be performed during business hours. The City shall, or shall cause the party conducting the inspection or audit, to provide a complete copy of the inspection or audit report to the DBOM Contractor following receipt of such report. If an inspection or audit reveals that the DBOM Contractor has overstated any component of the Design-Build Price, the Service Fee or any other City payment obligation arising out of this DBOM Agreement, then the DBOM Contractor shall, at the election of the City, either immediately reimburse to the City or offset against future Design-Build Price or Service Fee payments, as applicable, the overstated amount plus interest at the Overdue Rate, from the time such amount was initially overpaid until reimbursed or credited to the City. If the overpayment exceeds 1% of the total amount that should have been properly paid by the City during the period audited, then the DBOM Contractor shall, in addition, reimburse the City for any and all fees and costs incurred in connection with the inspection or audit. The foregoing remedies shall be in addition to any other remedies the City may have, including remedies for a DBOM Contractor Event of Default. For clarity, the parties acknowledge and agree that the City shall not be entitled to audit the underlying costs that comprise any lump sum payments, including the Design-Build Price, any fixed price component of the Service Fee or any lump sum amount that is agreed upon by the parties pursuant to Section 26.6 (Negotiated Lump Sum Pricing of Additional Work). 42 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 4 DBOM Agreement Project Services Generally Section 4.10. DELIVERY OF DOCUMENTS. (A) DBOM Contractor. In this DBOM Agreement, the DBOM Contractor is obligated to deliver reports, records, designs,plans,drawings, specifications, proposals and other documentary submittals in connection with the performance of its duties hereunder. The DBOM Contractor agrees that all such documents shall be submitted to the City both in digital form and, at the City's request, in printed form. Digital copies shall consist of computer readable data submitted in any standard interchange format which the City may reasonably request to facilitate the administration and enforcement of this DBOM Agreement. In the event that a conflict exists between the signed or the signed and stamped hard copy of any document and the digital copy thereof, the signed or the signed and stamped hard copy shall govern. (B) City. The City shall make available to the DBOM Contractor upon request information relating to the Project which is in the possession of the City and material to the DBOM Contractor's performance hereunder, subject, however, to rights of attorney-client privilege and Applicable Law, including, for example, any confidentiality of records requirements. Section 4.11. CITY PAYMENT OBLIGATIONS GENERALLY. In addition to the Design-Build Price and the Service Fee (as further described in Article 7 (Payment for the Design-Build Work) and Article 17 (Service Fee and Other Payments)), this DBOM Agreement obligates the City to pay: (1) costs of Capital Modifications required due to a Relief Event pursuant to Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date) or at the City's direction pursuant to Section 11.5 (Capital Modifications at City Direction); and (2) costs for Design-Build Work or Reinstatement Works required pursuant to Section 15.2 (Uninsurable Force Majeure Events), Section 16.1 (Change in Law Events) and Section 16.3 (Other Relief Events). All such costs shall be paid on a negotiated lump sum basis in accordance with Section 26.6 (Negotiated Lump Sum Pricing of Additional Work) or subject to Cost Substantiation in accordance with Section 26.7 (Cost Substantiation of Additional Work Not Subject to Lump Sum Price Negotiation). The City shall pay any such costs from currently available funds or from the proceeds of a City financing. The DBOM Contractor shall have no obligation to finance any such costs; provided, however, the DBOM Contractor shall cooperate with and assist the City in providing any information, certifications or documents, and in attending meetings, hearings or forums, which may be reasonably required in connection with any public financing by the City with respect to any such costs. The City shall have no payment obligations to the DBOM Contractor other than set forth above. 43 3935946.13 043463 ARTICLE 5 DESIGN AND CONSTRUCTION Section 5.1. DESIGN-BUILD WORK GENERALLY. (A) Commencement and Prosecution of Design-Build Work. Subject to satisfaction of the conditions set forth in this subsection, the City shall issue a notice to proceed with the Design-Build Work (the "Design-Build Work Notice to Proceed") within 45 days following the Effective Date, and following issuance of such Design-Build Work Notice to Proceed the DBOM Contractor shall promptly proceed to undertake, perform and complete the Design- Build Work in accordance with the Contract Standards. Thereafter, the DBOM Contractor shall be paid the Design-Build Price pursuant to Article 7 (Payment for the Design-Build Work). The DBOM Contractor's unexcused failure to satisfy the Acceptance Conditions by or before the Scheduled Acceptance Date shall result in the imposition of delay liquidated damages during the period of delay as and to the extent provided in subsection 6.6(A) (Delay Liquidated Damages). Failure to satisfy the Acceptance Conditions by the Longstop Date shall constitute a DBOM Contractor Event of Default upon which the City may terminate this DBOM Agreement for cause in accordance with subsection 23.2(A) (City Termination Rights). If the Design-Build Work Notice to Proceed is not issued by the City on or prior to the date specified above in this subsection, and such delay is not the result of any DBOM Contractor Fault (including failure of the DBOM Contractor to maintain satisfaction of the conditions set forth below in this subsection), then such delay shall constitute an Other Relief Event, and the DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures) and Section 16.3 (Other Relief Events). The issuance of the Design-Build Work Notice to Proceed by the City shall not occur prior to the satisfaction of the following conditions by the DBOM Contractor: (1) The DBOM Contractor has obtained and submitted to the City certificates of insurance for all Required Design-Build Period Insurance that the DBOM Contractor is obligated to obtain in accordance with Section 13.1 (Insurance) and Appendix 12 (Insurance Requirements); (2) The DBOM Contractor has obtained and submitted to the City a certified copy of each of the P8513 Bonds, as required by and in accordance with Section 18.2 (Payment and Performance Bonds); and (B) DBOM Contractor Control of the Design-Build Work; No City Responsibility. The DBOM Contractor shall have total control of the Design-Build Work and shall effectively direct and supervise the Design-Build Work so that it is undertaken in compliance with the terms of this DBOM Agreement. The DBOM Contractor shall have the sole and exclusive responsibility and liability for the design, construction and performance of the Project hereunder, notwithstanding the fact that the RFP included certain minimum conceptual design criteria for the Design-Build Work and the Design and Construction Requirements that the Project would be required to meet. The DBOM Contractor acknowledges that any such minimum conceptual design criteria and the City's participation in design development activities do not in any manner or to any degree impair the DBOM Contractor's ability to perform the Design-Build Work and the Operation and Maintenance Services in compliance herewith. Nothing in this DBOM Agreement shall be interpreted as giving any responsibility for the Design- Build Work to the City or any City Indemnitee. The City's rights of review and comment with respect to any aspect of the Design-Build Work shall be for the City's benefit only, and no review or comment by any representative of the City shall in any way relieve the DBOM Contractor of its obligation for all aspects of the Design-Build Work of the Project. 44 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (C) Materials, Labor and Services. The DBOM Contractor shall furnish all necessary architectural, design and engineering services, labor, materials, equipment, supplies, tools, scaffolding, transportation, Utilities, insurance, temporary facilities and utilities, completed structures, assemblies, fabrications, acquisitions, installations, testing, accounting, recordkeeping and other things and services of every kind whatsoever necessary for the full performance and completion of the DBOM Contractor's design, engineering, construction, start- up, Commissioning, obtaining and maintaining DBOM Contractor Managed Governmental Approvals and related obligations with respect to the design, construction and Commissioning of the Project during the Design-Build Period under this DBOM Agreement. The materials, machinery, structures, improvements, and equipment to be furnished as part of the Design- Build Work shall be new, of recent manufacture, and meet or exceed the Design and Construction Requirements. (D) Project Sequencing, Schedule and Reports. The DBOM Contractor shall not be limited in the sequencing or staging of the Design-Build Work, except to the extent that the Contract Standards impose limitations. The DBOM Contractor shall prepare and provide the City with the "critical path method" Project Schedule for Design-Build Work in accordance with Appendix 7 (General Design-Build Work Requirements). Throughout the Design-Build Period, the DBOM Contractor shall submit to the City a monthly progress schedule and report (the "Monthly Progress Report") in accordance with the requirements of Appendix 7 (General Design-Build Work Requirements). The DBOM Contractor's submittal of the Monthly Progress Report (or any revised Monthly Progress Report) is for the City's information only and shall not limit or otherwise affect the DBOM Contractor's obligations to achieve Acceptance by the Scheduled Acceptance Date. The City's acceptance of the Monthly Progress Report (or any revised Monthly Progress Report) shall not bind the City in any manner and shall not imply City approval or consent to any of the matters set forth therein. (E) Design and Construction Requirements. The DBOM Contractor shall perform the Design-Build Work in compliance with the Design and Construction Requirements. The Design and Construction Requirements include the basic design principles, concepts and requirements for the Design-Build Work but do not include the final, detailed design, plans or specifications or indicate or describe each and every item required for full performance of the physical Design-Build Work or for achieving Acceptance. The DBOM Contractor agrees to prepare and furnish all necessary detailed designs, plans, drawings and specifications in conformity with the Design and Construction Requirements. The DBOM Contractor further agrees that it shall not have the right to bring any claim whatsoever against the City or any of its consultants or subcontractors, arising out of any designs, plans, drawings or specifications included in the RFP or made available during the procurement process or included in the Design and Construction Requirements. (F) Standards of Workmanship and Materials. Where this DBOM Agreement does not specify any explicit quality or standard for construction materials or workmanship, the DBOM Contractor shall use only workmanship and new materials of a quality consistent with that of construction workmanship and materials specified elsewhere in the Design and Construction Requirements, and the Design and Construction Requirements are to be interpreted accordingly. (G) Technical Standards and Codes. References in this DBOM Agreement to all professional and technical standards, codes and specifications are to the most recently published professional and technical standards, codes and specifications of the institute, organization, association, authority or society specified, all as in effect as of the Effective Date. Unless otherwise specified to the contrary, (1) all such professional and technical standards, codes and specifications shall apply as if incorporated in the Design and Construction Requirements, and (2) if any revision or series of revisions occurs during the Design-Build Period that increases the costs of the Design-Build Work, to the DBOM Contractor's knowledge, after 45 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction the Effective Date, and prior to completion of the applicable Design-Build Work, the DBOM Contractor shall notify the City. If so directed by the City, the DBOM Contractor shall perform the applicable Design-Build Work in accordance with the revised professional and technical standard, code or specification, and such direction shall be deemed to be an Other Relief Event. (H) Deliverable Material. The DBOM Contractor shall deliver to the City all Design Documents, reports, submittals and other materials ("Deliverable Material") required to be delivered under Appendix 6 (Design-Build Work Review Procedures), Appendix 8 (Commissioning and Acceptance Testing), Appendix 12 (Insurance Requirements) and Appendix 18 (Reports and Records). With respect to those Deliverable Materials required to be delivered within a certain number of days after the Effective Date under Appendix 6 (Design-Build Work Review Procedures), Appendix 8 (Commissioning and Acceptance Testing), Appendix 12 (Insurance Requirements) and Appendix 18 (Reports and Records), such obligation to provide such Deliverable Materials shall be counted from the Effective Date. The City shall have the right from and after the Effective Date to use (or permit use of) all such Deliverable Material, all oral information received by the City in connection with the Design-Build Work, and all ideas or methods represented by such Deliverable Material, without additional compensation. The City's use of any such Deliverable Material for any purpose other than the Project shall be at its own risk, and the DBOM Contractor shall have no liability therefor. (I) Payment of Costs. The DBOM Contractor shall pay directly all costs and expenses of the Design-Build Work of any kind or nature whatsoever, including: (1) all costs of permitting (regardless of permittee); (2) regulatory compliance and Legal Proceedings brought against the DBOM Contractor; (3) obtaining and maintaining the Required Insurance and Security Instruments; (4) DBOM Contractor-related financing costs; (5) payments due under the Subcontracts or otherwise for all labor and materials; (6) legal, financial, engineering, architectural and other professional services of the DBOM Contractor; (7) sales, use and similar Taxes on building supplies, materials and equipment; (8) general supervision by the DBOM Contractor of all Design-Build Work; (9) the preparation of schedules, budgets and reports; (10) keeping all construction accounts and cost records and (11) all other costs required to achieve Substantial Completion, Acceptance and Final Completion. Nothing set forth in this subsection is intended to limit the City's Design-Build Price payment obligations set forth in Article 7 (Payment for the Design-Build Work). (J) Quality Assurance and Quality Control. The DBOM Contractor shall have full responsibility for quality assurance and quality control for the Design-Build Work, including compliance with the Design-Build Quality Management Plan set forth in Appendix 22 (Design- Build Quality Management Plan). (K) Naming and Signs. The City shall have the exclusive right to name the Project and any parts thereof. The DBOM Contractor shall provide and maintain temporary Project identification and information signs during the Design-Build Period. No signs shall be erected (other than those required pursuant to subsection 5.14(B)(2) (Safety and Security) or as required in connection with a WIFIA financing) until their appearance, content, and location have been fully reviewed and approved by the City, which approval shall not be unreasonably withheld, conditioned or delayed. The DBOM Contractor shall remove temporary signs from the Project Site when they are no longer necessary and remove its signs from the Project Site upon termination of this DBOM Agreement. (L) Laydown Areas. Laydown and staging areas for construction materials shall be located on the Project Site, the TCWTP Site (to the extent approved by Portland) or at other locations agreed to by the DBOM Contractor and the City, provided there shall be no additional costs to the City. 46 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (M) Maintenance of the Project Site. During performance of the Design-Build Work, the DBOM Contractor shall be responsible for the overall maintenance of the Project Site. The DBOM Contractor shall keep the Project Site neat and orderly at all times, and shall clean up and remove all rubbish and construction debris from the Project Site as they accumulate in accordance with the Contract Standards. (N) Title and Risk of Loss. Title to the structures, improvements, fixtures, machinery, equipment and materials constituting the Project shall pass to the City upon the earlier of (i) payment by the City for such structures, improvements, fixtures, machinery, equipment or materials and (ii) incorporation into the Project, free and clear of all Liens (other than Permitted Encumbrances) as provided in subsection (O) of this Section. The DBOM Contractor shall, however, subject to the Relief Event provisions hereof, bear all risk of loss concerning such structures, improvements, fixtures, machinery, equipment and materials until Acceptance, regardless of the extent to which the loss was insured or the availability of Insurance Proceeds. (O) Encumbrances. Other than Permitted Encumbrances, the DBOM Contractor shall not directly or indirectly, without the City's consent, create or permit to be created or to remain, and shall promptly discharge or bond any Encumbrance arising on the Project Facilities, the Project Site or the Design-Build Work arising out of the DBOM Contractor's construction or operation of the Project. (P) Compliance with Easements and Limits; Surveying. The DBOM Contractor shall: (1) construct the Project Facilities in compliance with the requirements of the easements, exceptions to title, limits and setback requirements identified in Appendix 1 (Site- Related Information); (2) perform all construction surveying necessary in connection therewith; and (3) preserve or replace as necessary all existing property line and corner survey monuments encountered. (Q) Utilities. The DBOM Contractor shall make all arrangements necessary to secure the availability of all Utilities required to construct and operate the Project Facilities in the capacities required hereunder. (R) Relocation of Existing Utilities. The DBOM Contractor shall be responsible for all construction activities required with regard to existing Utility services and installations (e.g., conduits, pipelines, transmission mains and other Utility equipment and appurtenances), including any relocation of Utilities, whether such construction activities are performed by the DBOM Contractor or by the owner of the existing Utility. Residents shall be informed in advance of work that affects their Utility service. A reasonable effort shall be made to coordinate with the needs of the affected residents. (S) Software Programming. The DBOM Contractor's obligation to perform the Design-Build Work includes the obligation to provide all software programming for the monitoring instrumentation and controls relating to the Project. (T) Demolition Work. As required by ORS 279C.510(1), the DBOM Contractor shall salvage or recycle construction and demolition debris, if feasible and cost-effective. (U) Notice of Default. The DBOM Contractor shall provide to the City, promptly following the receipt thereof, copies of any notice of default, breach or non-compliance received under or in connection with any Governmental Approval, Security Instrument or any Subcontract pertaining to the Design-Build Period, that may have a material and adverse effect on performance by the DBOM Contractor of its obligations under this DBOM Agreement. 47 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (V) Plantings along Foothills Road. The DBOM Contractor shall provide plantings along Foothills Road in accordance with the preliminary design set forth in Appendix 5 (Secondary Technical Criteria) and Applicable Law. Section 5.2. ACCESS TO AND SUITABILITY OF THE PROJECT SITE. (A) Familiarity with the Project Site. The DBOM Contractor acknowledges: (1) the DBOM Contractor's agents and representatives have visited, inspected and are familiar with the Project Site, its surface physical conditions relevant to the obligations of the DBOM Contractor pursuant to this DBOM Agreement, including surface conditions, normal and usual soil conditions, roads, Utilities, topographical conditions and air and water quality conditions; (2) that the DBOM Contractor has conducted all diligence it believes to be necessary to fulfill its obligations under this DBOM Agreement, including the review of all Project Site investigations and studies previously conducted that have been made available to the DBOM Contractor as Reference Documents; (3) that the DBOM Contractor is familiar with all local and other conditions which may be material to the DBOM Contractor's performance of its obligations under this DBOM Agreement (including transportation, seasons and climate, access, availability, disposal, handling and storage of materials and equipment, and availability and quality of labor and Utilities), and has reviewed all information regarding the Project Site made available to it or otherwise obtained in the course of performing its due diligence, has made any other investigations that it deems necessary to make a determination as to the suitability of the Project Site; and (4) that based on the foregoing, the Project Site constitutes an acceptable and suitable site for the construction of the Project in accordance herewith, and the Project can be constructed on the Project Site by the Scheduled Acceptance Date and within the Design-Build Price. (B) Access to Project Site. The execution of this DBOM Agreement shall be deemed to constitute the granting of a license to the DBOM Contractor for full unfettered access to the Project Site for the purposes of this DBOM Agreement. The City is solely responsible for obtaining full unfettered access and title to the Project Site, as further described in this DBOM Agreement, and for paying all costs to acquire the Project Site, including any relocation costs for the current landowners. (C) Access to TCWTP Site. Following the Design-Build Work NTP Date, the DBOM Contractor shall have full access to the TCWTP Site for the purposes of this DBOM Agreement. Such access shall be subject to planning and coordination with the City and Portland to minimize adverse impacts to the services performed by Portland at TCWTP. The DBOM Contractor shall assume all risks associated with such activities and shall indemnify, defend and hold harmless the City, the City Indemnitees and Portland in accordance with Section 25.1 (DBOM Contractor's Obligation to Indemnify) from and against all Loss-and-Expense arising therefrom. Section 5.3. [RESERVED]. Section 5.4. DIFFERING SITE CONDITIONS. (A) Further Investigations and Protection of Utilities. Prior to commencing any trenching or excavations, the DBOM Contractor shall, taking into account the information included in the Reference Documents and in compliance with Good Design-Build Practice, conduct further site investigations, including exploratory excavations and further borings, to confirm the location and type of structures that could be damaged as a result of the excavations (as well as other conditions that may impact construction). Such structures include buildings, all sewer, water, gas, and other piping, and manholes, chambers, electrical conduits, wires, tunnels and other existing subsurface work located within or adjacent to the Project Site. The DBOM Contractor shall carefully sustain in their places and support, or if necessary, relocate, 48 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction all underground and surface structures located within or adjacent to the Project Site in accordance with the Contract Standards and as required by the party owning or controlling such structure. Existing surface facilities which are temporarily removed to facilitate installation of the Design-Build Work shall be replaced and restored to their original condition. The DBOM Contractor shall notify the City as soon as possible but in any event at least five business days in advance of any work that might impact utilities of businesses or residents in the area surrounding the Project Sites so that the City can notify such businesses or residents of such work. The DBOM Contractor shall comply with all requirements set forth under Applicable Law prior to and during undertaking such excavations or tunneling. (B) DBOM Contractor Responsibility for Site Conditions. The DBOM Contractor acknowledges and agrees that, subject to subsections (C), (D) and (E) of this Section, the DBOM Contractor shall have the exclusive responsibility and liability for any physical conditions, underground structures, and subsurface conditions at the Project Site. (C) Discovery of Differing Site Conditions. Upon discovering an alleged Differing Site Condition and before the condition is further disturbed, the DBOM Contractor shall immediately, after taking appropriate measures to secure the affected Design-Build Work: (1) stop work in and secure the affected area; and (2) notify the City of the alleged Differing Site Condition. The DBOM Contractor's notice to the City shall be issued by telephone or in person and followed no later than by the end of the next business day thereafter by written notice, providing a brief description of why the condition encountered is considered a Differing Site Condition. Such notice shall describe the specific site conditions encountered and the measures taken to deal with the site conditions. Notwithstanding anything set forth in this Section or in Article 14 (Relief Event Procedures), no Relief Event relief shall be allowed for any alleged Differing Site Condition unless the DBOM Contractor provides the City with notice in accordance with this subsection. Promptly upon receipt of the DBOM Contractor's notice, the City will investigate the Project Site conditions. (D) Relief for Differing Site Conditions. If the DBOM Contractor establishes that the actual conditions encountered during Construction: (1) meet the criteria for a Differing Site Condition, and (2) directly and materially impact the DBOM Contractor's cost or time of performance, then it shall constitute an Other Relief Event and the DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures). Section 5.5. REGULATED SITE CONDITIONS. (A) DBOM Contractor Responsibilities. The parties recognize that in performing the Design-Build Work, the DBOM Contractor may encounter various Regulated Site Conditions. In performing the Design-Build Work, the DBOM Contractor shall exercise due care, in light of all relevant facts and circumstances, to avoid exacerbating any Regulated Site Condition after the location and existence of such Regulated Site Condition has been disclosed to the DBOM Contractor or becomes actually known by the DBOM Contractor. Notwithstanding anything to the contrary in this Section, the DBOM Contractor shall bear full responsibility for the handling, treatment, storage, removal, remediation, avoidance or other appropriate action (if any), with respect to: (1) Any Hazardous Substance present at, on, in or under or migrating or emanating to or from the Project Sites, that was generated by or brought or caused to be brought on the Project Sites by any act or omission of the DBOM Contractor or any Subcontractor; and (2) The creation of any Regulated Site Condition due to DBOM Contractor Fault, or the exacerbation of any Regulated Site Condition due to DBOM Contractor Fault 49 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction once the location and existence of such Regulated Site Condition becomes actually known to the DBOM Contractor. All remediation costs resulting from Hazardous Substances or Regulated Site Conditions for which the DBOM Contractor bears responsibility pursuant to this subsection (A) shall be borne solely by the DBOM Contractor. The DBOM Contractor shall indemnify, defend and hold harmless the City Indemnitees in accordance with and to the extent provided in Article 25 (Indemnification) from and against all Loss-and-Expense resulting from Hazardous Substances or Regulated Site Conditions for which the DBOM Contractor bears responsibility pursuant to this subsection (A). (B) Cultural Resources. The DBOM Contractor shall not remove or disturb, or cause to be removed or disturbed, any historical, archaeological, architectural or other cultural artifacts, relics, vestiges, remains or objects of antiquity. If the DBOM Contractor discovers any of these items, the DBOM Contractor shall immediately notify the City Representative and comply with any applicable cultural resources discovery plans and all Applicable Law. (C) Endangered Species. Should either threatened or endangered plant or animal species (as determined under Applicable Law) be encountered in the performance of the Design-Build Work, the DBOM Contractor shall cease work immediately in the area of encounter, notify the City Representative and comply with all Applicable Law. The DBOM Contractor shall not resume Design-Build Work in the affected area until authorized to do so by the City Representative. (D) Encountering of Hazardous Substances. If the DBOM Contractor encounters any materials or substances at the Project Site that it reasonably believes to be Hazardous Substances, it shall immediately notify the City, stop work to the extent required to avoid any safety or health hazard or to comply with Applicable Law, take all actions required by Applicable Law regarding notifications and isolation of the impacted area, and confer with the City regarding the appropriate course of action. (E) Uncontrollable Circumstance Relief. Without limiting the DBOM Contractor's obligations under subsection (D) of this Section, if the DBOM Contractor establishes that the actual conditions encountered during performance of the Design-Build Work: (1) Meet the criteria for Regulated Site Conditions; (2) Directly and materially impact the DBOM Contractor's cost or time of performance; and (3) Were not known or could not have been reasonably discovered through the DBOM Contractor's performance of the review of Reference Documents or reasonable diligence in accordance with the Contract Standards; then the DBOM Contractor shall be entitled to relief as and to the extent provided in Section 16.3 (Other Relief Events) and Article 14 (Relief Event Procedures). No relief will be granted due to the presence of Hazardous Substances that were disclosed to the DBOM Contractor as of the Effective Date. (F) Generator Liability. Nothing contained herein is intended to identify the DBOM Contractor as the generator of any pre-existing Hazardous Substance, except as provided by Applicable Law. Except with respect to those Hazardous Substances identified in subsection (A) of this Section as to which the DBOM Contractor bears responsibility, the City shall execute, 50 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction as generator, Hazardous Substance manifests required in order for the DBOM Contractor to fulfill its obligations under this Section, as and to the extent required under Applicable Law. Section 5.6. DESIGN-BUILD GOVERNMENTAL APPROVALS. (A) Generally. The DBOM Contractor shall make all applications and take all other action necessary to obtain and maintain all Design-Build Governmental Approvals that are DBOM Contractor Managed Governmental Approvals and shall pay all fees, costs and charges due in connection therewith unless provided otherwise in Appendix 2 (Governmental Approvals). Where required under Applicable Law, such applications shall be made in the name of the City, subject to the City's rights hereunder. The DBOM Contractor shall manage the process of obtaining the Design-Build Governmental Approvals that are DBOM Contractor Managed Governmental Approvals in a manner which affords the City a reasonable opportunity to review and comment upon such submittals and all material documentation submitted to and issued by any Governmental Body in connection therewith as provided in Appendix 6 (Design-Build Work Review Procedures). The DBOM Contractor shall not knowingly take any action in any application, data submittal or other communication with any Governmental Body regarding the Design-Build Governmental Approvals or the terms and conditions thereof that would impose any unreasonable cost or burden on the City. The City reserves the right to reject, modify, alter, amend, delete or supplement any information supplied, or term or condition proposed, by the DBOM Contractor which would have the effect described in the preceding sentence. (B) Limited Permitting Assistance by the City. The City shall provide reasonable assistance to the DBOM Contractor in connection with the DBOM Contractor's obligation to obtain and maintain the Design-Build Governmental Approvals that are DBOM Contractor Managed Governmental Approvals required under this Section, including signing permit applications, attending public hearings and meetings of the Governmental Bodies charged with issuing the Design-Build Governmental Approvals, and providing the DBOM Contractor with existing relevant data and documents that are within the City's custody or control or are reasonably obtainable by the City and which are reasonably required for such purpose; provided, however, that the City's obligation to provide such reasonable assistance shall be limited, in light of the DBOM Contractor's primary role in the permitting and development of the Project, only to those actions which are legally required to be taken by the City as permittee or which involve providing information which is in the possession of or reasonably obtainable by the City. Any such assistance shall be provided only upon the reasonable request of the DBOM Contractor made directly to the City, and the City shall have no affirmative obligation independently to initiate or to provide such assistance. This covenant shall not obligate the City to staff the DBOM Contractor's permitting or development efforts, to undertake any new studies or investigations with respect to the Project, or to affirmatively seek to obtain the issuance of the Design-Build Governmental Approvals that are DBOM Contractor Managed Governmental Approvals. (C) DBOM Contractor Assumption of Permitting Risk for Design-Build Work. Except as set forth in subsection (D) and subsection (E) of this Section, the DBOM Contractor explicitly assumes the risk of obtaining and maintaining the Design-Build Governmental Approvals that are DBOM Contractor Managed Governmental Approvals, including the risk of delay, non-issuance or imposition of any term or condition in connection therewith by a Governmental Body. In assuming this risk, the DBOM Contractor acknowledges in particular that the Governmental Body issuing any such Design-Build Governmental Approval may impose terms and conditions that require the DBOM Contractor to make changes or additions to the Project or Project operations that may increase the cost or risk to the DBOM Contractor of performing the Project Services, all of which costs or risks shall be for the account of and borne by the DBOM Contractor. (D) Relief for Delays in the Issuance of DBOM Contractor Managed Governmental Approvals Caused by Governmental Bodies. If in seeking to obtain a required 51 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction Design-Build Governmental Approval that is a DBOM Contractor Managed Governmental Approval set forth in Attachment 2A (Expected Design-Build Governmental Approvals) of Appendix 2 (Governmental Approvals), (1) the DBOM Contractor has complied with the requirements of this DBOM Agreement and has in all respects used its best efforts to obtain the Design-Build Governmental Approval in a timely manner consistent with the Project Schedule; (2) the DBOM Contractor in a timely manner, based on the anticipated Project Schedule, has submitted all applications, data, studies, reports, responses and other information required under Applicable Law and the adopted administrative practice of the Governmental Body in order to obtain the Design-Build Governmental Approval; (3) the DBOM Contractor has submitted a complete application for the Design-Build Governmental Approval by the "Anticipated Governmental Approval Application Date" set forth in Attachment 2A (Expected Design-Build Governmental Approvals) of Appendix 2 (Governmental Approvals); and (4) there has been a failure by the Governmental Body to issue the Design-Build Governmental Approval by the "Assumed Governmental Approval Issuance Date" set forth in Attachment 2A (Expected Design- Build Governmental Approvals) of Appendix 2 (Governmental Approvals), then any such delay shall constitute an Other Relief Event. (E) Exception to DBOM Contractor Assumption of Permitting Risk with Respect to the NPDES Permit. The parties acknowledge and agree that the Effluent Guarantee in effect as of the Effective Date has been established, in part, based on the expected Effluent requirements of the NPDES Permit, which requirements are identified in Table 4-1 (Effluent Requirements, Dry Weather Season (May 1 -October 31)) and Table 4-2 (Effluent Requirements, Wet Weather Season (November 1 - April 30)) of Appendix 4 (Design and Construction Requirements). In the event that the Effluent requirements of the NPDES Permit are materially consistent with the Effluent Guarantee in effect as of the Effective Date, the DBOM Contractor shall not be entitled to any price, performance or schedule relief under this subsection. In the event that the Effluent requirements of the NPDES Permit include additional Effluent requirements or more stringent Effluent requirements than the requirements of the Effluent Guarantee, in either case which may be reasonably expected to require Project modifications or result in increased operating expenses to the DBOM Contractor in performing the Operation and Maintenance Services, the Effluent requirements shall be incorporated into the Effluent Guarantee and the DBOM Contractor shall be entitled to claim an Other Relief Event for any increased design-build costs and/or operating expenses in accordance with and to the extent provided in this subsection and Article 14 (Relief Event Procedures). To the extent demonstrated pursuant to Article 14 (Relief Event Procedures), the parties intend for the costs or risks of differing Effluent requirements of the NPDES Permit to be for the account of and borne by the City. The DBOM Contractor shall provide the City with written notice of its determination and reasoning as to whether and why the Effluent requirements of any draft or final NPDES Permit contains Effluent requirements which are more stringent than the Effluent Guarantee in effect as of the Effective Date within 15 days following receipt of information as to proposed Effluent requirements to be contained in the NPDES Permit. (F) DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals. In connection with Design-Build Governmental Approvals that are City Managed Governmental Approvals, the DBOM Contractor shall reasonably cooperate with and assist the City in carrying out the City's responsibilities hereunder with respect such City Managed Governmental Approvals, including: (i) providing assistance to the City in preparing and completing required filings, applications, notices and reports; (ii) providing readily available data, information, plans, documentation and supporting material; and (iii) performing the DBOM Contractor's responsibilities with respect to the NPDES Permit set forth in Appendix 2 (Governmental Approvals). If requested by the City, the DBOM Contractor will: (1) develop and furnish all necessary data, information, plans, documentation and supporting material that is not readily available; (2) familiarize itself with all applicable terms and conditions; (3) attend all required meetings and hearings; and (4) take all other actions reasonably necessary in accordance with Good Design-Build Practice to assist the City in obtaining, maintaining, 52 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction renewing, and extending all City Managed Governmental Approvals; in each case, after the parties enter into a Change Order or DBOM Agreement Amendment authorizing the performance of such services and the compensation therefor. (G) Relief for Delays in the Issuance of City Managed Governmental Approvals Caused by Governmental Bodies. In the event any delay in the issuance of a Design-Build Governmental Approval that is a City Managed Governmental Approval materially delays the achievement of Substantial Completion and Acceptance, an Other Relief Event shall be deemed to have occurred and the DBOM Contractor shall be entitled to an adjustment to the Scheduled Acceptance Date and any increased design-build costs in accordance with and to the extent provided in this subsection and Article 14 (Relief Event Procedures), except to the extent the DBOM Contractor fails to comply with its obligations with respect thereto under this Section, under Appendix 2 (Governmental Approvals), or under Section 26.10 (General Duty to Mitigate). Relief shall be granted under this subsection only if the delay in issuance of a City Managed Governmental Approval adds a material activity to, or materially affects an activity that is on the Project Schedule's critical path. Section 5.7. DBOM CONTRACTOR DESIGN- GENERAL. (A) Design Considerations. The design for the Project Facilities undertaken and performed by the DBOM Contractor shall: (1) Be undertaken in accordance with the Contract Standards, and the DBOM Contractor shall appoint a design team that: (a) is so qualified; (b) includes (as required by Applicable Law) licensed or registered professional engineers and architects; and (c) has sufficient expertise and experience to expeditiously and efficiently perform all of the design in a proper and professional manner; (2) Include specific consideration of "constructability" and "life cycle" cost issues at all stages of design, as appropriate; and (3) Include consideration of efficient and cost-effective operation and maintenance; provided, however, that nothing in this subsection (A) shall relieve the DBOM Contractor of its obligation to comply with the Contract Standards including the Acceptance Standards and the Performance Guarantees. (B) City Review and Comment on Design Documents. The DBOM Contractor shall provide the City with the design submittal protocol in accordance with the specific requirements set forth in Appendix 6 (Design-Build Work Review Procedures). The City shall have the right to review and comment on all Design Documents as provided in Appendix 6 (Design-Build Work Review Procedures) in order to confirm the compliance and consistency of the Design Documents with the Design and Construction Requirements and the Secondary Technical Criteria. In no event shall the DBOM Contractor proceed with the physical construction of any particular segment of the Design-Build Work without first complying with the requirements of the design submittal protocol and Appendix 6 (Design-Build Work Review Procedures). The DBOM Contractor shall give due consideration and provide written responses in the time and manner provided in Appendix 6 (Design-Build Work Review Procedures) to any 53 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction comments delivered by the City as to the DBOM Contractor's design submittals. Neither compliance by the DBOM Contractor with the Design and Construction Requirements and the Secondary Technical Criteria, nor review and comment by the City of the DBOM Contractor's Design Documents, nor any failure or delay by the City in commenting on any design submittals shall in any way relieve the DBOM Contractor of full responsibility for the design, construction, performance, operation and maintenance of the Project in accordance with the Contract Standards. (C) Documents at the Project Site. The DBOM Contractor shall maintain at the Project Site digital copies of all design and construction documents, including a complete digital set of record drawings. These digital documents shall be available to the City for reference, copying and use when it visits the Project Site, and one complete digital set thereof shall be delivered to the City upon completion and Acceptance of the Design-Build Work. (D) Ownership of Design and Intellectual Property. Except as otherwise set forth in this subsection with respect to Intellectual Property that the parties agree cannot be transferred to the City, the City shall own the Design Documents upon making payments therefore. Except for reference purposes, the Design Documents shall not be used by the City or the DBOM Contractor on any other project. The City is the owner of the Design and Construction Requirements. For any Intellectual Property relating to the Deliverable Material (including the Design Documents) that the parties agree cannot be transferred to the City, such Intellectual Property is, upon the City making payments for such Deliverable Material, hereby licensed to the City on a non-exclusive, cost free, perpetual basis for use by the City and any successor designer, builder or operator of the Project (but, with respect to any successor designer, builder or operator, only in connection with the design, construction or operation of the Project Facilities). The City shall have an irrevocable, perpetual, royalty-free and unrestricted right to use, reuse, reproduce, publish, display, broadcast and distribute such Intellectual Property, and to prepare derivative and additional documents based on such Intellectual Property, for any City purpose, whether before or following the termination of this DBOM Agreement. Neither the City nor the DBOM Contractor shall license, transfer or otherwise make available such Intellectual Property to any third-party for remuneration except with the consent of the other, which consent may be conditioned upon mutual agreement as to the sharing of any such remuneration. The use by the City of any such Intellectual Property for purposes other than in connection with the Project shall be at the City's own risk and the DBOM Contractor shall have no liability therefor. Section 5.8. DBOM CONTRACTOR DESIGN- REQUIREMENTS. The DBOM Contractor shall prepare all Design Documents necessary or appropriate to carry out and complete the Design-Build Work. The Design and Construction Requirements and the Secondary Technical Criteria shall form the basis of design for the Project and all design work shall be completed in accordance therewith. The DBOM Contractor shall ensure that all of the working and final Design Documents comply with the Design and Construction Requirements and the Secondary Technical Criteria, as applicable, and that the Project is constructed to a standard of quality, integrity, durability and reliability which is equal to or better than the standard established by the Design and Construction Requirements and the Secondary Technical Criteria. Section 5.9. SECONDARY TECHNICAL CRITERIA. (A) Relation to Design and Construction Requirements. The Secondary Technical Criteria contained in Appendix 5 (Secondary Technical Criteria) are provided in order to establish in further detail (1) the manner in which the design work, as of the Effective Date, is reasonably expected to be developed and carried to full completion; and (2) the standards of 54 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction quality, workmanship, integrity, durability and reliability to which the Project are to be constructed. (B) Permissible Variations. The design portion of the Design-Build Work shall be completed in accordance with the Secondary Technical Criteria. In light of the design-build- operate-maintain nature of this DBOM Agreement and the partially completed level of the design work as of the Effective Date, however, reasonable, minor variations from the Secondary Technical Criteria shall be permitted in the final design of the Project, to the extent such variations do not diminish the quality, workmanship, integrity, durability, functionality and reliability of the Project. Examples of elements of the Secondary Technical Criteria from which there may be reasonable, minor variations in the final design include thickness, level and composition of individual structural members; exact dimensions of rooms and buildings (to the extent overall functionality is not impaired); routes and depth of pipe conduit work; exact size, weight and height of mechanical components; and dimensions, ratings and positions of electrical, power and control cables, switchgear, transformers and control panels. No such variations shall be inconsistent with the Design and Construction Requirements, with the purposes of the Secondary Technical Criteria as set forth in subsection (A) (Relation to Design and Construction Requirements) of this Section, or with any limits specifically provided in the Secondary Technical Criteria regarding the range or nature of permissible variations or with any standards or principles regarding permissible deviations set forth therein. Variations in the final design from the Secondary Technical Criteria that conform to the provisions of this Section shall not require affirmative City consent; provided, however, that any such variations that the City determines, in its discretion, do not conform to the provisions of this Section shall require the consent of the City. The DBOM Contractor shall notify the City of any variations to the Secondary Technical Criteria and shall clearly show and mark any such variations on the Design Documents submitted to the City pursuant to subsection 5.7(B) (City Review and Comment on Design Documents). The DBOM Contractor shall be responsible for correcting any Design Documents reflecting variations that do not conform to the provisions of this Section unless the City consents to such variations. The City's consent to any such variation shall be reflected in a Contract Administration Memorandum or Change Order, depending on the materiality of the change. Section 5.10. CHANGES TO DESIGN AND CONSTRUCTION REQUIREMENTS GENERALLY. The DBOM Contractor acknowledges the City's material interest in each provision of the Design and Construction Requirements, and agrees that, subject to Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date), no material change to the Design and Construction Requirements shall be made except with the consent of the City,which after taking into account the standards of quality, integrity, durability and reliability established for the Project by the Contract Standards will not be unreasonably withheld, conditioned or delayed. Any such changes shall be evidenced by a Contract Administration Memorandum, DBOM Agreement Amendment, or Change Order, as applicable. Section 5.11. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES MADE AT DBOM CONTRACTOR REQUEST. The DBOM Contractor shall give the City written notice of, and reasonable opportunity to review and comment upon, any Design and Construction Requirement Changes proposed to be made at the DBOM Contractor's request. The notice shall contain sufficient information for the City to determine that the Design and Construction Requirement Change: (1) Does not diminish the capacity of the Project to be operated so as to meet the Contract Standards; 55 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (2) Does not impair the quality, integrity, durability and reliability of the Project; (3) Is reasonably necessary or is advantageous for the DBOM Contractor to fulfill its obligations under this DBOM Agreement; and (4) Is feasible. The City shall review each Design and Construction Requirement Change notice, and have the right in its sole discretion to accept, reject or modify any Design and Construction Requirement Change proposed by the DBOM Contractor. The City shall act in good faith to review such Design and Construction Requirement Change notice as soon as possible following receipt, but shall complete its review within 15 days following receipt of such notice, or as otherwise reasonably agreed to by the parties. Any such Design and Construction Requirement Change accepted or modified by the City, and any related change in the terms and conditions of this DBOM Agreement, shall be reflected in a Change Order. Section 5.12. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES, REPAIRS AND REPLACEMENTS REQUIRED DUE TO RELIEF EVENTS OCCURRING PRIOR TO THE ACCEPTANCE DATE. Upon the occurrence of a Relief Event occurring prior to the Acceptance Date, the DBOM Contractor shall promptly proceed to make or cause to be made any Design and Construction Requirements Changes, repairs and replacements reasonably necessary to address the Relief Event, as provided in Article 14 (Relief Event Procedures), Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. The DBOM Contractor and the City shall consult concerning possible means of addressing and mitigating the effect of the Relief Event, and the DBOM Contractor and the City shall cooperate in order to minimize any delay, lessen any additional cost and repair, replace or modify the Project so as to permit the DBOM Contractor to continue providing the Project Services in light of the Relief Event. The design and construction costs resulting from any work shall be paid by the City through a Fixed Design-Build Price Adjustment as and to the extent provided in Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. Any related operation, maintenance, repair and replacement costs, shall be borne by the City (through an adjustment of the Service Fee payable solely following the Acceptance Date, subject to Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events)), as applicable. Any such Design and Construction Requirement Change and any related change in the terms and conditions of this DBOM Agreement, including schedule, shall be reflected in a Change Order. The DBOM Contractor shall not be required to undertake any Design and Construction Requirement Change under this Section unless and until (1) the parties have agreed upon a scope, price and schedule for the implementation of the Design and Construction Requirement Change in accordance with all applicable provisions of this DBOM Agreement, or (2) the City has agreed to pay the DBOM Contractor on a Cost Substantiation basis pending resolution of, or instead of proceeding to, dispute resolution. Section 5.13. DESIGN AND CONSTRUCTION REQUIREMENT CHANGES MADE AT CITY DIRECTION. The City shall have the right, but not the obligation, to make Design and Construction Requirement Changes at any time prior to the Acceptance Date at its discretion for any reason whatsoever, whether and however the exercise of such rights affects this DBOM Agreement so long as such Design and Construction Requirement Change does not contravene the limitations referred to in Section 4.7 (Restrictions on City-Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes). 56 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction The design and construction costs resulting from any such Design and Construction Requirement Change made at the City's direction under this Section shall be paid directly by the City through a Fixed Design-Build Price Adjustment during the Design-Build Period. Any related operation, maintenance, repair and replacement costs shall be borne by the City through an adjustment to the Service Fee. Any such Design and Construction Requirement Change and any related change in the terms and conditions of this DBOM Agreement, including schedule, shall be reflected in a Change Order. The DBOM Contractor's obligation to perform the work related to a Design and Construction Requirement Change is subject to the conditions set forth in Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date). The DBOM Contractor and the City shall be responsible for the costs of preparing any Design and Construction Requirement Change as and to the extent each party would be responsible for such costs with respect to a Capital Modification proposal, as further described in Section 11.6 (Primary Procedure for Implementing Capital Modifications). Section 5.14. CONSTRUCTION PRACTICE, SAFETY AND SECURITY. (A) Means and Methods. The DBOM Contractor shall perform the Design- Build Work in accordance with the Contract Standards and shall have exclusive responsibility for all construction means, methods, techniques, sequences, and procedures necessary or desirable for the correct, prompt, and orderly prosecution and completion of the Design-Build Work as required by this DBOM Agreement. The responsibility to provide the construction means, methods, techniques, sequences and procedures referred to above shall include the obligation of the DBOM Contractor to provide the following construction requirements: (1) temporary offices and construction trailers; (2) required design certifications; (3) required approvals; (4) weather protection; (5) clean-up and housekeeping of the Project Site; (6) construction trade management; (7) temporary parking; (8) vehicle traffic; (9) safety and first aid facilities and equipment; (10) correction of or compensation for defective work or equipment; (11) Subcontractors' insurance; (12) storage areas; (13) workshops and warehouses; (14) temporary fire protection; (15) security of the Project Site and storage areas; (16) temporary utilities, including electricity; (17) potable water; (18) sanitary services; (19) Subcontractor and vendor qualification; (20) receipt and unloading of delivered materials and equipment; (21) erection rigging; (22) temporary supports; and (23) construction coordination. (B) Safety and Security. The DBOM Contractor shall maintain safety and security at the Project Site at all times at a level consistent with the Contract Standards. Without limiting the foregoing, the DBOM Contractor shall: (1) Take all necessary precautions for the safety and security of the Design- Build Work and provide all necessary protection that is consistent with Good Design- Build Practice and required by Applicable Law to prevent damage, injury or loss caused by trespass, negligence, vandalism, malicious mischief or any other course related to the Design-Build Work, for: (a) workers at the Project Site and all other persons who may be involved with deliveries or inspections; (b) visitors to the Project Site; (c) passersby, neighbors and adjacent properties; (d) materials and equipment under the care, custody or control of the DBOM Contractor or Subcontractors on the Project Site; 57 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (e) other property constituting part of the premises or the Project under construction; and (f) City property; (2) Establish and enforce all necessary safeguards for safety and protection, including posting danger signs and other warnings against hazards; (3) Implement a comprehensive safety program in accordance with Applicable Law; (4) Give all notices and comply with all Applicable Law relating to the safety of persons or property or their protection from damage, injury or loss; (5) Operate and maintain all equipment in a manner consistent with the manufacturer's safety requirements; (6) Provide for safe and orderly vehicular movements; and (7) Develop and implement a written site-specific health and safety plan (the "Health and Safety Plan") that includes management commitment to maintaining a safe workplace, employee participation, hazard evaluation and controls, employee training and periodic inspections which shall: (a) designate an appropriately certified safety professional with a minimum of five years of construction safety experience who is to develop and sign the Health and Safety Plan including all safety rules at the Project Site; (b) designate a qualified safety professional stationed full-time at the Project Site during on-site construction activities whose primary/only duty shall be the implementation of safety rules at the Project Site, the prevention of fires and accidents, monitoring compliance with the Health and Safety Plan, and the coordination of such activities as shall be necessary with the City and all Governmental Bodies having jurisdiction; (c) require all Subcontractors to implement the Health and Safety Plan; and (d) comply with the DBOM Contractor's on-site safety requirements and designate a qualified safety professional whose duty shall be the implementation of safety rules at the Project Site and monitoring compliance of Subcontractor employees with the Health and Safety Plan. Section 5.15. CONSTRUCTION MONITORING, OBSERVATIONS, TESTING AND UNCOVERING OF WORK. (A) Observation and Design Review Program. During the progress of the Design-Build Work through Final Completion, the DBOM Contractor shall at all times afford the City every reasonable opportunity for observing all Design-Build Work, and shall comply with the Design-Build Work review procedures set forth in Appendix 6 (Design-Build Work Review Procedures). The DBOM Contractor shall use all reasonable efforts to provide City employees and representatives with safe access to the Design-Build Work. During any such observation, all employees and representatives of the City shall comply with the Health and Safety Plan for the Design-Build Work applicable to areas visited and all safety instructions or directions made 58 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction by the DBOM Contractor in this respect, and shall not interfere with or delay the DBOM Contractor's performance of any Design-Build Work. (B) DBOM Contractor Tests and Inspections. The DBOM Contractor shall conduct all tests of the Design-Build Work (including shop tests) or inspections required by the Contract Standards; provided, however, that nothing set forth herein shall be construed as requiring the Design-Builder to provide special third party inspection services required pursuant to Oregon State Building Code, and any such inspection services will be conducted by third parties separately engaged by the City. The DBOM Contractor shall give the City reasonable advance notice (at least one Business Day) of tests or inspections prior to the conduct thereof; provided, however, that in no event shall the City's inability, failure or refusal to attend or be present at or during any such test or inspection delay the conduct of such test or inspection or the performance of the Design-Build Work. All analyses of test samples of Effluent or Influent shall be conducted by persons appearing on lists of laboratories authorized to perform such tests by the City or federal agency having jurisdiction and shall be subject to the approval of the City, which approval shall not be unreasonably withheld, conditioned or delayed. (C) City Tests, Observations and Inspections. Subject to the terms of subsection (A) of this Section, the City, its employees, agents, representatives and contractors (which may be selected in the City's discretion) may at any reasonable time and with reasonable notice conduct such on-site observations and inspections, and such civil, structural,mechanical, electrical, chemical, or other tests as the City deems necessary or desirable to ascertain whether the Design-Build Work complies with this DBOM Agreement. Such authorized agents include all third party inspection firms engaged by the City to provide special inspections of the Design- Build Work required pursuant to the Oregon State Building Code. The DBOM Contractor shall be responsible for coordinating, scheduling and cooperating with any such third party inspection firms in connection with the performance of special inspections of the Design-Build Work. The City's costs of any such test, observation or inspection which would not have otherwise been conducted in the normal course of the Design-Build Work shall be borne by the City,unless such test, observation or inspection reveals a material failure of the Design-Build Work to comply with this DBOM Agreement or Applicable Law, in which event the DBOM Contractor shall pay all reasonable costs and expenses of such observation, inspection or test within 30 Business Days of receipt of an invoice from the City. In the event that any such requested test, observation or inspection causes a delay in the construction schedule, the Scheduled Acceptance Date shall be adjusted to reflect the actual period of time needed for completion as directly caused by the requested testing, but only if such testing, observation or inspection does not reveal any material failure or non-compliance as set forth herein. (D) Certificates and Reports. The DBOM Contractor shall secure and deliver to the City promptly, at the DBOM Contractor's sole cost and expense, all required certificates of inspection, test reports, work logs, certified payroll and approvals with respect to the Design- Build Work as and when required by the Contract Standards. The DBOM Contractor shall provide to the City, immediately after the receipt thereof, copies of any notice of default, breach or non-compliance received by the DBOM Contractor under or in connection with any Governmental Approval or Subcontract pertaining to the Design-Build Period. (E) Notice of Covering Design-Build Work. The DBOM Contractor shall give the City reasonable advance notice of its upcoming schedule and upcoming hold points with respect to the covering and completion of any Design-Build Work, and shall update such notice, if necessary, within a reasonable time period before such covering and completion. Such notice shall be given such that the City will have a reasonable opportunity to inspect such Design-Build Work. The City shall give the DBOM Contractor notice of any intended inspection or testing of such Design-Build Work prior to its covering or completion. 59 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (F) Meetings and Design-Build Work Review. During the Design-Build Period, the DBOM Contractor and the City shall conduct periodic meetings in accordance with Appendix 6 (Design-Build Work Review Procedures). (G) City's Third Party Oversight. The City may in its discretion utilize a third party to assist with monitoring, observation and testing of the Design-Build Work. In the event that the City does utilize such a third party, it shall notify the DBOM Contractor of the contact person for such third party and such third party shall have the same rights as the City pursuant to this Section 5.15 (Construction Monitoring, Observations, Testing and Uncovering of Work). Section 5.16. CORRECTION OF DESIGN-BUILD WORK. (A) Correction of Non-Conforming Design-Build Work. Throughout the Design-Build Period, the DBOM Contractor shall promptly complete, repair, replace, restore, re- perform, rebuild and correct any Design-Build Work which does not conform with the Contract Standards. (B) Election to Accept Non-Conforming Design-Build Work. The City may elect by Change Order, at the DBOM Contractor's request, to accept non-conforming Design-Build Work and charge the DBOM Contractor (through a reduction to the Fixed Design-Build Price) an amount agreed upon by the parties by which the value of the DBOM Contractor's services or Design-Build Work has been adversely impacted or reduced, if any. (C) Relation to Other Obligations. The obligations specified in this Section establish only the DBOM Contractor's specific obligation to correct the Design-Build Work and shall not be construed to establish any limitation with respect to any other obligations or liabilities of the DBOM Contractor under this DBOM Agreement. This Section is intended to supplement (and not limit) the DBOM Contractor's obligations under the Acceptance Tests, Acceptance Conditions and any other provisions of this DBOM Agreement or Applicable Law. Section 5.17. WARRANTIES OF DESIGN-BUILD WORK. The DBOM Contractor shall, for the protection of the City, obtain from all Subcontractors and other persons from which the DBOM Contractor procures structures, improvements, fixtures, machinery, equipment and materials to be incorporated in the Project such warranties and guarantees as are normally provided with respect thereto or, to the extent superior in scope or length, as are specifically required in Appendix 4 (Design and Construction Requirements), Appendix 5 (Secondary Technical Criteria) and the Contract Standards, each of which shall be assigned to the City and be enforceable by the DBOM Contractor to the full extent of the terms thereof. No such warranty shall relieve the DBOM Contractor of any obligation hereunder, and no failure of any warranted or guaranteed structures, improvements, fixtures, machinery, equipment or material shall be the cause for any increase in the Design-Build Price or the Service Fee or excuse any non-performance of the Project Design-Build Work unless such failure is itself attributable to a Relief Event. The DBOM Contractor shall enforce such warranties and guarantees as provided in 9.15 (Enforcement of Project Warranties). Section 5.18. COMMISSIONING. The DBOM Contractor shall comply with the Commissioning requirements of Appendix 8 (Commissioning and Acceptance Testing) and shall, as provided therein: (1) Prepare a detailed Commissioning Plan, meeting the minimum requirements set forth in Appendix 8 (Commissioning and Acceptance Testing); and 60 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (2) Conduct Commissioning activities in accordance with the Commissioning Plan and Appendix 8 (Commissioning and Acceptance Testing). Section 5.19. SUBSTANTIAL COMPLETION. (A) Conditions to Substantial Completion. "Substantial Completion" shall occur only when all of the following conditions have been satisfied except to the extent that any such conditions have been waived by the City: (1) Construction of the Project is physically complete and all Design-Build Work pertaining to the Project, except the Acceptance Tests and the items on the proposed Punch List, is complete and in all respects is in compliance with this DBOM Agreement; (2) The Project Equipment is installed such that the Project Equipment is ready for use and defect free, except for Punch List Items; (3) All Governmental Approvals, including the NPDES Permit, necessary to commence the Operation and Maintenance Services have been acquired; (4) All Utilities specified or required under this DBOM Agreement to be arranged for by the DBOM Contractor are connected and functioning properly; (5) The DBOM Contractor shall have provided a proposed Punch List for the City's review in accordance with Section 6.4 (Punch List Items); (6) The DBOM Contractor has delivered to the City written certification from the equipment manufacturers (including manufacturers of information technology systems and instrumentation and controls) that all major items of machinery and equipment included in the Project have been properly installed and tested in accordance with the manufacturers'recommendations and requirements; (7) The DBOM Contractor has delivered to the City a claims statement setting forth in detail all known claims of every kind whatsoever of the DBOM Contractor connected with, or arising out of, the Design-Build Work, and arising out of or based on events prior to the date when the DBOM Contractor gives such statement to the City; (8) The DBOM Contractor has delivered to the City the initial draft Operation and Maintenance Manual in accordance with Section 8.3 (Operation and Maintenance Manual and Operation and Maintenance Plan); (9) The DBOM Contractor is authorized to conduct the Acceptance Tests and to operate the Project under Applicable Law, and such authorization has not been withdrawn, revoked, superseded, suspended, or materially impaired or amended; (10) The DBOM Contractor has submitted its personnel training program in accordance with the requirements set forth in subsection 8.4(B) (Training); (11) The DBOM Contractor has submitted its emergency action plan in accordance with the requirements set forth in subsection 8.12(A) (Emergency Plan); and (12) The DBOM Contractor has submitted written certification that all of the foregoing conditions have been satisfied. 61 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 5 DBOM Agreement Design and Construction (B) Notice of Substantial Completion. The DBOM Contractor shall give the City Representative at least 30 days prior written notice of the expected date of Substantial Completion. 62 3935946.13 043463 ARTICLE 6 ACCEPTANCE Section 6.1. ACCEPTANCE TESTING. (A) Submittal of Acceptance Test Plan. Upon the earlier of ODEQ requiring such final plan or 150 days prior to the commencement of Commissioning, the DBOM Contractor shall prepare and submit to the City for its approval a detailed Acceptance Test Plan as part of the final Commissioning Plan, which shall conform to the requirements set forth in Appendix 8 (Commissioning and Acceptance Testing) and in Attachment 8A (Preliminary Commissioning Plan). (B) Acceptance Test Plan. The Acceptance Test Plan shall set forth in detail all procedures to be used, all specific measurements to be made, the proposed usage of permanent and temporary instrumentation, the organization of the test team, the testing schedule (including the estimated date, time and duration of each test) and the operating and maintenance schedule during testing. The Acceptance Test Plan shall also make provision for measuring and determining the effluent output from the Project Facilities and shall make provision for the determination of compliance of the Project with the requirements of Applicable Law. (C) Notice of Commencement of the Acceptance Tests. The DBOM Contractor shall provide the City with at least 30 days' prior written notice of the expected initiation of the Acceptance Tests in accordance with the requirements of Appendix 8 (Commissioning and Acceptance Testing). At least 10 days prior to the actual commencement of Acceptance Testing, the DBOM Contractor shall certify in writing that it is ready to begin Acceptance Testing in accordance with the Acceptance Test Plan and Appendix 8 (Commissioning and Acceptance Testing). (D) Conditions to Commencement of the Acceptance Tests. The DBOM Contractor shall not commence the Acceptance Tests until the following events have occurred: (1) Substantial Completion has been achieved; (2) The requirements of subsections (A) and (B) of this Section have been met and the City has approved the Acceptance Test Plan; (3) The DBOM Contractor has received specific authorization from all applicable Governmental Bodies necessary to commence the performance of the Acceptance Tests and has provided evidence of such authorization to the City; and (4) The DBOM Contractor has certified that it has complied with the pre- Acceptance Testing requirements of Appendix 8 (Commissioning and Acceptance Testing). (E) Conduct of the Acceptance Tests. The DBOM Contractor shall conduct the Acceptance Tests in accordance with Appendix 8 (Commissioning and Acceptance Testing) and the Acceptance Test Plan, and shall notify the City when the Acceptance Tests are scheduled to occur in accordance with subsection (C) of this Section. The DBOM Contractor shall permit any designated representatives of the City to inspect the preparations for the Acceptance Tests and to be present for the conduct of the Acceptance Tests for purposes of ensuring compliance with the Acceptance Test Plan and the integrity of the Acceptance Test results. Following the completion of the Acceptance Tests and prior to the Acceptance Date, the DBOM Contractor shall maintain the Project in accordance with the Contract Standards. 63 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance (F) Acceptance Test Report. Within 10 Business Days following conclusion of the Acceptance Tests, the DBOM Contractor shall furnish the City with copies of a certified written Acceptance Test report consistent with the requirements specified in Appendix 8 (Commissioning and Acceptance Testing), certified as true, complete and correct by the DBOM Contractor and the engineer-of-record. The Acceptance Test report shall describe and certify: (1) the Acceptance Tests conducted; (2) the results of the Acceptance Tests; (3) the level of satisfaction of the Acceptance Standards; and (4) the level of satisfaction of all Acceptance Conditions set forth in Section 6.2 (Acceptance Conditions). The written test report shall include copies of the original data sheets, log sheets and all calculations used to determine performance during the Acceptance Tests, and copies of laboratory reports conducted in conjunction with the Acceptance Tests, including all laboratory sampling and test results. There shall be no adjustment to the Scheduled Acceptance Date and no extension of the Longstop Date if the DBOM Contractor fails to timely furnish the certified Acceptance Test report within the 10 Business Day period following the conclusion of the Acceptance Tests. Section 6.2. ACCEPTANCE CONDITIONS. The following conditions shall constitute the "Acceptance Conditions", each of which shall be and remain satisfied in all material respects by the DBOM Contractor in order to achieve Acceptance and establish the Acceptance Date: (1) Substantial Completion. Substantial Completion has occurred; (2) Achievement of the Acceptance Standards. The DBOM Contractor has completed the Acceptance Tests and such tests have demonstrated that the Project has achieved the Acceptance Standards, as certified by the DBOM Contractor pursuant to subsection 6.1(F) (Acceptance Test Report); (3) Punch List. The DBOM Contractor and the City have agreed in writing upon the Punch List in accordance with Section 6.4 (Punch List Items) (or, if they are unable to agree, the City shall have prepared and issued the Punch List to the DBOM Contractor within 30 days of the DBOM Contractor having submitted its proposed Punch List to the City); (4) Operating Governmental Approvals. All Governmental Approvals required under Applicable Law, which are necessary to commence and continue routine operation of the Project (including the NPDES Permit) have been duly obtained by the DBOM Contractor and are in full force and effect. Certified copies of all such Governmental Approvals, to the extent not in the City's possession, have been delivered to the City; (5) No Encumbrances. There are no Encumbrances registered or recorded on the Project Site or any part of the Project other than Permitted Encumbrances; (6) Required Operation and Maintenance Period Insurance. The DBOM Contractor has obtained and submitted to the City certificates of insurance for all Required Operation and Maintenance Period Insurance that the DBOM Contractor is obligated to obtain in accordance with Section 13.1 (Insurance) and Appendix 12 (Insurance Requirements); (7) Operation and Maintenance Letter of Credit. The DBOM Contractor has obtained and submitted to the City the Operation and Maintenance Letter of Credit, as required by and in accordance with Section 18.3 (Operation and Maintenance Letter of Credit); and 64 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance (8) Operation and Maintenance Plan and Operation and Maintenance Manual. The DBOM Contractor has delivered to the City the final Operation and Maintenance Manual and the final Operation and Maintenance Plan, which shall be subject to City review and comment before being finalized and shall be consistent with the Preliminary Operation and Maintenance Plan set forth in Attachment 10B (Preliminary Operation and Maintenance Plan) to Appendix 10 (Operation and Maintenance Requirements). Section 6.3. ACCEPTANCE CERTIFICATE. (A) Generally. The City shall no later than 10 Business Days following receipt of the Acceptance Test report described in subsection 6.1(F) (Acceptance Test Report), determine whether to issue the Acceptance Certificate in accordance with this DBOM Agreement. (B) Certificate Issuance. If the City determines that the Acceptance Conditions have been satisfied, the City shall deliver, within 10 Business Days from the receipt of the Acceptance Test report described in subsection 6.1(F) (Acceptance Test Report), a signed Acceptance Certificate to the DBOM Contractor. If the City concurs with the Design-Builder's certification by issuance of the Acceptance Certificate, the Acceptance Date shall be deemed to have been established on the date of the Design-Builder's original certification in the Acceptance Test report. (C) Deficiencies. If the City determines that any of the Acceptance Conditions have not been satisfied, the City shall identify any deficiencies (or necessary clarifications that are required to determine if such Acceptance Conditions have been met) in a written report delivered as soon as possible but no later than 10 Business Days following the date of the receipt of the Acceptance Test report described in subsection 6.1(F) (Acceptance Test Report). In the event the DBOM Contractor, in conducting the Acceptance Tests, does not successfully meet the Acceptance Standards, the DBOM Contractor shall, at its sole cost and expense, take all action necessary(including making all capital investments, improvements or modifications, repairs and replacements and operating and management practice changes) in order for the Project to comply with the Acceptance Standards and shall re-test the Project in accordance with Appendix 8 (Commissioning and Acceptance Testing). The DBOM Contractor shall provide the City with at least seven days'written notice of any repetition of the Acceptance Tests. Any capital investment, improvement or modification required to be made pursuant to this subsection, and reasonably expected to result in a change to the Design and Construction Requirements, shall be subject to the City's rights under Section 5.11 (Design and Construction Requirement Changes Made at DBOM Contractor Request). Following a repeat of all or part of the Acceptance Tests, the DBOM Contractor shall issue a revised Acceptance Test report and certify Acceptance, all in accordance with the provisions hereof with respect to the original Acceptance Tests. If the City does not send a deficiency notice or request for clarification within 20 Business Days of the receipt of the Acceptance Test report described in subsection 6.1(F) (Acceptance Test Report), the City will be deemed to have determined that the Acceptance Conditions have been satisfied. (D) Effect of Issuance. Subject to the last sentence of subsection (C) of this Section, the Acceptance Certificate shall establish the Acceptance Date and, subject to subsections 6.3(E)(1) and 6.3(F), be final and binding on the City and the DBOM Contractor with respect to the occurrence of the Acceptance Date and the commencement of Service Fee payments in accordance with Article 17 (Service Fee and Other Payments). (E) Matters Not Affected By Certificate Issuance. Neither the issuance of the Acceptance Certificate, nor any use by the City of any part of the Project under the terms of this DBOM Agreement, shall: 65 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance (1) Limit the obligations of the DBOM Contractor under this DBOM Agreement, including its obligation to complete the Design-Build Work in accordance with this DBOM Agreement and to remedy any defects, deficiencies or items of outstanding Design-Build Work existing or discovered prior to or after the date of the Acceptance Certificate or the date of the Punch List; (2) Be construed as an approval by the City of the Project or the manner in which the Design-Build Work has been carried out by the DBOM Contractor; or (3) Have any effect other than as specified in subsection (D) of this Section. The City shall retain all of its rights with respect to any matter not affected by the issuance of the Acceptance Certificate. (F) Disputes Regarding Acceptance Determination. Any dispute in connection with the final determination of whether or not to issue an Acceptance Certificate shall, unless otherwise agreed to in writing by the parties, be resolved in accordance with Article 19 (Dispute Resolution). Section 6.4. PUNCH LIST ITEMS. (A) Punch List. The DBOM Contractor shall, as a condition to the achievement of Substantial Completion, prepare a list of all Punch List Items (the "Punch List") identified at that time and an estimate of the cost and the time for rectifying such Punch List Items. The City shall not withhold the Acceptance Certificate by reason solely that there are Punch List Items. The Punch List shall be a statement of repairs, corrections and adjustments to the Design-Build Work, and incomplete aspects of the Design-Build Work, which: (1) The DBOM Contractor can complete before the Final Completion deadline provided in Section 6.8 (Final Completion), and with minimal interference to the occupancy and use of the Project; and (2) Would represent, to perform or complete, a total cost of not more than 1% of the Design-Build Price (unless the City determines that a higher percentage is acceptable). In no event shall the Punch List contain any incomplete items necessary for full Project operations. The City shall have the right to approve the final Punch List. (B) Minimal Impact on Project Operations. The DBOM Contractor shall prepare a reasonable schedule for the completion and rectification of the Punch List Items. In determining the relevant time for rectifying Punch List Items, the DBOM Contractor shall schedule the completion and rectification of Punch List Items so as to minimize, to the greatest extent reasonably possible, disruption of the Operation and Maintenance Services. (C) Waiver of Acceptance Requirements. The City may, in its discretion, waive any Acceptance Condition completely, or waive a condition as a requirement of Acceptance but include it as a requirement of Final Completion. (D) Rectification of Punch List Items. The DBOM Contractor shall complete and rectify all Punch List Items within 180 days of the Acceptance Date or such longer period as the City may specify in the Punch List. Completion of the Punch List work shall be verified by a final walk-through of the Project conducted by the City and the City Representative with the DBOM Contractor and the Design-Build Project Manager. 66 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance (E) Failure to Rectify Punch List Items. In the event that the DBOM Contractor fails to complete and rectify the Punch List Items specified in the Punch List within the time period specified pursuant to subsection (D) of this Section: (1) The City may withhold from the retained City Contribution funds a holdback amount that is 200% of the amount reasonably estimated by the City to complete and rectify the Punch List Items (to the extent then outstanding) in accordance with subsection 7.5(E) (Retainage); and (2) The City may engage others to perform the work necessary to complete and rectify the Punch List Items, at the risk and cost of the DBOM Contractor, and the City may deduct such cost from the holdback amount set forth in subsection Section 6.4(E)(1) of this Section. Upon completion and rectification of all of the Punch List Items pursuant to this subsection, the City shall release to the DBOM Contractor the then-remaining amount of the holdback. If the cost of such completion and rectification exceeds the amount of such holdback, then the DBOM Contractor shall reimburse the City for all such excess cost. Section 6.5. SCHEDULED ACCEPTANCE DATE AND LONGSTOP DATE. (A) Scheduled Acceptance Date Defined. The "Scheduled Acceptance Date" is the date that is 1,764 days following the Design-Build Work NTP Date, as such date may be extended as provided in subsection (C) of this Section. In the event of any such adjustment, delay liquidated damages payable by the DBOM Contractor under subsection 6.6(A) (Delay Liquidated Damages), if any, shall be payable from the adjusted Scheduled Acceptance Date. (B) Longstop Date Defined. The "Longstop Date" is the date 180 days following the Scheduled Acceptance Date, as such date may be extended as provided in subsection (C) of this Section. (C) Extension for Relief Events. If a Relief Event occurs between the Effective Date and the Longstop Date, the Scheduled Acceptance Date (if such Relief Event occurs prior to the Scheduled Acceptance Date) and the Longstop Date shall be extended for such time as is reasonable in the circumstances to take account of the effect of the delay on any critical path matter in the Project Schedule caused by the Relief Event. Section 6.6. FAILURE TO ACHIEVE ACCEPTANCE BY THE SCHEDULED ACCEPTANCE DATE. (A) Delay Liquidated Damages. In the event the DBOM Contractor fails to achieve Acceptance by the Scheduled Acceptance Date, the DBOM Contractor shall pay delay liquidated damages to the City in the amount of $10,000 for each day of delay in achieving Acceptance until this DBOM Agreement is terminated. Such delay liquidated damages shall accrue daily and shall be payable monthly on the first Business Day of each month immediately following the month during which they have been incurred. The aggregate liability of the DBOM Contractor, with respect to any delay liquidated damages payable pursuant to this subsection shall not exceed an amount equal to 10% of the Design-Build Price. (B) Re-Testing. During any period of delay in achieving Acceptance, the DBOM Contractor shall be entitled to make any reasonably necessary improvements or modifications to the Project, and to conduct or repeat the Acceptance Tests as often as it determines to be appropriate in order to secure Acceptance of the Project by the Longstop Date in accordance with Appendix 8 (Commissioning and Acceptance Testing), all subject to (1) the 67 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance rights of the City under Section 5.11 (Design and Construction Requirement Changes Made at DBOM Contractor Request), and (2) the City's right to terminate this DBOM Agreement in accordance with Section 6.7 (Failure to Achieve Acceptance by the Longstop Date). (C) No City Contribution Payments for Acceptance Prior to Acceptance Date. In no event shall the DBOM Contractor be entitled to the payment of any portion of the Design- Build Price associated with the achievement of Acceptance under Article 7 (Payment for the Design-Build Work), if applicable, until the DBOM Contractor has actually achieved Acceptance in accordance with this Article 6 (Acceptance). Section 6.7. FAILURE TO ACHIEVE ACCEPTANCE BY THE LONGSTOP DATE. In the event the DBOM Contractor fails to satisfy the Acceptance Conditions by the Longstop Date, a DBOM Contractor Event of Default hereunder shall be deemed to have occurred, and the City may pursue all remedies available under Article 20 (Remedies of the Parties and City Step-In Rights) and Article 23 (Termination) in accordance with the terms thereof. Section 6.8. FINAL COMPLETION. (A) Requirements. "Final Completion" shall occur when all of the following conditions have been satisfied: (1) Acceptance. The DBOM Contractor has achieved Acceptance in accordance with this Article 6 (Acceptance); (2) Design-Build Work Completed. All Design-Build Work (including all items on the Punch List) is complete and in all respects is in compliance with this DBOM Agreement; (3) Deliverable Material. The DBOM Contractor shall have delivered to the City all Deliverable Material required by subsection 5.1(H) (Deliverable Material); (4) Equipment Warranties and Manuals. The DBOM Contractor shall be in possession of, and shall have delivered to the City, copies of the warranties of equipment and fixtures constituting a part of the Project required to be obtained under Section 5.17 (Warranties of Design-Build Work), together with copies of all related operating manuals supplied by the equipment supplier; (5) Spare Parts In Storage. All spare parts required by the applicable Design and Construction Requirements have been delivered and are in storage at the Project; (6) Record Drawings. The DBOM Contractor has delivered to the City a final and complete red-lined set and as-built set of construction record drawings; (7) Equipment Manufacturers' Certificate. The DBOM Contractor has delivered to the City written certification from the equipment manufacturers (including manufacturers of information technology systems and instrumentation and controls) that all major items of machinery and equipment included in the Project have been properly installed and tested in accordance with the manufacturers' recommendations and requirements; (8) Claims Statement. The DBOM Contractor has delivered to the City a claims statement setting forth in detail all outstanding claims known to it of every kind 68 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 6 DBOM Agreement Acceptance whatsoever of the DBOM Contractor connected with, or arising out of, the Design-Build Work, and arising out of or based on events prior to the date when the DBOM Contractor gives such statement to the City; (9) Baseline Project Record. The DBOM Contractor shall have furnished to the City the Baseline Project Record and record documentation required by subsection 10.3(B) (Baseline Project Record); and (10) Written Certification. The DBOM Contractor has submitted written certification that all of the foregoing conditions have been satisfied and the City has approved the DBOM Contractor's certification, which approval shall be effective as of the date of the DBOM Contractor's certification. Alternatively, Final Completion shall occur on any date certified by the City, which shall have discretion to waive any of the foregoing conditions. (B) Obligation to Achieve Final Completion; Punch List Items. The DBOM Contractor shall achieve Final Completion, and shall complete and rectify all Punch List Items as provided in Section 6.4 (Punch List Items), within 180 days after the Acceptance Date. In the event that Final Completion is not achieved within such period, the DBOM Contractor shall pay to the City daily delay liquidated damages in accordance with this subsection for each day that the date of Final Completion falls after the final day of such period. The amount of daily delay liquidated damages payable by the DBOM Contractor pursuant to this subsection shall be $5,000 for each day of delay in achieving Final Completion. Such damages shall be payable on the first day of each month. The aggregate liability of the DBOM Contractor, with respect to any liquidated damages payable pursuant to this subsection and subsection 6.6(A) (Delay Liquidated Damages) shall not exceed the limit set forth in subsection 6.6(A) (Delay Liquidated Damages). 69 3935946.13 043463 ARTICLE 7 PAYMENT FOR THE DESIGN-BUILD WORK Section 7.1. PROJECT DESIGN AND CONSTRUCTION COSTS AND FINANCING. The City intends to secure the availability of all funds necessary to pay the Design- Build Price in a timely manner. The City may fund the Design-Build Price (i) through a WIFIA loan as further described in Section 4.5(G) (Water Infrastructure Finance and Innovation Act (WIFIA)), (ii) through proceeds of general obligations or revenue obligations of the City, (iii) through currently available funds or (iv) otherwise as determined by the City. The DBOM Contractor shall cooperate with and assist the City in providing any information, certifications or documents, and in attending meetings, hearings or forums, which may be reasonably required in connection with obtaining the funds necessary to pay the Design-Build Price and shall comply with all requirements necessary for the City to obtain State and federal funding including the requirements set forth in Appendix 3 (Certain Federal Requirements). Payments of the Design- Build Price shall be made by the City to the DBOM Contractor in the manner provided in this Article. Section 7.2. PAYMENT FOR DESIGN-BUILD WORK GENERALLY. (A) Design-Build Price. The DBOM Contractor shall be entitled to receive the Design-Build Price from the City for properly performed and completed Design-Build Work on a progress basis during the Design-Build Period in accordance with the terms of this Article. The Design-Build Price shall be the Fixed Design-Build Price, as adjusted by any Fixed Design-Build Price Adjustments set forth in subsection Section 7.3(B) (Fixed Design-Build Price Adjustments). The DBOM Contractor shall not be entitled to any compensation for costs or expenses incurred, or Design-Build Work performed, prior to the Design-Build Work NTP Date. (B) Limitation on Payments for Costs of the Design-Build Work. The Design- Build Price shall be the DBOM Contractor's entire compensation and reimbursement from the City for the performance of the Design-Build Work including the payment of any Taxes in connection with the Design-Build Work, obtaining all Utilities that the DBOM Contractor will require to perform the Design-Build Work as and to the extent provided in subsection 5.1(Q) (Utilities), Commissioning and starting up the Project, operating and maintaining the Project during the Acceptance Tests and prior to the Acceptance Date and correcting all nonconforming Design-Build Work, all in accordance with the terms and conditions of this DBOM Agreement. In no event shall the DBOM Contractor be entitled to any payment from the City for Design-Build Work costs in excess of the amount payable by the City with respect to the Design-Build Price notwithstanding any cost overruns the DBOM Contractor may incur. (C) No Service Fee Payment Prior to Acceptance. Prior to the Acceptance Date, the DBOM Contractor shall not be entitled to payment of the Service Fee. All costs for design, construction through Final Completion, permitting, Commissioning, start-up, Acceptance Testing, and operations prior to the Acceptance Date, including costs for labor, materials, chemicals and Utilities for which the City is responsible hereunder prior to the achievement of Acceptance by the DBOM Contractor are included in the Fixed Design-Build Price, which shall be payable to the DBOM Contractor in accordance with this Article. Section 7.3. DESIGN-BUILD PRICE. (A) Fixed Design-Build Price. The "Fixed Design-Build Price" is $372,621,065. The Fixed Design-Build Price is the amount payable by the City for all Design- 70 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work Build Work. Except as provided in subsection (B) of this Section, the Fixed Design-Build Price shall not be subject to adjustment in any manner whatsoever. (B) Fixed Design-Build Price Adjustments. Each adjustment to the Fixed Design-Build Price provided for in this subsection shall be deemed a "Fixed Design-Build Price Adjustment" and shall be reflected in a Change Order. The Fixed Design-Build Price Adjustment shall be adjusted only for the following: (1) Adjustment for Change Orders. The Fixed Design-Build Price shall be adjusted to account for the cost of any Change Orders issued by the City with respect to Design and Construction Requirements Changes or otherwise pursuant to and to the extent provided in Section 5.10 (Changes to Design and Construction Requirements Generally), Section 5.11 (Design and Construction Requirement Changes Made at DBOM Contractor Request), Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date) and Section 5.13 (Design and Construction Requirement Changes Made at City Direction), as applicable. (2) Adjustment for Uncontrollable Circumstances. The Fixed Design-Build Price shall be adjusted to account for costs resulting from Relief Events not reflected in item (1) above, as and to the extent provided in Article 14 (Relief Event Procedures),Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. (3) Adjustment for Equipment and Material Cost Escalation. The Fixed Design-Build Price shall be adjusted to account for fluctuations in the unit costs of the equipment and materials indicated in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), as such Appendix is updated in accordance with this subsection. No later than 90 days after the Design-Build Work NTP Date, the DBOM Contractor shall provide an update to Appendix 22 (Equipment and Materials Subject to Cost Adjustment) that provides in reasonable detail the description of the equipment or material that was the basis of the per unit or lump sum pricing(with all lump sum pricing updated to reflect a per unit price) and the anticipated buy-out dates for of each line item set forth therein for equipment and material costs that are subject to adjustment pursuant to this subsection. The updated Appendix 22 (Equipment and Materials Subject to Cost Adjustment) shall be subject to the approval of the City, which approval shall not be unreasonably withheld, conditioned or delayed. The approved updated Appendix 22 (Equipment and Materials Subject to Cost Adjustment) shall be set forth in a Contract Administration Memorandum. Appendix 22 (Equipment and Materials Subject to Cost Adjustment) establishes a pricing benchmark based on the design status at the time of estimate and materials reasonably required for the Design-Build Work. Items may be refined, added, substituted, resized, or reconfigured through design development, and shall remain eligible for adjustment when reasonably attributable to the identified benchmark categories and with appropriate justification provided by the DBOM Contractor and approval by the City. Any further updates to Appendix 22 (Equipment and Materials Subject to Cost Adjustment) agreed to by the parties due to design development or otherwise shall be set forth in subsequent Contract Administration Memoranda. (a) Equipment/Materials Cost Adjustments for Cost Increases. In the event the actual per unit dollar value for a particular item of equipment or material is greater than the per unit dollar value benchmark for its line item set forth in the column titled "UC" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), the DBOM Contractor shall be entitled to a Fixed Design-Build Price Adjustment as follows: 71 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work (i) Items Valued at Less than $1,000,000. For each particular item of equipment or material with a total benchmark dollar value for its line item set forth in the column titled "Direct Cost (August 2026)" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) of less than $1,000,000, the Fixed Design-Build Price Adjustment shall be an amount equal to: (x) the difference between the actual per unit dollar value for the equipment or material and the per unit dollar value benchmark for its line item set forth in the column titled"UC"in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) multiplied by the quantity for its line item set forth in the column titled "QTY" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), plus (y) a mark- up in accordance with subsection 26.7(E) (Mark-Ups). (ii) Items Valued at Greater than $1,000,000. For each particular item of equipment or material with a total benchmark dollar value for its line item set forth in the column titled "Direct Cost (August 2026)" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) equal to or greater than $1,000,000, the Fixed Design-Build Price Adjustment shall be an amount equal to: (x) the difference between the actual per unit dollar value for the equipment or material and the per unit dollar value benchmark for its line item set forth in the column titled "UC" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) multiplied by the quantity for its line item set forth in the column titled "QTY" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), plus (y) a mark-up in accordance with subsection 26.7(E) (Mark-Ups); provided, however, that such Fixed Design-Build Adjustment shall be reduced by 50% in the event that the direct cost for such equipment or material, calculated by multiplying the actual per unit dollar value by the actual quantity of such equipment or material, is less than the benchmark dollar value for such equipment or material set forth in the column titled "Direct Cost (August 2026)" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment). For the avoidance of doubt, the DBOM Contractor shall not be entitled to a Fixed Design-Build Price Adjustment for any excess amount (i) attributable to quantities of the equipment or material greater than the benchmark amount for its line item set forth in the column titled "QTY" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) or (ii) resulting from a change to the description of the item of equipment or material described in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) (except as agreed to by the parties in a Contract Administration Memorandum). (b) Equipment/Materials Cost Adjustments for Cost Decreases. In the event the actual per unit dollar value for a particular item of equipment or material is lower than the per unit dollar value benchmark for its line item set forth in the column titled "UC" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), the City shall be entitled to a deductive Fixed Design-Build Price Adjustment in an amount equal to the difference between the per unit benchmark dollar value set forth in the column titled "UC" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) and the actual per unit dollar value incurred, multiplied by the quantity set forth in the column titled "QTY" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) for the particular item of equipment or material. 72 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work (c) Implementation of Equipment/Materials Cost Adjustments. Following completion of the buy-out of a particular item of equipment or material indicated in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), the DBOM Contractor shall submit a detailed accounting setting out (i) the increase or decrease in the actual per unit dollar value for the item of equipment or material against the per unit dollar value benchmark for its line item set forth in the column titled "UC" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), (ii) the actual aggregate costs for the item of equipment or material against the benchmark dollar value for its line item set forth in the column titled "Direct Cost (August 2026)" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) for each particular item of equipment or material with a total benchmark dollar value for its line item set forth in the column titled "Direct Cost (August 2026)" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) equal to or greater than $1,000,000, (iii) the actual quantity of the item of equipment or material purchased against the benchmark quantity amount for its line item set forth in the column titled "QTY" in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) for each particular item of equipment or material with a total benchmark dollar value for its line item set forth in the column titled"Direct Cost (August 2026)"in Appendix 22 (Equipment and Materials Subject to Cost Adjustment) equal to or greater than $1,000,000, and (iv) the value of the cost increase due the DBOM Contractor or the savings credit due the City in accordance with this subsection. The detailed accounting shall be in a format reasonably acceptable to the City and be accompanied by copies of such documentation as shall be necessary to reasonably demonstrate the actual unit and aggregate costs incurred for the equipment and materials, including copies of invoices, canceled checks, expense reports, receipts and other documents, as appropriate. The detailed accounting shall be submitted to the City in one or more reconciliation packages following completion of the buy- out of particular items of equipment or material and shall be subject to the approval of the City. Any such City approval providing for a Fixed Design-Build Price Adjustment shall be reflected in a Contract Administration Memorandum. (d) Equipment/Materials Cost Adjustments Records and Final Reconciliation. The DBOM Contractor shall keep, and provide to the City upon request, a working reconciliation log identifying the information required pursuant to clause (c) of this subsection for each item of equipment and material indicated in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), including whether any adjustments pursuant to this subsection have been reviewed and approved by the City, and an ongoing record of the costs incurred for those items of equipment and materials as required by clause (c) of this subsection. On or prior to the Acceptance Date following buy-out of all equipment and materials indicated in Appendix 22 (Equipment and Materials Subject to Cost Adjustment), the DBOM Contractor shall provide to the City a reconciliation statement including (i) a confirmation (or re-calculation, if necessary) of the information required to be provided pursuant to clause (c) of this subsection (including all supporting documentation if not previously provided to the City) for all items of equipment and materials and (ii) a reconciliation of the Fixed Design- Build Price Adjustments implemented at such time pursuant to Contract Administration Memoranda, any necessary adjustments thereto, and any outstanding Fixed Design-Build Price Adjustment that needs to be implemented in accordance with this subsection. At a time agreed to by the parties following the DBOM Contractor's submittal of the reconciliation statement, the DBCOM Contractor and the City shall meet to determine any further Fixed Design-Build Price Adjustment on account of excess costs incurred by the DBOM Contractor or savings credits due to the City based upon changes to unit prices, and, if 73 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work necessary, enter into a Contract Administration Memorandum providing for a final reconciled Fixed Design-Build Price Adjustment pursuant to this subsection. In the event the City is owed a credit that exceeds the amount of the outstanding Design-Build Price at the time of reconciliation, the DBOM Contractor shall pay such amount to the City within 60 days after the execution of the Contract Administration Memorandum providing for the final reconciled Fixed Design- Build Price Adjustment. Section 7.4. [RESERVED]. Section 7.5. PAYMENT PROCEDURE. (A) Progress Payments. The DBOM Contractor shall be paid the Design-Build Price for the performance of Design-Build Work on a progress payment basis in accordance with the Design-Build Price Schedule of Values and the terms and conditions of this Section. The DBOM Contractor shall submit monthly Requisitions for requests of progress payments with respect to the Design-Build Price unless otherwise agreed to in writing by the City. (B) Draft Requisitions. Prior to the submission of each Requisition, the DBOM Contractor shall provide the City with a draft Requisition and the DBOM Contractor and the City shall meet to review the DBOM Contractor's draft Requisition and estimate of the percentage of Design-Build Work completed in accordance with the Project Schedule and the Design-Build Price Schedule of Values, as applicable. (C) Construction Disbursement Procedure. Following each meeting described in subsection (B) of this Section, the DBOM Contractor shall be entitled to submit Requisitions and receive from the City the payments, which (i) shall be made based on a percentage of work completed for each month in accordance with the Design-Build Price Schedule of Values, (ii) shall be subject to the maximum monthly drawdown limitations specified in the Design-Build Price Maximum Drawdown Schedule set forth in Appendix 9 (Design-Build Work Schedule of Values and Maximum Drawdown Schedule), and (iii) shall be subject to the conditions to payment set forth in this Section; provided, however, that, on the Acceptance Date, the DBOM Contractor shall be entitled to receive all payments due for completed Design-Build Work (which is unencumbered) that remains unpaid as of such date except for the payment conditioned on achievement of Final Completion. For clarity, the maximum monthly drawdown limitations specified in Appendix 9 (Design-Build Work Schedule of Values and Maximum Drawdown Schedule) shall apply to the cumulative payments requested with respect to the Design-Build Price. Each Requisition must be accompanied by a monthly requisition report, which shall include: (1) a reasonably detailed description of all Design-Build Work actually completed to date and the Design-Build Work expected to be completed in the upcoming month; (2) revisions to the Project Schedule (or a revised Project Schedule) which shall reflect changes in the DBOM Contractor's critical path schedule since the date of the last Requisition; (3) Monthly Progress Reports in accordance with Appendix 7 (General Design-Build Work Requirements); (4) a signed and sealed certificate of an authorized representative of the DBOM Contractor certifying (a) the portion of the Design-Build Price which is payable to the DBOM Contractor, (b) that the DBOM Contractor is neither in default under this 74 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work DBOM Agreement nor in breach of any material provision of this DBOM Agreement such that the breach would, with the giving of notice or passage of time, constitute a DBOM Contractor Event of Default, and (c) that all items applicable to the Design-Build Work entitling the DBOM Contractor to the requested payment under the Design-Build Price Schedule of Values have been completed in accordance therewith and with the Design and Construction Requirements; (5) a verified statement setting forth the information required under any Applicable Law and Appendix 3 (Certain Federal Requirements) pertaining to prevailing wages; (6) notice of any Encumbrances which have been filed together with evidence that the DBOM Contractor has discharged or bonded against any such Encumbrances; and (7) other documents or information relating to the Design-Build Work as may be reasonably requested by the City or as may be required by Applicable Law, this DBOM Agreement or GAAP. The City shall review each Requisition, which must be submitted by the fifth day of the month following completion of the Design-Build Work in the previous month. If the City determines that the Design-Build Work has progressed as indicated in the Requisition, the City shall pay the DBOM Contractor all amounts due within 15 days following such determination (but in no event later than 30 days after the City's original receipt of the Requisition, subject to the City's right to dispute payment in accordance with this DBOM Agreement and Applicable Law). Disputes regarding payments of the Design-Build Price shall be resolved in accordance with subsection (D) of this Section. The City shall pay any undisputed amounts of the Design-Build Price in accordance with this DBOM Agreement and Applicable Law. The DBOM Contractor shall provide the City with an explanation of any amounts disputed or otherwise held back from payment to any of its Subcontractors. (D) Disbursement Dispute Procedures. If the City determines, pursuant to subsection (C) of this Section, that the Design-Build Work required for any payment has not progressed as indicated by the DBOM Contractor, or otherwise disputes any Requisition, the City shall provide prompt written notice to the DBOM Contractor as to the City's reasons, in reasonable detail, for such determination or the basis for such dispute. After receiving such determination notice, the DBOM Contractor may make the necessary corrections and resubmit a Requisition to the City, or the DBOM Contractor and the City may agree on a revised amount, in which case the City shall promptly pay such revised amount. If the DBOM Contractor is unable to reach agreement with the City as to the progress of Design-Build Work, the DBOM Contractor may exercise its right to contest the City's determination in accordance with the dispute resolution procedures set forth in Article 19 (Dispute Resolution). Any proceedings undertaken to resolve a dispute arising under this subsection shall immediately terminate if (1) the DBOM Contractor demonstrates to the City that the Design-Build Work has proceeded as indicated in the Requisition giving rise to the dispute or that any disputed Requisition is correct, and (2) the City concurs with such demonstration. The DBOM Contractor shall not be entitled to payment of the amount so requisitioned and disputed except upon resolution of the dispute in accordance with this subsection. In the event that upon resolution of any such dispute, it is determined that the DBOM Contractor was properly entitled to the disputed amount as of a date earlier than the date on which payment is actually made, the DBOM Contractor shall be entitled to receive, promptly following such resolution, such disputed amount plus interest on such disputed amount for the period of dispute calculated at the Overdue Rate. 75 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work (E) Retainage. Each Design-Build Price drawdown payment will be subject to a 5% retainage holdback until Acceptance is achieved in accordance with Article 6 (Acceptance). The retainage will be placed in an interest-bearing account as provided by OAR 137-049-0820 and any such earnings on the account will accrue to the DBOM Contractor. Alternatively, in lieu of cash retainage, the DBOM Contractor may substitute bonds, securities or other instruments pursuant to OAR 137-049-0820(6). Consistent with OAR 137-049-0820, the DBOM Contractor may, after 50 percent of the value of the Design-Build Work is completed, request that the City reduce the amount of retention or eliminate retainage on any remaining Design-Build Work, if progressing satisfactorily, upon the DBOM Contractor's submission of a written application containing the DBOM Contractor's surety's written approval. Any decision to reduce retainage or eliminate retainage on remaining Design-Build Work shall be at the sole discretion of the City. Upon Acceptance, the City shall release to the DBOM Contractor the accumulated funds retained from all prior Design-Build Price payments (excluding interest); provided, however, that to the extent items are contained on the final Punch List, the City shall reasonably estimate the cost to make each correction or to complete each such item and the City shall be entitled to withhold from payment of the retained funds an amount equal to 200% of the aggregate value of such items, in addition to the amount of unresolved or unbonded claims by third parties or Encumbrances in connection with the Design-Build Work. Within 30 days after Final Completion has occurred and so long as authority contained in the Governmental Approvals to operate the Project remains unimpaired, the City shall release to the DBOM Contractor all remaining retained funds, including any interest accrued on the amount of the retained funds which interest shall be for the account of the DBOM Contractor. In lieu of retainage holdback, the DBOM Contractor may submit a letter of credit as permitted under OAR 137-049-0820. Section 7.6. PERMISSIBLE WITHHOLDINGS. The City may disapprove and withhold and retain all or any portion of any payment requested in any Requisition in an amount equal to the sum of: (1) any amounts which are permitted under Section 7.5 (Payment Procedure) to be withheld from any payment requested in any Requisition; (2) any amounts which are due the City hereunder, including any liquidated damages which are payable by the DBOM Contractor under subsection 6.6(A) (Delay Liquidated Damages) and any indemnification amounts which are due and owing to the City under Article 25 (Indemnification); (3) any other deductions which are required by Applicable Law; (4) any payments with respect to which documents to be delivered in connection therewith are not correct and complete; (5) any payments with respect to which the Design-Build Work covered by such Requisition (or any previous Requisition) does not comply with this DBOM Agreement; (6) any payments with respect to which any person has asserted a Lien resulting from the acts or omissions of the DBOM Contractor in performing the Design- Build Work and such Lien remains unreleased or unbonded; and (7) all requisitioned payments, if a DBOM Contractor Event of Default has occurred and is continuing under Section 21.1 (DBOM Contractor Events of Default). In addition to the items listed above in this subsection, in the event the DBOM Contractor fails to pay any Taxes, assessments, penalties or fees imposed by any Governmental Body, then the 76 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 7 DBOM Agreement Payment for the Design-Build Work DBOM Contractor authorizes the City to deduct and withhold or pay over to the appropriate Governmental Body those unpaid amounts upon demand by the Governmental Body. Section 7.7. FINAL REQUISITION AND PAYMENT. (A) Final Requisition for Design-Build Price. Upon achieving Final Completion in accordance with Section 6.8 (Final Completion), the DBOM Contractor shall prepare and submit to the City a final Requisition. The final Requisition shall enclose: (1) AIA Document G707 (Consent of Surety Company to Final Payment) certifying the surety agrees that final payment with respect to the Design-Build Price shall not relieve the surety of any of its obligations under the P&P Bonds provided pursuant to Section 18.2 (Payment and Performance Bonds); (2) an affidavit regarding settlement of claims and complete and legally effective releases or waivers acceptable to the City in the full amount of the Design-Build Price, or if any Subcontractor refuses or fails to furnish such release or waiver, a bond or other security acceptable to the City to indemnify the City Indemnitees against any payment claim; and (3) a list of all pending property damage and personal injury or death insurance claims arising out of or resulting from the Design-Build Work or identifying the claimant and the nature of the claim. (B) Final Payment of Design-Build Price. If based on the City's (1) observation of the Design-Build Work, (2) final inspection, and (3) review of the final Requisition and other documents required by subsection (A) of this Section, the City is satisfied that all conditions for Final Completion have been satisfied, and the City shall, within 15 days after receipt of the final Requisition, file a written notice of Final Completion and notify the DBOM Contractor of such concurrence. As soon as reasonably practicable (but in no event later than 30 days after the City's original receipt of the DBOM Contractor's final Requisition, subject to the City's right to dispute payment in accordance with this DBOM Agreement and Applicable Law) after filing such notice of Final Completion, the City shall pay to the DBOM Contractor the balance of the Design- Build Price subject to any withholdings and any other provisions governing final payment specified herein. If the City does not concur that all conditions for Final Completion have been satisfied, the City shall return the Requisition to the DBOM Contractor (in no event later than 15 days after the City's original receipt of the DBOM Contractor's final Requisition), indicating in writing its reasons for refusing final payment and Final Completion. The DBOM Contractor shall promptly make the necessary corrections and resubmit the Requisition to the City. The City's written determination shall bind the DBOM Contractor, unless the DBOM Contractor delivers to the City a written notice of a claim within 30 days after receipt of that determination. Any dispute regarding final payment of the Design-Build Price shall be resolved in accordance with the dispute resolution procedures set forth in Article 19 (Dispute Resolution). Final payment does not constitute a waiver by the City of any rights relating to the DBOM Contractor's obligations under this DBOM Agreement. Final payment constitutes a waiver of all claims by the DBOM Contractor against the City relating to the Design-Build Work, the payment of the Design-Build Price, or otherwise in connection with the Design-Build Period, other than those previously filed in writing with the City on a timely basis and still unsettled. 77 3935946.13 043463 ARTICLE 8 OPERATION AND MANAGEMENT Section 8.1. DBOM CONTRACTOR OBLIGATIONS GENERALLY. (A) Commencement of Operations. Commencing on the Acceptance Date, the DBOM Contractor shall operate, maintain, repair, and replace the Project on a 24-hour per day, 7-day per week basis during the Term in accordance with the Operation and Maintenance Requirements and the other Contract Standards. (B) Scope. The DBOM Contractor shall furnish all labor, materials, equipment, supplies, tools, storage, transportation, insurance, delivery, accounting, record- keeping and other things and kinds of services whatsoever necessary for the full performance of the DBOM Contractor's operation, maintenance, repair, replacement, management, obtaining and maintaining DBOM Contractor Managed Governmental Approvals and related obligations under this DBOM Agreement. (C) Quality Assurance and Quality Control. The DBOM Contractor shall develop an operation and maintenance quality assurance and quality control plan in accordance with the requirements set forth in Appendix 10 (Operation and Maintenance Requirements) including the laboratory protocols/quality assurance plan described therein. The DBOM Contractor shall have full responsibility for quality assurance and quality control for the Operation and Maintenance Services, including compliance with such operation and maintenance quality assurance and quality control plan. (D) No-Nuisance Covenant. The DBOM Contractor shall keep the Project and the Project Site neat, clean and litter-free at all times, ensure that the operation of the Project does not create any odor, litter, noise, fugitive dust, vector, excessive light or other adverse environmental effects on the surrounding community constituting, with respect to each of the foregoing, a nuisance condition under Applicable Law. (E) Emergency Orders and Directives. The DBOM Contractor shall comply with all orders and directives given or issued by the City or any Governmental Body having police power or regulatory jurisdiction based on an emergency condition. Section 8.2. SERVICE COORDINATION. (A) Communications and Meetings. On or before the Acceptance Date, the DBOM Contractor shall inform the City of the phone numbers, e-mail addresses and other means by which the Operation and Maintenance Supervisor may be contacted. The Operation and Maintenance Supervisor, or its proxy, shall be reachable 24 hours a day, seven days a week and shall, at the City's reasonable request, attend meetings with the City's staff. The City shall furnish to the DBOM Contractor comparable communications information with respect to the City Representative. On a monthly basis, the DBOM Contractor shall meet with the City to review the contents of the operations reports required to be prepared pursuant to Section 8.11 (Periodic Reports). The Operation and Maintenance Supervisor shall personally attend these monthly operations meetings with the City. In addition, the City shall have the right to require special meetings, acting reasonably, to review management, operational, performance and planning matters arising with respect to the Project and this DBOM Agreement. The Operation and Maintenance Supervisor shall attend all such special meetings. Any issue in dispute which the parties are unable to resolve at such monthly operations meetings and special meetings may be referred to the dispute resolution procedures set forth in Article 19 (Dispute Resolution), and the resolution of any issues resolved at such meetings or through the dispute resolution 78 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management procedures shall be reflected in a Contract Administration Memorandum or a DBOM Agreement Amendment, as applicable. (B) Complaints and Inquiries. The DBOM Contractor shall respond in a timely and effective manner to all complaints and inquiries received by the DBOM Contractor or the City regarding the performance of the Operation and Maintenance Services, odor and air emissions, noise, light emissions, construction, maintenance or any other matter related to the Operation and Maintenance Services. The City shall, as early as practicable, notify the DBOM Contractor if the City receives any complaints and inquiries regarding the performance of the Operation and Maintenance Services, odor and air emissions, noise, light emissions, construction, maintenance or any other matter related to the Operation and Maintenance Services. The DBOM Contractor shall investigate each such complaint and inquiry and, if it has a valid basis, the DBOM Contractor shall promptly rectify the matter. Complaints and inquiries concerning odors, spillages, leaks, breaks, noise, light emissions and emergencies relating to the Project shall be acknowledged by the DBOM Contractor within two hours, and all other communications within 24 hours. All such complaints and inquiries shall be immediately logged and promptly transmitted in writing, faxed or emailed to the City on a daily basis, and reported to the City as part of the monthly operations reports delivered pursuant to Section 8.11 (Periodic Reports). The DBOM Contractor shall establish, maintain and make freely known a telephone number, e-mail address and mailing address to which customer or citizen complaints and inquiries may be directed. The City shall maintain this contact information on its website for its citizens. Section 8.3. OPERATION AND MAINTENANCE MANUAL AND OPERATION AND MAINTENANCE PLAN. (A) DBOM Contractor Responsibility. The DBOM Contractor shall develop, provide and maintain the Operation and Maintenance Manual and the Operation and Maintenance Plan for the Project in accordance with the Contract Standards and based on the Preliminary Operation and Maintenance Plan set forth in Appendix 10 (Operation and Maintenance Requirements). The DBOM Contractor shall keep the Operation and Maintenance Manual and the Operation and Maintenance Plan current and shall supply the City with appropriate updates, supplements or revisions thereto annually or at any earlier time that a material change to the Operation and Maintenance Manual and the Operation and Maintenance Plan is made. Such updates shall preserve the standards set forth in the Operation and Maintenance Manual and the final Operation and Maintenance Plan provided as a condition to Final Completion pursuant to Section 6.8 (Final Completion). Notwithstanding any such review and comment by and discussion with the City, the Operation and Maintenance Manual and the Operation and Maintenance Plan shall remain, at all times, the responsibility of the DBOM Contractor. Neither the review of or comment upon, nor the failure of the City to comment upon, the Operation and Maintenance Manual and the Operation and Maintenance Plan shall: (1) relieve the DBOM Contractor of any of its responsibilities under this DBOM Agreement; (2) be deemed to constitute a representation by the City that operating the Project pursuant to the Operation and Maintenance Manual and the Operation and Maintenance Plan will cause the Project to be in compliance with the Contract Standards; or (3) impose any liability upon the City. The Operation and Maintenance Manual and the Operation and Maintenance Plan shall be maintained in an electronic form in such a manner that the City shall have immediate access to the current version of the Operation and Maintenance Manual and the Operation and Maintenance Plan at all times during the Operation and Maintenance Period. (B) Supplements for Capital Modifications. The DBOM Contractor shall prepare supplements and revisions to the Operation and Maintenance Manual and the Operation and Maintenance Plan which are required due to the design, construction and installation of all Capital Modifications. Such supplements and revisions shall be provided, reviewed and approved in the same manner as provided in this Section with respect to the initial Operation 79 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management and Maintenance Manual and the Operation and Maintenance Plan. The cost and expense of all such supplements and revisions shall be borne by the DBOM Contractor, except with respect to supplements and revisions necessitated by Capital Modifications directed by the City or required by a Change in Law Event or Relief Event, or by any Capital Modifications not undertaken by the DBOM Contractor. Section 8.4. STAFFING AND PERSONNEL. (A) Staffing. The DBOM Contractor shall adequately staff the Project during the Term in accordance with the Contract Standards and the Operation and Maintenance Plan. All personnel shall be qualified and shall meet the licensing and certification requirements of the State. The DBOM Contractor shall discipline or replace, as appropriate, any employee of the DBOM Contractor or any Subcontractor engaging in unlawful, unruly or objectionable conduct. Staffing levels and qualifications shall be consistent with the requirements of Applicable Law and staffing requirements of Appendix 10 (Operation and Maintenance Requirements). In no event may the DBOM Contractor reduce the number of staff members to less than any number indicated in Appendix 10 (Operation and Maintenance Requirements) and final approved Operation and Maintenance Plan without the approval of the City, which approval shall be in the City's sole discretion and may be conditioned upon an equitable reduction to the Operation and Maintenance Charge of the Service Fee. The DBOM Contractor shall notify the City of any material change in staffing levels and positions from time to time, and shall not make any such material change if the new staffing level would contravene the provisions of this subsection or otherwise adversely affect the ability of the DBOM Contractor to provide the Operation and Maintenance Services in accordance with the Contract Standards. (B) Training. The DBOM Contractor shall be responsible for training the Operation and Maintenance Supervisor and all other DBOM Contractor personnel. No later than 180 days prior to Substantial Completion, the DBOM Contractor shall submit to the City for its review and comment a personnel training program which the DBOM Contractor proposes to institute in order to ensure that the Project is managed and operated in accordance with this DBOM Agreement. Such personnel training program shall be consistent with the requirements set forth in Appendix 10 (Operation and Maintenance Requirements) and shall include, at a minimum, the personnel training guidelines, policies and procedures established: (1) in any Governmental Approval or operator's certificate required or issued by any Governmental Body; (2) by any applicable equipment manufacturer; and (3) in any other Applicable Law. Section 8.5. TRAINING OF CITY PERSONNEL. (A) Permanent Operations. The DBOM Contractor shall, on not less than 45 days'prior written notice from the City, conduct a one-time training program for the City and its designees in order to enable the City to assume operating and management responsibility for the Project at the expiration or earlier termination of this DBOM Agreement. The program shall include 45 days of review of Project operations and shall be substantially equivalent to the training afforded the DBOM Contractor's employees in connection with the Commissioning of the Project. In addition, the DBOM Contractor shall permit the City supervisory and operating personnel to observe the DBOM Contractor's operation of the Project for a period of up to 180 days prior to expiration or termination of this DBOM Agreement, which observation activities shall not interfere unreasonably with the DBOM Contractor's performance of the Operation and Maintenance Services. All City employee expenses pertaining to the observation activities of the City supervisory and operating personnel shall be borne by the City. (B) Compensation. The cost and expense of providing the required training pursuant to this Section, other than City employee time, shall be borne by the DBOM Contractor and has been priced into the Service Fee. 80 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management Section 8.6. UTILITIES DURING THE OPERATION AND MAINTENANCE PERIOD. (A) Arrangement of Utilities. The DBOM Contractor shall have the right and the responsibility, at its cost and expense, to arrange for the supply of all Utilities required to perform the Operation and Maintenance Services, including electricity, gas, telephone (but only without the installation or use of overhead cables), telecommunications, and potable water for general use at the Project. The DBOM Contractor shall negotiate and establish rates and terms of service with the respective Utility providers (including the City, as applicable) and shall pay all such Utility bills in a timely manner. The DBOM Contractor acknowledges that, except with respect to the costs of electricity which will be paid as a pass-through by the City to the DBOM Contractor, the Operation and Maintenance Charge includes all compensation to which the DBOM Contractor is entitled on account of such Utility service, subject to any deductions or incentive payments set forth in Article 9 (Performance) or Appendix 13 (Performance Guarantees and Deductions). (B) Generation and Utilization of Project Site Solar Panels. With respect to all solar panels required by the Design and Construction Requirements and the Operation and Maintenance Requirements, any electricity generated by such solar panels shall be for the benefit of the City and the Project and shall be consumed on-site by the Project first and before the DBOM Contractor acquires any electricity from its Utility provider. The use of solar panels shall not in any way alleviate the DBOM Contractor of its obligation to meet the Guaranteed Maximum Electricity Consumption. It is the intent of the parties that all electricity generated by solar panels on the Project Site will reduce the amount of electricity acquired from a Utility provider and therefore reduce the pass-through electricity component payable by the City to the DBOM Contractor pursuant to subsection 17.3(C) (Pass-Through Electricity Component). Section 8.7. SAFETY AND SECURITY. (A) Safety. The DBOM Contractor shall maintain the safety of the Project at a level consistent with the Contract Standards. Without limiting the foregoing, the DBOM Contractor shall: (1) take all reasonable precautions for the safety of, and provide all reasonable protection to prevent damage, injury or loss by reason of or related to the operation of the Project to, (a) all employees working at the Project and all other persons who may be involved with the operation, construction, maintenance, repair and replacement of the Project, (b) all visitors to the Project, (c) all materials and equipment under the care, custody or control of the DBOM Contractor on the Project Site, and (d) other property constituting part of the Project; (2) establish and enforce all reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards and promulgating safety regulations; (3) give all notices and comply with all Applicable Laws relating to the safety of persons or property or their protection from damage, injury or loss; (4) designate a qualified and responsible employee whose duty shall be the supervision of Project safety, the prevention of fires and accidents and the coordination of such activities as shall be necessary with federal, State and City officials; (5) operate all equipment in a manner consistent with the manufacturer's safety recommendations; 81 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management (6) provide for safe and orderly vehicular movements; and (7) develop and carry out a Project Site-specific safety program, including employee training and periodic inspections, designed to implement the requirements of this Section. The DBOM Contractor shall report to the City as to compliance with its obligations under this subsection in accordance with Section 8.11 (Periodic Reports) and Appendix 10 (Operation and Maintenance Requirements). (B) Project Security. The DBOM Contractor shall be responsible for the security of the Project, and shall maintain all electronic surveillance equipment and locks at the Project in accordance with the Contract Standards, including the specific requirements set forth in Appendix 10 (Operation and Maintenance Requirements). The DBOM Contractor shall guard against damage or injury to such properties caused by trespass, negligence, vandalism or malicious mischief of third parties in accordance with the Contract Standards. The DBOM Contractor shall provide the City, upon request, all information necessary to assist the City and any federal agency with respect to any vulnerability assessment required under Applicable Law. Section 8.8. OPERATING GOVERNMENTAL APPROVALS. (A) Applications and Submittals. The DBOM Contractor shall, with the City's reasonable cooperation which shall be limited to executing any permit applications as necessary, submit all filings, applications, notices and reports prepared by the DBOM Contractor reasonably necessary to obtain and maintain all Governmental Approvals that are DBOM Contractor Managed Governmental Approvals required to be made, obtained or maintained by or in the name of the DBOM Contractor or the City under Applicable Law in order to operate the Project. In connection therewith,the DBOM Contractor shall: (1) prepare the application and develop and furnish all necessary supporting material; (2) supply all data and information which may be required; (3) familiarize itself with the terms and conditions of such Governmental Approvals; (4) attend all required meetings and hearings; and (5) take all other action necessary in obtaining, maintaining, renewing, extending and complying with the terms of such Governmental Approvals. All permit and filing fees required in order to obtain and maintain DBOM Contractor Managed Governmental Approvals shall be paid by the DBOM Contractor, regardless of the identity of the applicant or permittee, except for Governmental Approvals required in connection with a Relief Event; provided, however, that the City shall be responsible for any new permitting fees or increases in permitting fees established by a Change in Law Event following the Effective Date. The DBOM Contractor shall not knowingly take any action in any application, data submittal or other communication with any Governmental Body regarding Governmental Approvals or the terms and conditions thereof that would impose any unreasonable cost or unreasonable burden on the City. The City reserves the right to modify, alter, amend, delete or supplement any information supplied, or term or condition proposed, by the DBOM Contractor which would have the effect described in the preceding sentence. The final terms and conditions of any Governmental Approval shall be subject to the City's approval, which approval shall not be unreasonably withheld, conditioned or delayed. (B) Data and Information. All data, information and action required to be supplied or taken by the DBOM Contractor in connection with the Governmental Approvals required for the Operation and Maintenance Services shall be supplied and taken on a timely basis considering the requirements of Applicable Law and the responsibilities of the City as the legal and beneficial owner of the Project and primary permittee. The data and information supplied by the DBOM Contractor to the City and all Governmental Bodies shall be correct and complete in all material respects, and shall be submitted in draft form to the City sufficiently in advance to allow full and meaningful review and comment by the City in accordance with 82 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management Appendix 10 (Operation and Maintenance Requirements). The DBOM Contractor shall be responsible for any schedule and cost consequences that may result from the submission of materially incorrect or incomplete information. The City reserves the right to reject, modify, alter, amend, delete or supplement any information supplied by the DBOM Contractor pursuant to this Section to the extent that any such information would impose any unreasonable cost or burden on the City. (C) Non-Compliance and Enforcement. The DBOM Contractor shall report to the City, promptly upon obtaining knowledge thereof, all violations of the terms and conditions of any Governmental Approval or Applicable Law pertaining to the Project and shall have all obligations and responsibilities with respect thereto as set forth in Section 4.5 (Compliance with Applicable Law). The City shall have the right independently to enforce compliance with this DBOM Agreement regarding the requirements of any Governmental Approval regardless of whether a concurrent or different regulatory enforcement action has been undertaken by any other Governmental Body. The failure of the DBOM Contractor to comply with any Governmental Approval shall constitute a breach of this DBOM Agreement by the DBOM Contractor as well as an event of non-compliance with the Governmental Approval. (D) Reports to Governmental Bodies. The DBOM Contractor shall prepare all periodic and annual reports, make all information submittals and provide all notices to all Governmental Bodies required by all DBOM Contractor Managed Governmental Approvals and under Applicable Law with respect to the Project. Such reports shall contain all information required by the Governmental Body, and may be identical to comparable reports prepared for the City, if such are acceptable to the Governmental Body. The DBOM Contractor first shall provide the City with copies of such regulatory reports for review, comment and signature, as applicable. (E) Potential Regulatory Change. The DBOM Contractor and the City shall keep the other party regularly advised as to potential changes in regulatory requirements affecting the performance of the Operation and Maintenance Services of which it has knowledge, and the DBOM Contractor shall provide recommended responses to such potential changes so as to mitigate any possible adverse economic impact on the City should a Change in Law Event actually occur. (F) DBOM Contractor Responsibilities in Connection with City Managed Governmental Approvals. In connection with Governmental Approvals that are City Managed Governmental Approvals, the DBOM Contractor shall reasonably cooperate with and assist the City in carrying out the City's responsibilities hereunder with respect such City Managed Governmental Approvals, including: (i) providing assistance to the City in preparing and completing required filings, applications, notices and reports; (ii) providing readily available data, information, plans, documentation and supporting material; and (iii) performing the DBOM Contractor's responsibilities with respect to the NPDES Permit set forth in Appendix 2 (Governmental Approvals). If requested by the City, the DBOM Contractor will: (1) develop and furnish all necessary data, information, plans, documentation and supporting material that is not readily available; (2) familiarize itself with all applicable terms and conditions; (3) attend all required meetings and hearings; and (4) take all other actions reasonably necessary in accordance with Good Operation and Maintenance Practice to assist the City in obtaining, maintaining, renewing, and extending all City Managed Governmental Approvals; in each case, after the parties enter into a DBOM Agreement Amendment authorizing the performance of such services and the compensation therefor. 83 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management Section 8.9. CITY AND PORTLAND ACCESS TO THE PROJECT. The City (as owner of the Project) and all appropriate Governmental Bodies shall have the right at any time, on a 24-hour per day, 365-day per year basis, to enter and inspect the Project and observe the DBOM Contractor's performance of the Operation and Maintenance Services; provided, however, to the extent circumstances permit, reasonable notice shall be provided to the DBOM Contractor of such intent to access the Project. In addition, Portland shall have the right at any time, on a 24-hour per day, 365-day per year basis, to enter the Project for the limited purposes associated with accessing the Tryon Creek Interceptor and the Willamette Interceptor; provided, however, to the extent circumstances permit, reasonable notice shall be provided to the DBOM Contractor of such intent to access the Project. The DBOM Contractor shall permit and facilitate access to the Project for such purposes, including all necessary compliance and confirmation sampling, by City personnel and by agents and contractors designated by the City. Keys or passwords, as applicable, for the facilities or structures comprising the Project shall be provided to the City Representative by the DBOM Contractor in accordance with the DBOM Contractor's physical security plan and key control program. All visitors (including Portland, its personnel, agents and contractors, and all City Indemnitees, personnel, agents and contractors) shall comply with the DBOM Contractor's reasonable operating and safety procedures and rules, and shall not interfere with the DBOM Contractor's operations of the Project. The parties agree that the City shall have immediate access to the Project, and no DBOM Contractor rule or procedure shall impede, impair or delay such access. The DBOM Contractor shall maintain a visitors' log during the Term and shall require that all visitors to the Project(other than DBOM Contractor personnel) sign in and sign out in the visitors' log. Section 8.10. OPERATING DATA AND PROJECT RECORDS. (A) Computerized Information System. The DBOM Contractor, on and after the Acceptance Date, shall establish and maintain a computerized information system with respect to the Project for operations and maintenance data, including the information necessary to verify calculations made pursuant to this DBOM Agreement and demonstrate compliance with the Contract Standards, in accordance with the specific requirements set forth in Appendix 10 (Operation and Maintenance Requirements). The DBOM Contractor shall maintain current and up to date records of the Operation and Maintenance Services in accordance with the Contract Standards throughout the Term. (B) Sampling, Testing and Laboratory Work. The DBOM Contractor shall perform and provide and bear the cost of, all sampling, laboratory testing and analyses, and quality assurance and quality control procedures and programs required by the Contract Standards. All testing laboratories shall be certified by the appropriate State or federal agency, as applicable, for the applicable test, shall be operated in accordance with Good Operation and Maintenance Practice, and shall be monitored by the DBOM Contractor for compliance with standard test methods. All sampling and test data shall be available for review by, and reported to, the City in accordance with Section 8.11 (Periodic Reports) and Appendix 10 (Operation and Maintenance Requirements). The DBOM Contractor explicitly assumes the risk of incorrect sampling, testing and laboratory work and any consequences thereof or actions taken or corrections needed based thereon, whether such work is performed by itself or third parties subcontracted with the DBOM Contractor, both as to failures to detect and as to false detections. The DBOM Contractor shall permit the City, at the City's expense, to perform any testing, sampling or analytical procedure it deems appropriate. (C) Availability of Operating Data and Project Records to the City. The DBOM Contractor shall make available to the City all operations, maintenance, performance, and similar records and data as are available to the Project Manager. The City shall have real time, 84 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management continuous read-only computer access to such records and data, and hard copy reproduction capability, through information systems installed in accordance with the Design and Construction Requirements. (D) Record Documents. The DBOM Contractor shall maintain at the Project and make available to the City upon request for review and copying: (1) all designs, drawings, blueprints, plans, specifications and "as-built" or record drawings and documents pertaining to the Project, copies of which were delivered to the City by the DBOM Contractor pursuant to Appendix 6 (Design-Build Work Review Procedures); and (2) similar documents relating to any Capital Modifications. The DBOM Contractor shall: (x) keep current all such records to show any changes to the Project (including valves, pipes, pumps, meters and other assets) made by the DBOM Contractor in the performance of the Operation and Maintenance Services; (y) provide advice and reasonable assistance to the City, based on such records, in establishing and maintaining any City geographic mapping and information systems; and (z) provide an updated electronic copy of all record documents to the City when changes occur. Section 8.11. PERIODIC REPORTS. (A) Monthly and Quarterly Operations. The DBOM Contractor shall provide the City with monthly and quarterly operations reports in accordance with the requirements set forth in Appendix 10 (Operation and Maintenance Requirements). (B) Annual Operation and Maintenance Reports. The DBOM Contractor shall furnish the City, within 90 days after the end of each Contract Year, an annual report in accordance with the provisions set forth in Appendix 10 (Operation and Maintenance Requirements), including a summary of the information contained in the monthly and quarterly operations reports. (C) Default Reports. The DBOM Contractor shall provide to the City, promptly after the receipt thereof(in no event later than three days following receipt), copies of any written notice of a material default, breach or non-compliance received or sent under or in connection with any Subcontract relating to the Operation and Maintenance Services. (D) Permit Communications and Reports. The DBOM Contractor shall provide to the City copies of all communications and reports furnished to any Governmental Body pursuant to this Section simultaneously with their submittal to the Governmental Body. Section 8.12. EMERGENCIES. (A) Emergency Plan. No later than 90 days prior to Substantial Completion, the DBOM Contractor shall have provided the City with a plan of action to be implemented in the event of an emergency, including fire, weather, environmental, health, safety and other potential emergency conditions occurring during the Operation and Maintenance Period in accordance with the requirements set forth in Appendix 10 (Operation and Maintenance Requirements). The emergency plan shall be subject to review and approval by City (which approval shall not be unreasonably withheld, conditioned or delayed) and shall be reviewed by the parties annually as part of the review of the annual operations report, and updated when necessary. (B) Emergency Action. In case of an emergency which threatens immediate loss or damage to property or safety of life, the DBOM Contractor shall act, at its discretion and risk, to prevent threatened loss, damage, injury or death. The DBOM Contractor shall notify the City of the situation and all actions taken immediately thereafter. If, in the opinion of the DBOM Contractor, immediate action is not required, the DBOM Contractor shall notify the City of the 85 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 8 DBOM Agreement Operation and Management emergency situation and proceed in accordance with the City's instructions. However, if any loss, damage, injury or death occurs that could have been prevented by the DBOM Contractor's prompt and immediate action, the DBOM Contractor shall be fully liable for all costs, damages, claims, actions, suits, attorneys'fees and all other expenses arising therefrom or relating thereto. At all times during the performance of the Operation and Maintenance Services, the DBOM Contractor shall provide the City with two 24 hour emergency phone numbers where its representatives can be contacted. Section 8.13. DOCUMENTS AND REPORTS. (A) Plans, Programs, Reports and Documents. The DBOM Contractor shall provide the City with the plans, programs, reports and documentation required with respect to the Operation and Maintenance Services under Appendix 10 (Operation and Maintenance Requirements). (B) Default Reports. The DBOM Contractor shall provide to the City, promptly after the receipt thereof, copies of any written notice of a material default, breach or non- compliance received or sent under or in connection with any Material Contract with respect to the Operation and Maintenance Services. Section 8.14. DISPOSAL OF SURPLUS EQUIPMENT. The DBOM Contractor may, at the direction of the City, remove, dispose of and sell, in accordance with Applicable Law, equipment constituting part of the Project that is unused or obsolete and no longer needed. All proceeds from any sale, net of the DBOM Contractor's expense in removing the equipment and arranging the sale, shall be the property of the City. Section 8.15. ENFORCEMENT OF PROJECT WARRANTIES. During the Term, the DBOM Contractor shall be responsible for meeting operating and maintenance obligations under all manufacturers'warranties on new equipment purchased and installed in the Project by the DBOM Contractor, and shall be the agent of the City in enforcing all equipment warranties and guarantees, including warranties and guarantees of the Design-Build Work obtained by the DBOM Contractor pursuant to Section 5.17 (Warranties of Design-Build Work). The DBOM Contractor shall not be required to commence or maintain any litigation with respect to such warranties or guarantees, but may do so in its discretion. The DBOM Contractor shall cooperate with and assist the City, at the City's expense unless otherwise agreed to by the parties, if the City seeks to enforce warranties and guarantees through litigation; provided, however, the City is under no obligation to seek to enforce any warranties or guarantees described in this Section. No manufacturers' warranty of any Project Equipment shall relieve the DBOM Contractor of any obligation hereunder, and no failure of any warranted or guaranteed structures, improvements, fixtures, machinery, equipment or material shall be the cause for any increase in the Service Fee or excuse any non-performance of the Operation and Maintenance Services unless such failure is itself attributable to a Relief Event. 86 3935946.13 043463 ARTICLE 9 PERFORMANCE Section 9.1. PROJECT PERFORMANCE GENERALLY. (A) Reliance. The DBOM Contractor acknowledges that the City, as the owner of the Project, is providing an essential governmental function, and is relying on the performance by the DBOM Contractor of its obligations hereunder. (B) Curtailments and Shutdowns. If the operation of the Project for any reason is temporarily reduced, curtailed or shut down so that the DBOM Contractor is unable to collect, receive and treat any quantity of Influent or discharge or divert Effluent in accordance herewith, the DBOM Contractor shall immediately advise the City as to the nature and probable duration thereof and the expected effect on the operation of the Project, and take all steps necessary to remedy the curtailment or shutdown and to resume full performance hereunder as soon as possible. (C) Limitations on DBOM Contractor Rights. The DBOM Contractor shall not treat wastewater other than Influent and shall not use the Project for any purpose other than the purposes contemplated hereby. The DBOM Contractor shall not impose a fee or charge on any third party for the treatment of Influent or any other waste. The only compensation payable by the City to the DBOM Contractor for providing the Operation and Maintenance Services shall be the Service Fee payable by the City hereunder. (D) Timing of Applicability of Performance Guarantees. The Performance Guarantees set forth in this Article and Appendix 13 (Performance Guarantees and Deductions) shall not apply during the Design-Build Period and shall only apply during the Operation and Maintenance Period. Section 9.2. EFFLUENT GUARANTEE. (A) Generally. Except to the extent relieved due to the occurrence of a Relief Event in accordance with Article 14 (Relief Event Procedures),the DBOM Contractor shall operate the Project on a continuous,uninterrupted 24-hour per day, 7-day per week basis so as to receive and treat all Influent and discharge or convey Effluent in compliance with the requirements of Applicable Law and the specific requirements set forth in Appendix 13 (Performance Guarantees and Deductions) (the "Effluent Guarantee"). (B) Deductions for Failure to Comply with the Effluent Guarantee. Except to the extent the DBOM Contractor is relieved due to the occurrence of a Relief Event in accordance with Article 14 (Relief Event Procedures), the DBOM Contractor shall pay Deductions in the amounts set forth in Appendix 13 (Performance Guarantees and Deductions) for the DBOM Contractor's failure to comply with the Effluent Guarantee. (C) Indemnity for Loss-and-Expense from Non-Complying Effluent. In the event that any Effluent discharged by the DBOM Contractor fails to comply with the requirements of the Effluent Guarantee, except to the extent such failure of compliance is caused by a Relief Event, the DBOM Contractor, in addition to its obligations under Section 9.10 (City Remedies for Non-Compliance with Performance Guarantees) and subsection (B) of this Section, shall pay all fines and penalties assessed by any Governmental Body and shall indemnify, defend and hold harmless the City Indemnitees in accordance with and to the extent provided in Article 25 (Indemnification) from and against any Loss-and-Expense resulting from the discharge or conveyance of such non-complying Effluent. This indemnity shall extend to any liability resulting 87 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance from property loss or damage or death or personal injury suffered or alleged to be suffered by any person from exposure to such non-complying Effluent based on any theory of recovery, including theories of toxic tort or environmental impairment. (D) Change in Law Event Affecting Effluent. The parties acknowledge that a Change in Law Event may affect Effluent standards or impose more stringent requirements relating to equipment or processes than those established hereunder as of the Effective Date. In the event such a Change in Law Event occurs, the DBOM Contractor shall not be entitled to performance relief or additional compensation under Article 14 (Relief Event Procedures) unless (1) such Change in Law Event imposes a regulatory standard or operating requirement with respect to any particular Effluent characteristic or parameter which is (i) more stringent or burdensome to comply with than the Contract Standards applicable to such characteristic or parameter, (ii) requires equipment or processes not then in place or practiced at the Project Facilities, or (iii) requires an increase in the use of power, labor or chemicals, and (2) the DBOM Contractor is unable, after taking all mitigation measures required under Article 14 (Relief Event Procedures) with respect to such a Change in Law Event, to avoid the necessity for such performance relief or additional compensation. Section 9.3. ODOR GUARANTEE. (A) Applicable Law Limits. Except to the extent relieved due to the occurrence of a Relief Event in accordance with Article 14 (Relief Event Procedures), in operating the Project the DBOM Contractor shall comply with all limits and requirements established by Applicable Law with respect to odor control. (B) Contract Limits. In addition to its obligation to comply with odor limits and requirements imposed by Applicable Law as provided in subsection (A) of this Section and except to the extent relieved due to the occurrence of a Relief Event in accordance with Article 14 (Relief Event Procedures), the DBOM Contractor shall operate the Project in a manner that ensures that no odor emanating from the Project creates an Odor Incident (the "Odor Guarantee"). (C) Odor Control Practices Report. The DBOM Contractor shall submit to the City,within the monthly operations report required by Section 8.11 (Periodic Reports), a monthly odor control section which shall include the information required to be included in such section pursuant to Section 2 (Minimum Proactive Odor Control Plan) of Appendix 11 (Odor Control Standard and Odor Control Plan). (D) Preventing Recurrence of Violations. The general remedies for exceeding odor limits are set forth in Section 9.10 (City Remedies for Non-Compliance with Performance Guarantees) and this Section and may include termination as and to the extent provided in Section 21.1 (DBOM Contractor Events of Default). With respect to odor particularly, the parties acknowledge the extreme importance of this issue to the general public. The DBOM Contractor further acknowledges that, in the process leading to the execution of this DBOM Agreement, the DBOM Contractor had a full opportunity to propose additional capital improvements for odor control, and by making its proposal and by executing this DBOM Agreement, the DBOM Contractor has assumed the risk that the Project is capable of controlling odor to a level required to comply with the Odor Guarantee absent the occurrence of a Relief Event. Accordingly, in the event the DBOM Contractor fails to comply with its odor control obligations set forth or referred to in this Section, and is not excused by a Relief Event, the DBOM Contractor shall be obligated to implement such capital investments, improvements or modifications, repairs and replacements and operating and management practices changes as shall be necessary, in light of the nature, extent and repetitiveness of such non-compliance, to assure that the odor violation will not recur. Any capital investment, improvement or modification required to be made 88 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance pursuant to this subsection, reasonably expected to result in a material change to the Project, shall be considered a Capital Modification subject to the provisions of Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault). Nothing in this Section shall be construed to limit the DBOM Contractor's obligation to respond to any odor complaint in the manner and within the time requirements established by subsection 8.2(B) (Complaints and Inquiries). (E) Odor Incident. An "Odor Incident" for the purposes of this DBOM Agreement is an odor condition determined in accordance with Section 3 (Determination of an Odor Incident for Purposes of the Odor Guarantee) of Appendix 13 (Performance Guarantees and Deductions), to the extent not caused by a Relief Event. (F) Sustained Odor Condition. A "Sustained Odor Condition" for purposes of this DBOM Agreement is any Odor Incident, or combination of Odor Incidents, occurring over the course of three or more consecutive days. (G) Citations for Odor Incidents. Upon the occurrence of any Odor Incident, the City shall have the right to issue a citation ("Odor Citation") to the DBOM Contractor in accordance with this subsection. Prior to issuing an Odor Citation, the City shall give written notice of the proposed issuance of the Odor Citation to the DBOM Contractor, together with a written statement as to the basis of the determination. The DBOM Contractor shall have five Business Days after receipt of the City's written notice to respond in writing to the City. The DBOM Contractor may, in its written statement, present information in refutation of the proposed City determination that an Odor Incident has occurred, including information as to the role of any Relief Event in any odor condition, other mitigating factors, and any possible assessment of Deductions which may result from the City's issuance of an Odor Citation. The City may exercise discretion in making its final determination of whether to issue an Odor Citation, and if so, the amount of Deductions to be assessed, if any. The limitations of this discretionary power are described in subsection (H) (Deductions for Odor Citations) of this Section. In exercising this discretion, the City shall consider the number, frequency, legitimacy and forcefulness of odor complaints logged; the size of the area or magnitude of the number of individuals affected; and the degree of impact on the individuals affected. In exercising this discretion, the City shall also consider the information presented by the DBOM Contractor (including information concerning the efforts of the DBOM Contractor to correct the odor condition). (H) Deductions for Odor Citations. The DBOM Contractor shall pay Deductions for each Odor Citation issued by the City in the following amount: (1) for the first Odor Citation, $15,000 (Index-Linked); (2) for the second Odor Citation $25,000 (Index-Linked); and (3) for the third and each subsequent Odor Citation, $50,000 (Index-Linked). The City shall have the right in its discretion to set the Deductions within such parameters. (I) City Monitoring. The City shall have the right at any time to monitor the Project for odor and emissions or to hire a third party for the purpose of monitoring the Project for odor and emissions and compliance with the odor related Operation and Maintenance Requirements. The City or any third party hired for the purpose may perform odor panel testing or sampling and monitoring. All City costs and any costs relative to any third party hired for the purpose shall be borne by the City. Notwithstanding Section 8.9 (City and Portland Access to the Project), the City shall give the DBOM Contractor reasonable notice in connection with any sampling, testing or monitoring conducted in connection with this subsection and DBOM Contractor shall have the right to observe any such sampling, testing, or monitoring. Should City or any third-party testing require that DBOM Contractor be present for any such sampling, testing or monitoring outside of normal business hours, the DBOM Contractor shall be compensated for additional reasonable and substantiated costs; provided, however, that such costs shall be borne solely by the DBOM Contractor if the sampling, testing or monitoring 89 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance demonstrates that Project odor and emissions are not in compliance with the odor related Operation and Maintenance Requirements. (J) Disregarding Prior Odor Citations. In the event that a period of 365 or more days elapses following the issuance of an Odor Citation without any further Odor Citations being issued by the City, all previous Odor Citations regardless of number shall be disregarded for the purposes of the City's termination rights pursuant to Section 21.1 (DBOM Contractor Events of Default) and for determining Deductions under subsection (H) of this Section, and the next Odor Citation, if any, which occurs shall be deemed to be the "first Odor Citation" for such termination and Deduction amount purposes. (K) Sustained Odor Condition Determination. Upon the occurrence of a Sustained Odor Condition, the City shall have the right to make a determination that a Sustained Odor Condition has occurred in accordance with this subsection. Prior to making a Sustained Odor Condition determination, the City shall give written notice of the proposed determination to the DBOM Contractor, together with a written statement as to the basis of the determination. The DBOM Contractor shall have ten Business Days after receipt of the City's written notice to respond in writing to the City. The DBOM Contractor may, in its written statement, present information in refutation of the proposed City determination that a Sustained Odor Condition has occurred, including information as to the role of any Relief Event in any odor condition and as to other mitigating factors. The City may exercise discretion in making its final determination as to whether a Sustained Odor Condition has occurred and if so, the amount of Deductions to be assessed, if any. The limitations of this discretionary power are described in subsection (L) (Deductions for Sustained Odor Condition Determination) of this Section. In exercising this discretion, the City shall also consider the information presented by the DBOM Contractor (including the efforts of the DBOM Contractor to correct the odor condition). (L) Deductions for Sustained Odor Condition Determination. The DBOM Contractor shall pay Deductions upon a Sustained Odor Condition determination made by the City, in an amount equal to $60,000 (Index-Linked) per day commencing on the fourth day of consecutive Odor Incident days and for each day thereafter for as long as the Sustained Odor Condition continues. The City shall have the right in its discretion to set the Deductions within such parameters. (M) City Termination Rights Based on Failure to Meet Odor Guarantee. The City shall have the right, but not the obligation, to terminate this DBOM Agreement based upon failure to meet the Odor Guarantee pursuant to and in accordance with Section 21.1 (DBOM Contractor Events of Default). The rights of the City to receive Deductions from the Service Fee, or to terminate this DBOM Agreement based on Odor Citations or a Sustained Odor Condition determination, shall not be exclusive, and the City shall have all of the other remedies provided herein in the event of a breach of this DBOM Agreement relating to odor, including the right to require the DBOM Contractor to prevent the recurrence of odor violations as provided in subsection (D) of this Section. (N) Concurrent Odor Incidents and Sustained Odor Conditions. Notwithstanding the pendency of proceedings relating to the issuance of an Odor Citation, the City shall have the right to give notice of a Sustained Odor Condition (whether based on the continuance of the Odor Incident giving rise to the possible issuance of the Odor Citation or based upon other odor conditions). In any such event the DBOM Contractor shall have the rights set forth in subsection (K) of this Section with respect to the determination of a Sustained Odor Condition. (O) Number of Odor Citations and Sustained Odor Condition Determinations. Nothing in this Section limits the number of Odor Incidents or Sustained Odor Condition determinations that the City may declare if circumstances warrant hereunder. 90 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance Section 9.4. ELECTRICITY CONSUMPTION GUARANTEE. (A) Guaranteed Maximum Electricity Consumption Calculation. The "Guaranteed Maximum Electricity Consumption" by the DBOM Contractor for the operation of the Project in any Contract Year shall not exceed the kWh determined pursuant to the following formula: 145 x Average Annual BOD (lb/day) + 166,944 x Average Annual Flow (MGD) + 2,003,317 (B) Deductions for Excess Electricity Consumption. The City shall have the right in its discretion to impose a Deduction annually for excess electricity consumption over the Guaranteed Maximum Electricity Consumption amount. The Deduction to be applied in any Contract Year shall be equal to: (1) the actual aggregate electricity consumed by the Project for the Contract Year in excess of the Guaranteed Maximum Electricity Consumption, rounded to the nearest hundredth of a kWh; multiplied by (2) the average per kWh rate paid by the DBOM Contractor to its electric Utility provider during the Contract Year. (C) Guaranteed Maximum Electricity Consumption Based on Total Project Consumption. The parties acknowledge and agree that any calculation related to electricity consumption made pursuant to this Section shall be based on the Project's total electricity consumption, regardless of whether the electricity consumed is provided by a Utility provider or another source of electricity such as on-site solar panels. (D) Electricity Usage Benchmarking Program. The DBOM Contractor shall implement a benchmarking program to optimize electricity usage during the first two years of the Operation and Maintenance Period and implement an annual review with the City of such each Contract Year thereafter.The Wastewater Treatment Facility shall be equipped with variable frequency drives for motor operation to help facilitate optimization, coupled with instrumentation and control inherent in the design of the Wastewater Treatment Facility. Performance data will be reviewed by the DBOM Contractor as historical information is accumulated to adjust operating strategies to optimize electricity consumption to the benefit of the City without negatively impacting performance of the Operation and Maintenance Services. In the event Capital Modifications are identified that could provide an overall benefit to the City, they will be evaluated with the City for potential implementation in accordance with Article 11 (Capital Modifications and Operation and Maintenance Services). Section 9.5. NOISE GUARANTEE. Noise levels during operation of the Project shall comply with the requirements set forth in OAR 340-035-0035. If noise from the operation of the Project exceeds the requirements set forth in OAR 340-035-0035, the DBOM Contractor will be required to implement additional treatments until noise is reduced to the required level. Section 9.6. MANAGEMENT OF RESIDUALS. (A) General Obligations. Except to the extent relieved in accordance with Article 14 (Relief Event Procedures) due to the occurrence of a Relief Event, the DBOM Contractor shall be responsible for the processing and management of all Residuals at the Project Site and the transportation and disposal of all Residuals in accordance with the Contract Standards, including the specific requirements set forth in this Section. The obligations of the DBOM 91 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance Contractor pursuant to this Section and Appendix 13 (Performance Guarantees and Deductions) shall be the "Residuals Management Guarantee" hereunder. (B) Sludge and Scum Processing. The DBOM Contractor shall process Sludge and Scum to meet all requirements set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements) and Section 4 (Residuals Management Guarantee) of Appendix 13 (Performance Guarantees and Deductions). (C) On-Site Storage and Loading. The DBOM Contractor shall, at the Project Site, only store (i) Sludge and Scum in enclosed and odor-controlled sludge holding tanks, as contemplated by the Design and Construction Requirements, or in sealed tanker trucks, and (ii) Grit and Screenings in an enclosed and odor controlled building, and shall handle Residuals and complete all vehicle and container loading operations relating to Residuals in accordance with the Contract Standards. The DBOM Contractor acknowledges that the primary purpose of this provision is to minimize odors. Except to the extent the DBOM Contractor is relieved in accordance with Article 14 (Relief Event Procedures), for any Sludge and Scum that is not stored in enclosed and odor-controlled sludge holding tanks or in a sealed tanker truck or Grit and Screenings that are not stored in an enclosed and odor controlled building at the Project Site in accordance with requirements set forth above in this subsection, the DBOM Contractor shall pay Deductions in the amount of$1,000 (Index-Linked) for each of the first eight hours after being produced that each load of(i) Sludge and Scum is not stored in an enclosed and odor-controlled sludge holding tank or in a sealed tanker truck, and/or (ii) Grit and Screenings are not stored in an enclosed and odor controlled building in accordance with requirements set forth above in this subsection; and, in each case, $2,000 (Index-Linked) for each additional hour thereafter. (D) Sludge and Scum Transportation and Off-Loading. All Sludge and Scum shall be transported in sealed tanker trucks to, and off-loaded by the DBOM Contractor at, Portland's Columbia Boulevard Wastewater Treatment Facility, except as otherwise provided below in this subsection. The DBOM Contractor shall not be required to pay a fee to Portland for the off-loading of Sludge and Scum which meets the requirements set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements). In the event that the Sludge and Scum does not meet the standards set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements), the DBOM Contractor shall transport and dispose of such Sludge and Scum at a Qualified Residuals Disposal Facility and be responsible for any incremental additional cost of transportation and disposal of such Sludge and Scum. If the Sludge and Scum does meet such standards, and such Sludge and Scum cannot be disposed of at the Columbia Boulevard Wastewater Treatment Facility due to no fault of the DBOM Contractor, such occurrence shall constitute an Other Relief Event and the DBOM Contractor shall be provided relief as and to the extent provided in Section 16.3 (Other Relief Events). (E) Transportation and Disposal of Grit and Screenings. All Grit and Screenings shall be transported in a manner that meets Good Operation and Maintenance Practice in commercially available trash disposal trucks in compliance with Applicable Law, including any applicable Oregon Department of Transportation regulations. Grit and Screenings shall be dried non-putrescible material and no drippings from transportation vehicles shall be permitted. All Grit and Screenings shall be transported to and disposed of at a Qualified Residuals Disposal Facility by the DBOM Contractor in accordance with Applicable Law only during the period between 9:00 p.m. on any day and 8:00 a.m. on the following day. (F) Residuals Transportation and Spills. All Residuals transportation operations shall be conducted in accordance with Applicable Law by properly licensed haulers in a safe and reliable manner. In the event of a spill or loss of Residuals during transfer or transit, the DBOM Contractor shall immediately arrange for the clean-up and proper disposal of the material, pay any resulting fines, assessments, penalties or damages resulting therefrom, and indemnify, defend and hold harmless the City from any Loss-and-Expense resulting from 92 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance any Legal Proceeding originated by a third party therefrom in the manner provided in Article 25 (Indemnification). (G) Sludge and Scum Information and Reporting. The DBOM Contractor shall keep and maintain such logs, records, manifests, bills of lading or other documents pertaining to Residuals as are necessary or appropriate to comply with the Contract Standards and to monitor and confirm compliance by the DBOM Contractor with the requirements of this Section, and shall collect and promptly provide the City as may be requested from time to time with a copy of all weights and measures data of Sludge and Scum generated, transported and off-loaded to the Columbia Boulevard Wastewater Treatment Facility or disposed of at a Qualified Residuals Disposal Facility hereunder. The DBOM Contractor shall provide monthly reporting in accordance with Appendix 13 (Performance Guarantees and Deductions), including as required to conform with Portland's Hauled Waste Plan. (H) Hazardous Substances. The DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures) in the event that Residuals contain Hazardous Substances, unless the DBOM Contractor has failed to comply with the Contract Standards so as to prevent the introduction of Hazardous Substances into the Residuals. (I) Title to Residuals. Without limiting any of the rights or remedies of the City under subsection (J) of this Section in the event of a failure of the DBOM Contractor to comply with the Residuals Management Guarantee, the City acknowledges and agrees that, except as otherwise provided in this subsection, the City shall be considered to be the owner and generator of all Residuals produced by or at the Project. Notwithstanding the foregoing, the DBOM Contractor shall be considered to be the owner and generator of(1) Residuals bypassed, released, leaked or spilled on or into,the environment in contravention of the DBOM Contractor's obligations under Section 9.9 (Releases, Leaks and Spills), and (2) Residuals containing Hazardous Substances as a result of DBOM Contractor Fault. The DBOM Contractor shall not be considered to be the owner and generator of Residuals that contain Hazardous Substances unless the DBOM Contractor introduced the Hazardous Substances into the Residuals or failed to properly notify, treat or dispose of known Hazardous Substances in connection with the performance of the Operation and Maintenance Services. (J) Failure to Comply with the Residuals Management Guarantee. In the event that the DBOM Contractor fails at any time to comply with the Residuals Management Guarantee, the DBOM Contractor shall, without limiting any other remedy available to the City upon such an occurrence and notwithstanding any other provision of this DBOM Agreement: (1) promptly correct such failure and resume compliance with the Residuals Management Guarantee; (2) pay any Deductions provided for in Appendix 13 (Performance Guarantees and Deductions) with respect to certain failures to comply with the Residuals Management Guarantee, and (3) indemnify, defend and hold harmless the City Indemnitees in accordance with and to the extent provided in Article 25 (Indemnification) from and against all Loss-and- Expense resulting therefrom. (K) Company Rolling Stock and Labor. The DBOM Contractor shall at its sole cost and expense, by ownership, leasing, subcontracting or otherwise, provide all transportation vehicles, equipment and rolling stock necessary in order to carry out and perform its obligations hereunder, including its obligations to transfer and transport Residuals. Without limiting the foregoing, the DBOM Contractor shall provide or have available a sufficient number of tractors, trailers and duly licensed and trained drivers to provide the transfer, transportation and disposal services required hereunder. The DBOM Contractor shall have sole responsibility for operating, maintaining, insuring and servicing such equipment and shall bear all risk of loss thereof or damage thereto and all risk of damage or injury caused by the operation thereof. 93 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance (L) Transportation Vehicle Loading and Operation. The loading, transportation and unloading of Residuals shall be performed so as to prevent any blowing, spilling or leakage of the material being transported. The DBOM Contractor acknowledges and represents that the Project Site and the Project Facilities will contain sufficient staging space and operational capabilities to enable the DBOM Contractor to perform all of its handling, transfer and transportation obligations hereunder. (M) Authorized Truck Routes. The DBOM Contractor shall only use truck routes approved by the City in connection with the transportation of Residuals (such approval not to be unreasonably withheld, conditioned or delayed). Section 9.7. UPSETS AND NONCOMPLIANT INFLUENT AFFECTING DBOM CONTRACTOR COMPLIANCE WITH PERFORMANCE GUARANTEES. (A) Relief Generally. The DBOM Contractor shall be relieved of its obligation to comply with a Performance Guarantee to the extent and for any period during which such Performance Guarantee cannot be achieved due to the operation of the Project being affected by the receipt of Noncompliant Influent or any other Relief Event. (B) Response Measures to Upsets. If an Upset occurs due to the receipt of Noncompliant Influents, the DBOM Contractor shall, without limiting its obligations under the Contract Standards: (1) use all efforts consistent with Good Operation and Maintenance Practice to maintain Project performance as if the Upset had not occurred; (2) immediately advise the City of the situation; (3) promptly provide the City with the DBOM Contractor's planned course of action (in any event within 24 hours after the DBOM Contractor's first knowing of the occurrence of an Upset; (4) submit any notice thereof required by Applicable Law; and (5) return the Project to be in compliance with the requirements of Applicable Law and the Performance Guarantees as soon as reasonably possible in accordance with the Contract Standards. (C) Service Fee Impact. To the extent the receipt of Noncompliant Influent constitutes a Relief Event hereunder, the Service Fee shall reflect the reasonable costs incurred by the DBOM Contractor with respect to such Relief Event, subject to Cost Substantiation, in accordance with and to the extent provided in Article 14 (Relief Event Procedures), including the reasonable costs incurred by the DBOM Contractor in responding to the effect of the Relief Event on the Project and on the performance of the Operation and Maintenance Services but excluding any such increased costs which would have been avoided had the DBOM Contractor complied with any remedial measures required under Applicable Law and appropriate mitigating measures required by Article 14 (Relief Event Procedures). Section 9.8. TESTING, METERING AND WEIGHING. (A) Testing. The DBOM Contractor shall conduct all tests of Influent, Effluent, Residuals, air emissions and odor in accordance with the Contract Standards. (B) Metering and Weighing. The DBOM Contractor shall maintain in good working order, and repair and replace when necessary, devices capable of (1) metering the continuous and daily total volume of Influent and Effluent and (2) metering or weighing the daily amount of (a) Grit and Screenings transported from the Project Facilities for disposal by the DBOM Contractor, and (b) Sludge and Scum trucked to Portland's Columbia Boulevard Wastewater Treatment Facility for subsequent processing and disposal by the City.The City shall have full access to such meters, instruments, controls, recorders, scales and other metering and weighing devices. All operating data produced by such metering and weighing devices shall be subject to audit, and shall be summarized in the monthly operations reports delivered to the City pursuant to Section 8.11 (Periodic Reports). All such metering and weighing devices shall be 94 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance calibrated to the accuracy required by, and shall be operated and maintained in accordance with the requirements of, the Contract Standards. To the extent any metering or weighing device is incapacitated or is being tested, the DBOM Contractor shall estimate as accurately as practicable the data required by the DBOM Contractor to perform the Operation and Maintenance Services. This estimate and methodology shall, with the City's approval and as allowed under Applicable Law, be used as the basis for determining the operating data required hereunder during the outage. The City shall have the right, at the City's expense, to monitor, inspect and test such metering and weighing devices which are part of the Project at any time and for any purpose and to take measurements regarding Influent, Effluent, and Residuals without unreasonably interfering with the DBOM Contractor's ordinary operations. Section 9.9. RELEASES, LEAKS AND SPILLS. (A) Unauthorized Releases Prohibited. The DBOM Contractor shall operate the Project in such a manner that Influent, Effluent, Residuals and Hazardous Substances will not contaminate, or be bypassed, released, leaked or spilled on or into, the environment, other than as permitted by Applicable Law. (B) Notification and Reporting. The DBOM Contractor shall notify all Governmental Bodies with regulatory jurisdiction in accordance with Applicable Law upon the occurrence of any unauthorized release of Influent, Effluent, Residuals or Hazardous Substances into the environment from or in connection with its operation and management of the Project and shall fulfill all applicable reporting requirements established by Applicable Law with respect thereto. Immediately following the initial notification of the applicable Governmental Body or, to the extent practicable, concurrently therewith, the DBOM Contractor shall notify the City of any such unauthorized release. The DBOM Contractor shall prepare a memorandum evidencing such notification and reporting and provide copies thereof to the City, along with any documents provided to the relevant Governmental Body regarding the release. (C) Cleanup and Costs. The DBOM Contractor shall coordinate with the City and all appropriate Governmental Bodies in effectuating the prompt remediation of any known, unauthorized release of Influent, Effluent, Residuals or Hazardous Substances into the environment from the Project Facilities. The DBOM Contractor shall, in the most expeditious manner possible under the circumstances, cause any Influent, Effluent, Residuals or Hazardous Substances known to be released in violation of this Section to be cleaned up and remediated in accordance with Applicable Law. All costs associated with performing any such cleanup and remediation measures shall be borne by the DBOM Contractor, subject to relief as and to the extent provided in Article 14 (Relief Event Procedures). (D) Indemnification. Subject to subsection 5.6(E) (Exception to DBOM Contractor Assumption of Permitting Risk with Respect to the NPDES Permit) and Section 9.7 (Upsets and Noncompliant Influent Affecting DBOM Contractor Compliance with Performance Guarantees), the DBOM Contractor shall indemnify, defend and hold harmless the City Indemnitees in accordance with and to the extent provided in Article 25 (Indemnification) from and against all Loss-and-Expense that may result from a failure to comply with this Section. Section 9.10. CITY REMEDIES FOR NON-COMPLIANCE WITH PERFORMANCE GUARANTEES. (A) Remedies. If the DBOM Contractor fails to comply with any Performance Guarantee or Applicable Law (as provided for in Section 4.5 (Compliance with Applicable Law)) and is not excused from performance due to the occurrence of a Relief Event as provided in Article 14 (Relief Event Procedures), the DBOM Contractor shall, without relief under any other Performance Guarantee, and in addition to any other remedy provided herein, allowed by 95 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance Applicable Law or required by a Governmental Body: (1) promptly notify the City and all Governmental Bodies with regulatory jurisdiction of any such non-compliance in accordance with the applicable Governmental Approval, but in any event notice shall be provided to the City within 24 hours of the DBOM Contractor having knowledge of the failure of compliance; (2) promptly provide the City within two hours copies of any notices sent to or received from any Governmental Body having regulatory jurisdiction with respect to any violations of Applicable Law; (3) pay any applicable Deductions, indemnification payments or reimbursements specifically provided for herein or have its Service Fee reduced in the amount of such Deductions, indemnification payments or reimbursements; (4) pay any other resulting damages, fines (discretionary or mandatory in nature), levies, assessments, impositions, penalties or other charges resulting therefrom; (5) take any action (including making all capital investments, improvements or modifications, repairs and replacements and operating and management practices changes) necessary in order to comply with such Performance Guarantee, continue or resume performance hereunder and eliminate the cause of, and avoid or prevent the recurrence of non-compliance with such Performance Guarantee; (6) promptly prepare all public notifications required by Applicable Law, and submit such notifications for publication; and (7) assist the City with all public relations matters necessary to adequately address any public concern caused by such non-compliance, including preparation of press releases, attendance at press conferences, and participation in public information sessions and meetings. Any capital investment, improvement or modification required to be made pursuant to this subsection, reasonably expected to result in a material change to the Project, shall be considered a Capital Modification subject to the provisions of Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault). (B) Performance Testing. In the event the City reasonably suspects that the Project is not being operated in compliance with Applicable Law or the Performance Guarantees, the City may require a performance test to be conducted by the DBOM Contractor, at the City's cost and expense, to demonstrate that the Project is operating in compliance with Applicable Law and the Performance Guarantees. The performance tests shall be conducted in the manner provided in Appendix 8 (Commissioning and Acceptance Testing) to the extent applicable. If the test is not successfully passed, the DBOM Contractor shall reimburse the City and, at its own cost and expense, make all necessary repairs and replacements, including major repairs and replacements, and the test shall be re-performed at the DBOM Contractor's sole cost. Section 9.11. ADMINISTRATIVE SANCTIONS. (A) Compliance Failures. The DBOM Contractor shall perform the Operation and Maintenance Services in accordance with the Contract Standards. Except to the extent the DBOM Contractor is relieved for a Relief Event, the DBOM Contractor shall pay the Deductions provided in subsection (B) of this Section for the DBOM Contractor's failures of compliance indicated below: (1) failure to report any exceedance as required by the Contract Standards; (2) failure to calibrate or verify calibration of flow meters as required by Appendix 10 (Operation and Maintenance Requirements); (3) failure to respond within three business days to a written request for information related to this DBOM Agreement made by the City and designated as a "priority request"; (4) failure to provide any plan, proposal, report or other deliverable required hereunder with respect to Relief Events or any regulatory matter by the deadline agreed upon by the parties with respect thereto; 96 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 9 DBOM Agreement Performance (5) failure to keep monthly maintenance logs as required by Section 8.11 (Periodic Reports); (6) failure of DBOM Contractor staff to attend City meetings as reasonably requested, with adequate advance notice from the City; (7) failure to provide any reports required in this DBOM Agreement by the due date; (8) failure to maintain proper certification as required by any Governmental Body; (9) failure to maintain accurate and current maintenance system records, equipment histories, and reports relative to Project Services and make such records (reflecting the full length of the Term) available for review by the City; (10) failure to ensure that the DBOM Contractor, any director, officer, employee, or agent of the DBOM Contractor, or any subcontractor or representative of the DBOM Contractor engaged in the delivery of the Project Services complies with all Contract Standards, including those related to security clearances; personal identification, licensure and access control; training; control and detection of contraband; safety; key control; and tool control; (11) failure to meet any cybersecurity requirements required by the Contract Standards; (12) failure to ensure that all hazard notices and safety signs are maintained, recorded, located, and displayed correctly; (13) failure to respond to alarms at the Project as required hereunder; and (14) failure to properly sample, test or report the results thereof as required by Applicable Law. (B) Deductions. If the DBOM Contractor fails to comply with any of its performance obligations as set forth in subsection (A) of this Section, the City, within 30 days after its discovery of such violation, shall notify the DBOM Contractor in writing of its alleged failure to perform. The DBOM Contractor shall pay to the City, as Deductions, the following amounts: (1) S1,500 (Index-Linked) for the first failure to perform in any Contract Year. (2) $2,000 (Index-Linked) for the second failure to perform in any Contract Year. (3) $4,000 (Index-Linked) for the third and any subsequent failure to perform in any Contract Year. The DBOM Contractor shall have the right to contest the occurrence of any alleged violation or alleged failure to cure, and the DBOM Contractor shall have no obligation to pay such contested amounts until the contest is resolved. The City shall have the right to waive the assessment of Deductions in its sole discretion. 97 3935946.13 043463 ARTICLE 10 MAINTENANCE, REPAIR AND REPLACEMENT Section 10.1. MAINTENANCE, REPAIR AND REPLACEMENT GENERALLY. (A) Ordinary Maintenance. The DBOM Contractor shall perform all normal and ordinary maintenance of the machinery, equipment, structures, improvements and all other property constituting the Project (including the Project Facilities identified in Attachment 1B (Operations and Maintenance Project Site Plan) of Appendix 1 (Site-Related Information)), shall keep the Project in good working order, condition and repair, in a neat and orderly condition and in accordance with the Contract Standards, and shall maintain the aesthetic quality of the Project as originally constructed and in accordance with the Design and Construction Requirements. The DBOM Contractor shall provide or make provisions for all labor, materials, supplies, equipment, spare parts, consumables and services which are necessary for the normal and ordinary maintenance of the Project and shall conduct predictive, preventive and corrective maintenance of the Project as required by the Contract Standards. The DBOM Contractor shall keep maintenance logs in accordance with the requirements set forth in Appendix 10 (Operation and Maintenance Requirements). The ordinary maintenance, repair and replacements described in this subsection shall be included as part of the Operation and Maintenance Charge of the Service Fee and shall not be included as part of the Annual Capital Maintenance Charge. (B) Repair and Maintenance of the Grounds of the Project Site. The DBOM Contractor, in accordance with the Contract Standards, shall keep the grounds of the Project Site in a neat and orderly condition (including the cleanup of litter and debris on a weekly basis or more frequently as required by the Contract Standards). The DBOM Contractor shall also maintain and repair all Project Site fencing and signage and shall provide landscape maintenance (including the plantings provided by the DBOM Contractor along Foothills Road), including the replacement of all dead or dying plants. (C) Major Maintenance, Repair and Replacement by the DBOM Contractor. The DBOM Contractor shall perform all Major Maintenance, Repair and Replacement of the machinery, equipment, structures, improvements and all other property constituting the Project during the Term required under the Contract Standards, including all maintenance, repair and replacement which may be characterized as "major" or "capital" in nature. The City's approval for any such maintenance, repair or replacement shall not be required unless it constitutes a Capital Modification in which event the City shall have the approval rights set forth in Article 11 (Capital Modifications and Operation and Maintenance Services Changes). The obligations of the DBOM Contractor under this Article are intended to assure that the Project is fully, properly and regularly maintained, repaired and replaced in order to preserve its long-term reliability, durability and efficiency, and that in any event the Project at the end of the Term is in a condition that does not require the City to undertake a significant overhaul or immediate replacements in order to continue to provide reasonably priced and efficient wastewater treatment services. Nothing in this subsection shall limit the DBOM Contractor's obligations with respect to the required condition of the Project Structures and the Project Equipment at the end of the Term under Section 10.3 (Project Evaluation). The Service Fee, including payments to the DBOM Contractor requisitioned from the MRR Account in accordance with Section 17.5 (Annual Capital Maintenance Charge), shall constitute the only compensation available to the DBOM Contractor for the performance of its Major Maintenance, Repair and Replacement obligations under this Article. 98 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement Section 10.2. MAJOR MAINTENANCE, REPAIR AND REPLACEMENT SCHEDULE. (A) Major Maintenance, Repair and Replacement Schedule. The Preliminary Operations and Maintenance Plan set forth in Attachment 10A (Preliminary Operations and Maintenance Plan) to Appendix 10 (Operation and Maintenance Requirements) includes a detailed schedule of Major Maintenance, Repair and Replacement which would be required to be performed by the DBOM Contractor over the Term hereof in order to achieve the standard of overall Project maintenance and repair deemed essential by the parties for the proper operability, durability and reliability of the Project over its expected useful life (the "Major Maintenance, Repair and Replacement Schedule"). Without limiting any of the DBOM Contractor's obligations under this Article, the DBOM Contractor shall make and complete all Major Maintenance, Repair and Replacement which are necessary to achieve such standard of repair and replacement by performing Major Maintenance, Repair and Replacement in accordance with the Major Maintenance, Repair and Replacement Schedule, as such schedule may be altered or amended pursuant to subsection (B) of this Section. The DBOM Contractor shall also perform any additional maintenance, repair and replacement work which is necessary in order to comply with the Contract Standards. (B) Major Maintenance, Repair and Replacement Schedule Adjustments. The parties acknowledge that, in light of the long term nature of this DBOM Agreement and the practical limitations on predicting with specificity the useful life of any particular asset, it may be appropriate from time to time to alter the Major Maintenance, Repair and Replacement Schedule. Accordingly, the DBOM Contractor shall have the right to alter the Major Maintenance, Repair and Replacement Schedule at any time during the Term;provided, however, that no such alteration to any component valued at over $50,000 (Index-Linked) on the Major Maintenance, Repair and Replacement Schedule shall be made unless the DBOM Contractor demonstrates to the satisfaction of the City, acting reasonably, that the sum of all Major Maintenance, Repair and Replacement performed to date by the DBOM Contractor, and all Major Maintenance, Repair and Replacement to be performed under any such alterations, shall result in a standard of overall Project maintenance, repair and replacement which is equal to or better than the standard represented by the activities to be performed under the Major Maintenance, Repair and Replacement Schedule. Upon receiving a requested alteration to the Major Maintenance, Repair and Replacement Schedule, the City shall approve or disapprove such alteration within 30 days, or such timeframe as is reasonably agreed to by the parties. Any alterations to the Major Maintenance, Repair and Replacement Schedule shall be reflected in a Contract Administration Memorandum. The DBOM Contractor shall cooperate with the City in identifying any such alterations which may be desirable in order to anticipate or address the technical obsolescence of any component, system or process of the Project, and in proposing such alterations for the City's approval. The parties acknowledge and agree that the City's approval rights pursuant to this subsection apply only to a change to the Major Maintenance, Repair and Replacement Schedule that defers Major Maintenance, Repair and Replacement components that are valued over $50,000 (Index-Linked) beyond the date established in the Major Maintenance, Repair and Replacement Schedule; the DBOM Contractor shall have the right in its discretion to perform any Major Maintenance, Repair and Replacement prior to any date required by the Major Maintenance, Repair and Replacement Schedule. In no event shall any alteration of the Major Maintenance, Repair and Replacement Schedule result in an increase in the amount to be funded or otherwise paid by the City pursuant to Section 17.5 (Annual Capital Maintenance Charge) for any particular Contract Year. Section 10.3. PROJECT EVALUATION. (A) Initial and Final Valuation of Vehicles, Rolling Stock, Spare Parts and Consumables. The DBOM Contractor shall, within 180 days following the Acceptance Date and 99 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement in conjunction with the City, prepare an itemized inventory and valuation of all non-leased vehicles, rolling stock, spare parts and consumables having operational utility and present at the Project as of the Acceptance Date. In like manner, prior to the Termination Date, the DBOM Contractor shall prepare an itemized inventory and valuation of all non-leased vehicles, rolling stock, spare parts and consumables in stock at the Project and having operational utility at the Project which are to be transferred to the City on the Termination Date. The final valuation amount shall be compared to the initial valuation amount as Index-Linked. The amount of any valuation shortfall or excess shall be paid by the DBOM Contractor to the City or by the City to the DBOM Contractor as appropriate, on or before the Termination Date. (B) Baseline Project Record. Concurrently with the inventory and valuation conducted pursuant to subsection (A) of this Section, the DBOM Contractor shall photograph and prepare an itemized inventory of all property constituting the Project, including records of assets originally installed, the manufacturer, identification number and original cost data (the "Baseline Project Record"). The Baseline Project Record shall reflect, based on the Design- Build Price and the Design and Construction Requirements, the condition, functionality, value and estimated useful life of the Project as originally constructed by the DBOM Contractor hereunder. The Baseline Project Record shall be prepared in accordance with the protocol established in Appendix 15 (Project Facilities Evaluation Protocol). The purpose of the Baseline Project Record shall be to establish an informational baseline for determining compliance by the DBOM Contractor with its maintenance, repair and replacement obligations under this Article. (C) Final Evaluation of the Project. Not later than 18 months prior to the Termination Date resulting from the expiration of this DBOM Agreement, the DBOM Contractor shall conduct a final evaluation of the Project in accordance with the protocol established in Appendix 15 (Project Facilities Evaluation Protocol). In connection with the final asset evaluation, the DBOM Contractor shall furnish the City with the Baseline Project Record prepared pursuant to subsection (B) of this Section and all database information developed in connection with the implementation of the CMMS. The evaluation of the Project Structures shall determine and establish the physical condition of the Project Structures. The evaluation of the Project Equipment shall determine and establish the weighted average useful life of the Project Equipment as of the date of evaluation (expressed as a single number of years, carried to one decimal place), taking into account the performance capability and value of each piece of Project Equipment. The final evaluation shall exclude the value of any Capital Modifications, which shall be evaluated separately in accordance with subsection (F) of this Section. (D) Required Condition of Project Structures at the End of the Term. The Project Structures shall at the end of the Term be in good condition, working order and repair as when new,with ordinary wear and tear excepted as determined in light of the DBOM Contractor's maintenance, repair and replacement obligations under this Article. If any periodic inspection establishes that there are Project Structures which fail to meet structural integrity and functionality rankings of 3 or greater, as defined in Appendix 15 (Project Facilities Evaluation Protocol), the DBOM Contractor shall remedy the deficiency in accordance with the provisions of subsection 10.4(C) (Remediation). If the final evaluation establishes that there are Project Structures which fail to meet structural integrity and functionality rankings of 3 or greater, as defined in Appendix 15 (Project Facilities Evaluation Protocol), the DBOM Contractor shall, at the election of the City, either remedy the deficiency or make a cash payment to the City sufficient to enable the City to remedy the deficiency. (E) Required Condition of Project Equipment at the End of the Term. The Project Equipment shall at the end of the Term be in a condition and state of repair such that, in the aggregate, the weighted average useful life of the Project Equipment is equal to or greater than five years. In addition, each blower, standby generator, influent pumps, sludge thickener and the odor control system fans and equipment shall also each have a useful life of at least five years. Such determinations shall be based on the Project Equipment being maintained in a 100 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement manner consistent with Good Operation and Maintenance Practice following the end of the Term. If the final evaluation establishes a maintenance, repair and replacement weighted average useful life deficiency, the DBOM Contractor shall make a cash payment to the City in an amount equal to (i) the actual replacement cost for the Project Equipment multiplied by (ii) one minus the quotient derived by dividing the required weighted average useful life by the actual weighted average useful life determined by the final evaluation. (F) Required Condition of Capital Modifications at the End of the Term. If Capital Modifications constituting Project Structures are made during the Term, such assets shall at the end of the Term be in good condition, working order and repair, with ordinary wear and tear excepted as determined in light of the DBOM Contractor's maintenance, repair and replacement obligations under this Article. If Capital Modifications constituting Project Equipment are made during the Term, such Capital Modifications shall be disregarded in preparing the final evaluation of the Project pursuant to subsection (C) of this Section. The weighted average useful life of all Capital Modifications constituting Project Equipment assets as an aggregate, however, shall be separately determined in the final asset evaluation, and shall be equal to or greater than the weighted average useful life for Project Equipment provided in subsection (E) of this Section. Reasonable conventions may be adopted in the weighting analysis to take account of the varying dates of installation. If the final evaluation establishes a maintenance, repair and replacement weighted average useful life deficiency, the DBOM Contractor shall make a cash payment to the City in an amount equal to (i) the actual replacement cost for Capital Modifications constituting Project Equipment multiplied by (ii) one minus the quotient derived by dividing the required weighted average useful life by the actual weighted average useful life determined by the final evaluation. (G) Exit Testing. Not later than 180 days following the Acceptance Date, the DBOM Contractor shall prepare and submit to the City for its approval a plan for exit testing of the Project, which shall conform to the requirements of Appendix 16 (Exit Testing) in all respects, such approval not to be unreasonably withheld, conditioned or delayed. The City shall submit its comments on the exit testing plan to the DBOM Contractor within 30 days after receipt thereof, and the DBOM Contractor thereafter shall prepare a final exit testing plan, incorporating the City's comments, for submission to the City within 30 days, after receiving the City's comments, if any. In the event the DBOM Contractor has not been in compliance with the Performance Guarantees for the twelve consecutive months preceding the Termination Date, the DBOM Contractor (or a reputable third party with industry experience at the City's option), at the request of the City and after 10 Business Days'notice to the DBOM Contractor, shall perform the exit test of the Project for compliance with the Exit Test Procedures and Standards in the first month of the 3-month period preceding the Termination Date. If such test shows that the Project is operating out of compliance with the Exit Test Procedures and Standards, then within 14 days after such test results, the DBOM Contractor shall submit to the City a plan for remediation and retesting. The City shall have 14 days after receiving the DBOM Contractor's plan to approve such plan, which approval shall not be unreasonably withheld, conditioned or delayed. The DBOM Contractor shall make all capital investment, repairs, replacements, renewals and operating changes necessary and take all other actions which may be necessary to enable the Project to meet the Exit Test Procedures and Standards. The Project shall then be re- tested to demonstrate that the necessary corrective action has been taken and the Project is in compliance with the Exit Test Procedures and Standards. No such testing or retesting shall relieve the DBOM Contractor of its obligations under this DBOM Agreement during the performance of the test or retest. Any capital investment, improvement or modification required to be made pursuant to this subsection, reasonably expected to result in a material change to the Project, shall be considered a Capital Modification subject to the provisions of Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault). 101 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement (H) Termination Letter of Credit. Following completion of the final evaluation of the Project described in subsection (C) of this Section, the City shall in good faith determine and notify the DBOM Contractor, in writing, of the dollar value amount necessary to ensure all Project Structures, Project Equipment and Capital Modifications at the end of the Term are in the condition required by this Section (the "Termination LOC Amount"). Within 15 days after City notifies the DBOM Contractor of the Termination LOC Amount, the DBOM Contractor shall deliver to the City a letter of credit in an amount equal to the Termination LOC Amount, from a Qualified Commercial Bank, in a form reasonably acceptable to the City and on the basis that the City shall be the sole beneficiary thereof (the "Termination Letter of Credit"). The Termination Letter of Credit shall have a term of not less than one year and be continuously renewed, extended or replaced so that it remains in effect until 60 days following the Termination Date or until returned by the City to the DBOM Contractor in accordance with this subsection. If the DBOM Contractor fails to deliver the Termination Letter of Credit to the City in accordance with this subsection, the City shall have the right to hold back and retain from the Service Fee an amount equal to the Termination LOC Amount until the DBOM Contractor delivers the Termination Letter of Credit to the City. On, or within five Business Days after the Termination Date, the City shall either: (1) issue to the DBOM Contractor a certificate confirming compliance with the requirements of this Section and return the Termination Letter of Credit to the DBOM Contractor; or (2) notify the DBOM Contractor of its decision not to issue the certificate, setting out each respect in which the work required by this Section was not properly performed or the Project does not comply with the requirements of this Section and stating the City's estimate of the cost it reasonably believes is necessary to complete all work required for the Project to comply with this Section and the City shall have the right to draw such amount on the Termination Letter of Credit. The City shall have the further right to draw on the Termination Letter of Credit in the full amount of the Termination LOC Amount: (i) if the issuer of the Termination Letter of Credit ceases to be a Qualified Commercial Bank; or (ii) if a notice of non-renewal of the Termination Letter of Credit is received or any required renewal, extension or replacement of the Termination Letter of Credit is not made earlier than the date which is 30 days prior to its expiration date. (I) Disputes. If the City disputes any of the information or conclusions presented by the DBOM Contractor pursuant to this Section, the City shall notify the DBOM Contractor of such dispute and the parties shall use good faith efforts to resolve any dispute. If the parties are unable to resolve the dispute within 30 days after the City's notification, the City shall have the right to appoint an independent evaluator, with sufficient expertise in wastewater treatment plants similar to the Project, to review such information or conclusions. The DBOM Contractor shall have the right to approve the City's selection, the exercise of which shall not unreasonably be withheld or delayed. The expense of the independent evaluator for all services performed pursuant hereto shall be borne equally by the parties. The final determination by the independent evaluator as to any matter arising under this Section involving amounts less than $250,000 which is in dispute between the City and the DBOM Contractor shall be final and binding upon the parties. For disputes involving amounts greater than $250,000, the independent evaluator's determination shall be advisory only. Section 10.4. PERIODIC MAINTENANCE INSPECTIONS. (A) Annual Maintenance Inspection. The City may at its expense, upon fifteen days prior written notice, perform an inspection of the Project and relevant records of the DBOM Contractor each Contract Year to determine compliance with the Contract Standards.The DBOM Contractor shall cooperate fully with the inspections,which shall not interfere unreasonably with the DBOM Contractor's performance of the Operation and Maintenance Services. (B) Full-Scale Inspections. Commencing upon the third anniversary of the Acceptance Date, and every third year thereafter during the Term, the City may request there be a full-scale inspection and review of the state of repair, working condition and performance 102 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement capability of the Project. Any such inspection and review shall be performed by or on behalf of the City at the City's expense, and shall take place at such time as the City shall determine upon 30 days written notice to the DBOM Contractor. The principal purpose of the inspection and review shall be to permit the City to ascertain on a comprehensive and focused basis the extent to which the Project is being properly maintained, repaired and replaced in accordance with the Contract Standards.The inspection shall include a concurrent review of all relevant data, records and reports. The DBOM Contractor shall cooperate fully with the inspections and reviews,which shall not interfere unreasonably with the DBOM Contractor's performance of the Operation and Maintenance Services. (C) Remediation. Based on the annual operation and maintenance reports submitted by the DBOM Contractor pursuant to Section 8.11 (Periodic Reports) or the annual or periodic inspections and reviews conducted pursuant to this Section or any unscheduled inspection provided for herein, the City may submit a statement to the DBOM Contractor detailing any deficiencies found and requiring the DBOM Contractor to submit a plan of remediation. Deficiencies identified by the City shall be limited to (1) Project Structures which fail to meet structural integrity and functionality ratings of 3 or greater, as defined in Appendix 15 (Project Facilities Evaluation Protocol), and (2) items that, if not addressed, could directly affect the performance of the Project and are vital to the successful operation of the Project in accordance with Good Operation and Maintenance Practice. The remediation plan shall be sufficient to reasonably demonstrate that, if implemented, the Project will be promptly brought into compliance with the requirements of this Article. If the City accepts the remediation plan, the DBOM Contractor shall thereupon correct all deficiencies noted in accordance therewith. Failing such corrective action, the Service Fee shall be reduced by the amount of the City's estimated cost of remediation, the City shall have the right to perform any necessary corrective action to bring the Project into compliance with this Article, and the DBOM Contractor shall be responsible for any actual costs incurred by the City in excess of the amount by which the Service Fee has been reduced pursuant to this subsection, subject to Cost Substantiation. If the actual costs incurred by the City are less than the amount by which the Service Fee has been reduced pursuant to this subsection, the DBOM Contractor shall be entitled to the difference between the amount of the Service Fee reduction and the actual costs incurred by the City. (D) Unscheduled Inspections. Nothing in this Section shall limit the City's right, on an unscheduled basis, at any time to inspect the Project and relevant records of the DBOM Contractor to determine compliance with this Article. The DBOM Contractor acknowledges that the City's inspection rights pursuant to this Section are intended solely for the informational purposes of the City to monitor the DBOM Contractor's compliance with its obligations under this Article and agrees that no inspection by the City pursuant to this Section, nor any failure of the City to inspect the Project in accordance with this Section, shall serve to transfer the maintenance, repair and replacement responsibility for the Project from the DBOM Contractor to the City or to limit or otherwise affect the DBOM Contractor's full responsibility for the maintenance, repair and replacement of the Project in accordance with this Article. Section 10.5. COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM. The DBOM Contractor shall, in accordance with Appendix 10 (Operation and Maintenance Requirements), install, maintain, upgrade, repair and replace, as appropriate during the Term, a computerized maintenance management system ("CMMS") capable of providing a record of repair and replacement of the Project on a detailed, item-by-item basis; scheduling, carrying out, monitoring and controlling predictive, preventive and corrective maintenance programs; monitoring routine operations within the Project; issuing work orders and purchase orders; maintaining a spare parts inventory; and issuing exception, equipment status and repair priority reports. The CMMS shall be modified when appropriate during the Term to take account of removals from and additions to the Project. The DBOM Contractor shall utilize the CMMS to provide the City with documentation which allows it to efficiently monitor 103 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 10 DBOM Agreement Maintenance, Repair and Replacement compliance by the DBOM Contractor with its maintenance obligations hereunder. The City shall have computer-based real time, read-only access to such system. The DBOM Contractor shall permit all electronic data to be replicated and provided to the City for review by the City Representative. 104 3935946.13 043463 ARTICLE 11 CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES Section 11.1. CAPITAL MODIFICATIONS GENERALLY. (A) City Approval. Subject to subsection (B) of this Section and Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault), the City shall have the right, in its discretion, to accept, reject, approve or modify all Capital Modifications. All Capital Modifications and related changes to the terms and conditions of this DBOM Agreement shall be reflected in a DBOM Agreement Amendment. (B) Small-Scale Capital Modifications. The City's rights under subsection (A) of this Section with respect to Small-Scale Capital Modifications shall extend only to those affecting the functional or aesthetic quality of the Project. (C) Conditioned Approvals. The City shall have the express right to condition its approval of Capital Modifications upon a sharing of any net cost savings expected to result therefrom or upon any further term or condition that the City may seek to establish with respect thereto. (D) Responsibility for Costs. All Capital Modifications shall be made and implemented in accordance with this Article. The DBOM Contractor shall bear the cost and expense of all Small-Scale Capital Modifications and all Capital Modifications required in accordance with Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault). The responsibility for the cost and expense of any Capital Modifications requested by the DBOM Contractor in accordance with Section 11.2 (Capital Modifications at DBOM Contractor Request) and agreed to by the City shall be borne by the DBOM Contractor unless otherwise agreed to by City in its sole discretion as reflected in a Contract Amendment. The City shall bear the cost and expense of all Capital Modifications made pursuant to Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date) and pursuant to Section 11.5 (Capital Modifications at City Direction). (E) No DBOM Contractor Ownership. In no event shall the DBOM Contractor have any ownership interest in the Project as a result of any Capital Modification. Section 11.2. CAPITAL MODIFICATIONS AT DBOM CONTRACTOR REQUEST. The DBOM Contractor shall give the City written notice of, and reasonable opportunity to review and comment upon, any Capital Modification proposed to be made at the DBOM Contractor's request. To assist the City in the exercise of its approval rights under Section 11.1 (Capital Modifications Generally), the notice shall contain sufficient information for the City to determine that the Capital Modification: (1) Does not materially diminish the capacity of the Project to be operated so as to meet the Contract Standards; (2) Does not materially impair the quality, integrity, durability and reliability of the Project; (3) Is reasonably necessary or is advantageous for the DBOM Contractor to fulfill its obligations under this DBOM Agreement; and 105 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes (4) Is feasible. Section 11.3. CAPITAL MODIFICATIONS ARISING FROM REPAIRS AND REPLACEMENTS OR REQUIRED TO REMEDY A DBOM CONTRACTOR FAULT. In the event that (1) any repair or replacement proposed to be performed by the DBOM Contractor in satisfaction of its obligations under Article 10 (Maintenance, Repair and Replacement), or (2) any capital investment, improvement or modification required to be made by the DBOM Contractor in order to remedy a breach of this DBOM Agreement, can be reasonably expected to result in a material change to the Project, such repair, replacement, capital investment, improvement or modification shall constitute a Capital Modification. The City shall have all approval rights provided under this Article with respect to any such Capital Modifications, including the right to accept, reject or modify any such Capital Modification. In no event shall the rejection or modification of any such Capital Modification by the City relieve the DBOM Contractor of its obligations under this DBOM Agreement. The design and construction costs of any such Capital Modification, and any related operation, maintenance, repair and replacement costs, shall be borne by the DBOM Contractor. Any such Capital Modification, and any related change in the terms and conditions of this DBOM Agreement, shall be reflected in a Contract Amendment. In the event the DBOM Contractor in good faith submits a proposal for a Capital Modification under this Section and such proposal is unreasonably rejected by the City or the City does not respond to the DBOM Contractor within 30 days of submittal of the proposal and all other information that it reasonably requires to review the proposal, the DBOM Contractor shall not incur liquidated damages for the breach that the proposed Capital Modification is intended to remedy during the course of the DBOM Contractor's good faith proposal resubmittal process until the parties reach an agreement on the implementation of such Capital Modification. Section 11.4. CAPITAL MODIFICATIONS, REPAIRS AND REPLACEMENTS REQUIRED DUE TO RELIEF EVENTS OCCURRING FOLLOWING THE ACCEPTANCE DATE. Upon the occurrence of a Relief Event occurring following the Acceptance Date, the DBOM Contractor shall promptly proceed to make or cause to be made all Capital Modifications, repairs and replacements to the Project reasonably necessary to address the Relief Event, as provided in Section 11.6 (Primary Procedure for Implementing Capital Modifications), Article 14 (Relief Event Procedures), Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. The DBOM Contractor and the City shall consult concerning possible means of addressing and mitigating the effect of the Relief Event, and the DBOM Contractor and the City shall cooperate in order to minimize any delay, lessen any additional cost and repair, replace or modify the Project so as to permit the DBOM Contractor to continue providing the Project Services in light of the Relief Event. The design and construction costs resulting from any such work shall be paid by the City as and to the extent provided in Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. Any related operation, maintenance, repair and replacement costs shall be borne by the City (through an adjustment to the Service Fee payable solely following the Acceptance Date), subject to Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), as applicable. The DBOM Contractor shall not be required to undertake any Capital Modification, repair or replacement under this Section unless and until (1)the parties have agreed upon a scope,price and schedule for the implementation of the Capital Modification in accordance with all applicable provisions of this DBOM Agreement including Section 11.6 (Primary Procedure for Implementing Capital Modifications), and (2) the City has provided written assurances that funds necessary to pay the cost of any such work (or agreed- upon portion thereof) will be available for such purposes in the amounts and on the schedule agreed upon by the parties. 106 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes Section 11.5. CAPITAL MODIFICATIONS AT CITY DIRECTION. The City shall have the right to make Capital Modifications at any time and for any reason whatsoever after the Acceptance Date, whether and however the exercise of such rights affects this DBOM Agreement so long as the implementation of such Capital Modification does not contravene the limitations referred to in Section 4.7 (Restrictions on City-Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes). The design and construction costs of any such Capital Modification made at the City's direction under this Section, and any related operation, maintenance, repair and replacement costs, shall be borne by the City. The DBOM Contractor shall not be required to undertake any Capital Modification under this Section unless and until (1)the parties have agreed upon a scope, price and schedule for the implementation of the Capital Modification in accordance with all applicable provisions of this DBOM Agreement including Section 11.6 (Primary Procedure for Implementing Capital Modifications), and (2) the City has provided written assurances that funds necessary to pay the cost of the Capital Modification (or agreed-upon portion thereof) will be available for such purposes in the amounts and on the schedule agreed upon by the parties. Alternatively, the City may implement a Capital Modification through the implementation procedures set forth in Section 11.7 (Alternative Procedures for Implementing Capital Modifications). Section 11.6. PRIMARY PROCEDURE FOR IMPLEMENTING CAPITAL MODIFICATIONS. (A) Primary Implementation Procedure. Subject to Section 11.7 (Alternative Procedures for Implementing Capital Modifications), the implementation procedure set forth in this Section shall apply with respect to all Capital Modifications except Small-Scale Capital Modifications, which the DBOM Contractor may implement by means of its own choosing in accordance with Applicable Law. (B) Initial Assessment. When a Capital Modification is required or is proposed by either party, the DBOM Contractor shall prepare and deliver to the City an initial assessment of the matter. The cost and expense of preparing the initial assessment shall be paid by the City, except (i) if less than 20 professional hours are expended to prepare the initial assessment or (ii) with respect to Capital Modifications made pursuant to Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault)which, in each case, shall be borne by the DBOM Contractor. The initial assessment shall describe the need for or objective of the Capital Modification, set forth an overview of potential approaches to addressing the need or objective, and contain a preliminary assessment of potential cost and schedule considerations. The purpose of the initial assessment shall be to furnish the City with a reasonable basis for authorizing funds to pay for a conceptual plan and implementation proposal provided for in subsection (C) and subsection (D) of this Section with respect to Capital Modifications for which the City has payment responsibility. (C) DBOM Contractor Conceptual Plan and City Review. Following the initial assessment made pursuant to subsection (B) of this Section, at the request of the City and, except with respect to Capital Modifications made pursuant to Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault) at the cost and expense of the City, the DBOM Contractor shall prepare and deliver to the City a conceptual plan for the implementation of the Capital Modification. The conceptual plan shall include the DBOM Contractor's recommendations as to technology, design, construction, equipment, materials, and operating and performance impacts. The foregoing recommendations shall seek to allow for maximum competition in price and shall not favor the DBOM Contractor or any of its Affiliates. Preliminary schedule and capital and operating cost estimates shall be included, together with an assessment of possible alternatives. The conceptual plan shall 107 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes specifically evaluate reasonable alternatives to the mix of Capital Modifications and changed operating and management practices which the DBOM Contractor is recommending. The City shall review the DBOM Contractor's conceptual plan and recommendations and undertake discussions with the DBOM Contractor in order to reach agreement on a basic approach to the Capital Modification. (D) DBOM Contractor Implementation Proposal. Following agreement on a basic approach to the Capital Modification, at the request of the City and, except with respect to Capital Modifications made pursuant to Section 11.3 (Capital Modifications Arising from Repairs and Replacements or Required to Remedy a DBOM Contractor Fault), at the City's expense, the DBOM Contractor shall prepare on an open book (as defined below) basis and submit a formal implementation proposal to the City for its consideration. With respect to any Capital Modification to be undertaken at the City's expense and as otherwise required by Applicable Law, the implementation proposal shall contain (1) a DBOM Contractor services element, to be implemented through a DBOM Agreement Amendment and/or (2) a third-party services element, to be implemented through third-party contracting. (1) DBOM Contractor Services Element. The DBOM Contractor services element shall contain: (a) the DBOM Contractor's offer to perform design, construction management, commissioning and acceptance test services and obtain and maintain DBOM Contractor Managed Governmental Approvals with respect to the Capital Modification for a fixed price (or, if requested by the City, a guaranteed maximum price), and shall include a guarantee of the performance of the Capital Modification through an acceptance test; (b) as applicable, the DBOM Contractor's offer to operate, maintain, repair, replace, permit and manage the Capital Modification following construction and commissioning for compensation paid as an adjustment to the Operation and Maintenance Charge and Annual Capital Maintenance Charge with a revision of the composition or weighting of the indices used to adjust the Operation and Maintenance Charge in Section 17.3 (Operation and Maintenance Charge) and the Annual Capital Maintenance Change in Section 17.5 (Annual Capital Maintenance Charge), as appropriate, and shall include long-term performance guarantees appropriate to the Capital Modification; and (c) as applicable, the DBOM Contractor's proposed adjustment to the Guaranteed Maximum Electricity Consumption in subsection 9.4(A) (Guaranteed Maximum Electricity Consumption Calculation) appropriate to the Capital Modification. (2) Third-Party Services Element. The third-party services element shall be a proposal by the DBOM Contractor to conduct, as allowed by Applicable Law, either a qualifications-based selection process for design engineers and a bidding process for the construction work or a competitive proposal process for the design-build work involved in completing the Capital Modification. The resulting design services and construction contracts or design-build contract shall be held by and executed in the name of the DBOM Contractor, unless required to be held by the City under Applicable Law. A "competitive proposal process" referred to herein may include a qualifications-based request for proposals and a design-build contract award to the most advantageous proposer. For purposes of this Section, "open book" shall mean providing to the City: (i) all underlying information and data associated with pricing or compensation or adjustments thereto, including assumptions, bids, quotes and proposals for the design, construction management, commissioning, acceptance testing, operation, maintenance, repair, replacement and permitting services associated with the proposed Capital Modification; and (ii) schedule, composition of equipment spreads, equipment rates, labor rates, productivity, estimating factors, design and productivity allowance, contingency and indirect costs, allocation of corporate overhead, risk pricing, discount rates, interest rates, and other items reasonably required by the City to satisfy itself as to the reasonableness of the pricing or compensation amount. A Capital Modification 108 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes implementation proposal shall include a detailed and comprehensive open book description of how the proposed pricing set forth therein was derived and the material factors on which it was based, together with all other related information required pursuant to this Section. All costs, bids, quotes, estimates, and other information supporting the Capital Modification implementation proposal shall be made available to the City. The Capital Modification implementation proposal may include a mark-up on the aggregate direct costs incurred by the DBOM Contractor as full payment for all other costs, including indirect overhead costs and profit in accordance with subsection 26.7(E) (Mark-Ups). (E) Negotiation and Finalization of DBOM Contractor Implementation Proposal. The parties shall proceed, promptly following the City's review of the DBOM Contractor's submittal and quotation, to negotiate on an open book basis to reach an agreement on price and any adjustment to the terms and conditions of this DBOM Agreement resulting from the Capital Modification. Any final negotiated agreement for the implementation of a Capital Modification under this Section shall address, as applicable: (1) Design requirements; (2) Construction management services; (3) Commissioning procedures; (4) A guarantee of completion; (5) Performance guarantees; (6) Acceptance tests; (7) Any changes to the Contract Standards to take effect as a consequence of the Capital Modification; (8) A payment schedule for the design and construction management-related services; (9) Any adjustments to the Service Fee resulting from the Capital Modification, including any related operation, maintenance, repair and replacement costs; (10) Any adjustments to the Annual Capital Maintenance Charge for Major Maintenance, Repair and Replacements associated with the Capital Modification; (11) Any adjustments to the Guaranteed Maximum Electricity Consumption associated with the Capital Modification; and (12) Any other appropriate amendments to this DBOM Agreement. The DBOM Contractor shall not be obligated to undertake any Capital Modification under Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date) or Section 11.5 (Capital Modifications at City Direction) except following agreement as to scope, price and schedule and the delivery by the City of assurances as to the availability of funds, as provided in such Sections. Except as provided in subsection (D) of this Section, the City shall have no obligation to reimburse the DBOM Contractor for any costs incurred pursuant to this Section except as part of a negotiated DBOM Agreement Amendment. 109 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes (F) Implementation Procedures. With respect to each Capital Modification to be made by the DBOM Contractor, other than Small-Scale Capital Modifications, the City shall have the same substantive and procedural rights that it has with respect to the design, construction, commissioning, acceptance testing and final completion of the Project, as set forth in this DBOM Agreement. (G) Nutrient Removal Capital Modifications. Subject to Section 11.7 (Alternative Procedures for Implementing Capital Modifications), the implementation procedure set forth in this Section shall apply with respect to any Capital Modifications needed to comply with the NPDES Permit or Applicable Law in the event that the NPDES Permit or Applicable Law require the implementation of phosphorus and/or ammonia treatment at the Wastewater Treatment Facility after the Acceptance Date. Section 11.7. ALTERNATIVE PROCEDURES FOR IMPLEMENTING CAPITAL MODIFICATIONS. With respect to any Capital Modification to be undertaken at the City's expense and as otherwise required by Applicable Law, the City shall be under no obligation to utilize the primary implementation procedure for Capital Modifications set forth in Section 11.6 (Primary Procedure for Implementing Capital Modifications), and may instead, in its discretion, utilize any other implementation procedure available to it or required under Applicable Law. Alternative implementation procedures may include contracting with the DBOM Contractor (including on a Cost Substantiation basis) or any third party to implement the Capital Modification on a sole source or any competitive basis using any project delivery method available under Applicable Law. The City may determine to proceed with an alternative implementation procedure for Capital Modification at any time, whether before or after entering into negotiations with the DBOM Contractor under the primary implementation procedure specified under Section 11.6 (Primary Procedure for Implementing Capital Modifications). No alternative implementation procedure for Capital Modifications shall contravene the limitations referred to in Section 4.7 (Restrictions on City-Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes). Section 11.8. OPERATION AND MAINTENANCE SERVICES CHANGES. (A) Generally. The City may require the DBOM Contractor, at the City's expense, to implement an Operation and Maintenance Services Change in accordance with this Section but only if the implementation of a City requested Operation and Maintenance Services Change does not: (i) contravene the limitations referred to in Section 4.7 (Restrictions on City- Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes), (ii) impair or interfere with the DBOM Contractor's ability to meet the Contract Standards, (iii) impair or interfere with the DBOM Contractor's ability to perform its maintenance, repair and replacement obligations required under Article 10 (Maintenance, Repair and Replacement), or (iv) impair or interfere with the DBOM Contractor's ability to perform any other obligation under this DBOM Agreement. In the event the City requests an Operation and Maintenance Services Change, the City shall issue to the DBOM Contractor a written notice including a sufficient description of the contemplated Operation and Maintenance Services Change. (B) DBOM Contractor Operation and Maintenance Services Change Report. Within 15 Business Days, or such longer period as the parties agree acting reasonably, after receipt of the City's notice delivered pursuant to subsection (A) of this Section, the DBOM Contractor shall prepare and deliver to the City a report for the contemplated Operation and Maintenance Services Change ("Operation and Maintenance Services Change Report"). An 110 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes Operation and Maintenance Services Change Report shall include, to the extent that it is relevant to the proposed Operation and Maintenance Services Change: (1) A description of the scope of the contemplated Operation and Maintenance Services Change with respect to the Operation and Maintenance Services; (2) A comparison of the scope of Operation and Maintenance Services as a result of the contemplated Operation and Maintenance Services Change as compared to the scope prior to the Operation and Maintenance Services Change; (3) An estimate of all costs, if any, reasonably necessary for and directly associated with the contemplated Operation and Maintenance Services Change, as further described in subsection (C) of this Section, including the following, as applicable: (a) all Operation and Maintenance Services labor, material and equipment costs, supported as the case may be by quotations from the applicable Subcontractors; (b) all costs of an amendment or renewal of a Governmental Approval required by the contemplated Operation and Maintenance Services Change; and (c) all insurance costs; (4) An estimate of the cost savings, if any, resulting from the contemplated Operation and Maintenance Services Change; (5) A description of any changes to the Service Fee that are required to reflect any costs or cost savings described in items (3) and (4) above; (6) Identification of any amounts payable by the City to the DBOM Contractor, if any, other than the Service Fee; (7) The value of the loss or reduction of benefits resulting from the contemplated Operation and Maintenance Services Change; (8) A description of any additional consents or approvals required, including amendments, if any, of any Governmental Approvals required to implement the contemplated Operation and Maintenance Services Change; (9) A description of the extent to which the contemplated Operation and Maintenance Services Change or the implementation thereof would interfere with the DBOM Contractor's ability to comply with any of its obligations under this DBOM Agreement, the Material Contracts and any Governmental Approvals; (10) A description of any further effects (including, without limitation, benefits and impairments) which the DBOM Contractor foresees as being likely to result from the contemplated Operation and Maintenance Services Change or the implementation thereof; (11) A description of any actions that would be reasonably required by the City to implement the contemplated Operation and Maintenance Services Change; 111 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes (12) A description of the steps the DBOM Contractor will take to implement the contemplated Operation and Maintenance Services Change, in such detail as is reasonable and appropriate; (13) All proposed revisions to the Operation and Maintenance Plan and the Operation and Maintenance Manual; and (14) A description of any impact on expected usage of Utilities for the current Contract Year and subsequent Contract Years. If the DBOM Contractor prepares an Operation and Maintenance Services Change Report pursuant to this subsection and the City elects not to proceed with the contemplated Operation and Maintenance Services Change, then the City shall pay the DBOM Contractor's Operation and Maintenance Services Change Report preparation costs subject to Cost Substantiation. Notwithstanding the foregoing, the City shall not be responsible for any DBOM Contractor costs associated with an Operation and Maintenance Services Change Report prepared pursuant to subsection (J) of this Section. (C) Valuation of Operation and Maintenance Services Changes. The City and the DBOM Contractor shall negotiate in good faith the costs or savings associated with any Operation and Maintenance Services Change in accordance with subsection (E) of this Section. If the parties fail to agree on the costs or savings of such Operation and Maintenance Services Change, the costs or savings shall be determined as set forth in this subsection. The costs or savings of an Operation and Maintenance Services Change shall be the net incremental additional costs or savings of implementing the Operation and Maintenance Services Change, calculated as the aggregate cost, if any, of any additions to the DBOM Contractor's Operation and Maintenance Services obligations required to implement the Operation and Maintenance Services Change minus the aggregate cost savings, if any, from all reductions in the DBOM Contractor's Operation and Maintenance Services obligations resulting from the implementation of such Operation and Maintenance Services Change. An Operation and Maintenance Services Change may have a net cost, a net saving, or may result in no net cost or saving. The costs of an Operation and Maintenance Services Change are the aggregate of the costs reasonably incurred by the DBOM Contractor to implement the Operation and Maintenance Services Change, supported by invoices, purchase orders, time sheets and other reasonable documentation, as follows: (1) The amounts of all Subcontractor or supplier agreements; (2) The direct costs incurred for the Operation and Maintenance Services personnel, based on the number of personnel hours required to undertake the Operation and Maintenance Services Change; (3) The direct costs incurred for the procurement of materials, consumables and equipment, for the supply and delivery of such materials, consumables and equipment, including the costs of any associated testing, commissioning, spare parts, manuals and software, and including any related design and engineering costs; (4) All other additional direct costs pertaining to the Operation and Maintenance Services Change, including the costs incurred or borne by the DBOM Contractor in preparing an Operation and Maintenance Services Change Report. The costs applied pursuant to this subsection shall be no greater than the market rates prevailing at the time of the implementation of the Operation and Maintenance Services Change paid between parties contracting at arm's length. In addition to the direct costs incurred by the 112 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes DBOM Contractor, a mark-up shall be applied without duplication to such aggregate costs as full payment for all other costs, including indirect overhead costs and profit in accordance with subsection 26.7(E) (Mark-Ups). (D) Justification and Supporting Documentation. The DBOM Contractor shall use reasonable efforts to obtain competitive quotations and proposals for all work, equipment and materials required to implement an Operation and Maintenance Services Change. The cost estimates included in an Operation and Maintenance Services Change Report shall be in sufficient detail to allow evaluation by the City and will include such supporting information and justification as is reasonably necessary to demonstrate that: (1) The DBOM Contractor has used all reasonable efforts, including utilizing competitive quotes or proposals, to minimize the cost of a contemplated Operation and Maintenance Services Change and maximize potential related cost savings; (2) The DBOM Contractor have valued the Operation and Maintenance Services Change as described in subsection (C) of this Section, and have not included other margins or mark-ups; (3) The full amount of any and all expenditures that have been reduced or avoided (including any capital expenditures in accordance with GAAP) have been fully taken into account; and (4) The DBOM Contractor has mitigated or will mitigate the impact of the contemplated Operation and Maintenance Services Change, including on the performance of the Operation and Maintenance Services, the expected usage of Utilities, and the direct costs to be incurred. (E) Agreement on an Operation and Maintenance Services Change. Within 15 Business Days, or such longer period as the parties agree acting reasonably, following receipt by the City of an Operation and Maintenance Services Change Report prepared in accordance with subsection (B) of this Section, the City may deliver to the DBOM Contractor any requests for clarifications or amendments, and the parties'representatives shall meet and use all reasonable efforts to agree to the Operation and Maintenance Services Change Report. Such agreement shall include the costs, payments (including payment of direct costs and adjustments to the Service Fee, if any) and other information contained in the Operation and Maintenance Services Change Report. If the City would be required by Applicable Law to require the DBOM Contractor to competitively solicit any contract in relation to a contemplated Operation and Maintenance Services Change, the City may require the DBOM Contractor to seek and evaluate competitive proposals for the proposed Operation and Maintenance Services Change. The City may modify any Operation and Maintenance Services Change request notice delivered pursuant to subsection (A) of this Section, in writing, at any time prior to the parties reaching an agreement on the Operation and Maintenance Services Change Report pursuant to this subsection. In the event the City delivers notice of any such modification to the DBOM Contractor, the DBOM Contractor shall notify the City of any significant changes to the Operation and Maintenance Services Change Report within 20 Business Days after receipt of such modification notice. (F) Operation and Maintenance Services Change Certificate. Upon agreement of the parties with respect to the Operation and Maintenance Services Change in accordance with subsection (E) of this Section, the City shall issue a signed Operation and Maintenance Services Change Certificate to the DBOM Contractor. In the event the City and the DBOM Contractor do not agree on the Operation and Maintenance Services Change, the City may issue an Operation and Maintenance Services Change Certificate in accordance with subsection (G) of this Section. The DBOM Contractor shall not proceed with an Operation and Maintenance 113 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes Services Change prior to receiving a signed Operation and Maintenance Services Change Certificate from the City. An Operation and Maintenance Services Change Certificate issued in accordance with this subsection shall be binding upon the City and the DBOM Contractor. Upon receipt of an Operation and Maintenance Services Change Certificate the DBOM Contractor shall implement the Operation and Maintenance Services Change, without prejudice to the DBOM Contractor's right to refer any dispute concerning the Operation and Maintenance Services Change to Non-Binding Mediation, including valuation of the Operation and Maintenance Services Change in accordance with subsection (C) of this Section. (G) Disagreement on Operation and Maintenance Services Change Report. In the event the City and the DBOM Contractor cannot agree on an Operation and Maintenance Services Change Report, the City may elect not to proceed with the Operation and Maintenance Services Change described in the notice delivered to the DBOM Contractor in accordance with subsection (A) of this Section. Alternatively, the City may issue the Operation and Maintenance Services Change Certificate to the DBOM Contractor stating the City's determination of the matters referred to in the Operation and Maintenance Services Change Report, and if the DBOM Contractor disagrees with all or any of the determinations set forth in the Operation and Maintenance Services Change Certificate, then the DBOM Contractor may deliver the City a notice identifying any such disagreements within 10 Business Days of receipt of the Operation and Maintenance Services Change Certificate. Following delivery of the notice to the City identifying any points of disagreement to the Operation and Maintenance Services Change Certificate, the DBOM Contractor may, (1) pursuant to its rights under Section 4.7 (Restrictions on City-Directed Design and Construction Requirement Changes, Capital Modifications and Operation and Maintenance Services Changes) refuse to implement the Operation and Maintenance Services Change, or (2) without prejudice to its rights with respect to such disagreements, use all reasonable efforts to implement the Operation and Maintenance Services Change as directed in the Operation and Maintenance Services Change Certificate. If the DBOM Contractor fails to timely deliver the notice to the City identifying any points of disagreement with the Operation and Maintenance Services Change Certificate as set forth in this subsection, the DBOM Contractor shall be deemed to have waived any such objections to the Operation and Maintenance Services Change Certificate. (H) Responsibility and Payment for Operation and Maintenance Services Changes. Except as specifically provided in this DBOM Agreement, the City shall bear no risk or liability whatsoever arising from any Operation and Maintenance Services Change other than the liability to make payment in connection therewith. Subject to subsection (J) of this Section, the City shall bear the cost and expense of all Operation and Maintenance Services Changes made pursuant to this Section. Payments by the City and any adjustments to the Service Fee with respect to Operation and Maintenance Services Changes shall be made in accordance with Section 17.7 (Extraordinary Items) and Section 26.7 (Cost Substantiation of Additional Work Not Subject to Lump Sum Price Negotiation). (I) Cost Savings. In the event any Operation and Maintenance Services Change is reasonably expected to result in a net cost savings to the DBOM Contractor,the parties shall negotiate in good faith the extent to which any such net cost savings shall be allocated to the City, and the Service Fee shall be reduced accordingly. (J) Operation and Maintenance Services Changes at DBOM Contractor Request. The DBOM Contractor may give the City written notice of, and reasonable opportunity to review and comment upon, any Operation and Maintenance Services Change proposed to be made at the DBOM Contractor's request. The City shall have the right, in its discretion, to accept, reject, approve or modify all such Operation and Maintenance Services Change requests made by the DBOM Contractor. The responsibility for the cost and expense of any Operation and Maintenance Services Change requested by the DBOM Contractor in accordance with this 114 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 11 DBOM Agreement Capital Modifications and Operation and Maintenance Services Changes subsection shall be borne by the DBOM Contractor unless otherwise agreed to by the City in its sole discretion. The written notice provided by the DBOM Contractor shall contain sufficient information for the City to determine that the Operation and Maintenance Services Change: (1) Does not diminish the capacity of the Project to be operated so as to meet the Contract Standards; (2) Does not impair the quality, integrity and reliability of the Operation and Maintenance Services; (3) Is reasonably necessary or is advantageous for the DBOM Contractor to fulfill its obligations under this DBOM Agreement; and (4) Is feasible. Any Operation and Maintenance Services Change proposed to be made at the DBOM Contractor's request, and accepted by the City, shall be implemented as set forth in this Section, except that the notice provided by the DBOM Contractor pursuant to this subsection shall take the place of the notice provided by the City pursuant to subsection (A) of this Section. Section 11.9. FINANCING CAPITAL MODIFICATIONS AND OPERATION AND MAINTENANCE SERVICES CHANGES. (A) Financing Responsibilities. The City shall provide financing or secure an appropriation for any Capital Modification or Operation and Maintenance Services Change for which it is financially responsible under this DBOM Agreement, and shall make the proceeds of the financing or appropriation available to the DBOM Contractor to pay the negotiated price based on the requirements of Applicable Law. The DBOM Contractor shall finance and pay for any Capital Modification or Operation and Maintenance Services Change for which it is financially responsible under this DBOM Agreement without reimbursement from or other claim upon the City. (B) Third Party Borrowing or Financing. Unless otherwise approved by the City in its discretion, the DBOM Contractor shall not borrow from any third party to finance any cost or expense required to be borne by the DBOM Contractor under subsection 11.1(D) (Responsibility for Costs) or Section 11.8 (Operation and Maintenance Services Changes). In no event shall the DBOM Contractor have any ownership interest in the Project as a result of any Capital Modification or Operation and Maintenance Services Change undertaken by the DBOM Contractor under this Article. The City shall have the right to condition its approval of any third party borrowing or financing on any stipulation, term or condition that the City considers necessary or desirable in order to maintain its interest in and ownership of the Project. Notwithstanding the foregoing, the DBOM Contractor may borrow from an Affiliate of the DBOM Contractor to finance any cost or expense required to be borne by the DBOM Contractor under this DBOM Agreement without the approval of the City; provided however, that no such borrowing may create, grant or in any way establish any mortgage, Lien, security interest or other Encumbrance on or in this DBOM Agreement, the payments to be received by the DBOM Contractor under this DBOM Agreement, the Project or any City Property. 115 3935946.13 043463 ARTICLE 12 CONTRACTING AND LABOR PRACTICES Section 12.1. USE OF SUBCONTRACTORS. (A) Subcontractors. The City acknowledges that the DBOM Contractor may carry out portions of the Design-Build Work and the Operation and Maintenance Services by contracting such obligations to Subcontractors. (B) Use of Subcontractors and Key Individuals. The DBOM Contractor shall use the Subcontractors and Key Individuals listed in Appendix 19 (DBOM Contractor and Subcontractors Information) or such others as the City may approve, acting reasonably and without unreasonable conditions or delay, for the performance of the Project Services in the roles indicated in Appendix 19 (DBOM Contractor and Subcontractors Information). (C) Restricted Persons. In providing the Project Services, the DBOM Contractor shall not contract with, or allow any of its Subcontractors to contract with, any person that at the time of such contracting, in the reasonable opinion of the City, is a Restricted Person. (D) Oregon Construction Contractors Board. The DBOM Contractor shall ensure that all Subcontractors performing Project Services described in ORS 701.005(2) will be registered with the Oregon Construction Contractors Board in accordance with ORS 701.035 to ORS 701.055 before the Subcontractors commence any Project Services. Section 12.2. SUBCONTRACTS. (A) Terms and Actions. The DBOM Contractor shall retain full responsibility to the City under this DBOM Agreement for all matters related to the Project Services. No failure of any Subcontractor used by the DBOM Contractor in connection with the provision of the Project Services shall relieve the DBOM Contractor from its obligations hereunder to perform the Project Services. The DBOM Contractor shall be responsible for settling and resolving with all Subcontractors all claims arising from the actions or inactions of the DBOM Contractor or a Subcontractor. (B) Indemnity for Claims. The DBOM Contractor shall pay or cause to be paid to all Subcontractors all amounts due in accordance with their respective Subcontracts. No Subcontractor shall have any right against the City for labor, services, materials or equipment furnished for the Project Services. The DBOM Contractor acknowledges that its indemnity obligations under Section 25.1 (DBOM Contractor's Obligation to Indemnify) shall include all claims for payment or damages by any Subcontractor who furnishes or claims to have furnished any labor, services, materials or equipment in connection with the Project Services to the extent that those claims fall within the scope of the indemnity in Section 25.1 (DBOM Contractor's Obligation to Indemnify). (C) Assignability. All Subcontracts entered into by the DBOM Contractor with respect to the Project shall be assignable to the City, solely at the City's election and without cost or penalty, upon the expiration or termination of this DBOM Agreement. (D) DBOM Contractor Payment Requirements in General. As required in ORS 279C.505(1), the DBOM Contractor shall (1) make payment promptly, as due to all persons and Subcontractors supplying the DBOM Contractor labor or material for the performance of the Project Services, (2) pay all contributions or amounts due to the Oregon Industrial Accident Fund from the DBOM Contractor or Subcontractor incurred in the performance of the Project Services, 116 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 12 DBOM Agreement Contracting and Labor Practices if any; (3) not permit any lien or claim to be filed or prosecuted against the City, the State or a county, school district, municipality, municipal corporation or subdivision thereof, on account of any labor or material furnished to the Project; and (4) pay to the Oregon Department of Revenue all sums withheld from employees as required under ORS 316.167. (E) Subcontractor Timely Payment Requirements. As required by ORS 279C.515(2), the DBOM Contractor shall include in all of its Subcontracts and shall require that all Subcontractors include in all of their Subcontracts, a payment clause that obligates the applicable Subcontractor to pay its Subcontractors for satisfactory performance under its Subcontract within ten days after such amounts are paid by the DBOM Contractor to the Subcontractor. If a Subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with this DBOM Agreement within 30 days after receiving payment from the DBOM Contractor, then the Subcontractor shall owe such person the amount due plus interest charges that begin at the end of the 10-day period within which payment is due under ORS 279C.580(4) and that end upon final payment, unless payment is subject to a good faith dispute as defined in ORS 279C.580. The rate of interest on the amount due shall be 9% per annum. The amount of interest may not be waived. (F) Right to File a Complaint with the Oregon Construction Contractors Board. As required by ORS 279C.515(3), if the DBOM Contractor or a Subcontractor fails, neglects or refuses to make payment to a person furnishing labor or materials in connection with this DBOM Agreement, such person may file a complaint with the Oregon Construction Contractors Board, unless payment is subject to a good faith dispute as defined in ORS 279C.580. Section 12.3. MATERIAL CONTRACTS. (A) City Consents. Unless the DBOM Contractor has, at its earliest practicable opportunity, submitted to the City notice of the proposed course of action (and any relevant documentation) and the City has consented to such course of action, such consent not to be unreasonably withheld, conditioned or delayed, the DBOM Contractor shall not: (1) Terminate, or agree to or permit the termination of, all or any material part of any Material Contract; (2) Make, or agree to or permit the making of: (a) any material amendment of any Material Contract; or (b) any departure by any party from any material provision of any Material Contract; (3) Permit a Material Contract party to assign or transfer to any person any of the Material Contract party's rights or obligations under the Material Contract other than by way of a Subcontract that is not a subcontract of all or substantially all of the obligations under the Material Contract; or (4) Enter into, or permit the entering into, any Material Contract other than those entered on or before the Effective Date. (B) Timeframe for Consents. The City shall give or deny such consent within: (1) 5 Business Days of receipt of such notice and all relevant documentation, if the DBOM Contractor is seeking to immediately terminate a Material Contract for Design-Build Work during the Design-Build Period; 117 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 12 DBOM Agreement Contracting and Labor Practices (2) 10 Business Days of receipt of such notice and all relevant documentation, if the DBOM Contractor is seeking to immediately terminate a Material Contract for Operation and Maintenance Services during the Operations and Maintenance Period; and (3) 20 Business Days of receipt of such notice and all relevant documentation in all other cases. If the City fails to give or deny its consent within such time periods it shall be deemed to have given its consent. The giving or denial of consent by the City shall not create any liability of the City to the DBOM Contractor or to any third party. (C) Costs of Request for Consent. The DBOM Contractor shall pay, without duplication, the City's reasonable out-of-pocket costs in connection with considering any request for consent by the DBOM Contractor pursuant to this Section. At the time of the request, the DBOM Contractor shall make a payment to the City against its obligation under this Section of $25,000 (Index-Linked). After the City's decision is rendered, the City will either refund any overpayment or invoice the DBOM Contractor for any additional amounts due under this Section with reasonable substantiation of such costs. Section 12.4. REPLACEMENT MATERIAL CONTRACTS. If any Material Contract at any time lapses, terminates, or otherwise ceases to be in full force and effect (whether by reason of expiration or otherwise), unless the goods, services or rights which were the subject matter of such Material Contract are no longer reasonably required for the Project, the DBOM Contractor will forthwith enter into, or cause to be entered into, a replacement contract or contracts upon substantially similar terms as the contract so replaced (to the extent reasonably practicable). If at any time any amendment is made to any Material Contract, or a replacement Material Contract (or any agreement which materially affects the interpretation or application of any Material Contract) is entered into, the DBOM Contractor shall deliver to the City a copy of each such amendment or agreement within 10 Business Days of the date of its execution or creation. Section 12.5. EQUITY, INCLUSION AND DIVERSITY SUBCONTRACTING REQUIREMENTS. The DBOM Contractor shall comply with all requirements related to equity, inclusion and diversity subcontracting, if and to the extent, required under the WIFIA program. Section 12.6. DESIGN-BUILD WORK LABOR AND WAGE REQUIREMENTS. (A) Payment of Prevailing Wages; Recordkeeping Requirements. To the extent not preempted by federal prevailing wage requirements pursuant to subsection 4.5(G) (Water Infrastructure Finance and Innovation Act(WIFIA)), the DBOM Contractor shall comply fully with the prevailing wage provisions of ORS 279C.800 through ORS 279C.870. Pursuant to ORS 279C.830(1)(d), the DBOM Contractor shall pay workers at not less than the specified minimum hourly rate of wage for workers at the Project Site in the job classifications covered thereto, and shall include such requirement in all Subcontracts. Where rates for any class of workers differ between State and federal wage requirements, the higher of the applicable State or federal rate is required to be paid pursuant to ORS 279C.830(1)(d). The DBOM Contractor shall cause a copy of the prevailing rates of wages to be posted at the Project Site, shall keep and maintain payroll and other relevant information in order to permit the City to monitor compliance with 118 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 12 DBOM Agreement Contracting and Labor Practices this requirement, and shall furnish certified copies of such payrolls and other information to the City or its designee upon request. (B) Public Works Bond to Assume Payment of Prevailing Wages. As required by ORS 279C.830(2) and ORS 279C.836, the DBOM Contractor shall file with the Oregon Construction Contractors Board, and maintain in full force and effect, a public works bond in the stated amount of$30,000 while completing the Design-Build Work. The DBOM Contractor shall also include in every Subcontract a provision requiring such contractor to have a public works bond filed with the Oregon Construction Contractors Board before starting any Design- Build Work, unless otherwise exempt, and shall verify that the Subcontractor has filed a public works bond before permitting any Subcontractor to commence any Design-Build Work. Such public works bonds shall be subject to the notice of claim requirements set forth in ORS 279C.605. Section 12.7. LABOR RELATIONS AND DISPUTES. (A) Labor Relations. The DBOM Contractor shall furnish labor that can work in harmony with all other elements of labor employed for the performance of the Project Services. The DBOM Contractor shall have exclusive responsibility for disputes or jurisdictional issues among unions or trade organizations representing employees of the DBOM Contractor, the Subcontractors. The City shall have no responsibility whatsoever for any such disputes or issues and the DBOM Contractor shall indemnify, defend and hold harmless the City and the City Indemnitees in accordance with Section 25.1 (DBOM Contractor's Obligation to Indemnify) from any and all Loss-and-Expense resulting from any such labor dispute, except to the extent that such labor dispute is an Other Relief Event. (B) Labor Disputes. If the DBOM Contractor has knowledge of an actual or potential labor dispute that may affect any of the Project Services, the DBOM Contractor shall promptly: (1) Give notice thereof to the City, including all relevant information related to the dispute of which the DBOM Contractor has knowledge; and (2) Take all reasonable steps to ensure that such labor dispute does not affect the performance of any of the Project Services including by applying for relief to appropriate tribunals or courts. The DBOM Contractor acknowledges that if the labor dispute involves workers of a Subcontractor, or of anyone employed by or through them, the City will not be required to provide any facilities, space or assistance in the Project or on the Project Site for the purposes of such workers or any applicable union. Section 12.8. OVERTIME. (A) Employee Overtime Requirements. As required by ORS 279C.520(1)(a), ORS 279C.520(5), ORS 279C.540 and ORS 279C.545 with respect to construction work, the DBOM Contractor may not employ an employee for more than 10 hours in any one day, or 40 hours in any one week, except in cases of necessity, emergency or when the public policy absolutely requires otherwise, and in such exceptional cases, the DBOM Contractor shall pay the employee at least time and a half pay for: (A)(1) all overtime in excess of eight hours in any one day or 40 hours in any one week if the work week is five consecutive days, Monday through Friday; or (2) all overtime in excess of 10 hours in any one day or 40 hours in any one week if the work week is four consecutive days, Monday through Friday; and (B) all work the employee 119 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 12 DBOM Agreement Contracting and Labor Practices performs on Saturday and on any legal holiday specified in a collective bargaining agreement or pursuant to ORS 279C.540. (B) Overtime Notice Requirements. As required by ORS 279C.520(2) with respect to construction work, the DBOM Contractor and Subcontractors shall give notice in writing to employees either at the time of hire or before work begins on the contract, or by posting a notice in a location frequented by employees, of the number of hours per day and days per week that the DBOM Contractor or Subcontractor may require the employees to work. Section 12.9. OTHER LABOR REQUIREMENTS. (A) Prohibition of Discriminatory Wage Rates Based on Sex. As required by ORS 279C.520(1)(b) with respect to construction work, the DBOM Contractor shall comply with the prohibition set forth in ORS 652.220. As required by LOC 34.20.050(1), the DBOM Contractor shall not discriminate on the basis of an individual's race, religion, color, sex, national origin, marital status, age (if the individual is 18 years of age or older) or disability, by committing any of the acts made unlawful under the provisions of ORS 659A.030 and 659A.112. Further, the DBOM Contractor shall comply with all statutory non-discrimination requirements, including those stated in ORS Ch. 659A. Compliance with such prohibitions are a material element of this DBOM Agreement and a failure to comply shall constitute a DBOM Contractor Remediable Breach. (B) Compensation Discussion Prohibitions Restricted. As required by ORS 279C.520(1)(c) with respect to construction work, the DBOM Contractor may not prohibit any of its employees from discussing the employee's rate of wage, salary,benefits or other compensation with another employee or another person and may not retaliate against an employee who discusses the employee's rate of wage, salary, benefits or other compensation with another employee or another person. Section 12.10.WORKERS'COMPENSATION. As required by ORS 279C.530(2), ORS 656.017 and ORS 656.029, the DBOM Contractor and all Subcontractors that employ subject workers who work under this DBOM Agreement in the State shall comply with ORS 656.017 and provide the required workers' compensation coverage. Section 12.11.EMPLOYEE HEALTH REQUIREMENTS. (A) Employee Drug Testing Program. As required by ORS 279C.505(2) with respect to construction work, the DBOM Contractor shall, upon request, demonstrate that each Subcontractor has an employee drug testing program in place. (B) Payment of Medical Care. As required by ORS 279C.530(1) with respect to construction work, the DBOM Contractor shall promptly, as due, make payment to any person, co-partnership,association or corporation furnishing medical, surgical and hospital care services or other needed care and attention, incident to sickness or injury, to the employees of the DBOM Contractor, of all sums that the DBOM Contractor agrees to pay for the services and all moneys and sums that the DBOM Contractor collected or deducted from the wages of employees under any law, contract or agreement for the purpose of providing or paying for the services. 120 3935946.13 043463 ARTICLE 13 INSURANCE, DAMAGE AND DESTRUCTION Section 13.1. INSURANCE. (A) Required Insurance. At all times during the Design-Build Period and the Operation and Maintenance Period, as applicable, the DBOM Contractor shall obtain or cause to be obtained, maintain and comply with the terms and conditions of the Required Insurance. The DBOM Contractor shall pay all premiums with respect to the DBOM Contractor Required Insurance as such premiums become due and payable. (B) Subcontractors. The DBOM Contractor shall require that all Subcontractors secure and maintain all insurance coverage and other financial sureties required by Applicable Law and Appendix 12 (Insurance Requirements) in connection with their presence and the performance of their duties at or concerning the Project and provide evidence of such Subcontractor insurance in accordance Appendix 12 (Insurance Requirements). The DBOM Contractor shall pursue its remedies under the applicable Subcontract to require Subcontractor compliance with this subsection upon any failure of a Subcontractor to furnish evidence of the required insurance coverage. (C) Compliance with Insurer Requirements. The DBOM Contractor shall comply promptly with the requirements of all insurers pertaining to the Project Site and the Project under any policy of Required Insurance to which it is a named insured, a co-insured, or an additional insured person. The DBOM Contractor shall not do or permit anything to be done or fail to take any reasonable action that results in the cancellation or the reduction of coverage under any policy of Required Insurance. (D) DBOM Contractor Failure to Provide Insurance Coverage. If the DBOM Contractor fails to pay any premium for DBOM Contractor Required Insurance, or if any insurer cancels any DBOM Contractor Required Insurance policy and the DBOM Contractor fails to obtain replacement coverage so that the DBOM Contractor Required Insurance is maintained on a continuous basis, or if the DBOM Contractor fails to provide evidence of DBOM Contractor Required Insurance to the City in accordance with Appendix 12 (Insurance Requirements), the City may, following at least three days'notice to the DBOM Contractor of its intent and after 10 days of such insurance not being available, pay such premium or procure similar insurance coverage from another insurer. Upon such payment by the City, the amount thereof shall be reimbursable to the City by the DBOM Contractor within 30 days of receipt of a written demand. Subject to Section 15.6 (Unavailability of Insurance for Insurable Force Majeure Events or for Third-Party Liability), the failure of the DBOM Contractor to obtain and maintain any DBOM Contractor Required Insurance shall not relieve the DBOM Contractor of its liability for any losses intended to be insured thereby. Further, the DBOM Contractor obtaining and maintaining such DBOM Contractor Required Insurance shall not, be a satisfaction of any DBOM Contractor liability under this DBOM Agreement, or in any way limit, modify or satisfy the DBOM Contractor's indemnity obligations hereunder. (E) Reductions for Insurance Proceeds and Insurance Receivables. Whenever this DBOM Agreement obligates the City to pay any amount to the DBOM Contractor in respect of an event or circumstance for which, or with respect to the consequences of which, an insurance claim may be made by the DBOM Contractor under the Required Insurance, the amount which the City is obligated to pay will be reduced by the amount of Insurance Proceeds and Insurance Receivables which the DBOM Contractor recovers or would have been entitled to recover if it had complied with the requirements of this DBOM Agreement or any policy of Required Insurance. 121 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 13 DBOM Agreement Insurance, Damage and Destruction (F) Property Insurance Proceeds. Property Insurance Proceeds shall be for the account of the City and applied as provided in subsection 15.1(E) (Application of Property and Builder's Risk Insurance Proceeds Available for Repair, Replacement or Restoration). Section 13.2. LOSS, DAMAGE OR DESTRUCTION TO THE PROJECT AND PRIVATE PROPERTY. (A) Protection and Repair of the Project. The DBOM Contractor shall use care and diligence, and shall take all reasonable and appropriate precautions, to protect the Project from loss, damage or destruction in accordance with Good Operation and Maintenance Practice. The DBOM Contractor shall report to the City, any other appropriate Governmental Body, if required, and the insurers under any applicable Required Insurance, immediately upon obtaining knowledge thereof, any damage or destruction to the Project and as soon as practicable thereafter shall submit a full report to the City. The DBOM Contractor shall also submit to the City within 24 hours of receipt copies of all accident and other reports filed with, or given to the DBOM Contractor by, any insurer, adjuster or Governmental Body. The parties shall cooperate so as to promptly commence and proceed with due diligence to complete the repair, replacement and restoration of the Project to at least the character or condition thereof existing immediately prior to the loss, damage or destruction, in accordance with and subject to the procedures set forth in this Article, Article 11 (Capital Modifications and Operation and Maintenance Services Changes), Article 14 (Relief Event Procedures) and Article 15 (Force Majeure Events), as applicable. The City shall have the right to monitor, review and inspect the performance of any repair, replacement and restoration work by the DBOM Contractor as if such work constituted Design-Build Work hereunder. (B) Repair of City and Private Property. The DBOM Contractor shall promptly, at its cost and expense, repair or replace all property owned by the City or any other public or private owner that is damaged by the DBOM Contractor or any DBOM Contractor Person in connection with the performance of, or the failure to perform, the Project Services. The repair and replacements shall restore the damaged property, to the maximum extent reasonably practicable, to its character and condition existing immediately prior to the damage. Nothing in this subsection is intended to waive any rights of recovery under applicable policies of insurance. (C) Damage or Destruction from Uninsurable Force Majeure Events. Subject to subsection 23.2(C) (Termination Upon Total Constructive Loss), where damage or destruction of the Project is caused by the occurrence of an Uninsurable Force Majeure Event, the City shall be responsible for paying the cost of the Reinstatement Works in accordance with Section 15.2 (Uninsurable Force Majeure Events). (D) Damage or Destruction from Other Relief Events. Subject to subsection 23.2(C) (Termination Upon Total Constructive Loss), where damage or destruction of the Project is caused by the occurrence of an Other Relief Event, the City shall be responsible for paying the cost of the Reinstatement Works in accordance with Section 16.3 (Other Relief Events). (E) Damage or Destruction from Insurable Force Majeure Events. Subject to subsection 23.2(C) (Termination Upon Total Constructive Loss), where damage or destruction to the Project is caused by the occurrence of an Insurable Force Majeure Event, all Insurance Proceeds available for any repair, replacement or restoration costs incurred pursuant to this Section, including Insurance Proceeds from all policies of Required Insurance, shall be for the account of the City and shall be available to pay the DBOM Contractor for all such costs as required to enable the DBOM Contractor to comply with its obligations under Section 15.3 (DBOM Contractor's Obligations Upon Material Damage or Destruction). Each party shall assist each other in exercising such rights as it may have to obtain Insurance Proceeds and effectuate such recovery. Each party shall provide copies of all relevant documentation to the other party, 122 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 13 DBOM Agreement Insurance, Damage and Destruction and each party shall cooperate with and assist the other party upon request by participating in conferences, negotiations and litigation regarding insurance claims; provided, however, that neither party will be obligated pursuant to this subsection to provide the other party with documents subject to the attorney-client privilege under the laws of the State. (F) Other Third-Party Payments. To the extent that any repair, replacement or restoration costs incurred pursuant to this Section can be recovered from any third party, each party shall assist the other party in exercising such rights as it may have to effect such recovery. Each party shall provide copies of all relevant documentation to the other party, and each party shall cooperate with and assist the other party upon request by participating in conferences, negotiations and litigation regarding claims against third parties; provided, however, that neither party will be obligated pursuant to this subsection to provide the other party with documents subject to the attorney-client privilege under the laws of the State. (G) DBOM Contractor Cost Responsibility. The DBOM Contractor shall provide all funds necessary to pay the costs of repairing, replacing and restoring the Project that are not covered by Insurance Proceeds or that cannot be recovered from any third party, in each case as set forth above in this Section, to the extent the loss, damage or destruction was caused by DBOM Contractor Fault or to the extent that Insurance Proceeds are unavailable due to a failure of the DBOM Contractor to obtain or maintain any applicable policy of Required Operation and Maintenance Period Insurance. Section 13.3. DBOM AGREEMENT NOT AFFECTED BY DAMAGE OR DESTRUCTION. Except as otherwise expressly provided in this DBOM Agreement (including the terms of subsection 14.1(A) (Extent of Relief Available to the DBOM Contractor)), the partial destruction or damage or complete destruction of the Project by fire or other casualty will not permit either party to terminate this DBOM Agreement or entitle the DBOM Contractor to cease providing the Project Services or to demand any increase in any amounts payable to the DBOM Contractor under this DBOM Agreement. 123 3935946.13 043463 ARTICLE 14 RELIEF EVENT PROCEDURES Section 14.1. RELIEF EVENTS GENERALLY. (A) Extent of Relief Available to the DBOM Contractor. If a Relief Event occurs, the DBOM Contractor may seek relief from its obligations, seek extensions of time, claim compensation, and exercise an Extended Relief Event termination right, as and to the extent provided in this Article, Article 15 (Force Majeure Events), and Article 16 (Change in Law Events and Other Relief Events) and in accordance with Section 15.3 (DBOM Contractor's Obligations Upon Material Damage or Destruction). (B) Mitigation Given Effect. Any relief to which the DBOM Contractor is entitled under this Article on account of Relief Events shall be adjusted to account for the effect of the mitigation measures which were or should have been taken by the DBOM Contractor in compliance with its duty to mitigate under Section 26.10 (General Duty to Mitigate). The DBOM Contractor's obligation to mitigate shall include fully vetting any Relief Event claim submitted by a Subcontractor to the DBOM Contractor with such Subcontractor prior to submitting such claim to the City. (C) Applicable Law Compliance. Nothing in this Article shall be interpreted as relieving the DBOM Contractor of its obligation, following any and all Relief Events, to perform its obligations under this DBOM Agreement in compliance with Applicable Law to the extent such Applicable Law can be complied with notwithstanding such Relief Event. Section 14.2. PROCEDURES UPON THE OCCURRENCE OF A RELIEF EVENT. (A) Notice and Written Report. In order to assert an entitlement based on the occurrence of a Relief Event, the DBOM Contractor shall give notice of the occurrence of the Relief Event to the City as soon as practicable, and in any event within 10 Business Days of the date the DBOM Contractor has knowledge that the Relief Event has caused or is likely to cause an entitlement under this DBOM Agreement. The DBOM Contractor's notice shall include a written report: (1) Describing the Relief Event and the cause thereof, to the extent known; (2) Stating the date on which the Relief Event began and its estimated duration; (3) Summarizing the consequences of the Relief Event and the expected impact on the performance of the DBOM Contractor's obligations under this DBOM Agreement; and (4) Indicating the nature and scope of the DBOM Contractor's potential entitlement to relief. (B) Updates. The DBOM Contractor shall provide the City with periodic updates, together with further details and supporting documentation, as it receives or develops additional information pertaining to the Relief Event and the matters described in subsection (A) of this Section. In particular, the DBOM Contractor shall notify the City as soon as the Relief Event has ceased and of the time when performance of its affected obligations can be resumed. 124 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 14 DBOM Agreement Relief Event Procedures (C) Submittal of Relief Request. The DBOM Contractor shall submit to the City a further notice making its request for specific relief, the basis therefor and the event giving rise to the requested relief within 30 days after the notice referred to in subsection (A) of this Section. If the specific relief cannot reasonably be ascertained within such 30-day period, the DBOM Contractor at the conclusion of such 30-day period shall furnish a further notice to the City establishing the date by which the appropriate requested relief shall be definitively requested and the basis for such extension which extended date shall not, in any event, be longer than 60 days after the notice referred to in subsection (A) of this Section. The DBOM Contractor shall then specify the specific relief by the date established in such further notice. (D) Burden of Proof and Mitigation. The DBOM Contractor shall bear the burden of proof in establishing the occurrence of a Relief Event and the entitlement to relief based thereon, and shall demonstrate to the City's reasonable satisfaction that the DBOM Contractor complied with its mitigation obligations under Section 26.10 (General Duty to Mitigate). (E) Resumption of Performance. Promptly following the occurrence of a Relief Event, the DBOM Contractor shall use all reasonable efforts to eliminate the cause thereof and resume performance of this DBOM Agreement. (F) City Response. Within 30 days after receipt of a relief request by the DBOM Contractor pursuant to subsection (C) of this Section, the City shall issue a written determination as to the extent, if any, to which it concurs with the DBOM Contractor's request, and the reasons therefor. (G) Agreement or Dispute. The agreement of the parties as to the specific relief to be given the DBOM Contractor on account of a Relief Event shall be evidenced by a Contract Administration Memorandum, a DBOM Agreement Amendment or a Change Order, as applicable. Subject to Section 19.3 (Binding Arbitration for Certain Smaller Claims), either party may refer any dispute to Non-Binding Mediation. Section 14.3. RELEASE. The DBOM Contractor's acceptance of any performance, price or schedule adjustment under this Article shall be construed as a release of the City by the DBOM Contractor (and all persons claiming by, through or under the DBOM Contractor) from any and all losses or expenses resulting from, or otherwise attributable to, the event giving rise to the adjustment claimed. Notwithstanding the foregoing, the parties may agree that any schedule, performance or price relief does not constitute the entire relief to be afforded due to such event but only to the extent set forth in a written agreement of the parties. 125 3935946.13 043463 ARTICLE 15 FORCE MAJEURE EVENTS Section 15.1. INSURABLE FORCE MAJEURE EVENTS. (A) DBOM Contractor Reinstatement. If all or any part of the Project is damaged or destroyed on account of an Insurable Force Majeure Event, the DBOM Contractor shall, subject to Article 14 (Relief Event Procedures), promptly repair, replace or restore the part of the Project so damaged or destroyed to at least the character or condition with materials of like kind and quality and without deduction for depreciation at the time and place of loss, and in compliance with Applicable Law, and in accordance with the requirements of Section 15.3 (DBOM Contractor's Obligations Upon Material Damage or Destruction). The obligation of the DBOM Contractor to perform the work described in this subsection (including under any Reinstatement Plan), as it pertains to Insurable Force Majeure Events, is conditioned on (i) the receipt of Insurance Proceeds as contemplated in subsection (E) of this Section (unless such Insurance Proceeds are not available due to DBOM Contractor Fault in which case the DBOM Contractor shall pay for such work without payment from the City) or (ii) assurances from the City that are reasonably acceptable to the DBOM Contractor. (B) Schedule Relief. If an Insurable Force Majeure Event occurs: (1) The Scheduled Acceptance Date and the Longstop Date shall be extended as and to the extent provided in Section 6.5 (Scheduled Acceptance Date and Longstop Date); and (2) The occurrence of the Insurable Force Majeure Event shall not extend the period of time during which the DBOM Contractor is obligated to provide the Project Services and entitled to receive the Service Fee beyond the Termination Date. (C) Performance Relief. If an Insurable Force Majeure Event occurs, the DBOM Contractor shall be relieved from its obligation to perform the Project Services as and to the extent set forth in Article 14 (Relief Event Procedures), and the City shall not have the right to impose Deductions for any failure to meet any Performance Guarantee, to the extent caused by the Insurable Force Majeure Event. (D) No Compensation Relief. If an Insurable Force Majeure Event occurs after the Acceptance Date, the Service Fee shall continue to be payable, but shall: (1) Be reduced by an amount equal to Avoidable Costs; and (2) Not be increased to account for any costs resulting from the occurrence of the Insurable Force Majeure Event, it being understood that, subject to subsection (G) of this Section, the DBOM Contractor shall be obligated to comply with its obligations under subsection (A) of this Section and otherwise perform the Project Services notwithstanding the insufficiency for any reason of any Insurance Proceeds. (E) Application of Property and Builder's Risk Insurance Proceeds Available for Repair, Replacement or Restoration. Upon the occurrence of an Insurable Force Majeure Event, all property and builder's risk Insurance Proceeds available for the repair, replacement or restoration of the Project shall be for the account of the City and the City shall pay the DBOM Contractor for such repair, replacement or restoration costs with such Insurance Proceeds in accordance with the terms of this DBOM Agreement. 126 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 15 DBOM Agreement Force Majeure Events (F) Insurance Deductibles and Exceedances. The DBOM Contractor shall be responsible for and bear all costs associated with insurance deductibles; provided, however, the City shall bear such insurance deductible costs with respect to any insurance required under Appendix 12 (Insurance Requirements) to the extent such costs result from City Fault. The DBOM Contractor shall be responsible for any claims under the DBOM Contractor Required Insurance exceeding policy limits and sublimits to the extent any such costs and claims result from an Insurable Force Majeure Event; provided, however, the City shall bear such costs to the extent such costs result from City Fault. (G) City Remedies and Termination Right. The failure of the DBOM Contractor to comply with its obligations under subsection (A) of this Section shall constitute a DBOM Contractor Remediable Breach which, if not remedied by the DBOM Contractor, shall entitle the City to exercise all of its remedies, including the right, by notice to the DBOM Contractor, to terminate this DBOM Agreement in accordance with Article 21 (DBOM Contractor Events of Default) and Article 23 (Termination). Section 15.2. UNINSURABLE FORCE MAJEURE EVENTS. (A) DBOM Contractor Reinstatement. If all or any part of the Project is damaged or destroyed on account of an Uninsurable Force Majeure Event, the DBOM Contractor shall, subject to Article 14 (Relief Event Procedures), promptly repair, replace or restore the part of the Project so damaged or destroyed to at least the character or condition thereof existing immediately prior to the damage or destruction and in compliance with Applicable Law and in accordance with subsections (D), (E) and (F) of this Section and Section 15.3 (DBOM Contractor's Obligations Upon Material Damage or Destruction). (B) Schedule Relief. If an Uninsurable Force Majeure Event occurs: (1) The Scheduled Acceptance Date and the Longstop Date shall be extended as and to the extent provided in Section 6.5 (Scheduled Acceptance Date and Longstop Date); and (2) The occurrence of an Uninsurable Force Majeure Event shall not extend the period of time during which the DBOM Contractor is obligated to provide the Project Services and entitled to receive the Service Fee beyond the Termination Date. (C) Performance Relief. If an Uninsurable Force Majeure Event occurs, the DBOM Contractor shall be relieved from its obligation to perform the Project Services as and to the extent set forth in (Relief Event Procedures), and the City shall not have the right to impose Deductions for any failure to meet any Performance Guarantee, to the extent caused by the Uninsurable Force Majeure Event. (D) Compensation Relief. If an Uninsurable Force Majeure Event occurs, the parties shall comply with their respective obligations under Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date) and Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date), as applicable, and the City shall pay the DBOM Contractor an amount equal to the increase in the cost to the DBOM Contractor of performing the Design-Build Work, to the extent resulting from the Uninsurable Force Majeure Event, which amount shall be payable as soon as practicable by the City following agreement of the parties, pursuant to Section 26.6 (Negotiated Lump Sum Pricing of Additional Work) or Section 26.7 (Cost Substantiation of Additional Work Not Subject to Lump Sum Price Negotiation), as applicable, as to such cost or other appropriate relief measures. Any such amount shall be paid by the City to the DBOM Contractor: (1) through a 127 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 15 DBOM Agreement Force Majeure Events Fixed Design-Build Price Adjustment during the Design-Build Period; and (2) separate from and in addition to the Service Fee during the Operation and Maintenance Period. In addition, the Operation and Maintenance Charge shall be reduced by an amount equal to Avoidable Costs, and increased by an amount necessary to compensate the DBOM Contractor for any increase in the cost of performing the Operation and Maintenance Services to the extent resulting from the Uninsurable Force Majeure Event. (E) Disaster Relief Funds. Upon the occurrence of an Uninsurable Force Majeure Event, the City shall promptly apply for and use all reasonable efforts to obtain any available State and federal disaster relief funds in order to repair, replace or rebuild the Project. All such State and federal relief funds received shall be for the account of the City and the City shall pay the DBOM Contractor for repair, replacement or restoration costs with such funds in accordance with the terms of this DBOM Agreement. (F) Termination Rights. If (1) the Project is completely or substantially destroyed, or if an Uninsurable Force Majeure Event occurs and is continuing and persists, or its effects are continuing and persisting so as to render the Project Facilities, or a substantial part thereof, unusable, and (2) a period of 180 days expires during which (a) the City has been denied the benefits of this DBOM Agreement substantially as intended hereby, and (b) the parties have not agreed upon a scope, price and schedule for the Reinstatement Plan, then the City may, by notice to the DBOM Contractor, terminate this DBOM Agreement, in which case the City shall pay compensation to the DBOM Contractor in accordance with Section 23.2(F) (Termination Payments). Section 15.3. DBOM CONTRACTOR'S OBLIGATIONS UPON MATERIAL DAMAGE OR DESTRUCTION. (A) Draft Reinstatement Plan. If the Project suffers damage or destruction, whether on account of an Insurable Force Majeure Event or an Uninsurable Force Majeure Event, that is likely to cost more than $1,000,000 (Index-Linked), to repair, replace and restore, the DBOM Contractor shall, as soon as practicable and in any event within 30 days of such damage or destruction, and before undertaking any material remedial work (other than any emergency work required to stabilize other parts of the Project or to facilitate the continued provision of the Operation and Maintenance Services to other parts of the Project), provide the City with a draft plan (the "Draft Reinstatement Plan") for the carrying out of the works necessary (the "Reinstatement Works") to repair, replace and restore the damaged or destroyed portions of the Project and related assets, and containing to the extent possible the details required to be included in the Reinstatement Plan under subsection (C) of this Section. (B) City Responsibilities. As soon as reasonably practicable and in any event within 15 Business Days after the delivery of the Draft Reinstatement Plan, the City: (1) Shall provide the DBOM Contractor with any comments it may have on the Draft Reinstatement Plan; and (2) If it has decided that the Project is not required to be reinstated in the same form as prior to the damage or destruction, will issue a preliminary Capital Modification instruction to that effect. (C) Reinstatement Plan. As soon as reasonably practicable and in any event within 15 Business Days after receipt of the City's comments, the DBOM Contractor shall deliver to the City a revised plan (the "Reinstatement Plan") to reasonably take into account the comments received from the City and making changes to the Draft Reinstatement Plan necessary 128 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 15 DBOM Agreement Force Majeure Events to reflect the contractual terms agreed (as negotiated and finalized) with the person effecting the Reinstatement Works. (D) Reinstatement Plan Details. The Reinstatement Plan shall set forth in as much detail as is reasonable in the circumstances: (1) The identity of the person, or (if the DBOM Contractor is conducting a competitive process) persons, intended to effect the Reinstatement Works; (2) The terms and timetable or (if not then established) the reasonably anticipated terms and timetable upon which the Reinstatement Works are to be effected (including the date upon which the Project is reasonably expected to become fully operational again and the Operation and Maintenance Services to be fully provided); (3) The impact that implementation of the Reinstatement Plan will have on the DBOM Contractor under this DBOM Agreement; (4) The total cost or (if not then established) the reasonably anticipated total cost of the Reinstatement Works; and (5) The impact of any Capital Modification requested by the City as part of the reinstatement. Thereafter,unless the damage or destruction was caused by an Uninsurable Force Majeure Event and the City elects to terminate this DBOM Agreement in accordance with the provisions of Section 23.2 (Termination), the DBOM Contractor shall repair, replace or restore the Project, subject to Applicable Law and, if the Uninsurable Force Majeure Event occurred prior to the Acceptance Date, to Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date) or Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date), as applicable. Section 15.4. STANDARDS OF REPLACEMENT, REPAIR OR RECONSTRUCTION. Any replacement, repair, or reconstruction of the Project or any part thereof pursuant to the provisions of Section 15.1 (Insurable Force Majeure Events) or Section 15.2 (Uninsurable Force Majeure Events) shall be made or done in compliance with the Design and Construction Requirements and the requirements set forth in Appendix 6 (Design-Build Work Review Procedures), subject to any agreement made between the City and the DBOM Contractor to revise the Design and Construction Requirements or the requirements set forth in Appendix 6 (Design-Build Work Review Procedures) as they pertain to the replacement, repair or reconstruction work. Section 15.5. AVAILABILITY OF INSURANCE FOR UNINSURABLE FORCE MAJEURE EVENTS. (A) Additional Insurance. If during the Term insurance is or has become available for a risk constituting an Uninsurable Force Majeure Event, the City may itself, or may direct the DBOM Contractor to, take out and maintain insurance on terms which are in accordance with the requirements of this DBOM Agreement and have been accepted by the DBOM Contractor, acting reasonably. The premiums, plus any applicable mark-up pursuant to subsection 26.7(E) (Mark-Ups), for such additional insurance coverage shall be paid, as 129 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 15 DBOM Agreement Force Majeure Events applicable, by the City to the insurer or by an adjustment to the Service Fee pursuant to Section 17.7 (Extraordinary Items). (B) Additionally Insured Risk to Constitute an Insurable Force Majeure Event; Qualifications. In any period during which additional insurance is maintained pursuant to subsection (A) of this Section, the occurrence of the additionally insured risk shall be deemed to constitute an Insurable Force Majeure Event for the purposes hereof, and any Insurance Proceeds available due to the occurrence thereof shall be applied as provided in subsection 15.1(E) (Application of Property and Builder's Risk Insurance Proceeds Available for Repair, Replacement or Restoration). Section 15.6. UNAVAILABILITY OF INSURANCE FOR INSURABLE FORCE MAJEURE EVENTS OR FOR THIRD-PARTY LIABILITY. (A) Insurance Unavailability Event. If during the Term: (1) Any Required Insurance is not available in the market place with Qualified Insurers; or (2) The insurance premium payable or the terms and conditions for maintaining such Required Insurance at the levels and on the terms required by this DBOM Agreement are at such cost that the City, owners or others having a substantially similar interest in property such as the Project are not insuring against such risk with Qualified Insurers, and such premium payable, terms or conditions do not arise, directly or indirectly from DBOM Contractor Fault or the fault of any Subcontractor; then such circumstance shall constitute an "Insurance Unavailability Event" hereunder. (B) Termination by City. If and for so long as an Insurance Unavailability Event has occurred and is continuing but subject to subsection (C)(2)(b) of this Section, the City may by notice to the DBOM Contractor terminate this DBOM Agreement whereupon the DBOM Contractor shall be entitled to compensation upon termination as provided in Section 23.2(F) (Termination Payments). (C) Continuance of DBOM Agreement. During any period prior to the Termination Date in which an Insurance Unavailability Event has occurred and is continuing, and the City has not exercised its termination right under subsection (B) of this Section or the City has exercised such right but the Termination Date has not yet occurred: (1) The DBOM Contractor will not be obligated to maintain such Required Insurance and references in this DBOM Agreement to such Required Insurance will be construed accordingly. During such period the Service Fee shall be adjusted in accordance with Section 17.7 (Extraordinary Items) by agreement of the parties, acting reasonably, to reflect any savings in the DBOM Contractor's insurance cost as a result of the DBOM Contractor not having to provide such Required Insurance; and (2) On the occurrence of a loss with respect to which an Insurance Unavailability Event has occurred, the City will either: (a) pay to the DBOM Contractor an amount equal to the Insurance Proceeds that would have been payable directly to the DBOM Contractor or to the relevant third party (in the case of third-party liability insurance) under the relevant policy of Required Insurance in respect of the loss had the relevant 130 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 15 DBOM Agreement Force Majeure Events insurance continued to be available and in effect, and this DBOM Agreement will continue; or (b) by notice to the DBOM Contractor, terminate this DBOM Agreement, whereupon the DBOM Contractor shall be entitled to compensation on termination as provided in Section 23.2(F) (Termination Payments) together with an amount equal to the Insurance Proceeds that would have been payable directly to the DBOM Contractor or to the relevant third party(in the case of third- party liability insurance) under the relevant liability (but not property) policy of Required Insurance in respect of the loss had the relevant liability insurance continued to be available and in effect; provided, however, that the City shall not have the right to terminate this DBOM Agreement under this subsection if the DBOM Contractor (1) releases the City from all obligations under subsection Section 15.6(C)(2)(a) of this Section, and (2) deposits into an escrow account held by a Qualified Commercial Bank acting as trustee pursuant to an escrow agreement with terms acceptable to the City acting reasonably, an amount equal, in the reasonable opinion of the City, to the Insurance Proceeds, and all amounts in respect of deductibles and waiting periods, that would have been the responsibility of the DBOM Contractor under Appendix 12 (Insurance Requirements), that would have been payable in respect of such claim that was made had the relevant insurance continued to be available and in effect, and such payment shall be applied for the same purpose and in the same manner as insurance proceeds would have been applied had the relevant insurance continued to be available and in effect. (D) Subrogation. If the City makes any payment to the DBOM Contractor pursuant to subsection 15.6(C)(2)(a) of this Section, then the City, to the extent of the amount paid, will be subrogated to the DBOM Contractor's rights against any third party (other than DBOM Contractor Persons) in respect of the occurrence or claim as a result of which the payment was made. (E) City Right to Purchase Replacement Insurance Coverage. During the continuance of any Insurance Unavailability Event, the City may, but shall not be obligated to, purchase insurance policies in the commercial insurance market providing the coverage intended to be provided by the Required Insurance that is unavailable due to an Insurance Unavailability Event. The Service Fee shall be adjusted in accordance with Section 17.7 (Extraordinary Items) to reflect a credit in the amount of the cost to the City of any such replacement insurance coverage, but only to the extent that such costs would be considered commercially reasonable without giving effect to the occurrence of the Insurance Unavailability Event. By way of example, if the premium on a policy of Required Insurance was costing the DBOM Contractor $5 and it suddenly jumps to $100 due to an Insurance Unavailability Event, the Service Fee reduction would be $5, not $100. Section 15.7. CONTINUING ATTEMPTS TO OBTAIN INSURANCE. During any period when an Insurance Unavailability Event has occurred and is continuing, the DBOM Contractor shall approach the insurance market on a regular basis and in any event at regular intervals of no longer than six months to establish whether the Required Insurance remains unavailable. 131 3935946.13 043463 ARTICLE 16 CHANGE IN LAW EVENTS AND OTHER RELIEF EVENTS Section 16.1. CHANGE IN LAW EVENTS. (A) Schedule Relief. If a Change in Law Event occurs: (1) The Scheduled Acceptance Date and the Longstop Date shall be extended as and to the extent provided in Section 6.5 (Scheduled Acceptance Date and Longstop Date); and (2) The occurrence of a Change in Law Event shall not extend the period of time during which the DBOM Contractor is obligated to provide the Project Services and entitled to receive the Service Fee beyond the Termination Date. (B) Performance Relief. If a Change in Law Event occurs, the DBOM Contractor shall be relieved from its obligation to perform the Project Services as and to the extent set forth in Article 14 (Relief Event Procedures), and the City shall not have the right to impose Deductions for any failure to meet any Performance Guarantee, to the extent caused by a Change in Law Event. (C) Compensation Relief. If a Change in Law Event occurs, the parties shall comply with their respective obligations under Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date) and Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date) as applicable, and the City shall pay the DBOM Contractor an amount equal to the increase in the cost to the DBOM Contractor of performing the Design-Build Work) or making the Capital Modification, repairs and replacements as applicable, to the extent resulting from the Change in Law Event,which amount shall be payable as soon as practicable by the City following agreement of the parties, pursuant to Section 26.6 (Negotiated Lump Sum Pricing of Additional Work) or Section 26.7 (Cost Substantiation of Additional Work Not Subject To Lump Sum Price Negotiation), as applicable, as to such cost or other appropriate relief measures. Any such amount shall be paid by the City to the DBOM Contractor: (1) through a Fixed Design-Build Price Adjustment during the Design- Build Period; and (2) separate from and in addition to the Service Fee during the Operation and Maintenance Period. In addition, the Operation and Maintenance Charge shall be reduced by an amount equal to Avoidable Costs, and increased by an amount necessary to compensate the DBOM Contractor for any increase in the cost of performing the Operation and Maintenance Services to the extent resulting from the Change in Law Event. Section 16.2. DISCRIMINATORY OR SPECIFIED CHANGES IN TAX LAW. If a Discriminatory Change in Tax Law or a Specified Change in Tax Law occurs on or after the Effective Date, the DBOM Contractor shall be entitled to additional compensation for any loss for the DBOM Contractor directly attributable thereto or, if applicable, the City shall be entitled to a downward adjustment to the Service Fee, in each case, within 30 days of the determination of the amount of the costs or savings associated with the Discriminatory Change in Tax Law or a Specified Change in Tax Law. The City and the DBOM Contractor shall negotiate in good faith the costs or savings associated with any Discriminatory Change in Tax Law or a Specified Change in Tax Law in accordance with this Section. 132 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 16 DBOM Agreement Change In Law Events And Other Relief Events Section 16.3. OTHER RELIEF EVENTS. (A) Schedule Relief. If an Other Relief Event occurs: (1) The Scheduled Acceptance Date and the Longstop Date shall be extended as and to the extent provided in Section 6.5 (Scheduled Acceptance Date and Longstop Date); and (2) The occurrence of an Other Relief Event shall not extend the period of time during which the DBOM Contractor is obligated to provide the Project Services and entitled to receive the Service Fee beyond the Termination Date. (B) Performance Relief. If an Other Relief Event occurs, the DBOM Contractor shall be relieved from its obligation to perform the Project Services as and to the extent set forth in Article 14 (Relief Event Procedures), and the City shall not have the right to impose Deductions for any failure to meet any Performance Guarantee, to the extent caused by an Other Relief Event. (C) Compensation Relief. If an Other Relief Event occurs, the parties shall comply with their respective obligations under Section 5.12 (Design and Construction Requirement Changes, Repairs and Replacements Required Due to Relief Events Occurring Prior to the Acceptance Date) and Section 11.4 (Capital Modifications, Repairs and Replacements Required Due to Relief Events Occurring Following the Acceptance Date) as applicable, and the City shall pay the DBOM Contractor an amount equal to the increase in the cost to the DBOM Contractor of performing the Design-Build Work or making the Capital Modification, repairs and replacements as applicable, to the extent resulting from the Other Relief Event, which amount shall be payable as soon as practicable by the City following agreement of the parties, pursuant to Section 26.6 (Negotiated Lump Sum Pricing of Additional Work) or Section 26.7 (Cost Substantiation of Additional Work Not Subject To Lump Sum Price Negotiation), as applicable, as to such cost or other appropriate relief measures. Any such amount shall be paid by the City to the DBOM Contractor: (1) through a Fixed Design-Build Price Adjustment during the Design- Build Period; and (2) separate from and in addition to the Service Fee during the Operation and Maintenance Period. In addition, the Operation and Maintenance Charge shall be reduced by an amount equal to Avoidable Costs, and increased by an amount necessary to compensate the DBOM Contractor for any increase in the cost of performing the Operation and Maintenance Services to the extent resulting from the Other Relief Event. Section 16.4. TERMINATION FOR EXTENDED RELIEF EVENTS. (A) Termination Right. If any Relief Event occurs, which causes one or both parties to be unable to comply with its or their material obligations with respect to all or a material portion of the Project (other than any payment obligation of the City) and such event and inability continues for a continuous period of at least 180 days (in each case, an "Extended Relief Event"), then the City may in its sole discretion, at any time thereafter during which such Extended Relief Event is continuing, terminate this DBOM Agreement by written notice to the DBOM Contractor and upon such termination, the City shall pay the DBOM Contractor in accordance with Section 23.2(F) (Termination Payments). 133 3935946.13 043463 ARTICLE 17 SERVICE FEE AND OTHER PAYMENTS Section 17.1. SERVICE FEE GENERALLY. (A) Service Fee Payment Obligation. From and after the Acceptance Date and through the Termination Date, the City shall pay the Service Fee to the DBOM Contractor as compensation for the DBOM Contractor's performance of the Operation and Maintenance Services in accordance with this Article. (B) Limitation on Payments. Other than the payments and compensation amounts expressly provided for in this DBOM Agreement, the DBOM Contractor shall have no right to any further payment from the City in connection with the Operation and Maintenance Services. Section 17.2. SERVICE FEE FORMULA. The Service Fee shall be calculated in accordance with the following formula: SF = OMC + RC - DC ± EI Where, SF = Service Fee OMC = Operation and Maintenance Charge RC = Reimbursable Costs Charge DC = Deductions Credit EI = Extraordinary Items An example of the calculation of the Service Fee is included in Appendix 14 (Example Calculation of Service Fee). If there are any irreconcilable inconsistencies between this Article 17 (Service Fee and Other Payments) and Appendix 14 (Example Calculation of Service Fee), the provisions of this Article 17 shall govern. Section 17.3. OPERATION AND MAINTENANCE CHARGE. (A) Generally. The "Operation and Maintenance Charge" shall be the sum of the ordinary operation and maintenance component, the pass-through electricity component and the Sludge transportation component, as each is described in this Section. (B) Ordinary Operation and Maintenance Component. The base ordinary operation and maintenance component of the Operation and Maintenance Charge for the first Contract Year shall be$4,994,178 (Index-Linked) (pro-rated). The parties acknowledge and agree that compensation for all requirements set forth in Appendix 13 (Performance Guarantees and Deductions) is included in the base ordinary operation and maintenance component set forth in this subsection. (C) Pass-Through Electricity Component. The pass-through electricity component of the Operation and Maintenance Charge shall be equal to the actual amount paid 134 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments by the DBOM Contractor to its electric Utility provider for electricity supplied to the Project during the applicable Billing Period. Such amount shall not be subject to any mark-up. (D) Sludge Transportation to Columbia Boulevard Wastewater Treatment Facility. The DBOM Contractor shall be paid $508 (Index-Linked) for each ton of Sludge that meets the requirements set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements) delivered by or on behalf of the DBOM Contractor to the Columbia Boulevard Wastewater Treatment Facility for off-loading. Section 17.4. REIMBURSABLE COSTS CHARGE. The "Reimbursable Costs Charge" shall be an amount equal to all payments to the DBOM Contractor for Major Maintenance, Repair and Replacement in accordance with Section 17.5 (Annual Capital Maintenance Charge). Section 17.5. ANNUAL CAPITAL MAINTENANCE CHARGE. (A) Generally. The City shall pay the DBOM Contractor for Major Maintenance, Repair and Replacement solely in accordance with this Section. The Annual Capital Maintenance Charge shall be the maximum amount payable by the City in any Contract Year for Major Maintenance, Repair and Replacement in accordance with Article 10 (Maintenance, Repair and Replacement). The Annual Capital Maintenance Charge shall be determined in accordance with subsections (B) (Annual Capital Maintenance Charge) and (C) (Annual Adjustment to the Annual Capital Maintenance Charge) of this Section. (B) Annual Capital Maintenance Charge. The "Annual Capital Maintenance Charge" for each Contract Year shall be the amounts set forth in Attachment 10B (Major Maintenance, Repair and Replacement Schedule) of Appendix 10 (Operation and Maintenance Requirements). Each such amount shall be Index-Linked in accordance with subsection (C) (Annual Adjustment to the Annual Capital Maintenance Charge) of this Section. (C) Annual Adjustment to the Annual Capital Maintenance Charge. The amounts set forth in Attachment 10B (Major Maintenance, Repair and Replacement Schedule) of Appendix 10 (Operation and Maintenance Requirements) for each Contract Year shall be Index-Linked. (D) MRR Account. On or before the Acceptance Date, the City shall establish a bank account (the "MRR Account") with a commercial banking institution selected by the City into which the City shall deposit payments of the Annual Capital Maintenance Charge on an equal monthly installment basis over the course of each Contract Year, which payments shall accrue in the MRR Account over the Term. Amounts in the MRR Account shall be the property of the City, but the City shall not have the right to withdraw or use such amounts except upon the expiration or termination of this DBOM Agreement in accordance with subsection (G) (Amounts Remaining in MRR Account) of this Section. Interest accruing on amounts on deposit in the MRR Account shall be available for requisition by the DBOM Contractor as provided in subsection (E) (Requisitions Against MRR Account) of this Section; provided, however, that the City does not guarantee or warrant the amount of interest that will be earned on amounts invested in the MRR Account. (E) Requisitions Against MRR Account. The DBOM Contractor shall have the right to requisition any amounts on deposit in the MRR Account at such times as needed to pay for Major Maintenance, Repair and Replacements performed in accordance with Article 10 (Maintenance, Repair and Replacement), except for Major Maintenance, Repair and Replacements due to DBOM Contractor Fault. In connection with any requisition of funds from 135 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments the MRR Account, the DBOM Contractor shall include as part of its invoice for the Service Fee in accordance with Section 17.8 (Billing and Payment) a written notice indicating that the DBOM Contractor has incurred costs for Major Maintenance, Repair and Replacements in excess of $25,000 (Index-Linked) for amounts paid or incurred (excluding costs of any DBOM Contractor staff assigned and dedicated to the Project) for the performance of Major Maintenance, Repair and Replacement in accordance with Article 10 (Maintenance, Repair and Replacement), together with evidence of the costs that are the subject of such drawing and such other supporting information as the City may reasonably require; provided, however, that the DBOM Contractor shall use all reasonable efforts to utilize staff assigned and dedicated to the Project before engaging other personnel of the DBOM Contractor or its Affiliates for Major Maintenance, Repair and Replacements. Payments against the Annual Capital Maintenance Charge shall be under the Reimbursable Costs Charge of the Service Fee. The DBOM Contractor shall also provide a detailed report to the City describing all Major Maintenance, Repair and Replacements made and uses and withdrawals of funds from the MRR Account during the Contract Year as part of its Annual Settlement Statement in accordance with Section 17.10 (Annual Settlement). The DBOM Contractor shall not be entitled to draw funds from the MRR Account for any costs of Project operations and maintenance personnel of the DBOM Contractor. If the City determines that any funds withdrawn by the DBOM Contractor were not used for Major Maintenance, Repair and Replacements, then, upon notice from the City, the DBOM Contractor shall promptly reimburse to the City an amount equal to the funds previously withdrawn on account of ineligible costs, as determined by the City, for deposit into the MRR Account. Any dispute between the parties regarding the DBOM Contractor's draw of funds from the MRR Account under this subsection shall be subject to shall be subject to Section 17.13 (Billing Statement Disputes) and may be referred to the dispute resolution procedures established in accordance with Article 19 (Dispute Resolution). In no event shall the DBOM Contractor be entitled to withdraw funds from the MRR Account for any purpose other than in accordance with this Section. (F) Carryover and Insufficiency of MRR Account Funds. The portion of any Annual Capital Maintenance Charge amount deposited in the MRR Account that remains undisbursed to the DBOM Contractor at the end of any Contract Year, together with any undisbursed amounts from previous Contract Years, shall be carried forward into subsequent Contract Years and shall be available for withdrawal by the DBOM Contractor in accordance with this Section. If the DBOM Contractor incurs costs to pay third party subcontractors (excluding any Affiliate of the DBOM Contractor) for the performance of Major Maintenance, Repair and Replacement that exceed at any time the amounts available for withdrawal from the MRR Account, such costs shall be for the account of the DBOM Contractor, subject to the DBOM Contractor's right to make subsequent withdrawals from the MRR Account at such time, if any, as any funds may become available. The City shall have no responsibility to make any payment to the DBOM Contractor with respect to such costs except to the extent of the Annual Capital Maintenance Charge required to be paid into the MRR Account as provided in subsection (B) (Annual Capital Maintenance Charge) of this Section. (G) Amounts Remaining in MRR Account. Upon the expiration or earlier termination of this DBOM Agreement, any amount remaining in the MRR Account that has not been paid to the DBOM Contractor and that is not due and owing to the DBOM Contractor for Major Maintenance, Repair and Replacement in accordance with this Section may be withdrawn and retained by the City for its own account; provided, however, that any amount remaining in the MRR Account upon expiration or earlier termination of this DBOM Agreement shall first be available to reimburse the DBOM Contractor for third party Subcontractor (excluding any Affiliate of the DBOM Contractor) expenses paid or incurred by the DBOM Contractor in satisfying its obligation to remedy any deficiency in the condition of the Project Equipment upon expiration at the end of the Term in accordance with Section 10.3 (Project Evaluation). (H) No Limitation on DBOM Contractor Obligations. The DBOM Contractor acknowledges that the Annual Capital Maintenance Charge applicable in any Contract Year shall 136 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments not serve as a limitation of the DBOM Contractor's obligations with respect to Major Maintenance, Repair and Replacement under Article 10 (Maintenance, Repair and Replacement). Except to the extent relieved due to the occurrence of Relief Event in accordance with and to the extent provided in Article 14 (Relief Event Procedures) or a Force Majeure Event in accordance with and to the extent provided in Article 15 (Force Majeure Events), the DBOM Contractor shall be solely responsible for all costs of Major Maintenance, Repair and Replacement above the Annual Capital Maintenance Charge. Section 17.6. DEDUCTIONS CREDIT. The"Deductions Credit" shall be the sum of all Deductions imposed pursuant to Article 9 (Performance) and Appendix 13 (Performance Guarantees and Deductions) hereunder. Section 17.7. EXTRAORDINARY ITEMS. The Extraordinary Items component of the Service Fee, which may be a charge or a credit, shall be equal to the net amount of the following items (each an "Extraordinary Item" hereunder): (1) Any operation, maintenance, repair, or replacement costs payable by the City on account of a City-directed Design and Construction Requirement Change which is chargeable to the City hereunder pursuant to Section 5.13 (Design and Construction Requirement Changes Made at City Direction), net of any Avoidable Costs incurred by the DBOM Contractor that would have been saved or avoided if the DBOM Contractor had acted reasonably and in accordance with this DBOM Agreement; (2) An amount equal to any disposal fee, if any, the DBOM Contractor is required to pay Portland with respect to the disposal of Sludge at the Columbia Boulevard Wastewater Treatment Facility that meet all of the requirements set forth in Section 5 (Sludge Requirements) of Appendix 4 (Design and Construction Requirements); (3) Any amount payable by the DBOM Contractor during each Contract Year of the Operation and Maintenance Period for the offloading or disposal of Sludge and Scum at a Qualified Residuals Disposal Facility as and to the extent required by subsection 9.6(D) (Sludge and Scum Transportation and Off-Loading); (4) Any amount payable pursuant to subsection Section 9.7(C) (Service Fee Impact); (5) Any adjustment to the Service Fee resulting from a Capital Modification, repair, replacement or from an Operation and Maintenance Services Change under the provisions of Article 11 (Capital Modifications and Operation and Maintenance Services Changes); (6) Any adjustment reflecting additional insurance costs incurred pursuant to Section 15.5 (Availability of Insurance for Uninsurable Force Majeure Events); (7) Any adjustment reflecting savings in insurance costs, or additional insurance costs paid by the City for replacement insurance coverage, pursuant to Section 15.6 (Unavailability of Insurance for Insurable Force Majeure Events or for Third Party- Liability); (8) Any amount payable by the City for increased design, construction, operation,maintenance,repair, replacement or other costs incurred on account of a Relief 137 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments Event pursuant to Article 15 (Force Majeure Events) and Article 16 (Change in Law Events and Other Relief Events), net of any Avoidable Costs achieved by the DBOM Contractor in mitigating the effects of the occurrence of such a Relief Event; (9) Any adjustment resulting from the exercise by the City of its rights under Article 20 (Remedies of the Parties and City Step-In Rights); (10) Any indemnification payments owed by the DBOM Contractor pursuant to Section 25.1 (DBOM Contractor's Obligation to Indemnify) or any other provision hereof; (11) As required by ORS 279C.515(1), any amount paid by the City in the event (a) the DBOM Contractor fails, neglects or refuses to pay promptly a person's claim for labor or services that the person provides to the DBOM Contractor or a Subcontractor in connection with this DBOM Agreement as the claim becomes due, and (b) the proper officer that represents the City elects to pay the amount of the claim to the person that provides the labor or services and charge the amount of the payment against the Service Fee; (12) Any incentive payments by the City to the DBOM Contractor pursuant to Article 9 (Performance) or Appendix 13 (Performance Guarantees and Deductions); and (13) Any other payment or increase or reduction in the Service Fee provided for under any other provision of this DBOM Agreement. Section 17.8. BILLING AND PAYMENT. (A) Installments. The City shall pay the Service Fee in monthly installments in an amount equal to the sum of: (1) One-twelfth of the annual ordinary operation and maintenance component of the Operation and Maintenance Charge; (2) Any pass-through electricity component of the Operation and Maintenance Charge; (3) The Sludge transportation component of the Operation and Maintenance Charge; (4) Any Reimbursable Costs Charge for the applicable Billing Period; (5) Any Deductions Credit; (6) Any Extraordinary Items that are determined on a monthly basis; and (7) Any adjustments, plus or minus, to reconcile any prior Service Fee payments that may reasonably be made within the course of the Contract Year. Any overpayment from prior monthly periods shall be credited against the next monthly Service Fee payment. (B) Invoicing and Service Fee Payment Due Date. The DBOM Contractor shall provide the City with an invoice for each Billing Period by the fifteenth day following the end of such Billing Period. The invoice shall set forth the amount of the Service Fee due with respect to such Billing Period and, in addition, shall state the annual Service Fee and each component 138 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments thereof as calculated for the then-current Contract Year, together with the accumulated payments for each component to the date of such invoice and such other documentation or information as the City may reasonably require to determine the accuracy and appropriateness of the invoice in accordance with this DBOM Agreement. The City shall pay the invoice within 30 days of receipt. (C) Late Service Fee Payments. In the event the City fails to make a Service Fee payment when due under subsection (B) of this Section: (1) Interest shall accrue thereon, as and to the extent provided in Section 26.8 (Interest on Overdue Amounts); and (2) If such failure continues for the period described in Section 22.1(1) (City Events of Default), then such failure shall constitute a City Event of Default as provided in such subsection and the DBOM Contractor shall have the right to terminate this DBOM Agreement as provided in subsection 23.2(B) (DBOM Contractor Termination Rights) if not cured within the time set forth in Section 22.2 (DBOM Contractor Options Upon City Event of Default). Section 17.9. ESTIMATES AND ADJUSTMENTS. (A) First and Last Billing Periods. If the first or last Billing Period is a partial month, any computation made on the basis of a Billing Period shall be adjusted on a pro-rata basis to take account of the partial period of service. (B) Annual Service Fee Estimate for City Budgeting Purposes. For City budgeting purposes, no later than 90 days preceding each Contract Year (beginning with the Contract Year in which Acceptance occurs) the DBOM Contractor shall provide to the City a written statement setting forth for such Contract Year its reasonable estimate of the aggregate Service Fee, each component thereof, and the calculation of Index-Linked. The estimate shall not be binding on the DBOM Contractor but, upon concurrence by the City (not to be unreasonably withheld, conditioned or delayed), shall establish the basis for Billing Period invoicing for such Contract Year, subject to annual settlement pursuant to this Article. Section 17.10. ANNUAL SETTLEMENT. Within 90 days after the end of each Contract Year during the Operation and Maintenance Period, the DBOM Contractor shall provide to the City an annual settlement statement (the "Annual Settlement Statement") setting forth (A) the actual aggregate Service Fee payable with respect to such Contract Year; (B) a reconciliation of such amount with the amounts actually paid by the City with respect to such Contract Year (taking into account intra- Contract Year reconciliations pursuant to Section 17.8(A)(7) (Installments)); and (C) as required by ORS 305.385, a written certification, under penalty of perjury, that the DBOM Contractor is to the best of its knowledge not in violation of any tax laws described in ORS 305.380. The City or the DBOM Contractor, as appropriate, shall pay all known and undisputed amounts within 60 days after receipt or delivery of the Annual Settlement Statement. If any amount is then in dispute or is for other reasons not definitely known at the time the Annual Settlement Statement is due, the Annual Settlement Statement shall identify the subject matter and reasons for such dispute or uncertainty and, in cases of uncertainty, shall include a good faith estimate by the DBOM Contractor of the amount in question. When the dispute is resolved or the amount otherwise finally determined, the DBOM Contractor shall file with the City an amended Annual Settlement Statement which shall, in all other respects, be subject to this Section. 139 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments Section 17.11. SALES TAXES. The parties acknowledge and agree that neither the State, nor any subdivision thereof utilizes a sales tax as of the Effective Date. As a result, no State or local sales tax on materials nor operating supplies have been priced into the Service Fee. The introduction of any State or local sales tax shall constitute an Other Relief Event. As required by ORS 305.385, the DBOM Contractor, prior to executing this DBOM Agreement, will provide the City with a written certification, under penalty of perjury that the DBOM Contractor is, to the best of its knowledge, not in violation of any tax laws described in ORS 305.380 as of the Effective Date. Section 17.12. CITY'S RIGHT OF SET OFF. Once the City determines that any Deductions, payments, or reimbursements are owed to the City in accordance with the terms and conditions of this DBOM Agreement and have not been reflected in any previously submitted Billing Period invoice statement, the City shall notify the DBOM Contractor and the DBOM Contractor shall include such amounts as a Deductions Credit or Extraordinary Item, as applicable,in the next Billing Period invoice provided to the City under this Article. In the event the DBOM Contractor does not include such amounts in the next Billing Period invoice provided to the City in accordance with this Section, the City shall have the right to offset from the Service Fee otherwise payable for such Billing Period invoice by the amount of such Deduction, credits, payments, reimbursements or liquidated damages. Notwithstanding the foregoing, the City shall have the right to offset the Service Fee otherwise payable to the DBOM Contractor for the final three Billing Period invoices during the Term by the amount of any Deductions, payments, or reimbursements due to the City under this DBOM Agreement. Section 17.13. BILLING STATEMENT DISPUTES. If the City disputes in good faith any amount billed by the DBOM Contractor, the City shall pay all undisputed amounts when due but may withhold payment of the disputed amount, and shall provide the DBOM Contractor with a written objection indicating the amount being disputed and the reasons then known to the City for the dispute. When any billing dispute is finally resolved, if payment by the City to the DBOM Contractor of amounts withheld is required, such payment shall be made within 30 days of the date of resolution of the dispute, with interest at the Overdue Rate. Section 17.14. PRIVATE BUSINESS USE RESTRICTIONS. (A) Payments to DBOM Contractor. It is the intent of the City and the DBOM Contractor that this DBOM Agreement shall be construed and applied so as to constitute a management contract that does not result in private business use of property financed by the City within the meaning and intent of the applicable regulations and rulings of the Internal Revenue Service. In particular, the City and the DBOM Contractor agree that, notwithstanding any provision of this DBOM Agreement to the contrary, the City shall be under no obligation to, and shall not, pay compensation for services to the DBOM Contractor for any Contract Year, if such payment, or any portion thereof, would result in any portion of the DBOM Contractor's compensation being based on net profit or net losses, as such terms are defined in Internal Revenue Service Revenue Procedure 2017-13 ("Rev. Proc. 2017-13"), of the Project. The payment by the City of any reimbursable or pass-through costs to the DBOM Contractor pursuant to this DBOM Agreement shall not constitute "compensation for services" for purposes of this Section. (B) Review of Adjustments to the Service Fee. If, at any time or from time to time, during the Term: (1) the scope of the Operation and Maintenance Services is increased or reduced pursuant to the terms of this DBOM Agreement; and (2) there is an adjustment to the 140 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 17 DBOM Agreement Service Fee and Other Payments Service Fee due to such increase or reduction in the Operation and Maintenance Services, the parties shall review, as of the date of such adjustment, the Service Fee for compliance with Rev. Proc. 2017-13 and the requirements of this Section. Any such adjustment and review of the Service Fee shall, at the City's cost, be subject to the review and approval of counsel with expertise in public finance tax matters for confirmation that such adjustment will not adversely affect the tax-exempt status of any obligations issued by the City with respect to the Project. 141 3935946.13 043463 ARTICLE 18 SECURITY FOR PERFORMANCE Section 18.1. PARENT COMPANY GUARANTOR. (A) Parent Company Guaranty Agreement. The DBOM Contractor, concurrently with the execution and delivery of this DBOM Agreement, has caused the Parent Company Guaranty Agreement to be provided by the Parent Company Guarantor in the form attached hereto as Transaction Form A (Parent Company Guaranty Agreement) as security for the faithful performance of the DBOM Contractor's obligations hereunder. (B) Reports and Notifications Concerning the Financial Condition of the Parent Company Guarantor. The DBOM Contractor shall furnish the City,within 180 days after the end of each fiscal year of the Parent Company Guarantor, consolidated balance sheets and income statements for the Parent Company Guarantor certified by its chief financial officer. The DBOM Contractor shall also furnish the City with copies of quarterly financial statements of the Parent Company Guarantor certified by its chief financial officer within 60 days following the end of each quarter based on the Parent Company Guarantor's fiscal year. In addition, the DBOM Contractor shall provide reasonable notice to the City of any change to the financial condition of the Parent Company Guarantor that would reasonably be anticipated to impair the ability of the Parent Company Guarantor to meet its obligations under the Parent Company Guaranty Agreement. (C) Material Adverse Change to the Financial Condition of the Parent Company Guarantor. A "Material Adverse Change" shall be any change to the financial condition of the Parent Company Guarantor that actually has, or is reasonably likely to have, a significant adverse effect on the Parent Company Guarantor's ability to perform its obligations under the Parent Company Guaranty Agreement, including any change or changes which in the aggregate result in a 20% decline in the Parent Company Guarantor's net worth from its net worth on the Effective Date. For purposes of this Section, "net worth" shall mean stockholder or shareholder equity, as reported on the Parent Company Guarantor's balance sheet. Notwithstanding any of the forgoing, no Material Adverse Change shall be deemed to have occurred under this Section to the extent that the DBOM Contractor or the Parent Company Guarantor, at its sole cost and expense, either: (1) is able to obtain and maintain either a shadow or actual investment grade credit rating for the Parent Company Guarantor on its senior debt from one or more of the Rating Agencies; or (2) provides other evidence that the Parent Company Guarantor maintains sufficient financial wherewithal to fulfill its obligations under the Parent Company Guaranty Agreement, subject to the approval of the City in its discretion. For purposes of this subsection "investment grade" means a rating of at least BBB- from Standard 8s Poor's or Fitch and a rating of at least Baa3 from Moody's. The City shall notify the DBOM Contractor of any determination by the City of the occurrence of a Material Adverse Change. Such determination may be based on any of the information required to be provided by the DBOM Contractor pursuant to subsection (B) of this Section or based on any publicly available information concerning the financial condition of the Parent Company Guarantor. The DBOM Contractor shall provide the City with a written response concerning the City's determination within 10 days following the City's notification and the parties shall meet within a reasonable time thereafter (not to exceed an additional 10 days following the City's original notification unless otherwise agreed to by the City) to discuss the City's determination and the DBOM Contractor's response. Following such meeting, if the City determines, acting reasonably, that a Material Adverse Change has occurred, then the DBOM Contractor shall provide credit enhancement in accordance with subsection (D) of this Section. The DBOM Contractor shall also immediately notify the City of any Material Adverse Change. 142 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 18 DBOM Agreement Security for Performance (D) Credit Enhancement Upon a Material Adverse Change. If a Material Adverse Change occurs, the DBOM Contractor shall, at its sole cost and expense, cause to be provided credit enhancement of its obligations hereunder within 30 days after the City's final determination of such occurrence pursuant to subsection (C) of this Section or notification of such occurrence by the DBOM Contractor, as applicable. Such credit enhancement shall be in the form either of: (1) An unconditional guarantee of all of the DBOM Contractor's obligations hereunder provided by a corporation or financial institution meeting the minimum financial requirements set forth in subsection (C) of this Section and otherwise acceptable to the City; or (2) Subject to the approval of the City in its discretion, a substitute instrument providing security for the performance of the DBOM Contractor's obligations hereunder in a form and manner acceptable to the City. In the event that the DBOM Contractor provides credit enhancement in the form of a replacement guarantor pursuant to item (1) of this subsection, the replacement guarantor shall become the Parent Company Guarantor for purposes of this DBOM Agreement and the provisions of this Section shall apply equally to such replacement Parent Company Guarantor. The City shall have the right but not the obligation, exercisable in its discretion, to waive, modify, alter or replace the foregoing requirement from time to time as and to the extent the City deems necessary to protect the public interest and to secure the performance by the DBOM Contractor of its obligations hereunder and by the Parent Company Guarantor of its obligations under the Parent Company Guaranty Agreement in light of the nature, extent and potential duration of the Material Adverse Change. (E) City Termination Rights Associated with the Financial Condition of the Parent Company Guarantor. In the event the DBOM Contractor fails to provide credit enhancement when and as required by subsection (D) of this Section an Event of Default by the DBOM Contractor shall be deemed to have occurred under Section 21.1 (DBOM Contractor Events of Default) notwithstanding any absence of notice, further cure opportunity or other procedural rights accorded the DBOM Contractor thereunder, and the City shall thereupon have the right to terminate this DBOM Agreement upon written notice to the DBOM Contractor. Upon any such termination, the City shall have all of the rights provided in Section 21.4 (City Termination Right) and Article 23 (Termination) upon a termination of the DBOM Contractor for cause. Section 18.2. PAYMENT AND PERFORMANCE BONDS. The DBOM Contractor shall deliver a performance bond in an amount equal to 100% of the Design-Build Price and a payment bond in the amount of 100% of the Design-Build Price (the "P&P Bonds"). Each such payment bond and performance bond shall conform to all applicable requirements set forth in this DBOM Agreement, including naming the City as an obligee or beneficiary thereunder, and the DBOM Contractor shall deliver a certified copy thereof. Such P&P Bonds shall also comply with all requirements of ORS 279C.380. Delivery of the P&P Bonds by the DBOM Contractor to the City in accordance with this Section shall be a condition to the issuance of the Design-Build Work Notice to Proceed pursuant to subsection 5.1(A) (Commencement and Prosecution of Design-Build Work). Prior to the DBOM Contractor's undertaking any Capital Modification under this DBOM Agreement and to the extent required by Applicable Law, the DBOM Contractor shall provide a payment bond and a performance bond (or evidence of increases to the existing bonds), each in an amount equal to the costs of such Capital Modification or as otherwise agreed upon by the City, acting reasonably, and such bonds shall otherwise comply with the requirements of Applicable Law. 143 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 18 DBOM Agreement Security for Performance Section 18.3. OPERATION AND MAINTENANCE LETTER OF CREDIT. No later than the date that is six months prior to the Scheduled Acceptance Date, the DBOM Contractor shall cause to be delivered to the City a letter of credit securing its payment and performance obligations under the DBOM Agreement (the "Operation and Maintenance Letter of Credit"). The Operation and Maintenance Letter of Credit shall name the City as the beneficiary thereunder and shall be in an amount equal to $1,000,000 ($1M), and the DBOM Contractor shall deliver a certified copy thereof to the City upon issuance. Delivery of the Operation and Maintenance Letter of Credit by the DBOM Contractor to the City in accordance with this subsection shall be a condition to the achievement of Acceptance pursuant to Section 6.2 (Acceptance Conditions). No later than 30 days prior to the commencement of each Contract Year during the Operation and Maintenance Period, the DBOM Contractor shall replace, amend and extend the Operation and Maintenance Letter of Credit and the DBOM Contractor shall deliver a certified copy thereof to the City upon issuance. Section 18.4. ADDITIONAL SECURITY FOR PROJECT SERVICES. To the extent the DBOM Contractor obtains payment or performance security that is not otherwise required hereunder in respect of any Subcontractor's performance of Project Services, the DBOM Contractor shall cause the City to be named,upon issuance of such security, as an additional obligee or beneficiary thereunder, and shall deliver a certified copy thereof, with the multiple obligee rider or other comparable documentation, to the City within 10 days after issuance. Section 18.5. COSTS OF PROVIDING SECURITY FOR PERFORMANCE. The cost and expense of obtaining and maintaining the Security Instruments required under this Article as security for the performance of the DBOM Contractor's obligations hereunder is included in the Fixed Design-Build Price or Service Fee, as applicable, and shall be borne by the DBOM Contractor without further reimbursement from the City. 144 3935946.13 043463 ARTICLE 19 DISPUTE RESOLUTION Section 19.1. FORUM FOR DISPUTE RESOLUTION. The DBOM Contractor and the City each agree that the exclusive venue for all Legal Proceedings related to this DBOM Agreement or to the Project or to any rights or any relationship between the parties arising therefrom shall be the appropriate federal or state court located within Clackamas County, and no other court. The parties further agree that the dispute resolution procedures set forth in this DBOM Agreement and under this Article exclusively govern claims under this DBOM Agreement. Section 19.2. NON-BINDING MEDIATION GENERALLY. (A) Rights to Request and Decline. Either party may request Non-Binding Mediation of any dispute arising under this DBOM Agreement, whether technical or otherwise. The non-requesting party may decline the request in its discretion. If there is concurrence that any particular matter shall be mediated, the provisions of this Section shall apply. The costs of the Mediator shall be divided equally between the City and the DBOM Contractor. (B) Procedure. The Mediator shall be a professional mutually acceptable to the parties who has no current or on-going relationship to either party. The Mediator shall have full discretion as to the conduct of the mediation. Each party shall in good faith participate in the Mediator's program to resolve the dispute until and unless the parties reach agreement with respect to the disputed matter or one party determines in its discretion that its interests are not being served by the mediation. (C) Non-Binding Effect. Mediation is intended to assist the parties in resolving disputes over the correct interpretation of this DBOM Agreement. No Mediator shall be empowered to render a binding decision. (D) Relation to Judicial Legal Proceedings. Nothing in this Section shall operate to limit, interfere with or delay the right of either party under this Article to commence judicial Legal Proceedings upon a breach of this DBOM Agreement by the other party or in respect of any dispute under this DBOM Agreement, whether in lieu of, concurrently with, or at the conclusion of any Non-Binding Mediation. Section 19.3. BINDING ARBITRATION FOR CERTAIN SMALLER CLAIMS. The parties shall work together in good faith to resolve any disputes, including with respect to disputes relating to (a) deficiencies found or the proposed remediation plan as described in subsection 10.4(C) (Remediation); and (b) the existence of a Relief Event and the specific relief as described in subsection 14.2(G) (Agreement or Dispute). If the parties dispute such an amount that is equal to or less than $500,000, and such dispute cannot be resolved by the parties in good faith after 30 days, the parties shall proceed to arbitration in accordance with the arbitration procedures of the Arbitration Service of Portland, Inc. (www.arbservice.com), or such other procedures as the parties agree. The decision of such an arbitration shall be final and may be entered as a judgment in the Clackamas County Circuit Court in accordance with State law. The parties shall equally share in the cost of the arbitrator and each party shall be responsible for its own costs and fees. The arbitration proceeding shall be held in Clackamas or Multnomah counties, as the arbitrator shall select, unless the parties otherwise agree. The parties shall mutually agree upon an arbitrator and if the arbitrator cannot be agreed upon, the Arbitration Service of Portland, Inc. shall appoint a sole arbitrator in accordance with its 145 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 19 DBOM Agreement Dispute Resolution procedural roles. Binding arbitration shall not be mandatory for any disputes involving amounts equal to or greater than $500,000. 146 3935946.13 043463 ARTICLE 20 REMEDIES OF THE PARTIES AND CITY STEP-IN RIGHTS Section 20.1. REMEDIES FOR BREACH. The parties may exercise their rights and remedies for breach as and to the extent provided in Section 20.9 (Exercise of Remedies). Neither party shall have the right to terminate this DBOM Agreement for breach except as provided or referred to in Section 21.4 (City Termination Right), Section 22.2 (DBOM Contractor Options Upon City Event of Default) or Article 23 (Termination), or expressly set forth elsewhere in this DBOM Agreement. If this DBOM Agreement is terminated by the City for a DBOM Contractor Event of Default, the City shall have the right to pursue a cause of action for actual damages and to exercise all other remedies which are available to it under this DBOM Agreement, under the Security Instruments and under Applicable Law. The foregoing is subject to the provisions of Section 20.11 (No Special, Consequential or Punitive Damages) and Section 20.2 (City Liquidated Damages Rights). Section 20.2. CITY LIQUIDATED DAMAGES RIGHTS. (A) City Liquidated Damages Rights Defined. The City's rights under this DBOM Agreement include the right (each of the following, a "Liquidated Damages Right"): (1) To impose delay liquidated damages under subsection 6.6(A) (Delay Liquidated Damages); and (2) To impose Deductions from the Service Fee under the circumstances set forth in Article 9 (Performance) and Appendix 13 (Performance Guarantees and Deductions). (B) Sole Remedy; Exceptions. The parties acknowledge and agree that the City's actual damages or losses in each such circumstance (set forth in subsections (A)(1) and (2) above are impossible to ascertain as of the Effective Date and that the amounts payable to, or to be retained by, the City through the exercise of any Liquidated Damages Right are a fair and reasonable estimate of fair compensation to the City for the intended circumstance, as applicable, shall constitute liquidated damages in each such circumstance and are not a penalty against the DBOM Contractor. The DBOM Contractor is expressly estopped from claiming, and waives any right to claim, that the exercise of any Liquidated Damages Right by the City amounts to a penalty or is not enforceable. The liquidated damages resulting from the City's exercise of a Liquidated Damages Right shall constitute the only damages payable by the DBOM Contractor to the City to compensate the City for the damages or losses resulting from the specific circumstances contemplated by such Liquidated Damages Right, and the exercise of such right by the City shall constitute the City's sole remedy in respect of such circumstances; provided, however, that such limitation is subject and without prejudice to: (1) Any entitlement of the City to specific performance of any obligation of the DBOM Contractor under this DBOM Agreement; (2) Any right of the City under subsection Section 9.10(A) (Remedies); (3) Any entitlement of the City to injunctive relief; (4) The City's step-in rights under this Article; 147 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 20 DBOM Agreement Remedies of the Parties and City Step-In Rights (5) Any right of the City to declare the occurrence of a DBOM Contractor Remediable Breach under subsection 21.1(B) (DBOM Contractor Remediable Breach Defined), including a DBOM Contractor Remediable Breach resulting from the significant accumulation of Deductions based on the occurrence of any failure to meet any Performance Guarantee; (6) The DBOM Contractor's indemnification obligations under Article 25 (Indemnification) in respect of third-party claims; (7) The determination of DBOM Contractor liability in respect of a termination for a DBOM Contractor Event of Default if the City pursues a cause of action for actual damages pursuant to Article 20 (Remedies of the Parties and City Step-In Rights); or (8) Any other express right of the City pursuant to this DBOM Agreement. Section 20.3. CITY'S TEMPORARY STEP-IN RIGHTS DURING THE OPERATION AND MAINTENANCE PERIOD. If during the Operation and Maintenance Period the City reasonably considers that a breach by the DBOM Contractor of any obligation under this DBOM Agreement or an event is likely to create an immediate and serious threat to the health or safety of any property or the environment, then the City, acting reasonably, may either: (1) If it considers that there is sufficient time and that it is likely that the DBOM Contractor shall be willing and able to provide assistance, require the DBOM Contractor by notice to take such steps as are necessary or expedient to mitigate or rectify such state of affairs including, if applicable due to breach of any terms or conditions of this DBOM Agreement, and the DBOM Contractor shall use all reasonable efforts to comply with the City's requirements as soon as reasonably practicable; or (2) If it considers there is not sufficient time, or that the DBOM Contractor is not likely to be willing and able to take the necessary steps,take such steps as it considers are appropriate (either itself or by engaging others) to mitigate or rectify such state of affairs and to ensure performance of the relevant Project Services to the standards required by this DBOM Agreement (or as close as possible to those standards as the circumstances permit). The City will carry out such steps as quickly as is practicable, and in such manner as will minimize interference with the DBOM Contractor's performance of its obligations under this DBOM Agreement and will provide the DBOM Contractor with a reasonably detailed description of the steps taken by the City in the exercise of its rights under this Article as soon as practicable following the taking of such steps. The DBOM Contractor shall ensure that all Subcontracts permit the City to exercise its rights under this Article. Section 20.4. CITY'S RECTIFICATION RIGHTS. If the City gives notice to the DBOM Contractor under Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) and the DBOM Contractor either: (1) Does not confirm,within five Business Days of such notice, or such shorter period as is appropriate in the case of an emergency, that it is willing to take such steps as are required in such notice or present an alternative plan to the City to mitigate, rectify 148 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 20 DBOM Agreement Remedies of the Parties and City Step-In Rights and protect against such circumstances then the City may, within a further five Business Days, accept or reject, acting reasonably; or (2) Fails to take the steps as are referred to or required in such notice or accepted alternate plan within such time as set forth in such notice or accepted alternate plan or within such time as the City, acting reasonably, will stipulate; then the City,with notice to the DBOM Contractor,may take such steps as it considers necessary or expedient to mitigate,rectify or protect against such circumstances either itself or by engaging others to take any such steps. Such steps may include the partial or total suspension of the right and obligation of the DBOM Contractor to provide the relevant Project Services, but only for so long as the circumstances referred to in Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) persist. Section 20.5. NOTICE OF CAPITAL MODIFICATION. The City shall notify the DBOM Contractor of any Capital Modification which the City intends to make pursuant to the exercise of the City's rights under Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) or Section 20.4 (City's Rectification Rights) and provide the DBOM Contractor a reasonable opportunity, taking into account all the circumstances, to comment on the proposed Capital Modification. In making such Capital Modification, the City will reasonably consider comments received in a timely manner from the DBOM Contractor on the proposed Capital Modification. Section 20.6. NO EFFECT ON PROJECT SERVICES. Except as provided in this Article 20 (Remedies of the Parties and City Step-In Rights), the exercise by the City of any of its rights under this Article 20 (Remedies of the Parties and City Step-In Rights) shall not reduce or affect in any way the DBOM Contractor's other responsibilities hereunder to perform the Project Services. Section 20.7. ALLOCATION OF COSTS AND PROVISION OF RELIEF FOR CITY'S EXERCISE OF STEP-IN RIGHTS. To the extent that any of the circumstances set forth in Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) arise as a result of any breach by the DBOM Contractor of its obligations under this DBOM Agreement, then the DBOM Contractor shall pay the City the amount of all costs and expenses reasonably incurred by the City in exercising its rights under Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) or Section 20.4 (City's Rectification Rights) and an additional mark-up of 20% of such costs and expenses in respect of indirect costs and overhead not otherwise directly attributable to the exercise of such rights. In all other cases, the City shall compensate the DBOM Contractor, and provide schedule and performance relief to the DBOM Contractor, for actions taken under Section 20.3 (City's Temporary Step-In Rights During the Operation and Maintenance Period) or Section 20.4 (City's Rectification Rights) in the manner provided in Article 16 (Change in Law Events and Other Relief Events) as if such circumstances constituted a Relief Event affecting the DBOM Contractor. Section 20.8. NO WAIVER OF REMEDIES. No failure to exercise, and no delay in exercising, any right or remedy under this DBOM Agreement will be deemed to be a waiver of that right or remedy. No waiver of any breach of any provision of this DBOM Agreement will be deemed to be a waiver of any subsequent breach of that provision or of any similar provision. 149 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 20 DBOM Agreement Remedies of the Parties and City Step-In Rights Section 20.9. EXERCISE OF REMEDIES. (A) Remedies Exclusive. The respective rights and remedies of the parties set out in this DBOM Agreement shall be the exclusive rights and remedies for breach of this DBOM Agreement, and the parties shall have no obligations or liabilities in connection with this DBOM Agreement and the Project Services except as expressly set out in this DBOM Agreement. (B) Similar Rights and Remedies. A party will not be prevented from enforcing a right or remedy on the basis that another right or remedy hereunder deals with the same or similar subject matter. (C) Single or Partial Exercise of Remedies. No single or partial exercise by a party of any right or remedy precludes or otherwise affects the exercise of any other right or remedy to which that party may be entitled. Section 20.10.NO DUPLICATIVE RECOVERY OR CLAIMS OUTSIDE CONTRACT. Every right to claim compensation, indemnification or reimbursement under this DBOM Agreement shall be construed so that recovery is without duplication to any other amount recoverable under this DBOM Agreement. Neither party shall be entitled to make any claim against the other party for compensation, indemnification or reimbursement other than as provided under this DBOM Agreement. Section 20.11.NO SPECIAL, CONSEQUENTIAL OR PUNITIVE DAMAGES. In no event shall either party hereto be liable to the other or obligated in any manner to pay to the other party any special, incidental, consequential, punitive or similar losses or damages based upon claims arising out of or in connection with the performance or non- performance of its obligations or otherwise under this DBOM Agreement, or any representation made in this DBOM Agreement being materially incorrect, whether such claims are based upon contract, tort, negligence, warranty or any other legal theory. This Section shall not limit the recovery of any such losses or damages under Article 25 (Indemnification) in respect of claims by third parties. 150 3935946.13 043463 ARTICLE 21 DBOM CONTRACTOR EVENTS OF DEFAULT Section 21.1. DBOM CONTRACTOR EVENTS OF DEFAULT. (A) DBOM Contractor Events of Default Defined. For the purposes of this DBOM Agreement, "DBOM Contractor Event of Default" means any of the following events or circumstances: (1) The occurrence of a DBOM Contractor Remediable Breach that is not remedied in accordance with Section 21.3 (DBOM Contractor Remediable Breach Cure and Remedial Program); (2) The occurrence of a DBOM Contractor Bankruptcy-Related Event; (3) The DBOM Contractor effectively abandons the Project during the Design- Build Period for a continuous period in excess of 5 days where such abandonment is not consistent with the Project Schedule and is not expressly permitted or excused by the terms of this DBOM Agreement other than pursuant to its right to suspend performance or terminate in accordance with this DBOM Agreement; (4) The DBOM Contractor abandons the Project during the Operation and Maintenance Period by failing to perform a material part of the Operation and Maintenance Services for a continuous period in excess of 24 hours and is not expressly permitted or excused by the terms of this DBOM Agreement other than pursuant to its right to suspend performance or terminate in accordance with this DBOM Agreement; (5) The DBOM Contractor breaches subsection 4.5(F) (Tax Compliance), and has not cured such breach within 10 days of notice from the City; (6) The Acceptance Date does not occur on or before the Longstop Date as provided in Section 6.7 (Failure to Achieve Acceptance by the Longstop Date); (7) Following the Acceptance Date (and subject to the rights of the DBOM Contractor set forth in subsection 9.3(K) (Sustained Odor Condition Determination)), the issuance by the City of: (a) A fourth or any subsequent Odor Citation (taking into account the provisions of subsection 9.3(J) (Disregarding Prior Odor Citations), and provided that in order for such termination to occur such fourth or subsequent Odor Citation must be at least the second such Odor Citation in any calendar year, excluding Odor Citations resulting from reports from members of the surrounding community pursuant to paragraph (c) of Section 3 (Determination of an Odor Incident for Purposes of the Odor Guarantee) of Appendix 13 (Performance Guarantees and Deductions); (b) A Sustained Odor Condition lasting seven or more consecutive days without the DBOM Contractor (i) having provided the City with a Corrective Action Plan in accordance with Appendix 11 (Odor Control Standard and Odor Control Plan) or (ii) having taken reasonable steps to remediate and prevent the reoccurrence of the Sustained Odor Condition; 151 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 21 DBOM Agreement DBOM Contractor Events of Default (c) A second Sustained Odor Condition determination made in accordance with the applicable provisions of Section 9.3 (Odor Guarantee); or (d) A Sustained Odor Condition lasting 14 or more consecutive days; provided, however, that such event shall not constitute a DBOM Contractor Event of Default if the underlying cause of the Sustained Odor Condition and the necessary remediation measures requires an extended period to identify and complete and the DBOM Contractor continues to investigate and, if required under the terms of this DBOM Agreement, resolve and remediate the Sustained Odor Condition (which must be completed within 60 days from the initial occurrence of the Sustained Odor Condition unless otherwise expressly agreed to by the City) in accordance with the Contract Standards; (8) The DBOM Contractor fails to obtain and maintain any Security Instrument required by Article 18 (Security for Performance), subject to the terms and conditions of such Article; (9) The DBOM Contractor fails to provide credit enhancement when and as required by subsection 18.1(D) (Credit Enhancement Upon a Material Adverse Change); (10) The Parent Company Guarantor fails to make any payment or perform any other obligation under the Parent Company Guaranty within 10 days of notice from the City of such failure; or (11) The DBOM Contractor breaches Section 24.1 (Limitation on Assignment by the DBOM Contractor) or a Change in Control occurs which is prohibited by Section 24.2 (Limitation on Change in Control). (B) DBOM Contractor Remediable Breach Defined. For purposes of this DBOM Agreement, "DBOM Contractor Remediable Breach" means any of the following breaches, unless the breach is due to the occurrence of a Relief Event: (1) A failure by the DBOM Contractor to pay any amount due and owing to the City under this DBOM Agreement on the due date (which amount is not being disputed in good faith); (2) A failure of the DBOM Contractor to meet the Odor Guarantee, as and to the extent provided in subsection 9.3(M) (City Termination Rights Based on Failure to Meet Odor Guarantee); (3) A failure by the DBOM Contractor to maintain the policies of insurance required to be maintained by the DBOM Contractor under this DBOM Agreement and to comply with its obligation under Appendix 12 (Insurance Requirements) to include the City as an insured party; (4) A failure by the DBOM Contractor to comply with its obligations under subsection 12.9(A) (Prohibition of Discriminatory Wage Rates Based on Sex); (5) A failure by the DBOM Contractor to comply with its obligation under Section 15.1 (Insurable Force Majeure Events) to repair, replace or restore the Project following the occurrence of an Insurable Force Majeure Event; (6) The DBOM Contractor fails to immediately take all appropriate action in the event that the City notifies the DBOM Contractor that a public health or safety 152 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 21 DBOM Agreement DBOM Contractor Events of Default emergency exists or is threatened due to the DBOM Contractor's failure to comply with the Contract Standards; (7) Except as provided for in items (1) through (6) of this subsection (B), a breach, or series of breaches, by the DBOM Contractor of any agreement, covenant or undertaking made to the City or any representation or warranty made by the DBOM Contractor to the City in this DBOM Agreement (or any ancillary certificate, statement or notice issued hereto) being incorrect when made or at any time during the Term, the consequence of which is: (a) a material risk to the health or safety of the public; (b) a risk of material liability of the City to third persons; (c) an adverse effect on the performance of the Design-Build Work or the Operation and Maintenance Services to the extent that the City is reasonably likely to be materially deprived of the benefit of this DBOM Agreement; or (d) any material provision of this DBOM Agreement being unenforceable against the DBOM Contractor; or (8) A material breach occurs (or series of breaches occur, including the occurrence of any failure to meet any Performance Guarantee) which, due to its significance, frequency or recurrence, demonstrates either an inability, or an unwillingness, of the DBOM Contractor to comply with its obligations under this DBOM Agreement. (C) DBOM Contractor Bankruptcy-Related Event Defined. For purposes of this DBOM Agreement, "DBOM Contractor Bankruptcy-Related Event" means any of the following events: (1) A receiver, receiver manager or other encumbrance holder taking possession of or being appointed over, or any distress, execution or other process being levied or enforced upon, the whole or any material part of the assets of the DBOM Contractor or the Parent Company Guarantor, and such proceedings are not stayed, discontinued, withdrawn, dismissed or otherwise remedied within 30 days of such proceedings being instituted; or (2) Any proceedings with respect to the DBOM Contractor or the Parent Company Guarantor being commenced under the Bankruptcy Law and if such proceedings are commenced against the DBOM Contractor or the Parent Company Guarantor and are disputed by the DBOM Contractor or the Parent Company Guarantor, as applicable, such proceedings are not discontinued, withdrawn, dismissed or otherwise remedied within 30 days of such proceedings being instituted; or (3) The DBOM Contractor or the Parent Company Guarantor making an assignment for the benefit of its creditors, being declared bankrupt or committing an act of bankruptcy, becoming insolvent, making a proposal or otherwise taking advantage of provisions for relief under the Bankruptcy Law or similar legislation in any jurisdiction, or any other type of insolvency proceedings being commenced by or against the DBOM Contractor or the Parent Company Guarantor under the Bankruptcy Law or otherwise and, if proceedings are commenced against the DBOM Contractor or the Parent Company Guarantor and are disputed by the DBOM Contractor or the Parent Company Guarantor, 153 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 21 DBOM Agreement DBOM Contractor Events of Default as applicable, such proceedings are not stayed, dismissed or otherwise remedied within 30 days of such proceedings being instituted; or (4) The DBOM Contractor or the Parent Company Guarantor ceasing to carry on business. Section 21.2. NOTIFICATION BY THE DBOM CONTRACTOR. The DBOM Contractor shall notify the City of the occurrence, and details, of any DBOM Contractor Event of Default and of any event or circumstance which is likely, with the passage of time or otherwise, to constitute or give rise to a DBOM Contractor Event of Default, in either case promptly on the DBOM Contractor becoming aware of its occurrence. Section 21.3. DBOM CONTRACTOR REMEDIABLE BREACH CURE AND REMEDIAL PROGRAM. (A) Notice and Remedy or Remedial Program. After the occurrence of a DBOM Contractor Remediable Breach and while it is subsisting, the City may serve a notice on the DBOM Contractor specifying in reasonable detail the type and nature of the DBOM Contractor Remediable Breach and: (1) The DBOM Contractor shall remedy such DBOM Contractor Remediable Breach referred to in such notice (if it is continuing) within 20 Business Days of such notice; or (2) If either the City (as set forth in its notice) or the DBOM Contractor reasonably considers that a DBOM Contractor Remediable Breach cannot reasonably be remedied within 20 Business Days of such notice, the DBOM Contractor shall deliver to the City within 10 Business Days of such notice a reasonable program (set forth, if appropriate, in stages) for remedying the DBOM Contractor Remediable Breach and, in any event, such breach must be cured within 60 days unless otherwise expressly agreed to by the City. The program will specify in reasonable detail the manner in, and the latest date (which must be within 60 days unless otherwise expressly agreed to by the City) by which the DBOM Contractor Remediable Breach is proposed to be remedied. (B) City Acceptance or Non-Acceptance. If the DBOM Contractor puts forward a program in accordance with subsection (A)(2) of this Section, the City will have 10 Business Days from receipt of the program within which to notify the DBOM Contractor that the City, acting reasonably, does not accept the program, failing which the City will be deemed to have accepted the program. If the City notifies the DBOM Contractor that it does not accept the program as being reasonable, the parties will use all reasonable efforts within the following five Business Days to agree to any necessary amendments to the program put forward. In the absence of an agreement within such five Business Days, the City shall have the right to terminate pursuant Section 21.4 (City Termination Right). (C) Remediable Program Limited to DBOM Contractor Remediable Breaches. The DBOM Contractor Remediable Breach and remedial program provisions of this Section shall apply only to a DBOM Contractor Remediable Breach, and not to any other event or circumstance constituting a DBOM Contractor Event of Default. 154 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 21 DBOM Agreement DBOM Contractor Events of Default Section 21.4. CITY TERMINATION RIGHT. (A) Termination Right. If: (1) Any DBOM Contractor Event of Default occurs (other than that with respect to a DBOM Contractor Remediable Breach as set forth in subsection Section 21.1(A)(1) (DBOM Contractor Events of Default Defined)); or (2) With respect to a DBOM Contractor Remediable Breach: (a) a DBOM Contractor Remediable Breach is not remedied before the expiration of the period referred to in subsection Section 21.3(1) (Notice and Remedy or Remedial Program)and no program has been put forward by the DBOM Contractor under subsection Section 21.3(2) (Notice and Remedy or Remedial Program); (b) the DBOM Contractor puts forward a program pursuant to subsection Section 21.3(2) (Notice and Remedy or Remedial Program) which has been accepted by the City (including after agreement under Section 21.3 (DBOM Contractor Remediable Breach Cure and Remedial Program) to amendments to the program) and the DBOM Contractor fails to achieve any material element of the program by the end date for the program; or (c) any program put forward by the DBOM Contractor pursuant to subsection Section 21.3(2) (Notice and Remedy or Remedial Program), after good faith negotiations, is rejected by the City as not being reasonable; then the City may, subject to subsection 23.2(J) (Continued Performance), terminate this DBOM Agreement by notice to the DBOM Contractor. The right of the City to terminate this DBOM Agreement under this Section is in addition, and without prejudice, to any other right which the City may have in connection with the DBOM Contractor's non-compliance with this DBOM Agreement, including those set forth in Article 20 (Remedies of the Parties and City Step-In Rights). (B) Relief Events Affecting Performance of Remedial Program. For the purposes of subsection Section 21.4(2)(b), if the DBOM Contractor's performance of the program is adversely affected by the occurrence of a Relief Event or a City Fault, then, subject to the DBOM Contractor complying with the mitigation and other requirements in this DBOM Agreement concerning such events, the time for performance of the program or any relevant element of it will be deemed to be extended by a period equal to the delay caused by such events. 155 3935946.13 043463 ARTICLE 22 CITY EVENTS OF DEFAULT Section 22.1. CITY EVENTS OF DEFAULT. For the purposes of this DBOM Agreement, "City Event of Default" means any of the following events or circumstances: (1) A failure by the City to pay the Service Fee within 30 days of the due date for the Service Fee; (2) A failure by the City to pay an amount due during the Design-Build Period as provided or referred to Article 7 (Payment for the Design-Build Work) within 30 days of the due date for such amount; (3) A failure by the City to pay any other amount due from the City to the DBOM Contractor hereunder within 30 days of the due date for such amount; (4) The City breaches Section 24.4 (Limitation on Assignment by the City); (5) A failure by the City to provide access to the Project Site at any time from and after the Effective Date as reasonably necessary for the DBOM Contractor to perform the obligations under this DBOM Agreement; or (6) Except as otherwise provided in this Section, a breach, or series of breaches, by the City of any term, covenant or undertaking to the DBOM Contractor or any representation or warranty made by the City to the DBOM Contractor in this DBOM Agreement being incorrect when made, which has a material and adverse effect on the DBOM Contractor. Section 22.2. DBOM CONTRACTOR OPTIONS UPON CITY EVENT OF DEFAULT. After the occurrence of a City Event of Default and while a City Event of Default is continuing, the DBOM Contractor may, at its option, serve notice on the City of the occurrence and specifying the details of such a City Event of Default. If the relevant matter or circumstance has not been rectified or remedied by the City: (1) In the case of a City Event of Default under subsections 22.1(1), Section 22.1(2) or Section 22.1(3) (City Events of Default), within 30 days of such notice; or (2) In the case of a City Event of Default under subsections 22.1(4), Section 22.1(5) or Section 22.1(6) (City Events of Default), within 45 days of such notice or within such longer period as is reasonably required for the City to rectify or remedy such City Event of Default as long as the City is diligently pursuing such rectification or remedy; the DBOM Contractor may serve a further notice on the City terminating this DBOM Agreement with immediate effect and the DBOM Contractor also may bring an action to enforce payment of the amount due pursuant to this Article. Section 22.3. EFFECT OF TERMINATION. If this DBOM Agreement is terminated by the DBOM Contractor for cause as a result of an Event of Default by the City, the City shall pay the DBOM Contractor the same 156 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 22 DBOM Agreement City Events of Default amount which would be payable under Section 23.2(F) (Termination Payments) if this DBOM Agreement were terminated at the election of the City for convenience and without cause based on the date of termination. The City shall have no further liability to the DBOM Contractor for any Event of Default or termination under this Section. 157 3935946.13 043463 ARTICLE 23 TERMINATION Section 23.1. EXCLUSIVE RIGHTS OF TERMINATION. (A) Termination of this DBOM Agreement. The parties'sole right to terminate this DBOM Agreement shall be as set forth in this Article. (B) Exclusive Termination Rights. This Article, together with any other provisions of this DBOM Agreement expressly referred to in this Article or which expressly provide a party with a termination right, contain the entire and exclusive provisions and rights of the parties regarding termination of this DBOM Agreement; provided that termination of this DBOM Agreement shall not relieve the DBOM Contractor, Parent Company Guarantor, insurer, surety or financial institution that provides security for performance hereunder of its obligation for claims arising prior to termination. The right of the City to terminate this DBOM Agreement under this Article is in addition, and without prejudice, to any other right which the City may have in connection with the DBOM Contractor's non-compliance with this DBOM Agreement, including those set forth in Article 20 (Remedies of the Parties and City Step-In Rights). Section 23.2. TERMINATION. (A) City Termination Rights. This DBOM Agreement may be terminated by the City prior to the expiration of the Term: (1) In its discretion and for its convenience at any time, by delivery of notice to the DBOM Contractor stating that the termination is for the convenience of the City (a "Termination for Convenience"); (2) In connection with a DBOM Contractor Event of Default, pursuant to Article 21 (DBOM Contractor Events of Default); (3) In connection with an Uninsurable Force Majeure Event, pursuant to Section 15.2 (Uninsurable Force Majeure Events); (4) In connection with an Insurance Unavailability Event, pursuant to Section 15.6 (Unavailability of Insurance for Insurable Force Majeure Events or for Third-Party Liability); (5) In connection with the occurrence and persistence of an Extended Relief Event pursuant to Section 16.4 (Termination for Extended Relief Events); or (6) In connection with a Total Constructive Loss pursuant to subsection (C) of this Section. (B) DBOM Contractor Termination Rights. This DBOM Agreement may be terminated by the DBOM Contractor prior to the expiration of the Term in connection with a City Event of Default, pursuant to Article 22 (City Events of Default). (C) Termination Upon Total Constructive Loss. If a Total Constructive Loss occurs which renders the Project Facilities, or a substantial part thereof, unusable, and it is reasonably anticipated that the Project Facilities, or a substantial part thereof, will remain unusable for a continuous period of at least 180 days, then the City may terminate this DBOM 158 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination Agreement by notice to the DBOM Contractor, in which case the City shall pay compensation to the DBOM Contractor in accordance with Section 23.2(F) (Termination Payments). (D) Extent of Termination Rights. Except as provided or referred to in subsections (A) and (B) of this Section, neither party shall have the right to terminate this DBOM Agreement. (E) Termination Date. The Termination Date for any early termination of this DBOM Agreement as provided in subsections (A) or (B) of this Section shall be the date specified in the table below. It shall not be a condition to the establishment of the Termination Date that the applicable Termination Amount has been paid. Termination Circumstance Termination Date Termination for Convenience by the City The date specified in the City's written notice of termination which shall be no less than 60 days after the date on which such termination notice is given Termination Upon a DBOM Contractor Event The date written notice of termination is of Default delivered by the City Termination Upon a City Event of Default The date written notice of termination is delivered by the DBOM Contractor Termination for Extended Relief Events The date that is 30 days from the delivery of written notice thereof by the City Termination for Uninsurable Risk The date that is 30 days from the delivery of written notice thereof by the City Termination upon Total Constructive Loss The date that is 30 days from the delivery of written notice thereof by the City (F) Termination Payments. In the event that the City terminates this DBOM Agreement: (1) For convenience prior to the Acceptance Date, the DBOM Contractor shall be entitled to a convenience termination settlement payment in an amount equal to the sum of: (i) The difference between, (a) the value of all such Design-Build Period Work performed up to the Termination Date, and (b) all payments already made to the DBOM Contractor pursuant to this DBOM Agreement for Design-Build Work; (ii) Subject to subsection (F) of this Section, all actual and reasonable demobilization costs and reasonable amounts due in settlement of terminated Subcontracts; and (iii) A convenience termination fee in the amount of$1,000,000. In the event of a termination for convenience under this subsection, the DBOM Contractor acknowledges and agrees that it shall not be entitled to any compensation in excess of the value 159 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination of the Design-Build Work performed plus its settlement and closeout costs, except for the convenience termination fee included in item (iii) above. Under no circumstances shall the DBOM Contractor or any Subcontractor be entitled to anticipatory or unearned profits, unabsorbed overhead, opportunity costs, or consequential or other damages as a result of a Termination for Convenience. (2) For convenience on or after the Acceptance Date, the DBOM Contractor shall be entitled to a convenience termination settlement payment in an amount equal to the sum of: (i) The amount of Service Fees earned as of the Termination Date but not paid; (ii) All actual and reasonable demobilization costs and reasonable amounts due in settlement of terminated Subcontracts; and (iii) The sum of $1,000,000 if such termination occurs in the first Contract Year, which amount will decrease by one-thirtieth (1/30th) each Contract Year thereafter. In the event of a termination for convenience under this subsection, the DBOM Contractor acknowledges and agrees that it shall not be entitled to any compensation in excess of the value of the amount set forth above. Under no circumstances shall the DBOM Contractor or any Subcontractor be entitled to anticipatory or unearned profits, unabsorbed overhead, opportunity costs, or consequential or other damages as a result of a Termination for Convenience. (3) For an Uninsurable Force Majeure Event pursuant to Section 15.2 (Uninsurable Force Majeure Events), an Insurance Unavailability Event pursuant to Section 15.6 (Unavailability of Insurance for Insurable Force Majeure Events or for Third- Party Liability), an Extended Relief Event pursuant to Section 16.4 (Termination for Extended Relief Events) or a Total Constructive Loss pursuant to subsection (C) of this Section, the DBOM Contractor shall be entitled to a termination settlement payment equal to the sum of items (i) and (ii) under (1) above if such termination occurs prior to the Acceptance Date, or the sum of items (i) and (ii) under (2) above if such termination occurs on or after the Acceptance Date. (G) Settlement of Subcontracts. The obligation of the City to pay amounts due in settlement of Subcontracts under subsection (F) of this Section shall be limited to the reasonable costs incurred by the DBOM Contractor in settling and closing out Subcontracts that the City does not elect to have assigned to it pursuant to Section 23.3 (Transfer to the City of Assets, Contracts and Documents) and shall be subject to Cost Substantiation. Any termination settlement payment under any Subcontract shall be calculated in the same manner as provided in items (i) and (ii) in subsection (F) of this Section with respect to the convenience termination settlement payment to the DBOM Contractor. In no event shall the City be responsible for anticipatory or unearned profits, unabsorbed overhead, opportunity costs or consequential or other damages payable to any Subcontractor as a result of the termination of any Subcontract. (H) Payment of Amounts Due as a Result of Termination. The DBOM Contractor shall submit a termination claim for a termination described in (F) above in the form and with the certification prescribed by the City, promptly following the Termination Date but in any event not later than 60 (sixty) days following the Termination Date. In the event of a failure of the DBOM Contractor to submit a termination claim within the time allowed pursuant to this subsection (H), the City may determine, on the basis of information available to the City, the amount, if any, due to the DBOM Contractor by reason of the termination and shall thereupon pay to the DBOM Contractor the amount so determined, if any. Any amount payable to the DBOM Contractor pursuant to this Section shall be reduced in the amount of(1) any claim the 160 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination City may have against the DBOM Contractor under this DBOM Agreement, and (2) the fair value, as determined by the City, of property which is destroyed,lost, stolen or damaged so as to become undeliverable to the City, excluding normal spoilage and except to the extent that the City shall have otherwise expressly assumed the risk of loss with respect to such property hereunder. Any payment required to be made to the DBOM Contractor pursuant to this Section shall be made within 120 (one hundred twenty) days following the Termination Date, subject to compliance by the DBOM Contractor with its obligations under Section 23.3 (Transfer to the City of Assets, Contracts and Documents). Any payment required to be made by the DBOM Contractor to the City pursuant to this Section shall be made within 120 (one hundred twenty) days following the Termination Date. In the event of a dispute between the parties as to the amount of any payment required to be made pursuant to this Section, either party may elect to initiate dispute resolution procedures in accordance with Article 19 (Dispute Resolution). (I) Consideration for Convenience Termination Amount. The right of the City to terminate this DBOM Agreement for its convenience and in its discretion in accordance with this Article constitutes an essential part of the overall consideration for this DBOM Agreement, and it shall not be a breach of the City nor shall the DBOM Contractor be entitled to any damages, including a breach of the City's implied covenant of good faith and fair dealing, in the exercise of its right to terminate this DBOM Agreement under subsection (A)(1) of this Section for the convenience of the City. (J) Continued Performance. The parties shall continue to perform their obligations under this DBOM Agreement until the Termination Date, notwithstanding the giving of any notice of default or notice of termination. (K) Completion or Continuance by City. After the Termination Date, subject to Section 23.4 (Transitional Arrangements), the City may at any time (but without any obligation to do so) take any and all actions necessary or desirable to continue and complete the Project Services so terminated, including entering into contracts with other operators and contractors. Section 23.3. TRANSFER TO THE CITY OF ASSETS, CONTRACTS AND DOCUMENTS. (A) Transfer Responsibilities. On or promptly after the Termination Date: (1) If the Termination Date occurs prior to the Acceptance Date: (a) the DBOM Contractor shall preserve and protect the structures, equipment, materials and other property comprising the Project as so far constructed; and (b) insofar as any transfer will be necessary to fully and effectively transfer property to the City, the DBOM Contractor shall transfer to, and there will vest in, the City, free from all financial encumbrances, such part of the Project as has been constructed on or has become affixed to the Project Site and, subject to payment by the City of the DBOM Contractor's reasonable charges for work not previously compensated, if the City so elects: (i) the constructed plant and equipment will remain available to the City for the purposes of completing the Design-Build Work; and (ii) all other Project-related plant and all materials on or near the Project Site will remain available to the City for the purposes of completing the Design-Build Work; 161 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination (2) If the City so elects, the DBOM Contractor shall assign to the City each Subcontract that is exclusively for the Project that the City elects, in writing, to have assigned to it, with the City assuming, and the DBOM Contractor being relieved of, all obligations under the Subcontract from the date of assignment; (3) The DBOM Contractor shall turn over to the City, free from any security interest, all or any part of the stocks of material and other assets, spare parts and other moveable property reasonably required by the City in connection with the operation of the Project or the provision of the Project Services; (4) The DBOM Contractor shall deliver to the City (to the extent not already delivered to the City): (a) all existing designs, plans and other documents produced in connection with the Project and in the control of the DBOM Contractor; (b) one complete set of existing constructions drawings showing all alterations made to the Project since the commencement of operation of the Project; (c) one complete set of existing, up-to-date maintenance, operation and training manuals for the Project, subject to reasonable generally applicable third-party licensing terms; (d) relevant information pertaining to any Legal Proceedings against the DBOM Contractor by any Subcontractor or other third parties relating to the termination of the Design-Build Work or the Operation and Maintenance Services (or any Subcontracts); and (e) copies of all Subcontracts, together with a statement of: (i) the items ordered and not yet delivered pursuant to each agreement; (ii) the expected delivery date of all such items; (iii) the total cost of each agreement and the terms of payment; and (iv) the estimated cost of canceling each agreement; (5) The DBOM Contractor shall use all reasonable efforts to ensure that the benefit of existing Project Intellectual Property and all warranties in respect of mechanical and electrical plant and equipment used or made available by the DBOM Contractor under this DBOM Agreement and included in the Project but not previously assigned or licensed to the City are assigned, licensed or otherwise transferred to the City; (6) To the extent permitted by Applicable Law, the DBOM Contractor shall assign to the City all Governmental Approvals; (7) The DBOM Contractor shall deliver to the City all books, records and files required to be kept by the DBOM Contractor hereunder (the DBOM Contractor having the right to retain copies thereof) unless such documents are: 162 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination (a) required by Applicable Law to be retained by the DBOM Contractor or a Subcontractor, in which case complete copies will be delivered to the City; or (b) privileged from production pending resolution of any outstanding dispute, in which case such records will be delivered forthwith upon resolution of such dispute, provided that any records that are necessary for the performance of the Project Services will be delivered to the City no later than the Termination Date; (8) The DBOM Contractor shall give written notice of termination, promptly under each policy of Required Insurance (with a copy of each such notice to the City), but permit the City to continue such policies thereafter at its own expense, if possible; and (9) The DBOM Contractor shall take such other actions, and execute such other documents as may be necessary to effectuate and confirm the foregoing matters, or as may be otherwise necessary or desirable to minimize the City's costs, and take no action which shall increase any amount payable by the City under this DBOM Agreement. (B) No Additional Compensation. The DBOM Contractor shall ensure that provision is made in all applicable contracts to ensure that the City will be in a position to exercise its rights, and the DBOM Contractor shall be in a position to comply with its obligations, under this Section without additional payment or compensation to any person. (C) Use of Design Documents Following Termination During the Design-Build Period. If this DBOM Agreement is terminated during the Design-Build Period and the City (or any designee of the City) uses any Design Documents or other Intellectual Property developed by or on behalf of the DBOM Contractor without the involvement of the DBOM Contractor for such work, then the DBOM Contractor is hereby thereupon released from all liability on account of such use, except to the extent caused by any of the matters referred to in subsections (1) through (9), inclusive, of Section 25.1 (DBOM Contractor's Obligation to Indemnify); and Section 23.4. TRANSITIONAL ARRANGEMENTS. (A) DBOM Contractor Transitional Obligations. The DBOM Contractor shall, in connection with the expiration or termination of this DBOM Agreement: (1) Stop the Project Services on the Termination Date; (2) On the Termination Date deliver to the City: (a) all keys, access codes or other devices required to operate the Project; and (b) any Project Intellectual Property required to be delivered by the DBOM Contractor pursuant to subsection Section 23.3(A)(5) (Transfer Responsibilities); (3) As soon as practicable after the Termination Date vacate, and cause the DBOM Contractor Persons to vacate, the Project Site, and leave the Project Site and the Project in a safe, clean and orderly condition; (4) On request by the City and on payment of the DBOM Contractor's reasonable costs by the City, for a period not to exceed 90 days after the Termination Date, co-operate fully with the City and any successor providing to the City services in 163 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination the nature of any of the Project Services or any part of the Project Services, in order to achieve a smooth transfer of the manner in which the City obtains services in the nature of the Project Services and to avoid or mitigate in so far as reasonably practicable any inconvenience or any risk to the health and safety of the employees of the City and members of the public; (5) As soon as practicable following the Termination Date, remove from the Project Site all property of the DBOM Contractor or any DBOM Contractor Person that is not transferred to the City pursuant to Section 23.3 (Transfer to the City of Assets, Contracts and Documents) (or not belonging to the City) and if it has not done so within 60 days after any notice from the City requiring it to do so, the City may (without being responsible for any loss, damage, costs or expenses) remove and sell any such property and will hold any proceeds less all costs incurred to the credit and direction of the DBOM Contractor; and (6) Comply with all requirements of subsection 10.3(G) (Exit Testing). (B) Equitable Relief. Without prejudice to any other rights and remedies that the City may have, each of the parties agrees that damages may not be an adequate remedy for a breach of subsection (A) of this Section, and that the City will, in such case, be entitled to the remedies of injunction, specific performance or other equitable relief for any threatened or actual breach of subsection (A) of this Section. Section 23.5. DBOM CONTRACTOR TO COOPERATE. If the City wishes to conduct a competition prior to the Termination Date with a view to entering into an agreement for the provision of services (which may or may not be the same as, or similar to, the Project Services or any of them) following the Termination Date, the DBOM Contractor shall prior to the Termination Date co-operate with the City fully in such competition process, including by: (1) Providing any information in the DBOM Contractor's control or possession which the City may reasonably require to conduct such competition; and (2) Assisting the City by providing any participants in such competition process with access to the Project Site and the Project provided such access does not affect the Project Services in a way that results in any reduction in the Design-Build Price or the Service Fee, as applicable. Section 23.6. LIMITATION ON DBOM CONTRACTOR LIABILITY. (A) Initial Stated Monetary Limitation. The DBOM Contractor's aggregate liability under this DBOM Agreement and, accordingly, the liability of the Guarantor under the Guaranty Agreement, with respect to damages arising from a termination of this DBOM Agreement for the period beginning on the Effective Date and ending on the date which is two calendar years after the Acceptance Date shall not exceed an amount equal to the Design-Build Price. (B) Delay Liquidated Damages Sub-Limit. The DBOM Contractor's aggregate liability under this DBOM Agreement and, accordingly, the liability of the Guarantor under the Guaranty Agreement, with respect to the payment of liquidated damages pursuant to Section 6.6 (Failure To Achieve Acceptance by the Scheduled Acceptance Date), shall not exceed an amount equal to 10% of the Design-Build Price. 164 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 23 DBOM Agreement Termination (C) Stated Monetary Limitation Following First Calendar Year After Acceptance Date through the End of the Term. The DBOM Contractor's aggregate liability under this DBOM Agreement and, accordingly, the liability of the Guarantor under the Guaranty Agreement, with respect to damages payable to the City arising out of the termination of this DBOM Agreement for the period beginning on the date which is two years after the Acceptance Date and continuing until the end of the Term shall not exceed an amount equal to $20,000,000. Section 23.7. APPLICABILITY AND INTERPRETATION OF THE LIMITATIONS ON LIABILITY. The limitations on liability provided for in Section 23.6 (Limitation on DBOM Contractor Liability) apply solely to the liability of the DBOM Contractor and the Guarantor for damages to the City arising out of a termination of this DBOM Agreement and specified liquidated damages,as applicable. The limitations on liability provided for in Section 23.6 (Limitation on DBOM Contractor Liability) do not apply to any other liability, loss, damage, cost or expense that may be incurred by the DBOM Contractor or the Guarantor in connection with this DBOM Agreement, including any of the following liabilities, losses,damages,costs or expenses: (1) Any financial, economic or other loss, cost or expense sustained by the DBOM Contractor in the performance of the Project Services or any other loss sustained by the DBOM Contractor, the Guarantor, or any other party in connection with this DBOM Agreement, the Guaranty Agreement or other agreement relating to the Project; (2) Any loss, cost or expense sustained by the DBOM Contractor, the Guarantor, or the DBOM Contractor's Surety in order to perform the Project Services, including those incurred in seeking to cure or prevent any breach of this DBOM Agreement; (3) Any fines or penalties levied or imposed by any Governmental Body; (4) Any claims, losses or penalties incurred by the DBOM Contractor or the Guarantor to third parties in any Legal Proceedings; (5) Any defense or indemnity obligation incurred or owed by the DBOM Contractor pursuant to Article 25 (Indemnification); (6) Payment of any defense costs,including attorney's fees,to,for, or on behalf of the City or any other City Indemnitee with respect to any third party claim; (7) Any payments made to the City or to any other City Indemnitee in connection with any Required Insurance under this DBOM Agreement, including the proceeds of Required Insurance and the payment of any deductible; and (8) Any claims, losses, penalties or settlement payments paid to the City in connection with any tort claim by the City against the DBOM Contractor arising from gross negligence, intentional or willful misconduct, fraud, misrepresentation or false claims. 165 3935946.13 043463 ARTICLE 24 ASSIGNMENT AND CHANGE IN CONTROL Section 24.1. LIMITATION ON ASSIGNMENT BY THE DBOM CONTRACTOR. The DBOM Contractor shall not assign, transfer or otherwise dispose of any interest in this DBOM Agreement except with the prior written consent of the City. Section 24.2. LIMITATION ON CHANGE IN CONTROL. (A) Change in Control Defined. For purposes of this DBOM Agreement "Change in Control" means with respect to a person any direct or indirect change in the ownership or control of any legal, beneficial or equitable interest in any or all of the shares or equity in the person (including the control over the exercise of voting rights conferred on equity share capital, unit interests or equity interests or the control over the right to appoint or remove directors, a general partner, a managing member or other managers), including changes arising from assignment or transfer of existing shares or equity, issuance of new shares or equity or amalgamation, merger consolidation, amendment of a limited partnership certificate or other reorganization, or any other direct or indirect change which results in an equity holder or group of equity holders, other than the equity holders immediately prior to the change, directly or indirectly: (1) Controlling the composition of the majority of the board of directors of the person or of a general partner or manager of the person; (2) Controlling the decisions made by or on behalf of the person, including by controlling the voting power of the board of directors or by controlling the voting power of any class of shareholders or equity holders of any of the person, a general partner of the person or a manager of the person or otherwise; (3) Holding equity (either beneficially or otherwise) of that person with a subscribed value (taking into account contributions to be made in the case of a limited partnership) of more than one half of the subscribed value (taking into account contributions to be made in the case of a limited partnership) or equity (either beneficially or otherwise) of that person with more than one half of the voting rights; or (4) Having the ability to direct or cause the direction of the management, actions or policies of the person. (B) Limitations. No Change in Control of the DBOM Contractor shall be permitted (whether by the DBOM Contractor or otherwise) to occur except: (1) Arising from any bona fide open market transaction in any shares or other securities of the DBOM Contractor or of any Affiliate or holding company of the DBOM Contractor effected on a recognized public stock exchange; (2) Any assignment, sale or transfer by a shareholder, general partner, manager or member of the DBOM Contractor of any legal, beneficial or equitable interest in any shares or equity of the DBOM Contractor so long as an Affiliate of the DBOM Contractor remains in control of the DBOM Contractor, unless otherwise approved by the City, and the Parent Guaranty remains in effect; or 166 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 24 DBOM Agreement Assignment and Change in Control (3) With the prior written consent of the City, which will not be unreasonably withheld, conditioned or delayed. Section 24.3. FACTORS THE CITY MAY CONSIDER. In determining whether to provide its consent under Section 24.1 (Limitation on Assignment by the DBOM Contractor), or subsection Section 24.2(B) (Limitations), it will be reasonable for the City to refuse its consent if: (1) The proposed assignee or the new party in control of the DBOM Contractor, as the case may be, or any of their Affiliates, is a Restricted Person; (2) The proposed assignee cannot comply with the City's conflict of interest requirements; (3) The proposed assignee or the new party in control of the DBOM Contractor, as the case may be, is, in the reasonable opinion of the City, less creditworthy than the assignor; (4) The experience, background or reputation of the proposed assignee and the key individuals in operating projects or facilities of a similar nature, in the reasonable opinion of the City, is not sufficient to meet the DBOM Contractor's obligations under this DBOM Agreement; or (5) The assignment or Change in Control could, in the reasonable opinion of the City, have a material and adverse effect on the City or the Project. Section 24.4. LIMITATION ON ASSIGNMENT BY THE CITY. The City may assign, in its discretion, this DBOM Agreement to any agency, authority, commission, or similar administration of the City, that succeeds to the statutory powers and authority of the City regarding operations of a wastewater facility, with an actual (or expected, if such interest is to be transferred to a newly formed agency with a separate enterprise fund) credit profile that is equal to or better than the City. The City may otherwise assign this DBOM Agreement to any other party with the DBOM Contractor's prior written consent, which shall not be unreasonably withheld. It will not be unreasonable for the DBOM Contractor to withhold its consent to any assignment by the City where the assignee does not have an equal to or better credit rating as the City. Any assignee must assume all obligations under this DBOM Agreement or otherwise agree to be subject to the terms of this DBOM Agreement; and if an event of default by the assigning party has occurred and is continuing, either at the time of the request for consent or on the effective date of the proposed transfer, the assigning party must either cure such default prior to the assignment, or, as an express condition of such transfer, the proposed transferee shall agree to cure all defaults promptly following the effective date of such transfer. Section 24.5. COSTS OF REQUEST FOR CONSENT. If the DBOM Contractor requests consent to an assignment, transfer or disposition pursuant to Section 24.1 (Limitation on Assignment by the DBOM Contractor) or to a Change in Control pursuant to Section 24.2 (Limitation on Change in Control), the DBOM Contractor shall pay the City's reasonable internal administrative and personnel costs and all out-of-pocket costs in connection with considering any such request. At the time of the request the DBOM Contractor shall make a payment to the City against its obligation under this Section of$25,000 (Index-Linked). After the decision of the City is rendered, the City will either refund 167 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 24 DBOM Agreement Assignment and Change in Control any overpayment or invoice the DBOM Contractor for any additional amounts due under this Section with reasonable substantiation of such costs. 168 3935946.13 043463 ARTICLE 25 INDEMNIFICATION Section 25.1. DBOM CONTRACTOR'S OBLIGATION TO INDEMNIFY. The DBOM Contractor shall defend, indemnify and keep each City Indemnitee indemnified at all times from and against all Loss-and-Expense that any City Indemnitee may sustain in connection with any loss of or physical damage to property or assets of any City Indemnitee, or any claim made by one or more third parties (including for loss of or physical damage to property or assets), or any claim for, or in respect of, the death, personal injury, disease or illness of any person, including any City Indemnitee, arising by reason of any: (1) Breach of any representation or warranty by the DBOM Contractor under this DBOM Agreement; (2) Negligent act or omission of the DBOM Contractor; (3) Willful misconduct of the DBOM Contractor; (4) Non-compliance by the DBOM Contractor with any of the provisions of this DBOM Agreement or any document, instrument or agreement delivered to the City as required under this DBOM Agreement; (5) A claim pursuant to subsection 9.2(C) (Indemnity for Loss-and-Expense from Non-Complying Effluent); (6) A claim pursuant to subsection 9.6(J) (Failure to Comply with the Residuals Management Guarantee); (7) A claim pursuant to subsection 9.9(D) (Indemnification); (8) DBOM Contractor Hazardous Substances; or (9) Breach by the DBOM Contractor of, or non-compliance by the DBOM Contractor with, any Governmental Approval or Applicable Law, or the failure of the DBOM Contractor to obtain all necessary DBOM Contractor Managed Governmental Approvals in accordance with this DBOM Agreement; except to the extent caused by a Relief Event, City Fault, or a City Event of Default. The DBOM Contractor's indemnity obligations under this Section shall not be limited by any coverage exclusions or other provisions in any policy of Required Insurance or other insurance maintained by the DBOM Contractor which is intended to respond to such events. This Section may be relied upon by the City Indemnitees and may be enforced directly by any of them against the DBOM Contractor in the same manner and for the same purpose as if pursuant to a contractual indemnity directly between them and the DBOM Contractor. Section 25.2. INDEMNIFICATION PROCEDURES. (A) Notice. If a City Indemnitee receives any notice, demand, letter or other document concerning any claim for which it appears that the City Indemnitee is, or may become entitled to, indemnification or compensation under this DBOM Agreement in respect of the entire claim, the City Indemnitee shall give notice in writing to the DBOM Contractor as soon as reasonably practicable and in any event within 10 Business Days of receipt thereof. 169 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 25 DBOM Agreement Indemnification (B) DBOM Contractor Right to Dispute Claim. If notice is given as provided in subsection (A) of this Section, the DBOM Contractor shall be entitled to dispute the claim in the name of the City Indemnitee at the DBOM Contractor's own expense and take conduct of any defense, dispute, compromise, or appeal of the claim and of any incidental negotiations. The City Indemnitee will give the DBOM Contractor all reasonable cooperation, access and assistance for the purposes of considering and resisting such claim. (C) Conflicts of Interest. In defending any claim as described in subsection (B) of this Section in which there is a conflict of interest between the DBOM Contractor and the City Indemnitee, the City Indemnitee may appoint independent legal counsel in respect of such claim and, if it is determined that the City Indemnitee is entitled to indemnification by or compensation from the DBOM Contractor, all reasonable costs and expenses incurred by the City Indemnitee in so doing will be included in the indemnity or compensation from the DBOM Contractor. (D) Rights and Duties of the Parties. With respect to any claim conducted by the DBOM Contractor pursuant to subsection (B) of this Section: (1) The DBOM Contractor shall keep the City Indemnitee fully informed and consult with it about material elements of the conduct of the claim; (2) The DBOM Contractor shall demonstrate to the City Indemnitee, at the reasonable request of the City Indemnitee, that the DBOM Contractor has sufficient means to pay all costs and expenses that it may incur by reason of conducting the claim; and (3) The DBOM Contractor shall not pay or settle such claims without the consent of the City Indemnitee, such consent not to be unreasonably withheld or delayed. (E) City Indemnitee Rights to Conduct Defense. The City Indemnitee may take conduct of any defense, dispute, compromise or appeal of the claim and of any incidental negotiations if: (1) The DBOM Contractor is not entitled to take conduct of the claim in accordance with subsection (B) of this Section; or (2) The DBOM Contractor fails to notify the City Indemnitee of its intention to take conduct of the relevant claim within 10 Business Days of the notice from the City Indemnitee under subsection (B) of this Section or notifies the City Indemnitee that it does not intend to take conduct of the claim; or (3) The DBOM Contractor fails to comply in any material respect with subsection (D) of this Section. (F) Transfer of Conduct of Claim to City Indemnitee. The City Indemnitee may at any time give notice to the DBOM Contractor that it is retaining or taking over, as the case may be, the conduct of any defense, dispute, compromise, settlement or appeal of any claim, or of any incidental negotiations, to which subsection (B) of this Section applies. On receipt of such notice the DBOM Contractor will promptly take all steps necessary to transfer the conduct of such claim to the City Indemnitee, and will provide to the City Indemnitee all reasonable co- operation, access and assistance for the purposes of considering and resisting such claim. (G) Infringement of Intellectual Property Rights. In response to any claim of infringement or alleged infringement of the Intellectual Property rights of any person, the DBOM Contractor may replace such infringing or allegedly infringing item provided that: 170 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 25 DBOM Agreement Indemnification (1) The replacement is performed without additional cost to the City; and (2) The replacement has at least equal quality performance capabilities when used in conjunction with the Project. 171 3935946.13 043463 ARTICLE 26 MISCELLANEOUS PROVISIONS Section 26.1. OWNERSHIP OF THE PROJECT AND ENVIRONMENTAL ATTRIBUTES; NO LEASE. (A) Project Ownership. The Project shall be owned by the City at all times. This DBOM Agreement does not and is not intended by the parties to create in the DBOM Contractor any form of property interest, e.g., lease or fee, in the real or personal property of the Project Site. The Design-Build Price and the Service Fee paid by the City to the DBOM Contractor do not contain any element, adjustment, or offset for the DBOM Contractor's occupancy, but rather the DBOM Contractor's occupancy is as necessary and convenient to perform the Project Services under this DBOM Agreement. (B) Environmental Attributes Ownership. The DBOM Contractor acknowledges and agrees that the City owns and shall maintain ownership of all renewable energy credits or certificates, as well as all other environmental attributes (including carbon and carbon trading credits, emission reduction credits, emissions allowances, energy efficiency credits and green tags) associated with the Project. Any incentive payment, rebate, credit or other benefit provided or otherwise established by any company, organization, or governmental entity as a result of the Project shall inure to the benefit of the City. The DBOM Contractor recognizes the City's interest in the foregoing and hereby waives any interest it may otherwise have or be able to claim with respect to the same. The DBOM Contractor shall provide any assistance reasonably requested by the City in applying for, claiming and securing the benefit of the ownership of such environmental attributes, including complying with all applicable reporting and documentation requirements. Section 26.2. RELATIONSHIP OF THE PARTIES. The DBOM Contractor is an independent contractor of the City and the relationship between the parties shall be limited to performance of this DBOM Agreement in accordance with its terms. Neither party shall have any responsibility with respect to the services to be provided or contractual benefits assumed by the other party. Nothing in this DBOM Agreement shall be deemed to constitute either party a partner, agent or legal representative of the other party. No liability or benefits, such as workers compensation, pension rights or liabilities, or other provisions or liabilities arising out of or related to a contract for hire or employer/employee relationship shall arise or accrue to any party's agent or employee as a result of this DBOM Agreement or the performance thereof. Section 26.3. [RESERVED]. Section 26.4. DBOM CONTRACTOR PERSONS. The DBOM Contractor shall, as between itself and the City, be responsible for, and not relieved of its obligations hereunder by, the acts, omissions, breaches, defaults, non- compliance, negligence and willful misconduct of each DBOM Contractor Person, and all references in this DBOM Agreement to any act, omission, breach, default, non-compliance, negligence or willful misconduct of the DBOM Contractor shall be construed accordingly to include any such act, omission, breach, default, non-compliance, negligence or willful misconduct committed by a DBOM Contractor Person. 172 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions Section 26.5. RISK OF ADVERSE TAX OR ACCOUNTING TREATMENT. There shall be no adjustment of the Design-Build Price, the Service Fee or any other amount payable to, and no relief from any obligation of, the DBOM Contractor hereunder on account of: (1) Except as provided in Section 16.2 (Discriminatory or Specified Changes in Tax Law) with respect to a Discriminatory Change in Tax Law, any change in any provision of Income Tax law to take effect after the Effective Date pertaining to the transactions contemplated hereby which affects the DBOM Contractor or any other person (including, without limitation, any provisions thereof pertaining to Income Tax rates or to the Income Tax treatment of the Design-Build Price, the Service Fee or any other payment between the parties), notwithstanding any assumptions made by the DBOM Contractor in entering into this DBOM Agreement or any Material Contract as to the provisions of Income Tax law which would be applicable to this transaction or their effect on the DBOM Contractor or such other person, (2) Any administrative or judicial determination which is adverse to the DBOM Contractor or any other person as to any Income Tax treatment or consequence arising in connection herewith, including any such determination made with respect to depreciation, amortization or credits with respect to equity invested in the Project or with respect to the exclusion of interest on any obligation issued to finance the Project where such interest was intended to be excludable from taxpayer gross income, (3) Any inability of the DBOM Contractor or other person to fully utilize any Income Tax benefits which may have been assumed to accrue on account of the transactions contemplated hereby, or (4) Any application of or change in accounting standards to the transactions contemplated hereby which may be inconsistent with the accounting standards or application thereof which may have been assumed by the DBOM Contractor or any other person in connection with such transactions. Section 26.6. NEGOTIATED LUMP SUM PRICING OF ADDITIONAL WORK. This DBOM Agreement obligates the City to pay for certain additional costs resulting from Relief Events and otherwise as more specifically provided herein. It is the expectation of the parties, in general, that the City will pay for such costs on a lump sum basis, and that the lump sum price will be negotiated in advance of the DBOM Contractor's performance of the work. For example, if a Change in Law Event occurs, as required under Article 16 (Change in Law Events and Other Relief Events), the parties will assess the impact of the Change in Law Event, take all appropriate mitigation steps, determine any necessary Capital Modifications and operating changes, and agree upon lump sum pricing therefor. To facilitate such negotiations, the DBOM Contractor shall furnish the City with all information reasonably required by the City regarding the DBOM Contractor's expected costs of performing the work and its mark-up. Once the parties agree upon the lump sum price, the DBOM Contractor's actual costs of performance shall not be subject to Cost Substantiation unless after-the-fact Cost Substantiation with respect to all or a portion of the DBOM Contractor's actual costs was agreed to by the parties in establishing the lump sum price. 173 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions Section 26.7. COST SUBSTANTIATION OF ADDITIONAL WORK NOT SUBJECT TO LUMP SUM PRICE NEGOTIATION. (A) Cost Substantiation Generally. The DBOM Contractor shall provide a Cost Substantiation certificate in accordance with subsection (C) of this Section for any additional costs for which the City is financially responsible hereunder which have not been subject to lump sum price negotiation. In incurring costs which are or may be subject to Cost Substantiation, the DBOM Contractor shall utilize competitive practices to the maximum reasonable extent (including, where practicable, obtaining three competing quotes or estimates for costs expected to be in excess of$50,000 (Index-Linked)), and shall enter into Subcontracts on commercially reasonable terms and prices in light of the work to be performed and the City's potential obligation to pay for it; provided, however, that during the Design-Build Period, subject to the written consent of the City, the DBOM Contractor shall not be required to utilize competitive practices for additional work self-performed by a Subcontractor that is an original party to (and not an assignee under) Subcontracts that pre-existed the need and request for additional work. If the DBOM Contractor is not required to utilize competitive practices, it shall instead demonstrate to the City that the costs for which the City is financially responsible are commercially reasonable. (B) Costs Requiring Cost Substantiation. Cost Substantiation shall be provided as soon as reasonably practicable after the costs which require substantiation have been incurred by the DBOM Contractor. Examples of costs which require substantiation include: (1) Work done on an emergency basis to respond to a Relief Event, where it is not reasonably practicable for the parties in advance to negotiate a lump sum price for the work; and (2) Work done by the DBOM Contractor under Article 23 (Termination) upon the expiration or termination of this DBOM Agreement, to the extent such costs are the responsibility of the City under Article 23 (Termination). Cost Substantiation shall also be required where the parties agree that the DBOM Contractor shall perform additional work on lump sum or guaranteed maximum price basis, subject to the limitations set forth in subsection (E) of this Section. (C) Cost Substantiation Certificate. Any certificate delivered hereunder to substantiate cost shall state the amount of such cost and the provisions of this DBOM Agreement under which such cost is chargeable to the City, shall describe the competitive or other process utilized by the DBOM Contractor to obtain the commercially reasonable price, and shall state that such services and materials are reasonably required pursuant to this DBOM Agreement. The Cost Substantiation certificate shall be accompanied by copies of such documentation as shall be necessary to reasonably demonstrate that the cost as to which Cost Substantiation is required has been paid. Such documentation shall be in a format reasonably acceptable to the City and shall include reasonably detailed information concerning all Subcontracts and, with respect to self-performed work: (1) The amount and character of materials, equipment and services furnished or utilized, the persons from whom purchased, the amounts payable therefor and related delivery and transportation costs and any sales or personal property Taxes; (2) A statement of the equipment used or to be used and any rental payable therefor; (3) Employee hours, duties, wages, salaries, benefits and assessments; and 174 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions (4) Profit, administration costs, bonds, insurance,Taxes, premiums overhead and other expenses. (D) Evidence of Costs Incurred. To the extent reasonably necessary to confirm direct costs subject to Cost Substantiation, copies of timesheets, invoices, canceled checks, expense reports, receipts and other documents, as appropriate, shall be delivered to the City, with the request for reimbursement of such costs. (E) Mark-Ups. For any self-performed work requiring Cost Substantiation, the DBOM Contractor shall be entitled to a mark-up of 10% for a combination of overhead, risk, profit and contingency for costs of its own personnel, and for subcontracted work a mark-up of 10% for a combination of overhead, risk, profit and contingency for costs of its Subcontractors. Section 26.8. INTEREST ON OVERDUE AMOUNTS. If payment of any amount payable by either party under this DBOM Agreement is not made when due (including any Termination Amount), then interest shall be payable on such overdue amount at the rate of interest specified in ORS 279C.570(2) (the "Overdue Rate"). The party to whom payment is owed and overdue shall notify the other party at least monthly of the overdue amount. Section 26.9. ALL CITY PAYMENT OBLIGATIONS SUBJECT TO APPROPRIATION. The City's obligation to make any payments under this DBOM Agreement is subject to annual appropriation. City staff responsible for the management of this DBOM Agreement shall use reasonable efforts to obtain an appropriation in the full amount required under this DBOM Agreement, including the submission of budget requests each year that are sufficient to cover the City's payment obligations for the next fiscal year. The City shall promptly provide notice to the DBOM Contractor following a failure of the Lake Oswego City Council during its normal appropriation process to appropriate funds sufficient to cover the City's payment obligations for the next fiscal year. Nothing in this DBOM Agreement may be construed as permitting any violation of Article XI, Section 7 of the Oregon Constitution or any other law limiting the activities, liabilities or monetary obligations of the City. Any provisions herein which would conflict with such Applicable Law are deemed inoperative to that extent. Section 26.10.GENERAL DUTY TO MITIGATE. (A) Mitigation by the DBOM Contractor. In all cases where the DBOM Contractor is entitled to receive any relief from the City or exercise any rights, including the right to receive any payments, costs, damages or extensions of time, whether on account of Relief Events or otherwise, the DBOM Contractor shall use all reasonable efforts to mitigate such amount required to be paid by the City to the DBOM Contractor by the City under this DBOM Agreement, or the length of the extension of time. Such mitigation measures shall include compliance with all procedures and other requirements necessary to obtain any available waiver or exemption from Taxes that would otherwise be borne directly or indirectly by the City. Upon request from the City, the DBOM Contractor shall promptly submit a detailed description, supported by all such documentation as the City may reasonably require, of the measures and steps taken by the DBOM Contractor to mitigate and meet its obligations under this subsection. (B) Mitigation by the City. In all cases where the City is entitled to receive from the DBOM Contractor any compensation, costs or damages, but not in any other cases, the City shall use all reasonable efforts to mitigate such amount required to be paid by the DBOM 175 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions Contractor to the City under this DBOM Agreement, provided that such obligation shall not require the City to: (1) Take any action which is contrary to the public interest, as determined by the City in its discretion; (2) Undertake any mitigation measures that might be available arising out of its status as a Governmental Body, but which measure would not normally be available to a private commercial party; or (3) Alter the amount of deductions for Deductions it is entitled to make in accordance with Appendix 13 (Performance Guarantees and Deductions). The City shall have no obligation to mitigate, implied or otherwise, except as set forth in this subsection or otherwise as expressly provided in this DBOM Agreement. Upon request by the DBOM Contractor, the City shall promptly submit a detailed description, supported by all such documentation as the DBOM Contractor may reasonably require, of the measures and steps taken by the City to mitigate and meet its obligations under this subsection. Section 26.11.BUSINESS AND COMMERCIAL OPPORTUNITIES. Except as may be specifically agreed in writing between the City and the DBOM Contractor during the Term, the City reserves the right to all business, commercial and other opportunities for, or related to, the Project. Section 26.12.DBOM AGREEMENT ADMINISTRATION. (A) Authority of City Representative. The DBOM Contractor understands and agrees that the City Representative has only limited authority with respect to the implementation of this DBOM Agreement, and cannot bind the City with respect to any DBOM Agreement Amendment, to waivers, or to incurring costs in excess of the amounts appropriated therefor. Within such limitations, the DBOM Contractor shall be entitled to rely on the written directions of the City Representative. The City Representative shall have the right at any time to issue the DBOM Contractor a written request for information relating to this DBOM Agreement. Any written request designated as a"priority request" shall be responded to by the DBOM Contractor within three Business Days. (B) Operation and Maintenance Notices. Operation and Maintenance Notices hereunder shall be given by e-mail, and may be given personally or by telephone promptly followed by e-mail confirmation. Operation and Maintenance Notices to the DBOM Contractor shall be given by the City Representative and Operation and Maintenance Notices to the City shall be given by the DBOM Contractor Representative. (C) Administrative Communications. The parties recognize that a variety of contract administrative matters will routinely arise throughout the Term. These matters will by their nature involve requests, notices, questions, assertions, responses, objections, reports, claims, and other communications made personally, in meetings, by phone, by mail and by electronic and computer communications. The purpose of this Section is to set forth a process by which the resolution of these matters, once resolution is reached, can be formally reflected in the common records of the parties so as to permit the orderly and effective administration of this DBOM Agreement. (D) Contract Administration Memoranda. The principal formal tool for the administration of routine matters arising under this DBOM Agreement between the parties which 176 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions do not require a DBOM Agreement Amendment shall be a "Contract Administration Memorandum". A Contract Administration Memorandum shall be prepared, once all preliminary communications have been concluded, to evidence the resolution reached by the City and the DBOM Contractor as to matters of interpretation and application arising during the course of the performance of their obligations hereunder. Such matters may include, for example: (1) Issues as to the meaning, interpretation or application of this DBOM Agreement in particular circumstances or conditions; (2) Calculations required to be made; (3) Notices, waivers, releases, satisfactions, confirmations, further assurances, consents and approvals given hereunder; and (4) Other similar routine contract administration matters. (E) Procedure. Either party may request the execution of a Contract Administration Memorandum. When resolution of the matter is reached, a Contract Administration Memorandum shall be prepared by or at the direction of the City reflecting the resolution. Contract Administration Memoranda shall be serially numbered, dated, signed by the City Representative and the DBOM Contractor Representative. The City and the DBOM Contractor each shall maintain a parallel, identical file of all Contract Administration Memoranda, separate and distinct from the DBOM Agreement Amendments and all other documents relating to the administration and performance of this DBOM Agreement. (F) Effect. Executed Contract Administration Memoranda shall serve to guide the ongoing interpretation and application of the terms and conditions of this DBOM Agreement. Section 26.13.DBOM AGREEMENT AMENDMENTS. (A) Amendments Generally. Notwithstanding the provisions of Section 26.12 (DBOM Agreement Administration), no change, alteration, revision or modification of the terms and conditions of this DBOM Agreement shall be made except through a written amendment to this DBOM Agreement (a "DBOM Agreement Amendment") duly authorized, approved or ratified by the City and duly authorized by the DBOM Contractor. DBOM Agreement Amendments shall be dated and signed by the City Representative and the DBOM Contractor Representative. (B) DBOM Agreement Amendments and Contract Administration Memoranda. In order to maintain a complete file of all agreements made with respect to the administration of this DBOM Agreement, when a DBOM Agreement Amendment or other agreement with respect to this DBOM Agreement is entered into and executed by the parties, a Contract Administration Memorandum shall be prepared attaching and acknowledging the DBOM Agreement Amendment or other agreement, but need not be executed by the parties. Section 26.14.CITY APPROVALS AND CONSENTS. When this DBOM Agreement requires any approval or consent by the City to a DBOM Contractor submittal, request or report, the approval or consent shall, within the limits of the authority of subsection 26.12(A) (Authority of City Representative), be given by the City Representative in writing and such writing shall be conclusive evidence of such approval or consent, subject only to compliance by the City with the Applicable Law that generally governs its affairs. Unless expressly stated otherwise in this DBOM Agreement, and except for (1) approvals provided for in Section 4.2 (Or Equals) of Appendix 6 (Design-Build Work Review 177 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions Procedures), which shall be governed by the terms of such Appendix, and (2) requests, reports and submittals made by the DBOM Contractor that do not, by their terms or the terms of this DBOM Agreement, require a response or action, if the City does not find a request, report or submittal acceptable, it shall provide written response to the DBOM Contractor describing its objections and the reasons therefor within 30 days of the City's receipt thereof. If no response is received, the request, report or submittal shall be deemed rejected unless the City's approval or consent may not be unreasonably delayed by the express terms hereof, and the DBOM Contractor may resubmit the same, with or without modification. Requests, reports and submittals that do not require a response or other action by the City pursuant to some specific term of this DBOM Agreement shall be deemed acceptable to the City if the City shall not have objected thereto within 30 days of the receipt thereof. Section 26.15.REFERENCE DOCUMENTS. It is the DBOM Contractor's responsibility to have conducted its own analysis and review of the Project and, before the execution of this DBOM Agreement, to have taken all steps it considers necessary to satisfy itself as to the accuracy, completeness and applicability of any Reference Documents upon which it places reliance and to assess all risks related to the Project. The DBOM Contractor shall not be entitled to and will not make (and will ensure that no Subcontractor makes) any claim against any City Indemnitee, whether in contract, tort or otherwise, including any claim in damages for extensions of time or for additional payments under this DBOM Agreement on the grounds: (1) Of any misunderstanding or misapprehension in respect of the Reference Documents; (2) That the Reference Documents were incorrect or insufficient; or (3) That incorrect or insufficient information relating to any Reference Document was given to it by any person other than the City, nor will the DBOM Contractor be relieved from any obligation imposed on or undertaken by it under this DBOM Agreement on any such ground. Section 26.16.ACTIONS OF THE CITY IN THEIR GOVERNMENTAL CAPACITY. Nothing in this DBOM Agreement shall be interpreted as limiting the rights and obligations of the City (or any department or agency thereof) under Applicable Law in their governmental capacity (including land use review and police power actions to protect health, safety and welfare, or the adoption or enforcement of any ordinance of general applicability), or as limiting the right of the DBOM Contractor to bring any action against the City (or any department or agency thereof), not based on this DBOM Agreement, arising out of any act or omission of the City(or any department or agency thereof) in their governmental capacity. Unless otherwise specified in this DBOM Agreement, all references to the City and its obligations are to the City as a party to this DBOM Agreement, not in its governmental capacity. Section 26.17.CONFIDENTIALITY. (A) Confidential Information. Subject to subsection (B) of this Section, each party will hold in confidence any Confidential Information received from the other party, except that this Section will not restrict either party from disclosing or granting access to such information to its professional advisers and consultants, to the extent necessary, to enable it to perform (or to cause to be performed) or to enforce its rights or obligations under this DBOM Agreement, and provided further that the DBOM Contractor may, subject to obtaining 178 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions confidentiality restrictions similar to those set forth in this DBOM Agreement provide to a Subcontractor and its advisors, or provide or cause to be provided to other third parties, Confidential Information which is necessary to enable the DBOM Contractor to perform (or to cause to be performed) its obligations under this DBOM Agreement. (B) Exceptions. The obligation to maintain the confidentiality of the Confidential Information does not apply to Confidential Information: (1) Which is or comes into the public domain otherwise than through any disclosure prohibited by this DBOM Agreement; (2) To the extent any person is required to disclose such Confidential Information by Applicable Law, including Oregon's Public Records and Meetings Law (ORS Chapter 192); (3) Any Governmental Body which requires the information in relation to the Project; or (4) That the City may be entitled to receive from the DBOM Contractor pursuant to this DBOM Agreement for the operation, maintenance or improvement of the Project in the event of, or following, termination of this DBOM Agreement. (C) Security Plan. If requested by the City, the DBOM Contractor shall prepare a security plan to assure that Confidential Information obtained from the City or as a consequence of the performance of the Project Services is not used for any unauthorized purpose or disclosed to unauthorized persons. The DBOM Contractor shall advise the City of any request for disclosure of information or of any actual or potential disclosure of information. (D) Public Communications of Confidential Information. Unless expressly provided in this DBOM Agreement or otherwise required by Applicable Law (but only to that extent), neither party will make or permit to be made any public announcement or disclosure whether for publication in the press, radio, television or any other medium of any Confidential Information, without the written consent of the other party (which will not be unreasonably withheld or delayed). The parties will comply with Appendix 20 (Public Communications). (E) Equitable Relief. Without prejudice to any other rights and remedies that the other party may have, each of the parties agrees that damages may not be an adequate remedy for a breach of subsection (A) of this Section, and that the other party will, in such case, be entitled to the remedies of injunction, specific performance or other equitable relief for any threatened or actual breach of subsection (A) of this Section. Section 26.18.COMPLIANCE WITH MATERIAL AGREEMENTS. The DBOM Contractor shall comply with its obligations under agreements of the DBOM Contractor which are material to the performance of its obligations under this DBOM Agreement. The City shall comply with its obligations under agreements of the City which are material to the performance of its obligations hereunder. Section 26.19.BINDING EFFECT. This DBOM Agreement shall inure to the benefit of and shall be binding upon the City and the DBOM Contractor and any assignee acquiring an interest hereunder consistent with Article 24 (Assignment and Change in Control). 179 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions Section 26.20.CONSENTS. Any consent required to be given under this DBOM Agreement shall be in writing. Section 26.21.NOTICES. (A) Procedure. All notices, consents, approvals or written communications given pursuant to the terms of this DBOM Agreement (other than Operation and Maintenance Notices as provided in subsection 26.12(B) (Operation and Maintenance Notices)) will be in writing and will be considered to have been sufficiently given if delivered by hand, by a reputable overnight courier or transmitted by electronic transmission to the address, or electronic mail address of each party set forth below in this Section, or to such other address, or electronic mail address as any party may, from time to time, designate in the manner set forth above. Any such notice or communication will be considered to have been received: (1) If delivered by hand or by a reputable overnight courier during business hours (and in any event, at or before 5:00 p.m. local time in the place of receipt) on a Business Day, upon receipt by a responsible representative of the receiver, and if not delivered during business hours, upon the commencement of business hours on the next Business Day; (2) If delivered by electronic mail during business hours (and in any event, at or before 5:00 p.m. local time in the place of receipt) on a Business Day, upon receipt, and if not delivered during business hours, upon the commencement of business hours on the next Business Day. (B) City Notice Address. Notices (other than Operation and Maintenance Notices) required to be given to the City shall be addressed as follows: City Manager City of Lake Oswego P.O. Box 369 Lake Oswego, OR 97034 Office Phone Number: 503-635-0215 Email: mbennett@lakeoswego.city with a copy to: City Attorney City of Lake Oswego P.O. Box 369 Lake Oswego, OR 97034 Office Phone Number: 503-635-0225 Email: cao@lakeoswego.city (C) DBOM Contractor Notice Address. Notices required to be given to the DBOM Contractor shall be addressed as follows: Jacobs Project Management Co. 2020 SW 4th Ave. 3rd Floor Portland OR, 97201 Attn: Michelle Green Telephone No.: 503-475-8748 Email: Michelle.Green@jacobs.com 180 3935946.13 043463 Lake Oswego Wastewater Treatment Facility Article 26 DBOM Agreement Miscellaneous Provisions with a copy to: Jacobs Project Management Co. 7251 E Bellview Ave. Denver, CO 80237 Attn: Hope Anastasakis, Assistant General Counsel Telephone No.: 720-286-0411 Email: Hope.Anastasakis@Jacobs.com Section 26.22.NOTICE OF LITIGATION. In the event the DBOM Contractor or City receives notice of or undertakes the defense or the prosecution of any Legal Proceedings, claims, or investigations in connection with the Project, the party receiving such notice or undertaking such defense or prosecution shall give the other party timely notice of such proceedings and shall inform the other party in advance of all hearings regarding such proceedings. For purposes of this Section only, "timely notice" shall be deemed given if the receiving party has a reasonable opportunity to provide objections or comments or to proffer to assume the defense or prosecution of the matter in question, given the deadlines for response established by the relevant rules of procedure. Section 26.23.FURTHER ASSURANCES. The parties will do, execute and deliver, or will cause to be done, executed and delivered, all such further acts, documents (including certificates, declarations, affidavits, reports and opinions) and things as the other may reasonably request for the purpose of giving effect to this DBOM Agreement or for the purpose of establishing compliance with the representations, warranties and obligations of this DBOM Agreement. [SIGNATURE PAGE FOLLOWS] 181 3935946.13 043463 Lake Oswego Wastewater Treatment Facility DBOM Agreement Signature Page IN WITNESS WHEREOF, the parties have caused this DBOM Agreement to be executed and delivered by their duly authorized representatives on the day and year first above written. JACOBS PROJECT MANAGEMENT CO. By: Name: Title: By: Name: Title: CITY OF LAKE OSWEGO, OREGON By: Name: Title: Approved as to form: By : Name: Title: 182 3935946.13 043463 Execution Version APPENDICES TO THE DBOM AGREEMENT FOR THE DESIGN, CONSTRUCTION, OPERATION AND MAINTENANCE OF THE LAKE OSWEGO WASTEWATER TREATMENT FACILITY between CITY OF LAKE OSWEGO, OREGON and JACOBS PROJECT MANAGEMENT CO. Dated [ ], 2026 3953578.11 043463 TABLE OF CONTENTS Page APPENDIX 1 SITE-RELATED INFORMATION 1-1 1. PROJECT SITE DESCRIPTION- DESIGN-BUILD PERIOD 1-1 2. PROJECT SITE DESCRIPTION- OPERATION AND MAINTENANCE PERIOD 1-1 ATTACHMENT 1A- DESCRIPTION OF PROJECT SITE ATTACHMENT 1B - PROJECT SITE PLAN APPENDIX 2 GOVERNMENTAL APPROVALS 2-1 1. PURPOSE 2-1 2. DESIGN-BUILD GOVERNMENTAL APPROVALS 2-1 3. OPERATIONS GOVERNMENTAL APPROVALS 2-1 ATTACHMENT 2A- EXPECTED DESIGN-BUILD GOVERNMENTAL APPROVALS ATTACHMENT 2B - EXPECTED OPERATIONS GOVERNMENTAL APPROVALS APPENDIX 3 CERTAIN FEDERAL REQUIREMENTS 3-1 1. MISCELLANEOUS REQUIREMENTS 3-1 1.1. Debarment and Suspension 3-1 1.2. Federal Lobbying Restrictions (31 U.S.C 1352). 3-1 1.3. Disadvantaged Business Enterprises (DBE) 3-1 2. NON-DISCRIMINATION AND LABOR REQUIREMENTS 3-1 2.1. Civil Rights Obligations 3-1 2.2. Equal Employment Opportunity (EEO). 3-2 2.3. Compliance with Davis-Bacon and Related Acts. 3-3 3. MATERIALS AND EQUIPMENT 3-11 3.1. American Iron and Steel (AIS) Requirement. 3-11 3.2. Build America, Buy America (Effective May 14, 2022). 3-12 3.3. Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment (Effective August 13, 2020). 3-12 ATTACHMENT 3A- DAVIS-BACON ACT WAGE DETERMINATIONS APPENDIX 4 DESIGN AND CONSTRUCTION REQUIREMENTS 4-1 1. GENERAL DESIGN OBJECTIVES 4-1 2. INFLUENT FLOWS AND LOADINGS 4-2 3. FACILITY CLASSIFICATION AND FLOOD ELEVATION REQUIREMENTS 4-2 4. EFFLUENT REQUIREMENTS 4-3 5. SLUDGE AND SCUM REQUIREMENTS 4-4 6. SECONDARY TREATMENT 4-6 7. DISINFECTION 4-6 8. ODOR CONTROL 4-6 9. ELECTRICAL SYSTEM 4-6 10. SITE REQUIREMENTS 4-6 11. APPLICABLE CODES, STANDARDS AND ORDINANCES 4-6 3953578.11 043463 APPENDIX 5 SECONDARY TECHNICAL CRITERIA 5-1 1. PRELIMINARY DESIGN 5-1 APPENDIX 6 DESIGN-BUILD WORK REVIEW PROCEDURES 6-1 1. PURPOSE 6-1 2. DOCUMENTS TO BE SUBMITTED 6-1 2.1. Design-Build Work Information 6-1 3. CITY DOCUMENT REVIEW 6-2 3.1. City Review Responsibilities. 6-2 3.2. Changes to Design and Construction Requirements. 6-3 3.3. Time for City Review. 6-3 3.4. Time for DBOM Contractor Response. 6-3 3.5. Pre-Design-Build Work/Partnering Conferences. 6-4 3.6. Design-Build Progress Meetings. 6-4 3.7. Design Submittals During Design-Build Work. 6-5 3.8. Design Change Authority. 6-5 4. CITY CONSTRUCTION INSPECTION 6-6 4.1. Design-Build Work Review Intent. 6-6 4.2. "Or Equals". 6-6 4.3. Functionally Equal. 6-6 4.4. Named Suppliers. 6-7 4.5. Corrections and Changes. 6-7 5. RECORD DRAWINGS 6-7 APPENDIX 7 GENERAL DESIGN-BUILD WORK REQUIREMENTS 7-1 1. PURPOSE 7-1 2. MANAGEMENT AND COORDINATION 7-1 3. PROJECT SCHEDULES 7-1 3.1. Project Schedule. 7-1 3.2. Detailed Network Diagram 7-2 3.3. Project Schedule Updates 7-3 3.4. City Review 7-3 3.5. Events Affecting the Project Schedule 7-4 4. CONSTRUCTION REPORTS AND RECORDS 7-4 4.1. Monthly Progress Reports. 7-4 4.2. Project Records 7-5 5. CONSTRUCTION WORK GENERALLY 7-6 5.1. Geotechnical Work and Subsurface Exploration. 7-6 5.2. Signs 7-6 5.3. Maintenance of the Project Site. 7-6 5.4. Temporary Utilities. 7-7 5.5. Relocation of Existing Utilities 7-7 5.6. Noise Control and Design-Build Work Hours. 7-7 5.7. Traffic Control Parameters. 7-7 6. COORDINATION OF CONSTRUCTION WORK AND OPERATIONS 7-7 7. CONSTRUCTION SAFETY AND SECURITY 7-7 7.1. Safety and Security 7-7 ii 3953578.11 043463 7.2. Design-Build Work Site Security. 7-9 8. ENVIRONMENTAL REVIEW AND PROTECTION 7-9 8.1. Wildlife and Protected Species Protection 7-9 8.2. DBOM Contractor Design-Build Work Environmental Monitor. 7-9 8.3. DBOM Contractor Hazardous Substances. 7-10 8.4. Emergency/Spill Response Plan 7-10 8.5. Dust Control 7-10 ATTACHMENT 7A- PROJECT SCHEDULE APPENDIX 8 COMMISSIONING AND ACCEPTANCE TESTING 8-1 1. PURPOSE 8-1 2. COMMISSIONING PLAN 8-1 3. ACCEPTANCE TEST PLAN 8-1 ATTACHMENT 8A- PRELIMINARY PROJECT COMMISSIONING PLAN ATTACHMENT 8B -PRELIMINARY ACCEPTANCE TEST PLAN APPENDIX 9 DESIGN-BUILD WORK SCHEDULE OF VALUES AND MAXIMUM DRAWDOWN SCHEDULE 9-1 1. PROGESS PAYMENT SCHEDULES 9-1 2. MAXIMUM DRAWDOWN SCHEDULE 9-1 ATTACHMENT 9A- DESIGN-BUILD PRICE SCHEDULE OF VALUES ATTACHMENT 9B - MAXIMUM DRAWDOWN SCHEDULE APPENDIX 10 OPERATION AND MAINTENANCE REQUIREMENTS 10-1 1. OVERVIEW 10-1 ATTACHMENT 10A-PRELIMINARY OPERATIONS AND MAINTENANCE PLAN ATTACHMENT 10B- MAJOR MAINTENANCE, REPAIR AND REPLACEMENT SCHEDULE APPENDIX 11 ODOR CONTROL STANDARD AND ODOR CONTROL PLAN 11-1 1. PROJECT ODOR CONTROL TEAM 11-1 2. MINIMUM PROACTIVE ODOR PREVENTION PLAN 11-1 2.1. Facility Monitoring and Mitigating Measures. 11-1 2.2. Construction Activity. 11-2 2.3. Coordination of Operational and Construction Activities. 11-2 2.4. Odor Control Report. 11-2 3. ODOR CONTROL STANDARD 11-2 3.1. Odor Control Standard. 11-2 3.2. Dispersion Modeling. 11-2 3.3. Odor Test Protocols 11-3 3.4. Odor Tests 11-3 4. RESPONSE PLAN 11-4 5. ODOR CONTROL PLAN 11-6 3953578.11 043463 APPENDIX 12 INSURANCE REQUIREMENTS 12-1 1. DEFINITIONS AND SECTION REFERENCES 12-1 1.1. Definitions 12-1 1.2. Section References 12-1 2. INSURANCE DURING THE DESIGN-BUILD PERIOD 12-1 2.1. Project-Specific Builder's Risk Property. 12-1 2.2. Professional Liability 12-2 2.3. Project-Specific Commercial General Liability. 12-3 2.4. Automobile Liability 12-3 2.5. Workers' Compensation. 12-4 2.6. Employers' Liability. 12-4 2.7. Contractors Pollution Liability 12-4 2.8. Aircraft Liability Insurance 12-4 2.9. Contractors Tools and Equipment. 12-5 2.10. Project-Specific Excess/Umbrella Liability 12-5 3. INSURANCE DURING THE OPERATION AND MAINTENANCE PERIOD 12-5 3.1. Property. 12-5 3.2. Equipment Breakdown. 12-6 3.3. Business Interruption Insurance 12-6 3.4. Commercial General Liability. 12-6 3.5. Automobile Liability 12-7 3.6. Workers' Compensation. 12-7 3.7. Employers' Liability. 12-7 3.8. Excess/Umbrella Liability. 12-8 3.9. Pollution Legal Liability (Fixed Site). 12-8 3.10. Contractor's Pollution Liability. 12-8 3.11. Directors and Officers. 12-8 3.12. Employee Dishonesty 12-9 3.13. Cyber & Network Liability. 12-9 3.14. Other. 12-9 4. FULL INSURABLE VALUE 12-9 5. GENERAL POLICY REQUIREMENTS 12-9 5.1. Policy Requirements. 12-9 5.2. Waivers of Subrogation. 12-10 5.3. City Acceptance of Insurance. 12-10 5.4. Subcontractors 12-10 5.5. Deductibles and Self-Insured Retentions. 12-10 5.6. Required Insurance Issued on a "Claims Made" Basis 12-11 6. EVIDENCE OF INSURANCE 12-11 7. SUFFICIENCY OF COVERAGE 12-11 ATTACHMENT 12A- OWNER CONTROLLED INSURANCE PROGRAM REQUIREMENTS APPENDIX 13 PERFORMANCE GUARANTEES AND DEDUCTIONS 13-1 1. PURPOSE 13-1 2. EFFLUENT GUARANTEE 13-1 3. DETERMINATION OF AN ODOR INCIDENT FOR PURPOSES OF THE ODOR GUARANTEE 13-3 4. RESIDUALS MANAGEMENT GUARANTEE 13-4 4.1. Grit and Screenings. 13-4 4.2. Sludge and Scum Requirements and Transport 13-4 iv 3953578.11 043463 4.3. Sludge and Scum Sampling. 13-4 4.4. Reporting. 13-5 5. LIQUIDATED DAMAGES 13-5 APPENDIX 14 EXAMPLE CALCULATION OF SERVICE FEE 14-1 1. PURPOSE 14-1 2. INDEX-LINKED 14-1 3. OPERATION AND MAINTENANCE CHARGE 14-3 4. REIMBURSABLE COSTS CHARGE 14-4 5. DEDUCTIONS CREDIT 14-5 6. EXTRAORDINARY ITEMS 14-5 APPENDIX 15 PROJECT FACILITIES EVALUATION PROTOCOL 15-1 1. DETERMINING THE WEIGHTED AVERAGE REMAINING LIFE OF THE PROJECT EQUIPMENT 15-1 1.1. Step 1: Develop Project Registry. 15-1 1.2. Step 2: Estimate Service Lives and Remaining Useful Lives of Project Equipment. 15-2 1.3. Step 3: Service Life Evaluation. 15-2 1.4. Step 4: Remaining Useful Life Evaluation. 15-3 1.5. Determining Weights to be Applied to Each Asset. 15-4 1.6. Determine Weighted Average Remaining Life of the Project Equipment. 15-5 2. PROJECT STRUCTURES EVALUATION PROCEDURES 15-6 2.1. Functionality Evaluation 15-6 2.2. Structural Integrity Evaluation 15-6 3. EVALUATION REPORTS AND PRODUCTS 15-7 3.1. Project Registry 15-7 3.2. Weighted Average Remaining Life. 15-7 3.3. Functionality and Structural Integrity. 15-8 3.4. Supplemental Information. 15-10 3.5. Recommended Revisions to Evaluation Practices and Procedures Report.... 15-10 4. UPDATES AND EXIT EVALUATIONS 15-10 APPENDIX 16 EXIT TESTING 16-1 1. OVERVIEW 16-1 2. EXIT TEST PLAN 16-1 3. EXIT TEST PROCEDURES 16-3 3.1. General. 16-3 3.2. Exit Test 16-3 3.3. Monitoring Requirements 16-3 4. EXIT TEST STANDARDS 16-4 5. FAILURE OF THE EXIT TEST 16-4 6. EXIT TEST REPORT 16-4 v 3953578.11 043463 APPENDIX 17 REFERENCE DOCUMENTS 17-1 1. REFERENCE DOCUMENTS 17-1 APPENDIX 18 REPORTS AND RECORDS 18-1 1. GENERAL REQUIREMENTS 18-1 1.1. Duty to Maintain Records. 18-1 1.2. Maintenance of Records. 18-1 1.3. Disposal of Records. 18-1 1.4. Drawing Requirements 18-1 2. RECORDS TO BE KEPT 18-2 APPENDIX 19 DBOM CONTRACTOR AND SUBCONTRACTORS INFORMATION 19-1 1. PURPOSE 19-1 2. DBOM CONTRACTOR INFORMATION 19-1 2.1. DBOM Contractor Information. 19-1 3. SUBCONTRACTORS 19-1 3.1. Subcontractors Generally. 19-1 3.2. Approved Subcontractors 19-1 4. KEY INDIVIDUALS 19-2 4.1. Key Individuals Generally 19-2 4.2. Key Individuals 19-2 ATTACHMENT 19A- KEY INDIVIDUALS RESUMES APPENDIX 20 PUBLIC COMMUNICATIONS 20-1 1. CITY RESPONSIBILITIES 20-1 1.1. Lead Communications Role 20-1 1.2. Design-Build Period-Specific Responsibilities. 20-1 1.3. Marketing Materials 20-2 2. DBOM CONTRACTOR RESPONSIBILITIES 20-2 2.1. Support Communications Role 20-2 2.2. Design-Build Period-Specific Responsibilities. 20-2 APPENDIX 21 DESIGN-BUILD QUALITY MANAGEMENT PLAN 21-1 1. DESIGN-BUILD QUALITY MANAGEMENT PLAN 21-1 2. APPROACH TO QUALITY MANAGEMENT 21-1 2.1. Design-Build Quality Manager 21-1 2.2. Design Discipline Leads 21-1 2.3. Construction QA/QC Manager 21-2 2.4. Independent Technical Reviewers 21-2 3. DESIGN QUALITY CONTROL 21-2 3.1. Design Quality Assurance 21-2 3.2. Design Review Milestones 21-2 vi 3953578.11 043463 4. PROCUREMENT QUALITY CONTROL 21-3 5. CONSTRUCTION QA/QC 21-3 5.1. Construction Quality Control 21-3 5.2. Construction Quality Assurance 21-3 6. INSPECTION AND TESTING 21-4 7. COMMISSIONING AND STARTUP QUALITY VERIFICATION 21-4 APPENDIX 22 EQUIPMENT AND MATERIALS SUBJECT TO COST ADJUSTMENT 22-1 1. PURPOSE 22-1 vii 3953578.11 043463 APPENDIX 1 SITE-RELATED INFORMATION 3953578.11 043463 APPENDIX 1 SITE-RELATED INFORMATION 1. PROJECT SITE DESCRIPTION- DESIGN-BUILD PERIOD The DBOM Contractor's Design-Build Project Site plan is described in Attachment lA (Design-Build Project Site Plan). Specific to the Design-Build Period, the Project Site shall consist of: (a) Tax Lot Number 21E02CB01800; (b) Tax Lot Number 21E02CB02101; (c) Tax Lot Number 21E02CB01500; (d) City right-of-way immediately west of Tax Lot Number 21E02CB02101 and north of Foothills Road; (e) Easements related to the City's influent sewer and major storm sewer on Tax Lot Numbers 21E02CB01700 and 21E02CB01501 and those easements related to Portland's influent sewers; provided that, the Design-Build Work is allowed pursuant to the provisions of the respective easement; (f) Portions of the TCWTP Site (subject to subsection 5.2(C) (Access to TCWTP Site) of the DBOM Agreement) identified in the DBOM Contractor's Design- Build Project Site Plan set forth in Attachment lA (Design-Build Project Site Plan); and (g) Laydown and staging areas for construction materials on portions of TCWTP Site (subject to subsection 5.2(C) (Access to TCWTP Site) of the DBOM Agreement) during the Design-Build Period. 2. PROJECT SITE DESCRIPTION- OPERATION AND MAINTENANCE PERIOD The DBOM Contractor's Operations and Maintenance Project Site plan is described in Attachment 1B (Operations and Maintenance Project Site Plan). Specific to the Operations and Maintenance Period, the Project Site shall consist of: (a) Tax Lot Number 21E02CB01800; (b) Tax Lot Number 21E02CB02101; (c) Tax Lot Number 21E02CB01500, as modified by proposed lot line adjustment generally illustrated in Attachment 1B (Operations and Maintenance Project Site Plan); (d) City right-of-way immediately west of Tax Lot Number 21E02CB02101 and north of Foothills Road; and (e) Additional areas identified in the DBOM Contractor's Operations and Maintenance Project Site Plan set forth in Attachment 1B (Operations and Maintenance Project Site Plan). Attachment 1B (Operations and Maintenance Al-1 3953578.11 043463 Replacement Wastewater Treatment Facility Appendix 1 Project Agreement Site-Related Information Project Site Plan) illustrates delineated points of responsibility between the DBOM Contractor, the City and Portland. [Remainder of Page Intentionally Left Blank] Al-2 3953578.8 043463 CTR 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 1 DBOM Agreement Site-Related Information ATTACHMENT 1A DESIGN-BUILD PROJECT SITE PLAN [ATTACHED] Al-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 1 DBOM Agreement Site-Related Information ATTACHMENT 1B OPERATIONS AND MAINTENANCE PROJECT SITE PLAN [ATTACHED] Al-4 3953578.11 043463 APPENDIX 2 GOVERNMENTAL APPROVALS 3953578.11 043463 APPENDIX 2 GOVERNMENTAL APPROVALS 1. PURPOSE The purpose of this Appendix is to provide a preliminary outline of the Governmental Approvals that are expected to be required for the DBOM Contractor's construction of the Project. The DBOM Contractor shall obtain and maintain all Governmental Approvals necessary to construct and operate the Project, irrespective of whether any such Governmental Approval is identified in this Appendix. 2. DESIGN-BUILD GOVERNMENTAL APPROVALS Attachment 2A (Expected Design-Build Governmental Approvals) sets forth the Design- Build Governmental Approvals that are expected to be required for the construction of the Project. Attachment 2A (Expected Design-Build Governmental Approvals) also sets forth the anticipated Design-Build Governmental Approval application submittal and assumed approval dates,which the DBOM Contractor may utilize to claim an Other Relief Event pursuant to Section 5.6(D) (Relief for Delays in the Issuance of Governmental Approvals Caused by Governmental Bodies) (which are based on an assumed Design-Build Work NTP Date of November 2, 2026). The DBOM Contractor will be responsible for complying with the terms and conditions contained in the applicable Design-Build Governmental Approvals. 3. OPERATIONS GOVERNMENTAL APPROVALS Attachment 2B (Expected Operations Governmental Approvals) sets forth the Operations Governmental Approvals that are expected to be required for the operations of the Project. The DBOM Contractor will be responsible for complying with the terms and conditions contained in the applicable Operations Governmental Approvals. [Remainder of Page Intentionally Left Blank] A2-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 2 DBOM Agreement Governmental Approvals ATTACHMENT 2A EXPECTED DESIGN-BUILD GOVERNMENTAL APPROVALS [ATTACHED] A2-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 2 DBOM Agreement Governmental Approvals ATTACHMENT 2B EXPECTED OPERATIONS GOVERNMENTAL APPROVALS Name of Issuing Permittee / Application Fee Payment Governmental Entity Approval Manager Responsibility Approval Holder Wastewater DEQ City DBOM DBOM NPDES Permit** Contractor Contractor 1200-Z DEQ City City City Industrial Stormwater Permit Operator DEQ DBOM DBOM DBOM Certification Contractor Contractor Contractor Vehicle Department of DBOM DBOM DBOM Operators Motor Contractor Contractor Contractor License Vehicles Updates to DEQ City DBOM DBOM plans and Contractor Contractor annual reports required by NPDES Permits, e.g., O&M Plan, Safety and Security Plan, Air Permit Annual Report, Collection DEQ City City City System Management Plan (CMOM) Permit(s) related DEQ (and City DBOM DBOM to Indirect others as Contractor Contractor Discharge to necessary) Surface Water, if required All others DBOM DBOM Contractor Contractor ** The DBOM Contractor is responsible for maintaining continuous compliance with the Wastewater NPDES Permit and preparing future Wastewater NPDES Permit renewal applications. A2-3 3953578.11 043463 APPENDIX 3 CERTAIN FEDERAL REQUIREMENTS 3953578.11 043463 APPENDIX 3 CERTAIN FEDERAL REQUIREMENTS 1. MISCELLANEOUS REQUIREMENTS 1.1. Debarment and Suspension. The DBOM Contractor certifies that it will not knowingly enter into a contract with anyone who is ineligible under the 2 CFR part 180 and part 1532 (per Executive Order 12549, 51 FR 6370, February 21, 1986) or who is prohibited under Section 306 of the Clean Air Act or Section 508 of the Clean Water Act to participate in the Design-Build Work. Suspension and debarment information can be accessed at http://www.sam.gov. The DBOM Contractor represents and warrants that it has or will include a term or conditions requiring compliance with this provision in all of its Subcontracts under this DBOM Agreement. 1.2. Federal Lobbying Restrictions (31 U.S.C 1352). Recipients of federal financial assistance may not pay any person for influencing or attempting to influence any officer or employee of a federal agency, a member of Congress, an officer or employee of Congress, or an employee of a member of Congress with respect to the award, continuation, renewal, amendment, or modification of a federal grant, loan, or contract. These requirements are implemented for USEPA in 40 CFR Part 34, which also describes types of activities, such as legislative liaison activities and professional and technical services, which are not subject to this prohibition. Upon award of this DBOM Agreement, the DBOM Contractor shall complete and submit to the City the certification and disclosure forms in Appendix A and Appendix B to 40 CFR Part 34. The DBOM Contractor shall also require all Subcontractors and suppliers of any tier awarded a Subcontract over$100,000 to similarly complete and submit the certification and disclosure forms pursuant to the process set forth in 40 CFR 34.110. 1.3. Disadvantaged Business Enterprises (DBE). The DBOM Contractor must ensure that the DBE's six good faith efforts are used during the procurement of Subcontractors for the Design-Build Work. The six good faith efforts are found at: https://www.epa.gov/grants/disadvantaged-business-enterprise-program- requirements#sixgoo dfaithefforts 2. NON-DISCRIMINATION AND LABOR REQUIREMENTS 2.1. Civil Rights Obligations. The DBOM Contractor shall comply with the following federal non-discrimination requirements: (a) Title VI of the Civil Rights Act of 1964, which prohibits discrimination based on race, color, and national origin, including limited English proficiency (LEP). (42 U.S.C 2000D, et. seq); (b) Section 504 of the Rehabilitation Act of 1973, which prohibits discrimination against persons with disabilities. (29 U.S.C. 794, supplemented by EO 11914, 41 FR 17871, April 29, 1976 and EO 11250, 30 FR 13003, October 13, 1965); (c) The Age Discrimination Act of 1975,which prohibits age discrimination. (42 U.S.C 6101 et. seq); A3-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (d) Section 13 of the Federal Water Pollution Control Act Amendments of 1972,which prohibits discrimination on the basis of sex; and (e) 40 CFR Part 7, as it relates to the foregoing. 2.2. Equal Employment Opportunity (EEO). During the performance of the Design-Build Work, the DBOM Contractor agrees as follows: (a) The DBOM Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The DBOM Contractor will ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The DBOM Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this non-discrimination clause. (b) The DBOM Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the DBOM Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin. (c) The DBOM Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with the DBOM Contractor's legal duty to furnish information. (d) The DBOM Contractor will send to each labor union or representative of workers with which it has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of the DBOM Contractor's commitments under this subsection, and shall post copies of the notice in conspicuous places available to employees and applicants for employment. (e) The DBOM Contractor will furnish all information and reports required by rules, regulations, and orders of the United States Secretary of Labor, or pursuant thereto, and will permit access to its books, records, and accounts by the City, the EPA and the United States Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders. A3-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (f) In the event of the DBOM Contractor's noncompliance with the nondiscrimination clauses of this DBOM Agreement or with any of the said rules, regulations, or orders, this DBOM Agreement may be canceled, terminated, or suspended in whole or in part and the DBOM Contractor may be declared ineligible for further government contracts or federally assisted construction contracts in accordance with procedures authorized under Applicable Law and such other sanctions may be imposed and remedies invoked as provided by rule, regulation, or order of the United States Secretary of Labor, or as otherwise provided by law. (g) The DBOM Contractor will include the portion of the sentence immediately preceding paragraph (a) and the provisions of paragraphs (a) through (f) of this subsection in every Subcontract or purchase order unless exempted by rules, regulations, or orders of the United States Secretary of Labor, so that such provisions will be binding upon each Subcontractor or vendor. The DBOM Contractor will take such action with respect to any Subcontract or purchase order as the City, EPA or United States Secretary of Labor may direct as a means of enforcing such provisions, including sanctions for noncompliance; provided, however, that in the event the DBOM Contractor becomes involved in, or is threatened with, litigation with a Subcontractor or vendor as a result of such direction, the DBOM Contractor may request the United States to enter into such litigation to protect the interests of the United States. 2.3. Compliance with Davis-Bacon and Related Acts. (a) In any contract in excess of $2,000 which is entered into for the actual construction, alteration and/or repair, including painting and decorating, of a public building or public work, or building or work financed in whole or in part from Federal funds or in accordance with guarantees of a Federal agency or financed from funds obtained by pledge of any contract of a Federal agency to make a loan, grant or annual contribution (except where a different meaning is expressly indicated), and which is subject to the labor standards provisions of any of the acts listed in 29 C.F.R. § 5.1, the following clauses (or any modifications thereof to meet the particular needs of the agency, provided that such modifications are first approved by the Department of Labor): (1) Minimum wages. (i) All laborers and mechanics employed or working upon the site of the Design-Build Work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the Project), will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto in Attachment 3A (Davis-Bacon Act Wage Determinations) and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the DBOM Contractor and such laborers and mechanics. Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject A3-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements to the provisions of paragraph (a)(1)(iv) of this Section; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, except as provided in § 5.5(a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein; provided that the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under paragraph (a)(1)(ii) of this Section) and the Davis-Bacon poster (WH-1321) shall be posted at all times by the DBOM Contractor and its Subcontractors at the site of the Design-Build Work in a prominent and accessible place where it can be easily seen by the workers. (ii) (A) The WIFIA assistance recipient, the City, on behalf of the EPA, shall require that any class of laborers or mechanics, including helpers, which is not listed in the wage determination and which is to be employed under this DBOM Agreement shall be classified in conformance with the wage determination. The WIFIA assistance recipient shall approve an additional classification and wage rate and fringe benefits therefore only when the following criteria have been met: 1. The work to be performed by the classification requested is not performed by a classification in the wage determination; and 2. The classification is utilized in the area by the construction industry; and 3. The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination. (B) If the DBOM Contractor and the laborers and mechanics to be employed in the classification (if known), or their representatives, and the WIFIA assistance recipient agree on the classification and wage rate (including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent to the Administrator of the Wage and Hour Division (WHD Administrator), U.S. Department of Labor, Washington, DC 20210. The WHD Administrator, or an authorized representative, will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise the WIFIA assistance recipient or will notify the WIFIA assistance recipient within the 30-day period that additional time is necessary. (C) In the event the DBOM Contractor, the laborers or mechanics to be employed in the classification or their representatives, and the WIFIA assistance recipient do not agree on the proposed A3-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements classification and wage rate (including the amount designated for fringe benefits, where appropriate), the WIFIA assistance recipient shall refer the questions, including the views of all interested parties and the recommendation of the WIFIA assistance recipient, to the WHD Administrator for determination. The WHD Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the WIFIA assistance recipient or will notify the WIFIA assistance recipient within the 30-day period that additional time is necessary. (D) The wage rate (including fringe benefits where appropriate) determined pursuant to paragraphs (a)(1)(ii) (B) or (C) of this Section, shall be paid to all workers performing work in the classification under this DBOM Agreement from the first day on which work is performed in the classification. (iii) Whenever the minimum wage rate prescribed in this DBOM Agreement for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the DBOM Contractor shall either pay the benefit as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash equivalent thereof. (iv) If the DBOM Contractor does not make payments to a trustee or other third person, the DBOM Contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program; provided, that the Secretary of Labor has found, upon the written request of the DBOM Contractor, that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the DBOM Contractor to set aside in a separate account assets for the meeting of obligations under the plan or program. (2) Withholding. The City, shall upon written request of the WIFIA Director or an authorized representative of the Department of Labor withhold or cause to be withheld from the DBOM Contractor under this DBOM Agreement or any other Federal contract with the same prime contractor, or any other federally- assisted contract subject to Davis-Bacon prevailing wage requirements,which is held by the same prime contractor, so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the DBOM Contractor or any Subcontractor the full amount of wages required by this DBOM Agreement. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of the Design-Build Work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the Project), all or part of the wages required by this DBOM Agreement, the WIFIA Director may, after written notice to the DBOM Contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased. A3-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (3) Payrolls and basic records. (i) Payrolls and basic records relating thereto shall be maintained by the DBOM Contractor during the course of the Design-Build Work and preserved for a period of three years thereafter for all laborers and mechanics working at the site of the Design-Build Work (or under the United States Housing Act of 1937, or under the Housing Act of 1949, in the construction or development of the Project). Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made and actual wages paid. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section 1(b)(2)(B) of the Davis-Bacon Act, the DBOM Contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs. (A) The DBOM Contractor shall submit weekly for each week in which any Design-Build Work is performed a copy of all payrolls to the City. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses shall not be included on weekly transmittals. Instead the payrolls shall only need to include an individually identifying number for each employee (e.g., the last four digits of the employee's social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH-347 is available for this purpose from the Wage and Hour Division Web site at https://www.dol.gov/agencies/whd/forms/wh347 or its successor site. The DBOM Contractor is responsible for the submission of copies of payrolls by all Subcontractors. The DBOM Contractor and Subcontractors shall maintain the full social security number and current address of each covered worker, and shall provide them upon request to the City, for transmission to the EPA, the DBOM Contractor, or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this Section for the DBOM Contractor to require a Subcontractor to provide addresses and social security numbers to the DBOM Contractor for its own records, without weekly submission to the City). A3-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (B) Each payroll submitted shall be accompanied by a "Statement of Compliance," signed by the DBOM Contractor or Subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify the following: 1. that the payroll for the payroll period contains the information required to be provided under§ 5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate information is being maintained under § 5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and complete; 2. that each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in Regulations, 29 CFR part 3; and 3. that each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract. (C) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH-347 shall satisfy the requirement for submission of the "Statement of Compliance" required by paragraph (a)(3)(ii)(B) of this Section. (D) The falsification of any of the above certifications may subject the DBOM Contractor or Subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 231 of title 31 of the United States Code. (ii) The DBOM Contractor or Subcontractor shall make the records required under paragraph (a)(3)(i) of this Section available for inspection, copying, or transcription by authorized representatives of the City, EPA, or the Department of Labor, and shall permit such representatives to interview employees during working hours on the job. If the DBOM Contractor or Subcontractor fails to submit the required records or to make them available, the EPA may, after written notice to the City, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12. A3-7 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (4) Apprentices and trainees. (i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer and Labor Services, or with a State Apprenticeship Agency recognized by the Office, or if a person is employed in his or her first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Office of Apprenticeship Training, Employer and Labor Services or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice. The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the DBOM Contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. Where a contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the DBOM Contractor's or Subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the WHD Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination. In the event the Office of Apprenticeship Training, Employer and Labor Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship program, the DBOM Contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved. (ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration. The ratio of trainees to A3-8 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements journeymen on the job site shall not be greater than permitted under the plan approved by the Employment and Training Administration. Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed on the wage determination unless the WHD Administrator determines that there is an apprenticeship program associated with the corresponding journeyman wage rate on the wage determination which provides for less than full fringe benefits for apprentices.Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Employment and Training Administration shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. In the event the Employment and Training Administration withdraws approval of a training program, the contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved. (iii) Equal employment opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR part 30. (5) Compliance with Copeland Act requirements. The DBOM Contractor shall comply with the requirements of 29 CFR part 3, which are incorporated by reference in this DBOM Agreement. (6) Subcontracts. The DBOM Contractor or Subcontractor shall insert in any Subcontracts the clauses contained in 29 CFR 5.5(a)(1) through (10) and such other clauses as the EPA may by appropriate instructions require, and also a clause requiring the Subcontractors to include these clauses in any lower tier Subcontracts. The DBOM Contractor shall be responsible for the compliance by any Subcontractor or lower Subcontractor with all the contract clauses in 29 CFR 5.5. (7) Contract termination; debarment. A breach of the contract clauses in 29 CFR 5.5 may be grounds for termination of this DBOM Agreement, and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12. (8) Compliance with Davis-Bacon and Related Act requirements. All rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 CFR parts 1, 3, and 5 are herein incorporated by reference in this DBOM Agreement. (9) Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this DBOM Agreement shall not be subject to the general disputes clause of this DBOM Agreement. Such disputes shall be A3-9 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements resolved in accordance with the procedures of the Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the DBOM Contractor (or any of its Subcontractors) and the City, EPA, the U.S. Department of Labor, or the employees or their representatives. (10) Certification of eligibility. (i) By entering into this DBOM Agreement, the DBOM Contractor certifies that neither it (nor he or she) nor any person or firm who has an interest in the DBOM Contractor's firm is a person or firm ineligible to be awarded government contracts by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (ii) No part of this DBOM Agreement shall be subcontracted to any person or firm ineligible for award of a government contract by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (iii) The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C.1001. (b) Contract Work Hours and Safety Standards Act. The following clauses set forth in paragraphs (b)(1), (2), (3), and (4) of this Section shall be inserted in full in any contract in an amount in excess of $100,000 and subject to the overtime provisions of the Contract Work Hours and Safety Standards Act. These clauses shall be inserted in addition to the clauses required by § 5.5(a) or § 4.6 of part 4 of this title. As used in this paragraph, the terms laborers and mechanics include watchmen and guards. (1) Overtime requirements. Neither the DBOM Contractor or any Subcontractor contracting for any part of the Design-Build Work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. (2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (b)(1) of this Section the DBOM Contractor and any Subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such DBOM Contractor and Subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (b)(1) of this Section, in the sum of$25 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (b)(1) of this Section. (3) Withholding for unpaid wages and liquidated damages. The City shall upon its own action or upon written request of an authorized representative of the Department of Labor, or the EPA, withhold or cause to be withheld, from any A3-10 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements moneys payable on account of work performed by the DBOM Contractor or Subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such DBOM Contractor or Subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (b)(2) of this Section. (4) Subcontracts. The DBOM Contractor or Subcontractor shall insert in any Subcontracts the clauses set forth in paragraph (b)(1) through (4) of this Section and also a clause requiring the Subcontractors to include these clauses in any lower tier Subcontracts. The prime contractor shall be responsible for compliance by any Subcontractor or lower tier Subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this Section. (c) In addition to the clauses contained in paragraph (b) of this Section, in any contract subject only to the Contract Work Hours and Safety Standards Act and not to any of the other statutes cited in § 5.1, the DBOM Contractor or Subcontractor shall maintain payrolls and basic payroll records during the course of the Design-Build Work and shall preserve them for a period of three years from the completion of the Design-Build Work for all laborers and mechanics, including guards and watchmen, working on the contract. Such records shall contain the name and address of each such employee, social security number, correct classifications, hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and actual wages paid. Further, the EPA shall cause or require the City to insert in any such contract a clause providing that the records to be maintained under this paragraph shall be made available by the DBOM Contractor or Subcontractor for inspection, copying, or transcription by authorized representatives of the City, EPA and the Department of Labor, and the DBOM Contractor or Subcontractor will permit such representatives to interview employees during working hours on the job. 3. MATERIALS AND EQUIPMENT 3.1. American Iron and Steel (AIS) Requirement. The DBOM Contractor acknowledges to and for the benefit of City and the EPA that it understands the goods and services under this DBOM Agreement are being funded with monies made available by the Water Infrastructure Finance and Innovation Act program of the EPA that has statutory requirements commonly known as "American Iron and Steel" that requires all of the iron and steel products used in the Project to be produced in the United States ("American Iron and Steel Requirement")including iron and steel products provided by the DBOM Contractor pursuant to this DBOM Agreement. The DBOM Contractor hereby represents, warrants and covenants to and for the benefit of the City and the EPA that (a) the DBOM Contractor has reviewed and understands the American Iron and Steel Requirement, (b) all of the iron and steel products used in the Project will be and/or have been produced in the United States in a manner that complies with the American Iron and Steel Requirement, unless a waiver of the requirement is approved, and (c) the DBOM Contractor will provide any further verified information, certification or assurance of compliance with this Section, or information necessary to support a waiver of the American Iron and Steel Requirement, as may be requested by the City or the EPA. Notwithstanding any other provision of this DBOM Agreement, any failure to comply with this Section by the DBOM Contractor shall permit the City or the EPA to recover as damages against the DBOM Contractor any loss, expense, or cost (including without limitation attorney's fees) incurred by the City or the EPA resulting from any such failure (including without limitation A3-11 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements any impairment or loss of funding, whether in whole or in part, from the EPA or any damages owed to the EPA by the City). While the DBOM Contractor has no direct contractual privity with the EPA, as a lender to the City for the funding of its Project, the City and the DBOM Contractor agree that the EPA is a third-party beneficiary and neither this Section (nor any other provision of this DBOM Agreement necessary to give this paragraph force or effect) shall be amended or waived without the prior written consent of the EPA. 3.2. Build America, Buy America (Effective May 14, 2022). The DBOM Contractor acknowledges to and for the benefit of City and the EPA that it understands the goods and services under this DBOM Agreement are being funded with federal monies made available by the Water Infrastructure Finance and Innovation Act program of EPA that have statutory requirements commonly known as "Build America, Buy America;" that requires all of the iron and steel, manufactured products, and construction materials used in the project to be produced in the United States ("Build America, Buy America Requirements") including iron and steel, manufactured products, and construction materials provided by the DBOM Contractor pursuant to this DBOM Agreement. The DBOM Contractor further acknowledges that the City has confirmed that the Project has received approval for the WIFIA program's waiver of Build America, Buy America Requirements for WIFIA-financed projects that have initiated design planning prior to May 14, 2022 (the "BABAA Waiver"). The DBOM Contractor hereby represents and warrants to and for the benefit of the City and the EPA (a) the DBOM Contractor has reviewed and understands the Build America, Buy America Requirements, (b) if the BABAA Waiver is revoked, then all of the iron and steel, manufactured products, and construction materials used in the Project will be and/or have been produced in the United States in a manner that complies with the Build America, Buy America Requirements, and such BABAA Waiver revocation will constitute an Other Relief Event and the DBOM Contractor shall be entitled to relief as and to the extent provided in Article 14 (Relief Event Procedures), and (c) the DBOM Contractor will provide any further verified information, certification or assurance of compliance with this Section, or information necessary to support the BABAA Waiver, as may be requested by the City or the EPA. Notwithstanding any other provision of this DBOM Agreement, any failure to comply with this Section by the DBOM Contractor shall permit the City or the EPA to recover as damages against the DBOM Contractor any loss, expense, or cost(including without limitation attorney's fees) incurred by the City or the EPA resulting from any such failure (including without limitation any impairment or loss of funding, whether in whole or in part, from the EPA or any damages owed to the EPA by the City). If the DBOM Contractor has no direct contractual privity with the EPA, as a lender or awardee to the City for the funding of its Project, the City and the DBOM Contractor agree that the EPA is a third-party beneficiary and neither this Section (nor any other provision of this DBOM Agreement necessary to give this Section force or effect) shall be amended or waived without the prior written consent of the EPA. 3.3. Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment (Effective August 13, 2020). The John S. McCain National Defense Authorization Act for Fiscal Year 2019 (P.L. 115- 232), at Section 889 (the "Act"), prohibits EPA financial assistance recipients, including WIFIA borrowers, from expending loan funds to procure or obtain; extend or renew a contract to procure or obtain; or enter into a contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. As described in the Act, "covered telecommunications equipment or services" means: (a) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities). A3-12 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 3 DBOM Agreement Certain Federal Requirements (b) For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities). (c) Telecommunications or video surveillance services provided by such entities or using such equipment. (d) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country. The Act does not prohibit: (a) Procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements. (b) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles. [Remainder of Page Intentionally Left Blank] A3-13 3953578.11 043463 Replacement Wastewater Treatment Facility Appendix 3 Project Agreement Certain Federal Requirements ATTACHMENT 3A DAVIS-BACON ACT WAGE DETERMINATIONS [ATTACHED] A3-14 3953578.11 043463 APPENDIX 4 DESIGN AND CONSTRUCTION REQUIREMENTS 3953578.11 043463 APPENDIX 4 DESIGN AND CONSTRUCTION REQUIREMENTS This Appendix consists of general design objectives, as set forth in Section 1 (General Design Objectives) and the Design and Construction Requirements, as set forth in Sections 2 (Influent Flows and Loadings) through 11 (Applicable Codes, Standards and Ordinances). 1. GENERAL DESIGN OBJECTIVES The Facility shall be designed in compliance with the following minimum objectives: (a) Minimization of the site footprint. (b) Operational reliability under all design flow and loading ranges. (c) Operational efficiency under all design flow and loading ranges. (d) Utilization of gravity flow whenever possible. (e) Uncomplicated and efficient maintenance and repair approach, and minimization of the frequency of maintenance. (f) Ease, efficiency and safety of operations, maintenance, repair, and replacement activities (e.g., efficient and safe access to equipment). (g) Highly effective and proven odor control system(s), as described in Appendix 5 (Secondary Technical Criteria), that minimize odor-related complaints from adjacent populations. (h) Noise mitigation measures in accordance with contract requirements. (i) Consideration of coverings or other visual screening approaches for the facility structure, treatment process tanks, equipment, etc. This specifically includes the screening of open water basins visible from current and reasonably anticipated future viewing angles by way of canopies, covers, grating systems, or similar screening feature. Preference should be given to cost effective solutions that facilitate operations and maintenance. (j) Sustainable construction and operation and maintenance approaches. (k) Architectural, stormwater, and landscaping treatments compatible with the neighborhood, and complementary to the functional needs of providing wastewater treatment. (1) Use of materials that are intended to achieve a 50-year physical service life, based on industry standard practices for major components such as buildings, structures, and pipelines. A4-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements 2. INFLUENT FLOWS AND LOADINGS The Facility shall be designed to treat the following influent flows and loadings: Table 4-1 Flows and Loads FLOW (Million Gallons Per Day or MGD) Average Dry Weather Flow (May 1 to October 31) 6.2 Max Month Dry Weather Flow 10.2 Max Week Dry Weather Flow 13.6 Max Day Dry Weather Flow 18.7 Average Wet Weather Flow (November 1 to April 30) 9.3 Max Month Wet Weather Flow 14.7 Max Week Wet Weather Flow 22 Max Day Wet Weather Flow 39.2 Peak Instantaneous Flow 53.1 BOD LOAD (Pounds Per Day or PPD) Average Dry Weather (May 1 to October 31) 14,100 Max Month Dry Weather 19,400 Max Week Dry Weather 26,000 Max Day Dry Weather 46,400 Average Wet Weather (November 1 to April 30) 15,900 Max Month Wet Weather 24,700 Max Week Wet Weather 35,000 Max Day Wet Weather 62,000 TSS LOAD (PPD) Average Dry Weather (May 1 to October 31) 15,300 Max Month Dry Weather 25,300 Max Week Dry Weather 44,400 Max Day Dry Weather 56,900 Average Wet Weather (November 1 to April 30) 17,700 Max Month Wet Weather 30,300 Max Week Wet Weather 44,300 Max Day Wet Weather 61,800 AMMONIA LOAD (PPD) Average Annual 1,900 Max Month 2,300 TKN LOAD (PPD) Average Annual 3,100 Max Month 3,700 TP LOAD (PPD) Average Annual 400 Max Month 500 3. FACILITY CLASSIFICATION AND FLOOD ELEVATION REQUIREMENTS (a) The Facility shall be a Class I facility and is subject to associated constraints and requirements as defined in the Design Criteria for Mechanical, Electric, and Fluid System and Component Reliability, U.S. Environmental Protection Agency, 1973. A4-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements (b) All structures and equipment are required to be above the 100-year flood elevation or in compliance with LOC 50.05.011, whichever is most restrictive, with the exceptions noted below: (i) Pump station ground level finished floor and top of submersible wet wells shall be designed in accordance with Oregon DEQ pump station design standards. (ii) All electrical plant systems, other than ballasts for the UV system, will be located above the 500-year flood plain. 4. EFFLUENT REQUIREMENTS Until the NPDES Permit is finalized, the Effluent requirements will remain uncertain. The anticipated limits listed in Table 4-2 and Table 4-3 below are based on the Tryon Creek Facilities Plan, discussions with Oregon DEQ, work with other dischargers on the lower Willamette River and Table 4-1. The Effluent requirements and sampling frequencies provided in Table 4-2 and Table 4-3 below shall serve as the basis of design for the DBOM Contractor until final permit requirements are established or the City changes such requirements based upon Oregon DEQ guidance. The DBOM Contractor, however, shall be responsible for all customary terms and conditions that are typically included in NPDES permits but are not described in this Section including items such as (1) receiving stream monitoring for the Willamette River, (2) copper biotic ligand model and aluminum parameters, and (3) quarterly Effluent toxics characterizations and whole Effluent toxicity testing requirements. Upon issuance of the final NPDES Permit, this DBOM Agreement shall be amended to incorporate any NPDES Permit conditions that are more stringent than what is set forth in this Appendix. If any NPDES Permit condition is less stringent than what is set forth in this Appendix, the City may, in its discretion, either (a) agree to amend this DBOM Agreement to incorporate such less stringent requirement in exchange for a reduced Service Fee or other benefit to the City or (b) require the DBOM Contractor to continue to comply with the conditions set forth in this Appendix. Table 4-2 Effluent Requirements - Dry Weather Season (May 1 - October 31) Performance value Sample type Average Effluent Daily concentrations (mg/L) Monthly Weekly max average average (lb/day Parameter Monthly Weekly (lb/day) (lb/day) Biochemical oxygen ≤10 ≤15 ≤850 ≤1,300 ≤1,700 24-hr demand (BOD5) composite Total suspended ≤10 ≤15 ≤850 ≤1,300 ≤1,700 24-hr solids (TSS) composite Ammonia** ≤ 1 24-hr composite Total 0.3 mg/L 24-hr Phosphorous** composite A4-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements E coli bacteria Shall not exceed 126 organisms per 100 mL Grab monthly geometric mean. No single sample shall exceed 406 organisms per 100 ml. pH Shall be within the range of 6.0-9.0 Grab Excess Thermal N/A 7-day Load (June 1 - rolling September 3) (See average note 1 below) BOD5 and TSS Shall not be less than 85 percent monthly average Calculation Removal Efficiency for BOD5 and 85 percent monthly average for TSS Chlorine Residual No residuals allowed N/A **The DBOM Contractor shall not be required to meet the total phosphorous or ammonia requirements set forth in this DBOM Agreement during the Operation and Maintenance Period unless the City directs the DBOM Contractor to do so pursuant to a Capital Modification in accordance with Article 11 (Capital Modifications and Operation and Maintenance Services Changes). Furthermore,the Acceptance Standards and Acceptance Testing shall not impose any requirements on the DBOM Contractor with respect to phosphorous and ammonia unless such Capital Modifications are implemented. Note 1. While NPDES Permit requirements anticipate inclusion of an Excess Thermal Load Limit, DBOM Contractor is responsible only for monitoring and not compliance. The City maintains responsibility to incorporate future Capital Modifications for NPDES Permit compliance regarding Thermal Load. Table 4-3 Effluent Requirements —Wet Weather Season (November 1 —April 30) Sample Performance value type Average Effluent Monthly Weekly Daily concentrations (mg/L) average average max Parameter Monthly Weekly (lb/day) (lb/day) (lb/day) Biochemical oxygen ≤30 ≤45 ≤3,700 ≤5,500 ≤7,400 24-hr demand (BOD5) composite Total suspended ≤30 ≤45 ≤3,700 ≤5,500 ≤7,400 24-hr solids (TSS) composite E coli bacteria Shall not exceed 126 organisms per 100 mL monthly Grab geometric mean. No single sample shall exceed 406 organisms per 100 ml. pH Shall be within the range of 6.0-9.0 Grab BOD5 and TSS Shall not be less than 85 percent monthly average for Calculation Removal Efficiency BOD5 and 85 percent monthly average for TSS Chlorine Residuals No chlorine residuals allowed N/A 5. SLUDGE AND SCUM REQUIREMENTS Portland's Columbia Boulevard Wastewater Treatment Facility ("CBWTF") will accept Sludge and Scum that is delivered and meets the characteristics as described in the following sections: A4-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements (a) Sludge and Scum Delivery Requirements. The CBWTF will accept Sludge and Scum 24 hours a day, 7 days a week from tankers that are no larger than 6,500 gallons, at a frequency of no greater than two trucks per hour. The following requirements, characteristics and protocols shall apply to the DBOM Contractor's access to and off-loading of Sludge and Scum at the CBWTF and its Sludge and Scum receiving facilities: • Access to the CBWTF shall be in accordance with Portland's security protocol. Access will be obtained via a staffed security booth or access card. • Access to the CBWTF and the Sludge and Scum offloading station will be impeded by the train or queued trucks also offloading hauled waste no more than 50 hours annually. The DBOM Contractor will document instances and duration of delay in daily O&M reports and summarize monthly and annually. Where the annual delay exceeds 50 hours during a calendar year, the City will reimburse DBOM Contractor on a time and materials basis for additional hauling costs, subject to Cost Substantiation, incurred beyond the initial 50 hours. No additional compensation shall be provided by the City for costs incurred during the initial 50 hours of any calendar year. • Portland will provide written direction to the DBOM Contractor, specific to routing of Sludge and Scum trucks through the CBWTF site. It is understood this may change time-to-time at Portland's discretion. Portland will provide written notice of any change to the City a minimum of one week in advance of change, except as required due to emergency issues, and the City will immediately advise the DBOM Contractor. • The Sludge and Scum receiving station includes a 350-gpm pump that will be used to empty the Sludge and Scum tanker at the CBWTF's Organic Waste Receiving Facility. Portland may require offloading at the Digester Booster Pumping Station via gravity. • Automated control system interface (e.g., card reader system) at the Sludge and Scum receiving station will allow the Sludge and Scum hauler to connect to infrastructure and initiate offloading. Interface with Portland BES staff will not be required. • The DBOM Contractor will have access to washdown and drain facilities at the point of offloading. The DBOM Contractor will leave the facility in clean, working order after offloading. (b) Sludge and Scum Characteristics. The Sludge and Scum will need to meet the criteria listed in Table 4-4 below to be accepted at the CBWTF. As regulations change, monitoring requirements will be updated to address future regulatory limits. Table 4-4 Acceptable Sludge Characteristics Parameter Test Method Acceptable Range pH EPA 9045 6-8 Total physical inerts TMECC 030 <0.5% dry weight Total solids* SM 2540 G-(1997) 2% - 7% A4-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements Ammonia (NH3-N) SM 4500-NH3 G- <600 mg/L (1997) * In the event of an unanticipated equipment failure or malfunction at the LOWWTF that is not the result of DBOM Contractor Fault and with notification by the DBOM Contractor to both the City and Portland, Sludge and Scum with a total solids concentration of less than 2% will be accepted at the CBWTF with Portland's approval, which shall not unreasonably withheld. 6. SECONDARY TREATMENT The Facility shall be designed to provide full secondary treatment for flows up to 32.9 MGD. 7. DISINFECTION Chlorine and/or chlorine compounds shall not be used for effluent disinfection purposes. Chlorine residual in effluent from chlorine as a result of maintenance or other purposes is also prohibited. 8. ODOR CONTROL The Facility shall be designed, constructed, operated and maintained so that odors from the Facility shall not exceed 5 dilutions-to-threshold (D/T) at the Project Site's property line as determined by dispersion modeling (AERMOD) on highest one-hour average. 9. ELECTRICAL SYSTEM Main electrical equipment shall be main-tie-tie-main configuration. 10. SITE REQUIREMENTS The DBOM Contractor shall provide a design of less than or equal to 0 cubic yards of net fill in the floodplain. The City has made available to the DBOM Contractor 12,450 cubic yards of cut (negative fill) credit from the 2004 construction of Foothills Park when calculating a balanced cut/fill excavation design for the Project. 11. APPLICABLE CODES, STANDARDS AND ORDINANCES Unless otherwise indicated in this or other Appendices, the DBOM Contractor shall perform the Design-Build Work in accordance with the most recent editions of all applicable codes, standards, and ordinances, including, but not limited to, the following. • American Association of State Highway and Transportation Officials (AASHTO) • American Concrete Institute (ACI) o American Concrete Institute, Code Requirements for Environmental Concrete Structures (ACI 350) • American Institute of Steel Construction (AISC) • American Iron and Steel Institute (AISI) • American National Standards Institute (ANSI) • American Society of Civil Engineers (ASCE) A4-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 4 DBOM Agreement Design and Construction Requirements o American Society of Civil Engineers (ASCE) 7 Document • American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE) • American Society of Mechanical Engineers (ASME) • American Society for Testing and Materials (ASTM) • American Water Works Association (AWWA) • American Welding Society (AWS) • Americans with Disabilities Act (ADA) • City of Lake Oswego Building Code • City of Lake Oswego Development Code (including approved variances) • Hydraulic Institute • International Building Code (IBC) • International Organization for Standardization (ISO) • National Electrical Code (NEC) • National Fire Protection Association (NFPA) o National Fire Protection Association, Fire Protection in Wastewater Treatment and Collection Facilities (NFPA 820) • Oregon Administrative Rules 340, Division 41, Water Quality Standards: Beneficial uses, policies, and criteria for Oregon • Occupational Safety and Health Administration (OSHA) • Oregon State Building Code (OBC) • Oregon Structural Specialty Code (OSSC) • Precast Concrete Institute • Underwriters' Laboratories, Inc. (UL) • Water Environment Federation (WEF) Manual of Practice No. 8 (MOP 8) Unless otherwise indicated in this or other Appendices, the DBOM Contractor shall consider guidance documents, recommended practices, industry references, or publications along with sound engineering judgement in performance of the Design-Build Work. Applicable codes, standards and ordinances will be documented in the 30% design deliverable. After completion of the 30% design deliverable, the DBOM Contractor shall prepare and submit a Design and Construction Requirements Change Notice to define the limited list of codes and standards applicable to the Project. [Remainder of Page Intentionally Left Blank] A4-7 3953578.11 043463 APPENDIX 5 SECONDARY TECHNICAL CRITERIA 3953578.11 043463 APPENDIX 5 SECONDARY TECHNICAL CRITERIA The Facility shall be designed in compliance with the following Secondary Technical Criteria: 1. PRELIMINARY DESIGN The DBOM Contractor's preliminary Design Documents are set forth below in this Appendix. [ATTACHED] A5-1 3953578.11 043463 APPENDIX 6 DESIGN-BUILD WORK REVIEW PROCEDURES 3953578.11 043463 APPENDIX 6 DESIGN-BUILD WORK REVIEW PROCEDURES 1. PURPOSE The purpose of this Appendix is to set forth the procedures for the City's review of each aspect of the Design-Build Work to verify that the Project has been designed and constructed in accordance with this DBOM Agreement. 2. DOCUMENTS TO BE SUBMITTED At a minimum, the documents to be submitted during the Design-Build Period shall include the following: (a) Monthly Project Schedule updates (b) Intermediate design submittals as indicated in the Deliverables section of the Project Schedule for review sessions and workshops on various materials, facilities, systems, equipment, and disciplines (c) Final Design Documents (issued for construction) (d) Test reports (e) Operation and Maintenance Manual (f) Applications and supporting documents required for any remaining Governmental Approvals (g) Record drawings and specifications 2.1. Design-Build Work Information. The DBOM Contractor shall have flexibility with how it organizes and performs the Design-Build Work so that it can proceed with ordering any necessary materials and prior to finalizing the design; provided, however, such construction or ordering of materials and equipment prior to the final design shall not negatively affect the remaining Design-Build Work, the Design-Build Price, the Service Fee or the Project Schedule. The DBOM Contractor shall provide the following information: (a) Specifications, Design Narratives and Lists: (1) Project design criteria (2) Specifications list (3) Piping list (4) Valve list, if applicable (5) Narrative documenting chlorine use for maintenance A6-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures (6) Cathodic protection narrative, if applicable (7) Design-Build Work sequencing and dewatering narrative (8) Specifications (general requirements, civil, structural, specialties and mechanical sections) (b) Drawings prepared and accepted for the 90% submittal shall continue to be progressed to final design completion and shall be submitted, in both electronic and standard design formats: (1) Cover sheet (2) Drawing index (3) List of abbreviations (4) Legends (5) Layouts of the Project Site and piping (6) Design-Build Work staging and phasing plans (7) Access and traffic control plans (8) Landscape plans, surface restoration and irrigation plans and details (9) Project Site grading and utility plans, with sections as needed for Design- Build Work clarity or dimensioning (10) Surface drainage plans and details (11) Details of connections to existing City of Lake Oswego influent piping and City of Portland influent and effluent piping (12) Sections through all major crossings and structures (13) Other systems plans, details and schedules, if applicable (14) Pipeline plan and profile sheets (15) Pipeline sections and details (16) Tunnel and access pit plans, sections and details (17) Dewatering plans and details 3. CITY DOCUMENT REVIEW 3.1. City Review Responsibilities. The City shall review documents included in the DBOM Contractor's final Design Documents for compliance and consistency with the design in the Design and Construction Requirements and for overall compliance with the requirements of this DBOM Agreement. The A6-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures City's input during finalization of the Design Documents shall be solicited by the DBOM Contractor on a timely basis so as to provide adequate periods for review by the City, revisions by the DBOM Contractor and final review by the City without negatively impacting the Project Schedule; however, in no case, unless otherwise reasonably agreed to by the parties, shall the City's review timeframe exceed seven Business Days. The City shall make reasonable efforts to bring staff or representatives with review and decision-making authority to the work sessions as requested and scheduled by the DBOM Contractor. The DBOM Contractor shall provide the City with advance notice of the work sessions and agenda topics to facilitate the City's scheduling of the appropriate participants for the work sessions. Design-Build Work activities shall not vary from the final Design Documents submitted to the City except where such variations are allowed, subject to the City's and applicable Governmental Body's review and approval. 3.2. Changes to Design and Construction Requirements. Other than as set forth in this DBOM Agreement, any change requested by the DBOM Contractor to the Design and Construction Requirements (regardless of prior oral discussion) must be clearly identified by the DBOM Contractor in its cover letter that transmits the submittal and must be fully documented with compelling justification of the DBOM Contractor's request for a change to the Design and Construction Requirements and describe any benefits to the City for consenting to such a change. Any such change shall comply with the requirements set forth in Article 5 (Design and Construction) of this DBOM Agreement, as applicable. No change to the Design and Construction Requirements shall be made except with the City's approval pursuant to the terms of this DBOM Agreement. The DBOM Contractor shall assume all risks associated with obtaining City approval of any change to the Design and Construction Requirements. 3.3. Time for City Review. City review time for submittals shall normally be seven Business Days from when the City receives a complete submittal; provided, however, that the City may, upon notice to the DBOM Contractor, extend such review for up to an additional 8 Business Days if necessary in light of the nature of the submittal; provided, however the City's review time shall not begin until the DBOM Contractor provides a complete submittal. Partially complete submittals will not be subject to any review timeline until complete unless otherwise approved in writing by the City. If the City deems a submittal incomplete, the City shall notify the DBOM Contractor within 5 Business Days as to why such submittal is not complete. The DBOM Contractor and the City shall periodically review key submittals and the target submittal dates, and develop a submittal review schedule for each submittal based on the content and criticality of each submittal. The City shall complete its review of each submittal in a timely manner based on such target submittal dates in order to determine that the Design- Build Work conforms to the Design and Construction Requirements and other Contract Standards. Nothing in this Section shall prevent the City from conducting a subsequent review raising a question as to whether the submittal was in compliance with the Contract Standards. The review and comment rights of the City under this Appendix are intended for the City to determine whether the Design Documents comply with the Design and Construction Requirements and other Contract Standards. The City's approval of any Design-Document shall not be required in order for the DBOM Contractor to proceed with the performance of the Design- Build Work. 3.4. Time for DBOM Contractor Response. For each submittal, the City shall provide written comments in a tabular summation describing any concerns, problems, or assertions of non-compliance with the applicable Contract Standards. The tabular summation shall be on a form created mutually by the DBOM Contractor A6-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures and the City, with provisions on the form for the DBOM Contractor's responses. The DBOM Contractor shall provide a written response to the City's comments within 15 days of receipt of the City's comments, primarily through use of the tabular summary form, including documentation of responses and agreed-upon action items. 3.5. Pre-Design-Build Work/Partnering Conferences. The DBOM Contractor shall hold a pre-Design-Build Work conference prior to commencement of the Design-Build Work. The DBOM Contractor shall prepare an agenda which shall be reviewed with the City prior to the conference, and shall preside at the conference, contribute appropriate items for discussion, provide any data requested, record minutes to summarize significant proceedings and decisions, and distribute the minutes to all parties in attendance. The pre-Design-Build Work conference shall be scheduled by the DBOM Contractor at a time reasonably acceptable to the City and shall be attended by the Project Manager and the Design-Build Project Manager. Other attendees will be added at the discretion of the DBOM Contractor and the City. 3.6. Design-Build Progress Meetings. For the purpose of facilitating a timely review process, the DBOM Contractor shall schedule design-build progress meetings with the City on a routine basis and at least bi-weekly (unless both parties agree that more or less frequent meetings are required) throughout the design finalization period. Any outstanding review comments not satisfactorily resolved shall be transferred to an issues tracking form by the DBOM Contractor for subsequent follow-up. The primary purpose of these meetings shall be to discuss overall DBOM Contractor work progress, and to address outstanding issues arising from the review and response process. The status and issues of related permitting and early Design-Build Work activities may also be included as agenda items for each design-build progress meeting. These meetings shall be held either virtually or at a location agreed to by the City. DBOM Contractor representatives with responsibility for design and Design-Build Work shall participate in the meeting. Similarly, the City shall be appropriately represented by individuals with knowledge and authority for decision making at the meeting. The DBOM Contractor shall prepare an agenda, preside at meetings, record minutes to include significant proceedings and decisions, and distribute the minutes to all parties in attendance within three Business Days of the meeting. The agenda shall generally include the status of the following matters, as applicable: (a) Summary of previous meeting issues, actions and assignments. (c) Progress since last meeting (DBOM Contractor and Subcontractors). (d) Schedules, including updates on planned progress for next four weeks, off-site fabrication and delivery schedules; corrective action measures, if required and when to be implemented. (e) Problems, issues and considerations. (f) Change Orders, Contract Administration Memoranda and DBOM Agreement Amendments. A6-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures (g) Status of submittals, including to be submitted, submitted, responses requiring corrective actions and resubmittal and approved. (h) Requests for information, including those to be submitted, submitted, responses and whether adequate or more information is required. (i) QA/QC reviews, findings, issues and actions. 6) Coordination among parties. (k) Safety program update, concerns, accidents, and injuries, if any. (1) Public affairs and issues or concerns of nearby businesses and other stakeholders. (m) Project Site visits by the City, the City's representatives, representatives of Governmental Bodies, issuers of non-Governmental Approvals and DBOM Contractor's representatives. (n) Compliance with Governmental Approval mitigations and any environmental issues. (o) Status of record drawings and specifications. 3.7. Design Submittals During Design-Build Work. It is anticipated that there could be some redesign or design clarifications needed during the Design-Build Work. Additional design work by the DBOM Contractor shall be subject to the City's review for compliance and consistency with applicable Design and Construction Requirements and Contract Standards. Design changes to a particular Design Document performed following the issuance of the Design Document for Design-Build Work shall be issued under a Design Change Notice ("DCN") process that accurately tracks and documents changes to the design. No later than 15 Business Days prior to initiation of Design-Build Work, the DBOM Contractor shall submit to the City any DCNs. The City shall be provided with copies of all DCNs in a timely manner to allow review, comment, and, where appropriate, approval in the same manner as set forth with respect to the initial design. Design clarifications shall be issued in a timely manner using a similar procedure. If a DCN requires a material change from what was reflected in the applications for Governmental Approvals, the DCN must be approved by the appropriate Governmental Body if required by Applicable Law. 3.8. Design Change Authority. The DBOM Contractor shall be responsible for providing design changes to the Design Documents necessary to complete the Project in accordance with this DBOM Agreement. All such changes shall be implemented in accordance with the DCN process described above, and in accordance with this Appendix. No DCN shall operate to change the Design and Construction Requirements unless approved by the City in writing. Any DCN which requests a change to the Design and Construction Requirements shall be subject to the City's rights under this Appendix. A6-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures 4. CITY CONSTRUCTION INSPECTION 4.1. Design-Build Work Review Intent. The City and its designated representatives shall have the right, as provided in this Appendix, to review and inspect Design-Build Work activities and participate in Design-Build Work progress meetings as needed to verify compliance with the Contract Standards. The City will provide adequate inspectors as to not delay the work and be available during normal work hours to inspect work prior to covering up said work. The DBOM Contractor will provide the City 48 hours' advance notice (where required). The DBOM Contractor will provide the City of Portland 72 hours'advance notice to inspect portions of the new infrastructure that will be owned by the City of Portland at the conclusion of construction. Notwithstanding the City's review of Design-Build Work activities, the DBOM Contractor shall be fully responsible for means, methods, techniques, sequences, and procedures of Design-Build Work, as well as safety precautions and programs in the performance of the Design-Build Work. The City's review and involvement in Design-Build Work activities is intended for the informational purposes of the City and to monitor compliance with this DBOM Agreement. Such activities shall also be a part of the City's independent quality assurance process and shall not be viewed as an additional layer or integral part of the DBOM Contractor's quality management processes. 4.2. "Or Equals". With respect to items with a value of over $20,000, whenever such item of material or equipment is specified in the Design and Construction Requirements by using the name of a proprietary item or the name of a particular supplier, and is followed by the words "or equal", material or equipment of other suppliers may be considered. The City shall determine, acting reasonably, the acceptability of proposed"or equal"items associated with the Design-Build Work. The DBOM Contractor shall reserve adequate time for the City to review and approve all "or equal" items for the Design-Build Work. Any delays resulting from submittal of"or equal" items shall be the responsibility of the DBOM Contractor. The DBOM Contractor's design personnel shall be permitted to review proposed "or equal" suppliers for the balance of the Design-Build Work. 4.3. Functionally Equal. With respect to items with a value of over$20,000, if such item of material or equipment proposed by the DBOM Contractor for the Design-Build Work is functionally equal to that named, it may be considered by the City as an"or equal"item. A proposed item of material or equipment shall be considered functionally equal to an item so named if: (a) the City determines that: (1) it is at least equal in quality, durability, appearance, strength, and design characteristics; and (2) it shall reliably perform at least equally well the function imposed by the design concept of the completed Project as a functioning whole; and (b) the DBOM Contractor certifies that it shall conform substantially, even with deviations, to the detailed requirements of the item named in this DBOM Agreement. A6-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 6 DBOM Agreement Design-Build Work Review Procedures 4.4. Named Suppliers. Whenever an item of material or equipment is specified in the Design and Construction Requirements by using the name of a proprietary item or the name of a particular supplier, and is not followed by the words "or equal", the DBOM Contractor shall provide the named material or equipment. 4.5. Corrections and Changes. The procedures to be followed for correction of non-conforming Design-Build Work and for instituting changes and additions to such work are set forth in Article 5 (Design and Construction) of this DBOM Agreement. 5. RECORD DRAWINGS At the completion of the Design-Build Work, the DBOM Contractor shall conduct a final survey of the Project Site including all structures. The record drawings shall be prepared in accordance with the Contract Standards. The DBOM Contractor shall obtain the City's approval of the record drawings as a condition of Final Completion. The City's approval of the record drawings shall not be unreasonably withheld. [Remainder of Page Intentionally Left Blank] A6-7 3953578.11 043463 APPENDIX 7 GENERAL DESIGN-BUILD WORK REQUIREMENTS 3953578.11 043463 APPENDIX 7 GENERAL DESIGN-BUILD WORK REQUIREMENTS 1. PURPOSE The purpose of this Appendix is to set forth certain requirements for the performance of the Design-Build Work. The DBOM Contractor shall perform the Design-Build Work in accordance with the Contract Standards, including the requirements set forth in this Appendix. 2. MANAGEMENT AND COORDINATION As needed, the DBOM Contractor shall hold meetings that are separate from and in addition to weekly Design-Build Work progress meetings described in this Appendix, and shall prepare correspondence and make any other arrangements as necessary to coordinate the Design-Build Work. The DBOM Contractor shall coordinate its activities with other contractors performing work at or near the Project Site. The DBOM Contractor and the City, working together, shall endeavor to identify other construction contracts that may be in progress in close proximity to or bordering on the Project. The DBOM Contractor shall coordinate all Design-Build Work activities that could impact existing Utility services and installations (e.g., conduits, pipelines, transmission mains and other Utility equipment and appurtenances)with the Utilities, and shall coordinate, arrange for and/or implement any required utility relocations with the applicable utility. Coordination meetings may include review of the Project Schedule and installation procedures of other contractors to identify potential conflicts, allocation of space on the Project Site, drawing/design interchange among contractors, establishment and modification of schedules and sequences of Design-Build Work operations, and planning of future meetings. 3. PROJECT SCHEDULES 3.1. Project Schedule. All activities comprising the Design-Build Work shall be scheduled and monitored by use of Microsoft Project or Primavera software which sets forth all tasks and key subtasks in a logical and efficient work sequence that the DBOM Contractor intends to utilize to plan, organize and execute design and Design-Build Work in taking the Project from the Design and Construction Requirements to Final Completion, to record and report actual performance and progress, to show plans to complete all remaining activities as of the end of each progress report period, and to enable the City to monitor and evaluate work progress. If Primavera is used, the DBOM Contractor shall provide schedule information to the City in both native and PDF format as directed by the City. The Project Schedule shall be in the form of an activity oriented network diagram (Critical Path Method) and the principles and definitions of the terms used herein shall be as set forth in the Associated General Contractors of America (AGC) publication The Use of CPM in Design- Build Work, 1976. In the event of discrepancies, this Appendix shall govern the development and utilization of the Project Schedule. The Project Schedule shall include the Detailed Network Diagram (described in Section 3.2 below) and reports described herein. The Project Schedule shall show the sequence and interdependence of activities required for complete performance of all the work including design development, procurement, Design-Build Work,Acceptance, Final Completion and the Operation and Maintenance Period. The Project Schedule shall begin with the Design-Build Work NTP Date, include milestones representing release of design packages for Design-Build Work, include milestones representing completion of Acceptance and conclude with a milestone representing Final Completion. A7-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements The DBOM Contractor shall undertake and complete the Design-Build Work in accordance with the Project Schedule. The DBOM Contractor shall develop, revise and provide all information and input necessary for the Project Schedule required pursuant to this Appendix in accordance with the Contract Standards. The planning, scheduling, coordination and execution of the Design-Build Work are the sole responsibility of the DBOM Contractor. The initial Project Schedule is set forth in Attachment 7A (Project Schedule). The Scheduled Acceptance Date and the date for Final Completion shall not be changed in any updates without written permission from the City in accordance with this DBOM Agreement. 3.2. Detailed Network Diagram The Project Schedule shall include a time-scaled "Detailed Network Diagram" based on calendar days. The Detailed Network Diagram shall be in Critical Path Method ("CPM") precedence format and shall show the sequence and interdependence of activities required for complete performance of all items of work. A calendar shall be shown on all sheets along the entire sheet length. Each activity shall be plotted so that the beginning (and completion dates) of the activity can be determined graphically (by comparison) with the calendar scale. The Detailed Network Diagram shall provide sufficient detail and clarity of form and technique so that the DBOM Contractor can plan, schedule, and control the Design-Build Work properly and the City can readily monitor and follow progress for all portions of the Design-Build Work. The Detailed Network Diagram shall include all activities of the Design-Build Work. Critical path activities shall be identified, including critical paths for milestone dates. The Detailed Network Diagram shall include the following information related to the activities: • Activity number. • Activity description. • Estimated duration in working days. • Major materials and equipment acquisition and arrivals/departures at/from the Project. The degree of detail of the Detailed Network Diagram shall consider the following factors: • The type of work to be performed and the labor trades involved. • All delivery activities for all major materials and equipment. • A schedule for all submittals requiring outside approval, including allowed review response time, and logic linked to start of appropriate work items so that any resubmittal requirements shall adjust the start or ordering of the consequential work item(s) • Submittal and approval of shop and working drawings and material samples. • Efforts and activities for all Subcontract work by discrete Subcontractor. • Test, submissions, and acceptance of test results. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures and/or precipitation to ensure completion of all Design-Build Work by the Final Completion date. Seasonal weather conditions shall be determined by an assessment of average historical climatic conditions based upon the preceding ten year records published for the locality by the National Ocean and Atmospheric Administration based on the Portland International Airport reporting station. The DBOM Contractor may use labor or equipment restraints separately noted to optimize and level labor and equipment requirements. The individual activities involved may be A7-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements sequenced within the limits of total float to the next control milestone in the logic chain. When this technique is used in establishing the working schedule, it shall be reflected in the logic. Critical or near-critical paths developed from the use of labor restraints shall be kept to a minimum. Near-critical paths shall be defined as those paths having 14 calendar days or less of total float at time of initial submission. The Project Schedule (and any updates thereto) shall be submitted to the City in pdf and native format as well as hardcopy upon request. 3.3. Project Schedule Updates. The DBOM Contractor shall, as required from time to time during the Design-Build Period, but no less than once per calendar month, in consultation with the City update the Project Schedule so that it is at all times an accurate, reasonable and realistic representation of the DBOM Contractor's plans for the completion of the Design-Build Work in accordance with the requirements of this DBOM Agreement. The DBOM Contractor shall submit schedule updates to the City three business days in advance of the first progress meeting of each month. Each schedule update shall include the following elements: (a) A complete updated CPM schedule showing progress against each activity; (b) a four week look ahead schedule and a present to complete summary schedule and a Design-Build Work activity status report to include current and forecasted status of each Design-Build Work activity and submittal event in WBS start sort order; and (c) status for any weather schedule buffers shall be made on the number of observed and recorded weather delays that occurred to date for the schedule buffer timespan, which must be verifiable against the daily field reports for each work segment. The updates shall include adjustments resulting from Relief Events, if any, as permitted by this DBOM Agreement. Should any negative float items appear, the DBOM Contractor shall provide specific explanation of the causes of each and proposed remedies. 3.4. City Review. The City shall review the updated Project Schedule and may advise the DBOM Contractor as to any of its concerns, along with proposed changes for the DBOM Contractor's consideration. Every three months, or more frequently if requested by the City, in addition to the weekly Design- Build Work progress meetings, the DBOM Contractor shall meet with the City to discuss Project progress and the updated Project Schedule. The DBOM Contractor shall respond to the City concerns and indicate how the proposed changes or revisions thereto can be made to satisfactorily address City concerns or, why such concerns cannot be satisfactorily addressed. Changes agreed to by the DBOM Contractor, shall be incorporated in the updated Project Schedule and replace the previous baseline Project Schedule. Project Schedule updates are for the purpose of providing the DBOM Contractor with flexibility in its work activity durations and sequences, but in no event shall such updates result in a change in the Scheduled Acceptance Date or the date for Final Completion, except as provided in this DBOM Agreement due to the occurrence of a Relief Event. A7-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements 3.5. Events Affecting the Project Schedule. Within 15 days, or as otherwise reasonably agreed to by the parties, following the occurrence of a Relief Event or a City-directed Change Order, or delays are experienced that may impact the critical path, the DBOM Contractor shall submit a report containing a"Time Impact Analysis" illustrating the effects of such events on the current Project Schedule, including any new dates for work task and major subtasks, Acceptance, the Scheduled Acceptance Date or the date for Final Completion. Additionally, the analysis shall demonstrate the time impact based on the date that the DBOM Contractor was notified of the authorization of the change or the date that the delay began, the status of Design-Build Work at that point in time, and the event time computation of all affected activities. The DBOM Contractor shall present mitigation measures that were considered to offset potential work delays; those proposed for City review and acceptance; and a revised Project Schedule incorporating the DBOM Contractor's proposed changes. The event items used in the analysis shall be those included in the latest updated copy of the detailed progress schedule. In cases in which the DBOM Contractor does not submit a Time Impact Analysis for a specific change within the time requirements established under this Section, then it is mutually agreed that that particular potential revision or delay has no time impact on any of the scheduled completion dates and the Project's critical path and no time extension will be granted. 4. CONSTRUCTION REPORTS AND RECORDS 4.1. Monthly Progress Reports. The Monthly Progress Report required to be submitted by the DBOM Contractor shall include: (a) a summary of Design-Build Work activities during the reporting month; (b) a schedule of upcoming Design-Build Work activities; (c) a listing of submittals delivered during the reporting month and their status; (d) a listing of submittals scheduled for delivery the following month; (e) the DBOM Contractor's verification that the record documents have been updated as appropriate; (f) a summary of activities involved with obtaining Governmental Approvals and non- Governmental Approvals; (g) a listing of any violations of Governmental Approvals, non-Governmental Approvals or Applicable Law and actions taken or to be taken to eliminate any subsequent violations; (h) a listing of issues needing resolution; (i) a listing of all telephone calls received during the reporting month involving material inquiries or complaints; (j) Project Schedule updates and Cost/Schedule Status Report (CSSR); A7-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements (k) the DBOM Contractor's recovery plan for meeting the Scheduled Acceptance Date should the DBOM Contractor's progress-to-date indicate that the DBOM Contractor's Design-Build Work is behind schedule and at risk of not being completed by the Scheduled Acceptance Date; and (1) a description of the percentage of the Design-Build Work complete with a breakdown of subsets of the Design-Build Work and the percentage of each subset complete. The Monthly Progress Reports shall also provide a description of (1) any concerns or issues raised by the City or other parties regarding the Design-Build Work, and the DBOM Contractor's approach to promptly addressing and resolving such concerns or issues, and (2) a section containing health and safety statistics and a description of any accidents or injuries that occurred and the follow up investigations as to cause and subsequent corrective actions to be taken or already implemented by the DBOM Contractor. The format of the Monthly Progress Reports shall be developed by the DBOM Contractor and approved by the City prior to the commencement of any Design-Build Work on the Project Site. 4.2. Project Records. The DBOM Contractor, in connection with the Design-Build Work generally, shall maintain and provide the following records: (a) Record Drawings and Specifications: The DBOM Contractor shall: (1) throughout the Design-Build Work, update the Design Documents (with respect to the drawings, such update shall be in "CAD" or other electronic format reasonably acceptable to the City), including approved shop drawings that are available from Subcontractors in CAD format, so as to produce accurate and complete record documents for the Project; (2) as requested from time to time during the Design-Build Work, make available such record drawings and specifications to the City for review to permit the City to monitor the DBOM Contractor's compliance with the requirements of this Section; and (3) provide all CAD files, including 3D CAD model files, of the completed record drawings as a condition to Final Completion. The record drawings shall not be deemed to have satisfied the condition to Final Completion unless reviewed and deemed final by the City. (b) Design Records: The DBOM Contractor shall retain records of the design development. (c) Minutes of Meetings: The DBOM Contractor shall retain minutes of meetings between the City and the DBOM Contractor relating to the Design-Build Work, and shall circulate such minutes to the City for review and comment. (d) Inspection Reports and Tests Results: The DBOM Contractor shall retain official reports and certified test records of all inspections and tests which were undertaken as part of the Design-Build Work. (e) Utility Plans: The DBOM Contractor shall retain utility plans for the Project and the Project Site. A7-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements (f) Landscape and Irrigation Plans: The DBOM Contractor shall retain landscape and irrigation plans for the Project and the Project Site. (g) Copies of all Governmental Approvals: The DBOM Contractor shall retain copies of all Governmental Approvals for the Design-Build Work and operation of the Project. (h) Signed Design-Build Quality Management Plan: The DBOM Contractor shall retain a signed copy of the Design-Build Quality Management Plan for the design and Design-Build Work and all records of the quality assurance program implemented as required by this DBOM Agreement. (i) Daily field logs recording the weather at each work site throughout the day, what contractors are on site and equipment/material deliveries as well as any events such as outages, work stoppage, accidents, material/equipment loss, and property damage. The records referred to in this Section shall be retained for at least five years following the Acceptance Date. 5. CONSTRUCTION WORK GENERALLY 5.1. Geotechnical Work and Subsurface Exploration. The DBOM Contractor shall conduct any additional subsurface investigations of the Project Site as necessary in accordance with the Standard of Care to determine design requirements for Design-Build Work, including dewatering and foundation requirements. The DBOM Contractor shall employ a qualified firm to perform the subsurface investigations. The DBOM Contractor shall employ a professional engineer, licensed in the State, to plan, oversee, and evaluate the results of all additional subsurface investigations and to determine requirements for the design of the Project, including foundations, superstructures, and dewatering systems, with regard to seismic conditions and existing soil conditions. The engineer shall provide recommendations for Design-Build Work requirements as to protecting the Design- Build Work and any existing structures and Utilities. The DBOM Contractor shall perform all geotechnical work and subsurface explorations in accordance with the Contract Standards. The DBOM Contractor shall have the full responsibility for verifying the presence and location of all subsurface utilities structures at the Project Site. 5.2. Signs. The DBOM Contractor shall provide and maintain temporary identification and information signs during the Design-Build Period and as required in connection with a WIFIA loan. No signs shall be erected until their appearance, content, and location have been fully reviewed and approved by the City, which approval shall not unreasonably be withheld, conditioned or delayed. The DBOM Contractor shall remove temporary signs from the Project Site when they are no longer necessary. 5.3. Maintenance of the Project Site. During performance of the Design-Build Work, the DBOM Contractor shall be responsible for the overall maintenance of the Project Site. The DBOM Contractor shall keep the Project Site neat and orderly at all times, and shall clean up and remove all rubbish and construction debris from the Project Site as they accumulate in accordance with the Contract Standards. A7-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements 5.4. Temporary Utilities. The DBOM Contractor shall supply all necessary temporary Utilities, including electricity, telecommunications services, potable water, fire protection, lighting, and sanitary facilities, during Design-Build Work, testing and start-up of the Project. Prior to the Acceptance Date, the DBOM Contractor shall disconnect and arrange for the disconnection and removal of all temporary Utility connections and services. The DBOM Contractor shall coordinate with the City on all temporary Utilities. 5.5. Relocation of Existing Utilities. The DBOM Contractor shall be responsible for all Design-Build Work activities required with regard to existing utility services and installations (e.g., conduits, pipelines, transmission mains and other utility equipment and appurtenances), including after City review and approval of any relocation of Utilities. 5.6. Noise Control and Design-Build Work Hours. The DBOM Contractor shall comply with all noise regulations required pursuant to Applicable Law. The DBOM Contractor shall not perform Design-Build Work between 7:00 PM and 6:00 AM, or on Sundays or holidays without specific permission from the City. Any blasting shall be subject to the City's approval, and the DBOM Contractor shall provide at least two Business Days'notice to the City prior to any planned blasting. 5.7. Traffic Control Parameters. The DBOM Contractor will be required to secure a Traffic Control Permit from the City for construction activities that may affect vehicular traffic at or in the vicinity of the Project Site. The DBOM Contractor shall prepare a detailed Traffic Control Plan that will specify the type and location of all proposed traffic control devices for all phases of construction that affect the public right of way. The Traffic Control Plan shall be consistent with Good Design-Build Practice and relevant reference manuals, including the Oregon Temporary Traffic Control Handbook and the Manual on Uniform Traffic Control Devices issued by the Federal Highway Administration. The Traffic Control Plan will also need to ensure that operations at the TCWTP are not disturbed. The DBOM Contractor shall maintain access for emergency vehicles with possible exceptions for short term durations and/or night construction when required to perform Design-Build Work activities with the consent of the City. City approval of the Traffic Control Plan shall be obtained prior to performing any construction activities that affect the public right of way. 6. COORDINATION OF CONSTRUCTION WORK AND OPERATIONS The DBOM Contractor shall take no actions during the Design-Build Period that adversely affect operation of City, public or private Utilities, without reasonable notice to the City and City approval. The DBOM Contractor, to the extent practicable, shall arrange and provide all necessary bypasses and other measures needed to maintain utility service. 7. CONSTRUCTION SAFETY AND SECURITY 7.1. Safety and Security. The DBOM Contractor shall maintain safety and security at the Project Site at all times at a level consistent with the Contract Standards. Without limiting the foregoing, the DBOM Contractor shall: A7-7 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements (a) Take appropriate precautions for the safety and security of the Design-Build Work and provide appropriate protection to prevent damage, injury or loss related to the performance of the Design-Build Work over the Design-Build Period for: (1) Workers at the Project Site and all other persons who may be involved with deliveries or inspections; (2) Visitors to the Project Site; (3) Passersby, neighbors and adjacent properties with respect to the Design- Build Work activities; (4) Materials and equipment under the care, custody or control of the DBOM Contractor or Subcontractors on the Project Site; (5) Other property constituting part of the premises or the Project under construction; and (6) City property. (b) Establish and enforce appropriate safeguards for safety and protection, including posting danger signs and other warnings against hazards. (c) Provide temporary fencing of all open or partially open trenches and excavations, all open or partially completed structures, and all work and storage areas at all times while unattended by workmen. (d) Implement a comprehensive safety program in accordance with Applicable Law. (e) Give all notices and comply with all Applicable Law relating to the safety of persons or property or their protection from damage, injury or loss. (f) Operate and maintain all equipment in a manner consistent with the manufacturer's safety requirements. (g) Provide for safe and orderly vehicular movements. (h) Develop and implement a written Project Site-specific Health and Safety Plan that includes management commitment, maintaining a safe workplace, employee participation, hazard evaluation and controls, employee training and periodic inspections ("Health and Safety Plan"). (i) Designate an appropriately certified and experienced safety professional to develop and sign the Project Site-specific Health and Safety Plan, including all safety rules at the Project Site. (j) Designate a qualified safety professional at the Project Site during on-site Design- Build Work activities who shall be responsible for the implementation of safety rules at the Project Site, the prevention of fires and accidents, monitoring compliance with the DBOM Contractor's Project Site-specific Health and Safety Plan, and the coordination of such activities as shall be necessary with the City and all Governmental Bodies related to health and safety. A7-8 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements (k) Require all Subcontractors to work in accordance with and implement the Health and Safety Plan, comply with the DBOM Contractor's on-site safety requirements, and designate a qualified safety professional whose duty shall be the implementation of safety rules at the Project Site and monitoring compliance of Subcontractor employees with the Project Site-specific Health and Safety Plan. 7.2. Design-Build Work Site Security. The DBOM Contractor shall develop, maintain and comply with a Project Site security plan that is approved by the City and constitutes part of the Health and Safety Plan. The security plan shall assure the security of the Project Site when perimeter fencing cannot be continuously maintained. 8. ENVIRONMENTAL REVIEW AND PROTECTION 8.1. Wildlife and Protected Species Protection. In accordance with the environmental mitigation measures, if any exist, the DBOM Contractor shall develop and implement a plan that is consistent with required mitigation measures for wildlife and protected species that may be affected by Design-Build Work activities of the DBOM Contractor. Prior to implementing the plan, the DBOM Contractor shall obtain City approval. 8.2. DBOM Contractor Design-Build Work Environmental Monitor. If required by the environmental mitigation measures, if any exist, the DBOM Contractor shall assign a DBOM Contractor Design-Build Work Environmental Monitor ("CEM") to confirm that its mitigations plan is properly and fully implemented. The CEM shall be the single, identified entity or person responsible for, at a minimum, the following duties: (a) planning of environmentally compliant construction methods; (b) oversight of Design-Build Work activities to determine compliance with mitigation measures; (c) ensuring that all training has been conducted, and signage, marking and barriers to protected areas have been installed; (d) ensuring compliance with the Stormwater Pollution Prevention Program (SWPPP); (e) coordination with the City on implementation of environmental mitigation measures; (f) coordination with Governmental Bodies that have administrative oversight of the environmental sites to be protected, if required; (g) compliance with environmental Governmental Approvals; and (h) meeting or interacting with representatives of Governmental Bodies with environmental oversight authority, if required. All environmental monitoring duties conducted by the CEM shall be recorded in the form of a standard report and photographic log (as required). The photographic log shall be kept in both electronic and hardcopy form. All reports shall be submitted to the City in summary form A7-9 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements on a monthly basis or more frequently if required by the City. Copies of all daily monitoring records shall be maintained at the Project Site by the CEM. 8.3. DBOM Contractor Hazardous Substances. Any Hazardous Substances generated by the DBOM Contractor shall be the responsibility of the DBOM Contractor. The DBOM Contractor shall obtain an EPA identification number for all DBOM Contractor Hazardous Substances, listing the DBOM Contractor's name and construction site address as the generator of the DBOM Contractor Hazardous Substances. The DBOM Contractor shall be responsible for the identification, analysis, profiling, documentation, reporting, transport and disposal of DBOM Contractor Hazardous Substances. Any fines that are levied against the City for violations of Applicable Law as determined by any Governmental Body relating to DBOM Contractor Hazardous Substances shall be reimbursed immediately by the DBOM Contractor after payment by the City. 8.4. Emergency/Spill Response Plan. As part of the Design-Build Work, the DBOM Contractor shall develop an Emergency/Spill Response Plan ("Emergency Response Plan"), for each Hazardous Substance or class/group of Hazardous Substances either known to be on the Project Site or intended to be brought to the Project Site by the DBOM Contractor. At a minimum, the Emergency Response Plan must include the following: (a) A description of on-site equipment available to contain and respond to an emergency/spill of the Hazardous Substance. (b) Notification procedures, including notification to potentially impacted residents adjacent to the Project Site. (c) Response coordination procedures between the DBOM Contractor and the City. (d) A Hazardous Substance site map showing the location of stored Hazardous Substances and location spill containment/response equipment. (e) A description of the Hazardous Substances handling and spill response training provided to the DBOM Contractor's employees and Subcontractors. 8.5. Dust Control. The DBOM Contractor shall be responsible for dust control during the performance of the Design-Build Work and shall comply with all applicable air pollution control regulations and the environmental mitigation measures, if any exist. The DBOM Contractor shall furnish all necessary labor, materials and equipment for dust control. [Remainder of Page Intentionally Left Blank] A7-10 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 7 DBOM Agreement General Design-Build Work Requirements ATTACHMENT 7A PROJECT SCHEDULE [ATTACHED] A7-11 3953578.11 043463 APPENDIX 8 COMMISSIONING AND ACCEPTANCE TESTING 3953578.11 043463 APPENDIX 8 COMMISSIONING AND ACCEPTANCE TESTING 1. PURPOSE The purpose of this Appendix is to set forth the requirements for Commissioning, testing, and start-up of the Project. Commissioning will consist of the following two elements: (1) Commissioning; and (2) Acceptance Testing. 2. COMMISSIONING PLAN The DBOM Contractor shall prepare and implement the Commissioning Plan substantially consistent with the preliminary plan set forth in Attachment 8A (Preliminary Commissioning Plan) that describes the process that will be implemented and deliverables that will be provided in order to commission, test, accept and start up the Project. The DBOM Contractor shall complete this plan upon the earlier of ODEQ requiring such final plan or 150 days prior to the commencement of Commissioning. The Commissioning Plan shall meet all ODEQ requirements and fully describe the DBOM Contractor's approach that will be implemented to: (a) Commissioning of the Project; (b) implement the approach necessary to ensure stable and reliable operation of the TCWTP during the Commissioning and Acceptance Testing processes; (c) start up the Project; and (d) implement the transition process to transfer all wastewater treatment services of the TCWTP to the Project. 3. ACCEPTANCE TEST PLAN The Commissioning Plan shall include an Acceptance Test Plan. The Acceptance Test Plan shall describe the DBOM Contractor's approach to conduct an Acceptance Testing process to demonstrate performance of individual components of the Project and the Project's ability to meet all performance requirements described in this DBOM Agreement. This sub plan shall describe the testing protocols, procedures and processes for the performance of Acceptance Tests and the DBOM Contractor's approach to complying with the requirements set forth in Article 6 (Acceptance) of this DBOM Agreement. A preliminary Acceptance Test Plan is set forth in Attachment 8B (Preliminary Acceptance Test Plan). [Remainder of Page Intentionally Left Blank] A8-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 8 DBOM Agreement Commissioning and Acceptance Testing ATTACHMENT 8A PRELIMINARY COMMISSIONING PLAN [ATTACHED] A8-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 8 DBOM Agreement Commissioning and Acceptance Testing ATTACHMENT 8B PRELIMINARY ACCEPTANCE TEST PLAN [ATTACHED] A8-3 3953578.11 043463 APPENDIX 9 DESIGN-BUILD WORK SCHEDULE OF VALUES AND MAXIMUM DRAWDOWN SCHEDULES 3953578.11 043463 APPENDIX 9 DESIGN-BUILD WORK SCHEDULE OF VALUES AND MAXIMUM DRAWDOWN SCHEDULE 1. PROGESS PAYMENT SCHEDULES The Design-Build Price Schedule of Values that has been agreed upon by the parties as of the Effective Date is provided in Attachment 9A (Design-Build Price Schedule of Values). The DBOM Contractor shall be entitled to submit Requisitions and receive from City the payments of the Design-Build Price that are on a percent complete basis subject to the conditions to payment set forth in Section 7.5 (Payment Procedure) of this DBOM Agreement. 2. MAXIMUM DRAWDOWN SCHEDULE The schedule of maximum monthly progress payments of the Design-Build Price that has been agreed upon by the parties as of the Effective Date is provided in Attachment 9B (Design- Build Price Maximum Drawdown Schedule). In no event shall the cumulative Design-Build Price payments in any month exceed the maximum drawdown amount for the particular month, as indicated in Attachment 9B (Design-Build Price Maximum Drawdown Schedule). The DBOM Contractor may request a modification to the maximum drawdown schedule in Attachment 9B (Design-Build Price Maximum Drawdown Schedule) by delivering its requested modifications to the City not less than 90 days prior to the date on which the DBOM Contractor proposes such modifications to come into effect and the City agrees to reasonably consider any such request presented by the DBOM Contractor. All agreed upon modifications to the maximum drawdown schedule in Attachment 9B (Design-Build Price Maximum Drawdown Schedule) shall be reflected in a DBOM Agreement Amendment. [Remainder of Page Intentionally Left Blank] A9-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 9 DBOM Agreement Design-Build Work Schedule of Values and Maximum Drawdown Schedules ATTACHMENT 9A DESIGN-BUILD PRICE SCHEDULE OF VALUES [ATTACHED] A9-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 9 DBOM Agreement Design-Build Work Schedule of Values and Maximum Drawdown Schedules ATTACHMENT 9B DESIGN-BUILD PRICE MAXIMUM DRAWDOWN SCHEDULE [ATTACHED] A9-3 3953578.11 043463 APPENDIX 10 OPERATION AND MAINTENANCE REQUIREMENTS 3953578.11 043463 APPENDIX 10 OPERATION AND MAINTENANCE REQUIREMENTS 1. OVERVIEW The DBOM Contractor prepared the Preliminary Operation and Maintenance Plan set forth in Attachment 10A (Preliminary Operations and Maintenance Plan) that documents all protocols, procedures, and systems the DBOM Contractor will implement in order to operate and maintain the Project in accordance with this DBOM Agreement. The final Operation and Maintenance Plan, which shall be provided prior to the Acceptance Date, shall be subject to review and approval by the City for consistency with the Contract Standards as well as consistency with the Preliminary Operation and Maintenance Plan set forth herein. The final Operation and Maintenance Plan shall address any and all ODEQ requirements as well as the requirements otherwise set forth in this DBOM Agreement, including the following: (a) Operational procedures and protocols. (b) Organizational chart and communications protocols. (c) Standard operating procedures for all equipment and treatment processes. (d) SCADA management approach. (e) Lockout-tagout blockout-tagout (LOBOs). (f) Odor control procedures. (g) Noise control procedures. (h) Laboratory protocols. (i) Residuals management and disposal plan. 0) Mitigation monitoring and reporting plan. (k) Staffing plan. (1) License management. (m) Emergency response and disaster recovery plan. (n) Hazard analysis and critical control points. (o) Safety plan. (p) Security plan. (q) Meetings and City access to records and administrative space. (r) Computerized Maintenance Management System (CMMS) plan. (s) Operations period operating reports. A10-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 10 DBOM Agreement Operation and Maintenance Requirements (t) Operation and maintenance inspections. (u) Major Maintenance, Repair and Replacement Plan including: (1) A detailed Major Maintenance, Repair and Replacement Schedule, identifying all asset repair and replacement activities and intervals for each year of the 30-year Term, as described in subsection 10.2(A) (Major Maintenance, Repair and Replacement Schedule) of this DBOM Agreement. (2) Asset inventory / registry. (3) Asset identification methodology. (4) Asset useful life assumptions and calculations. (5) Asset repair data management methodology. (6) CMMS interfaces. (7) Asset inspection protocol. (8) Spare / replacement part inventory. (9) Reporting protocol. [Remainder of Page Intentionally Left Blank] A10-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 10 DBOM Agreement Operation and Maintenance Requirements ATTACHMENT 1OA PRELIMINARY OPERATIONS AND MAINTENANCE PLAN [ATTACHED] A 10-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 10 DBOM Agreement Operation and Maintenance Requirements ATTACHMENT l0B MAJOR MAINTENANCE, REPAIR AND REPLACEMENT SCHEDULE [ATTACHED] A 10-4 3953578.8 043463 CTR 3953578.11 043463 APPENDIX 11 ODOR CONTROL STANDARD AND ODOR CONTROL PLAN 3953578.11 043463 APPENDIX 11 ODOR CONTROL STANDARD AND ODOR CONTROL PLAN 1. PROJECT ODOR CONTROL TEAM The DBOM Contractor will form a "Project Odor Control Team" comprising the Operation and Maintenance Supervisor, a representative from DBOM Contractor's senior management and representative(s) from the City. The team will meet on a quarterly basis to review any odor complaints received and actions taken to mitigate, review facility conditions, provide recommendations for problem resolution and, if required, conduct on-site survey of odor conditions and their characterization. 2. MINIMUM PROACTIVE ODOR PREVENTION PLAN 2.1. Facility Monitoring and Mitigating Measures. DBOM Contractor will routinely monitor the Facility for odors including the presence of Hydrogen Sulfide ("H2S") using a portable H2S meter. The DBOM Contractor shall make plant patrols (rounds) of the Facility and the Facility boundary(which may be included in other regular patrols or maintenance of the Facility) using both the portable meter as well as their own senses to determine if H25 or other odor conditions are detectable. H25 levels will be measured in the odor control system exhaust, in exhaust air from the solids thickening building and headworks, as well as any other location with a history of sulfide odor emission. Rounds will be performed once per week. If after the first 6 months of operation, no Odor Incidents have occurred, the frequency of rounds may be reduced to once per month; provided, however, that upon the occurrence of an Odor Incident, the weekly rounds requirement shall be reinstated and may be reduced to once per month if no Odor Incidents have occurred during the 6 months following correction of the Odor Incident. The weekly rounds reinstatement, with potential reduction to monthly rounds following 6 months from correction, described above shall apply upon the occurrence of any subsequent Odor Incidents. Any detection of an Odor Incident in accordance with Section 3 (Determination of an Odor Incident for Purposes of the Odor Guarantee) of Appendix 13 (Performance Guarantees and Deductions), to the extent not caused by a Relief Event, will be cause for the DBOM Contractor to implement a Corrective Action Plan, as described in Section 4 (Response Plan). Written guidelines will be prepared by the DBOM Contractor employees to follow if H2S or odor is detected. The Operation and Maintenance Supervisor will ensure that each plant patrol finding, including any measured readings of H2S or detection of odor, is recorded in a bound logbook kept at the Facility. The Operation and Maintenance Supervisor will ensure that the log for each patrol is signed, indicating the individual making and signing the entry, time of patrol, weather conditions, wind speed and direction. Summary findings will be included in the odor control section of the monthly operations report described below. The DBOM Contractor shall submit to the City within the monthly operations report required by Section 8.11 (Periodic Reports) of this DBOM Agreement, a monthly odor control section which shall include: (1) a listing of all odor complaints received during the month, with name, address, and nature of complaint; (2) all investigations conducted and actions taken or planned in response to such complaints; (3) evidence showing compliance with the odor control operating practices required by this DBOM Agreement, including a summary of the results of the H2S metering and odor detection required by this Section; (4) the quantity of odor control consumables used during the month; and (5) such other matters pertaining to odor control as the City may require from time to time. All-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 11 DBOM Agreement Odor Control Standard and Odor Control Plan The DBOM Contractor shall check to ensure that doors are closed, exhaust systems are operating properly and that no abnormal amounts of dust or abnormal odors are present. The DBOM Contractor shall check at a minimum the thickening and headworks area to ensure that H2S levels do not exceed safe levels for operational personnel. Safe levels within buildings for personnel should be low enough to preclude generation of objectionable odors that could extend to the community. 2.2. Construction Activity. No process equipment, tankage or process stream shall be taken out of service for the purpose of construction activity without a written procedure that addresses odor concerns and odor prevention procedures. The DBOM Contractor shall ensure that no equipment or processes are taken out of service for construction activity without this written procedure that indicates, as a minimum, estimated duration of outage, potentials for production of odors and mitigating measures and potentials for non-compliance with discharge requirements and mitigating measures. 2.3. Coordination of Operational and Construction Activities. Any activity associated with operation and maintenance of the Project which may increase the risk of odor formation must be timed, to the extent reasonably possible, to minimize adverse interaction with high profile events (i.e. such as community events in and around downtown Lake Oswego and major conventions) in the City and surrounding area. 2.4. Odor Control Report. In addition to the measures described in this Appendix, the DBOM Contractor will prepare its own odor control report within three months after the Acceptance Date, to identify additional measures, procedures and Facility and system improvements to mitigate against the release of odors necessary to achieve the Contract Standards. 3. ODOR CONTROL STANDARD 3.1. Odor Control Standard. The Project shall be designed to prevent an Odor Incident and dispersion modeling developed during design shall show 5 D/T or less at the Project Site's property line at least 99% of the time. Nothing set forth in this Section 3.1 shall limit the determination of an Odor Incident. 3.2. Dispersion Modeling. As part of final design services and during the Acceptance Tests, the DBOM Contractor will prepare a dispersion model demonstrating conformance with the odor control standard set forth in Section 3.1 (Odor Control Standard) of this Appendix that considers all areas that could generate odors including the odor treatment discharge stacks and ventilation discharges from any areas without a dedicated odor treatment system such as the aeration basins, if not covered and provided with an odor treatment system on the Acceptance Date. Dispersion modeling shall not include emissions due to plant disruptions, equipment maintenance or atypical conditions. The dispersion model shall be set up to predict maximum hourly impacts to demonstrate compliance with the 5 D/T requirement. The dispersion model developed during design shall be used to identify the maximum allowable stack discharge concentration needed to achieve compliance with the Odor Guarantee with odor control equipment and systems sized and selected accordingly. A11-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 11 DBOM Agreement Odor Control Standard and Odor Control Plan 3.3. Odor Test Protocols. Any odor tests necessary in response to any odor complain or observation shall be performed in accordance with the following protocol or such other protocol established in the Operation and Maintenance Manual. Any combination of these methods may be utilized as deemed appropriate by the parties to investigate and confirm the presence of odors: (a) Assessment of prevailing wind direction and speed data (from the onsite weather station) to determine if a correlation exists between the location of the odor and Wastewater Treatment Facility sources. (b) H2S testing shall be accomplished using a properly calibrated handheld H2S meter at the locations listed in Table 11-1. (c) If odors are perceived within the Project Site boundary, onsite assessment of D/T shall be performed at the fence line using a Field Olfactometer to directly measure odor strength. (d) Odor samples shall be collected in Tedlar bags through Tygon tubing at a fixed air flow rate of 5 liters/minute for point sources using a lung pump and a flux chamber for area sources. Each bag shall be preconditioned twice with a sample of the gas being evaluated and then evacuated before collecting the sample. Bags shall be filled to approximately 80% of capacity. Samples shall be processed in accordance with Section 3.4 (Odor Tests) of this Appendix. (e) The canopy enclosure shall be used to collect samples from weirs. The canopy enclosure shall consist of a two-foot by three-foot wooden frame covered with polyethylene sheeting. The sheeting shall extend into the weir trough to isolate three linear feet of weir. (1) A plastic funnel shall be used to collect samples from odor sources such as exhaust fans,vents, and open-air sources. The funnel shall have an opening eight inches in diameter. Table 11-1 H2S Testing Locations Location Description 1 Facility 21 Odor Control System Stack 2 Facility 26 Odor Control System Stack 3 Fenceline (Point Closest to Odor Compliant Location) 3.4. Odor Tests. The forced-choice Olfactometry Method in accordance with ASTM E-679 and EN 13725 shall be used to determine the dilutions to threshold ratio of the samples. Samples shall be sent to the lab for analysis of 20 Reduced Sulfur Compounds (RSC) using ASTM D 5504-12 or similar test. Only a laboratory specializing in odor evaluation using Forced Choice Olfactometry Method shall be used for odor qualification. A11-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 11 DBOM Agreement Odor Control Standard and Odor Control Plan 4. RESPONSE PLAN The DBOM Contractor will maintain a phone line and email address at the Facility to receive and record odor complaints, which shall be staffed during normal business hours. When an odor complaint is received, either in person, via email or telephonically, the DBOM Contractor's shift supervisors will complete an odor complaint form. The DBOM Contractor's shift supervisors will then investigate all complaints and attempt to determine the cause. If the cause of the odor is a source other than the Project, the DBOM Contractor will notify the City of the responsible party of the odor source, and the City shall seek the appropriate recourse with the responsible party of the odor source as determined by the City in its discretion. Odor complaint forms shall include the following information: (a) Nature and location of the complaint; (b) Date and time the complaint was received; (c) Name of DBOM Contractor staff receiving the complaint; (d) Complainant contact information (name, street, mailing and e-mail address, and telephone); (e) Other complaints registered by the complainant or specific to the property in question; (f) Manner in which complaint filed: indirect (through City or another party), anonymously or identified in person by telephone e-mail or writing; (g) Project operating condition at the time the odor was detected, including odor control systems (e.g. normal operations, certain processes "in trouble", unusual influent conditions, equipment off-line for maintenance, variance in normal operations, etc.); (h) Weather conditions at time odor was noticed, including wind speed and direction, temperature, barometric pressure and relative humidity as recorded at the Project; (i) Date and time of response and name of employee responding to the complaint; (j) Operator and complainant observations at the site where the odor was noticed; (k) Description of remedial/mitigation action taken by the DBOM Contractor in response to the complaint and its effectiveness; (1) Description of the follow up with the complainant: in person verbally, follow up telephone call, e-mail or by letter; (m) Attitude of the person registering the complaint (i.e. satisfied/dissatisfied with the response, cooperative and understanding, impatient, confrontational, or other); and (n) Day and time the City's representative received verbal notice of the complaint and day and time the City received the complaint form and follow-up and response information. Al 1-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 11 DBOM Agreement Odor Control Standard and Odor Control Plan The following actions will be taken in the following order of priority following receipt of an odor complaint: (a) The DBOM Contractor shall, as promptly as reasonably practicable after receipt of the odor complaint complete the odor complaint form. (1) The DBOM Contractor shall make a preliminary determination as promptly as reasonably practicable after completion of the odor complaint form as to whether the odor which is the subject of the odor complaint emanates from the Project in accordance with the methodology set forth in Section 3.3 (Odor Test Protocols) of this Appendix. (2) The DBOM Contractor shall submit the completed odor complaint form to the City, marked to indicate the DBOM Contractor's preliminary determination of whether the odor which is the subject of the odor complaint emanates from the Project. (3) If a determination is made by the DBOM Contractor that the odor does not emanate from the Project, the DBOM Contractor shall so advise the person who submitted the odor complaint and shall have no obligation to take any corrective action with respect to such odor complaint unless the conditions described in clause (4) below occur. (4) If either: (i) Additional odor complaints are received proximate to the first odor complaint regarding what the DBOM Contractor reasonably believes to be the same odor situation, whether or not the DBOM Contractor has previously determined on a preliminary basis that the odor does not emanate from the Project; or (ii) The DBOM Contractor makes a preliminary determination based upon the first odor complaint or any of the additional odor complaints that the odor which is the subject of the odor complaint emanates from the Project, then the DBOM Contractor shall conduct odor tests at test sites it determines are appropriate for testing such odors. The DBOM Contractor shall perform a comprehensive review of odor sources at the Facility (and review all unit processes and emission points); conduct sampling of the odor sources (including wastewater sulfides, sulfates, dissolved oxygen, and) wastewater pH); conduct smoke testing to observe air flow patterns in ventilated areas; and undertake additional odor tests as it determines are appropriate to identify the applicable odor. If the odor source is in areas with covered equipment, the DBOM Contractor shall perform differential pressure measurements and smoke testing to determine whether the facilities are operating under negative pressure. The DBOM Contractor shall advise the City as to the results of such odor tests. If such odor tests indicate the presence of odor above the Odor Incident thresholds defined in Section 3 (Determination of an Odor Incident for Purposes of the Odor Guarantee) of Appendix 13 (Performance Guarantees and Deductions), then the DBOM Contractor shall promptly develop and implement a corrective action plan for such odor condition (the "Corrective Action Plan") and shall submit the Corrective Action Plan to the City for its review and comment. The Corrective Action Plan shall include, among other things, a description of A11-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 11 DBOM Agreement Odor Control Standard and Odor Control Plan the actions reasonably necessary to mitigate against the release of odors and a reasonable period of cure for the DBOM Contractor to implement the Corrective Action Plan in order to correct the abnormal odor. 5. ODOR CONTROL PLAN The DBOM Contractor's plan to meet the Odor Guarantee as described in this DBOM Agreement and comply with this Appendix's odor control standard is set forth in Appendix 10 (Operation and Maintenance Requirements) and in Attachment 10A (Preliminary Operations and Maintenance Plan) and such plan shall be updated and finalized in accordance with Section 8.3 (Operation and Maintenance Plan and Operation and Maintenance Manual) of this DBOM Agreement. [Remainder of Page Intentionally Left Blank] A11-6 3953578.11 043463 APPENDIX 12 INSURANCE REQUIREMENTS 3953578.11 043463 APPENDIX 12 INSURANCE REQUIREMENTS 1. DEFINITIONS AND SECTION REFERENCES 1.1. Definitions. In this Appendix, in addition to the definitions set out in this DBOM Agreement: "City Insured Parties" means the City Indemnitees other than the advisors, contractors and subcontractors (of any tier) of either the City or Portland. "Qualified Insurer" has the meaning set forth in Section 5.1(a) of this Appendix. 1.2. Section References. All Section references in this Appendix are to Sections of this Appendix, except Section references explicitly made to Sections or Articles of this DBOM Agreement. 2. INSURANCE DURING THE DESIGN-BUILD PERIOD The City, DBOM Contractor and Subcontractors shall obtain and keep in force, or cause to be obtained and kept in force, the following policies of insurance as specified in this Section 2 during the Design-Build Period. Evidence of such insurance shall be provided as specified Section 6. Unless otherwise specified in this Appendix, each policy shall be in full force and effect for the Design-Build Period. The DBOM Contractor and Subcontractors may, at their sole discretion, provide their respective required insurance as either project-specific policies or corporate policies. 2.1. Project-Specific Builder's Risk Property. The City shall obtain a builder's risk course of construction property insurance policy, covering direct damage to all Design-Build Work (including Commissioning and Acceptance Tests) at the Project Site, while in transit, while awaiting installation, or at any temporary off- site storage location. This policy shall cover all materials, machinery, fixtures and equipment intended to become a permanent part of used in the Project, or that are incidental to the construction (including all temporary structures at the Project Site that are to be used in or incidental to the fabrication, erection, testing, or completion of the Project). The builder's risk policy shall: (a) be maintained until the Acceptance Date; (b) be issued on replacement cost basis without an obligation to rebuild in an amount not less than the Full Insurable Value as defined in Section 4 (Full Insurable Value) of this Appendix; (c) be written on an"all risk"policy form basis, including loss arising from equipment breakdown, natural catastrophes (including but not limited to flood, water intrusion, earth movement including earthquake, and/or volcanic activity) and collapse. Sublimits shall not be less than $25,000,000 for flood and earth movement including earthquake; Al2-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements (d) include extension delay in start-up coverage for the benefit of the DBOM Contractor in an amount equivalent to twelve months of loss of revenue, extra expense, expediting expense and payment of debt service, with a deductible (waiting period) not to exceed 30 days; (e) include extension for extra and/or continuing expenses of any named insured related to project administration, legal expenses, accounting, permitting, salaries, equipment rent and overhead arising out of a schedule delay subject to a $25,000,000 sublimit; (f) include extension for debris removal; (g) include extension for state law/local ordinance extension, including demolition, increased cost of repairs and replacement; and (h) indicate the named insureds as the City, City Insured Parties, DBOM Contractor and any named Subcontractors. Other parties who have an insurable interest in the Design-Build Work shall be included as loss payees as their interests may appear at the time of loss. Such other parties shall include other City Insured Parties. 2.2. Professional Liability. Professional liability insurance shall be maintained as follows: (a) The Engineer, or Subcontractor of the DBOM Contractor responsible for stamping and sealing the Design Documents for the Project, shall obtain and keep in force a project-specific professional liability insurance policy in an amount of $10,000,000 per claim and annual aggregate. The policy shall be continuously maintained from the Design-Build Work NTP Date or contain an extended reporting period for no less than 10 years. Such policy shall not be cancellable for the duration of the Project. (b) All other professional consultants and/or subconsultants of any level to the DBOM Contractor shall provide evidence of professional liability insurance in an amount of $1,000,000 per claim and in aggregate. The policy shall be continuously maintained from the Design-Build Work NTP Date for a period of no less than 3 years following Acceptance, or contain an equivalent extended reporting period. (c) The DBOM Contractor shall obtain and keep in force professional liability insurance for its liability related to negligent acts, errors, or omissions resulting to professional services delivered under this DBOM Agreement in the amount of $10,000,000 per claim and annual aggregate. Such insurance be in full force and effect for 10 years commencing on Design Builder Work NTP Date. The retroactive date on this policy shall be prior to, or coinciding with, the effective date of the Preliminary Services Agreement, or as at first design, whichever is earlier. Each professional liability policy required in this Section shall not include any exclusionary language relative to design-build joint ventures or partnerships or otherwise invalidate or limit coverage available for losses arising out of the Project. Al2-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements 2.3. Project-Specific Commercial General Liability. The City shall obtain and keep in force for the benefit of the DBOM Contractor and the Subcontractors performing Design-Build Work commercial general liability insurance with general aggregate limits dedicated to the Project, on the latest ISO Form CG 00 01 at the time of policy issuance or equivalent reasonably acceptable to City. Coverage shall be provided in the form of an owner controlled insurance program, and the DBOM Contractor shall comply with all requirements set forth in Attachment 12A (Owner Controlled Insurance Program Requirements). Such coverage shall be maintained for a period of not less than 10 years following the Acceptance Date or the Termination Date, whichever occurs first. This insurance shall: (a) provide limits to all named insureds with a limit of liability not less than $2,000,000 per occurrence, $4,000,000 general aggregate, and $4,000,000 products/completed operations aggregate dedicated to the Project; (b) apply on an occurrence basis; (c) provide defense in addition to policy limits; (d) not contain any explosion, collapse or underground exclusion; (e) not contain exclusions for blasting, demolition, excavating, under-pinning, pile- driving, shorting, caisson work, below-ground surface work and similar operations associated with the Design-Build Work; (f) include liability for operation of unlicensed equipment on Project Site; (g) provide the broadest available coverage for damage: (i) to that particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the "property damage" arises out of those operations; or (ii) to that particular part of any property that must be restored, repaired or replaced because "your work" was incorrectly performed on it; or (iii) "Property damage" to "your work" arising out of it or any part of it and included in the "products-completed operations hazard" (i.e., exclusions in Section 2.j(5),j(6), and (1) of the CG 00 01 policy form); (h) include a cross liability and severability of interest extension with respect to each named insured such that coverage shall apply separately to each insured against whom a claim is made or lawsuit is brought, subject only to the policy limits of liability; (i) expressly include the full scope of work on all site(s) where Project Services are performed without restriction; (j) named insureds shall be the City, DBOM Contractor, City Insured Parties, and Subcontractors at any tier, for their liability arising from Design-Build Work; and (k) coverage shall be primary and noncontributory to any other insurance maintained by the named insureds. 2.4. Automobile Liability. The DBOM Contractor and its Subcontractors shall each provide and keep in force an automobile liability insurance policy on a current ISO Form CA 00 01 at the time of policy Al2-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements issuance covering liability arising from the ownership, maintenance or use of any automobile, including owned, hired or non-owned automobiles, assigned to or used in connection with the construction of the Project with a limit of liability of not be less than$1,000,000 combined single limit, per occurrence. This policy shall: (a) cover trailers or semi-trailers, including any machinery or apparatus attached thereto, including loading and unloading; (b) in the event that any covered automobile will be used to transport hazardous materials, provide FMCSA Form MCS 90, and the applicable policy shall be endorsed with ISO form CA 99 48 for the operator of the automobile; and (c) name any entity operating autos on behalf of the DBOM Contractor or a Subcontractor and in connection with the Project as named insureds. 2.5. Workers'Compensation. The DBOM Contractor and its Subcontractors shall provide and keep in force statutory workers' compensation insurance (including, if applicable, coverage or endorsements for Occupational Disease Benefits, Voluntary Compensation and Disability benefits, Jones Act and U.S. Longshoremen's and Harbor Worker's Act). The insurance shall provide limits required by the applicable workers' compensation statute and contain an "other states endorsement" if applicable. 2.6. Employers'Liability. The DBOM Contractor and its Subcontractors shall provide and keep in force employer's liability insurance having coverage limits of$1,000,000 for each accident, $1,000,000 for disease (each employee), and $1,000,000 for disease (policy limit). 2.7. Contractors Pollution Liability. The City shall obtain and keep in force for the benefit of the DBOM Contractor and its Subcontractors, a contractors pollution liability insurance policy for direct damage, consequential loss or damage (including clean-up and restoration costs both on-site and off-site), arising from a pollution event related to the Design-Build Work in an amount not less than $5,000,000 per claim and in aggregate. The City and City Insured Parties shall be included as additional insureds. Such insurance shall be maintained (by renewal or extended reporting period) for a period of not less than 10 years following the Acceptance Date or the Termination Date, whichever occurs first. 2.8. Aircraft Liability Insurance. Should aircraft or unmanned aviation vehicles be utilized in connection with the Project, the owner/operator of such aircraft shall provide aircraft liability insurance, in addition to the required regulatory and license documents. This insurance shall: (a) provide limits of $2,000,000 per occurrence and aggregate for operation of unmanned aircraft/drones; (b) name the City and City Insured Parties as additional insureds; and (c) provide limits of $2,000,000 per occurrence and aggregate for operation of manned aircraft. A 12-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements 2.9. Contractors Tools and Equipment. The DBOM Contractor and its Subcontractors shall obtain and keep in force whatever insurance the DBOM Contractor deems necessary for protection against loss of owned, rented, or borrowed capital equipment and tools, including, but not limited to, any tools, equipment, scaffolding, trailers, cranes, towers, and forms owned, rented, or borrowed by the DBOM Contractor or its Subcontractors. 2.10. Project-Specific Excess/Umbrella Liability. The City shall obtain and keep in force excess or umbrella liability insurance with coverage at least as broad as the general liability insurance required by Section 2.3 of this Appendix. Coverage shall be provided in the form of an owner-controlled insurance program. Such coverage shall be maintained for a period of not less than 10 years following the Acceptance Date or the Termination Date, whichever occurs first. This insurance shall: (a) provide limits to the DBOM Contractor and Subcontractors at any tier of not less than $50,000,000 per occurrence, $50,000,000 aggregate; (b) include all parties who are named insureds, and/or additional insureds on any policy of underlying insurance, to the same extent as the underlying insurance; (c) include a duty to defend additional insureds and shall state that the coverage afforded to the additional insureds is primary and noncontributory to any other insurance maintained by the additional insureds; and (d) schedule the wrap-up liability insurance specified in Section 2.3 of this Appendix as an underlying policy. 3. INSURANCE DURING THE OPERATION AND MAINTENANCE PERIOD The City and DBOM Contractor shall obtain and keep in force, or cause to be obtained and kept in force, throughout the Operation and Maintenance Period the following policies of insurance, in accordance with the terms of this Section 3, where identified. Evidence of such insurance shall be provided as specified Section 6. Unless otherwise specified in this Appendix, each policy shall be obtained on or prior to the Acceptance Date. 3.1. Property. The City shall obtain "All risk" property insurance on a replacement cost basis (not subject to coinsurance or obligation to rebuild)for the Full Insurable Value insuring all buildings, improvements, furnishings and equipment for the Facility. Such insurance shall: (a) provide coverage for the perils of theft and vandalism; (b) include coverage for natural catastrophes including, but not limited to, flood/water intrusion, earth movement including earthquake, named storms and/or sudden change of temperature, and sublimits for flood and earth movement including earthquake shall be no less than $10,000,000 and $25,000,000 per occurrence, respectively; (c) include coverage for damage resulting from building collapse; (d) include extension for debris removal with a $5,000,000 limit; Al2-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements (e) include the DBOM Contractor as loss payee; (f) serve as primary and not require pro-rata sharing or contribution of any loss with any insurer of any other named insured or loss payee; and (g) provide ordinance or law coverage with no sublimit for the undamaged portion of the building and not less than $10,000,000 for demolition and increased cost of repair or replacement. 3.2. Equipment Breakdown. The City shall obtain equipment breakdown insurance on covered objects forming part of Facility against internal forces such as but not limited to power surges, electrical shorts/arching, or mechanical breakdown, motor burnout or operator error for Full Insurable Value. Loss payees under this policy shall include the DBOM Contractor at time of loss. 3.3. Business Interruption Insurance. The City shall obtain business interruption coverage for loss of anticipated revenue including debt servicing and economic additional expenditures necessarily and reasonably incurred for the purpose of avoiding or reducing loss of revenue of the DBOM Contractor arising from loss or damage covered by property and/or equipment breakdown insurances effected in accordance with Sections 3.1 (Property) and 3.2 (Equipment Breakdown) of this Appendix with a period of indemnity of twelve months after a 30 day deductible period. Such insurance shall: (a) provide coverage for extra and expediting expenses with a sublimit of not less than $25,000,000; (b) provide coverage for changes in ordinance or law with a sublimit of not less than $2,000,000; (c) provide coverage for utility service interruptions with a sublimit of not less than $5,000,000; (d) provide coverage for DBOM Contractor computer equipment and data restoration expense with a sublimit of not less than $1,000,000; (e) include the DBOM Contractor as loss payee; and policy shall be primary and not require pro-rata sharing or contribution of any loss with any insurer of any other named insured or loss payee. 3.4. Commercial General Liability. The DBOM Contractor and its Subcontractors shall each provide and keep in force commercial general liability insurance on the latest version of ISO Form CG 00 01 at the time of policy issuance, or equivalent reasonably acceptable to the City, for liability related to bodily injury (including death), property damage (including loss of use) and/or personal injury arising from activities during the Operation and Maintenance Period. Such insurance shall: (a) provide limits of $1,000,000 per occurrence, $1,000,000 aggregate for products/completed operations and $2,000,000 general aggregate for other than products/completed operations; Al2-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements (b) provide defense in addition to policy limits; (c) include blanket contractual liability; (d) include products and completed operations period no less than 36 months; (e) employees included as insureds; (f) coverage territory to be worldwide, with service of suite in Canada or USA; (g) contain no explosion, collapse or underground exclusion; (h) not exclude blasting, demolition, excavating, under-pinning, pile-driving, shorting, caisson work, below-ground surface work and similar operations; (i) include a cross-liability and severability of interest clause with respect to each insured; 6) include the City and City Insured Parties as additional insured; and (k) include a duty to defend additional insureds and shall state that the coverage afforded to the additional insureds is primary and noncontributory to any other insurance maintained by the additional insureds. 3.5. Automobile Liability. The DBOM Contractor and its Subcontractors shall each provide and keep in force an automobile liability insurance policy on a current ISO Form CA 00 01 at the time of policy issuance covering liability arising from the ownership, maintenance or use of any automobile, including owned, hired or non-owned automobile, assigned to or used in connection with the construction of the Project. Such coverage shall: (a) cover and trailers or semi-trailers, including any machinery or apparatus attached thereto, including loading and unloading; (b) provide a limit of liability of$5,000,000 per accident combined single limit; and (c) in the event that any covered automobile will be used to transport hazardous materials, provide FMCSA Form MCS 90, and the applicable policy shall be endorsed with ISO form CA 99 48 for the operator of the automobile; 3.6. Workers' Compensation. The DBOM Contractor and its Subcontractors shall each provide and keep in force statutory workers' compensation insurance (including, if applicable, coverage or endorsements for Occupational Disease Benefits, Voluntary Compensation and Disability benefits, Jones Act and U.S. Longshoremen's and Harbor Worker's Act). The insurance shall (a) provide limits required by the applicable workers' compensation statute and contain an "other states endorsement" if applicable. 3.7. Employers'Liability. The DBOM Contractor and its Subcontractors shall each provide and keep in force employer's liability insurance having coverage limits of$1,000,000 for each accident, $1,000,000 Al2-7 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements for disease (each employee), and$1,000,000 for disease (policy limit). The limits may be satisfied with a combination of primary employers'liability and excess liability insurance. 3.8. Excess/Umbrella Liability. The DBOM Contractor shall provide and keep in force, or cause to be provided and kept in force, excess or umbrella liability insurance with coverage at least as broad as the general liability, automobile liability, and employer's liability insurance required herein for the Term. This insurance shall: (a) provide limits to the DBOM Contractor of $15,000,000 per occurrence and in aggregate; (b) shall afford insured status to all individuals and entities required to be insureds on the underlying insurance policies, to the same extent as the underlying insurance; and (c) include a duty to defend additional insureds and shall state that the coverage afforded to the additional insureds is primary and noncontributory to any other insurance maintained by the additional insureds. 3.9. Pollution Legal Liability (Fixed Site). The DBOM Contractor shall provide pollution legal liability insurance, in an amount of $5,000,000 for liability arising from bodily injury and property damage, consequential loss or damage due to escape of pollutants from the site including necessary on-site and off-site clean- up costs, subsequent to the commencement of the Operation and Maintenance Period. Coverage shall be extended to include underground and above ground storage tanks (as applicable). The City and City Insured Parties shall be additional insureds. 3.10. Contractor's Pollution Liability. DBOM Contractor shall provide Contractor's Pollution Liability insurance for covering bodily injury and property damage and remediation costs for any accidental pollution condition related to the DBOM Contractor's operations, actions, inactions and completed operations associated with any work performed by the DBOM Contractor and its Subcontractors, employees, agents or representatives subsequent to the commencement of the Operation and Maintenance Period. The insurance shall: (a) provide limits of$5,000,000 per claim and annual aggregate; (b) include the City and City Insured Parties as additional insureds; and (c) include DBOM Contractor as additional insured. 3.11. Directors and Officers. The DBOM Contractor shall provide Director's and officers' legal liability and corporate indemnification insurance providing coverage for any one occurrence or claim of$5,000,000 per occurrence and in annual aggregate, subject to a sublimit of $2,000,000 for any employment practices liability, crime or fiduciary matters. Al2-8 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements 3.12. Employee Dishonesty. The DBOM Contractor shall provide employee theft (crime) insurance against the fraudulent/dishonest acts of employees of the DBOM Contractor, including additional coverage for inside the premises - theft of money and securities and outside the premises, money orders and counterfeit paper currency, forgery or alteration, computer fraud and funds transfer fraud, expenses incurred to establish amount of covered loss, and credit, debit or charge card forgery with coverage for any one occurrence or claim of$1,000,000. This coverage shall include clients coverage and loss resulting from impersonation fraud (social engineering). 3.13. Cyber 86 Network Liability. The DBOM Contractor shall provide cyber 86 network liability insurance subject to a limit of$5,000,000 each occurrence and annual aggregate for operator's liability arising from media, breach of security/privacy, or network interruption. Events related to ransomware or extortion are sublimited to $2,500,000 per occurrence and in annual aggregate with a deductible of $500,000 per occurrence. 3.14. Other. Any other form of insurance and with such limits, in such form, in amounts and for risks as the City, acting reasonably, may require from time to time. The Service Fee shall be adjusted to reflect the cost of any such additionally required insurance. 4. FULL INSURABLE VALUE For the purposes of this Appendix, "Full Insurable Value" means the limit of insurance available under the specified policy. Full Insurable Value is based on the estimated replacement cost of any building, improvement, equipment, or other tangible property forming part of the work at the Project Site at (a) the time the insurance is initially effective, and (b) thereafter by independent appraisal arranged by the City at least once every 60 months and at the City's expense. 5. GENERAL POLICY REQUIREMENTS 5.1. Policy Requirements. Each policy of insurance required under this Appendix shall: (a) be issued by an insurer that: (1) is admitted in the State, or if not admitted in the State an insurer that makes any placement in accordance with the requirements applicable to surplus line placements; (2) has a Best's Financial Strength Rating of"A-" or better, and a Financial Size Category of"Class VII" or better in the latest evaluation of A.M. Best Company, Inc., or a comparable rating from any other nationally- recognized rating agency or a qualified self-insured program or trust,when the City grants specific approval for an exception; and (3) is mutually acceptable to the City and DBOM Contractor, acting reasonably (a"Qualified Insurer"); Al2-9 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements (b) be in a form approved by the City, such approval not to be unreasonably withheld; (c) be non-contributing with and shall apply only as primary and not excess to any other insurance, self-insurance, or other risk financing program available to the City; and (d) contain an undertaking by the insurers to notify the named insured of any policy required by this Appendix with (i) 30 days written notice before any material change, lapse, cancellation or termination and (ii) 10 days written notice before any cancellation or termination for nonpayment of premium. 5.2. Waivers of Subrogation. The DBOM Contractor shall ensure that the insurance it obtains in accordance with the requirements of this Appendix, excluding professional liability insurance, includes a waiver of subrogation in favor of the City and City Insured Parties, including damages that are covered by any owner controlled insurance program. The DBOM Contractor shall require that all Subcontractors obtain waivers of subrogation waivers in favor of the City and City Insured Parties for all insurance they are required to provide in accordance with this Appendix. A waiver of subrogation shall be effective as to a person or entity even though that person or entity would otherwise have a duty of indemnification, contractual or otherwise, did not pay the insurance premium directly or indirectly, and whether or not the person or entity had an insurable interest. 5.3. City Acceptance of Insurance. No acceptance or approval of any insurance by the City shall be construed as relieving or excusing any other party, or their surety from any liability or obligation imposed upon any of them by the provisions of this DBOM Agreement. Nothing herein shall be construed as permitting the DBOM Contractor or any Subcontractor to allow the insurance coverage required by this DBOM Agreement to lapse. 5.4. Subcontractors. The DBOM Contractor shall require all Subcontractors to maintain, during the term of this DBOM Agreement, business auto liability insurance, workers'compensation and employers' liability insurance as described in this Appendix. The City may request a certificate of insurance from any Subcontractor for review at any time during the Term, acting reasonably in the manner indicated in Section 6 (Evidence of Insurance) of this Appendix. 5.5. Deductibles and Self-Insured Retentions. The DBOM Contractor shall disclose deductibles and self-insured retentions in excess of the following (which shall be subject to the City's written approval): (i) any deductible under a controlled insurance program, contractors pollution liability policy, or any property insurance policy that exceeds $500,000; (ii) any self-insured retention under a pollution or professional liability/indemnity policy that exceeds $1,000,000; and (iii) any self-insured retention of $500,000 or greater for any other Required Insurance. Any deductible or self-insured retention amounts elected by the City, DBOM Contractor or any Subcontractors or imposed by the City's, DBOM Contractor's or any Subcontractor's insurers shall be the sole responsibility of the party purchasing such insurance are not chargeable as expenses, other than as provided for in Section 15.1(F) (Insurance Deductibles and Exceedances) of this DBOM Agreement. Al2-10 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements 5.6. Required Insurance Issued on a "Claims Made" Basis. If any Required Insurance purchased by the DBOM Contractor or any Subcontractor has been issued on a"claims made"basis, the purchaser of such claims made coverage must comply with the following additional conditions. The limits of liability and the extensions to be included remain the same. The DBOM Contractor must either: (a) agree to provide certificates of insurance to the City, within 5 business days of a written request, evidencing continuity of the above coverages for a minimum period of three (3) years after termination, unless a longer period is specified in this Appendix; or (b) purchase an extended (minimum three (3) years) reporting period endorsement (unless a longer period is specified in this Appendix) for each such "claims made" policy in force as of the date of termination and evidence the purchase of this extended reporting period endorsement by means of a certificate of insurance. 6. EVIDENCE OF INSURANCE Upon the issuance, renewal, extension, or replacement of a policy of insurance required herein, each party to this DBOM Agreement shall promptly deliver acceptable evidence of insurance to those with an insurable interest in the required insurance. This may include, but is not limited to the City, DBOM Contractor and/or Subcontractors. Acceptable forms of insurance evidence include binder(s), certificate of insurance or copies of policy declarations (including relevant endorsements). Each party, acting reasonably, may redact proprietary information from the copy of the policies delivered to interested parties. Upon request by the City, the DBOM Contractor shall deliver proof of payment of premiums for insurance required to be effected pursuant to this Appendix. No review or approval of any insurance certificate or insurance policy by the City shall derogate from or diminish the City's rights under this DBOM Agreement. All evidence of insurance required by this Appendix should be sent in electronic form unless otherwise requested. Hardcopies may be mailed upon written request. Insurance communication to City shall be sent to: Stefan Broadus P.O. Box 369, 380 A Avenue, Lake Oswego, OR 97034 sbroadus@ci.oswego.or.us Insurance communication to DBOM Contractor shall be sent to: Kevin Shane 7001 E. Belleview Ave., Suite 100, Denver, CO 80237 kevin.shane@jacobs.com 7. SUFFICIENCY OF COVERAGE The City in no way warrants that the limits stated in this Appendix are sufficient to protect the DBOM Contractor from the liabilities that might arise out of the performance of the Project Services by the DBOM Contractor or any other DBOM Contractor Person, and DBOM Contractor may purchase such additional insurance as it determines necessary. [Remainder of Page Intentionally Left Blank] Al2-11 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements ATTACHMENT 12A OWNER CONTROLLED INSURANCE PROGRAM REQUIREMENTS With respect to the insurance described in Section 2.3 (Project-Specific Commercial General Liability) of this Appendix, the DBOM Contractor shall, and shall cause its Subcontractors to, comply with all provisions of this Attachment 12A (Owner Controlled Insurance Program Requirements). The City, as part of an Owner Controlled Insurance Program ("OCIP"), has obtained a primary commercial general liability insurance policy ("OCIP Policy"), also commonly referred to as a "Wrap Up Policy," naming it, as well as other designated construction participants, including DBOM Contractor, Subcontractors, and other eligible and enrolled trades (hereinafter collectively referred to as "Participants"), for certain insurable risks on this Project. The OCIP is administered through Paladin Risk Management (the "Program Administrator"). The OCIP Policy is specific to the Project and extends coverage to the DBOM Contractor and all eligible and enrolled Subcontractors performing Design-Build Work in connection with the Project on the property. Execution hereof by the DBOM Contractor constitutes the DBOM Contractor's agreement to enroll in such OCIP Policy and to abide and be bound by (a) all the terms, conditions, limitations, and exclusions of the OCIP Policy and (b) all the provisions and requirements of the OCIP Insurance Program Manual("Insurance Manual"as it may be amended from time to time, the "Manual"). Without in any manner modifying the OCIP Policy, enrollment in the OCIP occurs upon the issuance of a Certificate of Enrollment. Enrollment must take place prior to an occurrence for which coverage is sought under the OCIP. Eligible parties shall be enrolled in the OCIP through the Program Administrator ("Eligible Parties"). Certain parties may be ineligible for enrollment into the OCIP if their scope of Design-Build Work is of the type which would be excluded under the OCIP ("Ineligible Parties"). These Ineligible Parties shall provide insurance as set forth herein and in this DBOM Agreement. In limited circumstances, parties may be excluded from the OCIP by the City in its sole discretion ("Non-Enrolled Parties"). These Non- Enrolled Parties shall provide insurance as set forth herein and in this DBOM Agreement. The OCIP Coverages shall cover Enrolled Parties only. Enrolled Parties are: the City, DBOM Contractor and eligible Subcontractors of all tiers that enroll in the OCIP, and such other trades, persons or entities as City may designate, in its sole discretion (each party insured under the OCIP is an "Enrolled Party"). Enrolled Parties shall obtain and maintain, and shall require each of their Subcontractors of all tiers to obtain and maintain, the insurance coverage specified in this Attachment 12A (Owner Controlled Insurance Program Requirements) and in the Insurance Manual. The OCIP Coverages do not cover the following"Excluded Parties": (a) hazardous materials remediation, removal and/or transport companies and their consultants; (b) architects, surveyor, engineers, and soil testing engineers, and their consultants as it relates to their professional services unless by an insured contract; (c) vendors, suppliers, fabricators. material dealers, truckers, haulers, drivers and others who merely transport, pick up, deliver, or carry materials, personnel, parts or equipment, or any other items or persons to or from the Project site; Al2-12 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements (d) subcontractors and each of its or their respective subcontractors of all tiers that do not perform any actual labor on the Project site; and (e) any parties or entities not specifically identified in this Attachment 12A (Owner Controlled Insurance Program Requirements), as well as any parties or entities excluded by the City in its sole discretion, even if they are otherwise eligible. The DBOM Contractor agrees that Excluded Parties and parties no longer enrolled in or covered by the OCIP shall obtain and maintain, and shall require each of their subcontractors of all tiers to obtain and maintain, the insurance coverage specified in Appendix 12, except for Commercial General Liability Insurance which, in lieu, shall be commercial General Liability Insurance, written on a full occurrence policy form, primary and non-contributory to the OCIP, and covering work and operations on-premise and off-premise, with minimum limits of liability of not less than: $1,000,000 Each Occurrence $2,000,000 General Aggregate $2,000,000 Products/Completed Operations Aggregate Such insurance shall contain all standard comprehensive or commercial General liability broad form terms and conditions including coverage for liability for bodily injury, property damage, personal injury, products, contractual liability, XCU coverage (required of subcontractors involved in utility work, excavation, mechanical, electrical and/or plumbing work), and products/completed operations. Additionally, such insurance shall not contain restrictions or exclusions for subsidence or any type of earth movement, if Subcontractor's role involves excavation, residential construction of any kind, or third-party action over claims. The types of risks covered by this policy are defined and specified in the actual insurance policy. The DBOM Contractor is charged with the responsibility of obtaining from the Broker-of- Record, AssuredPartners of Oregon, a copy of the OCIP Policy for review. It is the DBOM Contractor's responsibility to obtain professional assurance and/or legal counsel regarding this insurance policy. The City makes no representations regarding the scope, adequacy, nature, quality or limits of the OCIP and the DBOM Contractor expressly acknowledges the lack of reliance upon any representations made by the City or its representatives regarding the scope, adequacy, nature, quality or limits of the insurance provided by the OCIP Policy. The DBOM Contractor shall hold City and its representatives, including, but not limited to the Program Administrator, insurance brokers and/or agents, free and harmless from any and all claims asserting or alleging that the scope, type and/or amount of coverage provided under the OCIP is inadequate or insufficient. The OCIP is intended to be the primary source of coverage for the risks covered thereunder and shall assume primary position to the DBOM Contractor's insurance in the areas of risk covered by the OCIP. The City shall be responsible for payment of insurance premiums for the OCIP Policy. The DBOM Contractor and all enrolled Subcontractors are not permitted to submit any costs related to insurance that are otherwise addressed by the OCIP policy; the City reserves the right to audit all submittals for this purpose. The OCIP requires satisfaction of a per occurrence deductible in an amount of not more than $50,000. The DBOM Contractor shall, and shall require its Subcontractors to, contribute towards the deductible in the manner set forth herein. Al2-13 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements In the event of an occurrence during the course of construction (prior to Acceptance of the Project) or after the course of construction (during the policy's statute of repose), which requires the City to satisfy all or any portion of the deductible/SIR and which arises out of the Design-Build Work by or for the DBOM Contractor or Subcontractor, the DBOM Contractor, if "involved", and each "involved" Subcontractor, shall contribute, but only to the same extent for which DBOM Contractor or Subcontractor of any tier, or anyone for whom they are responsible cause or contribute to the underlying occurrence giving rise to the loss, up to the maximum amount of the deductible due. If the amount collected hereunder exceeds the amount actually expended in satisfaction of the deductible, the contribution from the DBOM Contractor and each Subcontractor will be reduced by a proportionate amount so that the total amount collected equals the actual deductible amount incurred. "Involved" includes, but is not limited to, occurrences where an employee of contractor, a Subcontractor or third party is injured on the job site and sues for a claim that is covered by the OCIP or if the work or property of the City, DBOM Contractor, a Subcontractor or third party is damaged in any way arising out of or in connection, directly or indirectly, with the scope of work of the DBOM Contractor or Subcontractor. This allocation of the deductible is not an indemnity claim and shall remain uninsured by the OCIP. It is a contractual allocation of the mutual obligations of the insureds under the OCIP Policy. Upon written notice from the City of the required deductible contribution amount provided above and the basis therefore, DBOM Contractor shall provide said sum to City within thirty (30) days after receipt of such notice. DBOM Contractor and Subcontractors and sub tier contractors who are enrolled in the OCIP shall, prior to commencement of their work and prior to entry onto the Project, provide evidence of all applicable Required Insurance coverages as set forth in Appendix 12 and meeting all requirements set forth in Appendix 12. The DBOM Contractor attests that its general liability policy does not include any exclusion of coverage for the DBOM Contractor's work and operations away from and/or adjacent to the Project (off-site), such as its own premises, work performed by others on DBOM Contractor's behalf, and third party claims arising outside the Project. The DBOM Contractor's, Subcontractors' and their sub tier contractors' enrollment into the OCIP is mandatory unless specifically stated otherwise by the OCIP Policy. The DBOM Contractor shall take all necessary steps to cooperate with the Program Administrator to enroll all Subcontractors and their sub tier contractors into the OCIP. The DBOM Contractor assumes full responsibility for the Subcontractors and sub tier contractors and the work that they do. DBOM Contractor assumes full responsibility for any and all Subcontractors' and sub tier contractors' compliance with and, where required, the submission to City of all insurance requirements set forth in this DBOM Agreement and the Insurance Manual. Notwithstanding Article 25 (Indemnification) of this DBOM Agreement, the City, DBOM Contractor and Subcontractors are Participants under the OCIP Policy. The indemnity requirements and obligations set forth in Article 25 (Indemnification) of this DBOM Agreement shall apply in the event the OCIP Policy does not in fact fully protect, indemnify and defend the City Indemnitees. The obligations of the DBOM Contractor pertaining to indemnification under the indemnity requirements and obligations set forth in Article 25 (Indemnification) of this DBOM Agreement are excess to any such OCIP Insurance and shall not take effect until and unless the insurance provided under the OCIP is exhausted, insufficient, inapplicable to the particular Al2-14 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 12 DBOM Agreement Insurance Requirements claims or otherwise unavailable. In the event that the OCIP is exhausted, inapplicable or unavailable, the DBOM Contractor's obligations under the indemnity requirements and obligations set forth in Article 25 (Indemnification) of this DBOM Agreement shall immediately be triggered.The DBOM Contractor's obligations to defend and indemnify the City and other City Indemnitees shall exist whether or not there is available insurance coverage. The DBOM Contractor and its insurance providers shall waive any and all of its and their rights of subrogation against the City Indemnitees. [Remainder of Page Intentionally Left Blank] Al2-15 3953578.11 043463 APPENDIX 13 PERFORMANCE GUARANTEES AND DEDUCTIONS 3953578.11 043463 APPENDIX 13 PERFORMANCE GUARANTEES AND DEDUCTIONS 1. PURPOSE This Appendix sets forth certain additional specific standards, requirements and Deductions associated with the Performance Guarantees identified in Article 9 (Performance) of this DBOM Agreement. 2. EFFLUENT GUARANTEE Except as relieved by a Relief Event, the Effluent Guarantee shall include all requirements set forth in Table 13-1, as well as any additional requirements imposed by the NPDES Permit, excluding Effluent temperature requirements, or otherwise under Applicable Law. Table 13-1 Effluent Guarantee Performance Parameter Value Sampling Type Frequency DRY SEASON REQUIREMENTS (May 1 - October 31) 5-day Biochemical Oxygen Demand ≤ 10 24-hour Daily (BOD5), monthly, mg/1 composite 5-day Biochemical Oxygen Demand ≤ 15 24-hour Daily (BOD5), 7-day average, mg/1 composite 5-day Biochemical Oxygen Demand ≥ 85 24-hour Daily (BOD5), monthly average, removal composite efficiency, % Total Suspended Solids, monthly ≤ 10 24-hour Daily average, mg/1 composite Total Suspended Solids, 7-day average, ≤ 15 24-hour Daily mg/1 composite Total Suspended Solids, monthly ≥ 85 24-hour Daily average, removal efficiency, % composite pH 6.0 - 9.0 Grab Daily Total Phosphorus, monthly average, ≤ 0.3 24-hour Daily mg/1 as phosphorus composite Ammonia, monthly average, mg/1 ≤ 1 24-hour Daily composite A13-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 13 DBOM Agreement Performance Guarantees and Deductions Performance Parameter Value Sampling Type Frequency E. Coli, organisms per 100 ml, monthly ≤ 126 Grab Daily geometric mean If a single sample exceeds 406 organisms/100 mL, the permittee may take at least 5 consecutive re-samples at 4-hour intervals beginning within 28 hours after the original sample was taken. A geometric mean of the 5 re- samples that is less than or equal to 126 E. coli organisms/100 mL demonstrates compliance with the limit. E. Coli, organisms, maximum single ≤ 406 Grab Daily sample value, organisms per 100 ml If a single sample exceeds 406 organisms/100 mL, the permittee may take at least 5 consecutive re-samples at 4-hour intervals beginning within 28 hours after the original sample was taken. A geometric mean of the 5 re- samples that is less than or equal to 126 E. coil organisms/100 mL demonstrates compliance with the limit. WET SEASON REQUIREMENTS (November 1-April 3031) 5-day Biochemical Oxygen Demand ≤ 30 24-hour Daily (BOD5), 30-day average, mg/1 composite 5-day Biochemical Oxygen Demand ≤ 45 24-hour Daily (BOD5), 7-day average, mg/1 composite 5-day Biochemical Oxygen Demand ≥ 85 24-hour Daily (BOD5), monthly average, removal composite efficiency, % Total Suspended Solids, 30-day ≤ 30 24-hour Daily average, mg/1 composite Total Suspended Solids, 7-day average, ≤ 45 24-hour Daily mg/1 composite Total Suspended Solids, monthly ≥ 85 24-hour Daily average, removal efficiency, % composite pH 6.0 - 9.0 Grab Daily A13-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 13 DBOM Agreement Performance Guarantees and Deductions Performance Parameter Value Sampling Type Frequency E. Coli, organisms per 100 ml, monthly ≤ 126 Grab Daily geometric mean If a single sample exceeds 406 organisms/100 mL, the permittee may take at least 5 consecutive re-samples at 4-hour intervals beginning within 28 hours after the original sample was taken. A geometric mean of the 5 re- samples that is less than or equal to 126 E. coli organisms/100 mL demonstrates compliance with the limit. E. Coli, organisms, maximum single ≤ 406 Grab Daily sample value, organisms per 100 ml If a single sample exceeds 406 organisms/100 mL, the permittee may take at least 5 consecutive re-samples at 4-hour intervals beginning within 28 hours after the original sample was taken. A geometric mean of the 5 re- samples that is less than or equal to 126 E. coil organisms/100 mL demonstrates compliance with the limit. ** The DBOM Contractor shall not be required to meet the total phosphorous or ammonia requirements set forth in this DBOM Agreement during the Operation and Maintenance Period unless the City directs the DBOM Contractor to do so pursuant to a Capital Modification in accordance with Article 11 (Capital Modifications and Operation and Maintenance Services Changes). 3. DETERMINATION OF AN ODOR INCIDENT FOR PURPOSES OF THE ODOR GUARANTEE The thresholds for determining an "Odor Incident" are any of the following: (a) Based on any odor sampling by the DBOM Contractor or the City that exceeds the maximum allowable stack discharge H2S concentration that would result in exceeding a value of five dilution-to-threshold (D/T) at the Project Site's property line as determined by dispersion modeling (AERMOD) for the highest one-hour average and as documented in the Odor Control Plan; (b) Based on any odor sampling by the DBOM Contractor or the City that exceeds the maximum allowable H2S concentration, as documented in the Odor Control Plan, or detection of odors at levels higher than 5 D/T, as measured at the Project Site's property line; (c) Three or more independent reports within a 24 hour period to either the DBOM Contractor or the City from members of the surrounding community of a perceptible odor emanating from the Project as investigated and confirmed by the City. The City's investigation will consider the nature of the complaints, potential conflicts of interest from the complainants, conditions experienced upon a site A13-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 13 DBOM Agreement Performance Guarantees and Deductions inspection, and/or the results of the DBOM Contactor's odor testing pursuant to the Response Plan as described in Section 4 (Response Plan) of Appendix 11 (Odor Control Standard and Odor Control Plan) if made available within one week of the initial complaint; or (d) Confirmation by either of the parties that there is odor at the Project Site's property line emanating from Wastewater Treatment Facility sources and not from an off-site source; provided, however, that such confirmation shall not constitute an Odor Incident if arising on the transportation routes from the active transportation of Grit and Screenings from the Wastewater Treatment Facility. The investigation will consider conditions experienced upon a site investigation and/or available reports and odor sampling data. 4. RESIDUALS MANAGEMENT GUARANTEE 4.1. Grit and Screenings. The DBOM Contractor shall treat, transport and dispose of all Grit and Screenings in accordance with Applicable Law and subsection 9.6(E) (Transportation and Disposal of Grit and Screenings) of this DBOM Agreement. The DBOM Contractor shall transport all Grit and Screenings to a Qualified Residuals Disposal Facility in a safe and environmentally sound manner and in accordance with Applicable Law. The DBOM Contractor may utilize more than one Qualified Residuals Disposal Facility for the disposal of Grit and Screenings; provided, however, that each disposal site utilized by the DBOM Contractor must be a Qualified Residuals Disposal Facility as defined in Section 1.1 (Definitions) of this DBOM Agreement. The DBOM Contractor shall provide evidence satisfactory to the City, from time to time as requested, that the intended disposal location is a Qualified Residuals Disposal Facility in accordance with this DBOM Agreement. The DBOM Contractor may dispose of Grit and Screenings through a beneficial reuse application other than a beneficial reuse facility only with the express written approval of the City. Any revenues generated from the beneficial reuse of Grit and Screenings shall be for the account of the City. 4.2. Sludge and Scum Requirements and Transport. All Sludge and Scum shall meet the requirements set forth in Section 5(b) (Sludge and Scum Requirements-Sludge and Scum Characteristics) of Appendix 4 (Design and Construction Requirements) and be trucked to the Columbia Boulevard Wastewater Treatment Facility ("CBWTF") for stabilization and disposal by Portland in accordance with subsection 9.6(D) (Sludge and Scum Transportation and Off-Loading) of this DBOM Agreement. 4.3. Sludge and Scum Sampling. All sampling of Sludge and Scum transported to the CBWTF to demonstrate compliance with the Residuals Management Guarantee shall be conducted by the DBOM Contractor in accordance with the Contract Standards and a sampling plan developed by the DBOM Contractor and approved by the City(and subject to review by Portland). The sampling plan shall document the location of online monitoring, including frequency and method of instrument calibration, along with the location, frequency, volume, sample storage procedures and method of analysis for each grab sample. Sampling will include: (a) Total solids ("TS") and volatile solids ("VS") concentrations, collected weekly via a grab sample, of the combined TWAS and Scum sampling tap on the sludge loadout A13-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 13 DBOM Agreement Performance Guarantees and Deductions pump discharge line at the Wastewater Treatment Facility or other suitable location that provides a representative sample of the trucked material. (b) Rotary drum thickener process performance data(based on online monitoring and recording): (i) Daily total feed volume; and (ii) Total solids concentration (as monitored/measured by the DBOM Contractor for process control; number will not include scum). 4.4. Reporting. Monthly Sludge and Scum data shall be documented in a monthly "Trucked Solids Report" consistent with Portland's Hauled Sludge Management Plan requirements and delivered to the City and Portland on the 5th day of each month. The contents of the monthly Trucked Solids Report will include: (a) Daily and monthly total haul volumes from the Wastewater Treatment Facility sludge loadout flow meter; (b) Number of truck trips per day; (c) Daily train delay hours at the CBWTF entrance; (d) VS and TS concentrations from weekly grab sample and the date of sample; (e) Rotary drum thickener process performance monitoring data: (i) Daily total feed volume; and (ii) TS concentration (as monitored/measured by the DBOM Contractor for process control; number will not include scum); and (f) Signature/certification by the Operation and Maintenance Supervisor that the numbers are correct to the best of their knowledge. 5. LIQUIDATED DAMAGES The DBOM Contractor shall be subject to liquidated damages for certain failures to meet the Performance Guarantees, as identified in Table 13-2. All dollar amounts referenced in this Appendix shall be Index-Linked. [Table follows on next page] A13-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 13 DBOM Agreement Performance Guarantees and Deductions Table 13-2 Performance Guarantee Liquidated Damages Liquidated Damages for Noncompliance Noncompliance Event 1 (Index-Linked) Exceeding maximum daily, daily range or S2,000 maximum single value Effluent performance value requirement, concentration for any constituent listed in Table 13-1 or otherwise included in the NPDES Permit, per day Exceeding non-detect Effluent performance value $3,000 requirement, concentration for any constituent listed in Table 13-1 or otherwise included in the NPDES Permit, per exceedance Exceeding weekly average Effluent performance $5,000 value requirement, concentration for any constituent listed in Table 13-1 or otherwise included in the NPDES Permit, per week Exceeding monthly average or monthly median $7,000 Effluent performance value requirement, concentration for any constituent listed in Table 13-1 or otherwise included in the NPDES Permit, per month Violations (not caused by a Relief Event) $50,000 Requiring Public Notification 2 Odor Citation See subsection 9.3(H) of DBOM Agreement Sustained Odor Condition See subsection 9.3(L) of DBOM Agreement 1 All liquidated damages are per occurrence per parameter and are additive. These damages do not include other regulatory penalties that may apply. All regulatory penalties are the obligation of the DBOM Contractor. 2 Public notification refers to a discharge event from the Project that causes or has the potential to cause a public health impact, water quality problem or an impact on use of the reclaimed water or on the receiving body of water and for which the DBOM Contractor is required by Applicable Law or ordered by a Governmental Body to issue a public notification. [Remainder of Page Intentionally Left Blank] A13-6 3953578.11 043463 APPENDIX 14 EXAMPLE CALCULATION OF SERVICE FEE 3953578.11 043463 APPENDIX 14 EXAMPLE CALCULATION OF SERVICE FEE 1. PURPOSE The following examples illustrate the calculation of the Service Fee paid to the DBOM Contractor in accordance with Article 17 (Service Fee and Other Payments). All capitalized terms have the meaning set forth in Section 1.1 (Definitions) of the DBOM Agreement. Interpretation of this Appendix is subject to Section 1.2 (Interpretation) of the DBOM Agreement. The cost figures used in these sample calculations utilize hypothetical index values and are for illustrative purposes only. As provided in Section 17.2 (Service Fee Formula) of the DBOM Agreement, the Service Fee calculation is based on the following formula: SF = OMC + RC - DC +/- EI where, SF = Service Fee OMC = Operation and Maintenance Charge RC = Reimbursable Costs Charge DC = Deductions Credit EI = Extraordinary Items Charge or Credit 2. INDEX-LINKED Index-Linked has the meaning set forth in Section 1.1 (Definitions) of the DBOM Agreement and is determined as follows. Index-LinkedN = (0.572 x (ECI-TCN/ECI-TCN_1) + 0.316 x (PPI-GPMEN/PPI-GPMEN_ i) + 0.054 x (PPI-ICN/PPI-ICN_1) + 0.044 x (PPI-WCN/PPI-WCN-1) + 0.014 x (PPI- TTLN/PPI-TTLN_J) + 0.01632) x Index-LinkedN_1 Where, N = The period from the immediately preceding June to the previous June (except that for the initial July 1, 2027 adjustment, it will be for June 2027 to December 2025). N-1 = The same annual period one year earlier. Table 14-1 Indices 12-2025 6-2026 6-2027 6-2028 6-2029 6-2030 6-2031 Name / Series ID Weight Value Value' Value2 Value2 Value2 Value* Value* ECI: Total 57.2% 184.843 190.442 193.244 199.041 205.013 211.163 217.498 Compensation A14-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 14 DBOM Agreement Example Calculation of Service Fee (Utilities)/ CIU2014400000000I PPI: General Purpose Machinery 31.6% 371.907 377.275 388.810 400.474 412.489 424.864 437.610 &Equipment / WPS114 PPI: Industrial 5.4% 292.404 343.719 354.031 364.651 375.591 386.859 398.465 Chemicals / WPU061 PPI: Waste Collection 4.4% 200.956 206.484 210.089 216.392 222.884 229.571 236.458 / PCU562111562111 PPI: Truck&Trailer Leasing / 1.4% 132,407 132.422 136.910 141.017 145.248 149.605 154.093 WPU442102 1 Preliminary(to be verified) 2 Hypothetical Inflation Index Lookup: https://data.bls.gov/series-report Year 2026 (NTP through June 2026) Index-Linked Calculation: Prorated days from 12/2025 = 31 + 28 + 31 +30 + 31 + 30 = 181 Days. Index-Linked26 = (0.572*(190.442/184.843) + 0.316*(377.275/371.907) + 0.054*(343.719/292.404) + 0.044*(206.484/200.956) + 0.014*(132.422/132.407) + 0.01632) * (181/365) * 1.0 Index-Linked2o26 = 1.0267. (Note that the adjustment factor is prorated to account for partial year.) Year 2027 (July 2026 through June 2027) Index-Linked Calculation: Index-Linked2027 = (0.572*(193.244/190.442) + 0.316*(388.810/377.275) + 0.054*(354.031/343.719) + 0.044*(210.089/206.484) + 0.014*(136.910/132.422) + 0.01632) * 1.0267 Index-Linked2o27 = 1.0649. Year 2028 (July 2027 through June 2028) Index-Linked Calculation: Index-Linked2028 = (0.572*(199.041/193.244) + 0.316*(400.474/388.810) + 0.054*(364.651/354.031) + 0.044*(216.392/210.089) + 0.014*(141.017/136.910) + 0.01632) * 1.0649 Index-Linked2o2s = 1.1143. Year 2029 (July 2028 through June 2029) Index-Linked Calculation: Index-Linked28 = (0.572*(205.013/199.041) + 0.316*(412.489/400.474) + 0.054*(375.591/364.651) + 0.044*(222.884/216.392) + 0.014*(145.248/141.017) + 0.01632) * 1.1143 A14-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 14 DBOM Agreement Example Calculation of Service Fee Index-Linked2o29 = 1.1659. Year 2030 (July 2029 through June 2030) Index-Linked Calculation: Index-Linked2oso = (0.572*(211.163/205.013) + 0.316*(424.864/412.489) + 0.054*(386.859/375.591) + 0.044*(229.571/222.884) + 0.014*(149.605/145.248) + 0.01632) * 1.11690 Index-Linked2oso = 1.2199. Year 2031 (July 2030 through June 2031) Index-Linked Calculation: Index-Linked2031 = (0.572*(217.498/211.163) + 0.316*(437.610/424.864) + 0.054*(398.465/386.859) + 0.044*(236.458/229.571) + 0.014*(154.093/149.605) + 0.01632) * 1.2199 Index-Linked2031 = 1.2764. 3. OPERATION AND MAINTENANCE CHARGE The OMC is equal to the sum of the Ordinary Operation and Maintenance Component (OOMC), Pass-Through Electricity Component (PTEC) and Sludge Transportation to Columbia Boulevard (STCB): OMC = OOMC + PTEC + STCB A. Ordinary Operation and Maintenance Charge Component (OOMC): i. OOMC12-2o25 = $4,670,000 (in December 2025 Dollars). Assumed Acceptance Date/Commencement of Operations and Maintenance Period: 4/17/30. ii. Contract Year 1 (April 2030 -June 2030) example calculation: OOMCcy1-Annual = OOMC12-2025 * Index-Linked2oso OOMC CY1-Annual = $4,670,000 * 1.2199 = $5,696,933 Contract Year 1 Prorated OOMC: Contract Year 1 (CY1) commencement date: April 17, 2030. Contract Year 1 Days in Contract Year = 14 + 31 + 30 = 75 Days. OOMCcyi = OOMCCY1-Annual * Days in Contract Year / 365 Days per Year OOMCcyi = $5,696,933 * 75 / 365 = $1,170,603 Contract Year 1 OOMC Billing Period: Billing PeriodcYi Month = Days in Billing Period / Days in CY1 * OOMC1 Billing PeriodcYl April = 14 / 75 * $1,170,603 = $218,512 A14-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 14 DBOM Agreement Example Calculation of Service Fee Billing Periodcyi May = 31 / 75 * $1,170,603 = $482,849 Billing Periodcyi June = 30 / 75 * $1,170,603 = $468,241 iii. Contract Year 2 (CY2) (July 2030 -June 2031) example calculation: OOMCcy2 = OOMC 12-2025 * Index-Linked2031; OOMC CY2 = $4,670,000 * 1.2764 = $5,960,788 Contract Year 2 OOMC Billing Period: Total Billing Periods: 12 Months. OOMCcy2-Mthly = OOMCcy2 * / Months in Contract Year OOMCcy2-Mthly = $5,960,788/ 12 = $496,732 B. Pass-Through Electricity Component (PTEC) is billed based on actual costs, as substantiated by billings from Portland General Electric. C. Sludge Transportation to Columbia Boulevard (STCB) i. STCB12-2o25 = $508 / Dry Ton of Sludge (in December 2025 Dollars) ii. Contract Year 1 example calculation: STCBcyi = STCB12-2025 * Index-Linked2o3o STCBcyi = $508 * 1.2199 = $619.71 per Dry Ton of Sludge iii. Contract Year 2 example calculation: STCBcY2 = STCB12-2025* Index-Linked2031 STCBcY2 = $508 * 1.2764 = $648.41 per Dry Ton of Sludge 4. REIMBURSABLE COSTS CHARGE A. The Reimbursable Costs Charge is defined in Section 17.4 (Reimbursable Costs Charge) of the DBOM Agreement as an amount equal to all payments to the DBOM Contractor for Major Maintenance, Repair and Replacement in the Billing Period in accordance with Section 17.5 (Annual Capital Maintenance Charge) of the DBOM Agreement. B. Annual Capital Maintenance Charge: i. Contract Year 1 example calculation: ACMCcy,12-2025 = $0 (Attachment 10B (Major Maintenance, Repair and Replacement Schedule) of Appendix 10 (Operation and Maintenance Requirements) in December 2025 Dollars) ACMCcyi = ACMC12-2025 * Index-Linked2oso A14-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 14 DBOM Agreement Example Calculation of Service Fee ACMCcY1 = $0 * 1.2199 = $0 ii. Contract Year 2 example calculation: ACMCcy2,12-2025= $50,751 (Attachment 10B (Major Maintenance, Repair and Replacement Schedule) of Appendix 10 (Operation and Maintenance Requirements in December 2025 Dollars) ACMCcy2 = ACMC12-2025 * Index-Linked2031 ACMCcy2 = $50,751 * 1.2764 = $64,778 C. MRR Account Balance: Contract Year-end MRR Balance example calculation: MRRcyl Unused Balance = $0 RCCcY2 = $37,158 (hypothetical) ACMCcY2= $64,778 MRRcy2 YE BALANCE = MRRcY1 Unused Balance+ ACMCcy2 - RCCcY2 MRRcY2 YE BALANCE = $0 + $64,778 - $37,158 = $27,620 5. DEDUCTIONS CREDIT The Deductions Credit is the sum of all Deductions imposed pursuant to Article 9 (Performance) and Appendix 13 (Performance Guarantees and Deductions) of the DBOM Agreement as described in Section 17.6 (Deductions Credit) of the DBOM Agreement. 6. EXTRAORDINARY ITEMS The Extraordinary Items component includes changes in costs attributable to Relief Events and other DBOM Agreement provisions as more specifically defined in Section 17.7 (Extraordinary Items) of the DBOM Agreement. [Remainder of Page Intentionally Left Blank] A14-5 3953578.11 043463 APPENDIX 15 PROJECT FACILITIES EVALUATION PROTOCOL 3953578.11 043463 APPENDIX 15 PROJECT FACILITIES EVALUATION PROTOCOL The purpose of this Appendix is to detail the protocol and procedures to be followed by the City, DBOM Contractor, and independent evaluator (if applicable pursuant to Section 10.3(I) (Disputes) of the DBOM Agreement) to assess the condition of the Project for accurate quantification of any changes in condition that may, from time to time, occur (herein referred to as the "Protocol"). 1. DETERMINING THE WEIGHTED AVERAGE REMAINING LIFE OF THE PROJECT EQUIPMENT The DBOM Contractor and City shall determine the weighted average remaining life of the Project Equipment using the four-step procedure presented below (the "Weighted Average Remaining Life"). The DBOM Contractor, with the assistance of the City, shall perform Step 1. The City and/or an independent evaluator hired pursuant to Section 10.3(I) (Disputes) of the DBOM Agreement shall perform Steps 2, 3, and 4. 1.1. Step 1: Develop Project Registry. Prior to any evaluation, the DBOM Contractor shall develop, with the assistance of the City, a registry of the Project (the "Project Registry", herein referred to as the "registry") of all assets that comprise the Project. Each asset shall be assigned a unique asset number that is entered into the registry along with a short verbal description (name) of the asset. The asset numbers, naming conventions and nomenclature used in the DBOM Contractor's CMMS developed pursuant to Section 10.5 (Computerized Maintenance Management System) of this DBOM Agreement shall be used. To the greatest extent possible, the registry shall also include the date the asset was initially purchased and installed and its original purchase or installed cost, (which shall be based on the Design-Build Price). The registry shall include a designator that indicates whether the asset is considered part of the Project Equipment or Project Structures. Assets included in the spare part valuation conducted pursuant to subsection 10.3(A) (Initial and Final Valuation of Vehicles, Rolling Stock, Spare Parts and Consumables) of this DBOM Agreement, hereto shall be included in the registry and clearly identified as a spare part but shall not be included in the determination of the Weighted Average Remaining Life of the Project Equipment. Obsolete or non-functional assets not used by the DBOM Contractor in future operations shall be included in the registry and clearly designated as being obsolete and shall not be included in determination of the Weighted Average Remaining Life of the Project Equipment. In the City's sole discretion, the DBOM Contractor shall compile the registry in Microsoft Excel or another program approved by the City. The master copy of the registry shall consist of a hard copy (or digital if agreed to by all parties in their discretion), each page of which shall be initialed by all parties. The City will keep the master copy. An example of the Project Registry is presented below (based on a project that involved pre-existing assets): A15-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Example Project Registry Manufacturer Designation (1 Date Initial Asset Asset / Model Serial = Equipment; Purchase/ Installed Number Name Process Location Number Number 2 = Structures) Installed Cost 3221 Sump Pipe 1 11/8/2010 $1,650 pump, gallery TOS #1 Main Plant 3222 Sump Pipe Spare 11/8/2010 $1,650 pump, gallery TOS #2 Main Plant 20901 Aeration Blower 1 12/15/2016 $440,063 blower#1 Building 01204- Conveyor Grit 85 1 9/26/2015 $47,227 03 #3, grit 85 Screenings screenings Building 020216- Motor, Thickener 1 5/1/2017 $6,000 001 RAS Building Pump#2 3218 WAS Thickener Obsolete 1/1/1994 $0 pump#3 Building S52026 York York 2 6/15/1962 Street Street 1.2. Step 2: Estimate Service Lives and Remaining Useful Lives of Project Equipment. The City and/or the independent evaluator will verify the accuracy, including the proper designation of each asset, and completeness of the registry prepared by the DBOM Contractor in Step 1. The City and/or the independent evaluator will then estimate the service lives and remaining useful lives of all the Project Equipment listed in the registry. 1.3. Step 3: Service Life Evaluation. The City and/or the independent evaluator will estimate the service life values (in years, rounded to the nearest whole number) using available maintenance and repair records for each asset and, as appropriate,vendor information and trade/professional reference materials. In the absence of adequate maintenance, repair and replacement records, and vendor information to establish the service life for any asset, the City and/or the independent evaluator will use the following default service life values. (a) Electrical/Mechanical Process and Prime Mover Equipment. The default service life of process and prime mover (pumps and blowers) equipment are: (1) Mechanical components - 15 years (2) Continuous duty sewage and sludge pumps - 10 years (3) Electrical components - 15 years (4) Electrical substations- 25 years (5) Electrical motor control centers -25 years A15-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol (b) Heating, Ventilation and Air Conditioning Equipment. The default service life of equipment used for heating, ventilation or air conditioning are: (1) Heating plants (boilers), chillers and air handling equipment- 20 years (2) Appurtenant systems- 15 years 1.4. Step 4: Remaining Useful Life Evaluation. The City and/or the independent evaluator will estimate the remaining useful lives of the Project Equipment using the following methods and procedure. The remaining useful life of an asset shall be based upon its reliability to perform its intended function(s), taking into consideration its performance history, physical condition, availability, replacement costs and maintenance costs, provided, however, in determining the remaining useful life of an asset the independent evaluator will not consider whether an asset is outmoded and if replaced would enhance the capabilities of the Project. The City and/or the independent evaluator will conduct a visual inspection of the Project Equipment and, as appropriate, monitor related instrumentation to determine the associated assets'physical condition and operation characteristics; review all repair and placement records; and consult with manufacturers to establish remaining lives of the assets. All readily accessible parts and surfaces will be inspected for any installation problems; excessive vibration, noise or temperature; the condition of coatings; signs of wear or corrosion; and leakage of any fluids. These inspection activities shall be conducted while motor-driven equipment is operating. For high-valued and critical assets, as identified jointly by the City and DBOM Contractor or independently by the independent evaluator (following a criticality review of each asset as it relates to the process and maintenance of the NPDES Permits), diagnostic testing will be performed to supplement and enhance the information obtained through the visual inspections and review of repair and replacement records. Such diagnostic testing may include vibration analysis, oil sampling and testing, and motor circuit analysis. In such cases, the additional testing shall be conducted by manufacturer approved personnel. If the City and DBOM Contractor, after consulting with the independent evaluator, both agree that such diagnostic testing is unwarranted for any asset, then they may instruct the independent evaluator to determine the remaining useful life without such testing. If the City and/or the independent evaluator cannot estimate the remaining life of any asset using the procedures detailed above, then, as a last resort and only with the concurrence of the City, as applicable, and DBOM Contractor, the City and/or the independent evaluator may calculate the remaining life by subtracting the age of the asset from the service life of the asset. If the age of the asset is greater than the service life, then the remaining life shall be equal to zero years. The age of the asset shall be the number of days between the date it was placed into service and the date of the evaluation divided by 365, rounded to the nearest whole year. The service and remaining useful lives shall be added to the Project Registry as illustrated below. Example Service and Remaining Life of Project Equipment Designation Asset (1 = Equipment; Service Life Remaining Useful Number Asset Name 2 = Structures) in Years Life in Years 3221 Sump pump,TOS #1 1 15 5 3222 Sump pump,TOS #2 Spare 0 0 20901 Aeration blower#1 1 20 18 A15-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Conveyor#3, grit 85 01204-03 screenings 1 10 3 020216-001 Motor, RAS Pump #2 1 15 12 3218 WAS pump #3 Obsolete 0 0 S52026 York Street 2 0 0 (a) Spare parts included in the spare part inventory are not included in calculation of the Weighted Average Useful Life. (b) Obsolete and unused assets are not included in the calculation of the Weighted Average Useful Life. (c) Assets comprising Project Structures are not included in the calculation of the Weighted Average Useful Life. 1.5. Determining Weights to be Applied to Each Asset. Weighting factors to be applied to each asset shall be calculated using the following equation: Weighting Factor = Vi Vi) Where Vi = replacement value of asset "I" in current dollars E Vi = the sum of the replacement values of all assets comprising the Project Equipment i = 1 to n n = number of assets included in this evaluation The City and/or the independent evaluator shall determine the replacement value of each asset using standard valuation techniques. If replacement value of an asset cannot be readily determined, then the independent evaluator will inflate the initial installed cost of the asset by the same rate of change in the Handy-Whitman Water Utility Construction Costs Trend Tables, North Atlantic Region for Pumping Plant-Electric Pumping Equipment; Water Treatment Plant- Large Treatment Plant Equipment; and Water Treatment Plant - Small Treatment Plant Equipment, as appropriate, from the year the asset was installed (or purchased) to the year for which the replacement value is being calculated. The initial installed cost for an asset may be estimated using the following methods that are listed in order of preference: (a) Actual, as-built vendor information (that is, labor and materials invoices) is preferred. (b) Historical vendor bid and quotation documents are the next best data source. (c) Other means of determining initial value of various assets, if approved by all parties, may be used. An example of the calculation of asset weighting factors is presented in the following table. Although the asset Weighting Factors in the table are only shown to four decimal places, the Weighting Factors should not be rounded when calculating the Weighted Average Remaining Life. For the sump pump number 3221 the Weighting Factor of .03389 was calculated by dividing $18,770 by$553,860. A15-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Example Asset Weighting Factor Designation Service Remaining Asset (1 = Equipment; Replacement Life in Useful Life Weighting Number Asset Name 2 = Structures) Value Years in Years Factor Sump pump,TOS 3221 #1 1 $18,770 15 5 .03389 Aeration 20901 blower#1 1 $475,970 20 18 .85937 Conveyor 01204- #3, grit 86 03 screenings 1 $53,120 10 3 .09591 020216- Motor, RAS 001 pump #2 1 $6,000 15 12 .01083 TOTAL $553,860 1.0000 1.6. Determine Weighted Average Remaining Life of the Project Equipment. The Weighted Average Remaining Life shall be calculated by summing the products of remaining life and replacement value of all assets and dividing by the sum of the replacement values of all assets as shown in the following equation: Weighted Average Remaining Life = Y (Vi)(Li) E Vi where Li = remaining life of asset "i" in years An example of the calculation of the Weighted Average Remaining Life is presented in the following table. The weighted average remaining life of .16945 for the sump pump number 3221 is calculated by multiplying the .03389 weighting factor by 5 years. Although the weighted average remaining life in this example is shown to 5 decimal places the independent evaluator will not round the weighted average remaining life for any asset when calculating the Weighted Average Remaining Life for all of the Project Equipment. The Weighted Average Remaining Life is the remaining life of all assets, in their current condition, of the Project Equipment expressed in years rounded to three decimal places. The Weighted Average Remaining Life determined during the Baseline Asset Evaluation shall not be changed. Future Weighted Average Life Expectancies will change over time. [Table follows on next page] A15-5 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Example Weighted Average Remaining Life Designation Remaining Weighted Average Asset (1 = Equipment; Weighting Useful Life Remaining Life, Number Asset Name 2 = Structures) Factor in Years years Sump pump,TOS 3221 #1 1 .03389 5 .16945 20901 Aeration blower#1 1 .85937 18 15.46866 01204- Conveyor#3, grit 03 85 screenings 1 .09591 3 .28773 020216- Motor, RAS pump 001 #2 1 .01083 12 .12996 TOTAL 1.0000 16.056 2. PROJECT STRUCTURES EVALUATION PROCEDURES The Baseline Asset Evaluation shall be the standard against which all future evaluations are compared. The independent evaluator, as part of its evaluation, shall produce a photographic and video record of the exterior and interior of the Project. 2.1. Functionality Evaluation. The functionality evaluation shall determine if the assets evaluated operate properly and perform the function(s) for which they were intended. Assets to be evaluated as part of the functionality evaluation shall include: (a) all piping, both buried and exposed; (b) all pipe valves together with hydraulic system gates and weirs; (c) instrumentation and control equipment and software; and (d) minor electrical/mechanical process equipment including any asset/component whose installed cost is less than $7,500 or whose expected life is less than three years. All motorized and manually operated equipment together with electrical equipment shall be tested for proper operation. Pipes shall be checked to assure that they are free of blockage, that fluids can be conveyed and there is no leakage. Detection, transmission and recording instrumentation shall be checked. Only those assets that are not functioning as designed or intended shall be noted in the evaluation results. The independent evaluator shall estimate the cost to restore functionality. 2.2. Structural Integrity Evaluation. The structural integrity evaluation shall include visual inspection with photographic and video recording of all Project Structures, including: (a) buildings and concrete structure, both above and below ground, including doors and windows; (b) walkways, roads and other paved areas; (c) fencing; A15-6 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol (d) finish system-paint, sealants and other liquid applied finishes; and (e) floor, ceiling, roofs and wall system - tiles, carpeting, raised floors and drop ceilings. Structures and paved areas shall be checked for structural defects and damage that could reduce their service life. Finished systems shall be visually inspected to assure that they provide adequate coverage and afford the desired protection. Occurrence of flaking, corrosion, rot and inadequate coverage should be noted. Floor, ceiling, roofs and wall systems should be visually inspected for excess wear and damage. Only exceptions shall be recorded. The independent evaluator shall estimate the cost to restore structural integrity. 3. EVALUATION REPORTS AND PRODUCTS The procedures followed together with the findings and results of the evaluation process shall be presented in a series of reports. Text, spreadsheets and databases shall all be prepared using Windows Office software. The independent evaluator will provide the City and DBOM Contractor with preliminary drafts of all documents for review and comment. The independent evaluator may consider comment from the City and DBOM Contractor, but will have, in its sole discretion, control over the content of the evaluation reports and products, provided, however, the independent evaluator's work is performed in accordance with the Protocol. All parties necessary for authentication shall sign final documents on each page. Each party shall receive an authenticated copy of all final reports, databases, spreadsheets, video documentation and handwritten notes. The evaluation report shall consist of at least the following clearly delineated sections: (a) The Project Registry; (b) Weighted Average Remaining Life of the Project Equipment; (c) Functionality and Structural Integrity of the Project Structures; (d) Supplemental Information as may be determined by the independent evaluator; (e) Recommended revisions to the Protocol for the evaluation the Project. 3.1. Project Registry. This section of the report shall include the Project Registry. The registry will be sorted and presented in the following five parts: (1) Project Equipment; (2) Project Structures; (3) spare parts and inventory; (4) obsolete and unused assets; and (5) rolling stock and vehicles. The Project Equipment portion of the registry shall include the listing of all assets to be included in the calculation of the Weighted Average Remaining Life together with their corresponding service lives and remaining lives. The procedures used to determine which assets to include in or exclude from the schedule shall be detailed. The basis for establishing service life for any asset shall be delineated. 3.2. Weighted Average Remaining Life. This section of the report shall provide the Weighted Average Life Expectancy of the Project Equipment and summarize the steps followed by the independent evaluator to establish A15-7 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol the Weighted Average Remaining Life. All calculations performed to determine weighting factors and the Weighted Average Remaining Life shall be included with the report. 3.3. Functionality and Structural Integrity. A report summarizing the findings of the functionality evaluation will be prepared. As discussed above, only those assets that exhibit physical or structural defects shall be noted in this report. The findings shall be tabulated on a spreadsheet such as the examples presented below. (a) All Piping and Valves. Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. Estimated Cost of Asset Number Asset Name Repair Functionality Defect(s) Leaking sludge pumping EX00020 Example 00020 valves (total: 6) Leaking PVC piping in EX00021 Example 00021 pumping station D 200 feet of DI piping replaced with PVC- EX00022 Example 00025 building E (b) Underground Structures. Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. Estimated Cost of Asset Number Asset Name Repair Functionality Defect(s) Tunnel wall (section F) see EX00021 Example 00023 page of 2 gallons per day Foundation wall to EX00024 Example 00024 building G cracked Dry well in pumping station H is cracked and EX00025 Example 00025 seeping (c) Instrumentation and Control Systems. Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. The version of hardware installed and software utilized should also be noted, and number of facility licenses available for use with the systems. Estimated Cost of Asset Number Asset Name Repair Functionality Defect(s) Flow metering in pumping EX00026 Example 00026 station I is inoperable Low water alarm in pumping station J is EX00027 Example 00027 inoperable A15-8 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Influent flow totalizer is EX00028 Example 00028 not reliable (d) Minor Electrical/Mechanical Process Equipment. Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. Estimated Cost of Asset Number Asset Name Repair Functionality Defect(s) Sump pump inoperative, EX00045 Example 00045 motor being replaced EX00062 Example 00062 Hatch cover inoperative EX00112 Example 00112 Valve inoperative This section will also include a summary of the findings of the structural integrity evaluation. As discussed above, only structures that are damaged or in need of maintenance to protect their integrity shall be noted in this report. The findings shall be tabulated on a spreadsheet such as the examples presented below. Video tape records made of the initial condition of assets, noting structural or other physical defects shall be included as part of this report. The location on video tape corresponding to the listed defect shall be entered in the spreadsheet with each listing. (e) Aboveground Systems (including Buildings and Concrete Structures). Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. Estimated Structural Cost of Asset Number Asset Name Integrity Defect(s) Repair Video Location Collapsed building EX00011 Example 00011 wall Broken concrete EX00012 Example 00012 steps Cracked and EX00013 Example 00013 leaking foundation (f) Finish Systems (including Paints and Coating). Listings of asset numbers and names together with corresponding descriptions of the deficiencies similar to those presented below shall be included in the report. Estimated Structural Cost of Asset Number Asset Name Integrity Defect(s) Repair Video Location Interior structures in pumping station EX00014 Example 00014 A in need of pain Inadequate coating EX00015 Example 00015 of walkways Exterior of building EX00016 Example 00016 B needs pain (g) Wall, Roofs and Flooring System. Exceptions will be noted on a spreadsheet such as the example presented below: A15-9 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 15 DBOM Agreement Project Facilities Evaluation Protocol Estimated Structural Cost of Asset Number Asset Name Integrity Defect(s) Repair Video Location Flaking ceiling in building C to be EX00017 Example 00017 replaced with tile Wooden flooring to be replaced with EX00018 Example 00018 tile Plywood walls to be replaced with EX00019 Example 00019 sheetrock 3.4. Supplemental Information. This section of the report shall include all supplemental information used by the independent evaluator, including results of diagnostic testing, values of Hardy-Whitman Water Utility Construction Costs indices used, equipment supplier information, and notes and calculations to support its findings and conclusion. This supplemental information may be included as appendices or attachments to the report. 3.5. Recommended Revisions to Evaluation Practices and Procedures Report. It is anticipated that unexpected situations may occur during the course of an evaluation that will necessitate modification of procedures presented herein or development of procedures not covered by this Appendix. It is important that such modifications and additions that are approved by the City and DBOM Contractor be incorporated into the Protocol and that the amended protocol be used to establish the condition of the Project, and the Weighted Average Remaining Life, for future evaluations. In the course of conducting an evaluation, new and better evaluation practices and procedures may be developed. The independent evaluator will, as an attachment to the evaluation report, produce a document that recommends changes to the evaluation procedures and shall circulate this supplement and formally invite review prior to the completion of the evaluation report. Such recommendations shall not become part of the Protocol unless mutually agreed to by the City and DBOM Contractor. 4. UPDATES AND EXIT EVALUATIONS The DBOM Contractor shall update the Project Registry regularly and as new assets are added or existing ones removed from service. All newly added assets shall be entered in the registry together with their evaluation designators, installation date, and installed cost. All assets that are removed from the Project shall be deleted from the registry. Assets that are removed from service but left in place shall continue to be shown in the registry. However, initial value, replacement value and remaining life will be set equal to zero. These assets shall be designated as not included in the evaluations. The DBOM Contractor shall provide the City a spreadsheet in Microsoft Excel format of all updated Project Registry along with a written summary of the changes made in the registry since it was last updated. The final evaluation, as required pursuant to subsection 10.3(C) (Final Evaluation of the Project) of this DBOM Agreement, shall use the same protocol described in this Appendix. [Remainder of Page Intentionally Left Blank] A15-10 3953578.11 043463 APPENDIX 16 EXIT TESTING 3953578.11 043463 APPENDIX 16 EXIT TESTING 1. OVERVIEW This Appendix describes in general terms the DBOM Contractor's Exit Test Plan with respect to the Project upon termination or expiration of this DBOM Agreement, and the protocol for the final evaluation of the Project to establish, among other things, the final condition and state of repair of the Project at the time of their transfer to the City ("Exit Testing"). The objectives of the Exit Test Plan are to: (a) preserve and protect the Project and all related equipment and tools that are to be transferred to the City; (b) leave the Project in a neat and orderly condition; (c) provide the City all material documentation, books, software licenses, service agreements, and records that are relevant to the continued operation and maintenance of the Project; (d) minimize transition costs for the DBOM Contractor and the City; and (e) work closely with the City in the efficient and effective transfer of the Project. 2. EXIT TEST PLAN The DBOM Contractor shall prepare and submit to the City for its review and approval the Exit Test Plan and include the following minimum requirements: (a) procedures for demonstrating compliance with Performance Guarantees; (b) procedures for testing all process, treatment, and ancillary systems; (c) procedures for testing the standby power capabilities of the Facility, including operation of the Facility on standby power; (d) use of permanent and temporary instrumentation; (e) organization of the test team, including responsibilities, authority, and decision making protocols; (f) response procedures for unsuccessful test results including definition of threshold results that constitute overall exit test failure, as described in Section 6 (Exit Test Report) of this Appendix; (g) testing schedule; (h) operating and maintenance schedule during testing; (i) procedures for demonstrating compliance with every Exit Test Procedure and Standard described in Section 3 (Exit Test Procedures) and Section 4 (Exit Test Standards) of this Appendix; and A16-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 16 DBOM Agreement Exit Testing (j) descriptions of all parameters to be monitored and measurements to be made that states sampling frequencies and includes: (1) a list of all parameters to be monitored and a schedule of monitoring, describing analytical methods and sampling frequencies at which parameters will be monitored on a continuous or other defined basis; (2) identification of equipment calibrations to be performed, including: (i) all calibration techniques to be used; (ii) timing of calibrations relative to Exit Testing (including adherence to all manufacturers' requirements for calibration of instruments used in Exit Testing operations and to monitor and evaluate Exit Testing); (iii) calibration practices, including the frequency and accuracy requirements; (iv) consideration of intermediate spot and cross checks, in addition to the formal calibration periods; and (v) quality assurance and quality control procedures (including those to be utilized for all equipment used for testing and measuring different parameters within the treatment process and at the in- house laboratory and contract laboratories); (3) a full description of any analytical methods and techniques that will be utilized to ensure that all Applicable Law and Performance Guarantees are met. In addition, descriptions of how data collected will be compared with Performance Guarantees shall be provided and shall be in a manner that complies with City requirements and regulatory requirements. Provide examples of any tools such as flow charts, check sheets or any other data presentation and evaluation techniques that will be utilized; (4) SCADA system monitoring and control functions; (5) a list of real-time data fields that will be provided to the City during Exit Testing; and (6) a listing of all samples requested by the City and a protocol for delivering samples to the City for the City's own testing program should the City elect to have such a program during Exit Testing. The Exit Test Plan shall also specify the form and contents of a report to summarize and communicate the results of the exit test ("Exit Test Report"), as further described in Section 6 (Exit Test Report) of this Appendix, and include specific, detailed sampling protocols to be utilized while conducting the exit tests. Preliminary tests may be conducted at the DBOM Contractor's expense; however, the results of such tests shall not be made part of the Exit Test Report. No later than 60 days prior to the Termination Date, the DBOM Contractor shall submit copies of a draft and final Exit Test Plan to the City for review. The City will review the Exit Test Plan drafts and return one marked-up copy with comments within 15 days of receipt of the draft Exit Test Plan. A16-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 16 DBOM Agreement Exit Testing 3. EXIT TEST PROCEDURES 3.1. General. Exit test procedures include: (a) demonstration of the ability of all components of the Project to meet the influent design capacity for a 24-hour period; (b) determination of the ability of the Facility to produce Effluent that meet the Performance Guarantees for an uninterrupted period of at least 14 days at throughputs requested by the City, which will be equal to or less than the design capacity of the Facility (i.e., 14-day testing); (c) demonstration of the proper function of the Facility upon loss of power, loss of control system, manual start-up and shutdown, and automatic shutdown; (d) demonstration that the Project functions as intended; (e) demonstration that all control systems function as intended without interruption; and (f) demonstration that the Project otherwise complies with all of the Performance Guarantees. 3.2. Exit Test. The exit test shall have a minimum duration of 14 days and shall also have duration sufficient to demonstrate that all system operations over the exit test period are in full and continuous compliance with the Performance Guarantees when the Project is operating at design capacity with all normally operating units in continuous service. If feasible, the City may deliver to the Project different sources or blends of sources of wastewater to reflect as best as possible the full future range of influent characteristics the Project is required to treat. If the 14-day exit test is terminated, it shall be restarted at the beginning of day 1 of the 14-day exit test and the entire 14-day exit test shall be run. 3.3. Monitoring Requirements. During the exit test, the DBOM Contractor shall regularly monitor the Effluent for specified key parameters in order to evaluate the performance of the Project. These key parameters include those needed to demonstrate compliance with the Performance Guarantees. All samples shall be analyzed by a state-certified independent laboratory agreed to by both the DBOM Contractor and the City, using laboratory analytical quality control standard procedures. Sample analyses performed during the exit test shall be performed by an independent state- certified laboratory pre-approved by the City. The City may collect its own samples and analyze them during Exit Testing to confirm the results of the DBOM Contractor's analyses. A16-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 16 DBOM Agreement Exit Testing 4. EXIT TEST STANDARDS The ability of the Project to meet the following exit test standards shall be demonstrated during Exit Testing, including demonstration of the following: (a) The Project operates properly with only the normal complement of employees included in the DBOM Contractor's staffing plan for the Project,with the exception of additional DBOM Contractor staffing related to collection and analysis of samples and other test data. (b) The Project complies with all Performance Guarantees and applicable Governmental Approvals at all times. The results of all samples taken during Exit Testing shall be reported and included in the calculation of reported averages or other evaluations applicable to determining compliance with Performance Guarantees. (c) The Project operates at design capacity. (d) All operations are consistent with Contract Standards. (e) The Project operates properly during manual and automatic shutdown and start- up. (f) The Project operates with automated and computerized systems in full and continuous operation. (g) The residuals handling system operates as intended in accordance with the Performance Guarantees. (h) The process and treatment systems operate as intended and in accordance with the Operation and Maintenance Manual. (i) All odor control equipment operates properly and as intended. 5. FAILURE OF THE EXIT TEST Failure to continuously demonstrate compliance with the Exit Test Procedures and Standards during the period of the exit test shall constitute a failure of the exit test. Any failure of an exit test shall require (a) correction of those components or conditions that resulted in the failure, (b) performance of a repeat of the exit test after proper notification is provided to the City. Any failure to meet Exit Test Procedures and Standards during the 14-day testing shall require a repeat of the 14-day test. 6. EXIT TEST REPORT The Exit Test Report shall be prepared in accordance with the Exit Test Procedures and Standards described in Section 3 (Exit Test Procedures) and Section 4 (Exit Test Standards) of this Appendix and include at a minimum: (a) A certification that testing was conducted in accordance with the approved Exit Test Procedures and Standards. A16-4 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 16 DBOM Agreement Exit Testing (b) A certification of the results of the testing with respect to each of the Exit Test Procedures and Standards. Each of the Exit Test Procedures and Standards shall be addressed separately and the basis for the determination shall be presented. This certification of the results of the testing shall include a determination of the extent to which the Project complies with the applicable Performance Guarantees. (c) All data measured and recorded during the tests including laboratory analyses, instrument calibrations, and measurement. (d) Record of equipment outages, failures, and preventative maintenance. (e) Summary of test results and conclusive evidence of compliance with all test requirements. (1) All calculations used in determining test results. (g) Any other data reasonably requested by the City to be included in such reports. (h) All certifications shall be signed by the DBOM Contractor. [Remainder of Page Intentionally Left Blank] A16-5 3953578.11 043463 APPENDIX 17 REFERENCE DOCUMENTS 3953578.11 043463 APPENDIX 17 REFERENCE DOCUMENTS 1. REFERENCE DOCUMENTS The following documents are included as Reference Documents as described in Section 26.15 (Reference Documents) of this DBOM Agreement. Document Archeology Survey, Prepared by AINW, Revised 3/13/2024 Biological Assessment (Terrestrial), Prepared by WSP, October 2022 Cultural Resources Report, Prepared by Jacobs, October 2025 Easement, Sanitary Sewer, Tax Lot 21E02CB01700, 3/23/1965 Easement, Storm Sewer, Tax Lot 21E02CB01501, 6/27/2000 Federal Cross-Cutting Authorities Review Memorandum, July 2025 Federal Cross-Cutting Authorities Review Memorandum Amendment, December 2025 Flows and Loads Project Memorandum by Carollo Engineers dated January 23, 2026 Geotechnical Report, Prepared by WSP, 7/13/2023 Geotechnical Data Report, Prepared by Jacobs, December 2025 Geophysical Reconnaissance: Data Report, Prepared by Siemens and Associates, September 2025 Groundwater Memo, Prepared by Wood, 9/26/2022 Noise Impact Assessment, Prepared by Wood, 8/13/2021 Phase I ESA Results — 101 Foothills Road, Prepared by Wood, 9/8/2021 Phase I ESA Results - 113 Foothills Road, Prepared by Wood, 9/8/2021 Phase I ESA Results -99 Foothills Road, Prepared by Wood, 9/8/2021 Phase II ESA Results — 101 Foothills Road, Prepared by Wood, 9/8/2022 Phase II ESA Results - 113 Foothills Road, Prepared by Wood, 9/8/2022 Phase II ESA Results -99 Foothills Road, Prepared by Wood, 9/8/2022 Report of Geotechnical Findings for TCWWTP, City of Portland, May 1991 TCWWTP Historical Drawings, City of Portland, Various date in the 1960s TCWWTP NPDES Permit No. 101614, 5/3/2024 TCWWTP Sampling Data 2012-2025, City of Portland Trip Generation 86 Sight Distance Analysis, Prepared by Lancaster Mobley, 5/10/2022 WIFIA Programmatic Environmental Assessment Adequacy Memorandum, July 2025 [Remainder of Page Intentionally Left Blank] A17-1 3953578.11 043463 APPENDIX 18 REPORTS AND RECORDS 3953578.11 043463 APPENDIX 18 REPORTS AND RECORDS 1. GENERAL REQUIREMENTS 1.1. Duty to Maintain Records. The DBOM Contractor shall retain and maintain all the records (including superseded records) referred to in Section 2 (Records to be Kept) of this Appendix in accordance with this Appendix and other applicable terms of this DBOM Agreement, in chronological order, in a form that is capable of audit. The DBOM Contractor shall make such records (other than books of account) available to the City for inspection during normal business hours upon reasonable notice. 1.2. Maintenance of Records. Wherever practical and unless otherwise agreed, the DBOM Contractor shall retain and maintain original records in hard copy form. True copies of the original records may be kept by the DBOM Contractor if it is not practicable to retain original records. (a) The DBOM Contractor shall retain and maintain all records referred to in Section 2 (Records to be Kept) of this Appendix for the duration of this DBOM Agreement and for a period of at least six years following the Termination Date, all in sufficient detail, in appropriate categories and generally in such a manner to enable each party to comply with its obligations and exercise its rights under this DBOM Agreement. (b) On the expiration of such period or at the earlier request of the City after termination of this DBOM Agreement, the DBOM Contractor shall deliver all those records (or, if those records are required by statute to remain with the DBOM Contractor or a Subcontractor, copies thereof to the City in the manner and at the location as the City specifies, acting reasonably.) The City shall make available to the DBOM Contractor for inspection during normal business hours all records the DBOM Contractor delivers pursuant to this Section upon reasonable notice. 1.3. Disposal of Records. During the Term, the DBOM Contractor may dispose of any records referred to in Section 2 (Records to be Kept) of this Appendix if any are more than 15 years old or in respect of which the required period for their retention has expired, provided that the DBOM Contractor first notifies the City in writing and provides the City with 60 days to elect to receive delivery of such records. 1.4. Drawing Requirements. Any drawings required to be made or supplied pursuant to this DBOM Agreement shall be of a size appropriate to show the detail to be depicted clearly without magnifying aids. Where by prior agreement with the DBOM Contractor the City has agreed to accept digital (including CAD and 3D CAD model) other storage media (which must include secure back up facilities), the DBOM Contractor shall make or supply, or have made or supplied, drawings and other documents in such agreed upon form. A18-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 18 DBOM Agreement Reports and Records 2. RECORDS TO BE KEPT The DBOM Contractor shall retain the following: (a) this DBOM Agreement, the documents referred to in the Transaction Forms and Reference Documents, including all amendments to such agreements; (b) all reports required by Section 8.11 (Periodic Reports) of this DBOM Agreement; (c) all Annual Settlement Statements; (d) the Project records described in Appendix 6 (Design-Build Work Review Procedures), Appendix 7 (General Design-Build Work Requirements) and Appendix 10 (Operation and Maintenance Requirements); (e) records relating to the appointment and supervision of the City Representative and the DBOM Contractor Representative; (f) documents relating to Governmental Approvals, including applications, refusals and appeals; (g) notices, reports, results and certificates relating to completion of the Design-Build Work, Design and Construction Requirement Changes, Commissioning and Capital Modifications; (h) all operation and maintenance manuals; (i) documents relating to Relief Events; (j) all notices made to or received from the City Representative; (k) documents relating to a request for the consent of the City to any Change in Control by the DBOM Contractor; (1) tax invoices and records applicable to the Project (other than any income tax records for the DBOM Contractor or records pertaining to other taxes personal to the DBOM Contractor); (m) records required by Applicable Law (including in relation to health and safety matters) to be maintained by the DBOM Contractor with respect to the Design- Build Work and Operation and Maintenance Services; (n) documents relating to the Required Insurance; (o) documents referred to in Appendix 13 (Performance Guarantees and Deductions); and (p) all other records, notices or certificates required to be produced or maintained by the DBOM Contractor pursuant to the express terms of this DBOM Agreement. [Remainder of Page Intentionally Left Blank] A18-2 3953578.11 043463 APPENDIX 19 DBOM CONTRACTOR AND SUBCONTRACTORS INFORMATION 3953578.11 043463 APPENDIX 19 DBOM CONTRACTOR AND SUBCONTRACTORS INFORMATION 1. PURPOSE The purpose of this Appendix is to identify: (1) the DBOM Contractor's formation and other relevant entity-related information; (2) those Subcontractors that the City has approved for use by the DBOM Contractor in performing the Project Services; and (3) the key management and supervisory personnel proposed to be used by the DBOM Contractor in performing the Project Services. 2. DBOM CONTRACTOR INFORMATION 2.1. DBOM Contractor Information. The DBOM Contractor represents and warrants that the following information regarding DBOM Contractor is true and complete as of the Effective Date: 1. Name: Jacobs Project Management Co. 2. Date of Incorporation/ January 4, 2008 Formation: 3. State of Incorporation/ Delaware Formation: 4. Registration Number: 4484626 3. SUBCONTRACTORS 3.1. Subcontractors Generally. As provided in Article 12 (Contracting and Labor Practices) of this DBOM Agreement, the Subcontractors have been proposed and shall be used by the DBOM Contractor in connection with the performance of the Project Services. At any time during the Design-Build Period or the Operation and Maintenance Period, as applicable, the DBOM Contractor may request the City to update the list of approved Subcontractors. The City will review any suggested changes to such list in accordance with the provisions of Article 12 (Contracting and Labor Practices) of this DBOM Agreement. The City will have the right at any time to review and revise the then current list of approved Subcontractors consistent with Article 12 (Contracting and Labor Practices) of this DBOM Agreement. 3.2. Approved Subcontractors. The Subcontractors that the City has approved as of the Effective Date, and the DBOM Contractor is permitted to engage for the Project Services, are the following: Subcontractor Role 1. Christenson Electric, Inc. Electrical subcontractor A19-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 19 DBOM Agreement DBOM Contractor and Subcontractors Information Subcontractor Role Primary site civil and structural 2. Tapani, Inc. subcontractor 3. Harder Mechanical Contractors, Inc. Primary process mechanical subcontractor 4. KEY INDIVIDUALS 4.1. Key Individuals Generally As referenced in Section 4.4 (Key Individuals) of this DBOM Agreement, certain key management and supervisory personnel were proposed and shall be used by the DBOM Contractor in connection with the performance of the Project Services. Any change in the Key Individuals shall be subject to review and approval of the City in accordance with Section 4.4 (Key Individuals) of this DBOM Agreement. Resumes for the Key Individuals are included in Attachment 19A (Key Individuals Resumes) and establish the general level of qualifications for the role identified. 4.2. Key Individuals. The Key Individuals are the following: DBOM Contractor Party Position Name 1. DBOM Contractor Project Manager Michelle Green 2. DBOM Contractor Design Manager Kristen Jackson 3. DBOM Contractor Design-Build Manager Enrique Ramos 4 DBOM Contractor Construction QA/QC Jose Castro Manager 5 DBOM Contractor Operation and Dan Black Maintenance Manager 6. DBOM Contractor Safety Officer Matt Smith [Remainder of Page Intentionally Left Blank] A19-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 19 DBOM Agreement DBOM Contractor and Subcontractors Information ATTACHMENT 19A KEY INDIVIDUALS RESUMES [ATTACHED] A19-3 3953578.11 043463 APPENDIX 20 PUBLIC COMMUNICATIONS 3953578.11 043463 APPENDIX 20 PUBLIC COMMUNICATIONS 1. CITY RESPONSIBILITIES 1.1. Lead Communications Role. The City shall assume the lead communications role for the Project. The City shall take primary responsibility for all communications matters and shall be responsible for performing the following functions: (a) provide identified, dedicated lead communications contacts with applicable skills and experience with 24 hours per day, seven days per week, availability on applicable aspects of communications; (b) provide identified, dedicated media-trained lead media spokesperson, with back- up media-trained personnel as required with 24 hours per day, seven days per week, availability on applicable aspects of communications; (c) primary media contact for the Project; (d) provide final review and approval of all public communications materials; (e) communicate promptly with all relevant parties on crisis issues and communicate within 24 hours of general issues; (f) maintain and update the Project web site, as required; and (g) provide updates to internal and external stakeholders, as required. 1.2. Design-Build Period-Specific Responsibilities. In the period up to the Acceptance Date, the City shall take the lead role in providing: (a) communications (including web site): a comprehensive program including print, web-based, audio-visual and other elements describing and providing information about the Project as it proceeds; (b) community relations: a community relations program to ensure two-way communication and problem-solving between the parties and external stakeholder groups, neighborhoods, cities, and others regarding design and construction issues, public reporting and communications. Such actions may include community events and presentations to community groups; (c) media relations: a media relations policy and protocol to be developed in cooperation with the parties and internal stakeholders; (d) public reporting and consultation: for day to day, and more broadly, for each year, of construction to highlight and provide progress updates and information and how community issues have been considered and addressed throughout the year; (e) crisis communications: required planning for potential crisis issues; A20-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 20 DBOM Agreement Public Communications (f) government relations: communications between the parties involved in the project and Governmental Bodies; (g) public-related communications: all communications related to Project Services and City policies; and (h) performance review: periodically review the DBOM Contractor's performance in providing communications as outlined in Section 2 of this Appendix. 1.3. Marketing Materials. (a) The City shall have the right, acting reasonably, to approve all Project-related marketing or advertising in any form. (b) The City shall have the right to approve the use of the name of the City for any commercial purpose. 2. DBOM CONTRACTOR RESPONSIBILITIES 2.1. Support Communications Role. The DBOM Contractor shall assume the support communications role. The DBOM Contractor shall be responsible for performing the following functions: (a) respond to communications issues in accordance with agreed timeframes; (b) review and provide communications and technical materials including reasonable requests by the City for web site content, community meetings and City Council presentations; (c) involvement and participation in community events as requested by the City; (d) direct all media inquiries and interview requests to the City Representative; (e) maintain a written record of all material public inquiries, complaints and communications and provide copies to the City Representative on a weekly basis (or immediate if urgent); and (f) during a crisis situation, the parties acknowledge that a ramping up of communications efforts shall be required. The DBOM Contractor shall ensure and make available sufficient resources to effectively and proactively manage and perform its communications responsibilities during a crisis, including 24 hours per day, seven days per week, availability. 2.2. Design-Build Period-Specific Responsibilities. In the period up to the Acceptance Date, the DBOM Contractor shall perform the following: (a) Communicate regularly with the immediately affected property owners and neighborhoods on design and construction related issues with particular attention to communicating the scope, schedule and status of the construction program. This shall include processes to proactively address any work-related inquiries and issues (e.g., public inquiries, complaints regarding noise,hours of work, dust etc.). A20-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 20 DBOM Agreement Public Communications (b) Provide management information for the management of local and regional traffic during the construction process. (c) Develop a plan outlining roles and responsibilities for a list of potential crisis issues that could develop during this period. This plan shall be developed jointly with the City. [Remainder of Page Intentionally Left Blank] A20-3 3953578.11 043463 APPENDIX 21 DESIGN-BUILD QUALITY MANAGEMENT PLAN 3953578.11 043463 APPENDIX 21 DESIGN-BUILD QUALITY MANAGEMENT PLAN 1. DESIGN-BUILD QUALITY MANAGEMENT PLAN The DBOM Contractor will implement a comprehensive Design-Build Quality Management Plan (QMP) so that all project deliverables meet the contractual, regulatory, and performance requirements of the LOWWTF. The QMP will establish the policies, procedures, and responsibilities necessary to deliver a facility that meets the City's expectations for safety, reliability, and long-term operational performance. The DBOM Contractor will finalize the QMP following contract award and submit it to the City for review and approval prior to commencement of design and construction activities. The QMP will comply with the requirements of the DBOM Agreement and will be applied consistently across all phases of the project, including design, procurement, construction, commissioning, and startup. Our quality management approach is based on three key principles: • Quality is planned into the project from the outset. • Quality control is performed by those performing the work. • Quality assurance provides independent verification that requirements are met. 2. APPROACH TO QUALITY MANAGEMENT The DBOM Contractor will establish a project quality management structure that provides clear accountability and independent oversight of quality activities. Our quality management organization will include the following key roles. 2.1. Design-Build Quality Manager The quality manager will be responsible for implementation and oversight of the QMP. This individual will have the authority to halt work that does not meet project quality requirements. Other responsibilities include: • Implementing and maintaining the QMP • Coordinating quality control and quality assurance activities • Conducting quality audits and inspections • Maintaining project quality documentation • Reporting quality performance to the DBOM project manager and the City 2.2. Design Discipline Leads Each design discipline lead will be responsible for quality control within their technical area, confirming that design deliverables meet project requirements. A21-1 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 22 DBOM Agreement Design-Build Quality Management Plan 2.3. Construction QA/QC Manager The construction QA/QC manager will oversee quality during construction, including inspections, testing, and documentation of construction activities. 2.4. Independent Technical Reviewers Senior technical specialists will conduct independent design reviews of critical systems and major treatment processes. 3. DESIGN QUALITY CONTROL Quality management during design confirms that all design deliverables meet the project's technical, regulatory, and contractual requirements. Design quality control will be carried out by the design team responsible for producing each deliverable. Quality control activities will include: • Discipline-specific technical reviews • Verification of design calculations • Constructability reviews with construction staff • Operability reviews with operations personnel • Coordination reviews across disciplines 3.1. Design Quality Assurance Independent design quality assurance reviews will confirm that design deliverables meet all project requirements. These reviews will include: • Interdisciplinary design checks • Independent technical reviews • Compliance verification against design criteria • Constructability and life-cycle cost evaluations 3.2. Design Review Milestones Formal design reviews will occur at key stages of design development, including: • 30 percent design review • 60 percent design review • 90 percent design review • Final design verification All review comments will be tracked and resolved prior to issuance of the next design milestone. A21-2 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 22 DBOM Agreement Design-Build Quality Management Plan 4. PROCUREMENT QUALITY CONTROL Quality management during procurement confirms that all equipment and materials meet project specifications and performance requirements. Procurement quality activities will include: • Vendor prequalification • Technical review of vendor submittals • Verification of compliance with specifications • Factory acceptance testing (FAT) for critical equipment • Inspection of fabricated equipment prior to shipment Major process equipment, including pumps, blowers, electrical systems, instrumentation, and treatment systems, will undergo enhanced review and testing prior to delivery. 5. CONSTRUCTION QA/QC Construction quality management confirms that the facility is constructed in accordance with approved design documents and project specifications. 5.1. Construction Quality Control Construction quality control will include: • Inspection of installed work • Verification of materials and equipment • Review of contractor submittals and shop drawings • Field testing and inspection activities • Documentation of inspection and testing results Qualified inspectors will conduct routine inspections to verify compliance with project requirements. 5.2. Construction Quality Assurance Construction quality assurance will provide independent verification that quality control procedures are being implemented effectively. Quality assurance activities include: • Independent quality audits • Third-party laboratory testing • Verification of inspection reports A21-3 3953578.11 043463 Lake Oswego Wastewater Treatment Facility Appendix 22 DBOM Agreement Design-Build Quality Management Plan • Review of quality documentation 6. INSPECTION AND TESTING Inspection and testing activities will be conducted throughout construction to verify that installed systems meet design and performance requirements. Testing may include: • Structural concrete testing • Weld inspections • Electrical system testing • Instrumentation calibration • Mechanical equipment testing • Pressure testing and leak testing All inspection and testing results will be documented and maintained in the project quality records. 7. COMMISSIONING AND STARTUP QUALITY VERIFICATION Quality management continues through commissioning and startup to confirm that all facility systems operate in accordance with design intent. Commissioning activities will include: • Functional testing of mechanical and electrical systems • Supervisory control and data acquisition and control system verification • Integrated process testing • Performance testing of treatment systems • Operator training verification These activities confirm that all systems perform as required prior to facility acceptance [Remainder of Page Intentionally Left Blank] A21-4 3953578.11 043463 APPENDIX 22 EQUIPMENT AND MATERIALS SUBJECT TO COST ADJUSTMENT 3953578.11 043463 APPENDIX 22 EQUIPMENT AND MATERIALS SUBJECT TO COST ADJUSTMENT 1. PURPOSE The equipment and materials that are subject to cost adjustment pursuant to subsection 7.3(B)(3) (Adjustment for Equipment and Material Cost Escalation) of this DBOM Agreement are identified below in this Appendix. [ATTACHED] A22-1 3953578.11 043463 . 0 • I S Cr Laydown Area /'i • ' r' 4 /IP, Area to be paved and , •-- f -• �, ;/ / �{ used for craft parking ; in 2029.2031 Construction Area Construction ti .i.4' + M r• Trailers . Laydown area • during DP 2, ; ,, 3,and 4 Tower Crane Reach • ❑nunuuuuua :Illlllllttlllem: i Tower Crane Base Trailer Parking rr —_ Mg Tryon Creek access through ' construction road ;�. iiil >< , -1- IL r . Enterprise access through •• - I ,'I'�. • iii.(4* :• construction road r rlt.: �" / s. i • 40 1 �x Install push-button activated stoplight woo �-;,.. �'''. "I for pedestrian/bike crossing with flashing indicators for pedestrian Vcrossing in both directions l\�- �. sue` AO . %- Construction Access Only '"' a * ;' f' `ate . 4` Lrc l:usiness 'wlic,an s _ 4+1 4 • a Try.nCr ek cress •I, rL ! •4464.* •A •I•' , f 1 �r l�*Ijik A . �c /../% ff 1 . 'al 10 I 1 . 14 ,,,•.. . kiti It..., r • ' • Road Closed:Only construction vehicles allowed within the hard closure including concrete trucks from Lakeshore Concrete. it l .: • Enterprise Rent-A Car,Caliber Collision,Landcare,and other businesses with y:ton and smaller vehicles to follow detour oogle,Earth route including local delivery drivers at • Detour signs to be provided throughout the detour route. Jacobs ©JACOBS �,-U/ LOWWTF Outfall / ���/v ` ,Easement (approx.) 20-INFLUENT PUMP STATION 4 / 21 OPUMPST STATION iI Tryon creek 22-IFS ELECTRICAL BUILDING Y \\,,,,,,, / O WTF Interceptor N. \•\\\ EXISTING TRYON CREEK Y / PUMP STATION CONNECT TO . EXISTING WILLAMETTE / PORTLAND RS INTERCEPTOR r _ /1 60-TRUCK LOADOUT SEWER DROP STRUCTURE + /„ �y cobs) / CONNECT TO NEW RS TO NEW " __ ^EXISTI CONNECT TO ,I 0 LAKE \ TRYON CREEK PS ,.•� lc -T OUTFACE I DROP STRUCTURE •'' �I EFFLUE JUNCTION STRUCTURE RS TO i r CONTROL _--- _no�, < > 1 28-ODOR/Y ll I 12-MAINTENANCE BLDG ��, .■ 1' I _ yyy��' LOWWTF/+ LOWWTF 25-HEADWORKS/SOLIDS HANDLING I.I` I�u '1,.' I I, (Jacobs) Outfall � II II I� � E. HEADWORKS iii �r c (City) LAKE OSWEGO R��S: / I �I � -..-- 'I1I, Jacobi 1' /�_II+ �•FE TO EXISTING/ OSWEGO P TRN LAKE --LO T �� I 1N/ OUTFALL O JUNCTION UPSTREAM I_i 1 J�� JUNCTION STRUCTURE (J a♦ S) ❑ o BW EFFLUENT To TO E"�� 1 I^ '� - U� r 11� AB/WW 27-ELECTRICAL BUI DING TO RA I 1�'1 AND GENERA TORS 111 FILTERS FILTRATION , v ; s ► �� Foothills ' BASINS" �� , o Interceptors WASTD ' TOUV IRDTs ❑ (City) V LOWWTF `. ii _SE TG RAS TOAI ) Property Line FILTERS BASINS \ 35 BLOWER CANOPY \ \ //)1 !� 40-CLARIFIERS I 30-AERATION '1 I BASINS I ,.\ _ II PW/FW ML TO LOOP - �y'a CLARIFIERS �'/� 1 (-----55 I I �——X71; �s®/ /� , � u- Ns ADMINISTRATION L rte/� CONNECT TO CI TY RY WAT - I I�I i � --''-'-' BLDG l I / I7 'i�� LINE,TVP.2LOCATIONS a / � ' I o '� /� RELOCATED I I o... � STORM / I / ' SEWER I / - I p I I I , - CONNECT TO CITY I I I III I - STM LINE AT I N. ./ NG LINE. EXISTING MANHOLE I V CONNECT TO I f I N. CITY GAS LINE I I I I 1 " 1 MAIN ENTRANCE I I 1 `• f 11 i \ I I I Jacobs ©JACOBS Table 2-1 Expected Design-Build Governmental Approvals Anticipated Governmenal Assumed Anticipated Approval Governmental Permit Reviewing Permitting Jacobs Review Application Approval Fee Groups Permit Types/Sequencing Agency Responsibility Reference Documents Deliverables Duration Date Issuance Date Comments Responsibility Scope Assumptions Federal WIFIA Funding/NEPA EPA COLO WIFIA Memo July&Dec N/A N/A N/A N/A EPA was lead;federal nexus and all agencies had an N/A City is responsible for WIFIA grant administration 2025 opportunity to review The FONSI was published Dec responsibilities, if any(e.g. reporting). Section 106 National Historic SHPO COLO 2025 Jacobs Cultural N/A N/A N/A N/A The DOEs are complete; recommended not eligible. N/A Preservation Act-Built Resources Report Resources No new Section 106 required. Section 106 National Historic SHPO COLO WIFIA Memo July&Dec N/A N/A N/A N/A 2025 Jacobs report recommends fulltime monitoring where N/A Preservation Act- 2025 excavation is deeper than 3 feet,within areas as No new Section 106 required. However, Archaeological Resources 2024 AINW Cultural designated in report. monitoring is recommended and included in Resources Report scope. Clean Water Act(Section USAGE COLO WIFIA Memo July 18,2025 N/A N/A N/A N/A N/A 404/401) 2022 Wood Wetland No wetlands onsite and no work in-water per 2022 wetland Delineation Report delineation. No 404/401 required Clean Air Act EPA COLO WIFIA Memo July 18,2025 N/A N/A N/A N/A Per WIFIA Memo, Project is not located in a N/A [attachment F] nonattainment or maintenance area for any relevant Clean Air Act is covered for NEPA purposes. No pollutants. federal permitting. Conditional and Final Letter FEMA COLO WIFIA Memo July 18,2025 N/A N/A N/A N/A Notes: A CLOMR-F was evaluated during WIFIA N/A of Map Revision [attachment F]; USFWS/NMFS ESA review. City Floodplain Administrator (CLOMR/LOMR) Meeting notes with City has conveyed fill approaches that would trigger a CLOMR- Floodplain Administrator; F.Jacobs design avoids fill impacts that would trigger a Technical Proposal TM 6-09 CLOMR-F. No CLOMR-F is required. ESA decision on the WIFIA EPA COLO WIFIA Memo July 18,2025 N/A N/A N/A N/A WIFIA Memo states"no effect"to endangered species or N/A funding habitat therefore no consultation with USFWS No new ESA consultation required. Bald and Golden Eagle USFWS Jacobs WIFIA Memo July 18,2025 Nest survey Not a permit, but N/A N/A A survey conducted in 2022 found no eagle nests. N/A Nest surveys are included to support tree and Protection Act a process Prior to tree or vegetation removal during Oregon Nesting vegetation removal during Nesting Window. Window(2/1 -7/31),a survey must be conducted to Jacobs'schedule assumes no delays due to the confirm there are no eagle nests. presence of nests. Migratory Bird Act USFWS Jacobs WIFIA Memo July 18,2025 Bird Survey Not a permit, but N/A N/A Prior to tree or vegetation removal during Oregon Nesting N/A Nest surveys are included to support tree and a process Window(2/1 -7/31),a survey must be conducted to vegetation removal during Nesting Window. confirm there are no eagle nests. Jacobs'schedule assumes no delays due to the presence of nests. DEQ Permits NPDES Wastewater Discharge ODEQ COLO N/A N/A N/A N/A City is in the process of pursuing and securing a Mass COLO Permit Load Limit Increase. Per 3/26 email from City,Jacobs is to assume City will secure requested Mass Load Limit Jacobs Proposal assumes effluent criteria as Increase documented in RFP NPDES Permit Transfer ODEQ COLO Permit Transfer N/A N/A N/A City is pursuing co-permittee status with City of Portland COLO Jacobs proposal assumes Jacobs will prepare application BES. permit transfer document(s).City will hold responsibility for DEQ approvals.Jacobs scope does not include schedule delay or impacts to startup and commissioning activities associated with DEQ approval of Permit Transfer DEQ Authority to Construct ODEQ COLO Carollo Flow and Load Memo 30%and 100% N/A N/A N/A COLO Design Per 3/26 email from City,City will take Documents responsibility for DEQ approvals Air Contaminant Discharge ODEQ Jacobs Permit 30 days 4/19/2028 5/19/2028 Inclusion of emergency generators in the Project triggers Jacobs Scope includes preparation of General ACDP Permit(ACDP) application the need for a ACDP.A General ACDP is assumed. Permit application(Fee is$2,160).Completion of a Toxic Air Contaminant Emissions Inventory is assumed to not be required. County/City LOWWTF DBOM Agreement 1 Table 2-1 Expected Design-Build Governmental Approvals Anticipated Governmenal Assumed Anticipated Approval Governmental Permit Reviewing Permitting Jacobs Review Application Approval Fee Groups Permit Types/Sequencing Agency Responsibility Reference Documents Deliverables Duration Date Issuance Date Comments Responsibility Scope Assumptions Minor Development Review COLO Jacobs See comments 1. 1-2 months for 3/3/2027 7/1/2027 Requires Pre-app conference and neighborhood meeting COLO (DR)Permit Pre-app. prior to application submittal. (LOC 50.07.003.14) 2. 120 days from Submittal requirements: submittal to •Pre-application conference Decision •Neighborhood Meeting and associated submittal package •Letter of Authorization/Proof of Ownership •Narrative addressing applicable criteria •Land Use Plan Set including site plan,elevations and building materials,floor plans, renderings, landscape plan, grading plan, utility plan, lighting plan •Traffic Impact Study •Stormwater Report Scope assumes Minor Development Review •Circulation Analysis(confirm at pre-app conference) Permit.A public hearing or appeal is not assumed to be required. Environmental Review COLO Jacobs See comments Concurrent with 3/3/2027 7/1/2027 The Resource Protection overlay is along Tryon Creek COLO (LOC 50.07.004.8.c) DR application corridor north of the project site. Because of pipe work extending to the northeast and potential tree removals in the RP, Environmental Review is assumed to be required. Submittal Requirements: •Stream Corridor Delineation(may be an existing delineation). •Mitigation Plan(if required). Environmental Review will occur as part of Development Review. Greenway Review COLO Jacobs N/A N/A N/A N/A Assumed not to be applicable because no development is COLO (LOC 50.05.009) proposed in the Greenway overlay,which is within 150 feet of the ordinary low waterline of the Willamette River. Greenway Review not required. Floodplain Management Area COLO Jacobs Meeting notes with City Floodplain Concurrent with 3/3/2027 7/1/2027 Required if developing within the floodplain. Land use will COLO Development Permit Floodplain Administrator; Development DR application need to show compliance with Flood Management Area FMA review will occur as part of Development (LOC 50.07.004.13) Technical Proposal TM 6-09 Memo (LOC 50.05.011). FMA permit will be obtained from the Review. Refer to Technical Proposal TM 6-09 for Engineering Department after land use is approved. additional assumptions. Hillside Protection Review COLO Jacobs See comments Concurrent with 3/3/2027 7/1/2027 COLO Required where work is proposed on slopes greater than (LOC 50.07.004.3) DR application 20%,or at the City Manager's discretion.Assumed applicable because of the steep grades in areas of the site.Also,within areas of moderate to high landslide susceptibility per DOGAMI SLIDO. Submittal Requirements: •Site Survey •Geotechnical Engineering Analysis •Landscape Plan(part of LU plan set) Hillside Protection Review will occur as part of •Grading Plan(part of LU plan set) Development Review. Weak Foundational Soil COLO Jacobs See comments Concurrent with 3/3/2027 7/1/2027 A Geotech report will be needed to confirm soil stability COLO Determination DR application and remedial actions. (LOC 50.07.004.10) Submittal Requirements: •Geotechnical Engineering Analysis •Erosion Control Plan Weak Foundational Soil Review will occur as part of Development Review. Park and Open Space COLO Jacobs See comments Concurrent with 3/3/2027 7/1/2027 COLO Required for construction or alteration of major public Contribution Review DR application facilities(LOC 50.06.005.1.a.ii).20%of the net (LOC 50.06.005) developable area shall be open space,though this value should be confirmed at the pre-app conference. LOC 50.07.004.7.d.ii states the final approval shall be made by the hearing body at the time of the public hearing.Will Park and Open Space Contribution review will need to confirm at pre-app whether a hearing will be occur as part of Development Review.A public needed. hearing or appeal is not assumed to be required. Submittal Requirements: Refine assumptions based on Pre-application •Landscape Plan(part of LU plan set). conference. LOWWTF DBOM Agreement 2 Table 2-1 Expected Design-Build Governmental Approvals Anticipated Governmenal Assumed Anticipated Approval Governmental Permit Reviewing Permitting Jacobs Review Application Approval Fee Groups Permit Types/Sequencing Agency Responsibility Reference Documents Deliverables Duration Date Issuance Date Comments Responsibility Scope Assumptions Type 11 Tree Cutting Permit COLO Jacobs See comments Concurrent with 3/3/2027 7/1/2027 A Type II Tree Cutting Permit is required for tree removal COLO (LOC 55.02.035) DR application (>6"DBH)associated with a minor development permit (LOC 55.02.035). City Manager may require an arborist's report,to be confirmed at the pre-application conference. Trees>15"DBH are significant trees and are not eligible to be removed under a Type II Tree Cutting Permit unless an alternatives analysis is performed(LOC 55.02.080.3 Exceptions).Trees between 6"and 15"DBH require 1:1 mitigation,and trees>15"DBH require 2:1 mitigation.After approval,complete the verification permit process. Submittal Requirements: •Tree Inventory •Tree Protection Plan(could be part of LU plan set or contained in separate report) •Arborist's Report(to be confirmed at pre-app Tree Cuttting Review will occur as part of conference) Development Review. City is currently updating Tree Code. Proposal is based on current code. Lot Line Adjustment COLO Jacobs See comments 2 months 5/1/2031 6/30/2031 The LO Planning Department has recommended that the COLO (Ministerial Development— lot line adjustment be undertaken after construction is LOC 50.07.003.13.e.ii) complete,when the properties have been transferred to the City of Lake Oswego per the IGA with the City of Portland. Construction work will require an easement from Portland to proceed in the meantime.This is a ministerial decision,with no pre-application or neighborhood meeting required.There is no opportunity to appeal this decision. Submittal Requirements: •Proof of Ownership •Title Report •Site Survey •Lot line plan showing proposed lot lines and demonstrating that applicable setbacks are met •Clackamas County Property Line Adjustment or Replat Evaluation Form •Narrative responding to the applicable criteria Assume this effort and approvals carry no Project schedule impacts. Variance COLO Jacobs N/A N/A N/A N/A Will only be required if there are standards that cannot be COLO (Major-LOC 50.08.004, met. Current assumption is that site design meets all Minor-LOC 50.08.002) applicable standards. Minor variances primarily apply to setbacks, lot widths,and access. Major variances are all Assume no Variance is required.Verify at Pre- other variances. application conference PreCon Permits Grade and Fill Permit COLO Jacobs Lake Oswego-Commercial Application 10 weeks Includes Grading-Possible to pursue a separate grading COLO Building Permit permit for demolition 5/23/2027 8/1/2027 Work to support demolition 5/28/2027 8/6/2027 Balance of Work Tree Removal Permit COLO Jacobs Lake Oswego-Tree Application 2 weeks 11/20/2026 12/11/2026 Stand alone from the DR Application package;Tree COLO Removal/Protection protection/removal for trees related directly to demolition Applications/Forms work Street Opening Permit COLO Jacobs Lake Oswego-Street Opening Application 3 weeks As needed As needed COLO Permit Application Temporary Construction COLO Jacobs Application 4 weeks 6/3/2027 7/1/2027 COLO Permits -Trailers Lake Oswego Building Separate early building permit required for temporary Application construction trailers -Temp Traffic Control Lake Oswego Traffic Control Necessary prior to altering/impeding the flow of traffic Permit&Info LOWWTF DBOM Agreement 3 Table 2-1 Expected Design-Build Governmental Approvals Anticipated Governmenal Assumed Anticipated Approval Governmental Permit Reviewing Permitting Jacobs Review Application Approval Fee Groups Permit Types/Sequencing Agency Responsibility Reference Documents Deliverables Duration Date Issuance Date Comments Responsibility Scope Assumptions -Temp Power Lake Oswego-Electrical Low Required for trailers,cranes, lighting,etc. Voltage Permit -Temp Water/Sewer Included under Public Improvement Permit -Lake Oswego Erosion Control Lake Oswego Erosion Control Necessary before any site disturbance takes place Permit Application -Franchise Utility Permit Lake Oswego-Franchise Assuming these are obtained separately by utility Utility Permit performing work(PGE,NWN) -Radon Mitigation Lake Oswego Mandatory Information regarding radon mitigation requirements Radon Mitigation 1200-C Construction ODEQ Jacobs Oregon 1200-C Permit Application 2 months 11/3/2025 1/2/2026 Erosion control plan,SWPPP Jacobs 1200-C permit fee is$1515 for initial permit and Stormwater Permit Application Information $1558 annually thereafter Construction Permits Public Improvements Permit COLO Jacobs Lake Oswego-Public Application Up to 4 weeks 6/3/2027 7/1/2027 For any improvements within the Public ROW COLO Demolition COLO Jacobs Lake Oswego-Commercial Application Up to 4 weeks 11/13/2026 12/11/2026 Necessary for all above ground structure demolition COLO Structural COLO Jacobs Lake Oswego-Commercial Application Up to 10 weeks Necessary for all new above ground structures(excludes COLO Structural Permit piping/manholes,etc.) Lake Oswego-Structural Special Inspections Form 5/28/2027 8/6/2027 DP3-Deep foundations 1/26/2028 4/5/2028 DP4-Early Concrete 4/19/2028 6/28/2028 DP5-Main Plant Package Plumbing COLO Jacobs Lake Oswego Plumbing Application Up to 10 weeks 4/19/2028 6/28/2028 Separate permits required for temporary and permanent COLO Electrical COLO Jacobs Lake Oswego-Electrical Low Application Up to 10 weeks 4/19/2028 6/28/2028 Separate permits required for temporary and permanent COLO Mechanical COLO Jacobs Lake Oswego-Mechanical Application Up to 10 weeks 4/19/2028 6/28/2028 Separate permits required for temporary and permanent COLO Potable water connection COLO Jacobs Application 4/19/2028 6/28/2028 COLO Fire Suppression&Signaling COLO Jacobs Lake Oswego-Fire System Application Up to 10 weeks 4/19/2028 6/28/2028 COLO Union Pacific Railroad UPRR Jacobs Union Pacific RR-Survey& Minimum 6 7/2/2027 1/1/2028 Shoring/tiebacks for Aeration Basin close to close to being Jacobs Encroachment Permits months, up to 12 within UPRR zone of influence. months Survey and outreach to UPRR is in the scope. Solid Waste/Subtitle D landfill N/A Jacobs Phase I, Phase II ESAs. N/A N/A N/A N/A There is some history of use of oils onsite, but the ESAs N/A deemed the site low risk. Jacobs will test soils during geotech. If needed,this permit is to bring dirty dirt offsite. Jacobs Proposal assumes this is not required Reviewing Entities EPA:WIFIA SHPO: State Historic Preservation Officer USFWS: US Fish&Wildlife Service COLO:City of Lake Oswego ODEQ:Oregon Dept of Environmental COP:City of Portland CC: Clackamas County LOWWTF DBOM Agreement 4 "General Decision Number: OR20260053 05/18/2026 State: Oregon Construction Types: Heavy Counties: Oregon Counties of Clackamas Excludes Dredging Modification Number Publication Date 0 01/02/2026 1 05/18/2026 BROR0001-033 06/01/2025 Rates Fringes BRICKLAYER $ 49.60 25.15 CARP0096-006 06/01/2025 Rates Fringes MILLWRIGHT $ 59.35 22.38 CARP0503-017 06/01/2025 Rates Fringes PILEDRIVERMAN $ 53.94 16.81 CARPENTER (INCLUDING FORM WORK) $ 53.94 16.81 ELEC0048-018 01/01/2025 Rates Fringes ELECTRICIAN $ 63.50 29.73 ELEC0048-026 01/01/2025 Rates Fringes ELECTRICIAN (LOW VOLTAGE WIRING INSTALLER FOR FIRE ALARM, NURSE CALL, BURGLAR ALARM, SECURITY AND VOICE EVACUATION SYSTEMS AND OTHER SYSTEMS THAT ARE PART OF A FIRE OR LIFE SAFETY SYSTEM. ) $ 52.12 24.37 ELECTRICIAN (LOW VOLTAGE WIRING INSTALLER FOR ALL OTHER WORK) $ 42.68 23.14 ENGI0701-029 01/01/2024 Rates Fringes POWER EQUIPMENT OPERATOR GROUP 6 LOADERS: (LESS THAN 1 CU YD. ); OILER; BOBCAT/SKID LOADER; GRADE CHECKER; CRANE OILER; FORKLIFT; ASPHALT SPREADER; BROOM OPERATOR; FORKLIFT; ROLLER (NON-ASPHALT) ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 45.81 16.90 POWER EQUIPMENT OPERATOR GROUP 5 TRACKHOE/BACKHOE HYDRAULIC: TRACK TYPE UP TO AND INCLUDING 20,000 LBS, WHEEL TYPE (FORD, JOHN DEER, CASE TYPE); BOOM TRUCK OPERATOR; DRILLING: CHURM DRILL AND EARTH BORING MACHINE OPERATOR; DIRECTIONAL DRILL OPERATOR LESS THAN 20,000 LBS PULLBACK; CONCRETE PUMPER; CONCRETE PAVER: COMPACTOR; LOADERS, RUBBER TIRED TYPE , LESS THAN 25,00 LBS; FORKLIFT OVER 5 TON, BULLDOZER 20,000 LBS OR 100 HORSES OR LESS; MIXER OPERATOR; ROLLER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 49.03 16.90 POWER EQUIPMENT OPERATOR GROUP 4 CRANE: HYDRAULIC CRANE OPERATOR, UNDER 50 TONS; LATTICE BOOM CRANE OPERATOR: LATTICE BOOM CRANE OPERATOR, UNDER 50 TONS; TRACKHOE/BACKHOE-ROBOTIC: TRACK AND WHEEL TYPE, UP TO AND INCLUDING 20,0000 LBS. WITH ANY OR ALL ATTACHMENTS; BLADE: BLADE OPERATOR; TRACTOR OPERATOR WITH BOOM ATTACHMENT; DRILLING: CHURM DRILL AND EARTH BORING MACHINE OPERATOR; DIRECTIONAL DRILL OPERATOR OVER 20,000 LBS PULLBACK; CRANE: CHICAGO BOOM AND SIMILAR TYPES; BOOM TYPE LIFTING DEVICE, 5 TON CAPACITY OR LESS; ASPHALT PAVER; RUBBER-TIRED SCRAPER, SINGLE ENGINE, SINGLE SCRAPER; COMPACTOR-SELF PROPELLED; LOADERS 25,000 LBS AND LESS THAN 60,000 LBS; BULLDOZER OVER 20,000 LBS AND MORE THAN 100 HORSE UP TO 70,000 LBS; MECHANIC;CRANE: DERRICK BARGE OPERATOR LESS THAN 30 TON; PILEDRIVER; EXCAVATOR OVER 20,000 LBS THROUGH 80,000 LBS; SCREED ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 50.27 16.90 POWER EQUIPMENT OPERATOR GROUP 3 HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR, 50 TONS THROUGH 89 TONS (WITHOUT LUFFING OR TOWER ATTACHMENT); LATTICE BOOM CRANES: LATTICE BOOM CRANE-50 THROUGH 89 TONS (AND LESS THAN 150 FEET BOOM); RUBBER TIRED SCRAPER: WITH TANDOM SCRAPERS; SELF LOADING, PADDLE WHEEL, AUGER TYPE, FINISH AND/OR 2 OR MORE UNITS; LOADER 60,000 LBS AND LESS THAN 120,000 LBS; BULLDOZER OVER 70,000 LBS UP TO AND INCLUDING 120,000 LBS; EXCAVATOR OVER 80,000 LBS THROUGH 130,000 LBS ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 53.60 16.90 POWER EQUIPMENT OPERATOR GROUP 2 CRANE: CABLEWAY OPERATOR, 25 TONS AND OVER; HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR 90 TONS THROUGH 199 TONS (WITHOUT LUFFING OR TOWER ATTACHMENT); TOWER/WHIRLEY OPERATOR: TOWER CRANE OPERATOR; WHIRLEY OPERATOR, UNDER 90 TONS; LATTICE BOOM CRANE: 90 THROUGH 199 TONS AND/OR 150 TO 200 FEET BOOM; HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR, 50 TONS THROUGH 89 TONS (WITH LUFFING OR TOWER ATTACHMENT); RUBBER TIRED SCRAPER WITH TANDOM SCRAPERS, MULTI-ENGINETRENCHING MACHINE-WHEEL OPERATOR; LOADER 120,000 LBS AND ABOVE; BLADE: AUTO GRADER; BLADE OPERATOR-ROBOTIC; BULLDOZER OVER 120,000 LBS AND ABOVE; CRANE : DERRICK BARGE OPERATOR 30 TON BUT LESS THAN 150 TON; EXCAVATOR OVER 130,000 LBS AND ABOVE ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 54.75 16.90 POWER EQUIPMENT OPERATOR GROUP 1B LATTICE BOOM CRANE: OPERATOR, 300 TONS THROUGH 399 TONS WITH OVER 200 FEET BOOM; OPERATOR 400 TONS AND OVER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. .$ 60.98 16.90 POWER EQUIPMENT OPERATOR GROUP 1A HYDRAULIC CRANE: HYDRAULIC OPERATOR, 200 TONS AND OVER (WITH LUFFING OR TOWER ATTACHMENT); LATTICE BOOM CRANE: OPERATOR, 200 TONS THROUGH 299 TONS, WITH OVER 200 FEET BOOM; ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. .$ 58.82 16.90 POWER EQUIPMENT OPERATOR GROUP 1 CRANE: HELICOPTER OPERATOR, WHEN USED IN ERECTING WORK; WHIRLEY OPERATOR, 90 TON AND OVER; LATTICE BOOM CRANE: OPERATOR 200 TONS THROUGH 299 TONS, AND/OR OVER 200 FEET BOOM; HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR 90 TONS THROUGH 199 TONS WITH LUFFING OR TOWER ATTACHMENTS; ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES) : ZONE 2 - $3.00 ZONE 3 - $6.00 FOR THE FOLLOWING METROPOLITAN COUNTIES: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: ALL JOBS OR PROJECTS LOCATED IN MULTNOMAH, CLACKAMAS AND MARION COUNTIES, WEST OF THE WESTERN BOUNDARY OF MT. HOOD NATIONAL FOREST AND WEST OF MILE POST 30 ON INTERSTATE 84 AND WEST OF MILE POST 30 ON STATE HIGHWAY 26 AND WEST OF MILE POST 30 ON HIGHWAY 22 AND ALL JOBS OR PROJECTS LOCATED IN YAMHILL COUNTY, WASHINGTON COUNTY AND COLUMBIA COUNTY AND ALL JOBS OR PORJECTS LOCATED IN CLARK & COWLITZ COUNTY, WASHINGTON EXCEPT THAT PORTION OF COWLITZ COUNTY IN THE MT. ST. HELENS ""BLAST ZONE"" SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED IN THE AREA OUTSIDE THE IDENTIFIED BOUNDARY ABOVE, BUT LESS THAN 50 MILES FROM THE PORTLAND CITY HALL SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE PORTLAND CITY HALL, BUT OUTSIDE THE IDENTIFIED BORDER ABOVE, SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS. FOR THE FOLLOWING CITIES: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG ALL JOBS OR PROJECTS LOCATED WITHIN 30 MILES OF THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE I PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 30 MILES AND LESS THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE II PAY FOR ALL CLASSIFICATIONS. ALL JOBS OR PROJECTS LOCATED MORE THAN 50 MILES FROM THE RESPECTIVE CITY HALL OF THE ABOVE MENTIONED CITIES SHALL RECEIVE ZONE III PAY FOR ALL CLASSIFICATIONS $ 56.66 16.90 IRON0029-011 07/07/2025 Rates Fringes IRONWORKER (ORNAMENTAL, REINFORCING, AND STRUCTURAL) $ 48.31 34.52 LAB00737-005 06/01/2024 Rates Fringes LABORERS: (MASON TENDER-CEMENT/CONCRETE) $ 43.79 17.05 LAB00737-024 06/01/2024 Rates Fringes LABORERS: GROUP 3 TRAFFIC CONTROL-CONE SETTER $ 34.39 17.30 LABORERS: GROUP 2 GRADE CHECKER; VIBRATING PLATE $ 40.41 17.30 LABORERS: GROUP 1 BLASTER, DEMOLITION; CHAIN SAW $ 39.11 17.30 PAIN0010-005 07/01/2025 Rates Fringes PAINTER (HIGHWAY & PARKING LOT STRIPER) $ 41.19 17.09 PAIN0010-006 07/01/2025 Rates Fringes PAINTERS: (BRUSH, ROLLER AND SPRAY) $ 39.94 16.68 PLAS0555-006 06/01/2025 Rates Fringes CEMENT MASON/CONCRETE FINISHER $ 46.13 20.31 PLUM0290-012 04/01/2025 Rates Fringes PIPEFITTER $ 60.77 34.72 SUOR2009-051 11/23/2009 Rates Fringes TRUCK DRIVER: LOWBOY TRUCK $ 17.07 5.50 TRUCK DRIVER: DUMP TRUCK $ 19.58 6.47 OPERATOR: TRACTOR $ 20.00 0.73 OPERATOR: ROTOMILL $ 28.25 9.70 OPERATOR: COMPACTOR $ 28.99 5.02 LABORER: WATER, SEWER, UNDERGROUND $ 17.00 1.75 LABORER: PIPELAYER $ 23.93 7.46 LABORER: MASON TENDER - BRICK $ 28.14 4.53 LABORER: LANDSCAPE $ 19.01 7.45 LABORER: FORM-STRIPPING $ 19.27 6.32 LABORER: FLAGGER $ 20.70 5.48 LABORER: COMMON OR GENERAL $ 22.34 7.86 LABORER: ASPHALT SPREADER $ 22.18 9.39 TEAM0037-010 06/01/2025 Rates Fringes TRUCK DRIVER GROUP 4 WATER TRUCK OVER 10,000 TO 15,000 GALLONS $ 36.08 18.30 TRUCK DRIVER GROUP 3 WATER TRUCK OVER 5,000 TO 10,000 GALLONS $ 35.74 18.30 TRUCK DRIVER GROUP 2 VACTOR TRUCK; WATER TRUCK OVER 3,000 TO 5,000 GALLONS $ 35.57 18.30 TRUCK DRIVER GROUP 1 FLATBED TRUCK; OFF THE ROAD TRUCK; WATER TRUCK UP TO 3,000 GALLONS $ 35.41 18.30 WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts. Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts. Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)) . The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate. Union Rate Identifiers A four-letter identifier beginning with characters other than SU , UAVG , SA , or SC denotes that a union rate was prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate. Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification. Union Average Rate Identifiers The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE: UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio. The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate. A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based. Survey Rate Identifiers The SU identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier. SU wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1) . State Adopted Rate Identifiers The SA identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h) . Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the SA identifier took effect under state law in the state from which the rates were adopted. WAGE DETERMINATION APPEALS PROCESS 1) Has there been an initial decision in the matter? This can be: a) a survey underlying a wage determination b) an existing published wage determination c) an initial WHD letter setting forth a position on a wage determination matter d) an initial conformance (additional classification and rate) determination On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to: Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations. Requests can be submitted via email to BCWD-Office@dol.gov or by mail to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7) . Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc. ) that the requestor considers relevant to the issue. 3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board) . Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210. END OF GENERAL DECISION "General Decision Number: 0R20260081 05/18/2026 State: Oregon Construction Types: Heavy Counties: Oregon Counties of Baker, Benton, Clackamas, Clatsop, Columbia, Coos, Crook, Curry, Deschutes, Douglas, Gilliam, Grant, Harney, Hood River, Jackson, Jefferson, Josephine, Klamath, Lake, Lane, Lincoln, Linn, Malheur, Marion, Morrow, Multnomah, Polk, Sherman, Tillamook, Umatilla, Union, Wallowa, Wasco, Washington, Wheeler and Yamhill Dredging Modification Number Publication Date 0 01/02/2026 1 05/18/2026 ENGI0701-004 01/01/2024 Rates Fringes DREDGING: TENDERMAN ZONE C - OVER 60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 57.82 16.70 DREDGING: TENDERMAN ZONE B - OVER 30-60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 54.82 16.70 DREDGING: TENDERMAN ZONE A - ALL JOBS OR PROJECTS LOCATED WITHIN 30 ROAD MILES OF PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 51.82 16.70 DREDGING: LEVERMAN, HYDRAULIC ZONE C - OVER 60 ROAD MILES FROM PORTLAND CITY HALL.*ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 62.47 16.70 DREDGING: LEVERMAN, HYDRAULIC ZONE B - OVER 30-60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 59.47 16.70 DREDGING: LEVERMAN, HYDRAULIC ZONE A - ALL JOBS OR PROJECTS LOCATED WITHIN 30 ROAD MILES OF PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 56.47 16.70 DREDGING: LEVERMAN, DIPPER, FLOATING CLAMSHELL ZONE B - OVER 30-60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 59.47 16.70 DREDGING: LEVERMAN, DIPPER, FLOATING CLAMSHELL ZONE C - OVER 60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 62.47 16.70 DREDGING: LEVERMAN, DIPPER, FLOATING CLAMSHELL ZONE A - ALL JOBS OR PROJECTS LOCATED WITHIN 30 ROAD MILES OF PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 56.47 16.70 DREDGING: ASSISTANT MATE ZONE C - OVER 60 ROAD MILES FROM PORTLAND CITY HALL.*ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 53.95 16.70 DREDGING: ASSISTANT MATE ZONE B - OVER 30-60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 50.95 16.70 DREDGING: ASSISTANT MATE ZONE A - ALL JOBS OR PROJECTS LOCATED WITHIN 30 ROAD MILES OF PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 47.95 16.70 DREDGING: ASSISTANT ENGINEER ZONE C - OVER 60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 59.31 16.70 DREDGING: ASSISTANT ENGINEER ZONE B - OVER 30-60 ROAD MILES FROM PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 56.31 16.70 DREDGING: ASSISTANT ENGINEER ZONE A - ALL JOBS OR PROJECTS LOCATED WITHIN 30 ROAD MILES OF PORTLAND CITY HALL. *ALL JOBS OR PROJECTS SHALL BE COMPUTED FROM THE CITY HALL BY THE SHORTEST ROUTE TO THE GEOGRAPHICAL CENTER OF THE PROJECT $ 53.31 16.70 WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts. Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts. Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)) . The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate. Union Rate Identifiers A four-letter identifier beginning with characters other than SU , UAVG , SA , or SC denotes that a union rate was prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate. Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification. Union Average Rate Identifiers The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE: UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio. The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate. A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based. Survey Rate Identifiers The SU identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier. SU wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1) . State Adopted Rate Identifiers The SA identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h) . Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the SA identifier took effect under state law in the state from which the rates were adopted. WAGE DETERMINATION APPEALS PROCESS 1) Has there been an initial decision in the matter? This can be: a) a survey underlying a wage determination b) an existing published wage determination c) an initial WHD letter setting forth a position on a wage determination matter d) an initial conformance (additional classification and rate) determination On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to: Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations. Requests can be submitted via email to BCWD-Office@dol.gov or by mail to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7) . Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc. ) that the requestor considers relevant to the issue. 3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board) . Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210. END OF GENERAL DECISION Oregon Bureau of Labor and Industries Prevailing Wage Rates for Public Works Contracts ‘,0%ORAv4, O�c � O w � **P ts * THE UNION 0 * rid * tifA ** * 1859 Christina E. Stephenson Labor Commissioner Rates Effective July 5, 2026 BUREAU II CHRISTINA E.STEPHENS0N WLABOR& Labor Commissioner INDUSTRIES In this rate book are the new prevailing wage rates for Oregon non-residential public works projects, effective July 5, 2026. Prevailing wage rates are the minimum hourly wages that must be paid to all workers employed on all public works projects. Thank you for your engagement in the process and commitment to Oregon law. Our team is ready to help support you with any questions you have. We also offer regular, free, informational seminars and webinars for contractors and public agencies. Contact us at PWR.Email@boli.oregon.gov or (971) 245-3844. Christina E. Stephenson Labor Commissioner More information about prevailing wage rates: The Oregon Bureau of Labor& Industries publishes the prevailing wage rates (PWR) that are required to be paid to workers on non-residential public works projects in Oregon. Separate documents, Definitions of Covered Occupations for Public Works Contracts in Oregon, provide occupational definitions used to classify the duties performed on public works projects. These definitions are used to find the correct prevailing wage rate. The rate book and definition publications are available online at https://www.oregon.gov/boli, as well as additional information, supporting documents, and forms. Please contact us at PWR.Email@boli.oregon.gov or (971)245-3844, for additional information such as: • Applicable prevailing wage rates for projects (Generally, the rates in effect at the time the bid specifications are first advertised are those that apply for the duration of the project.) • Federal Davis-Bacon rates (In cases where projects are subject to both state PWR and federal Davis-Bacon rates, the higher wage must be paid.) • Required PWR provisions for specifications and contracts • Apprentice rates 9 Portland Salem Eugene oregon.gov/boll 971-245-3844 �° Help@bolLoregon.gov la Ore.Relay TTY:711 L',..2* • TABLE OF CONTENTS JULY 5, 2026 Required Postings for Contractors and Subcontractors 1 Public Works Bonds 2 Finding the Correct Prevailing Wage Rate 3 Prevailing Wage Rates by Occupations 4 List of Ineligible Contractors 31 Forms necessary to comply with ORS 279C.800 through ORS 279C.870 can be found on our website at https://www.oregon.gov/boll/employers/Pages/prevailing-wage.aspx. Contractors are encouraged to use and keep on file the forms provided as master copies for use on future prevailing wage rate projects. All of the information in this booklet can be accessed and printed from the Internet at: www.oreqon.qov/BOLI Pursuant to ORS 279C.800 to ORS 279C.870, the prevailing wage rates contained in this booklet have been adopted for use on public works contracts in Oregon. Required Postings for Prevailing Wage Contractors and Subcontractors PREVAILING WAGE RATES Every contractor and subcontractor engaged in work on a public works must post the applicable prevailing wage rates for that project in an obvious place on the worksite, so workers have ready access to the information. DETAILS OF FRINGE BENEFIT PROGRAMS When a contractor or subcontractor provides or contributes to a health and welfare plan or a pension plan, or both, for employees who are working on a public works project, the details of all fringe benefit plans or programs must be posted on the worksite. The posting must include a description of the plan or plans, information about how and where claims can be made and where to obtain more information. The notice must be posted in an obvious place on the work site in the same location as the prevailing wage rates. WORK SCHEDULE Contractors and subcontractors must give workers their regular work schedule (days of the week and number of hours per day) in writing before beginning work on the project. Contractors and subcontractors may provide the schedule at the time of hire, prior to starting work on the contract, or by posting the schedule in a location frequented by employees, along with the prevailing wage rate information and any fringe benefit information. If an employer fails to give written notice of the worker's schedule, the work schedule will be presumed to be a five-day schedule. The schedule may only be changed if the change is intended to be permanent and is not designed to evade the PWR overtime requirements. ORS 279C.840(4); OAR 839-025-0033(1). ORS 279C.840(5); OAR 839-025-0033(2). ORS 279C.540(2); OAR 839-025-0034. PAGE 1 JULY 5, 2026 PUBLIC WORKS BONDS Every contractor and subcontractor who works on public works projects subject to the prevailing wage rate (PWR) law is required to file a $30,000 "PUBLIC WORKS BOND" with the Construction Contractors' Board (CCB). This includes flagging and landscaping companies, temporary employment agencies, and sometimes sole proprietors. The key elements of ORS 279C.830(2) and ORS 279C.836 specify that: ■ Specifications for every contract for public works must contain language stating that the contractor and every subcontractor must have a public works bond filed with the CCB before starting work on the project, unless otherwise exempt. ■ Every contract awarded by a contracting agency must contain language requiring the contractor: ■ To have a public works bond filed with the CCB before starting work on the project, unless otherwise exempt; and ■ To include in every subcontract a provision requiring the subcontractor to have a public works bond filed with the CCB before starting work on the project unless otherwise exempt ■ Every subcontract that a contractor or subcontractor awards in connection with a public works contract between a contractor and a public agency must require any subcontractor to have a public works bond filed with the CCB before starting work on the public works project, unless otherwise exempt. ■ Before permitting a subcontractor to start work on a public works project, contractors must first verify their subcontractors either have filed the bond or have elected not to file a public works bond due to a bona fide exemption. ■ The PWR bond is to be used exclusively for unpaid wages determined to be due by the Bureau of Labor & Industries. ■ The bond is in effect continuously (you do not have to have one per project). ■ A public works bond is in addition to any other required bond the contractor or subcontractor is required to obtain. Exemptions: ■ Allowed for a disadvantaged business enterprise, a minority-owned business, woman- owned business, a business that a service-disabled veteran owns, or an emerging small business certified under ORS 200.055, for the first FOUR years of certification; ■ Exempt contractor must still file written verification of certification with the CCB and give the CCB written notice that they elect not to file a bond. ■ The prime contractor must give written notice to the public agency that they elect not to file a public works bond. ■ Subcontractors must give written notice to the prime contractor that they elect not to file a public works bond. ■ For projects with a total project cost of$100,000 or less, a public works bond is not required. (Note this is the total project cost, not an individual contract amount.) ■ Emergency projects, as defined in ORS 279A.010(f). PAGE 2 JULY 5, 2026 PREVAILING WAGE RATES FINDING THE CORRECT PREVAILING WAGE RATE To find the correct rate(s) required on your public works project, you will need: • the date the project was first advertised for bid • the county your project is in • the duties of workers on the job Generally, the rate you should look for is based on the date the project was first advertised for bid. (See OAR 839-025-0020(8) for information about projects that contract through a CM/GC, or contract manager/general contractor.) The Labor Commissioner must establish the prevailing rate of wage for each region as defined in law. (See ORS 279C.800.) A map of these regions can be found on BOLI's website. To find the correct rate in this rate book: 1. Determine the duties that are being performed by each worker. Use the booklet Definitions of Covered Occupations to find the definition that most closely matches the actual work performed by the worker. You can find this publication online at https://www.oregon.gov/boli/employers/Pages/occupational-definitions.aspx. 2. Find the correct occupation in the "Prevailing Wage Rate for Public Works Contracts"below. The prevailing wage rate is made up of an hourly base rate and an hourly fringe rate. The combination of these two amounts must be paid to each worker. Watch for possible zone differential, shift differential, and/or hazard pay. If the occupation lists different rates for different Areas of the state, locate the Area that includes the county where the project is located. Apprentices must be paid consistent with their registered apprenticeship program standard. You can find apprenticeship rates on our website at https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx. You may also contact the agency to confirm the correct apprenticeship rate. The "Prevailing Wage Rate Laws" handbook provides specific information and answers questions regarding prevailing wage laws and is available on our website at https://www.oregon.gov/boli/employers/Documents/2026%20PWR%20Laws%20Handbook%2 06.5.26%20ed ition.pdf. If you have any questions about any of this information, please contact the Bureau of Labor & Industries at PWR.Email@boli.oregon.gov or (971) 245-3844. PAGE 3 JULY 5, 2026 July 5, 2026 Prevailing Wage Rates by Occupations—Table of Contents Using the booklet, Definitions of Covered Occupations,find the definition and group number, if applicable,that most closely matches the actual work being performed by the worker. ASBESTOS WORKER/INSULATOR 5 BOILERMAKER 5 BRICKLAYER/STONEMASON 5 CARPENTER 5 CEMENT MASON 7 DIVER& DIVER TENDER 7 DREDGER 8 DRYWALL, LATHER,ACOUSTICAL CARPENTER &CEILING INSTALLER 8 ELECTRICIAN 9 ELEVATOR CONSTRUCTOR, INSTALLER AND MECHANIC 14 FENCE CONSTRUCTOR (NON-METAL) 14 FENCE ERECTOR(METAL) 14 GLAZIER 15 HAZARDOUS MATERIALS HANDLER 15 HIGHWAY/PARKING STRIPER 15 IRONWORKER 15 LABORER 16 LANDSCAPE LABORER/TECHNICIAN (Laborer Group 5) 16 LIMITED ENERGY ELECTRICIAN 17 LINE CONSTRUCTOR 19 MARBLE SETTER 19 PAINTER & DRYWALL TAPER 19 PLASTERER AND STUCCO MASON 20 PLUMBER/PIPEFITTER/STEAM FITTER 21 POWER EQUIPMENT OPERATOR 22 ROOFER 24 SHEET METALWORKER 25 SOFT FLOOR LAYER 27 SPRINKLER FITTER 27 TENDER TO MASON TRADES (Brick and Stonemason, Mortar Mixer, Hod Carrier) 28 TENDER TO PLASTERER AND STUCCO MASON 28 TESTING AND BALANCING (TAB)TECHNICIAN 28 TILE SETTER/TERRAZZO WORKER: Hard Tile Setter 29 TILE, TERRAZZO, AND MARBLE FINISHER 29 TRUCK DRIVER 29 PAGE 4 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ASBESTOS WORKER/INSULATOR Base Rate: 64.37 26.57 Firestop Containment: 50.29 21.14 BOILERMAKER Base Rate: 45.33 32.22 BRICKLAYER/STONEMASON Base Rate: 51.47 26.64 • This trade is tended by "Tenders to Mason Trades." • Add $1.00 per hour to base rate for refractory repair work. CARPENTER Zone A(Base Rates) Group 1 56.69 17.81 Group 2 56.86 17.81 Group 3 (Millwrights) 64.82 23.63 Group 4 Eliminated Group 5 (Bridge & Highway) 58.06 17.81 Group 6 (Piledrivers) 58.06 17.81 Zone Differential for Carpenters -Add to Zone A Base Rate Zone B: 1.25 per hour Zone C: 1.70 per hour Zone D: 2.00 per hour Zone E: 3.00 per hour Zone F: 5.00 per hour Zone G: 10.00 per hour Zone A: Projects located within 30 miles of the respective city hall of the cities listed below. Zone B: Projects more than 30 miles but less than 40 miles from the respective city hall of the cities listed below. Zone C: Projects more than 40 miles but less than 50 miles from the respective city hall of the cities listed below. Zone D: Projects more than 50 miles but less than 60 miles from the respective city hall of the cities listed below. Zone E: Projects more than 60 miles but less than 70 miles from the respective city hall of the cities listed below. Zone F: Projects more than 70 miles but less than 100 miles from the respective city hall of the cities listed below. Zone G: Projects more than 100 miles from the respective city hall of the cities listed below. See more information on Reference Cities for Zone Differential and Premium Pays on page 6. PAGE 5 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate CARPENTER (continued) Reference Cities for Group 1 and 2 Carpenters Albany Coos Bay Klamath Falls Newport Rosburg Astoria Eugene La Grande Ontario Salem Baker City Goldendale Lakeview Pendleton The Dalles Bend Grants Pass Longview Portland Tillamook Brookings Hermiston Madras Port Orford Vancouver Burns Hood River Medford Reedsport Reference Cities for Group 3 Carpenters Eugene Medford Portland Vancouver Longview North Bend The Dalles Reference Cities for Group 5 and 6 Carpenters Bend Longview North Bend Eugene Medford Portland Note: All job or project locations shall be computed (determined)on the basis of road miles and in the following manner. A mileage measurement will start at the entrance to the respective city hall, facing the project (if possible), and shall proceed by the normal route (shortest time--best road via Google Maps)to the geographical center on the highway, railroad, and street construction projects (end of measurement). On all project contracts, the geographical center where the major portion of the construction is located shall be considered the center of the project(end measurement). Groups 1, 2, 5, and 6: ■ Welders shall receive a 5% premium per hour based on their Group's journeyman wage rate, with an 8-hour minimum. Groups 1, 2, and 3: ■ When working with toxic treated wood, workers shall receive $.25/hour premium pay for minimum of eight (8) hours. Groups 5 and 6: ■ When working with creosote and other toxic treated wood, workers shall receive $.25/hour premium pay for minimum of eight(8) hours.. Group 6: ■ When working in sheet pile coffer dams or cells up to the external water level, workers shall receive$0.15/hour premium pay for minimum of eight (8) hours. PAGE 6 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate CEMENT MASON ■ This trade is tended by "Concrete Laborer." Base Rates Group 1 48.13 23.39 Group 2 49.13 23.39 Group 3 49.13 23.39 Group 4 50.13 23.39 Zone Differential for Cement Mason -Add to Basic Hourly Rate Zone A: 3.00 per hour Zone B: 5.00 per hour Zone C: 10.00 per hour Zone A: Projects located 60-79 miles of the respective city hall of the Reference Cities listed below. Zone B: Projects located 80-99 miles of the respective city hall of the Reference Cities listed below. Zone C: Projects located 100 or more miles of the respective city hall of the Reference Cities listed below. Reference Cities for Cement Mason Bend Eugene Pendleton Salem Vancouver Corvalis Medford Portland The Dalles DIVER & DIVER TENDER Zone 1 (Base Rates) DIVER 109.83 21.40 DIVER TENDER 65.82 21.40 Zone Differential Any Diver or Diver's Tender working on a project more than 50 miles from Portland, OR city hall shall receive forty dollars ($40.00) per day in addition to their regular pay. Miles are calculated via the "shortest route"filter using Google Maps from Portland, OR city hall or the employee's primary residence; whichever one is closer. Diver Depth Pay Depth Below Water Surface (FSW) Daily Depth Pay 50— 100 ft: 2.00 per foot over 50 feet 101 — 150 ft: 3.00 per foot over 100 feet 151 —220 ft: 4.00 per foot over 150 feet Over 220 ft: 5.00 per foot over 220 feet The actual depth in FSW shall be used in determining depth premium. See more information on Premium Pay on page 8. PAGE 7 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate DIVER & DIVER TENDER (continued) Diver Enclosure Pay(working without vertical escape) Distance Traveled in the Enclosure Daily Enclosure Pay 0—25 ft: N/C 25—300 ft: 1.00 per foot from the entrance 300—600ft: 1.50 per foot beginning at 300 ft. Over 600 ft: 2.00 per foot beginning at 600 ft. DREDGER Zone A(Base Rates) Leverman (Hydraulic &Clamshell) 61.80 17.55 Assistant Engineer (Watch Engineer, Mechanic Machinist) 58.64 17.55 Tenderman (Boatman Attending Dredge Plant), Fireman 57.15 17.55 Fill Equipment Operator 55.98 17.55 Assistant Mate 53.28 17.55 Zone Differential for Dredgers—Add to Zone A Base Rate Zone B: 3.50 per hour Zone C: 6.50 per hour • Zone milage based on road miles Zone A: Center of jobsite to no more than 30 miles from the City Hall of Portland. Zone B: Center of jobsite that is more than 30 miles but not more than 60 miles from the City Hall of Portland. Zone C: Center of jobsite that is over 60 miles from the City Hall of Portland. DRYWALL, LATHER, ACOUSTICAL CARPENTER & CEILING INSTALLER Base Rates DRYWALL INSTALLER 56.49 18.01 LATHER, ACOUSTICAL CARPENTER & CEILING INSTALLER 56.49 18.01 Zone Differential for Lather, Acoustical Carpenter& Ceiling Installer—Add to Base Rate Zone A: 6.00 per hour Zone B: 9.00 per hour Zone C: 12.00 per hour See more information on Zone Pay and Premium Page on page 9. PAGE 8 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate DRYWALL, LATHER, ACOUSTICAL CARPENTER & CEILING INSTALLER (continued) • Zone mileage based on road miles: Zone A: 61 —80 miles from the city hall of the reference cities listed below. Zone B: 81 — 100 miles from the city hall of the reference cities listed below. Zone C: 101 or more miles from the city hall of the reference cities listed below. • The correct transportation allowance shall be based on AAA road mileage from the City Hall of the transportation reference cities listed herein: Reference Cities for Drywall, Lather,Acoustical Carpenter&Ceiling Installer Albany Brookings Klamath Falls Pendleton Seaside Astoria Coquille Kelso-Longview Portland The Dalles Baker Eugene Medford Reedsport Tillamook Bandon Grants Pass Newport Roseburg Vancouver Bend Hermiston North Bend Salem • Certified welders shall receive 5% over the base wage rate, with an eight (8) hour minimum. ELECTRICIAN Electrician/Limited Energy Electrician Area Map uatsop Colombia ti j ry umahIla U.Won��A,,� 1 Wallows .4.% Multnomah Hood RN L f Ilamook It°as' Morrow r Vamhill AREA 5 G'l m Clackamas —) Was(o Polk Manor Ci j AREA 2 wheeler Baker AREA 3 i'r,ialn S Jette „„ton�' inn C Grant —� AREA 4 - Crook Deschutes AREA 1 Haney Malheur Coos Douglas AREA 6 lake Klamath Cunt' Josephine Jackson PAGE 9 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ELECTRICIAN (continued) Note: If you are unable to determine the area of a project located on or near the cross-county boundaries marked in red on the map, call or email the BOLT Prevailing Wage Rate Coordinator at (971) 245-3844 or ✓VR.email@boli.oregon.gov. Area 1 Base Rates Electrician 45.33 20.41 Wireman Welder/Cable Splicer 49.86 20.66 Reference County Malheur Shift Differential* 1st Shift"Day" Between the hours of 8:00am and 4:30pm 8 hours pay for 8 hours work. 2nd Shift"Swing" Between the hours of 4:30pm and 1:00am 8 hours pay for 8 hours'work plus 10%for all hours worked. 3rd Shift"Graveyard" Between the hours of 12:30am and 9:00am 8 hours pay for 8 hours work plus 15%for all hours worked. *The Employer shall be permitted to adjust the starting hours of the shift by up to two (2) hours. • Work will be paid at time and one half the regular rate: (1) When workmen are under compressed air or where gas masks are required. (2)When working tunnels or shafts where danger of falling rocks or other debris exists. (3)When working from suspended or swinging scaffolds or boson's chairs. Area 2 Base Rates Electrician 63.00 28.47 Cable Splicer 66.15 28.56 Certified Welder 78.75 28.94 Material Handler 37.80 20.76 Reference Counties Baker Grant Umatilla Wallowa Gilliam Morrow Union Wheeler See more information on Premium Pay on page 11. PAGE 10 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ELECTRICIAN (continued) ■ Add 50% of the base rate when workers are required to work under the following conditions: 1) Under compressed air with atmospheric pressure exceeding normal pressure by at least 10%. 2) From trusses, swing scaffolds, bosun's chairs, open platforms, unguarded scaffolds, open ladders, frames, tanks, stacks, silos and towers where the workman is subject to a direct fall of(a) more than 60 feet or(b) into turbulent water under bridges, powerhouses or spillway faces of dams. Area 3 Base Rate Electrician 53.20 29.01 Reference Counties Coos Curry Douglas (a) Lane (a) Lincoln (a)Those portions of Lane and Douglas counties lying west of the red line on the Electrician Area Map posted above. Shift Differential* 1st Shift"Day" Between the hours of 8:00am and 4:30pm 8 hours pay for 8 hours work. 2nd Shift"Swing" Between the hours of 4:30pm and 1:00am 8 hours pay for 8 hours'work plus 17%for all hours worked. 3rd Shift"Graveyard" Between the hours of 12:30am and 9:00am 8 hours pay for 8 hours work plus 31%for all hours worked. *The Employer shall be permitted to adjust the starting hours of the shift by up to two (2) hours. • When workers are required to work under compressed air or where gas masks are required, or to work from trusses, all scaffolds including mobile elevated platforms, any temporary structure, bosun's chair or on frames, stacks, towers, tanks, within 15' of the leading edges of any building at a distance of**: 1) 50—70 feet to the ground Add 1 1/2 x the base rate 2) 75+feet to the ground Add 2 x the base rate ** High Time is not required to be paid on any permanent structure with permanent adequate safeguards (handrails, mid- rails, and toe guards). Any vehicle equipped with outriggers are exempted from this section. Area 4 Base Rates Electrician 59.34 26.17 Cable Splicer 65.27 26.35 Lighting Maintenance/ Material Handler 31.60 11.45 See more information on Zone Pay and Shift Differential on page 12. PAGE 11 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ELECTRICIAN (continued) Reference Counties Benton Deschutes Lane(b) Marion Yamhill(c) Crook Jefferson Linn Polk (b)Those portions of Lane and Douglas counties lying east of the red line on the Electrician Area Map posted above. (c)The portion of Yamhill county lying south of the red line on the Electrician Area Map posted above. Shift Differential* 1st Shift"Day" Between the hours of 8:00am and 4:30pm 8 hours pay for 8 hours work. 2nd Shift"Swing" Between the hours of 4:30pm and 1:00am 8 hours pay for 8 hours'work plus 17%for all hours worked. 3rd Shift"Graveyard" Between the hours of 12:30am and 9:00am 8 hours pay for 8 hours work plus 31.4%for all hours worked. *The Employer shall be permitted to adjust the starting hours of the shift by up to two (2) hours. Area 5 Base Rates Electrician 65.50 34.04 Electrical Welder 72.05 34.23 Material Handler/Lighting Maintenance 37.34 24.08 Reference Counties Clackamas Columbia Multnomah Tillamook Washington Clatsop Hood River Sherman Wasco Yamhill (d) (d)The portion of Yamhill County lying north of the red line on the Electrician Area Map posted above. Shift Differential* 1st Shift"Day" Between the hours of 7:00am and 5:30pm 8 hours pay for 8 hours work. 2nd Shift"Swing" Between the hours of 4:30pm and 3:00am 8 hours pay for 8 hours'work plus 17.3%for all hours worked. 3rd Shift"Graveyard" Between the hours of 12:30am and 11:00am 8 hours pay for 8 hours work plus 31.4%for all hours worked. *The Employer shall be permitted to adjust the starting hours of the shift by up to two (2) hours. See more information on Zone Differential and Premium Pay on page 13. PAGE 12 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ELECTRICIAN (continued) Zone Differential for Electrician and Electrical Welder—Add to Basic Hourly Rate Zone 1: 1.50 per hour Zone 2: 3.50 per hour Zone 3: 5.50 per hour Zone 4: 9.00 per hour Zone mileage based on air miles. Zone 1: 31 —50 miles from the city hall of the reference cities listed below. Zone 2: 51 —70 miles from the city hall of the reference cities listed below. Zone 3: 71 —90 miles from the city hall of the reference cities listed below. Zone 4: Beyond 90 miles from the city hall of the reference cities listed below. Reference Cities* Astoria Portland The Dalles Hood River Seaside Tillamook *There shall be a 30-mile free zone from downtown Portland City Hall and a similar 15-mile free zone around the other listed reference cities. Further, the free zone at the Oregon coast shall extend along Hwy 101 west to the ocean Hwy 101 east 10 miles if not already covered by the above 15-mile free zone. • When workers are performing electrical work on a structure at or above the 90 ft. level directly above the ground, floor, roadway, roof or water where scaffolding or special safety devices which have not been approved by the Occupational Safety and Health Administration are used, the wage rate for such work shall be double the straight time hourly rate. Area 6 Base Rates Electrician 47.04 21.84 Material Handler/Lighting Maintenance 25.53 11.21 Reference Counties Douglas (e) Jackson Klamath Harney Josephine Lake Shift Differential* 1st Shift"Day" Between the hours of 8:00am and 4:30pm 8 hours pay for 8 hours work. 2nd Shift"Swing" Between the hours of 4:30pm and 1:00am 8 hours pay for 8 hours'work plus 7.5%for all hours worked. 3rd Shift"Graveyard" Between the hours of 12:30am and 9:00am 8 hours pay for 8 hours work plus 15%for all hours worked. *The Employer shall be permitted to adjust the starting hours of the shift by up to two (2) hours See more information about Premium Pay on page 14. PAGE 13 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ELECTRICIAN (continued) ■ When workers are required to work under compressed air or to work from trusses, scaffolds, swinging scaffolds, bosun's chair or on building frames, stacks or towers at a distance, the following should be added to base rate: 1) 50—90 feet to the ground Add 1 '/2 x the base rate* 2) 90+ feet to the ground Add 2 x the base rate* *When such work is performed outside of the regularly scheduled working hours,workmen shall be paid three(3)times the regular rate of pay.An assignment of work referred to in this Section shall entitle the workman to the premium rate for a period of at least two(2) hours. ELEVATOR CONSTRUCTOR, INSTALLER AND MECHANIC Area 1 Base Rate Mechanic: 70.47 44.62 Reference Counties Baker Union Wallowa Umatilla—See Area 2 Rate Area 2 Base Rate Mechanic: 70.76 44.65 Reference Counties Benton Deschutes Jefferson Malheur Umatilla Clackamas Douglas Josephine Marion Wasco Clatsop Gilliam Klamath Morrow Washington Columbia Grant Lake Multnomah Wheeler Coos Harney Lane Polk Yamhill Crook Hood River Lincoln Sherman Curry Jackson Linn Tillamook FENCE CONSTRUCTOR (NON-METAL) Base Rate: 42.74 19.40 FENCE ERECTOR (METAL) Base Rate: 42.74 19.40 PAGE 14 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate GLAZIER Base Rate: 54.82 23.39 • Add $1.00 to base rate when employee works from a swing stage, scaffold, suspended contrivance or mechanical apparatus from the third floor up or thirty feet of free fall (whichever is less), and employee is required to wear a safety belt. • Add twenty percent (20%)to base rate when employee works from a bosun chair (non-motorized single-man apparatus), regardless of height. • Certified welders shall receive twenty percent (20%) above the base rate for actual time spent performing welding duties. HAZARDOUS MATERIALS HANDLER Base Rate: 33.03 18.18 HIGHWAY/PARKING STRIPER Base Rate: 71.89 22.48 IRONWORKER Zone 1 (Base Rate): 49.80 34.98 Zone Differential for Ironworker—Add to Base Hourly Rate Zone 2: 8.13/hr. or$65.00 maximum per day Zone 3: 11.25/hr. or$90.00 maximum per day Zone 4: 16.25/hr. or$130.00 maximum per day Zone 1: Projects located within 45 miles of city hall in the reference cities listed below. Zone 2: Projects located more than 46 miles, but less than 60 miles. Zone 3: Projects located more than 61 miles, but less than 100 miles. Zone 4: Projects located more than 100 miles. Note: Zone pay for Ironworkers shall be determined using the quickest route per Google Maps and computed from the city hall or dispatch center of the reference cities listed below or the residence of the employee, whichever is nearer to the project. Reference Cities and Dispatch Center Portland PAGE 15 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate LABORER Zone A(Base Rates) Group 1 (includes Flagger) 42.74 19.40 Group 2 44.18 19.40 Group 3 44.73 19.40 Group 4 37.54 19.40 Group 5 (Landscape Laborer) 30.53 19.40 Zone Differential for Laborers—Add to Zone A Base Rate Zone B: 0.85 per hour Zone C: 1.25 per hour Zone D: 2.00 per hour Zone E: 4.00 per hour Zone F: 5.00 per hour Zone A: Projects located within 30 miles from the city hall in the reference cities listed (below). Zone B: Projects located more than 30 miles but less than 40 miles from the city hall in the reference cities listed. Zone C: Projects located more than 40 miles but less than 50 miles from the city hall in the reference cities listed. Zone D: Projects located more than 50 miles but less than 80 miles from the city hall in the reference cities listed. Zone E: Projects located more than 80 miles but less than 100 miles from the city hall in the reference cities listed. Zone F: Projects located more than 100 miles from the city hall in the reference cities listed. Reference Cities for Laborer Albany Bend Eugene Klamath Falls Roseburg Astoria Burns Grants Pass Medford Salem Baker City Coos Bay Hermiston Portland The Dalles Note: All job or project locations shall be computed (determined)on the basis of road miles and in the following manner. A mileage measurement will start at the entrance to the respective city hall, facing the project (if possible), and shall proceed by the normal route (shortest time, best road)to the geographical center on the highway, railroad, and street construction projects (end of measurement). On all other project contracts, the geographical center where the major portion of the construction is located shall be considered the center of the project(end measurement). ■ Any Laborer working in Live Sewers shall receive forty dollars ($40) per day in addition to their regular pay. LANDSCAPE LABORER/TECHNICIAN (Laborer Group 5) Base Rate: See Laborer Group 5 Rate PAGE 16 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate LIMITED ENERGY ELECTRICIAN Electrician/Limited Energy Electrician Area Map CI Cok,n b,a , I J Multrwmah ,Hood Riven Wallows �llamookr ., 'am Morrow r Yam AREAS I G" -� Limon Ysrnhill Clackamas Wsxo Polk Wheeler AREA 2 Baker AREA 3 "^'r, Jefferson „, llrlh Fj Grant AREA 4 Dischut. [1 1 AREA 1 Coos nlaS °° AREA h Klamath Curry Josephlnh JadsOh Note: If you are unable to determine the area of a project located on or near the cross-county boundaries marked in red on the map, call or email the BOLT Prevailing Wage Rate Coordinator at (971)245-3844 or WR.email@boli.oregon.gov. Area 1 Base Rate: 37.90 18.10 Reference County Malheur Area 2 Base Rate: 40.47 18.76 Reference Counties Baker Grant Umatilla Wallowa Gilliam Morrow Union Wheeler PAGE 17 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate LIMITED ENERGY ELECTRICIAN (continued) Area 3 Base Rate: 43.11 26.08 Reference Counties Coos Douglas (a) Lincoln Curry Lane (a) (a)Those portions of Lane and Douglas counties lying west of the red line on the Electrician Area Map posted above. Area 4 Base Rate: 44.79 20.39 Reference Counties Benton Deschutes Lane (b) Marion Yamhill (c) Crook Jefferson Linn Polk (b)Those portions of Lane and Douglas counties lying east of the red line on the Electrician Area Map posted above. (c)The portion of Yamhill county lying south of the red line on the Electrician Area Map posted above. Area 5 Base Rate: 54.50 28.76 Reference Counties Clackamas Columbia Multnomah Tillamook Washington Clatsop Hood River Sherman Wasco Yamhill (d) (d)The portion of Yamhill county lying north of the red line on the Electrician Area Map posted above. Area 6 Base Rate: 36.58 19.00 Reference Counties Douglas (e) Jackson Klamath Harney Josephine Lake (e)The portion of Douglas county lying east of the red line on the Electrician Area Map posted above. PAGE 18 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate LINE CONSTRUCTOR Area 1 (ALL Regions) Base Rates Group 1 79.24 28.27 Group 2 70.75 27.88 Group 3 41.12 17.94 Group 4 60.85 24.24 Group 5 53.06 19.89 Group 6 42.45 19.41 Group 7 22.84 14.16 Reference Counties All counties in Oregon Pursuant to ORS 279C.815(2)(b), the Line Constructor Area 1 rate is the highest rate of wage among the collective bargaining agreements for Line Constructor Area 1 and Area 2. Shift Differential 1st Shift (Groups 1,2, 4, 5, & 6) Between the hours of 8:00am and 4:30pm Base rate. 2nd Shift (Groups 1,2, 4, 5, & 6) Between the hours of 4:30pm and 12:00am Add 10% per hour to base rate. 3rd Shift(Groups 1,2, 4, 5, & 6) Between the hours of 12:00am and 8:00am Add 15% per hour to base rate. MARBLE SETTER Base Rate: 52.47 26.64 • This trade is tendered by "Tile, Terrazzo, & Marble Finishers." • Add $1.00 per hour to base rate for refractory repair work. PAINTER & DRYWALL TAPER Base Rates COMMERCIAL PAINTING 38.12 17.22 INDUSTRIAL PAINTING 40.34 17.22 BRIDGE PAINTING 47.77 17.22 See more information on Shift Differential and Zone Pay on page 20. PAGE 19 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate PAINTER & DRYWALL TAPER (continued) Shift Differential for Painter ■ Add $3.00/hour to base rate for all hours worked when the employee's scheduled shift starts between 1:30PM and 1:30AM. DRYWALL TAPER Zone A(Base Rate): 50.52 22.03 Zone Differential for Drywall Taper—Add to Zone A Base Rate Zone B: 6.00 per hour Zone C: 9.00 per hour Zone D: 12.00 per hour Zone A: Projects located less than 61 miles from the respective city hall of the dispatch cities listed below. Zone B: Projects located 61 miles to 80 miles from the respective city hall of the dispatch cities listed below. Zone C: Projects located 81 miles to 100 miles from the respective city hall of the dispatch cities listed below. Zone D: Projects located 101 miles or more from the respective city hall of the dispatch cities listed below. Dispatch Cities for Drywall Taper Albany Bend Grants Pass Medford Portland Seaside Astoria Brookings Hermiston Newport Reedsport The Dalles Baker Coquille Klamath Falls North Bend Roseburg Tillamook Bandon Eugene Kelso-Longview Pendleton Salem Vancouver Note: Zone pay is based on AAA road milage. PLASTERER AND STUCCO MASON • This trade is tended by"Tenders to Plasterers." Zone A(Base Rate) 46.56 19.83 Zone Differential for Plasterer and Stucco Mason —Add to Zone A Base Rate Zone B: 6.00 per hour Zone C: 9.00 per hour Zone D: 12.00 per hour Zone A: Projects located less than 61 miles from the respective city hall of the reference cities listed below. Zone B: Projects located 61 miles to 80 miles from the respective city hall of the reference cities listed below. Zone C: Projects located 81 miles to 100 miles from the respective city hall of the reference cities listed below. Zone D: Projects located 101 miles or more from the respective city hall of the reference cities listed below. Reference Cities for Plasterer&Stucco Mason Bend Eugene Medford Portland Seaside Coos Bay La Grande Newport Salem The Dalles • Add $1.00 to base rate for swinging scaffold work. • Add $2.00 to base rate for nozzle technicians on plastering machines. PAGE 20 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate PLUMBER/PIPEFITTER/STEAM FITTER Area 1 Reference Counties Harney—See Area 3 rates Malheur—See Area 3 rates Baker—See Area 2 rates Area 2 Zone 1 (Base Rate): 65.20 37.91 Reference Counties Baker Grant Union Wallowa Gilliam Marrow Umatilla Wheeler Zone Differential for Area 2—Add to Base Rate Zone 2: 10.62/hr. not to exceed $80.00 per day Zone 2: Eighty (80) miles or more from City Hall in Pasco, Washington. Note: Zone milage based on road miles. • Add $1.00 to base rate in one-hour minimum increments if it is possible for worker to fall 35 ft. or more. • Add $1.00 to base rate in one-hour minimum increments if worker is required to wear a mask in hazardous areas. Area 3 Base Rate: 62.87 37.10 Reference Counties Benton Curry Jefferson Linn Tillamook Clackamas Deschutes Josephine Malheur Wasco Clatsop Douglas Klamath Marion Washington Columbia Harney Lake Multnomah Yamhill Coos Hood River Lane Polk Crook Jackson Lincoln Sherman Gilliam —See Area 2 rates Grant—See Area 2 rates Morrow —See Area 2 rates Umatilla—See Area 2 rates Wheeler—See Area 2 rates PAGE 21 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate POWER EQUIPMENT OPERATOR POWER EQUIPMENT OPERATOR MAP ZONE 1 SSW CLAT OP UMSIA1 IMO r 011111 • •Ce W TIllAYO �` NMI sift sirSIASHI GT 0 I ► MOO } . rAUHRL � t • HOOD- "Qrs. . L 4f K\AAA S � v....� ..... .m,.a. • ..... , NAIL POLKA�'� +A' '�1�( MARICN 1. „.w n ..,� FOREST Zone 1 (Base Rates) Group 1 61.99 17.55 Group 1A 64.15 17.55 Group 1B 66.31 17.55 Group 2 60.08 17.55 Group 3 58.93 17.55 Group 4 55.60 17.55 Group 5 54.36 17.55 Group 6 51.14 17.55 Zone Pay Differential for Power Equipment Operator—Add to Zone 1 Base Rate Zone 2: 3.50 per hour Zone 3: 6.50 per hour See more information on Zone Pay and Premium Pay on page 23. PAGE 22 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate POWER EQUIPMENT OPERATOR (continued) For projects in the following metropolitan counties: Clackamas Marion Washington Columbia Multnomah Yamhill a) All jobs or projects located in Multnomah, Clackamas and Marion counties, West of the western boundary of Mt. Hood National Forest and West of Mile Post 30 on Interstate 84 and West of Mile Post 30 on State Hwy 26 and West of Mile Post 30 on Hwy 22 and all jobs located in Yamhill County, Washington County and Columbia County shall receive Zone 1 pay for all classifications. b) All jobs or projects located in the area outside the identified boundary above (white area on map), but less than 50 miles from Portland City Hall shall receive Zone 2 pay for all classifications. c) All jobs or projects located more than 50 miles from Portland City Hall, but outside the identified border above, shall receive Zone 3 pay for all classifications. Reference cities for projects in all remaining counties: Albany Coos Bay Grants Pass Medford Bend Eugene Klamath Falls Roseburg a) All jobs or projects located within 30 miles of the respective city hall of the above mentioned cities shall receive Zone 1 pay for all classifications. b) All jobs or projects located more than 30 miles and less than 50 miles from the respective city hall of the above mentioned cities shall receive Zone 2 for all classifications. c) All jobs or projects located more than 50 miles from the respective city hall of the above mentioned cities shall receive Zone 3 pay for all classifications. Note: All job or project locations shall be computed (determined)on the basis of road miles and in the following manner. A mileage measurement will start at the entrance to the respective city hall, facing the project (if possible), and shall proceed by the normal route (shortest time-best road)to the geographical center on the highway, railroad, and street construction projects (end of measurement). On all other project contracts, the geographical center where the major portion of the construction is located, shall be considered the center of the project (end measurement). • Add $10.00/hour hyperbaric pay for Group 4 Tunnel Boring Machine Mechanic. • Add $0.40 to the base rate for any and all work performed underground, including operating, servicing and repairing of equipment. • Add $0.50 to the base rate per hour for any employee who works suspended by a rope or cable. • Add $0.50 to the base rate for employees who do"pioneer"work (break open a cut, build road, etc.) more than one hundred fifty (150)feet above grade elevation. Note: A Hazardous Waste Removal Differential must be added to the base rate if work is performed inside the boundary of a Federally Designated Waste Site. For information on this differential, call the Prevailing Wage Rate Coordinator at (971)245-3844. See more information on Zone Differential on page 24. PAGE 23 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate POWER EQUIPMENT OPERATOR (continued) Shift Differential Two-Shift Operations: ■ On a two-shift operation, when the second shift starts after 4:30 p.m., second-shift workers shall be paid the base hourly wage rate plus 5% for all hours worked. ■ When the second shift starts at 8:00 p.m. or later, the second-shift workers shall be paid at the base hourly wage rate plus 10% for all hours worked. Three-Shift Operations: ■ On a three-shift operation, the base hourly wage rate plus five percent (5%) shall be paid to all second-shift workers for all hours worked, and the base hourly wage rate plus ten percent(10%) shall be paid to all third shift workers for all hours worked. ROOFER Area 1 Base Rate: 44.51 22.70 Reference Counties Baker Crook Hood River Sherman Wasco Clackamas Deschutes Jefferson Tillamook Wallowa Clatsop Gilliam Marrow Umatilla Washington Columbia Grant Multnomah Union Wheeler ■ Add 10% to the base rate for handling coal tar pitch or coal tar-based materials. • Add 10%to the base rate for handling fiberglass insulation. Area 2 Base Rate: 40.88 20.49 Reference Counties Benton Harney Lake Malheur Coos Jackson Lane Marion Curry Josephine Lincoln Polk Douglas Klamath Linn Yamhill Crook—See Area 1 rates Deschutes—See Area 1 rates • Application, spudding and cutting or removal of coal tar products 10% over basic wage scale. • Application, spudding and cutting fiberglass insulation add a 10% over the basic wage scale. PAGE 24 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate ROOFER (continued) Area 4 Base Rate: 44.51 22.70 Reference Counties Umatilla Union Wallowa • Add 10% to the base rate for handling coal tar pitch or coal tar-based materials. • Add 10% to the base rate for handling fiberglass insulation. Pursuant to ORS 279C.815(2)(b), the Roofer Area 1 rate is the highest rate of wage among the collective bargaining agreements for Roofer Areas 1, 4 and 5. Area 5 Base Rate: 44.51 22.70 Reference County Morrow • Add 10% to the base rate for handling coal tar pitch or coal tar-based materials. • Add 10% to the base rate for handling fiberglass insulation. Pursuant to ORS 279C.815(2)(b), the Roofer Area 1 rate is the highest rate of wage among the collective bargaining agreements for Roofer Areas 1, 4 and 5. SHEET METAL WORKER Area 1 Base Rate: 59.24 35.27 Reference Counties Benton Deschutes Lincoln Polk Washington Clackamas Gilliam Linn Sherman Wheeler Clatsop Grant Marion Tillamook Yamhill Columbia Hood River Morrow Umatilla Crook Jefferson Multnomah Wasco Swing Shift Operations: • When a second (or"swing") shift starts between 2:00pm -7:00pm, second-shift workers shall be paid the base hourly wage rate plus $8.70 for all hours worked. See more information on Shift Differential and Premium Pay on page 26. PAGE 25 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate SHEET METAL WORKER (continued) Graveyard Shift Operations: • When the second (or"graveyard") shift starts between 7:00pm— 1:00am, second-shift workers shall be paid the base hourly wage rate plus $13.34 for all hours worked. ■ Add 10% to base rate for work performed on any swinging platform, swinging chair or swinging ladder. • Add 10% to base rate for work where a worker is exposed to resins, chemicals, or acid. Area 2 Reference Counties Baker—See Area 3 rate Malheur—See Area 4 rate Area 3 Base Rate: 50.00 28.37 Reference Counties Baker Union Wallowa Morrow—See Area 1 rate Umatilla—See Area 1 rate ■ Add $.45 to base rate for work performed on any swinging stage, swinging scaffold or boson chair in excess of thirty (30)feet above the ground. ■ Add $1.00 to base rate for work where it is necessary to wear a chemically activated type face mask. Area 4 Base Rate: 47.69 32.58 Reference Counties Douglas Jackson Klamath Lane Harney Josephine Lake Malheur Coos—See Area 5 rate Curry—See Area 5 rate Swing Shift Operations: ■ When a second (or"swing") shift starts between 2:00pm -7:00pm, second-shift workers shall be paid the base hourly wage rate plus $7.09 for all hours worked. Graveyard Shift Operations: ■ When the second (or"graveyard") shift starts between 7:00pm— 1:00am, second-shift workers shall be paid the base hourly wage rate plus $10.87 for all hours worked. ■ Add 10% to base rate for work performed on any swinging platform, swinging chair or swinging ladder. • Add 10% to base rate for work where a worker is exposed to resins, chemicals, or acid. PAGE 26 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate SHEET METAL WORKER (continued) Area 5 Base Rate: 47.33 34.34 Reference Counties Coos Curry Swing Shift Operation: • When a second (or"swing") shift starts between 2:00pm -7:00pm, second-shift workers shall be paid the base hourly wage rate plus $7.15 for all hours worked. Graveyard Shift Operation • When the second (or"graveyard") shift starts between 7:00pm— 1:00am, second-shift workers shall be paid the base hourly wage rate plus $10.96 for all hours worked. • Add 10% to base rate for work performed on any swinging platform, swinging chair or swinging ladder. • Add 10% to base rate for work where a worker is exposed to resins, chemicals, or acid. SOFT FLOOR LAYER Base Rate: 45.78 19.40 SPRINKLER FITTER Area 1 Base Rate: 54.74 28.87 Reference Counties Benton Deschutes Jefferson Malheur Umatilla Clackamas Douglas Josephine Marion Wasco Clatsop Gilliam Klamath Morrow Washington Columbia Grant Lake Multnomah Wheeler Coos Harney Lane Polk Yamhill Crook Hood River Lincoln Sherman Curry Jackson Linn Tillamook PAGE 27 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate SPRINKLER FITTER (continued) Area 2 Base Rate: 47.11 28.86 Reference Counties Baker Unions Wallowa Gilliam—See Area 1 rate Malheur—See Area 1 rate Umatilla—See Area 1 rate Grant — See Area 1 rate Morrow —See Area 1 rate TENDER TO MASON TRADES (Brick and Stonemason, Mortar Mixer, Hod Carrier) Base Rate: 47.44 18.90 ■ Add $0.50 to base rate for refractory repair work. TENDER TO PLASTERER AND STUCCO MASON Zone A(Base Rate): 46.59 19.40 Zone Differential for Tender to Plasterer and Stucco Mason — Add to Zone A Base Rate Zone B: 6.00 per hour Zone C: 9.00 per hour Zone D: 12.00 per hour Zone A: Projects located within 60 miles from the city hall in the reference cities listed below. Zone B: More than 61 miles but less than 80 miles from the city hall in the reference cities listed below. Zone C: More than 81 miles but less than 100 miles from the city hall in the reference cities listed below. Zone D: More than 101 miles from the city hall in the reference cities listed below. Reference Cities Bend Eugene Medford Portland Seaside Coos Bay La Grande Newport Salem The Dalles • Add $0.50 to base rate for refractory repair work. TESTING AND BALANCING (TAB) TECHNICIAN • For work performed under the sheet Meta classification, including Air-Handling Equipment, Ductwork: See SHEET METAL WORKER RATE • For work performed under the Plumber/Pipefitter/Steamfitte classification, including Water Distribution Systems: See PLUMBER/PIPEFITTER/STEAMFITTER RATE PAGE 28 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate TILE SETTER/TERRAZZO WORKER: Hard Tile Setter Base Rate: 44.42 23.01 • This trade is tended by"Tile, Terrazzo, & Marble Finisher." • Add $2.00 when performing terrazzo work. • Add $1.00 to base rate when working with epoxy, furnane, or alkor acetylene. TILE, TERRAZZO, AND MARBLE FINISHER Base Rates TILE, TERRAZZO FINISHER: 32.92 17.43 • Add $2.00 per hour to base rate when performing terrazzo work. • Add $1.00 per hour to base rate when working with epoxy, furnane, or alkor acetylene. 2. BRICK& MARBLE FINISHER: 32.92 17.56 • Add $1.00 per hour to base rate for refractory repair work. TRUCK DRIVER Zone A(Base Rates) Group 1 37.17 19.23 Group 2 37.34 19.23 Group 3 37.51 19.23 Group 4 37.87 19.23 Group 5 38.16 19.23 Group 6 38.39 19.23 Group 7 38.65 19.23 Zone Differential for Truck Drivers— Add to Zone A Base Rate Zone B: 0.65 per hour Zone C: 1.15 per hour Zone D: 1.70 per hour Zone E: 2.75 per hour Zone A: Projects within 30 miles from the cities listed below. Zone B: More than 30 miles but less than 40 miles from the cities listed below. Zone C: More than 40 miles but less than 50 miles from the cities listed below. Zone D: More than 50 miles but less than 80 miles from the cities listed below. Zone E: More than 80 miles from the cities listed below. See more information on Zone Pay on page 30. PAGE 29 JULY 5,2026 Occupation and Premium/Differential Pay Base Rate / Fringe Rate TRUCK DRIVER (continued) Reference Cities Albany Burns Hermiston Madras Pendleton The Dalles Astoria Coos Bay Hood River Medford Portland Tillamook Baker Corvallis Klamath Falls McMinnville Port Orford Vancouver Bend Eugene La Grande Newport Reedsport Bingen Goldendale Lakeview Ontario Roseburg Brookings Grants Pass Longview Oregon City Salem Note: All job or project locations shall be computed (determined) on the basis of road miles and in the following manner. A mileage measurement will start at the entrance to the respective city hall, facing the project (if possible), and shall proceed by the normal route (shortest time-best road)to the geographical center on the highway, railroad, and street construction projects (end of measurement). On all other project contracts, the geographical center where the major portion of the construction is located shall be considered the center of the project (end measurement). PAGE 30 JULY 5,2026 LIST OF CONTRACTORS INELIGIBLE TO RECEIVE PUBLIC WORKS CONTRACTS PUBLICATION DATE: JULY 5, 2026 To: All Oregon Contracting Agencies Pursuant to ORS 279C.860, contractors on this list are ineligible to receive public works contracts subject to the Prevailing Wage Rate Law. These contractors and subcontractors, as well as any firm, corporation, partnership or association in which the contractor or subcontractor has a financial interest are ineligible to receive public works contracts until removed from this list. You can find the most current and up to date list of contractors ineligible to receive public works contracts on our website at https://www.oregon.gov/boli/employers/Pages/pwr-ineligible- contractors.aspx. If you have questions regarding the list or for the most current information regarding persons ineligible to receive prevailing wage contracts, please contact the Prevailing Wage Rate Coordinator in Portland at (971) 245-3844. Date Removal Contractor Address placed date Al Dumptruck Services LLC 703 N Hayden Meadows Dr.,#206 2/24/2020 2/23/2027 Portland,OR 97213 731 N Hayden Meadows Dr.,#206 Portland,OR 97217 2408 NE 164th Avenue Vancouver,WA 98684 Cameron Creations,Steven Cameron, PO Box 2 5/25/2000 Nancy Cameron* Lowell,OR 97452 David Miller* 731 NW Naito Parkway,#215 6/17/2020 Portland,OR 97209 Eugene Graeme 169 SE Cody Lane 7/3/2017 7/2/2027 Madras,OR 97741 Lisa Hoang aka Kim Lien Hoang aka 703 N Hayden Meadows Dr.,#206 2/24/2020 2/23/2027 Lien Kim Hoang Portland,OR 97213 aka Kim Hope aka Lisa K Ryan aka Ryan Lien Hoang aka Kim L Hoang aka Lien 731 N Hayden Meadows Dr.,#206 Hoang Ryan aka Lien K Hoang-Ryan aka Portland,OR 97217 Hoang K Lien aka Lisa Hall aka Lisa Kim Ryan aka Lien Ryan aka Lien Hoang 2408 NE 164th Avenue Ryan aka Kim Hoang Lien aka K Lisa Vancouver,WA 98684 Hoang NW Flagging LLC 703 N Hayden Meadows Dr.,#206 2/24/2020 2/23/2027 Portland,OR 97213 731 N Hayden Meadows Dr.,#206 Portland,OR 97217 2408 NE 164th Avenue Vancouver,WA 98684 f PAGE 31 JULY 5, 2026 Date Removal Contractor Address placed date Oregon Building&Landscaping 703 N Hayden Meadows Dr.,#206 2/24/2020 2/23/2027 Services LLC Portland,OR 97213 731 N Hayden Meadows Dr.,#206 Portland,OR 97217 2408 NE 164th Avenue Vancouver,WA 98684 Pacific NW Drywall&Acoustics LLC 731 NW Natio Parkway#215 6/17/2020 aka Pacific NW Drywall&Acoustics Portland,OR 97209 LLC* Regional Traffic Management LLC 703 N Hayden Meadows Dr.,#206 2/24/2020 2/23/2027 Portland,OR 97213 731 N Hayden Meadows Dr.,#206 Portland,OR 97217 2408 NE 164th Avenue Vancouver,WA 98684 Sang In Nam dba Cornerstone 130 NE Danbury Ave 9/20/2016 Janitorial Services* Hillsboro, OR 97124 WCI Construction LLC 169 SE Cody Lane 7/3/2017 7/2/2027 Madras,OR 97741 * Not to be removed from debarment. PAGE 32 JULY 5, 2026 Prevailing Wage Rate Laws Handbook The 2026 edition of the Prevailing Wage Rate Laws Handbook is now available on our website at https://www.oregon.gov/boll/employers/Pages/prevailing-wage.aspx. In addition to providing this and other PWR publications, Oregon BOLT Labor & Industries' PWR Unit regularly offers free, informational seminars for both public agencies and contractors. The current schedule is available online at https://www.oregon.gov/boll/employers/Pages/prevailing-wage-seminars.aspx. If you are interested in being included on our mailing lists for future seminar notifications, please contact us at PWR.Email@boli.oregon.gov or (971) 245-3844. PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate ASBESTOS WORKER Period $64.37 1st Yr/1st 6 mos 45% $23.38 $19.03 $26.57 1st yr/2nd 6 mos 50% $26.71 $23.00 2nd Year/1 nd 6 mos 60% $33.36 $23.00 2nd Year/2nd 6 mos 60% $33.16 $28.82 3rd Year 75% $41.79 $32.52 4th Year 85% $48.44 $32.52 BOILERMAKER Hours $45.33 0-1000 70% $31.73 $32.22 $32.22 1001-2000 75% $34.00 $32.22 2001-3000 80% $36.26 $32.22 3001-4000 85% $38.53 $32.22 4001-5000 90% $40.80 $32.22 5001-6000 95% $43.06 $32.22 BRICK AND MARBLE FINISHER $32.92 1-1000 hrs $24.13 $16.84 $17.56 1001-2000 hrs $27.02 $16.84 BRICKLAYER Hours $51.47 1-1000 50% $25.74 $26.64 $26.64 1000-2000 55% $28.31 $26.64 2000-3000 60% $30.88 $26.64 3000-4000 70% $36.03 $26.64 4000-5000 80% $41.18 $26.64 5000-6000 90% $46.32 $26.64 CARPENTER Group 1 Period $56.69 1st 60% $34.01 $17.31 $17.81 2nd 65% $36.85 $17.31 3rd 70% $39.68 $17.81 4th 75% $42.52 $17.81 5th 80% $45.35 $17.81 6th 85% $48.19 $17.81 7th 90% $51.02 $17.81 8th 95% $53.86 $17.81 Page 1 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate CARPENTER(continued) Group 2 Period $56.86 1st 60% $34.12 $17.31 $17.81 2nd 65% $36.96 $17.31 3rd 70% $39.80 $17.81 4th 75% $42.65 $17.81 5th 80% $45.49 $17.81 6th 85% $48.33 $17.81 7th 90% $51.17 $17.81 8th 95% $54.02 $17.81 Group 3 Period $64.82 1st 60% $41.84 $18.63 $23.63 2nd 65% $44.72 $18.63 3rd 70% $47.59 $23.63 4th 75% $50.46 $23.63 5th 80% $53.33 $23.63 6th 85% $56.20 $23.63 7th 90% $59.08 $23.63 8th 95% $61.95 $23.63 Group 4-Eliminated Group 5 Period $58.06 1st 60% $34.84 $17.31 $17.81 2nd 73% $42.38 $17.31 3rd 75% $43.55 $17.81 4th 80% $46.45 $17.81 5th 83% $48.19 $17.81 6th 85% $49.35 $17.81 7th 90% $52.25 $17.81 8th 95% $55.16 $17.81 Group 6 Period $58.06 1st 60% $34.84 $17.31 $17.81 2nd 73% $42.38 $17.31 3rd 75% $43.55 $17.81 4th 80% $46.45 $17.81 5th 83% $48.19 $17.81 6th 85% $49.35 $17.81 7th 90% $52.25 $17.81 8th 95% $55.16 $17.81 Page 2 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate CEMENT MASON Hours $48.13 1-1000 55% $27.05 $21.99 $23.39 1001-2000 65% $32.04 $21.99 2001-3000 70% $34.54 $21.99 3001-4000 75% $37.04 $21.99 4001-5000 85% $42.04 $21.99 5001-6000 90% $44.53 $21.99 DRYWALL INSTALLER Period $56.49 1st 60% $33.89 $10.36 $18.01 2nd 65% $36.72 $10.36 3rd 70% $39.54 $18.01 4th 75% $42.37 $18.01 5th 80% $45.19 $18.01 6th 85% $48.02 $18.01 7th 90% $50.84 $18.01 8th 95% $53.67 $18.01 DRYWALL TAPER Hours $50.52 1st 1000 60% $30.31 $9.26 $22.03 2nd 1000 70% $35.36 $9.26 3rd 1000 75% $37.89 $22.03 4th 1000 80% $40.42 $22.03 5th 1000 85% $42.94 $22.03 6th 1000 90% $45.47 $22.03 ELECTRICIAN Area 1 $45.33 Period $20.41 1st 49% $22.21 $11.02 2nd 54% $24.48 $11.15 3rd 59% $26.74 $16.06 4th 64% $29.01 $16.59 5th 74% $33.54 $17.65 6th 84% $38.08 $18.72 Area 2 Period $63.00 1st 40% $25.20 $11.34 $28.47 2nd 45% $28.35 $19.02 3rd 50% $31.50 $19.88 4th 65% $40.95 $22.46 5th 80% $50.40 $25.03 6th 85% $53.55 $25.90 Page 3 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate ELECTRICIAN (continued) Area 3 Period $53.20 1st 50% $26.60 $13.65 $29.01 2nd 55% $29.26 $13.80 3rd 60% $31.92 $22.24 4th 65% $34.58 $23.09 5th 70% $37.24 $23.93 6th 80% $42.56 $25.62 Area 4 Period $59.34 1st 45% $26.70 $12.46 $26.17 2nd 50% $29.67 $12.62 3rd 55% $32.64 $20.08 4th 60% $35.60 $20.76 5th 70% $41.54 $22.11 6th 85% $50.44 $24.14 Area 5 Period $65.50 1st 40% $26.20 $15.74 $34.04 2nd 45% $29.48 $15.83 3rd 50% $32.75 $24.69 4th 60% $39.30 $26.64 5th 70% $45.85 $28.59 6th 85% $55.68 $31.51 Area 6 Period $47.04 1st 45% $21.17 $12.92 $21.84 2nd 50% $23.52 $12.99 3rd 55% $25.87 $17.54 4th 60% $28.22 $18.02 5th 65% $30.58 $18.50 6th 70% $32.93 $18.98 7th 75% $35.28 $19.45 8th 80% $37.63 $19.93 ELEVATOR CONSTRUCTOR Area 1 $70.47 Probationary 50% $35.24 $0.00 $44.62 1st Year 55% $38.76 $41.31 2nd Year 65% $45.81 $41.73 3rd Year 70% $49.33 $41.94 4th Year 80% $56.38 $42.37 Page 4 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate ELEVATOR CONSTRUCTOR(continued) Area 2 $70.76 Probationary 50% $35.38 $0.00 $44.65 1st Year 55% $38.92 $41.32 2nd Year 65% $45.99 $41.74 3rd Year 70% $49.53 $41.96 4th Year 80% $56.61 $42.38 FIRESTOP/CONTAINMENT WORKER Period $50.29 1st Year 55% $27.32 $11.17 $21.14 2nd Year 70% $32.28 $21.09 3rd Year 85% $39.93 $21.09 GLAZIER Period $54.82 1st 45% $24.67 $23.39 $23.39 2nd 55% $30.15 $23.39 3rd 65% $35.63 $23.39 4th 75% $41.12 $23.39 5th 80% $43.86 $23.39 6th 85% $46.60 $23.39 7th 90% $49.34 $23.39 8th 95% $52.08 $23.39 HIGHWAY PARKING STRIPER Hours $71.89 0-500 60% $43.13 $0.30 $22.48 501-1000 60% $43.13 $9.41 1001-2333 60% $43.13 $17.25 2nd period 73% $52.48 $18.95 3rd period 88% $63.26 $20.91 IRONWORKER Period $49.80 1st 65% $32.37 $15.48 $34.98 2nd 70% $34.86 $15.48 3rd 75% $37.35 $34.98 4th 80% $39.84 $34.98 5th 85% $42.33 $34.98 6th 90% $44.82 $34.98 7th 90% $44.82 $34.98 8th 95% $47.31 $34.98 Page 5 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate LABORER Group 1 $42.74 63% $26.93 $19.40 $19.40 70% $29.92 $19.40 80% $34.19 $19.40 90% $38.47 $19.40 Group 2 $42.74 63% $26.93 $19.40 $19.40 70% $29.92 $19.40 80% $34.19 $19.40 90% $38.47 $19.40 Group 3 $42.74 63% $26.93 $19.40 $19.40 70% $29.92 $19.40 80% $34.19 $19.40 90% $38.47 $19.40 Group 4 $42.74 63% $26.93 $19.40 $19.40 70% $29.92 $19.40 80% $34.19 $19.40 90% $38.47 $19.40 LATHER,ACOUSTICAL CARPENTER&CEILING INSTALLER Period $56.49 1st 60% $33.89 $10.36 $18.01 2nd 65% $36.72 $10.36 3rd 70% $39.54 $18.01 4th 75% $42.37 $18.01 5th 80% $45.19 $18.01 6th 85% $48.02 $18.01 7th 90% $50.84 $18.01 8th 95% $53.67 $18.01 LIMITED ENERGY ELECTRICIAN Area 1 Period $37.90 1st 50% $18.95 $10.65 $18.10 2nd 55% $20.85 $10.74 3rd 60% $22.74 $14.74 4th 65% $24.64 $15.16 5th 70% $26.53 $15.58 6th 80% $30.32 $16.42 Page 6 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate LIMITED ENERGY ELECTRICIAN (continued) Area 2 Period $40.47 1st 55% $22.26 $15.45 $18.76 2nd 60% $24.28 $15.82 3rd 65% $26.31 $16.19 4th 70% $28.33 $16.56 5th 80% $32.38 $17.29 6th 85% $34.40 $17.66 Area 3 Period $43.11 1st 55% $23.71 $24.83 $26.08 2nd 60% $25.87 $24.97 3rd 65% $28.02 $25.11 4th 70% $30.18 $25.25 5th 75% $32.33 $25.38 6th 85% $36.64 $25.66 Area 4 Period $44.79 1st 55% $24.63 $19.78 $20.39 2nd 60% $26.87 $19.85 3rd 65% $29.11 $19.92 4th 70% $31.35 $19.99 5th 75% $33.59 $20.05 6th 85% $38.07 $20.19 Area 5 Period $54.50 1st 6 months 50% $27.25 $15.47 $28.76 2nd 6 months 55% $29.98 $15.55 3rd 6 months 60% $32.70 $23.29 4th 6 months 65% $35.43 $24.01 5th 6 months 70% $38.15 $24.73 6th 6 months 80% $43.60 $26.17 7th 6 months 90% $49.05 $27.61 Area 6 Period $36.58 1st 55% $20.12 $18.50 $19.00 2nd 60% $21.95 $18.56 3rd 65% $23.78 $18.61 4th 70% $25.61 $18.67 5th 75% $27.44 $18.72 6th 85% $31.09 $18.83 Page 7 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate LINE CONSTRUCTOR Area 1 &Area 2/Group 2 Lineman Only Period $70.75 1st 60% $42.45 $18.96 $27.88 2nd 63% $44.57 $19.06 3rd 67% $47.40 $19.18 4th 72% $50.94 $19.34 5th 78% $55.19 $19.53 6th 86% $60.85 $19.79 7th 90% $63.68 $19.92 MARBLE SETTER Hours $52.47 1-1000 50% $26.24 $26.64 $26.64 1000-2000 55% $28.86 $26.64 2000-3000 60% $31.48 $26.64 3000-4000 70% $36.73 $26.64 4000-5000 80% $41.98 $26.64 5000-6000 90% $47.22 $26.64 PAINTER Commercial $38.12 70% $26.68 $9.21 $17.22 75% $28.59 $9.21 80% $30.50 $9.21 85% $32.40 $17.22 90% $34.31 $17.22 95% $36.21 $17.22 Industrial $40.34 70% $28.24 $9.21 $17.22 75% $30.26 $9.21 80% $32.27 $9.21 85% $34.29 $17.22 90% $36.31 $17.22 95% $38.32 $17.22 Bridge $47.77 70% $33.44 $9.21 $17.22 75% $35.83 $9.21 80% $38.22 $9.21 85% $40.60 $17.22 90% $42.99 $17.22 95% $45.38 $17.22 Page 8 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate PLASTERER $46.56 60% $27.94 $17.53 $19.83 65% $30.26 $17.53 70% $32.59 $17.53 75% $34.92 $17.53 80% $37.25 $17.53 85% $39.58 $17.53 90% $41.90 $17.53 PLUM BER/PIPEFITTER/STEAMFITTER Area 1 Baker County(See Area 2 Rates) Harney and Malheur Counties(See Area 3 Rates) Area 2 $65.20 Period $37.91 1st 6 months 45% $29.34 $25.18 2nd 6 months 50% $32.60 $26.34 3rd 6 months 55% $35.86 $27.49 4th 6 months 60% $39.12 $28.65 5th 6 months 65% $42.38 $29.81 6th 6 months 70% $45.64 $30.97 7th 6 months 75% $48.90 $32.12 8th 6 months 80% $52.16 $33.28 9th 6 months 85% $55.42 $34.44 10th 6 months 85% $55.42 $34.44 Area 3 Period $62.87 1st 6 months 40% $25.15 $18.74 $37.10 2nd 6 months 50% $31.44 $18.74 3rd 6 months 55% $34.58 $28.85 4th 6 months 60% $37.72 $29.76 5th 6 months 65% $40.87 $30.68 6th 6 months 70% $44.01 $31.60 7th 6 months 75% $47.15 $32.52 8th 6 months 80% $50.30 $33.43 9th 6 months 85% $53.44 $34.35 10th 6 months 90% $56.58 $35.27 Page 9 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate POWER EQUIPMENT OPERATOR Group 1 Period $61.99 1st 80% $49.59 $8.35 $17.55 2nd 85% $52.69 $17.55 3rd 90% $55.79 $17.55 4th 95% $58.89 $17.55 Group 1A Period $64.15 1st 80% $51.32 $8.35 $17.55 2nd 85% $54.53 $17.55 3rd 90% $57.74 $17.55 4th 95% $60.94 $17.55 Group 1B Period $66.31 1st 80% $53.05 $8.35 $17.55 2nd 85% $56.36 $17.55 3rd 90% $59.68 $17.55 4th 95% $62.99 $17.55 Group 2 Period $60.08 1st 80% $48.06 $8.35 $17.55 2nd 85% $51.07 $17.55 3rd 90% $54.07 $17.55 4th 95% $57.08 $17.55 Group 3 Period $58.93 1st 80% $47.14 $8.35 $17.55 2nd 85% $50.09 $17.55 3rd 90% $53.04 $17.55 4th 95% $55.98 $17.55 Group 4 Period $55.60 1st 80% $44.48 $8.35 $17.55 2nd 85% $47.26 $17.55 3rd 90% $50.04 $17.55 4th 95% $52.82 $17.55 Group 5 Period $54.36 1st 80% $43.49 $8.35 $17.55 2nd 85% $46.21 $17.55 3rd 90% $48.92 $17.55 4th 95% $51.64 $17.55 Group 6 Period $51.14 1st 80% $40.91 $8.35 $17.55 2nd 85% $43.47 $17.55 3rd 90% $46.03 $17.55 4th 95% $48.58 $17.55 Page 10 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate ROOFER Area 1 $44.51 60% $26.71 $18.35 $22.70 65% $28.93 $18.35 70% $31.16 $18.35 75% $33.38 $22.70 80% $35.61 $22.70 85% $37.83 $22.70 90% $40.06 $22.70 95% $42.28 $22.70 Area 2 $40.88 60% $24.53 $15.22 $20.49 65% $26.57 $15.22 70% $28.62 $15.22 75% $30.66 $20.49 80% $32.70 $20.49 85% $34.75 $20.49 90% $36.79 $20.49 95% $38.84 $20.49 Area 4 $44.51 60% $26.71 $18.35 $22.70 65% $28.93 $18.35 70% $31.16 $18.35 75% $33.38 $22.70 80% $35.61 $22.70 85% $37.83 $22.70 90% $40.06 $22.70 95% $42.28 $22.70 Area 5 $44.51 60% $26.71 $18.35 $22.70 65% $28.93 $18.35 70% $31.16 $18.35 75% $33.38 $22.70 80% $35.61 $22.70 85% $37.83 $22.70 90% $40.06 $22.70 95% $42.28 $22.70 Page 11 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate SHEET METAL WORKER Area 1 $59.24 50% $29.65 $29.80 $35.27 55% $32.60 $29.94 60% $35.56 $30.09 65% $38.52 $30.23 70% $41.48 $30.37 75% $44.44 $30.51 80% $47.40 $30.65 85% $50.36 $30.79 85% $50.36 $30.79 85% $50.36 $30.79 Area 2 Baker County(See Area 3 Rates) Malheur County(See Area 4 Rates) Area 3 $50.00 1st year/1st half 55% $27.50 $16.45 $28.37 1st year/2nd half 55% $28.75 $18.65 60% $30.00 $22.12 70% $35.00 $23.78 75% $37.50 $25.19 85% $42.50 $27.00 Area 4 $47.69 50% $23.87 $27.72 $32.58 55% $26.25 $27.86 60% $28.63 $28.01 65% $31.02 $28.15 70% $33.40 $28.29 75% $35.78 $28.43 80% $38.16 $28.57 85% $40.54 $28.71 85% $40.54 $28.71 85% $40.54 $28.71 Area 5 $47.33 50% $23.69 $29.06 $34.34 55% $26.05 $29.20 60% $28.42 $29.34 65% $30.78 $29.48 70% $33.15 $29.62 75% $35.51 $29.76 80% $37.87 $29.90 85% $40.24 $30.05 85% $40.24 $30.05 85% $40.24 $30.05 Page 12 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate SOFT FLOOR LAYER Period $45.78 1st 6 months 60% $26.94 $8.68 $19.40 2nd 6 months 65% $29.20 $17.48 3rd 6 months 70% $31.44 $17.75 4th 6 months 75% $33.69 $18.03 5th 6 months 80% $35.93 $18.30 6th 6 months 85% $38.17 $18.58 7th 6 months 90% $40.41 $18.85 8th 6 months 95% $42.67 $19.13 SPRINKLER FITTER Area 1 Class $54.74 1 43% $26.65 $10.23 $28.87 2 48% $29.75 $10.23 3 52% $32.22 $22.79 4 56% $34.70 $22.79 5 59% $36.56 $23.04 6 64% $39.66 $23.04 7 68% $42.14 $23.04 8 72% $44.62 $23.04 9 76% $47.10 $23.04 10 80% $49.58 $23.04 Area 2 Class $47.11 1 43% $23.36 $10.23 $28.86 2 48% $26.08 $10.23 3 52% $28.25 $22.79 4 56% $30.42 $22.79 5 59% $32.05 $23.04 6 64% $34.77 $23.04 7 68% $36.94 $23.04 8 72% $39.12 $23.04 9 76% $41.29 $23.04 10 80% $43.46 $23.04 TENDER TO MASON $47.44 63% $29.89 $18.90 $18.90 70% $33.21 $18.90 80% $37.95 $18.90 90% $42.70 $18.90 Page 13 PWR APPRENTICESHIP RATES EFFECTIVE JULY 5, 2026 Contact BOLT at(971) 245-3844 or email PWR.email@boli.oregon.gov if you have any questions regarding the use of these apprenticeship rates. The percentages shown for the various apprentice periods are taken from union agreements and may differ from the committee standard(ATD)for that trade. Please verify these percentages before using them. CLASSIFICATION Journeyman Base Hourly Rate Percentage/ Base Hourly Fringe Journeyman Fringe Rate Hours Rate Rate TENDER TO PLASTERER $46.59 63% $29.35 $19.40 $19.40 70% $32.61 $19.40 80% $37.27 $19.40 90% $41.93 $19.40 TILE TERRAZZO SETTER Hours $44.42 1-1000 70% $31.09 $23.01 $23.01 1001-2000 75% $33.32 $23.01 2001-3000 80% $35.54 $23.01 3001-4000 85% $37.76 $23.01 4001-5000 90% $39.98 $23.01 5001-6000 95% $42.20 $23.01 TILE TERRAZZO FINISHER $32.92 1-1000 hrs $24.13 $16.71 $17.43 1001-2000 hrs $27.02 $16.71 Page 14 Jacobs _ __ _ _. _ _ . _ ... _ _ _.... -•.• . . . � t. . • ',-::" , ,..: ' ' 0 ii i+, ,.cc .... r. 1.- ' _.__ , lI I Ill :., 4»+ BSc, i tiffs w 4 IC t ' v - r t _ .,,,,3 m A TECHNICAL MEMORANDA 1 . Design Criteria 2. Hydraulics 3. Unit Treatment Processes 4. Odor Control 5. Stormwater Management 6. Disciplines (as appropriate) 6-01 Architectural 6-02 Building Services 6-03 Corrosion Control 6-04 Electrical 6-05 Preliminary Geotechnical Analyses and Recommendations 6-06 Instrumentation and Control 6-07 Process Mechanical 6-08 Resiliency 6-09 Civil and Site Development 6-10 Structural 6-11 Landscape Architecture 7. Project Option 1 Nutrient Removal Treatment , TECHNICAL MEMORANDUM 1 Design Criteria Date: March 30,2026 Revised:10/1/2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BP00152J Stefan Broadus/City of Lake Oswego From: William Leaf/Jacobs Reviewer: Bruce Johnson/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final I 1 . Introduction The purpose of this technical memorandum (TM) is to present the proposal design criteria confirmation for the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2.Codes, Standards, Regulations, and References The State of Oregon, Department of Environmental Quality(DEQ), establishes overall standards required of treatment facilities.This includes the issuance of the National Pollutant Discharge Elimination System (NPDES)Waste Discharge Permit for discharge of effluent into the Willamette River.The City of Lake Oswego has also established design criteria for the LOWWTF. 3. Design Criteria Addendum 2 from the City of Lake Oswego, Table 1:Design Criteria—Assumed Influent Flows and Loadings and Table 2: Effluent Requirements(October 22, 2025) provides the influent and effluent design criteria for the treatment facility.Table 1 provides the influent design criteria. Table 1 —Design Criteria:Assumed Influent Flows and Loadings Design Criteria Parameter FLOW,mgd lverage Dry Weather Flow(May 1 to October 31) Max Month Dry Weather Flow 10.2 Max Week Dry Weather Flow 13.6 Max Day Dry Weather Flow 18.7 Average Wet Weather Flow(November 1 to April 30) Max Month Wet Weather Flow 14.7 Max Week Wet Weather Flow 22.0 Max Day Wet Weather Flow 39.2 Peak Instantaneous Flow 111 TECHNICAL MEMORANDUM 1 Design Criteria Parameter Maximum flow through secondary treatment 32.9 BIOCHEMICAL OXYGEN DEMAND(BOD5)LOAD,lb/day Average Dry Weather(May 1 to October 31) 14,100 ax Month Dry Weather 19,40 111 Max Week Dry Weather 26,000 Max Day Dry Weather 46,400 Average Wet Weather(November 1 to April 30) 15,900 ax Month Wet Weather 24,70 Max Week Wet Weather 35,000 Max Day Wet Weather 62,000 TOTAL SUSPENDED SOLIDS(T55)LOAD,lb/day Average Dry Weather(May 1 to October 31) 15,300 Max Month Dry Weather 25,300 Maw Dry tuther Max Day Dry Weather 56,900 Average Wet Weather(November 1 to April 30) 17,700 Max Month Wet Weather 30,300 M xW••kW W . h r 44,300 Max Day Wet Weather 61,800 AMMONIA-NITROGEN LOAD,lb/day Average Annual 1,900 Max Month 2,300 TOTAL KJELDAHL NITROGEN(TKN),lb/day Average Annual 3,100 Max Month 3,700 TOTAL PHOSPHORUS(TP),lb/day Average Annual 400 Max Month 500 The City of Lake Oswego has received a draft NPDES permit for the new LOWWTF (Permit No. 1O1614).The key effluent criteria are presented in Table 2, including parameters from the NPDES permit,together with City of Lake Oswego RFP criteria. *,1121 TECHNICAL MEMORANDUM 1 Table 2-Effluent Requirements Dry Weather Season(May 1 -October 31) Performance Value Average Effluent Monthly Concentrations(mg/L) average Weekly average Daily max Parameter Monthly Weekly (lb/day) (lb/day) (lb/day) Sample Type Biochemical Oxygen Demand ≤ 10 ≤15 ≤850 ≤ 1,300 ≤ 1,700 24-hr Composite (BOD5) Total Suspended Solids(TSS) ≤ 10 ≤15 ≤850 ≤ 1,300 ≤ 1,700 24-hr Composite Ammonia-N ≤ 1 24-hr Composite Total Phosphorus'. ≤0.3 24-hr Composite E Coli bacteria Shall not exceed 126 organisms per 100 mL monthly geometric mean.No single sample Grab shall exceed 406 organisms per 100 mL. pH Shall be within the range of 6.0-9.0 Grab I BOD5 and TSS Removal Shall not be less than 85 percent monthly average for BOD5 and 85 percent monthly average Efficiency for TSS Chlorine Residual No residuals allowed , N/A Wet Weather Season(November 1—April 30) Performance Value Average Effluent Monthly Concentrations(mg/L) average Weekly average Daily max Parameter Monthly (lb/day) (lb/day) (lb/day) Sample Type Biochemical Oxygen Demand ≤30 ≤45 ≤3,700 ≤5,500 ≤7,400 24-hr Composite (BODs) Total Suspended Solids(TSS) ≤30 ≤45 5 3,700 ≤5,500 ≤7,400 24-hr Composite E Coli bacteria Shall not exceed 126 organisms per 100 mL monthly geometric mean.No single sample Grab shall exceed 406 organisms per 100 mL. pH Shall be within the range of 6.0-9.0 Grab BOD5 and TSS Removal Shall not be less than 85 percent monthly average for BOD5 and 85 percent monthly average Grab Efficiency for TSS Chlorine Residual No residuals allowed N/A 1. Anticipated Future Limits. Draft National Pollutant Discharge Elimination System (NPDES) permit does not include effluent criteria for ammonia-nitrogen or total phosphorus.The details of Project Option 1,as described in the RFP and which include infrastructure necessary to meet effluent requirements for ammonia-nitrogen and total phosphorous, are captured in TM 7.All other TMs, including this TM and drawings are reflective of Project Option 2. 2. While NPDES Permit requirements anticipate inclusion of an Excess Thermal Load Limit, DBOM Contractor is responsible only for monitoring and not compliance.The City maintains responsibility to incorporate future Capital Modifications for NPDES Permit compliance regarding Thermal Load. The daily maximum mass limit for BODs and TSS, each set at 7,400 lbs/day, is equivalent to 22.6 mg/L at the 39.2-mgd I3 TECHNICAL MEMORANDUM 1 MDWWF.This equivalent concentration is lower than the monthly average value(≤ 30 mg/L) in the permit for BOD5 and TSS. Additional key sizing criteria are used as part of the treatment process development. Historical data from the Tryon Creek WWTP are used in part to establish these criteria: • Wastewater Temperature:Average 14-day Minimum (May—October) = 13.4°C;Average 14-day Minimum (November— April) = 10.3°C • Sludge Volume Index(SVI): 150 mL/g, based on a well-operating nutrient removal bioreactor with non-aerated selectors. Note that the average SVI for the Tryon Creek facility is 163 mL/g (January 2019—June 2024), but there is variation seasonally with this value higher in the wet weather season and lower in the dry weather season.Tryon Creek WWTP does not remove nutrients and operates with a short solids residence time(SRT) (3.5-day average),so it is not necessarily reflective of the potential SVI expected at the new LOWWTF. At commissioning of the LOWWTF,the anticipated influent flow and loads are presented in Table 3.The values are based on the influent flow and loads at the Tryon Creek WWTP,from 2019—2024 plant data. Table 3—Startup Conditions:Anticipated Influent Flow and Loads Startup Flow(mgd) BOD5(lb/d) TSS(lb/d) Flow(mgd) BOD5(lb/d) TSS(lb/d) Condition Dry Weather Wet Weather Average 3.99 8,716 8,392 6.44 8,624 7,687 Max Month 5.85 9,934 10,746 11.23 11,998 14,906 Max Week 7.60 11,958 15,816 15.33 15,035 20,561 Max Day 11.34 15,699 22,068 21.31 25,633 27,118 A typical diurnal flow pattern from June 2024 for the Tryon Creek WWTP is shown in Figure 1.This is the daily influent flow pattern expected during a summer startup condition at the LOWWTF. Flowrate Peak DW Diurnal Flow-June 2024 Flowrate Peak 6.00 X61812024 5.0 0 . •.._ 1619/2024 X6/10/2024 4.00 c , t6/1L2024 X6/12/2024 3.00 \ --611312024 6/14/2024 2.00 \ i --6/1512024 X6/16/2024 1.00 16/17/2024 -4,-6/18/2024 t 6/19/2024 12 AM 1 AM 2 AM 3AM 4AM 5AM 6AM 7AM 8 AM 9AM 10 AM 11 AM 12 PM 1 PM 2 PM 3 PM 4 PM 5 PM 6 PM 7PM 8 PM 9 PM 10 PM 11 PM Figure 1 —Typical Diurnal Flow:Tryon Creek WWTP(June 2024) Wet weather conditions during startup and commissioning of the LOWWTF are dependent on storm events. Non-storm conditions could have influent flows similar to Figure 1, but peak storm conditions can have influent flow values exceeding 35 mgd. 3.1 Reliability/Redundancy The State of Oregon has established reliability for facilities based in Western Oregon.The reliability and redundancy are documented in Preparing Wastewater Planning Documents and Environmental Reports for Public Utilities(Financed by Business 141 TECHNICAL MEMORANDUM 1 Oregon,Oregon Department of Environmental Quality, Rural Community Assistance Corporation, United States Department of Agriculture.June 2018).The following criteria from DEQ applicable to the LOWWTF are: • In general, all units should be able to handle the peak hourly flows without overflowing or damaging the equipment,with the largest flow capacity unit out of service.The system should also contain enough flexibility to allow any unit to be taken out of service and meet permit requirements by redistributing the wastewater to other active treatment units. • All pumping stations required to convey wastewater flows should have a firm capacity(largest pump out of service) equivalent to the peak hourly flow. • The headworks should be sized for peak hourly flow.A minimum of two units are required. Facilities with only one mechanical screen may include a manual bar screen for redundancy. No redundancy is needed for grit removal units. • Size aeration basins using modeling to generate desired treatment.Typically,this means 10 mg/L at maximum monthly average dry weather flow with a 10 percent chance of occurrence (summer) and 30 mg/L at maximum monthly average flow with a five percent chance of occurrence(winter).A minimum of two units are required. • Size the secondary clarifiers for either the peak average daily flow associated with a one-in-five-year storm with all clarifiers operational, or the MMDWF 10 (Maximum Month Dry Weather Flow with a 10 percent probability of occurrence) with the largest clarifier offline,whichever results in greater treatment capacity.A minimum of two secondary clarifiers are required. Use separate overflow rates for the dry and wet seasons. • Size the disinfection system for peak-hour flow with full redundancy. For UV systems, a minimum of two units are required.Sizing is based on a minimum dose of 30 mJ/cm2 at either the peak-hour flow with all units on, or the maximum day dry weather flow with largest unit offline,whichever results in the larger design.This dose must be calculated with a certain percentage of fouling and end-of-lamp life statistics as discussed in the Ten State Standards. Full redundancy of the ballasts and controls is required.A single control panel is acceptable, as long as there is full redundancy within the panel. In addition,a UV transmittance of more than 65 percent should be verified before selecting UV. The overall redundancy provided at the LOWWTF is presented in Table 4. Table 4—LOWWTF Reliability and Redundancy Unit Process Reliability/Redundancy Influent Pump Station Handle the peak instantaneous conditions(53.1 mgd)with one of the largest pumps offline Headworks(screening and grit removal) Convey the peak instantaneous conditions(53.1 mgd)with the largest unit out of service. Two grit removal chambers sized to accommodate peak instantaneous conditions(53.1 mgd). Aeration Basins Four aeration basins are provided,sized to treat influent flows to 32.9 mgd,and associated loads. Hydraulically,the four aeration basins together with four secondary clarifiers can convey approximately 40 mgd. Aeration Blowers Five aeration blowers provided,with four able to meet peak secondary treatment capacity conditions (32.9 mgd). Clarifiers Four secondary clarifiers are provided,sized to treat the peak secondary treatment conditions(32.9 mgd).Three secondary clarifiers can accommodate the MMDWF conditions(10.2 mgd). Filtration Four filtration units are provided to treat the dry weather peak flow conditions(25.8 mgd)with one unit offline.The dry weather peak flow value is calculated as a ratio from the wet weather values in Table 4-1 of Appendix 4 from the Appendices to the DBOM Agreement.Additional filtration capacity can be used if necessary during wet weather conditions,with selected wet weather flow diverted around secondary treatment(conveying the total 53.1-mgd peak instantaneous conditions through the LOWWTF). UV Disinfection Three UV disinfection channels are provided with three banks each.This provides treatment of the 53.1-mgd peak instantaneous condition with all units online,since this is a larger design than the maximum dry weather flow with the largest unit offline.A minimum dosage of 30 mJ/min is used. 5 TECHNICAL MEMORANDUM 1 IAssumptions and Exclusions The following assumptions and exclusions are documented for the design criteria: • Wastewater Temperature:Average 14-day Minimum (May—October) = 13.4°C;Average 14-day Minimum (November— April) = 10.3°C • Influent alkalinity data from 2016-2019 indicate a dry weather 30-day average minimum value of 120 mg CaCO3/L. The WWTF design will provide space for supplemental alkalinity(chemical storage and feed), as required to maintain nutrient removal(nitrification) performance. • SVI: 150 mL/g, based on a well-operating nutrient removal bioreactor with non-aerated selectors. Note that the average SVI for the Tryon Creek facility is 163 mL/g (January 2019—June 2024), but there is variation seasonally with this value higher in the wet weather season and lower in the dry weather months.Tryon Creek WWTP does not remove nutrients and operates with a short SRT(3.5-day average), so it is not necessarily reflective of the potential SVI expected at the new Lake Oswego WWTF. • The design SRT is 5 to 6 days. For the conventional activated sludge approach,the design SRT will not allow for reliable nitrification in the secondary process.The integrated fixed-film activated sludge system can reliably nitrify with a 5-to 6- day SRT, meeting the design conditions. • No design features are included to mitigate effluent temperature. No accommodations are incorporated to meet future effluent temperature criteria. • No modifications to the existing effluent outfall(from the Tryon Creek WWTP)are included in the design. 161 TECHNICAL MEMORANDUM 2 Hydraulics Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Michael Lloyd/Jacobs Reviewer: Jackson Corley/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 11. Introduction The purpose of this technical memorandum (TM)is to present the proposal hydraulic design for the Lake Oswego Wastewater Treatment Facility(LOWWTF). This analysis used ReplicaTM hydraulic modeling software and considered flow conditions through the following proposed facilities: influent pump station (IPS), headworks,aeration basins,clarifiers, rapid mix tank,filtration, UV disinfection,and the existing outfall. The hydraulic profile is presented in the Drawings. ' 2. Design Criteria The hydraulic design criteria for the LOWWTF include passing 53.1 mgd from the IPS through headworks and disinfection,with 32.9 mgd through the aeration basins,clarifiers,and filtration.The hydraulics were also checked to pass 40 mgd through aeration basins, clarifiers, and filtration for operations flexibility.A two-part flow path is incorporated to manage flows exceeding 32.9 mgd: 1. Selected Wet Weather Flow Treatment:The system can send aeration basin influent flows above 32.9 mgd directly to the rapid mix tank ahead of filtration. 2. Selected Secondary Effluent Treatment:The system can divert secondary effluent flows above 32.9 mgd directly to disinfection. For peak capacity,the hydraulic grade line on the hydraulic profile used 53.1 mgd plant influent flow through IPS at the 100-year flood elevation for the Willamette River,which is an elevation of 34.0-feet per NGVD29 datum.The hydraulic model was also checked with the 1996-flood elevation (elevation 36.3-feet)to determine which hydraulic control points may be submerged and whether any process walls would be overtopped. The headloss associated with a future 60-inch outfall was used in the hydraulic analysis to set the UV disinfection effluent weir elevation, but the headloss in the existing 36-inch lined outfall is what is included in the hydraulic grade line values on the hydraulic profile. 2.1 Flows Flows at the LOWWTF include IPS flow,stormwater,drains,filtration backwash, and return activated sludge(RAS). Each of these flows affects headlosses throughout the LOWWTF. Design flows from each source are described in Table 1. • Influent Pump Station Flow: Modeled as a pump station with flows split between active pumps and total flow being directly input into the pump station. • Stormwater and Drain Flow: Modeled as a source flow into the headworks upstream of the screens.This is an assumed constant flow. • Filtration Backwash Flow: Modeled as a source flow to the grit effluent channel at headworks.A constant flow was assumed. • RAS Flow: Modeled as an evenly split discharge flow at the clarifiers and an evenly split source flow to the aeration basins. 1 TECHNICAL MEMORANDUM 2 Table 1—LOWWTF Flows Flow Source Flow(mgd) Notes IPS 53.1 Peak Instantaneous Flow Stormwater/Drain 3.5 Filtration Backwash 1.0 Backwash from filtration; constant source flow in all scenarios RAS 14 Estimated at peak aeration flow(40 mgd);assumed lower at reduced flow Total Effluent Discharge 57.6 2.2 Upstream Boundary Conditions The upstream boundary condition for the hydraulic model is based on the IPS flow rate.The IPS was modeled with two wet wells, one small and one large. 2.3 Downstream Boundary Conditions The downstream boundary condition for the model is the Willamette River water level. For the peak influent design scenario (53.1 mgd),the 100-year flood river elevation of 34.0-feet per NGVD29 was used. 2.4 Hydraulic Criteria • Weir elevations at hydraulic control points remain unsubmerged when using the future 60-inch outfall and a 100-year flood stage of 34.0-feet NGVD29 for the Willamette River. • No process walls are overtopped when using the existing 36-inch outfall and the 1996 flood elevation of 36.3-feet NGVD29 for the Willamette River. 3. Description of Work To form a complete hydraulic profile and hydraulic model for the proposed design of LOWWTF,assumptions throughout portions of the processes were required.Assumptions are listed by process.The LOWWTF will convey flow through process treatment facilities as described herein: 3.1 Influent Pump Station Influent flow to the LOWWTF will enter the IPS from the City of Lake Oswego's and the City of Portland's sewer collection system. The IPS has seven pumps in total,with four pumps in the small wet well and three larger pumps in the larger wet well.The wet wells will operate as one pump station.There is a third wetwell for flows coming from the Tryon Creek Pump Station,which will be decommissioned in the future. 3.2 Headworks The influent flow to the headworks comes from the IPS.Stormwater and drain flows discharge to the headworks influent channel. The headworks has five screening channels and two grit concentrator units. Effluent from the grit concentrator units will pass over a weir to the grit effluent channel. Flow is then conveyed to the aeration basins,with provisions for flow over 32.9 mgd to go directly to the rapid mix tank ahead of filtration. 3.3 Aeration Basins The hydraulic model accounts for headlosses associated with the integrated fixed-film activated sludge(IFAS)design for the aeration basins.The aeration basins consist of four trains,all of which are in service for the peak design scenario,and flow split controlled with flow control valves. RAS is pumped from the clarifiers into Tank 1 of each aeration train,with an even flow split across all four trains. 3.4 Clarifiers Flow from the aeration basins splits four ways to feed each clarifier.There are four clarifiers in total. Flow into the clarifiers 2 TECHNICAL MEMORANDUM 2 accommodates influent flows plus the estimated maximum RAS flow of 14 mgd.All clarifiers remain active during the peak capacity scenario. Solids will be scraped from the bottom of the clarifiers and pumped as waste activated sludge(WAS)or RAS. Clarifier effluent will discharge over a launder weir and into the clarifier effluent channel.The effluent channel provides two discharge pathways,one to filtration,and one to the UV influent channel.The filtration flow path includes headloss for the rapid mix tank(upstream of filters) necessary for nutrient removal. 3.5 Filtration Filtration consists of four filter channels for disk filters.All filter disk channels are active during capacity assessments. Each disk filter will occasionally undergo backwash to clean the media. During backwash,flow will be sent to the headworks grit effluent channel. For preliminary hydraulic assessments,this backwash flow has been modeled as a constant proposed source. Flow through the filtration process was modeled based on concept drawings from Aqua-Aerobic Systems, Inc.These drawings indicate an influent and effluent weir for each filter channel. 3.6 UV Disinfection Flow exits the filter effluent channel into the UV influent channel. Flows from the clarifier effluent channel also enter at this UV influent channel.There are three UV channels,and all three are assumed active during capacity assessments. After passing through UV disinfection,flow will discharge over UV effluent weirs from each channel into the UV effluent channel. The UV effluent channel will then convey flow to the outfall. A pumped system for non-potable plant water at the UV facility is not included in the hydraulic analysis. 3.7 Outfall Discharge piping from UV disinfection will be connected to a junction structure to connect to the existing 36-inch lined outfall pipe. The headloss associated with a future 60-inch outfall pipe was used in the hydraulic analysis to set the UV disinfection effluent weir elevation, but the headloss in the existing 36-inch lined outfall is what is included in the hydraulic grade line values on the hydraulic profile. • Modeling assumptions for the 60-inch future outfall: - 60-inch CLDI pipe,800 LF — 3-feet of headloss across the diffuser during peak design flows 4. Results Static model flows were simulated to assess performance of hydraulic control points throughout the LOWWTF under specific flow conditions.This scenario was evaluated under varying downstream water levels in the Willamette River. Hydraulic control points, such as process weirs,were monitored during test runs to estimate the flow conditions at which weirs would submerge or overtopping of walls might occur. 4.1 Peak Instantaneous Flow — Existing Outfall This scenario included running the peak instantaneous flow 53.1 mgd plus stormwater/drain flows and backwash flows through the LOWWTF and using the existing outfall. For this evaluation,the capacity limit was defined as the maximum flow that can pass through the existing outfall without submerging the upstream UV effluent weir. It should be noted that the losses through the existing 36-inch outfall are based solely on the drawings for the existing diffusers and piping.Calibration using actual plant data to confirm the flow to headloss relationship through these sections of existing outfall pipe has not been performed at this time. Results indicate at the 1996-flood river level (EL 36.3-feet),the limiting plant discharge flow before the UV effluent weir is submerged is approximately 16.5 mgd. If the LOWWTF intends to discharge close to 40 mgd without submerging upstream processes,the river WSE can be no higher than approximately 10-feet.As outfall flows increase,the accuracy of the estimated headlosses through the existing outfall may decrease. 3 TECHNICAL MEMORANDUM 2 4.2 Analysis Based on the model scenarios tested,the estimated plant discharge flow of 57.6 mgd with the Willamette River 100-year flood WSE of 34-feet can be achieved without submerging hydraulic control points when using the future 60-inch outfall. When river levels exceed the 100-year flood elevation,as seen in the 1996 flood scenario(WSE 36.3-feet), hydraulic control points, starting with the UV facility,are expected to submerge at similar peak design flows. However,even under these conditions, no proposed process walls were overtopped. 5. Exclusions • Excludes existing outfall calibration. • Excludes upstream and downstream conveyance system modeling. • Excludes modeling of solids flow streams. • Excludes modeling of the Tryon Creek WWTP. 4 TECHNICAL MEMORANDUM 3 Unit Treatment Processes Date: March 30,2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater aabetment Facility Jacobs PN: BPO0152J Stefan Broadus/City of Lake Oswego From: William Leaf/Jacobs Revie er: Kristen Jackson/Jacobs ave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum(TM)is to present the unit treatment process design criteria of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References The State of Oregon,Department of Environmental Quality(DEQ),establishes overall standards required of treatment facilities.This includes the issuance of the National Pollutant Discharge Elimination System(NPDES)Waste Discharge Permit for discharge of effluent into the Willamette River.The City of Lake Oswego has also established design criteria for the LOWWTF. 3. Design Criteria Exhibit 1 illustrates the proposed Process Flow Diagram for the LOWWTF. Each unit processes is described in additional detail below. Exhibit 1 - LOWWTF Process Flow Diagram Selected Wet-Weather Flow,>32.9 mgd 20 mgd -- 23.6 mgd 20 mgd --Optional winter use of filtration capacity 16.4 mgd (40 mgd total) 32.9 mgd 53.1 mgd Secondary Clarifiers 56.5 mgd 56.5 mgd SE FE Influent Effluent ABI 16.5 mgd a Filtration UV Disinfection Screening Grit Removal PD WAS/RAS WAS Storage STORM 2.4 mgd 1.1 mgd WAS To Columbia Thickening TWAS Blvd WTP PD 1 TECHNICAL MEMORANDUM 3 3.1 Influent Pump Station The influent pump station(IPS)pumps influent raw wastewater into the Headworks.There is a junction structure that combines flow from the Portland and Lake Oswego sewer lines upstream of the IPS.Between the junction structure and the IPS there are rock traps. The IPS includes two wetwells for pumping the range of design flows.Flows from the existing Tryon Creek Pump Station(that will be demolished)are pumped to a dedicated third wetwell at the IPS. 3.2 Headworks (screening and grit removal) The Headworks includes screening and grit removal processes,comprised of 5 screening channels and 2 grit removal basins. Screening washing/dewatering and grit washing/classification are provided screenings and grit are conveyed to a removable dumpster. 3.3 Aeration Basins The aeration basins and blower system provide biological treatment of the wastewater.This system is designed for the Max Flow through Secondary Treatment of 32.9 mgd per the RFP.The aeration basins have 4 trains with equal capacity,each with 4 selector zones with mixers followed by 3 additional zones with fine bubble diffusers.The associated blower system is included to provide the required air demands to the aeration basin system. The aeration basins are designed for conventional activated sludge process.While the aeration basins do not include an IFAS system,the basins are designed for conversion to an IFAS system in the future.Exhibit 2 illustrates the difference in infrastructure to accommodate the conversion to IFAS.TM 7 describes this more fully. Exhibit 2 - LOWWTF Process Flow Diagram a ' Z p RAS SEL 1 SEL 4 H (9,500 mg/L) Z a AER 1 AER 2 AER 3* W z SEL 2* SEL 3 0 '(2,400 mg/L) ABI(100°,0) Lu X tj �`a< RAS SEL 1 SEL 4 > (9,500 mg/L) L++ AER 1 AER 2 AER 3* a (IFAS ZONE) SEL 2* SEL 3 ZW� '(2,400 mg/L) LEGEND RAS: Return Activated IFAS: Integrated Fixed-film AER: Aerobic Zone Sludge Activated Sludge ABI: Aeration Basin SEL: Selector Zone Influent 301 001Y, 3.4 Clarifiers The clarifiers provide settling and send return activated sludge(RAS)back to the aeration basin system.There are four rectangular clarifiers with equal capacity.There is biological foam collection and RAS pumps to convey the RAS back to the aeration basins. 3.5 Filtration The filtration facility includes four trains and will further treat the wastewater.The facility will typically be used in the dry 121 TECHNICAL MEMORANDUM 3 season but can also be utilized in the wet season as needed to meet wet season effluent criteria. 3.6 UV Disinfection Three UV Disinfection channels with three banks are included in the design.UV channels discharge into a common clearwell. No additional lifting devices are provided at the UV facility.Plant effluent piping leaving the UV facility will connect to the existing outfall piping. Checker plate covers provided over channels only,and a canopy over UV vendor-supplied master control panel and automatic strainer only. 3.7 Solids Handling Thickening of WAS is provided via Rotary Drum Thickeners(RDTs)that thicken sludge to the target value allowable for hauling and discharge to Columbia Boulevard WWTP.WAS is pumped directly to the RDTs and then discharged to mixed solids storage tanks.TWAS is pumped from the storage tank(s)to the Truck Loadout Facility. The Truck Loadout Facility is effectively a Loadout Bay that is fully enclosed,allowing for pull-through access for a single 6,000-gallon tanker truck.A loadout platform is provided for access to the top of the truck to connect TWAS piping to the truck.Odor control is provided locally at the sludge discharge. The Truck Loadout Facility is located below the Lake Oswego Design Flood Elevation and will therefore be floodproofed to meet City criteria.Provisions for backup loadout will be provided on the upper level(west side)of the LOWWTF to ensure loadout is available during extreme flood events. 3.8 Design Criteria Summary Table 1 provides additional detail for each Unit Process. Table 1 -Unit Process Design Criteria Influent Pump Station Wetwell 1 Number of Pumps 4 Pump Capacity,Each 4 MGD @ 50-ft TDH Pump Motor Size 70 HP Pump Type Non-Clog Submersible Wetwell 2 Number of Pumps 3 Pump Capacity,Each 19 MGD @ 50-ft TDH Pump Motor Size 335 HP Pump Type Non-Clog Submersible Wetwell 3 (Tryon Creek Pump Station) Number of Pumps 3 1250 GPM (Future Projection Provided by Pump Capacity,Each City of Portland) Pump Motor Size 40 HP Pump Type Non-Clog Submersible Headworks Screening Number 5 Type Perforated Plate Opening Size 1/4-inch Capacity 2 @ 8 MGD Capacity 3 @ 19 MGD Screening Washing and Dewatering Number 2 Type Reversing Auger Grit Removal Number 2 3 TECHNICAL MEMORANDUM 3 Type Stacked Tray Peak Loading Rate 20 GPM/ft2 Grit Pumps Recessed Impeller Capacity,Each 2 @ 300 GPM Drive Adjustable Motor,HP 20 Grit Washing and Dewatering Number 2 Type Conical Clarifier W/Fluidized Bed Aeration Basins Type _ Contact Stabilization,Activated Sludge Number 4 Total Volume,Each 1.15 MG Size,Each 47.5 ft X 129 ft Depth,Each 25 ft Selectors,Per Basin 4 Volume,Each 95,500 GAL Mixer,Per Selector Submersible,1 @ 8.3 HP Aerated Zone 1 292,000 GAL Aerated Zone 2 212,000 GAL Aerated Zone 3 212,000 GAL Minimum Air Flow Mixing,2 AB In Service 1,100 SCFM Maximum Air Flow Peak Day,4 AB In Service 14,700 SCFM Biofoam Pumps Number 2 Type Submersible,Chopper Recirculating Capacity,Each 200 GPM @ 30-ft TDH Drain Pump Number 1 Type Self-Priming Non-Clog Capacity,Each 700 GPM @ 40-ft TDH Secondary Process Design Solids Residence Time 6 Days Minimum Temperature May-October 14.3 °C Nov-April 11.5°C Sludge Volume Index 150 ML/G Aeration Process Blowers Number 5 Type Positive Displacement,Rotary Screw Capacity,Each 3,700 SCFM @ 300 HP Differential Pressure 13.5 PSI Inlet Air Temperature 10- 100°F Relative Humidity 70% Secondary Clarifiers Number(Basins) 4 Size,Each 40 ft X 150 ft Sidewater Depth 18 ft(1%Slope to 19.5 ft) Surface Area,Each 6000 ft2 ..1 141 TECHNICAL MEMORANDUM 3 Peak Surface Overflow Rate 1,370 GPD/ft2 at 32.9 MGD 1,670 GPD/ft2 at 40 MGD Peak Weir Loading Rate 25,000 GPD/LF at 32.9 MGD 30,000 GPD/LF at 40 MGD Sludge Collector _ Non-Metallic Chain&Flight Biofoam Pumps Number 1 Type Submersible,Chopper Recirculating Capacity,Each 200 GPM @ 30-ft TDH Return Activated Sludge (RAS) Pumps Number 4 Type Submersible Column or,Immersible Non-Clog Drive Adjustable Capacity,Each 3.15 MGD @ 23-ft TDH 3.5 MGD @ 27-ft TDH Motor,HP 25 Design RAS Capacity 12.6 MGD (Targeting 14.0 MGD) Thickening Tank Number 2 Max.Working Volume,Gal 67,000 WAS TSS% 2%-5% Thickening Tank Mixing System Number 3 (1 Per Tank, 1 Standby) Type Chopper Pump with Mixing Nozzle Drive Adjustable Motor,HP 40 Rotary Drum Thickener Feed Pumps Number 2 Type Dry Pit,Horz End Suct Non-Clog Drive Adjustable Capacity,Each 400 GPM @ 50-ft TDH Motor,HP 10 Rotary Drum Thickeners Number 2 (2 Drums Each) Hydraulic Loading 400 GPM Motor,HP 3 HP per Drum Solids Capture 95%Minimum Solids Concentration 4-6% Polymer Systems (Thickening) Number 2 Type Mechanical,Hydraulic Mixing Capacity,Each 2.0 GPH Motor,HP 1 Sludge Loadout Pumps Number 2 Type Rotary Lobe Drive _ Adjustable Capacity,Each 200 GPM Motor,HP 10 ‘.1151 TECHNICAL MEMORANDUM 3 Filtration Design Influent Flow 40 MGD Dry W.Influent TSS 25 MG/L Wet W.Influent TSS 75 MG/L Number 4 Type _ Cloth Disk,5 Micron Media Max Hydraulic Loading Rate 6.5 GPM/SF Max Solids Loading Rate 5.5 LB TSS/D/SF Backwash Pumps(if Needed) Number 4 Type Dry Pit Centrifugal Drive Adjustable Capacity,Each 690 GPM Motor,HP 20 Ultraviolet(UV) Disinfection Peak Instantaneous Flow 55.5 MGD (53.1+2.4 MGD Storm) Design Minimum Flow 2 MGD Storm,Plant Drain,Backwash Up to 4.5 MGD UV Transmittance 65% UV Dose 30 MJ/CM2 Effluent Disinfection 126 MPNH/100 ML,30-Day Geo-Mean 406 MPN/100 ML,Single Sample UV Lamp Type Low Pressure,High Output,Incline UV Channel Size 3'-8"X 30'-8"X 7'-8" Max Water Surface Depth 5.8' Plant Drain Pump Station Peak Instantaneous Flow 700 GPM Minimum Diurnal Flow _ 200 GPM Number Of Pumps 3 Type Non-Clog Submersible Capacity,Each 350 GPM Motor,HP 5.5 W3 Pumps Number 3 Type Vertical Turbine Capacity,Each 1 MGD @ 90 PSIG Motor,HP 30 Hypochlorite Chemical System (Plant Maintenance Activities) Storage Tanks 270-GAL IBC Tote Feed Pumps 2 Type Diaphragm Capacity 2 GPH Odor Control Number 4(1 Duty 1 Standby Each) Air Flow Capacity 2@1,750 ACFM,2@12,400 ACFM Fan Number 4(1 Duty 1 Standby Each) Motor,HP 2@15 HP,2@20 HP ..1 161 TECHNICAL MEMORANDUM 3 1. Assumptions and Exclusions The following assumptions and exclusions are documented for the design criteria: • The aeration basins do not include IFAS equipment. • There are no provisions for hydrocyclones or RAS chlorination to increase settleability of solids. 4 7 TECHNICAL MEMORANDUM 4 Odor Control Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Ken Galardi/Jacobs Reviewer: Scott Cowden/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal odor control design for the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References The odor control design will conform to the following codes,standards,and regulations,as required by the local authority. • 2024 National Fire Protection Association (NFPA)820 • 2024 Occupational Safety and Health Administration for General Industry(OSHA) • 2020 Sheet Metal and Air Conditioning Contractors National Association(SMACNA) 3. Design Criteria The Tryon Creek WWTP is located in an industrial area and odorous emissions have been reported as not an issue. However,the new LOWWTF will be located where sensitive receptors are closer,as the surrounding Foothills District evolves,and a strict off-site odor goal is a contract requirement.The odor sources will be covered and ventilated to provide odor control treatment. It is anticipated that odor levels will be low for most of the year; however,some hot days in warmer seasons may result in higher odors. The following foul air sources will be combined and directed to odor control systems: • Portland Interceptor Drop Structure. • The influent pump station (IPS)facility,the wet well and splitter box is ventilated. • The headworks facility contains covered channels,and the screen equipment has integral enclosures.The screenings washer/compactor,grit washer,and grit basins,and grit/screenings loadout room are ventilated. • The selector zones and aerated zone 1 of the aeration basins are covered and ventilated.The remaining aerated zone 2 and 3 will be covered to meet the visual criteria, but no odor control is provided. • The Truck Loadout includes odor control for the sludge loading platform connection to the top of the truck. No odor control is included for inside the Truck Loadout bay. • The rotary drum thickeners are enclosed and have odor control ventilation,and odor control is provided for the sludge storage tanks. 3.1 Odor Control Ventilation Criteria Ventilation rates for sizing odor control systems should comply with NFPA 820. In general,ventilation rates should meet the following objectives: 1 TECHNICAL MEMORANDUM • Maintain a negative pressure of 0.1-inch water column (WC)within wastewater or sludge holding tanks and raw wastewater wet wells to contain odors under the following conditions: — Dynamic liquid level changes — Estimated crack openings in storage tank covers treated as sharp-edged orifices • Maintain sufficient velocities across an opening to prevent fugitive odors when a single access cover is removed. • Provide adequate turnover rate and air scavenging within tanks to reduce corrosion resulting from hydrogen sulfide(H2S) pockets. For sludge storage tanks a slight negative pressure will contain odorous emissions from openings,such as air intakes,gaps around access doors,or when an access door is opened.The negative pressure is developed when air is being withdrawn from the tank and the open area for leakage into the tank is restricted.When the tank is being filled,the FA exhaust flow will exceed the sludge feed rate to prevent odors emitted through openings.An air turnover rate,or air exchanges per hour based on a half full tank volume, is used to determine the design air flow rate. 3.2 Odor Potential and Goals The Tryon Creek WWTP exhibits low levels of odor and odor control treatment is not currently used.The primary odor component associated with influent wastewater is H2S.The H2S level to be treated by the odor control system included in this proposal is assumed to range between 1 and 5 parts per million by volume(ppmV),with slightly higher levels expected at IPS and headworks. Less H2S is expected at solids processes; however,other reduced sulfur compounds may be present(such as methyl mercaptan and dimethyl sulfide). The odor control system for the LOWWTF is designed to meet contractual limits of less than 5 dilutions-to-threshold (D/T)at the property line as determined by dispersion modeling(AERMOD)on the highest one-hour average. 3.3 Odor Control Equipment Design Criteria The odor control system includes the exhaust fans,ductwork, dampers and odor control equipment.The odor control treatment approach is activated carbon. A separate odor control system will be used for the IPS versus the headworks and solids facilities. Each system will be located near the facilities being served to minimize the amount of ductwork. Table 3.1 summarizes the design criteria for the activated carbon adsorbers for both systems. Table 3.1—Activated Carbon Odor Control System Design Criteria IPS,Truck Loadout and Portland Headworks,Aeration Basins and Interceptor Drop Structure Description Solids Handling Criteria Criteria Quantity 1 duty and 1 standby 1 duty and 1 standby Carbon media type High capacity(0.2 gm H2S/cc High capacity(0.2 gm H2S/cc carbon) carbon) Performance requirements, H2S removal 99 percent H2S removal for inlet concentrations more than 10 ppmV; maximum of 0.1 ppmV if inlet is less than 10 ppmV Performance requirements,odor(D/T) removal 95 percent odor(D/T) removal for inlet concentrations more than 5,000 D/T; maximum of 100 D/T if inlet is less than 5000 D/T Odor Control Fan Quantity 2 2 D/T dilutions-to-threshold ppmV parts per million by volume 2 TECHNICAL MEMORANDUM 3.4 Discharge Stack Design Each odor control system will discharge treated air through a stack to help with dispersion.The following criteria will be incorporated into the stack design: • Stack diameters will be sized to maintain a minimum exit velocity of 3,000 feet per minute.This is for inducing adequate dilution through mixing of plume gases with fresh outside air to minimize offsite odor impacts. • To the extent possible,stack locations and heights will be such that stacks will extend above local recirculation zones and upwind and downwind obstacles. In addition,stacks will be located to prevent stack discharge gases from re-entering occupied spaces through intake louvers and openings. • Stacks will be uncapped to allow a full vertical exhaust jet.Any rainwater will be drained at the bottom of the stack. • Dispersion modeling will determine the stack heights necessary to achieve off-site odor goals. 3.5 Odor Control Fans Each carbon adsorber system will have a dedicated fan to ensure uninterrupted ventilation of the odor sources.The fans are directly driven to minimize maintenance associated with replacing belts.The fan speed can be manually adjusted to accommodate system changes. 3.6 Ductwork and Dampers Ductwork conveying foul air requires corrosion resistance to withstand acidic conditions resulting from H2S and warm moist air. Dampers will be the same material as the ductwork. Isolation dampers will be used at each fan for complete isolation during maintenance. Balancing dampers will be used at each air extraction point. Two air flow test ports, located on a straight run of duct and at 90 degrees apart,will be provided on each branch,stack,and common header for air flow balancing. Foul air sample ports will be used to obtain air samples for analysis on common ducts leading to the odor control system as well as at the stack discharge. Low point drains will be provided with P-traps and piped to nearby drains.All ducting shall slope in the direction of air flow by 1 percent. 4. Exclusions • Excludes collection system odor control except for the Portland Interceptor drop structure. • Excludes odor control for the existing Tryon Creek Pump Station. 3 TECHNICAL MEMORANDUM 5 Stormwater Management Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Debora Piemonti/Jacobs Reviewer: Marielle Coquia/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal for stormwater management design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). The site is located within the Foothills Flood Management Area(FFMA)and encompasses approximately six acres.The site is a bowl- like area north of Foothills Road; high ground separates it from the Willamette River to the east,Tryon Creek to the north, Oswego Pointe condominiums to the south, and State Street and the railroad to the west. Currently,stormwater is drained by a 48-inch pipe to Tryon Creek.The pipe is equipped with a flap gate at its outlet,and passive backflow valves at points of local connection in the FFMA preventing it from backflowing into the FFMA when it becomes surcharged at high river levels. During high flows,water is diverted to a nearby stormwater pond using a system of gates and pumps.The pond is manually operated and drained once capacity is available in the creek.Tryon Creek is listed as impaired for dissolved oxygen during the spawning period,which is October 15 to May 15. 2. Codes, Standards, Regulations, and References The codes and standards will conform to the following codes and references: • 2020 Lake Oswego Stormwater Management Manual • 2024 City Code and Charter of Lake Oswego 13. Design Criteria The existing site has approximately 200,000 square feet of impervious area.The proposed redevelopment will be equal to or less than the previous amount of impervious area. City Code 38.25.001:Stormwater Management • 38.25.120: Large project is more than 3,000 square feet of new, replaced/redeveloped,or both of impervious area. • 38.25.125 a. Use maximum extent practicable to reduce post-development runoff rate,volume,and pollutant load to match pre- development conditions. i. Pre-development is assumed to be pre-settlement. b. (part 3)All projects to use retention via infiltration to extent allowed by site's infiltration capacity and setbacks designated by the stormwater management model (SWMM). c. (part 4) Infiltrate 100%of the 10-year 24-hour storm event. Provide technical analysis based on infiltration test to clarify why that is not possible. Infiltration is likely infeasible due to low infiltration rates and avoiding infiltration at the base of the steep slope to the west of the 1 TECHNICAL MEMORANDUM site. 2020 Lake Oswego Stormwater Management Manual • 2.5.2 Box: Feasibility of infiltration can be a function of soil permeability,depth to groundwater, and landslide susceptibility. Lack of site area due to development is NOT a stand-alone reason to NOT do infiltration. • 2.5.3 Design for Water Quality:Treat 80%of average annual runoff(1 inch in 24 hours). a. Table 3.1 for list of stormwater best management practices(BMPs)that provide water quality treatment b. Part 4.6 for BMP design guidelines • Table 2.1: Requirements for Large Project a. Infiltrate 10-year, 24-hour storm if feasible b. Treat 80%of average annual runoff c. Flow Control for 2-year, 5-year,and 10-year to predeveloped amount(CN=70) d. Downstream Analysis per Section 5.8 • 2.5.4: Design for Flow Control a. Not required for projects that discharge directly to the Willamette River,Tualatin River,or Lake Oswego AND that have the following: ii. Must have man-made conveyance system all the way to ordinary high water of exempt water body iii. The man-made conveyance system going to exempt water body has capacity for the new project plus any previous areas that were draining to the pipe system iv. Any erodible elements in the man-made system are adequately stabilized to prevent erosion under conditions noted above. • 6.3.1: Floodplains:Stormwater facilities must be designed 3.3 feet above the highest base flood elevation reached on the property during the 1996 flood (as shown on LO Maps). • Section 7,table 4 Performance Standards: — 80%reduction in suspended solids, 30% reduction in copper,and 60%reduction in zinc. • Project assumes that Standard Local Operating Procedures for Endangered Species(SLOPES) is not triggered as the project does not require impacts to wetlands or work below ordinary high-water(OHW). 4. Description of Work Major components The LOWWTF occupies most of the site, leaving only small areas for stormwater facilities. Due to spatial limitations,the proposed stormwater design approach includes collecting site stormwater and conveying to the head of the LOWWTF for treatment through the facility.The proposed system complies with SWMM requirements for water quality and flow control. Calculations The expected surface water flows were calculated using the Simple Rational Method. Q = CiA Where Q(cubic feet per second) is the total runoff, C is the runoff coefficient based on land use, i(inch/hour) is the intensity of the rainfall of chosen frequency for a duration equal to the time on concentration,and A is the total area (acre). C=0.9 The intensity was calculated using the ODOT intensity curves,assuming that the time of concentration for the site is 11 minutes. Preliminary hydrologic analysis using the Rational Method estimates total site runoff at approximately 3.75 cubic feet per second (2.4 million gallons per day) under 10-year design storm conditions.This flow is routed to the LOWWTF headworks. 2 TECHNICAL MEMORANDUM 5. Exclusions None. 1 131 TECHNICAL MEMORANDUM 6-1 Architectural Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Caleb Lowery/Jacobs Reviewer: Geoff Kirsten/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal architectural design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References All facilities will be designed to conform to the following architectural design-related codes,standards,and regulations,as required by the local authority. • Building Code: 2025 Oregon Structural Specialty Code(OSSC) • Fire/Life Safety: 2025 Oregon Fire Code(OFC) • Energy Code: 2025 Oregon Energy Efficiency Specialty Code(OEESC)and 2022 American Society of Heating, Refrigerating, and Air Conditioning Engineers(ASHRAE)90.1 Energy Standard for Buildings • Accessibility: 2025 Oregon Structural Specialty Code, Chapter 11—Accessibility(OSSC)and in accordance with 2017 ICC A117.1. • Development Standards: City of Lake Oswego, OR—City Code, Chapter 50. 06.001.5; Commercial, Industrial, and Multi-Family Development not located in the Foothills Mixed-Use (FMU)Zone, and Minor Development in the R-DD(Res- Detached/Duplex)Zone Standards for Approval (Industrial Zone,City Code). • The proposed Lake Oswego Wastewater Treatment Facility is defined as a "major public facility,"which is a permitted use in the City's Industrial(I)zone.General development standards include: — Maximum building height of 50 feet. - Maximum Floor Area: 1.0:1. — Design standards include: ▪ The design of structures must show complementary relationship to adjacent buildings"of good design"with regard to materials,setbacks, roof lines, height,and overall proportions. • Design elements(awnings, lights,windows) must be complementary to style of structures. • Mechanical equipment must be screened or in locations where they will not be visible. • Design must complement and preserve existing natural landforms,trees,and shrubs. • Assumption that there are no public spaces at the LOWWTF. • Assumption that there is no visible water surfaces of treatment process water. Grating suffices as a cover option. 1 TECHNICAL MEMORANDUM 6-1 I 3. Fire Suppression System No facilities are planned to include an automatic fire suppression system based on OSSC requirements. No additional requirements per local ordinance have been determined. Fire extinguishers will be stationed in all facilities in compliance with code requirements and will be generally located at main points of egress. 4. Sanitary and Safety Provisions Required plumbing fixtures for the LOWWTF will be provided at the Administration and Maintenance Building per 2025 OSSC Plumbing Fixture Requirements(Chapter 29,Table 5.1).The minimum quantity of required fixtures(toilets, lavatories,service sinks, and drinking fountains) is based on the total building area and corresponding occupancy group and occupant load. Safety shower and eyewash stations will be provided near hazardous chemical storage, loading,and use locations.Washdown facilities, utility sinks,and hand-washing stations will be provided at process buildings,where appropriate. 5. Sustainability Tables 5.1 and 5.2 list the basic applicable data required by ASHRAE 90.1(2022),as referenced by the 2025 OEESC,for Climate Zone 4C(Clackamas County). Table 5.1—OSSC Building Envelope Insulation Rating Requirements—Fully Conditioned Building Envelope Element Required for Climate Zone 4C(Clackamas County,OR) Roofs: Insulation entirely above roof deck U-0.032(R-30 CI Min) Roofs: Metal Building U-0.037(R-30 CI or R-19C1 + R-11 Liner Min ) Walls: Mass U-0.104(R-9.5 CI Min) Walls: Metal Building U-0.060(R-15.8 CI Min) Walls: Below Grade C-0.119(R-7.5 CI Min) Slab-on-Grade Floors: Unheated F-0.520(R-15 for 24 In. Min) Doors: Non-swinging U-0.310(R-3.3 Min) Doors:Swinging U-0.370(R-2.7 Min) Vertical Fenestration: Entrance Doors Assembly maximum: U-0.63; SHGC maximum:0.33 VT/SHGC minimum: 1.10 Vertical Fenestration: Fixed Assembly maximum: U-0.36 SHGC max:0.36 VT/SHGC min: 1.10 Skylights Assembly maximum: U-0.50 SHGC max:0.40 Air Barrier(IECC C402.5) Yes Table 5.2—OSSC Building Envelope Insulation Rating Requirements—Semi-Heated Building Envelope Element Required for Climate Zone 4C(Clackamas County,OR) Roofs: Insulation entirely above roof deck U-0.093(R-10 CI Min) Roofs: Metal Building U-0.082(R-19 Min) Walls: Mass U-0.580(R Not Required) Walls: Metal Building U-0.162(R-13 Min) Walls: Below Grade C-1.140(R Not Required) Slab-on-Grade Floors: Unheated F-0.730(R Not Required) 2 TECHNICAL MEMORANDUM 6-1 Doors: Non-swinging U-0.310(R-3.3 Min) Doors:Swinging U-0.370(R-2.7 Min) Vertical Fenestration: Entrance Doors Assembly maximum: U-0.77; SHGC maximum: Not Required VT/SHGC minimum: Not Required Vertical Fenestration: Fixed Assembly maximum: U-0.55 SHGC max: Not Required VT/SHGC min: Not Required Skylights Assembly maximum: U-0.75 SHGC max: Not Required Air Barrier(IECC C402.5) Yes Source:2025 OEESC,Tables 502.1.1 and 502.1.2. Note: Project is in Lake Oswego,Oregon. 1 6. Accessibility Spaces frequented only by service personnel for maintenance, repair,and/or occasional monitoring of equipment are not required to comply with accessibility requirements(see OSSC Chapter 11,Section 1103.2.9).This includes all of the process spaces. Only the Administration Building and Maintenance Building will be accessible. Public tours are not planned for the LOWWTF. 7. Design Criteria Buildings are designed to provide functional space appropriate for the processes and the equipment being housed.Space size is determined by process function,equipment size,and operator needs for access,egress,and ease of equipment maintenance. Response to climate and local environment will be met by conformance to OEESC requirements. Facilities will be designed with forms,details,and materials consistent with the proposed architectural theme that complies with the City of Lake Oswego City Code.The Administration Building will use a unique mono-slope roof appearance and massing to set it apart from other process facilities on-site,and provide more visual interest as the primary street-facing facade. 8. Overview of Facilities A brief architectural description of each proposed building is included below: 8.1 Administration Building • A one-story facility to house the following: control room,water quality laboratory, break room,offices, restroom, and a locker room. • Building Enclosure: - Architectural wall finish with rigid insulation and furring. - Architectural wall finishes will be various colors, material types and textures to provide visual interest and distinction. - Roofing consists of sloped roof framing with metal roofing over rigid insulation.The roof will cantilever at portions to protect building entry points. - All building enclosure elements will be insulated to meet code minimum. • An automatic fire sprinkler system is not required by code and will not be provided. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: Chemicals used for laboratory are below the maximum allowable quantities set by the OFC. 3 TECHNICAL MEMORANDUM 6-1 8.2 Maintenance Building • A one-story facility to house the following: maintenance shop,vehicular storage bay,and storage areas for maintenance equipment.The building will meet the envelope requirements for conditioned spaces. • Building Enclosure: - Metal building with insulated wall and roof panels. • An automatic fire sprinkler system is not required by code and will not be provided. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: May be small storage of maintenance items such as lubricants and gasoline, but will be well within maximum allowable limits that do not trigger hazardous requirements. 8.3 Headworks • A facility to house the following: screens,grit washer,grit basins,grit pumps and roll-off container. • Building Enclosure: - Concrete walls and ceiling with exposed equipment on the roof. HVAC equipment on top of the facility will be screened per RFP requirements. - Majority of the facility consists of non-conditioned space and is exempt from all thermal envelope provisions of the code. Building enclosure elements at the electrical room will be insulated to meet code minimum. • An automatic fire sprinkler system is not required by code. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: None. 8.4 Blower Canopy • An open metal building canopy or concrete walls and ceiling to house blowers with associated equipment/piping. • An automatic fire sprinkler system is not required by code. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: None. 8.5 Solids Handling • A facility to house pumps,thickening equipment,and storage tanks. • Building Enclosure: - Metal building or concrete walls and roof slabs with exposed equipment on the roof. • An automatic fire sprinkler system is not required by code. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: None. 8.6 Truck Loading • A metal building for trucks to load and remove sludge off-site.The building will be naturally conditioned and mechanically ventilated. Given it's location within the floodplain,the building will include provisions to meet City floodproofing requirements for the portion of the building below the Lake Oswego Design Flood Elevation. • An automatic fire sprinkler system is not required by code. Portable fire extinguishers will be provided. • Chemical Storage/Hazardous Materials: None. 9. Exclusions • Facilities not listed in Section 8 have no architectural components. • Excludes structural or code upgrades to the existing Tryon Creek Pump Station. • Excludes concrete wall enhancements to process basins such as pilasters,form-liners,cladding,etc. • Excludes screening of any equipment other than HVAC equipment on the roof of a building. 4 TECHNICAL MEMORANDUM 6-2 Building Services Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: James Cutz/Jacobs Reviewer: Patrick Rausch/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal building services design for the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes/ Standards, Regulations, and References All facilities will be designed to conform to the following mechanical, plumbing and fire protection design-related codes,standards, and regulations,as required by the State of Oregon,Clackamas County and appropriate local ordinances in effect at the start of design include: • 2025 Oregon Structural Specialty Code • 2025 Oregon Energy Efficiency Specialty Code • 2025 Oregon Mechanical Specialty Code • 2023 Oregon Plumbing Specialty Code • 2025 Oregon Fire Code Design standards for mechanical, plumbing and fire protection published or otherwise referenced by adopted Codes at the start of design include: • American National Standards Institute(ANSI) - Z9.5,American National Standard for Laboratory Ventilation (2022) - Z358.1, Emergency Eyewash and Shower Equipment(2014) • American Society of Heating, Refrigerating and Air-Conditioning Engineers(ASHRAE) - 15,Safety Standard for Refrigeration Systems (2024) — 55,Thermal Environmental Conditions for Human Occupancy(2023) - 62.1,Ventilation for Acceptable Indoor Air Quality(2022) - ASHRAE Handbooks (2025) • Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) — HVAC Duct Construction Standards, Latest Edition (2020) — Seismic Restraint Manual (2024) - Fire Damper Guide(2002) • Air Moving and Conditioning Association (AMCA) • 1 TECHNICAL MEMORANDUM • American Society of Mechanical Engineers (ASME) • American Society of Plumbing Engineers(ASPE) • National Fire Protection Association (NFPA) — 13, Installation of Sprinkler Systems(2025) — 24,Standard for the Installation of Private Fire Service Mains and Their Appurtenances(2025) — 25,Standard for the Inspection,Testing and Maintenance of Water-Based Fire Protection Systems (2026) — 45,Standard on Fire Protection for Laboratories Using Chemicals(2024) — 72, National Fire Alarm and Signaling Code(2025) - 291, Recommended Practice of Fire Flow Testing and Marking of Hydrants(2025) - 820,Standard for Fire Protection in Wastewater Treatment and Collection Facilities(2024) 3. Design Criteria This section provides an overview of the criteria serving as the design basis for HVAC, plumbing,and fire protection. 3.1 HVAC Design 3.1.1 Outdoor, Indoor Design Temperatures and Ventilation Rates Table 3.1—Project Location Project Location: 195 SW Foothills Road,Lake Oswego, Oregon 97034 Latitude: 45°25'15.40" Longitude: 122°39'29.65" Elevation: 50 ft above MSL Climate Zone: 4C Table 3.2 contains the outdoor design conditions used for the project.Climatic data are sourced from the 2021 ASHRAE Handbook— Fundamentals. Table 3.2—Outdoor Design Conditions Weather Station Location: Portland International Airport Summer: 91.7 degrees Fahrenheit(°F) Dry Bulb(DB)/67.4°F Mean Coincident Wet Bulb (MCWB) (0.4%occurrence) Summer Extreme.]: 99.2°F DB/72.5°F Wet Bulb(WB) Winter: 25.9°F DB(99.6%occurrence) Winter Extreme[b]: 21.2°F DB Degree Days Cooling(50/65°F): 2764/484 Degree Days Heating(50/65°F): 983/4179 a. Cooling Extreme Temperature(DB and WB)design condition is used for determining the derated cooling capacity of outdoor condenser units for split systems and VRF systems and for sizing evaporative cooling units. b. Heating Extreme Temperature design condition is used for design of heating components for 100%outside makeup air systems.This temperature is also used for derating the heating capacity of heat pump systems and sizing of supplemental electric or gas heat for this process ventilation load. Table 3.3— Indoor Design Temperatures v 2 TECHNICAL MEMORANDUM Space Type Heating Condition Heating Design Cooling Condition Cooling Design Temperature (°F) Temperature (°F) Occupied Spaces: Occupied 72 Occupied. 75 Unoccupied 65 Unoccupied. 80 Laboratory: Design Temperature 68+/- 1°C Design Temperature 68+/- 1°C Maintenance Facility: Design Temperature 50 NA. Natural Ventilation Electrical Rooms: NA Not heated Design Temperature 75 Server Rooms: NA Not heated Design Temperature 68 Process Spaces- Design Temperature. 50 Design Temperature 104iai Insulated: Process Spaces— NA Not heated Design Temperature 104iai Uninsulated: a. Cooling is provided as ventilation-only(no refrigerant-based cooling).Temporary temperature excursions exceeding the cooling design temperature are expected to occur on days where the ambient temperature exceeds the summer ambient design temperature. 3.1.2 Ventilation, Outside Air, and Exhaust Rates Table 3.4 documents the minimum ventilation rates required by NFPA 820 for wastewater treatment plant areas and the Mechanical Code for non-process areas at the LOWWTF. Table 3.4— Minimum Ventilation Rates Space Type Minimum Ventilation Rate Minimum Exhaust Rate Ventilation Standard Occupied Spaces: Varies,contributions from both Varies, provided based on OMSC Ch.4,Table 403.3.1.1 number of occupants and floor area space type,quantity of plumbing fixtures and square footage or space pressurization Laboratory: Approximately 90%of fume hood 80 FPM wide-open fume hood ANSI Z9.5, IBC Ch. 12 exhaust air makeup and as required sash velocity for cooling Maintenance Facility: Natural ventilation openings equal to NR OMSC Ch.4,Section 402 and 4%of floor area or 10 CFM/person Table 403.3.1.1 plus 0.06 CFM/ft2 mechanical ventilation Electrical Rooms: NR; If economizer is used, provide NR OMSC Ch.4 approximately 10%OSA for pressurization Server Rooms: NR; If economizer is used, provide NR OMSC Ch.4 approximately 10%OSA for pressurization Process Spaces, 2 ACH If provided,approximately ASHRAE 62.1 Unclassified, 10% less than supply air rate Ventilated[al' Process Spaces, 6 ACH 6 ACH NFPA 820 Unclassified by Ventilation: 3 TECHNICAL MEMORANDUM a. Not all process spaces are provided with ventilation.Refer to Section 4 below. 3.1.3 Energy Code Compliance Requirements The HVAC and service water heating systems are to comply with the applicable requirements of the 2025 Oregon Energy Efficiency Specialty Code. Facility HVAC systems and service water heating systems will be designed to comply with this code, including local amendments. 3.1.4 HVAC Redundancy Redundancy for mechanical cooling systems is provided for electrical and server rooms site wide. Redundancy will be provided in an N+1 configuration,where one additional fully sized unit will be provided in addition to the number of equally sized duty units designed to meet the peak cooling load. Redundancy will be provided for critical cooling only. 3.2 Plumbing Design This section outlines the proposed plumbing design approach for the site. 3.2.1 General Onsite plumbing utilities include potable and non-potable water supply, natural gas,stormwater,sanitary drainage,and process drainage services. Plumbing services across the new buildings and site include water(potable, non-potable), plant effluent, natural gas, building drainage(process,sanitary),and venting(sanitary). Building plumbing services requiring compliance with building codes(non-process)will be specified,designed,and constructed in accordance with the Oregon Plumbing Specialty Code with local amendments.All piping and plumbing accessories in contact with potable water that is intended for drinking will be designed and installed to comply with lead-free standard NSF-61. 3.2.2 Fixtures and Equipment The Administration Building and Maintenance Building will be equipped with low-flow plumbing fixtures for water-use efficiency. Hot water at the Administration Building and Maintenance Building will be provided,as well as for emergency eyewashes. 3.2.3 Water Services Potable water(W1)will be used on site for domestic/potable water fixtures including safety fixtures,sinks,water closets, urinals, drinking fountains,and domestic hot water systems. Hot and cold pipes will be sized as required by the Oregon Plumbing Specialty Code. Process areas will use plant water(W3)service from the plant effluent for washdown hose valves,yard hydrants,seal water, and other process spray requirements. 3.2.4 Drains and Vents The sanitary building drainage from the Administration Building and Maintenance Building will be routed to an on-site sanitary sewer manhole upstream of the influent pump station. Rain and roof drains will be piped to storm drains either directly through pipes or sheet flow on the site to catch basins.See Stormwater TM for more detail. Process area drains for collecting washdown water or for draining basins,channels or tanks will be routed to the plant drain pump station. Process drainage piping is not governed by the applicable plumbing code. 4 TECHNICAL MEMORANDUM 4. Facility Building Mechanical System Descriptions This section presents the general HVAC system and plumbing approach for each facility. Note,all electrical rooms on site are conditioned. 4.1 Administration Building The Administration Building will be conditioned. Exhaust air systems will be required for laboratory fume hood, lab storage room, toilet rooms,and janitor closet. Fume hood exhaust will be an independent system. Other exhaust air inlets will be connected to exhaust fans mounted within the energy recovery ventilators to recover energy into the outdoor air makeup required for ventilation. 4.2 Maintenance Building The Maintenance Building will provide code required outdoor air by natural ventilation, using a combination of operable windows and overhead doors.The facility will also include heating systems.The restroom will be provided with an exhaust fan and heat. 4.3 Influent Pump Station The influent pump station structure is not in a building and no HVAC systems are included.W3 will be provided for washdown purposes. 4.4 Headworks The grit loadout room is exhausted to odor control and make-up air will be provided through passive air intakes. Other headworks areas are not heated or ventilated.The grit pump room and the screenings area will be equipped with W3 washdown stations and hose racks. Drains will be provided in the grit pump room and the grit loadout room for washdown water drainage. 4.5 Aeration Basins The aeration basins have W3 washdown stations with hoses and freeze protection.The pipe gallery has supply air. No heat is included. Drains are included to collect washdown water and convey to the plant drain pump station. 4.6 Blower Canopy The blowers are not in a building and no HVAC systems are included. 4.7 Clarifiers The clarifiers are not in a building and no HVAC systems are included.W3 will be provided for washdown purposes. 4.8 Filtration The filtration facility is not in a building and no HVAC systems are included.W3 will be provided for washdown purposes. 4.9 UV Disinfection The UV disinfection facility is not in a building and no HVAC systems are included.W3 will be provided for the UV process automatic strainer and general washdown. 4.10 Solids Handling The pump room is ventilated for hazardous declassification under NFPA 820.An exhaust air system will remove air from the room.A W3 washdown station and hose rack will be provided in the basement. Drains will be provided to collect washdown and convey to the plant drain pump station. 4.11 Truck Loading The Solids Loadout Facility contains roll-up doors for truck passage and in-situ loading of solids on the truck trailer.Trucks within the facility will adhere to a plant standard operating procedure for turning off engines.As such, no exhaust ventilation or direct connect exhaust ventilation is provided.W3 will be provided for washdown. Drains are provided to convey washdown water to the plant drain pump station. 5 TECHNICAL MEMORANDUM I 5. Exclusions • Facilities not listed in Section 4 have no building mechanical component. • Excludes building mechanical, plumbing and code upgrades to the Tryon Creek Pump Station. 1 6 v TECHNICAL MEMORANDUM 6-3 Corrosion Control Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Dean Wenger/Jacobs Reviewer: Craig Van Horn/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal corrosion control design for the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References The corrosion control design and approach will be in accordance with the following codes and standards: • American Concrete Institute(ACI) — PRC-201.2-2023, Durable Concrete—Guide • American Water Works Association (AWWA) — C104, Cement-Mortar Lining for Ductile-Iron Pipe and Fittings - C105, Polyethylene Encasement for Ductile-Iron Pipe Systems - C205, Cement-Mortar Protective Lining and Coating for Steel Water Pipe-4 In. and Larger—Shop Applied - C209,Tape Coatings for Steel Water Pipe and Fittings - C214, Machine Applied Polyolefin Tape Coatings for Steel Water Pipe - C216, Heat-Shrinkable Cross-Linked Polyolefin Coatings for Steel Water Pipe and Fittings. - C217, Microcrystalline Wax and Petrolatum Tape Coating Systems for Steel Water Pipe and Fittings - C602, Cement-Mortar Lining of Water Pipelines in Place-4 In. and Larger • National Association of Corrosion Engineers International(NACE)/Association for Materials Protection and Performance(AMPP) - NACE No. 1/SSPC-SP5,Joint Surface Preparation Standard White Metal Blast Cleaning - NACE No.2/SSPC-SP10,Joint Surface Preparation Standard Near-White Metal Blast Cleaning — NACE No.3/SSPC-SP6,Joint Surface Preparation Standard Commercial Blast Cleaning — NACE No.4/SSPC-SP7,Joint Surface Preparation Standard Brush-off Blast Cleaning — SP0169,Control of External Corrosion on Underground or Submerged Metallic Piping Systems - SP0188 Discontinuity(Holiday)Testing of New Protective Coatings on Conductive Substrates - SP0274, High Voltage Electrical Inspection of Pipeline Coatings - SP0287, Field Measurements of Surface Profile of Abrasive Blast Cleaned Steel Surfaces Using Replica Tape i 1 TECHNICAL MEMORANDUM • National Association of Pipe Fabricators(NAPF)—500-03, Surface Preparation Standard for Ductile Iron Pipe and Fittings in Exposed Locations Receiving Special External Coatings and/or Special Internal Linings. • The Society of Protective Coatings(SSPC), now AMPP — PA 1,Shop, Field, and Maintenance Painting of Steel — PA 2, Measurement of Dry Coating Thickness with Magnetic Gauges — SP1,Solvent Cleaning - SP2, Hand Tool Cleaning - SP3, Power Tool Cleaning - SP11, Power Tool Cleaning to Bare Metal - SP13,Surface Preparation of Concrete - SP16, Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel,Stainless Steels,and Non-Ferrous Metals - SP17,Thorough Abrasive Blast Cleaning of Non-Ferrous Metals 3. Design Criteria This section evaluates the corrosivity of the exposure conditions anticipated on the project. 3.1 Atmospheric Exposure The project site is located in Lake Oswego,Oregon,south of Portland,Oregon,and next to the Willamette River.Atmospheric exposure to carbon steel and iron is expected to be moderately corrosive,typical of the Pacific Northwest region. A critical value of relative humidity occurs at approximately 60 percent,above which metallic surfaces have sufficient moisture to allow corrosion even if they are not visibly wet. The corrosion potential of building interior conditions is determined by the extent of exposed water surfaces and washdown (which contribute to humidity) and chemical uses within the particular building under consideration. However, building ventilation systems can offset these conditions to a great extent. 3.2 Immersion/Vapor Space Exposure Immersion and vapor space exposure to raw sewage and hydrogen sulfide will be corrosive to unprotected metals.Corrosion resistant alloys will be used where feasible,otherwise high-performance coatings will be used for corrosion protection. Immersion and vapor space exposure to raw sewage and hydrogen sulfide will be corrosive to concrete at certain stages of the treatment process.Wastewater and hydrogen sulfide(H2S)concrete coatings will be used to protect concrete where necessary. 3.3 Buried Exposure 3.3.1 Metals Soil corrosivity testing was performed as part of the geotechnical explorations.Samples were tested for pH,saturated minimum resistivity,sulfide,water soluble sulfate,water soluble chloride,and oxidation-reduction potential (ORP).The results of the testing are presented in Table 3.1.The results indicate that buried metal piping should include cathodic protection due to the likelihood of sulfate reducing bacteria being present in the soil;therefore,cathodic protection is included. 2 TECHNICAL MEMORANDUM Table 3.1—Soil Corrosivity Test Data from Jacobs geotechnical borings, performed by Specialty Analytical Sample pH Resistivity Sulfide(mg/kg) Sulfate (mg/kg) Chloride ORP (mV) (ohm-cm) (mg/kg) B-1-25 4.67 4,450 1,100 61.2 ND ND B-2-25 6.41 5,900 42.3 17.3 3.22 83 B-3-25 7.27 11,000 2,140 35.4 4.50 145 B-4-25 7.13 4,100 1,120 16.0 ND 87 B-5-25 7.01 7,100 2,110 12.9 ND 161 Additional geotechnical soil corrosivity testing was performed by EPCOR and the results are provided in Table 3.2 for an additional point of reference. Table 3.2—Soil Corrosivity Data Provided in the EPCOR Geotechnical Report Sample pH Resistivity(ohm- Chloride (ppm) Sulfate(ppm) Sulfate(% by cm) mass) W-1(7-8 ft) 7.2 4,100 23 190 0.019% W-2(0.3 ft) 7.2 2,800 14 <10 <0.001% W-3(22.5 ft) 7.4 4,600 <10 150 0.015% W-6(4.5-5 ft) 8.0 1,000 20 1400 0.14% Resistivity: Based on the lab saturated minimum resistivity values,the soils range from highly corrosive to moderately corrosive. pH Sample B-1-25 has an acidic pH of 4.5,which will be very corrosive to unprotected carbon steel and iron. In addition to the acidic pH, there is a high concentration of sulfides in this borehole,suggesting that there is a fair possibility of encountering sulfate reducing bacteria in the soil,which creates extremely corrosive conditions toward most metals. Other samples are near neutral, between 6-8. However,samples B-2-25 and B-4-25 have high levels of sulfide and ORP values <100mV,which indicates a possibility of encountering sulfate reducing bacteria, in accordance with Appendix A of AWWA C105. Sulfides Sulfides were present in each sample tested as part of Jacobs' investigation.As mentioned in the pH section,sulfides can be indicative of the presence of sulfate reducing bacteria.These bacteria present extremely corrosive conditions for unprotected carbon steel and iron.Sulfate-reducing bacteria impact cathodic protection criteria;the-950mV polarized potential criterion in AMPP/NACE SP0169 is required if these bacteria are present in the soil. Chlorides The chloride concentration was generally low(<25 ppm) in each of the samples tested between the Jacobs investigation and the EPCOR report.Such a low chloride concentration is not expected to significantly impact the corrosion potential of the soil toward buried metals. Sulfates Sulfates are typically considered with respect to their corrosion potential towards concrete,although they can serve to increase the corrosion potential of the soil toward buried metals. In this case,the sulfate concentrations across the samples ranged from 0.0016%to 0.14%.The EPCOR sample with 1,400 ppm sulfates is classified as Class S1 in accordance with ACI PRC-201.2 and a minimum of Type II Portland cement or Type MS cement are required for sulfate resistance.The rest of the samples are considered Class SO for sulfate exposure and no special concrete requirements are necessary for sulfate resistance. i 3 TECHNICAL MEMORANDUM 3.3.2 Non-Metallics The EPCOR geotechnical report references an Environmental Site Assessment report developed by Wood that states that the soil/groundwater is contaminated with petroleum hydrocarbons.The sampling performed as part of the study indicates that the concentration levels of contaminants are not high based on State of Oregon requirements.Therefore, material selections are based on the assumption of no presence of petroleum hydrocarbons. 3.4 Chemical Exposure — Design Approach The following chemicals are anticipated to be stored and used on the project: • Sodium Hypochlorite, 12.5%:Storage in small tanks. Potentially used for W3 residual and filter cleaning. • Polymer:Storage at Solids Building. Used for solids thickening. 3.4.1 Sodium Hypochlorite, 12.5% Sodium hypochlorite is incompatible with most metals,and general material selection will be preferred materials such as FRP or PVC.Where sodium hypochlorite is injected into steel or ductile iron piping,the pipe will be lined with an epoxy to 10-pipe diameters away from the injection point. The secondary containment area(s)will be coated with a chemical-resistant coating. The W3 piping at the sodium hypochlorite injection point includes a chemical resistant lining from the injection point to a minimum of 10 pipe diameters in length downstream of the injection point. 3.4.2 Polymer Polymer will be used for solids thickening. It can increase the conductivity of water and thereby slightly increase the corrosion potential of water.Otherwise,typical materials will not be impacted. 4. Description of Work 4.1 Major Components — Concrete Coatings Concrete coatings for wastewater/H2S exposure and for protection against biogenic sulfide corrosion will be in accordance with Table 4.1.The extent of coated surfaces will include the vapor space (ceiling and walls)and walls subject to immersion down to a minimum of one foot below the minimum water surface elevation. For some structures it may be prudent to coat the concrete floor as well. Table 4.1—Concrete Coatings for Wastewater/H2S Exposure and Protection Against Biogenic Sulfide Corrosion Facility/ Location Coating System Included Administration Building None Maintenance Building None Portland Interceptor Drop Structure(interior roof,walls,floors) Yes Influent Pump Station (interior roof,walls,floors) Yes Headworks Screens Channels(interior floors and walls) Yes Headworks Grit Head Cells and Grit Effluent Channel (interior roof,walls,floors) Yes Aeration Basins(interior,selector zones and first aerated zone, roof and walls down to 2-feet below Yes minimum water surface) Clarifiers None Filtration None UV Disinfection None 4 TECHNICAL MEMORANDUM Facility/ Location Coating System Included Effluent Junction Box None Solids Handling(interior roof,walls,floors of sludge storage tanks) Yes Truck Loading None Odor Control None Plant Drain Pump Station Wetwell (interior roof,walls,floors) Yes Stormwater Pump Station None Blower Canopy None Concrete secondary containment areas(hypochlorite and polymer,walls and floors) Yes 5. Exclusions None. I 5 I TECHNICAL MEMORANDUM 6-4 Electrical Date: March 30, 2025 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Toby Palin/Jacobs Reviewer: Morgan MacRostie/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal electrical design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References All facilities will be designed to conform to the following electrical design-related codes,standards, and regulations,as required by the local authority: • 2023 Oregon Electrical Specialty Code(National Fire Protection Association [NFPA] 70-2023 National Electric Code) • 2025 Oregon Energy Efficiency Specialty Code(American Society of Heating, Refrigerating,and Air Conditioning Engineers [ASHRAE]Standard 90.1-2022) • 2025 NFPA 110,Standard for Emergency and Standby Power Systems • 2024 NFPA 820. Standard for Fire Protection in Wastewater Treatment and Collection Facilities • 2024 NFPA 101, Life Safety Code 3. Design Criteria 3.1 Reliability/Redundancy The design incorporates main-tie-main (MTM)electrical distribution gear, using a combination of switchgear,switchboards, and motor control centers(MCCs). Redundant process trains will be powered from opposite sides of the MTM gear,to reduce the number of trains offline at a time. The facility includes a centralized diesel standby power system to support critical process and control loads during a utility outage. This system will provide sufficient capacity for 12 hours of operation at full load and will comply with EPA Class 1 reliability requirements for electrical redundancy.The entire plant can be connected to the standby system. In accordance with NFPA 110, load shedding will be implemented for non-essential loads when generator capacity is insufficient to power all plant systems.The plant control system will manage load shedding and enable a controlled restart, prioritizing critical loads and preventing generator overload. 3.2 Utility Coordination Portland General Electric(PGE)will serve as the utility provider for the LOWWTF.The City submitted an application for electrical service to PGE,and PGE has completed a System Impact Study confirming their ability to supply the requested power. The initial plan is to connect to PGE via existing overhead power lines located on the west side of the site. PGE will provide redundant transformers feeding the plant's main switchgear. • 1 TECHNICAL MEMORANDUM The project does not include participation in PGE's Dispatchable Standby Generation Program,which offers cost-sharing for the standby power system. Under this program, PGE can operate the standby generators during periods of high utility demand.Jacobs can support the city in investigation or and participation in this program, but this is not the basis of our Proposal. 3.3 Electrical Distribution The main distribution system will be an MTM low voltage switchgear(480V).This main switchgear will be in the Electrical Building. It will have a transfer controller to connect both sides of the switchgear to a standby power system. 3.4 Facilities Electrical approaches for facilities are described below,see one-line diagram for details. Equipment List is included in Table 1. 3.4.1 Electrical Building The Electrical Building sub-feeds all of the unit processes at the LOWWTF and the Administration and Maintenance Buildings. Utility transformers and the plant standby power system are located next to the Electrical Building. Spare conduit is provided to the Administration Building parking lot to allow for future photovoltaic(PV)and electric vehicle(EV)charging. 3.4.2 Influent Pump Station The influent pump station (IPS) has an electrical room and power distribution equipment.The IPS will be powered from the main electrical switchgear in the Electrical Building.All loads in the IPS will be connected to the centralized standby power system. 3.4.3 Headworks Process equipment and facility loads in the Headworks Building will be powered from power distribution equipment in the Electrical Building.This includes the solids thickening equipment. 3.4.4 Aeration Basins All electrical loads for the aeration basins are powered from the Electrical Building.The main loads for the aeration basin facility are blowers,gates and mixers. 3.4.5 Clarifiers The Clarifier Facility will be fed from the Electrical Building.The main loads for the clarifier facility include return activated sludge (RAS)and biofoam pumps. 3.4.6 Filtration The filtration facility includes a cloth disk filter package system,that is powered from the Electrical Building.All equipment in the filtration facility will be connected to the standby power system. 3.4.7 UV Disinfection UV disinfection is powered from the Electrical Building.There are transformers and distribution panelboards outdoors at the UV facility to derive a neutral and provide power to the UV system for each of the three channels. 3.5 Lighting 3.5.1 Outdoor Lighting To address City requirements and minimize light pollution, all outdoor lighting will comply with the City of Lake Oswego Charter and be DarkSky compliant. Fixtures will use a warm color temperature of 3000K,and lighting along maintenance routes will not exceed an average of 0.3 footcandles. Maintenance lighting for outdoor process areas will also be DarkSky compliant but may provide higher illumination levels when required for safety and task performance.These lights will be manually controlled and normally remain off. Maintenance lighting will be installed at all critical process locations, including: • Influent pump station • Headworks • Aeration blowers • Aeration basin 2 TECHNICAL MEMORANDUM • Clarifiers • Filtration • UV disinfection • Solids handling Area lighting poles will not exceed a maximum height of 22 feet. 3.5.2 Indoor Lighting Indoor lighting shall provide suitable lighting levels for all process and people spaces. Lighting in process areas shall meet environmental criteria, including wet, corrosive, and hazardous combustible areas. Lighting fixtures and controls shall meet the energy efficiency requirements of 2025 Oregon Energy Efficiency Specialty Code(ASHRAE Standard 90.1-2022). 4. Exclusions None. Table 1—Equipment List Facility Type Quantity Capacity(EA) Influent Pump Station Wetwell 1 Non-Clog Submersible 4 4 MGD,70 HP Wetwell 2 Non-Clog Submersible 3 19 MGD,335 HP Wetwell 3 Non-Clog Submersible 3 1250 GPM,40 HP Headworks Screening&Screen Conveyor Perforated Plate 2 8 MGD Perforated Plate 3 19 MGD,250 HP Screening Washing and Dewatering Reversing Auger 2 N/A Grit Removal Stacked Tray 2 20 GPM/ft2 Grit Pumps Recessed Impeller 2 300 GPM Grit Washing and Dewatering Conical Clarifier with Fluidized Bed 2 N/A Aeration Basins Mixers Submersible 16 8.3 HP Biofoam Pumps Submersible,Chopper Recirculating 2 200 GPM @ 30-ft TDH Drain Pump Self-Priming Non-Clog 1 700 GPM @ 40-ft TDH Positive Displacement, Rotary Blowers Screw 5 3,700 SCFM,300 HP Diffusers Fine Bubble N/A N/A Secondary Clarifiers Sludge Collector Non-Metallic Chain&Flight 8(2 Per Clarifier) N/A Return Activated Sludge Pumps Submersible Column 4 3.15 MGD @ 23-ft TDH or, Immersible Non-Clog 4 3.5 MGD @ 27-ft TDH Biological Foam Pit Pumps Submersible,Chopper Recirculating 1 200 GPM @ 30-ft TDH Thickening Tank 3(1 per Tank, 1 Thickening Tank Mixing System Chopper Pump with Mixing Nozzle Standby) N/A Dry Pit, Horizontal End Suction Non- Rotary Drum Thickener Feed Pumps Clog 2 400 GPM @ 50-ft TDH Rotary Drum Thickener Rotary Drum 2(2 Drums Each) 400 GPM,3 HP Polymer System Mechanical, Hydraulic Mixing 2 2.0 GPH, 1 HP v 3 TECHNICAL MEMORANDUM Sludge Loadout Sludge Loadout Pumps Rotary Lobe 2 200 GPM, 10 HP Sludge Loading Platform Articulating N/A N/A Filtration Filtration Cloth Disk,5 Micron Media 4 6.5 GPM/SF Backwash Pumps Dry Pit Centrifugal 4 690 GPM,20 HP Ultraviolet(UV)Disinfection UV Lamp Type Low Pressure, High Output, Incline 3 Channels 30 MJ/cm2 Plant Drain Pump Station Pumps Non-Clog Submersible 3 350 GPM W3 Pumps Pumps Vertical Turbine 3 1 MGD, 30 HP Hypochlorite Chemical System(Plant Maintenance Activities) Feed Pumps Diaphragm 2 2 GPH Storage Tanks IBC-Tote 1 270-GAL Odor Control Odor Control System Activated Carbon 4 2@1,750 acfm, 2@12,400 acfm Centrifugal Fan 4 2@15 HP, 2@20 HP Miscellaneous Diesel Generator 4 600kW Gates Gates, Full Aperture Sealing Slide Gates Gates, Fabricated Slide Automatic Composite Sampler :, I 4 I TECHNICAL MEMORANDUM 6-5 Preliminary Geotechnical Analyses and Recommendations Date: March 30,2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Ben Hoffman/Jacobs Reviewer: Todd Cotten/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to summarize available subsurface information and present geotechnical proposal design criteria for the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes and Standards The following codes and standards were used to develop geotechnical design concepts and preliminary recommendations summarized in this memorandum: • 2025 Oregon Structural Specialty Code,which is based on the 2024 International Building Code(International Code Council [ICC] 2024a), 2024 International Fire Code(ICC 2024b),and 2024 International Existing Building Code(ICC 2024c). • Minimum Design Loads and Associated Criteria for Buildings and Other Structures (American Society of Civil Engineers [ASCE] 2022), including Supplements 1, 2,and 3; hereinafter referred to as ASCE 7-22. It is Jacobs' understanding that the proposed structures for the LOWWTF can be divided into the following two general risk categories,defined in Chapter 16 of the International Building Code(ICC 2024): • Risk Category III: Buildings and other structures that represent hazard to human life in the event of failure. • Risk Category IV: Buildings and other structures designated as essential facilities and buildings where loss of function represents a substantial hazard to occupants or users. A breakdown of each of the proposed structures and which Risk Category each will be designed for is provided in Technical Memorandum:Resiliency, Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility(Jacobs, 2026). 3. Available Subsurface Information Multiple geotechnical exploration programs have been performed at the project site and results of each exploration program were used to develop recommended geotechnical design parameters as well as geotechnical design and construction recommendations. Results of the geotechnical exploration programs are documented in the following reports: • City of Lake Oswego Wastewater Treatment Facility Geotechnical Report(WSP 2023) • Geotechnical Data Report (Jacobs 2025) • Geophysical Reconnaissance: Data Report(Siemens&Associates 2025) 4. Geotechnical Analyses and Recommendations Section 4 summarizes the conceptual level geotechnical analyses and resulting preliminary recommendations developed for the proposal design of the LOWWTF. 1 TECHNICAL MEMORANDUM 6-5 4.1 General Subsurface Conditions Based on review of soil borings and test pits advanced across the project site and presented in the geotechnical reports(WSP 2023 and Jacobs 2025),the general subsurface conditions consist of undocumented fill, underlain by alluvium, underlain by highly weathered bedrock, underlain by slightly weathered to fresh bedrock.The following layer descriptions summarize the general condition of each of the four soil layers encountered at the project site in the order in which they are encountered: • Layer 1,Undocumented Fill:The undocumented fill layer is found at the existing ground surface across the site.The layer thickness is not clearly defined but was generally observed to be less than 10 feet thick during site exploration.The fill material generally consists of gravel,sand,and silt with some construction or other man-made debris as well as occasional cobbles and boulders. • Layer 2,Alluvium:The alluvial soil layer is present below the surficial fill,and the thickness of the layer varies greatly across the site,as the depth to bedrock also varies greatly across the site.The alluvial soil generally consists of interbedded clay, silt,sand, and gravel and was found to have highly variable density/consistency with coarse-grained soil ranging from very loose to dense and fine-grained soil ranging from soft to stiff. Occasional cobbles and boulders as well as large organic material (timbers)were encountered within the alluvial soil,especially near the base of the layer. • Layer 3,Highly Weathered Bedrock:The highly weathered bedrock(weathered basalt) layer is present below the alluvial soil, and the thickness of the layer was observed to generally range from 2 to 5 feet.The weathered basalt can be described as a residual soil with basalt cobbles and boulders in a matrix of clay,silt,sand, and gravel (basalt fragments).The weathered basalt is dense to very dense. • Layer 4,Slightly Weathered to Fresh Bedrock:The slightly weathered to fresh bedrock(basalt) layer is present below the highly weathered bedrock and was generally observed to be massive and hard with moderate to widely spaced fracturing and jointing. More detailed subsurface data and information can be found in the geotechnical reports(WSP 2023 and Jacobs 2025). 4.2 Groundwater Groundwater elevations at select exploration locations have been measured and will continue to be measured where possible.At most locations,groundwater has been measured to be present between approximately 5 and 10 feet below ground surface but can be shallower in some areas at the site. In general terms,the groundwater elevation slopes from west to east toward the Willamette River,with an estimated elevation of 40 feet near the western site boundary and an estimated elevation of 24 feet between the center of the site and eastern site boundary. More detailed groundwater data can be found in the geotechnical reports(WSP 2023 and Jacobs 2025). 4.3 Seismic Design Parameters Seismic design parameters for the project were developed using the online ASCE 7 Hazard Tool. Based on geophysical testing measurements and results obtained at the project site (Siemens&Associates 2025),the site has been classified as Site Class C.Table 1 presents the recommended seismic design parameters developed using the online ASCE 7 Hazard Tool. Table 1—Recommended Seismic Design Parameters Parameter Description Value PGAM MCEG PGA adjusted for Site Class C(g) 0.46 Ss Mapped short-period (at 0.2 second)spectral acceleration (g) 0.94 Sl Mapped long-period (at 1 second)spectral acceleration (g) 0.35 SMs Site-adjusted MCER spectral acceleration at short period (0.2 second)(g) 1.05 SM1 Site-adjusted MCER spectral acceleration at 1 second (g) 0.49 SDS Design short-period (0.2 second)spectral acceleration (g) 0.70 SD1 Design 1 second spectral acceleration (g) 0.33 TL Long-period transition period (sec) 16 Source:ASCE Hazard Tool(https://ascehazardtool.org/) 2 TECHNICAL MEMORANDUM 6-5 Abbreviations: g=acceleration due to gravity MCE=maximum considered earthquake MCEG=maximum considered earthquake geometric mean MCER=risk-targeted maximum considered earthquake PGA=peak ground acceleration sec=seconds 4.4 Seismic Hazards 4.4.1 Liquefaction and Post-Liquefaction Settlement Soil liquefaction is the phase change phenomenon whereby a saturated soil substantially loses strength and stiffness in response to cyclic shear stress induced by earthquake shaking. In general, liquefaction is more likely to occur in loose and saturated granular soil (silty sand,sand,and gravel),although some low plasticity silt and clay may also be susceptible to liquefaction-type behavior, which is usually referred to as"cyclic softening."The susceptibility of a soil deposit to liquefaction is a function of the in situ stress state of the material,degree of saturation,soil grain size, relative density, percent of fines,age of deposit, plasticity of fines, earthquake ground motion characteristics,and several other factors. A preliminary liquefaction screening of each of the soil borings advanced at the project site(WSP 2023 and Jacobs 2025)was performed using the Youd et al. (2001) method to determine liquefaction triggering. Results of the preliminary liquefaction screening showed that isolated lenses of soil within the layer of alluvium in some, but not all, of the soil borings were determined to be potentially susceptible to liquefaction. Post-liquefaction settlement was estimated using procedures developed by Ishihara and Yoshimine(1992)and by Tokimatsu and Seed (1987). Using the available soil boring data and estimated thickness of layers susceptible to liquefaction,the estimated magnitude of post-liquefaction settlement across the project site ranges from 0 to 4 inches. 4.4.2 Lateral Spread and Seismic Slope Instability Lateral spread is defined as the finite, lateral displacement of gently sloping ground as a result of liquefaction in a shallow underlying deposit during earthquake loading.As discussed previously,soil layers susceptible to liquefaction are present at the project site. However, lateral spread is not considered a hazard present at the project site due to the contour of the top of bedrock across the site.Specifically,the eastern side of the site is bounded from north to south by basalt bedrock located just below the ground surface.This shallow bedrock would act as a buttressing force to any lateral soil movement caused by liquefaction of alluvium located west of and deeper than the shallow bedrock along the east side of the site. Due to existing and final grades across the portion of the site that will be developed for the project,seismic slope instability is not considered a hazard for the part of the site that will be developed for the project. However,there is a relatively steep slope that exists above the project along the western boundary of the site that was evaluated for seismic slope instability.A summary of the evaluation for this existing relatively steep slope is summarized in Section 4.7 of this TM. 4.4.3 Tectonic Deformations and Surface Fault Rupture Tectonic deformations result from fault displacements or regional uplift and subsidence during an earthquake. Because no known faults cross the project site,fault displacements and surface ruptures are not anticipated. Regional uplift and subsidence are generally associated with ruptures along subduction zones.Given that the site is located approximately 70 miles from the Cascadia Subduction Zone, minimal uplift and subsidence are estimated for the project site. 4.5 Lateral Earth Pressures Lateral earth pressures acting on buried structures and retaining walls proposed for the project can be influenced by the following: • Amount of wall movement, if any • Sequence of construction • Backfilling methods and materials • Groundwater levels • Presence of surcharge loads • Presence of earthquakes or other dynamic forces 3 TECHNICAL MEMORANDUM 6-5 For lateral earth pressure analyses presented in the Sections 4.5.1 and 4.5.2, it is assumed that imported backfill placed against buried structures and retaining walls will consist of crushed rock that is free-draining and has a total unit weight and internal angle of friction equal to 130 pounds per cubic foot and 35 degrees, respectively,or native overburden soil (existing fill and alluvium)with a total unit weight and internal angle of friction equal to 120 pounds per cubic foot and 32 degrees, respectively. 4.5.1 Static Lateral Earth Pressures Three different states of static lateral soil pressure can act against buried structures and retaining walls:the at-rest state,the active state,and the passive state.At-rest earth pressures are used when the structure is not permitted to move,acting completely rigid, such as a partially buried tank or any other buried structure.Active pressures are used when the top of the wall or structure is permitted to move away from the backfill,and the backfill has sufficient strength to resist creep and reconsolidation (for example, crushed rock backfill). Passive earth pressures are used to estimate the soils resistance to lateral loading from walls and other structures. The recommended static lateral earth pressure coefficients for the three states of stress described are listed in Table 2 for imported backfill and native overburden materials under static conditions with level backfill that is assumed to be free draining.Table 2 also lists the recommended equivalent fluid pressures and lateral load distributions for the same three states of stress. Lateral earth pressure parameters were developed using Rankine, Coulomb,and Log-Spiral theories. 4 4 TECHNICAL MEMORANDUM 6-5 Table 2—Lateral Earth Pressures for Design Earth Pressure Coefficient Equivalent Fluid Pressure (pcf*feet) State of Stress Imported Backfill Native Overburden Imported Backfill Native Overburden At-Rest, Ka 0.43 0.47 56*H 56*H Active, KA 0.25 0.28 33*H 34*H Passive, Kp 6.70 5.70 871*H 684*H Active Dynamic, KAE 0.41 0.45 53*H 54*H with movement Active Dynamic, KAE 0.70 0.78 91*H 94*H little or no movement General Notes: 1. The magnitude of lateral earth pressure at a given height of wall is presented in units of pcf per foot of wall height(H).The wall height is the distance between the ground surface and the base of the wall.Walls should be designed to resist surcharge loads and adjacent at-grade structures.The lateral earth pressure caused by a uniform surcharge load is equal to the anticipated surcharge load multiplied by the applicable earth pressure coefficient K0,KA,or Kp. 2. Substantial movement must take place before the available passive pressure is mobilized.Therefore,a reduced value of passive pressure one- third to one-half of the total passive pressure should be used when calculating resistance to thrust or sliding.The reduced value will depend on the amount of movement allowed by the structural designer. 3. Equivalent fluid pressures were calculated for imported backfill using an estimated moist unit weight of 130 pcf and an angle of internal friction of 35 degrees.Equivalent fluid pressures were calculated for native overburden soil using an estimated moist unit weight of 120 pcf and an angle of internal friction of 32 degrees. 4. For drained earth pressures to be used for design,provisions for adequate drainage behind the wall must be included for all service-life conditions of the structure. 5. Compaction within 3 horizontal feet of the walls should be performed with lightweight,hand-operated equipment so that compaction-induced lateral stresses are limited.If heavy or large equipment is used for compaction immediately adjacent to the arch culvert,lateral stresses will be larger than those listed in this table. 6. Several inches of movement of the buried structure is required in order to use the active dynamic with movement earth pressure coefficient listed in this table. If the buried structure cannot accommodate several inches of movement,the active dynamic with little or no movement earth pressure coefficient listed in this table should be used for design. Abbreviations: H=height of wall pcf=pounds per cubic foot 4.5.2 Seismic Lateral Earth Pressures The dynamic(seismic)active pressure was calculated using the Mononobe-Okabe method (Seed and Whitman 1970, Mononobe and Matsuo 1929,and Okabe 1926). Using the Mononobe-Okabe method,the lateral earth pressure loads from static and seismic loading are calculated as follows: EAE=%•yH2•KAE (resultant static plus seismic active force) Where: EAE= lateral active earth pressure force, including static and seismic conditions y=total unit weight of the soil H=wall height KAE=seismic active earth pressure coefficient The seismic active earth pressure coefficient(KAE)was determined using the soil properties for the imported backfill and native overburden materials and a seismic coefficient of 0.23g(50 percent of the MCEG peak ground acceleration [PGA] adjusted for Site Class C,0.46g,as shown in Table 1).The resulting KAE values for each of the materials are listed in Table 2,as well as the recommended equivalent fluid pressures. 5 TECHNICAL MEMORANDUM 6-5 The use of 50 percent of the PGA assumes several inches of movement is permissible during seismic loading.The resulting KAE and equivalent fluid pressures using a seismic coefficient of 0.46g are also listed in Table 2 for each of the materials. 4.6 Foundation Recommendations The project will include both Risk Category III and Risk Category IV structures as defined in Chapter 16 of the 2024 International Building Code(ICC 2024a). Based on preliminary evaluations,the following general recommendations for each Risk Category foundation approach should be used for conceptual design for the project: • Risk Category III Structures:The native overburden soil layers present at the site should adequately support and will meet general design criteria required for Risk Category III structures supported on shallow foundations. However,the native overburden soil may require removal of unsuitable material and replacement of imported foundations stabilization material in some structure areas across the site. • Risk Category IV Structures:The native overburden soil layers present at the site will not adequately support and will not meet general design criteria required for Risk Category IV structures supported on shallow foundations.Therefore,conceptual design for Risk Category IV structures assumes that drilled shaft or micropile foundations will be installed and socketed into the slightly weathered to fresh bedrock layer to transfer Risk Category IV structure loads to the bedrock layer.As an alternative foundation solution,the native overburden layers can be removed down to competent weathered bedrock or fresh bedrock and replaced with imported granular fill that is placed and compacted in lifts in all project site areas supporting Risk Category IV structures. Sections 4.6.1 and 4.6.2 summarize preliminary analyses and recommendations for structure foundations. 4.6.1 Shallow Foundations 4.6.1.1 Allowable Bearing Capacity Bearing capacity analyses for shallow foundations have been performed for the general foundation preparation approaches described previously for Risk Category III,In addition,bearing capacity analyses have been performed for Risk Category IV structures should the foundation design approach change to removal and replacement of native overburden layers.Bearing capacity analyses were performed using the ultimate bearing capacity equation for shallow foundations(slab-on-grade and spread footings)developed by Vesic(1975).An equivalent footing with dimensions of 12 feet by 12 feet was used in the analysis to best model a slab-on-grade foundation,and a square footing with dimensions of 4 feet by 4 feet was used to best represent shallow footing foundations. Ultimate bearing capacity values represent the bearing capacity of the soil for a factor of safety equal to 1.Jacobs recommends that a factor of safety equal to 3 be applied to the ultimate bearing capacity values in order to determine an allowable bearing pressure for use in design. Based on the analyses,Table 3 summarizes results of the preliminary allowable bearing capacity analyses performed for both risk categories and multiple foundation configurations. Table 3—Allowable Bearing Pressure Minimum Allowable Bearing Foundation Depth Pressure Structure Description) Foundation Type (feet)2 (ksf)3 Risk Category III Slab-on-grade 1 2.8 General structures with no over-excavation Spread footing 2 2.3 Risk Category IV Slab-on-grade 5 9.3 Deep basins with over-excavation to bedrock Slab-on-grade 1 4.4 Risk Category IV General Structures with over-excavation to bedrock Spread footing 2 3.6 Notes: 1. Minimal over-excavation anticipated for Risk Category III structures.Over-excavation of overburden soil to competent weathered bedrock or fresh bedrock required for Risk Category IV structures. 2. Minimum foundation depth below finished grade. 3. Allowable bearing pressure includes a factor of safety of 3 applied to ultimate bearing capacity. Abbreviations: ksf=kips per square foot 6 TECHNICAL MEMORANDUM 6-5 4.6.1.2 Sliding As discussed previously, Risk Category III foundations will be placed on native overburden soil that primarily consists of fine-to coarse-grained cohesionless soil; Risk Category IV foundations can be placed on imported granular fill that is placed and compacted in lifts with the removal of overburden layers. Based on Table 1 on page 7.2-63 of Foundations and Earth Structures(NAVFAC 1986), the recommended coefficient of sliding friction for use in foundation design for Risk Category III and Risk Category IV structures is provided in Table 4. Table 4—Coefficient of Sliding Friction 8' Coefficient of Sliding Risk Category (deg) (tan 6') III 26 0.49 IV 30 0.58 Abbreviations: 6'=interface friction angle between foundation and soil deg=degrees tan 8'=coefficient of sliding friction between foundation and soil 4.6.1.3 Settlement For preliminary analyses purposes,Jacobs assumed that static settlement of shallow will be less than 1 inch as long as bearing pressures are limited to the allowable bearing pressure values provided in Table 3 for both Risk Category III and Risk Category IV structures. Across the site, post-liquefaction settlement is estimated to vary between 0 and 4 inches.This range of post-liquefaction settlement (and differential settlement)should be used for seismic evaluation of Risk Category III structures. Because the native overburden soil will be removed down to competent weathered bedrock or fresh bedrock for Risk Category IV structures if shallow foundations are used,any liquefiable layers will be removed and no post-liquefaction settlement is expected for the Risk Category IV structures. 4.6.2 Deep Foundations 4.6.2.1 Drilled Shafts Drilled shaft foundations are proposed for Risk Category IV structures that have relatively high axial and lateral foundation loads (such as the aeration basins and secondary clarifiers)that cannot be reasonably carried by micropile foundations. Based on geotechnical and structural evaluation of the proposed drilled shaft foundations,the following are general recommendations for conceptual design: • Minimum diameter of 24 inches • Minimum rock socket length of 5 feet(depth below top of slightly weathered to fresh bedrock layer) • Nominal axial resistance estimated to be 1500 kips per shaft • Nominal uplift resistance estimated to be 300 kips per shaft 4.6.2.2 Micropiles Micropile foundations are proposed for the remaining Risk Category IV that have lower axial and lateral foundation loads that do not need to be supported by drilled shafts. Based on geotechnical and structural evaluation of the proposed micropile foundations,the following are general recommendations for conceptual design : • Typical diameter ranging from 9 to 12 inches • Minimum rock socket length of 5 feet(depth below top of slightly weathered to fresh bedrock layer) • Nominal resistance for both compression and uplift loading estimated to be 300 to 400 kips per micropile 4.7 Global Stability Limit equilibrium methods were used to preliminarily evaluate global stability for static and seismic loading conditions for the i 7 TECHNICAL MEMORANDUM 6-5 relatively steep slope located along the western boundary of the project site.The computer program SLIDE2 Version 9(Rocscience, 2021)was used to perform the analyses;the Spencer and GLE/Morgenstern-Price methods were used to calculate the factors of safety for each of the stability analyses performed.Additionally,a pseudo-static approach was implemented for the seismic evaluation to determine the yield acceleration, Icy.The yield acceleration is defined as the acceleration applied to the pseudo-static slope stability model that results in a factor of safety equal to 1.0. Based on Newmark(1965), if the PGA value exceeds the Icy value, the potential for permanent displacement of the critical failure plane exists. Methods developed by Bray and Macedo(2019)were used to determine the estimated magnitude of permanent displacement using the ky from the pseudo-static slope stability models as well as other parameters. In addition,the following assumptions were used for the preliminary global stability analyses: • A single boring, B-5-25,was advanced by Jacobs(2025)from the existing pedestrian path located on the slope above the project site.This boring was used to estimate subsurface conditions within the slope and showed that the upper 10 feet consists of firm to very stiff clay with sand and gravel that is underlain by very dense gravel and sand with clay.Subsurface conditions encountered in boring B-5-25 were used to model soil properties of the steep slope area separately from the remainder of the site. • A non-circular(block)failure surface was selected for the static and pseudo-static stability analyses. The results of the preliminary global stability analysis for static loading conditions show that the factor of safety of the existing steep slope is approximately 1.3.A minimum factor of safety equal to 1.3 meets the required criteria established in Chapter 7 of the Oregon Department of Transportation Geotechnical Design Manual (2024)for slopes adjacent to but not supporting structures. The results of the preliminary global stability analysis for pseudo-static(seismic) loading conditions show that a k,,value equal to 0.15g results in a factor of safety equal to 1.0,which is less than the PGA value of 0.46g(Table 1).Therefore,slope displacement was estimated using methods developed by Bray and Macedo(2019).A mean displacement of the upper 10 feet of the existing slope equal to 4 inches,with a range of slope displacement equal to 2 to 9 inches (plus or minus one standard deviation), was estimated for the existing steep slope.With a maximum estimated slope displacement of 9 inches, no impacts to proposed structures are anticipated due to slope displacement during and following a design-level seismic event. The results of the static and pseudo-static global stability analyses using SLIDE2 Version 9(Rocscience 2021)are provided in Attachment 1. 5• Preliminary Geotechnical Design and Construction Considerations The following preliminary geotechnical design and construction considerations have been developed for the project: • The thickness of overburden soil (primarily consisting of fill material and alluvium)varies greatly across the project site. In addition,the overburden soil is relatively non-uniform and varies greatly in particle size and consistency/density.Therefore, it should be expected that loose/soft and saturated zones of unsuitable soil will be encountered during excavation and subgrade preparation and will need to be removed. • Cobbles, boulders, logs,and other large debris were encountered occasionally within the overburden soil in most areas across the project site during the geotechnical exploration programs. In addition,the highly weathered bedrock layer was found to contain cobble and boulder sized fragments of basalt. It should be expected that large material and debris will be encountered during earthwork activities required for construction and will require removal. • The same cobbles, boulder, logs,and other large debris observed within the overburden soil as well as the weathered bedrock may be encountered during installation of the proposed drilled shaft and micropile foundations.Obstructions during installation of the proposed drilled shaft and micropile foundations should be anticipated. • Native overburden soil layers present at the project site will not adequately support and will not meet general design criteria required for Risk Category IV structures supported on shallow foundations.Therefore,Jacobs recommends that the Risk Category IV structures be supported on drilled shaft and micropile foundations in order to transfer foundation loads to the slightly weathered to fresh bedrock layer.As an alternative,shallow foundations could be used to support Risk Category IV structures with the removal of overburden soil down to competent weathered to slightly weathered (or fresh) bedrock and replacement with imported granular fill that is placed and compacted in lifts. If the shallow foundation alternative is selected for Risk Category IV structures, roundwater level measurements show that groundwater elevations are located above the depth of over-excavation required (generally a difference of approximately 5 to 10 feet). Design and construction for the project should consider dewatering scope and associated costs required to keep excavations dry during overburden removal and backfilling for Risk Category IV structures. • In project site areas where native overburden soil will not be removed (or improved), post-liquefaction settlement is estimated to range from 0 to 4 inches. Risk Category III structures and other project elements such as utilities that are located where 8 TECHNICAL MEMORANDUM 6-5 unimproved overburden soil will remain should be designed considering post-liquefaction settlement and differential settlement of up to 4 inches. • A relatively steep slope borders the west side of the site and is located above and outside of the footprint of any project development.Construction required for each of the proposed facilities for the project should not negatively affect the existing stability of the steep slope.Jacobs has performed preliminary global stability analyses for static and seismic loading conditions. However, if construction of the project will require potential disturbance of the slope,such as large excavations near the existing toe of slope,Jacobs recommends that additional static and seismic global stability evaluations of this slope during subsequent phases of design for the project. 16. Exclusions In soils,foundation,groundwater,and other subsurface investigations,the actual characteristics may vary significantly between successive test points and sample intervals and at locations other than where observations, exploration, and investigations have been made. Because of the inherent uncertainties in subsurface evaluations,changed or unanticipated underground conditions may occur that could affect total project cost and/or execution. Please see our proposal assumptions and clarifications,the Prime Agreement,and the project risk register for anticipated risk allocation. 9 TECHNICAL MEMORANDUM 6-5 I 7. References American Society of Civil Engineers(ASCE). 2022. Minimum Design Loads and Associated Criteria for Buildings and Other Structures. ASCE/SEI 7-22. Reston,Virginia. Bray,J.D. and J. Macedo.2019. Procedure for estimating shear-induced seismic slope displacement for shallow crustal earthquakes. Journal of Geotechnical and Geoenvironmental Engineering, 145(12). International Code Council (ICC). 2024a. International Building Code. Falls Church,VA. International Code Council (ICC). 2024b. International Fire Code. Falls Church,VA. International Code Council (ICC). 2024c. International Existing Building Code. Falls Church,VA. Ishihara, Kenji,and Mitsutoshi Yoshamine. 1992. "Evaluation of Settlements in Sand Deposits Following Liquefaction During Earthquakes."Soils and Foundations 32(1): 173-188. March. Jacobs. 2026.Technical Memorandum: Resiliency. Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility. March. Jacobs. 2025.Geotechnical Data Report: Lake Oswego Wastewater Treatment Facility. Prepared for City of Lake Oswego. December. Mononobe, N.and H. Matsuo. 1929. "On the Determination of Earth Pressure During Earthquakes." Proceedings: World Engineering Conference,Tokyo, 1929. Naval Facilities Engineering Command (NAVFAC). 1986. Foundations and Earth Structures. Design Manual 7.02. Department of the Navy.Alexandria,Virginia.September. Newmark, N.M. 1965. Effects of Earthquakes on Dams and Embankments. Geotechnique, 15, 139-160. Okabe,S. 1926. "General Theory of Earth Pressures."Journal of the Japan Society of Civil Engineering 12(1). Oregon Department of Transportation (ODOT).2024.Geotechnical Design Manual. May 2024. Rocscience. 2021.SLIDE2.Version 9. Seed, H.B.and R.V.Whitman. 1970. "Design of Earth Retaining Structures for Dynamic Loads." Lateral Stresses in the Ground and Design of Earth Retaining Structures:State-of-the-art Papers Presented at 1970 Specialty Conference. Pages 103-147.American Society of Civil Engineers. New York. Siemens&Associates. 2025. Geophysical Reconnaissance: Data Report.Cultural Resources Evaluative Testing&Geotechnical Investigations, Lake Oswego,Oregon. Prepared for Jacobs.September 25. Tokimatsu, Kohji,and H. Bolton Seed. 1987. "Evaluation of Settlements in Sands Due to Earthquake Shaking."Journal of Geotechnical Engineering 113(8):861-878.August. Vesic,A.S. 1975. "Bearing Capacity of Shallow Foundations." In Foundation Engineering Handbook,edited by H.F. Winterkorn and H. Fang, pp. 121-147. New York:Van Norstrand Reinhold. 1st Edition. WSP USA Environment& Infrastructure Inc. (WSP). 2023. City of Lake Oswego Wastewater Treatment Facility Geotechnical Report. Prepared for EPCOR/AECON.July. Youd,T.L., I.M. Idriss, R.D.Andrus, I.Arango,G.Castro,J.T. Christian, R. Dobry,W.D. Liam Finn, L.F. Harder Jr., M.E. Hynes, K. Ishihara,J.P. Koester,S.S.C. Liao,W.F. Marcuson III,G.R. Martin,J.K. Mitchell,Y. Moriwaki, M.S. Power, P.K. Robertson, R.B.Seed, K.H.Stokoe II. 2001. "Liquefaction Resistance of Soils:Summary Report from the 1996 NCEER and 1998 NCEER/NSF Workshops on Evaluation of Liquefaction Resistance of Soils."Journal of Geotechnical and Geoenvironmental Engineering 127(10):817-833. 10 TECHNICAL MEMORANDUM 6-6 Instrumentation and Control Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Katie Klacik/Jacobs Reviewer: Lionel Wood/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal instrumentation and control design for the Lake Oswego Wastewater Treatment Facility(LOWWTF). The process control system (PCS)will provide reliable monitoring of the entire LOWWTF manual and automatic control and will enable future expansion. Primary operation will be through the supervisory control and data acquisition (SCADA)system.The primary function of the SCADA network is for communication between the programmable logic controllers(PLCs), human machine interface(HMI)system,and historian. 2. Codes, Standards, Regulations, and References This following codes,standards,and regulations will be followed: • Instrumentation,Systems,and Automation Society(ISA) • National Institute of Standards and Technology(NIST) • Underwriters' Laboratories, Inc. (UL) • American Water Works Association • National Electrical Manufacturer's Association (NEMA) • Occupational Safety and Health Administration • American National Standards Institute • National Fire Protection Association (NFPA) • NFPA 79,Annex"D"Standards,2024 • Institute of Electrical and Electronic Engineers • National Electrical Code(NFPA 70), 2026 3. Design Criteria 3.1 Facility Network The LOWWTF communication networks are primarily on Ethernet.Separate segregated networks will be provided for PCS)/SCADA functions, business functions,and other facility systems, including fire alarm and security. Each of the networks will be configured in a ring for added reliability. Firewalls will be used to provide a demilitarized zone(DMZ) between the PCS/SCADA, business,and facility networks,which will allow data access to outside users without risking the security of each network. 1 TECHNICAL MEMORANDUM 3.1.1 General Consideration • Core network and computer equipment will be in a dedicated server room located in the Administration Building.Separate network racks will be provided for fiber/copper patching, PCS/SCADA,and business/facility networks. • Network and computer equipment associated with package systems will be installed inside the package control panel to maintain package responsibility. It will not be located within the facility network interface panels(NIPs). • PCS/SCADA core servers will use a hyper-converged virtualization architecture and virtual machines to provide an available and redundant server infrastructure. 3.1.2 Segregated Networks and Demilitarized Zone The following segregated networks will be provided for connectivity of the systems. Each segregated network will use a self-healing fiber optic ring routed through the major facility.The configuration will provide for communication re-routing in the event of fiber segment problems or failure of individual network devices. • PCS/SCADA Network.The PCS/SCADA network will connect the LOWWTF's control system equipment, including SCADA servers, facility PLCs, package system PLCs,SCADA historian,and SCADA printers.The primary function of the PCS/SCADA network is for communication between the PLCs, HMI system,and historian. • Ethernet Network.The ethernet network-connected electrical system components installed in motor control centers(MCCs; electronic motor controllers,variable frequency drives [VFDs], and digital power monitors)will be pre-wired to Ethernet switches supplied with the MCCs. • Business Network.The business network will connect equipment used for the facility's business functions, including business workstations,telephones,and office printers.Typical functions of the business network include email, internet access, and IP telephone. • Facility Network.The facility network will connect all other facility-related network devices not supported by the PCS/SCADA and business networks, including security/access control,closed-circuit television, and fire alarm systems. • DMZ.A DMZ will be provided at the LOWWTF to accommodate data exchange between the PCS/SCADA network and all other LOWWTF networks.The DMZ will accommodate secure remote access for remote SCADA viewing. • Firewalls will be used to separate the DMZ from the SCADA, business,facility networks,and radio networks for communication between the LOWWTF and Points of Interconnect. • The DMZ will accommodate the servers and applications to allow historical data access,security and system updates, user authentication,secure remote access,and notifications. 3.2 Servers • PCS/SCADA Core Servers.The PCS/SCADA server infrastructure will use a hyper-converged virtualization architecture and virtual machines to provide an available and redundant server infrastructure. Local onsite backups can be stored on the network attached storage (NAS).An external hard drive can be attached to the NAS to accommodate offsite storage. • Other Servers.All other servers used in the facility will be stand-alone servers capable of operating as a virtual machine host. 3.3 SCADA HMI Workstations Workstations throughout the LOWWTF will be thin clients.There will be a single thick client located in the Administration Building. The thick client workstation will have a standard desktop format or a server rack-mounted format. 3.4 Administration Building Server Room A dedicated server room will be provided in the Administration Building for housing the core network and computer equipment for the PCS/SCADA, business, and facility networks.The room will be provided with uninterruptible power supply(UPS) power for the critical network and computer equipment loads. 3.5 Administration Building Control Room A dedicated control room will be provided in the Administration Building for daily use for access to the PCS/SCADA HMI workstations that provide operator interface for monitoring and controlling treatment plant processes. 3.6 Network Interface Panels Network and computer equipment at the major LOWWTF facilities will generally be installed in dedicated NIPs located near the 2 TECHNICAL MEMORANDUM facility PLC panel inside the facility's electrical room. 3.7 SCADA Historian The primary SCADA Historian will be located on the PCS/SCADA network.An Enterprise Historian,for access from other systems, will be located in the DMZ. 3.8 Remote Access Connectivity Remote access will be accommodated via client VPN and multi-factor authentication connecting to a secure remote access solution in the DMZ. 3.9 Remote Alarm Notification Alarm call-out will be via Ignition. Primary notification will be by SMS text. 4. Process Control System Description The PCS will provide process monitoring and control functions, alarm processing,trending,data archive,and report generation. The PCS will consist of the following: • Field-mounted instruments • Local control panels • PLC components and software • Communication networks • SCADA servers, HMI workstations, printers,and software The PCS will provide monitoring of the facility and manual and automatic control. Primary operation will be through the SCADA system.The SCADA system will also compile,store,and report operational data for use in WWTF operations using current, commercially available hardware and software. The SCADA network will connect the LOWWTF SCADA equipment, including: • PLCs • SCADA HMI workstations • SCADA servers • SCADA historian The primary function of the SCADA network is for communication between PLCs, HMI system,and historian.The SCADA network will use a ring routed through the major facilities at the LOWWTF. PLCs,together with HMI workstations,will perform the monitoring and control functions. Field input and output signals will be connected to the PLCs. MCC and VFD networks will be connected to the PLCs. The PLCs will be connected to each other and to PC-based SCADA operator HMI workstations using local area network(LAN) connections within the facility.The SCADA workstations will have HMI software applications. There will be local manual control, indication, and alarming to allow safe operation of the equipment in the event of a PLC or SCADA system failure.The PCS will be configured to allow equipment and processes to be operated automatically or manually through the SCADA system as selected by the operator. 4.1 Adjustable Frequency Drives and Motor Control Center Controls Controls interfaces will be provided on the MCC face via the MCC-supplied HIM keypad. Motor control starters include the standard circuit breaker, hardwired interlocks,and smart overload.Adjustable frequency drives(AFDs)and electronic overload devices will be connected to the PLC system via Ethernet IP controls for parameter monitoring. 4.2 Safety Interlocks Safety and equipment protection shutdown/lockout interlocks will be implemented through hardwired connection to the motor control circuit. Interlocking for personnel and equipment safety and equipment protection will not be done through the PLC or SCADA systems. Interlock logic will include a local RESET push button at the local control station.Shutdown/lockout and RESET functions will be monitored by the PLC and SCADA systems to preclude automated system operation in the event of a 3 TECHNICAL MEMORANDUM shutdown/lockout occurrence. 4.3 Programmable Logic Controllers and Locations Individual PLCs will be located in the various process areas. PLCs will be located in electrical rooms near the process areas they serve, except vendor-provided PLCs in outdoor-rated enclosures,which may be located outdoors.The PLC system will use Allen-Bradley ControlLogix. The PLC software provided will be compatible with the PLC hardware provided.The software required for the PLC consists of the following types of components: • Latest version of fully licensed PLC programming and configuration software • Latest version of fully licensed communications software and drivers for supplied PLC to PC communication Distributed PLC processors, networks,and PLC power supplies units will provide system reliability for PLC and HMI systems. PLC I/O properties: • Digital inputs will be powered by 120V alternating current(AC) optically isolated,channel-to-channel. • Digital outputs will be isolated dry relay contacts rated for 120V AC for hardwired circuit operation. • Analog inputs will be 4-to 20-milliampere (mA)direct current(DC),optically isolated,channel-to-channel,signals from powered transmitters or 24V DC looped, powered from the PLC cabinet. • Analog outputs will be isolated 4-to 20-mA DC signals. 4.4 Package System Controls Some instrumentation and controls will be furnished with packaged system controls, including PLCs, by the equipment manufacturer.The package system controls will include PLC data I/O for data monitoring with the LOWWTF SCADA system network. 4.5 Enclosures and Panels A local control panel will be provided at each remote facility and at each PLC. Enclosures and panels will be located in control rooms or if not available, in electrical rooms.Within control panels,all field wiring will be terminated at terminal blocks. 4.6 Uninterruptible Power Supply Each PLC will be provided with backup power during power failure transitions from a UPS located in the vicinity of the PLC panel.The UPS will provide a reliable source of uninterruptible power with no break in air-conditioning output power during a complete or partial interruption of incoming line power. UPS status(health)will be monitored by the SCADA system. (Refer to Electrical Technical Memorandum.) 5. Exclusions • Excludes communication with collection systems. • Excludes communications with Columbia Boulevard WWTP,Tryon Creek WWTP and the existing Tryon Creek Pump Station. 4 TECHNICAL MEMORANDUM 6-7 Process Mechanical Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Jason Krumsick/Jacobs Reviewer: John Simonds/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal Process Mechanical design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). I 2. Codes, Standards, Regulations, and References All facilities will be designed to conform to the following process mechanical design-related codes,standards,and regulations for piping,valves,and process equipment. Codes • 2024 National Fire Protection Association (NFPA)820.Standard for Fire Protection in Wastewater Treatment and Collection Facilities Standards • American Water Works association (AWWA) • American Society of Mechanical Engineers (ASME) • American National Standards Institute • National Fire Protection Association (NFPA) • Occupational Safety and Health Administration 3. Design Criteria Equipment • Required space for equipment removal/replacement/maintenance will be provided. • Equipment and panels will be mounted on equipment pads to protect from washdown. • For pumps,compressors,and other rotating equipment where parallel units are provided,the orientation of the drive and the rotation shall be identical. • Pumps used for sludge shall be arranged to minimize the distance and number of bends through which the liquid must be conveyed to the pump suction. • Adequate headroom shall be provided for equipment removal. • Lifting eyes will be provided above equipment not otherwise provided with lifting means. • Washdown stations will be provided in logical areas to facilitate clean-up and pipe flushing. • Pump factory and field testing shall be in accordance with Hydraulic Institute standards. • 1 TECHNICAL MEMORANDUM 6-7 Piping Materials A preliminary pipe schedule can be found in the Drawings. Pipe materials and joint types for pressurized piping systems will be selected to provide thrust restraint of all joints. Piping Systems • Piping will be located to provide clear access as much as possible. • In general, piping will be routed close to walls or ceilings where it can be easily supported. • To permit purging of air from liquid pipelines while being filled, manual vent valves will be installed at pipeline high points. • To permit liquid drainage,drain valves will be installed at pipeline low points. • Wall penetrations will be perpendicular to the wall. • Provisions for pipe disassembly will be provided to allow removal of equipment or valves,such as dismantling of joints,flange coupling adapters,or other couplings. • Thrust restraint will be provided for all joints of pressurized pipelines. • Pipeline flexibility will be provided at interfaces between existing facilities,existing yard piping and new facilities with ground improvements to allow seismic movements and differential settlement. Examples may include the inherent pipe flexibility of HDPE piping harness-restrained couplings for steel piping,and double mechanical joints for ductile iron piping. • Cleanouts will be provided for buried sludge or biofoam services. • Piping identification and pipe labels will conform to ANSI/ASME A13.1 with flow stream service and flow arrows as well as colors identified on piping schedule. Valves • Valve selection will take into consideration flow streams with stringy materials versus flow streams without stringy materials. • The need for power-actuated valves will be determined by process requirements.All actuated valves will be provided with manual override operators to allow valves to be adjusted,opened or closed in the event of a power failure or equipment malfunction. Freeze Protection • Exterior water piping is heat traced and insulated or designed with provisions to drain the system during freezing weather. Pipe Supports • Pipe support and seismic bracing are included. Pump Seals • Pump seals will be single mechanical type with seal water lubrication (no packing).Split mechanical seals will be used on larger diameter pump shafts. 4. Exclusions Excludes pneumatic air systems, pneumatic valves,and air for tools. 2 TECHNICAL MEMORANDUM 6-8 Resiliency Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Kirsten Jackson/Jacobs Reviewer: Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the resiliency design criteria of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References • 2025 Oregon Structural Specialty Code(OSSC) 3. Design Criteria 3.1 Risk Category • Oregon Structural Specialty Code(OSSC) 2025—incorporates International Building Code (IBC)2024. - Risk Category 4: Public utility facilities providing power generation, potable water treatment,or wastewater treatment. • This project will be designed under 2025 OSSC,which includes wastewater treatment facilities as Risk Category 4. • Per meeting with authority having jurisdiction (AHJ)on October 28, 2025, interpretation of the 2025 OSSC allows for facilities that are not part of the critical treatment flow path to be Risk Category 3. • Based on the meeting with the AHJ,Table 1 includes the facility designations as Risk Category 3 or Risk Category 4 included in the LOWWTF design. Table 1—Risk Category per Facility Facility Risk Category Administration Building Risk Category 3 Maintenance Building Risk Category 3 Influent Pump Station Risk Category 4 Headworks Risk Category 4 Aeration Basins Risk Category 4 Blower Canopy Risk Category 4 Clarifiers Risk Category 4 Filtration (and rapid mix box) Risk Category 3 UV Disinfection Risk Category 4 1 TECHNICAL MEMORANDUM Facility Risk Category Solids Handling Risk Category 4 Truck Loading Risk Category 3 Odor Control Risk Category 3 Generators Risk Category 4 Stormwater Pump Station Risk Category 3 Plant Drain Pump Station Risk Category 3 *Any facility not listed in this table is assumed to be Risk Category 3. 3.2 Seismic Certifications for Equipment • Risk Category 4 facilities require seismic certification for equipment,and it can be obtained through the following methods: - Shake table testing - Determined by AHJ to be inherently"rugged" - Calculated - Experience • Per meeting with AHJ on October 28, 2025, interpretation of Risk Category 4 equipment requiring seismic certifications applies to the following scenario:ability to operate equipment in manual mode to move flow through the critical flow path.Therefore, seismic certification is assumed to not be required for the following computer systems,as equipment can be operated manually without these systems: • SCADA ▪ Local control panels • Programmable logic controllers(PLCs) • Computers 3.2.1 Shake Table Testing Some vendors will be able to provide shake table testing certifications for their equipment. 3.2.2 Determined by AHJ to be inherently "rugged" The City of Portland has a list of equipment that they consider to be rugged. Building Code Guide 17-11:Seismic Certification I Portland.gov G. Rugged Equipment and Components The equipment and components listed below are considered inherently rugged and must be considered to meet the requirements for Seismic Certification by Experience Data. 1. Valves(not in cast-iron housings, except for ductile cast iron) 2. Pneumatic operators 3. Hydraulic operators 4. Motors and motor operators 5. Horizontal and vertical pumps(including vacuum pumps) 6. Air compressors 7. Sterilizers 8. Blanket warmers 9. Anesthesia power columns,ceiling or wall mounted 2 TECHNICAL MEMORANDUM 10. Refrigerators and freezers 11. Microwave ovens for patient service 12. Film illuminators 13. Elevator cabs 14. Underground tanks 15. Equipment and components weighing not more than 20 pounds supported directly on structures(and not mounted on other equipment or components)with supports and attachments in accordance with Chapter 13,ASCE/SEI 7 3.2.3 Calculated Calculations can be used to provide that certain materials or parts of equipment can survive the applicable forces in a seismic event. 3.2.4 Experience The experience criteria are for equipment that survived an event that the AHJ agrees is sufficiently similar to an expected event at the site. 3.2.5 Seismic Certification for Equipment—Basis for the Project See equipment list. 4. Exclusions • Piles underneath yard piping are excluded. • Assumed that Risk Category 4 does not apply to collection system infrastructure. 3 TECHNICAL MEMORANDUM 6-9 Civil Site Development Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Gino Nguyen/Jacobs Reviewer: Marielle Coquia/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM) is to present the proposal for the civil site development design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References The codes and standards will conform to the following codes and references. • Oregon Department of Transportation (ODOT)Standard Specifications for Construction, 2024 • ODOT Pavement Design Guide, 2019 • City of Lake Oswego Stormwater Management Manual, 2020 • Building Code: 2025 Oregon Structural Specialty Code(OSSC) • Fire/Life Safety: 2025 Oregon Fire Code(OFC) • 1993 AASHTO Guide for Design of Pavement Structures • Development Standards:City of Lake Oswego,OR—City Code,Chapter 50.06.001.5; Commercial, Industrial, and Multi-Family Development not located in the Foothills Mixed-Use(FMU)Zone, and Minor Development in the R-DD(Res-Detached/Duplex) Zone Standards for Approval (Industrial Zone,City Code). 3. Design Criteria Access roads and entrances will be designed to allow emergency and delivery vehicles access to occupied facilities.The minimum road width is 26 feet with maximum longitudinal road grades of 10 percent.The roads will be paved.The roads,slopes,and drainage design will comply with building codes required by the City of Lake Oswego. 3.1 Road Design Three access points from Foothills Road are proposed to access the site,one road on the upper west side level and two roads on the lower east side level.AutoTURN software for a WB-67 design vehicle determines the minimum road extents to facilitate truck maneuvering and turnaround on the site. • Design vehicles used in road design: - American Association of State Highway and Transportation Officials(AASHTO)WB-67(semi-truck and trailer with 53-foot trailer) used for sludge trucks and chemical deliveries. — AASHTO SU-40 used for fire truck access and large maintenance truck access. — AASHTO P passenger vehicle used for parking lot access. 1 TECHNICAL MEMORANDUM 6-9 Required curbs,curb and gutter,or valley gutter will be used when stormwater management is necessary. Sidewalks are included to facilitate access to buildings. • Design road geometry: — 30-foot road width (two 15-foot lanes) - 5-foot sidewalk width - 9-foot by 18-foot parking stall 3.2 Pavement Design Asphalt concrete pavement is included for access roads and parking areas at the site. Reinforced concrete will be used for the pavement where heavy equipment is proposed.Asphalt concrete pavement will be designed in accordance with the ODOT Pavement Design Guide.The 1993 AASHTO Guide for Design Pavement Structures method for pavement design will be used. 3.3 Grading Design • Road grading: — Minimum 2% paved surface away from structures — Minimum 5%unpaved surface away from structures — Minimum 1.5%for vegetated drainage swales — Minimum 0.5% longitudinal grade for roads and straight sections of concrete gutter — Minimum 0.75% longitudinal grade for curved sections of concrete gutter — Maximum 8% longitudinal grade for site roads • Americans with Disabilities Act(ADA)grading: — Cross-slope design maximum 1.5%,constructed maximum 2% — Ramp minimum slope:slope exceeding 5%slope will be considered a ramp — Ramp maximum longitudinal slope:design maximum 7.5%,constructed maximum 8.33% • Site grading: — 4H:1V Typical vegetated slope for ease of mowing 3.4 Stormwater Design See Stormwater Management TM. 3.5 Existing Topography and Survey • Horizontal Datum: Local Datum. - Derived from OR State Plane North 3601 NAD83(2011)EPOCH 2010.000 by multiplying by a project mean ground combined scale factor of 1.0000941820. • Vertical Datum: NGVD 29 - Based on City of Lake Oswego Benchmark No 18F-3, EL 29.582. • There are four vertical datums to consider at the site.The correction factors have been verified through benchmarks,the City of Lake Oswego,the City of Portland,and the National Oceanic Atmospheric Administration (NOAA)website for datum correction. - The"Old"City of Lake Oswego datum:this is the lowest datum, located 1.997 feet below NGVD 29. - The National Geodetic Vertical Datum of 1929(NGVD 29). - The City of Portland (COP)datum is located 1.375 feet above NGVD 29. - The North American Datum of 1988(NAVD 88) is located 3.475 feet above NGVD 29. 2 TECHNICAL MEMORANDUM 6-9 3.6 Floodplain Development Based on the project location within the City of Lake Oswego Floodplain Management Area (FMA),the project must demonstrate compliance with LOC 50.05.011 Flood Management Area standards,the following are assumed to meet that compliance: - No ordinance amendment to LOC 50.05.011 FMA's which result in changes to the approach or assumptions listed below to meet the City's floodplain development standards. — No FEMA Flood Insurance Rate Map (FIRM)update such as a Conditional or Final Letter of Map Revision (C/LOMR)or Physical Map Revision (PMR)are required as part of the project. - The no-net fill requirement(50.05.011.6.b.i)will utilize some combination of past and future credits outlined in the Floodplain Credits Memo(dated 3/9/2025) in combination with the net grading change onsite as a result of the project. - If FEMA(Region X or its mapping partners) becomes involved in FMA review,the permitting approach and assumptions do not change.As outlined in the floodplain credits memo and subsequent correspondence with the City Floodplain Administrator(specific email chain attached). - As required by 50.05.011.6.b.xii Encroachment into Portions of Tryon Creek the project will show less than 0.5 feet of water surface rise such that no-rise(or no change in BFE)is met. — If a no-rise analysis(<0.005 ft of base flood elevation rise) is required,grading changes as part of the 2004 foothills park project will be included as part of"the project" being evaluated. - As part of the Oregon NFIP Implementation Plan for protection of ESA listed Species,the City of Lake Oswego model ordinance,the no net loss standards for floodplain habitat will be assessed based on pre-project(existing)site conditions. I 4. Exclusions - The Tryon Creek Pump Station will be decommissioned with the rest of the TCWWTP. - Survey for easements or lot line adjustments are excluded. - Upstream and downstream collection system hydraulic restrictions are not the responsibility of the DBOM contractor. 3 TECHNICAL MEMORANDUM 6-10 Structural Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Sterling Rose/Jacobs Reviewer: Alex Firth/Jacobs Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal structural design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References All facilities will be designed to conform to the following structural design-related codes,standards,and regulations,as required by the local authority. • 2025 Oregon Structural Specialty Code(OSSC) • American Society of Civil Engineers (ASCE)7-22: Minimum Design Loads and Associated Criteria for Buildings and Other Structures • American Concrete Institute(ACI)318-19: Building Code Requirements for Structural Concrete • ACI 350-20: Code Requirements for Environmental Concrete Structures • The Masonry Society(TMS)402/602-22: Building Code Requirements for Masonry Structures • American National Standards Institute/American Institute of Steel Construction (ANSI/AISC)360-22:Specification for Structural Steel Buildings • ANSI/AISC 341-22:Seismic Provisions for Structural Steel Buildings • Aluminum Design Manual (ADM)2020:Aluminum Design Manual 3. Design Criteria All structures and foundations will be designed per the load requirements and load combinations of the 2025 OSSC. Design parameters for the project site are as follows: 1. Equipment loads: Loads will be based on the calculated static and dynamic loads imposed throughout the potential operating range of the equipment. 2. Dead load: Dead loads will include the weight of permanent structures and equipment.They will also include the weight of attached piping and electrical items. a. For areas with small pipe,cable tray,conduit, and minor equipment that are permanent fixtures in the plant,a minimum of 10 pounds per square foot(psf)collateral dead load will be applied over these areas. 1 TECHNICAL MEMORANDUM 6-10 b. For roof areas designated as future solar ready, a minimum of 5 psf collateral dead load will be applied over these areas. 3. Live Load: a. Roof=20 psf; per ASCE 7-22 b. Mechanical operation floor area= 200 psf c. Electrical rooms=300 psf d. Galleries, platforms,and stairways= 100 psf e. Vehicular loading= HS 20 vehicle loading 4. Snow Load: a. Design ground snow load=66 psf; per the ASCE Hazard Tool b. Minimum roof snow load (flat or sloped)=20 psf x Importance Factor; per Clackamas County requirements c. Minimum rain-on-snow surcharge load =5 psf on roof with slope less than 4.76 degrees; per Clackamas County requirements d. Importance factor= 1.20(Risk Category IV) 5. Wind Load: a. Basic wind speed= 109 miles per hour(mph;for Risk Category IV) per 2025 OSSC and Clackamas County requirements b. Importance factor= 1.0 c. Exposure category=C 6. Seismic Load, per ASCE 7 Hazard Tool: a. Ss=0.94 b. 51=0.35 c. Importance factor= 1.5(Risk Category IV) d. Site soil class=C e. Seismic design category= D 7. Geotechnical Design Parameters: a. Allowable bearing pressure=2,500 psf minimum for granular fill over prepared bedrock surface; per 2023 Geotechnical Report by WPS b. At-rest lateral soil pressure=56 psf for granular fill c. Frost depth= 12 inches; per Clackamas County Design Criteria 4. Overview of Facilities A brief structural description of each proposed building is included in Table 1.Seismic risk categories are described in TM 6-8. Table 1—Facility Structural Descriptions Facility Description Administration Building Single story masonry structure with structural steel or steel joist roof framing and shallow concrete bearing foundation Maintenance Building Single story metal building structure and shallow concrete bearing foundation Influent Pump Station Deep buried concrete water holding structure Headworks Concrete structure with lower floor level,water holding basins, and elevated channels Aeration Basins Partially buried concrete water holding structure i 2 TECHNICAL MEMORANDUM 6-10 Facility Description Blower Canopy Single story structure Clarifiers Partially buried concrete water holding structure Filtration Partially buried concrete water holding structure UV Disinfection Partially buried concrete water holding structure Solids Handling Partially buried concrete water-holding structure Truck Loading Single story metal building structure and shallow concrete bearing foundation Odor Control Tanks and equipment on shallow foundations I 5. Exclusions • Excludes structural or code upgrades to collection system elements. • Excludes structural or code upgrades to the Tryon Creek Pump Station. • 3 TECHNICAL MEMORANDUM 6-11 Landscape Architecture Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Andrew Holder/GreenWorks Gill Williams/GreenWorks Reviewer: Kristen Jackson/Jacobs Dave Grigsby/Jacobs Revision: Final 1. Introduction The purpose of this technical memorandum (TM)is to present the proposal for landscape architecture design of the Lake Oswego Wastewater Treatment Facility(LOWWTF). 2. Codes, Standards, Regulations, and References The landscape design will conform to the following codes and standards: General: • 2024 City Code and Charter of Lake Oswego • 2020 Lake Oswego Stormwater Management Manual Hardscape and Site Design: • 2010 ADA Standards for Accessible Design—General requirements of surfacing,slope gradients,and operable parts like gate latches and card readers. • 2024 International Building Code—sets requirement for guardrail fall protection at vertical drops. • Occupational Safety and Health Administration—sets requirement for minimal fall protection at vertical drops that are only accessed by certain plant personnel, but not by the general public. • Lake Oswego Community Development Code,Chapter 50.06.004 Site Design—sets minimum proportion of site landscaping and open space. Planting: • Lake Oswego Community Development Code,Chapter 50.06.004 Site Design—states requirements for street trees and visual screening and buffering. 3. Design Criteria The total developable site is approximately 240,000 square feet.The zoning designation is Industrial.There are no public spaces included in the design. Per The City of Lake Oswego Development Standards 50.06.004-1-b, Industrial zones must have a minimum of 15%landscaping (including open space,courtyards,etc.)visible from offsite.This project is assumed to be a "major public facility"therefore requiring a minimum of 20%landscaping.The project design includes 20% landscaping (approximately 48,000 square feet)to meet the Development Code requirement. 1 TECHNICAL MEMORANDUM Major components The landscape architecture design includes irrigated shrubs, non-irrigated field grass, patio space,and trees. 11% Irrigated shrub planting 65% Non-irrigated field grass 23% Non-irrigated field grass(frontage) 1% Patio at Administration building, pavers or concrete 100% Total Landscaped area Irrigated Shrub Planting(quantities given are per 100 sf): - 12" depth imported amended topsoil (3.70 cy) - 3"depth bark mulch (0.93 cy) - Fine grading - Shrubs(mix of all three sizes): • 5 gal. potted shrub(1 ea.) ▪ 2 gal. potted shrub(4 ea.) • 1 gal potted shrub (13 ea.) — Automatic irrigation system (closer head spacing) — Establishment and maintenance — No screening shrubs are required along the fence on the Foothills Road frontage, if the fence is 6'tall or lower. Non-Irrigated Field Grass(quantities given are per 100 sf): — 2"depth compost(0.62 cy) plus lime and fertilizer mixed into site soil - Fine grading - Rough lawn seed, hydroseeded - Establishment and maintenance - Restoration of off-site staging areas will include non-irrigated field grass. Trees(quantities given are per tree): - 1.5"caliper native deciduous or 6'tall native conifer tree, ball and burlap - Imported amended topsoil backfill (0.45 cy) — Within field grass areas: 3"depth bark mulch ring,4'diameter(0.12 cy) - Establishment and maintenance - Street trees are not required along Foothills Road. - Planting of 36 trees are assumed in the design.To the extent possible,these will be planted on the LOWWTF site.Screening of process tankage along the east boundary will be a priority planting location. Planting trees offsite on City land may be required.There is also an option to pay into a mitigation fund for the value of those trees.The exact mitigation requirement will be determined after the site survey showing trees is completed. Hardscape: - Administration building will have a hardscape patio(pavers or concrete),approximately 500 sf. 2 TECHNICAL MEMORANDUM Fencing The north,east,and south site perimeter includes standard black 8-foot chain link fence with security topper.A 6-foot black steel picket decorative fence is included along Foothills Road.Where possible, buildings are utilized as fencing in lieu of additional fencing linear footage.There will be an automated vehicular and a manual person gate at each access point to the site off Foothills Road. 4. Exclusions • No public spaces included in the design. • An ADA accessible route will be provided from the public sidewalk to the front doors of the Administration Building. No other pedestrian or bike routes included in the design. • No integration of landscape architecture with the stormwater design. • No eco roofs are included in the design. • No landscape architecture design required for portions of the project(such as collection system)outside of the LOWWTF footprint. 3 TECHNICAL MEMORANDUM 7 Project Option 1 Nutrient Removal Treatment Date: March 30, 2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BPO0152J To: Stefan Broadus/City of Lake Oswego From: Kristen Jackson/Jacobs Reviewer: William Leaf/Jacobs Dave Grigsby/Jacobs Revision: Final I 1. Introduction The purpose of this technical memorandum (TM)is to present the scope basis for the Nutrient Treatment cost option for the Lake Oswego Wastewater Treatment Facility(LOWWTF). I 2. Description of Work Table 1 includes the differences in scope between project Option 1, Option 2a,and Option 2b. • Project Option 1: Based on the design criteria identified in Table 1 of Exhibit 1 of the RFP, Project will meet all effluent requirements identified in Table 2 of Exhibit 1 to the RFP. • Project Option 2a: Based on the design criteria identified in Table 1 of Exhibit 1 of the RFP, Project will meet all effluent requirements identified in Table 2 of Exhibit 1 to the RFP with the exception of ammonia and total phosphorus. • Project Option 2b: For Project Option 2,Jacobs shall also provide the fixed design-build price(in 2025 dollars)for the design and construction at a later date of the additional capital improvements necessary to meet the ammonia and total phosphorus effluent requirements identified in Table 2 of Exhibit 1 of the RFP. For the nutrient removal Options 1 and 2b,the integrated fixed film activated sludge(IFAS)system allows bioreactor configuration flexibility and adaptability given the activated sludge process,and is required to reliably remove ammonia nitrogen (NH3N)to meet the 1.0-mg/L monthly dry-weather average. Bioreactor selectors are designed to accommodate a level of enhanced biological phosphorus removal (EBPR).The reliability of EBPR will be dependent on the influent carbon availability(in terms of readily biodegradable chemical oxygen demand [COD],etc.).The special sampling completed for the project is limited,so the reliability of EBPR cannot be specifically defined.As a result,a level of chemical addition using aluminum sulfate(alum) is proposed.Alum feed points are located in the bioreactor and upstream from filtration. The non-nutrient removal approach requires the facility to meet the proposed effluent permit limits—without the NH3N or total phosphorus(TP) limits. 1 TECHNICAL MEMORANDUM 7 Table 1—Project Options Option 2a- Conventional Option 2b- Phased Nutrient Treatment Option Option 1- Nutrient Treatment Option Treatment Option Four conventional aeration basins (Option 2), Four IFAS basins Four conventional aeration convert to IFAS(Option 1) later basins Headworks Single stage screening Single stage screening Single stage screening Screening Aeration Basins Media 50%media fill None No fill, later on add 50%media fill Retention Screens Retention screens,sprays,and scum screen None No screens, later on demolish concrete end wall and (added structural to accommodate this) install retention screens Diffuser Type (IFAS zone) Coarse bubble Fine bubble Start with fine bubble diffusers, later on demolish fine bubble and install coarse bubble diffusers (address pressure changes) Diffuser Type-Non IFAS Zones Fine bubble Fine bubble Fine bubble(address pressure changes when convert to IFAS) Diffuser grid (IFAS zone) Grid designed for IFAS Grid designed for conventional Grid designed for conventional treatment later on treatment demolished and grid installed for IFAS(includes piping and valves) Mixing System Mechanical mixers Mechanical mixers Mechanical mixers Chemical Addition Chemical facility for alum (two tanks with a No Alum equipment No alum equipment, later on add a chemical facility canopy and pump room) for alum (2 tanks with a canopy and pump room) Equipment Rapid Mix and Flocculation box Rapid mix box and flocculation box ahead of No rapid mix and flocculation No rapid mix and flocculation box, later on build filtration box rapid mix box and flocculation box ahead of filters *hydraulics accommodates this Hypo Include hypo in chem facility(not at tote Hypo at tote area Hypo at tote area (not in chem facility) area) Polymer Polymer at rotary drum thickeners(RDTs) Polymer at RDTs Polymer at RDTs Blowers Five blowers(10%larger than Opt.2a) Five blowers Five blowers(10%larger than Opt.2a) Aeration Basin Covers Selector Zones Odor control covers Odor control covers Odor control covers %.01 � 1 TECHNICAL MEMORANDUM 7 Option 2a- Conventional Option 2b- Phased Nutrient Treatment Option Option 1- Nutrient Treatment Option Treatment Option Four conventional aeration basins (Option 2), Four IFAS basins Four conventional aeration convert to IFAS(Option 1) later basins First aerated zone/IFAS Zone Building over the IFAS zone for operator Odor control covers(aerated Odor control covers(aerated zone), later on add a access(plus added odor control) zone) building over the IFAS zone for operator access Remaining Zones Visual covers Visual covers Visual covers Auxiliary Systems Extra instrumentation for nutrient controls None No extra instruments, later on add extra (ammonia probe, phosphorus [PO4P]) instrumentation for nutrient controls(ammonia probe, PO4P) Additional sprays needed at IFAS zones None No additional sprays, later on add sprays at IFAS zones Electrical Systems Extra loads:chem facility/pumps,fine None Extra loads:chem facility/pumps,fine screens, screens,generator(10%more electrical loads generator(10%more electrical loads than Opt. 2a) than Opt.2a) Other Additional odor control for the building over Hydraulics accommodate Hydraulics accommodates additional headloss for the IFAS zone. additional headloss for IFAS and IFAS,and rapid mix/flocculation tank rapid mix/flocculation tank* Additional odor control for the building over the IFAS zone d 3 TECHNICAL MEMORANDUM 7 3. Exclusions • While Jacobs is able to commit to the cost of Option 1 today, implementation (Option 2b)at some future unknown date is subject to escalation and changes to technology and equipment.The cost impacts are unquantifiable and therefore pricing for this scenario is not provided.Jacobs commits to the infrastructure required for future implementation (Option 2b),so long as there is a recognition that adjustment to account for technology evolution may be warranted. 4 TECHNICAL MEMORANDUM 8 Assumptions,Clarifications,Discussions and Exclusions Date: August 18,2026 Project name: Design-Build-Operate-Maintain Services for the Lake Oswego Wastewater Treatment Facility Jacobs PN: BP00152J o: Stefan Bro s/City of Lake Oswego From: Ashley Currey/Jacobs Michelle Green/Jacobs Revision: Final I 1 . Introduction The purpose of this technical memorandum (TM) is to communicate assumptions, clarifications, exceptions, and discussions related to this BAFO proposal 2.Technical Approach Given the level of detail provided in the BAFO drawings and technical memoranda,the following items are provided to clarify the technical approach. 1) The BAFO is based upon the drawings and technical memoranda provided with this submittal with the following modifications: a) The switchgear arrangement will meet contractual requirements for a main-tie-tie-main arrangement.The proposal drawings and technical memoranda have not been updated to depict this requirement with this BAFO. b) Minor revisions to assumed influent temperature and alkalinity, as documented in track changes in TM 1. 2) Facility Characteristics: a) A single influent sampler is required at the Influent Pump Station. Separate influent samplers are not required on the Lake Oswego and Portland influent lines. b) The facility does not provide water quality sufficient for reuse.A tee and blind flange on the effluent pipe(s) leaving the UV disinfection facility will be provided to allow for connection to a future facility. c) Where feasible,the perimeter fencing installed during construction is planned to remain in place as part of the permanent project fencing. In areas requiring temporary construction access,temporary fencing will be provided and replaced with permanent fencing prior to project completion. d) Structural calculations to protect against uplift are based on the LODFE (1996 flood stage);these calculations do not consider the 500-year flood stage. e) The DBOM Contractor has assumed subsurface obstruction conditions consistent with refusal affecting up to 20%of the planned piers, including 400 additional drilling hours. Refusal rates, boulder presence, or other subsurface conditions requiring drilling beyond this value are not included in the Contract Price and shall be treated as a Differing Site Condition, entitling the DBOM Contractor to an equitable adjustment in cost and schedule. f) All heating systems(make-up air and water) utilize natural gas(not electric units). g) The City will allow the 2 restrooms at LOWWTF to tie into the existing collection system or onsite sanitary sewer pipelines upstream of IPS. h) The DBOM Contractor has included costs for a single electrical service connection to supply power to the new facility. 1 TECHNICAL MEMORANDUM 8 This proposal assumes adequate electrical capacity is available from the existing utility infrastructure, and PGE costs do not exceed $770,000.Any utility system upgrades,substation modifications, new feeders, conductor upgrades, or other off-site improvements required to provide sufficient power to the facility greater than this value shall be the responsibility of the City. i) Local control and local disconnects are not required for all process equipment. j) Secured remote SCADA access will be provided for use for offsite access during construction, commissioning, and post commissioning support by Jacobs OT and I&C staff. k) Cybersecurity.Jacobs BAFO is predicated upon the following proposed language: i) The Parties acknowledge and agree that three(3)separate and independent network environments shall exist and be maintained throughout the Term of this Agreement: (i)the Client Information Technology Network ("Client Network"), (ii)the Jacobs Information Technology Network("Jacobs Network"), and (iii)the Supervisory Control and Data Acquisition and Industrial Control System environment("SCADA Network"). Each network shall be operated,administered, and secured as a distinct environment, and no direct connectivity,trust relationship, unmanaged data pathway, or network interconnection shall exist between the Client Network,the Jacobs Network, and the SCADA Network except as expressly approved in writing by the Parties and implemented through documented,secured, and risk-assessed interfaces. Responsibility for the operation, maintenance, security, and governance of the Client Network and Jacobs Network shall remain with their respective owners and administrators. ii) The DBOM Contractor shall have primary responsibility for the administration, operation, maintenance, monitoring, cybersecurity, lifecycle management,and risk management of the SCADA Network and associated industrial control system assets within its scope of services.The DBOM Contractor shall perform such responsibilities in accordance with prudent industry practices and EPA guidance to industrial control systems, operational technology environments, and utility SCADA systems,as such standards may evolve during the Term. The DBOM Contractor shall use commercially reasonable efforts to identify, assess, document,and communicate cybersecurity risks,vulnerabilities, equipment obsolescence concerns, and recommended corrective actions; however,the DBOM Contractor does not warrant or guarantee that cybersecurity incidents, unauthorized access, operational disruptions, or technology failures will not occur notwithstanding compliance with such standards. iii) The Parties acknowledge that cybersecurity threats, regulatory requirements,technology standards,and industry best practices are continually evolving and may require future investments in hardware, software,services, monitoring capabilities,system upgrades, replacement projects, or other risk mitigation measures beyond the scope of this Agreement.The DBOM Contractor shall provide recommendations regarding such investments when reasonably necessary to maintain the SCADA Network in accordance with prudent industry practices. If the City elects not to implement or fund recommended measures intended to address identified or emerging risks, the DBOM Contractor shall not be liable for any resulting increase in risk or for incidents,failures, or damages arising directly or indirectly from such decision. In such circumstances,the Parties shall meet in good faith to review the resulting risk profile and may negotiate an equitable adjustment to the scope of services, performance obligations, pricing, risk allocation, or other applicable terms of this Agreement. l) The Maintenance Building does not include a welding shop. O&M staff will perform welding outside the Maintenance Building. m) Currently there is no historical data on influent odor loading.The design and O&M costs are based on a maximum H25 concentration of 5 ppm.The DBOM Contractor will perform sampling during design to confirm this assumption and document baseline H25 levels. Should baseline levels exceed 5 ppm,the DBOM Contractor will be entitled to cost relief, specific to O&M costs related to carbon replacement. n) Currently there is no historical data on noise levels at the fenceline.The DBOM Contractor will perform noise sampling during design to confirm baseline levels. Should baseline levels be above DBOM Agreement requirements, the DBOM Contractor and City will meet to discuss how this will impact the overall noise performance standards and potential exceptions beyond the DBOM Contractor's control. 3) Conveyance Systems: a) No collection system improvements upstream of proposed connection to LOWWTF are required. b) Hydraulic restrictions exist in the existing collection system upstream of the LOWWTF that may cause surcharges, I 2 I TECHNICAL MEMORANDUM 8 particularly during high flow events.This is outside the DBOM Contractor's responsibility.The City intends to address these restrictions as part of future CIP projects. c) There is an existing hydraulic restriction in the outfall pipeline downstream of the LOWWTF that may cause an overflow of the outfall junction structure during extremely high flow events or river levels.This is outside DBOM Contractor's responsibility.The City intends to address these restrictions as part of future CIP projects. d) No decommissioning or demolition is included for existing buried conveyance systems that will no longer be in use. 4) Foothills Road: a) No sidewalks or additional street lighting are required along Foothills Road,and repair/grind/overlay and restriping Foothills Road at the end of the project is not included. No costs have been included for these features. b) Extension of fiber within Foothills Road is not included. 3.Construction Approach The following items are provided to clarify the construction approach and serves as the basis for this BAFO. 1) Per the DBOM Agreement,the City will purchase Builder's Risk and Project Specific General Liability policies for the project. 2) The City will notify the adjacent stakeholders/businesses prior to NTP and project construction commencement.The DBOM Contractor and the City should coordinate these efforts. 3) Section 3.2.3 of Jacobs Technical Proposal,4/2/2026, describes Construction Staging Areas and Traffic Management, which are the basis for our price.Aspects of the proposed Traffic Management Plan differ from requirements detailed in Appendix 7 of the Agreement. If Jacobs approach is not acceptable, we would like to work with the City to develop an alternate approach that balances cost impacts with impacts to the neighbors and the public. 4) Discharge from dewatering systems will be sent to and accepted by the Tryon Creek Wastewater Treatment Plant (TCWWTP)for flows up to 100 gpm. 5) Workforce and Funding Program a) There is no Project Labor Agreement in place for this project.There will be Union and Non-Union labor working together on this project. b) This proposal is based on the following craft wage rates: i) Davis-Bacon determination 0R20260053 May 17. 2026. ii) State of Oregon Prevailing Wage Rates as defined on https://www.oregon.gov/boli/employers/pages/prevailing- wage.aspx c) All craft wage rates will be reported using LCP Tracker software each week. Please note that both of these sources are based on local union wage scales.Those wage scales are negotiated typically in three-year blocks. d) The project funding requirements include Davis-Bacon wages and American Iron and Steel in keeping with WIFIA loan requirements.The project funding requirements do not include Build America/ Buy America or any other provisions, and no costs have been included for these provisions. 6) This proposal assumes the City does not intend to retain any existing site materials, structures, or salvage value. Removal, recycling,and disposal of such materials will be performed at the DBOM Contractor's discretion and in accordance with applicable requirements. 7) Contaminated Soils: a) Based on the Phase II ESA, no Toxic Substance Control Act(TSCA) PCB soil cleanup will be required and any soil that is removed can be disposed as a non-TSCA waste. b) Soil with contaminants below industrial cleanup/risk levels can be reused onsite;soil containing contaminants above this level will not be reused. c) Offsite disposal of soil will be disposed of in a lined non-hazardous waste landfill(if not reused onsite)—but not a municipal solid waste/unlined landfill. 131 TECHNICAL MEMORANDUM 8 8) Utilities d) The DBOM Contractor will install a meter for the construction office trailer area and second meter(if required)for construction water.There will be no charge to the DBOM Contractor for the cost of the meter(s)or the water consumed. Note there is significant water volume that will be required for leak testing and commissioning activities. e) The DBOM Contractor will install a sewer connection for the temporary and permanent facilities.There will be no additional fees from the City for sewer connections(either for the construction trailers or for the permanent facilities). f) The DBOM Contractor will be responsible for the cost of chemicals and power for temporary and permanent facilities until Acceptance.The basis of this BAFO includes a power consumption cost based on an evaluation of historic PGE billing rates indicating an average energy cost of$0.12/kWh.The DBOM Contractor will be provided cost relief if the actual energy cost per kWh is higher at startup than currently anticipated. 9) Connection to the existing outfall assumes bypass pumping can be established; pumping from the Chlorine Contact Channel between the TCWTP primary clarifier tanks to the manhole immediately north of the PE Pump Station. 4. Schedule Approach The following clarifications are provided as a basis for the CPM schedule provided with the BAFO: 1) This BAFO is valid assuming NTP by November 2, 2026, as detailed in the CPM schedule.There will be numerous impacts on the project schedule and cost if this date is not met. 2) The City will complete Hazardous Materials Survey of existing buildings on site in advance of NTP. 3) It is understood that the City is in the midst of ongoing litigation related to two of the three parcels that comprise the Project Site.The Project CPM Schedule assumes all activities can proceed while this litigation is being resolved.The City and DBOM Contractor will work together to adequately document this prior to NTP. Delays to any planned activities will result in schedule and cost impacts. 4) The schedule includes(90)weather days and federal and state holidays. 5) Parallel reviews by the City and regulatory agencies are assumed in the schedule. 6) Parallel review by the Building Officials are assumed in the schedule(overlapping Development Review and the Building Permit review processes). 7) The schedule assumes DEQ review and approvals do not impact construction activities, including DP3 (Deep Foundations)and DP4(early concrete) packages. 8) The City will provide adequate inspectors as to not delay the work and be available during normal work hours to inspect work prior to covering up said work. 5. Permitting Approach 1) Preparation of legal descriptions for lot line adjustment and easement(temporary and permanent)descriptions, as well as work to file record of such with County are by the City. 2) Land Use Approval is not required for DP1 (Demolition Package)and DP2 (Storm/Sewer Reroute)work to commence in the field. 3) Proposal assumes that the City will grant a Variance to the requirement that restrooms be accessible within 300 feet. No additional restrooms beyond what is shown on the site plan are assumed. 4) For the intent of meeting City Code requirements,the Lake Oswego Base Flood Elevation (BFE) is the 1996 flood (36.4 ft NGVD29)as this is more restrictive than the 100-year floodplain elevation. 5) LOC 50.11.002 Appendix B—Industrial Land Use Policy Element was repealed.There are no standards in this code section,and it is not applicable to the LOWWTF. 6) Land Use requirements include specific building height, setbacks,view corridors, aesthetic requirements, etc.as required by Lake Oswego code. Requirements above and beyond what is shown in Technical Proposal and explicitly required by code are excluded. 141 TECHNICAL MEMORANDUM 8 7) Native plant requirements apply to the RP zone and do not apply to the LOWWTF site. 8) LOC 50.07.003.1.a.iii does not differentiate between trucks and passenger vehicles.Assume the project triggers the requirement to provide a Traffic Impact Study(TIS). No road improvements are needed for the LOWWTF as existing traffic from the previous 3 parcels will offset LOWWTF traffic.This will be documented in the updated TIS. 6•City Contingency Approach It is recommended that the City maintain and manage a contingency outside of the DBOM Agreement to address risks, uncertainties,and potential scope changes that are not fully defined at this stage of the Project. Such contingency should consider, at a minimum,the following: • Change in Law(specifically tariffs) • Differing Site Conditions(including, but not limited to, existing infrastructure conditions, hazardous materials, change in foundation design required due to Differing Site Conditions, drilling refusal beyond assumptions provided here, contaminated soils, and groundwater conditions) • Force majeure events(including, but not limited to,flooding and abnormal climactic conditions) • City delays(including, but not limited to, permitting delays outside the control of the DBOM Contractor,tribal coordination requirements, neighborhood concerns, and impacts on local business) • Local business mitigation measures such as potential compensation, offsets, or other accommodations. • Community engagement activities such as public tours, events, project watch days, or similar outreach efforts. • Repair of Foothills Road after completion of construction.Construction traffic may cause localized or widespread damage to the existing surface. • City directed scope changes(standby generator sizing,aesthetic enhancements, review and preparation of application for PGE's Dispatchable Standby Generation Program, seismic design criteria for control system components,accommodations for changes requested by City of Portland, or other project enhancements). • Inadequate electrical capacity from PGE requiring system upgrades above those previously envisioned. Escalation Allowance This BAFO includes a recommended Escalation Allowance,the amount of which is inclusive of taxes, bonds, and insurance associated with any work funded from the Escalation Allowance.The Escalation Allowance is available for the DBOM Contractor's use in the event of equipment and/or material cost escalation in those equipment and materials line items identified in Attachment 1 as potentially being subject to escalation.Calculation of any escalation for those line items shall be benchmarked against the values included in this BAFO for those items as shown in Attachment 1. Use of the Escalation Allowance shall require open-book demonstration of escalation by the DBOM Contractor and approval by the City. Upon such approval,the Escalation Allowance shall be reduced by the demonstrated cost of escalation plus associated taxes, bonds,and insurance and the total amount shall then be credited to the Lump Sum from the Escalation Allowance.The Design-Builder is also obligated to notify the Owner in the event of any de-escalation in the price of equipment or materials from the date of Contract Price Amendment execution. In such event, savings shall be credited back to the Escalation Allowance.At a time agreed to by the Parties following substantial completion of the buyout of materials and equipment(on a cost basis) DBOM Contractor shall meet with the City to determine any credits from the Escalation Allowance to the Lump Sum. Following buyout,any remaining Escalation Allowance shall be credited to the Allowances and made available for use by the Owner. Any overage required to cover the escalation cost will remain the Owner's responsibility and require a Change Order. The recommended Escalation Allowance is based on the following definitions for Allowances. "Allowance Item" means specified portion of Work listed in the DBOM Agreement,with costs estimated in assigned dollar amounts. "Allowance Values" means the dollar amounts assigned to Allowance Items. Any and all Allowance Items, as well as their corresponding Allowance Values,shall be set forth in the DBOM Agreement. DBOM Contractor and City will work together to review the Allowance Items and Allowance Values based on design information then-available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. DBOM Contractor and City will continue working closely together during the preparation of the 151 TECHNICAL MEMORANDUM 8 Design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by DBOM Contractor that the Allowance Item in question can be performed for the Allowance Value. No Work shall be performed on any Allowance Item without DBOM Contractor first obtaining in writing advanced authorization to proceed from City. City agrees that if DBOM Contractor is not provided written authorization to proceed by the date set forth in the Project Schedule approved with the DBOM Agreement, due to no fault of DBOM Contractor, DBOM Contractor may be entitled to an adjustment of the Fixed Design-Build Price and Extension of Term. The Fixed Design-Build Price shall be adjusted accordingly by Change Order to either increase the Fixed Design-Build Price or modify the Allowance Item scope to reflect the Allowance Value. Allowances and Alternates includes costs for aspects of the project that may not be required, are not part of the core scope or represent Project- or City-held risks that are not quantified at this time. 161 3acobs Drawings _ _____..........._.___ _ _ , ,__: .. .. . •. . ...... ._ • • . • . . lowu „ir T Mill"Ill" :., . :y. ate _ S. `_ - — - _� ,, , y der um Oit ''✓/,.d' rte%/.:. d .' La -_ - 1 I 2 I 3 I 4 I 5 I 6 0 W > L W w DC H I CITY OF LAKE OSWEGO Lt cd O CO CO z O O LAKE OSWEGO DBO WWTF < Y O U m Q 0 > W LAKE OSWEGO , w o OREGON Q Ct W(I) i_ °0 U) 0_Q CO W -, W 2 WO �z — -O WE MARCH 2026 z 'N we O Y �°z (1) 1 Q H > a zQ w 0 • J W vim)H [Q W I- W WOE C Ur W W = O) OH Z WO C)16 a - w B QO J Et W Qa m _i:C LLI Z W PROJECT LOCATION PROJECT LOCATION Q 0 O HL ASTORIA o O O Q PINE CONE z a O 0_ PARK O z_ z_ (,),HOOD RIVER z O W PORTLAND., 84 ,.../-'/<- PENDLETON w o oo Forest ~ THE DALLES Highlands z z v LAKE OSWEGO <o TILLAMOOK ENTERPRISE p` i- wLLI o O a 97 LA GRANDE 0 w = m 205 / FOREST HILLS so _.,,,,,c-)t O ~O ELEMENTARY 4 m O (n z TRYON CR K 1 /ti r a 0 O <8 SALEM STATE --� /F-11 �r- I O W z NATURAL AR l__J w Q Q 84 c- _QJl r l l i I I O J z NEWPORT 22 —1r OAK GROVE u) W w Q . ALBANY Forest Hills �� ELEMENTARY 0 Q O Op o E-) f W J } w U 126 Country Club Rd I Q U H Q 0 PRINEVILLE — - w in:: J U r. -5 in 5 20 REDMOND In COL° �_I 'I I' > II I H C W C Q SISTERS OSWEGO Lake Oswego w 2 a BEND VALE COUNTRY r" 'I LAKEv in IL____:_. Lr o EUGENE CLUB A Ave --JrD II O LJ =� C W A Ave Inc W North Shore _� U) Country Club LL Evergreen CURLICUE I� _ Lt 20 BURNS ITAININ CORRIDOR — Oak GrOV@ yl Z Iron M `Ja L� A E._ '1 IL H 97 °untain 6 J�� II Q ROSEBURG OREGON �s l L ZriJ- v r i` lir ROEHR PARK 'I - �r \� x 'J O ._1r ' v� , 1. � � o VJ �OD �j ( Oldtown 1_. ti O W C 1 Z O� �_ [� �- q V W GOLDL�� , f GEORGE r ROG RS PARK li \� 11 I� II n L �, ' L \BEACH ` _ �� MEDFORD i I� rl __-11---1-:--47------d (1------ KLAMATH FALLS LAKEVIEW r ri ‘--'-'---------- r‘,4' 1/4. 1'� IF / __ w H D H N N VICINITY MAP LOCATION MAP 1") NTS Cr) NTS VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0001 SHEET 1 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/23/2026 7:45:23 AM 1 2 3 4 5 6 w w w Sheet Number Drawing Number Drawing Number 01 - GENERAL OI 1 01-G-0001 TITLE, VICINITY AND LOCATION MAPS J 2 01-G-0002 DRAWING INDEX Q 3 01-G-0003 PROCESS FLOW DIAGRAM N 4 01-G-0004 PROCESS HYDRAULIC PROFILE m A 5 01-G-0005 PROCESS PIPING SCHEDULE SHEET 1 o z o 6 01-G-0006 PROCESS PIPING SCHEDULE SHEET 2 0 g Y O 7 01-G-0009 PROCESS AREA CLASIFICATION AND MATERIALS Qv 8 01-G-0021 INSTRUMENTATION AND CONTROL - P&ID LEGEND 1 >- 9 01-G-0022 INSTRUMENTATION AND CONTROL - P&ID LEGEND 2 m 10 01-G-0023 ELECTRICAL LEGEND 11 01-G-0050 RENDERINGS 12 01-G-0051 RENDERINGS > > ow 13 01-G-0052 RENDERINGS Q � 14 01-G-0053 RENDERINGS 15 01-G-0054 RENDERINGS w o 16 01-G-0055 RENDERINGS m w 17 01-G-0056 RENDERINGS w )Z 18 01-G-0057 RENDERINGS Y wo 19 01-G-0058 RENDERINGS > 20 01-G-0059 RENDERINGS p Y o 21 01-G-0060 RENDERINGS > y z Q 22 01-G-0061 RENDERINGS w o z 23 01-G-0062 RENDERINGS Tmu w w l=24 01-G-0063 RENDERINGS w- o 25 01-G-0064 RENDERINGS O w= 05 -CIVIL 0~ 26 05-C-2001 OVERALL SITE PLAN wo 27 05-C-2002 OVERALL YARD PIPING PLAN 09 - INSTRUMENTATION AND CONTROL Z w B 28 09-1-0001 INFLUENT PUMP STATION WETWELL 1 29 09-1-0002 INFLUENT PUMP STATION WETWELL 2 Q o W- (13 30 09-1-0003 INFLUENT SCREENS STATION SCREENS 1-5 w aw a z 31 09-1-0004 HEADWORKS GRIT CONCENTRATORS b 32 09-1-0005 GRIT WASHER 1 -TYPICAL Q w Q 33 09-1-0006 AERATION BASIN - LIQUID STREAM -TYPICAL 34 09-1-0007 AERATION BASIN -AIR -TYPICAL _ ce o 35 09-1-0008 SECONDARY CLARIFIER-TYPICAL 0 36 09-1-0009 FILTER -TYPICAL Oz °a O 37 09-1-0010 UV DISINFECTION -TYPICAL z z 38 09-1-0011 THICKENING -TYPICAL ?o 39 09-1-0012 ODOR CONTROL -TYPICAL OF 2 w0 02 40 09-1-0013 NETWORK DIAGRAM z 10 -ADMINISTRATION BUILDING Q Z 41 10-E-6001 ELECTRICAL - ONE LINE DIAGRAM O o 0 20 - INFLUENT PUMP STATION 0 w i U w w m 42 20-E-6001 ELECTRICAL - ONE LINE DIAGRAM 0 0 0 27 - ELECTRICAL BUILDING 0 co co 0 <8 43 27-E-6001 ELECTRICAL-27-SWGR-001-01 ONE LINE DIAGRAM o > 44 27-E-6002 ELECTRICAL -27-MCC-001-01 ONE LINE DIAGRAM J Dz 45 27-E-6003 ELECTRICAL -27-SWBD-001-01 ONE LINE DIAGRAM w o< 50 - FILTRATION Ow O} o 0 46 50-E-6001 FILTRATION - STRUCTURAL -ONE-LINE DIAGRAM v Z C w O O 0 w O w U) w LLI 7 Oo ti) Luz z r7 Q 1 0 D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0002 SHEET 2 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 11:05:58 AM 1 I 2 I 3 I 4 I 5 I 6 0 w > ct w w ct (/) H o ABI/WW E J r 1 N W m A Z 0 > O Q ALP ALP Q Y O U i I PROJECT OPTION 1 >- Q RAPID MIX W3 SYSTEM m FROM FLOCCULATION TANK STORMWATER PS SE --- l w AERATION BASIN 1 ML CLARIFIER 1 w o FROM PDPS ► ► I FILTER 1 NAOCL Q ct L--_ w o0 RAS ► RAS ► w co JM C O w• � - FROM TRYON INFLUENT LL1M UV 1 ~o m Lu• z_Ii7*-1CREEK M SAMPLER ABI ► o w� U Q I—+ z > � FA ► 0 a z o T4' I ABI AERATION BASIN 2 CLARIFIER 2 J ~ HEADWORKS O RKS) M ► FILTER 2 EFFLUENT O o w RS ML SAMPLER tY w r ► wwc CO O ( > SCREEN 1 -� FA T J J d W O H FROM CD I-IVi÷ RAS I . UV 2 2 PORTLAND GRIT RAS BIO BIO _ -► SCREEN 2 REMOVAL 1 M ► FOAM FOAM w ( ► C ► -w a Zw )++—( QQ0 B FROM LAKE M ABI AERATION BASIN 3 ( CLARIFIER 3 ► w z Q OSWEGO SCREEN 3 FILTER 3 U Q z w RAS � I U LT, o r, M w _ � ► CD El , ABI ► RAS H u_ Q al SCREEN 4 ML <o GRIT ► ( P' M UV 3 REMOVAL 2 LL1 o_ H ( ) ABI ► FIO ° 0 M FOAM z z LL1 SCREEN 5 * (/)cc z o o w FA �— ABI AERATION BASIN 4 ( )— CLARIFIER 4 FILTER 4 0 0 r— � l M ► L11 0 � J Qz I— waj O oD ML INFLUENT PUMP GS GS RAS U ww ► 4UV m o 00 STATION --I M RAS o O o FA FA ( ► DISINFECTION O w w <wz Ll1 O < 1-J ¢ ' Q WASHER AERATION Q CLARIFIERS M m FILTRATION ° O o J } U COMPACTOR 1 FA BASINS ° i v 1 0 i_—_I M J M FA m SE/W W C FA 2 0 WASHER 4- RAS o Li_ COMPACTOR 2 , RAS FEJF o 4 CO D w w L GRIT PUMP co ♦ ♦ AND WASHER TO EXISTING OUTFALL Q V V / < POS FA FA BW SCREEN O ► INFLUENT Q - Ilr t t CHANNEL TWAS SLUDGEAM °I RDT 1ill J ► STO RAGE TANK 1 HAULING TO O Q w w U 0 RDT FEED M -► COLUMBIA V E O J Q • BLVD WWTP CO LL ROLLOFF CONTAINER PUMPS TO PDPS4 - A ' 0_ 7 (/), 1II w FCV O NOTE: WAS M 0 1. THIS IS PRELIMINARY DESIGN CRITERIA THAT MAY CHANGE DURING DETAILED DESIGN. 4 D . FA POS FA t ♦ ♦ 12" = 1-0" ► SLUDGE VERIFY SCALE llr* TWAS STORAGE M RDT 2 TANK 2 BAR IS ONE INCH ON SLUDGE MIXING & ORIGINAL DRAWING. TRANSFER PUMPS 0 1" RDT FEED DATE MARCH 2026 PUMPS TO PDPS , PROJ BJO0152J DWG 01-G-0003 SHEET 3 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 12:57:45 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > Lt w w Lt w H I 70 164.1 61.6 60.4 59.0 70 0 - _, BACKWASH SCREENS (5) L I1 MGD _ _ i A - . - pZ STORM WATER PS - CL O Q ►--_ Q Y O PLANT DRAIN PS 3.5 MGD ► U co 60 `� 60 IE 59.0 � 52.3 - 51.7 50.7 49.7 48.9 —IE 57.5 �� �` — a o H EADWO RKS IE 54.7 TOS 55.0 (COVER DEPENDENT) 47.8 47.1 w o 0 Et° `♦ TOS 51.5 46.9 46.7 46.4 - 45.8 44.4 43.7 p w Ny - (COVER - > o STANDPIPE -�� DEPENDENT) - CO co 50 - - EL 58.5 0 - _ TOS 49.67 _ 500 YR 50 o 72,—WEIR �� 43.1 41.9 - 41.8 39.2 FLOOD 0 Y o Lo w—EL 50.0 ----_—y _ EL 40.5 ( I ai-36" GRIT / 7 —- �, U 1996 z REMOVAL (2) �_ w—WEIR J �� �� --� EL 44.0 FLOOD W 0 oz 42" w EL 49.0 WEIR Z w - WEIR w Ui I- TOS 44.92 EL 47.75 w Z WEIR — EL 41.7 EL 36.4 m o> —IE 43.1 � Q EL 46.0 7WE _- �� 1 FOOT z �i w = :THBOEV1E996 ~ o 40 TOS 41.0 p— w U IE 41.67_p Y w o a Q z- LOOD 40 o_ O- -�_ - IE 39.5- ��� L 37.4 - cC p IE38.0 z0 -IE38.0 `��� p Zw < Qo B IE 37.0 a s IE 36.45 •��� z a a OD -_ • zw (4) 30 U • ( • 100 YR = w= • - w O - 01 (2) 42" •�� FLOOD w � w o _Li, Owre x EL 34.0 H oz wQ ifl 30I ' GALLERY -Q54" a - - (2) 36" 30 IE30.0 - c - —3 IE 29.5 - IE 29.0 _WILLAMETTE RIVERLMETTE b u9 o a I -► Z IE 28.45 p z z c? w A cow N M _ FILTRATION (4) 36" EXISTING o w J J J J LL `♦ -w_w_w Q—w IE 25.0 - - ► [ OUTFALL o0 — CLARIFIERS V36" SE SELECT IE 24.0 . zz /' U V 5 YR FLOOD w cn o I 36" (4) - OUTFACE / EL20.4 O 20 DISINFECTION 20 0 0 w io AERATION - (3) JUNCTION m z0 - 16.0 16.0 - - 0 w �Z BASINS (4) - w , Q O J DZ. O INFLUENT _ w J Q T O o 0 153.1 MGD ► - ' Q O ~ 10 10 z z c w d c9 - - w U O O w SMALL-LARGE o RAS V u D w -INFLUENT 0 PUMP 36" ABI SELECT ► - 0 STATION — w J LL 0 O 0_O gWV U U w Q J al cD D r, a_ Q Et a >- LEGEND NOTES: I HYDRAULIC GRADE LINE AT 53.1 MGD PLANT ------ INFLUENT FLOW THROUGH IPS AND THE 100 1. SCREENING STATUS: 2 LARGE DUTY AND 2 SMALL DUTY/ 1 LARGE STANDBY YEAR FLOOD ELEVATION D WATER SURFACE 2. AERATION BASINS STATUS: ALL TRAINS IN SERVICE, INFLUENT FLOW TO TANK 1 ELEVATION (WSE) SYMBOL 3. CLARIFIER STATUS: ALL TRAINS IN SERVICE WET WEATHER PEAK 4. FILTRATION STATUS: ALL TRAINS IN SERVICE XX.X INSTANTANEOUS FLOW - 53.1 MGD 3/16" = 1-0" HYDRAULIC GRADE LINE ELEVATION 5. UV/DISINFECTION STATUS: ALL UV CHANNELS IN SERVICE VERIFY SCALE 6. RAS FLOW RATE = 14 MGD; SPLIT EVENLY TO AERATION BASINS BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" 7. NGVD29 DATUM USED FOR ELEVATIONS DATE MARCH 2026 8. THIS IS PRELIMINARY DESIGN CRITERIA THAT MAY CHANGE DURING DETAILED DESIGN PROJ BJO0152J DWG 01-G-0004 SHEET 4 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 12:58:05 PM 1 I 2 I 3 I 4 I 5 I 6 PIPING SCHEDULE PIPING SCHEDULE PIPING SCHEDULE w > L w CO w L LEGEND SERVICE SIZE (IN.)1 INSTALLATION2 PIPE MATERIAL3 LEGEND SERVICE SIZE (IN.)1 INSTALLATION2 PIPE MATERIAL3 LEGEND SERVICE SIZE (IN.)1 INSTALLATION2 PIPE MATERIAL3 w o I J IND IND Q SST cd EXP EXP SST o c 3 3 co IND BUR PVC POL POLYMER ALL ALL PVC o z o A CPVC EXP ENC Q O Q Y U AERATION BASIN IND CLDI >- Q ABI INFLUENT EXP WS IND POS POLYMER SOLUTION ALL ALL PVC m HDPE IND ≥4 BUR CLDI SST EXP CLDI o WS FE FINAL EFFLUENT WS ≤ 3 a o EXP SUB CLDI IND Q WS ≥ 4 CPVC w a m ENC RETURN ACTIVATED EXP Y °0 o IND ENC RAS SLUDGE IND O a a wL CLDI CLDI > i-o EXP WS EXP °0 �'o CLDI ≥ 4 w AERATION BASIN HDPE BUR HDPE > ABI/WW INFLUENT WET ≥4 BUR CLDI BUR WS O w o WEATHER WS HDPE ENC CLDI i IND O c Lu SUB CLDI 54 - 63 BUR HD ≤ 3" 304 SST W o z ENC WS > 3" CLDI w r m o PVC IND ≤ 3" 304 SST J a W IND EXP RETURN ACTIVATED EXP I- o'- PVC TUBING SST RAS SLUDGE > 3" CLDI 2 '215 w° PVC TUBING BUR CLDI m AL ALUM ALL EXP PVC TUBING ENC BUR HDPE H CONTAINED ≤ 3 >4„ WS a z° O B Qo z SUB PVC TUBING IND ENC CLDI U a a 2" w BUR PVC TUBING BUR PVC < EXP STL D 'a 0 CONTAINED > 2" � Y o z IND WS FLT FILTRATE ENC ≤ 3" PVC o Lu o EXP IND CELDI RS RAW SEWAGE BUR CELDI — o" EXP WS > 3" HDPE p u9 6 i- 5 2" SUB SST z o °a ≤ 3" PVC z z WS cow AIR CLDI — ENC — ENC > 3" CELDI ?w WSc ALP LOW PRESSURE SST ≥ 4 BUR HDPE HDPE o0 m IND PVC z z — WS BUR C900 PVC w ¢W > 2" , 30" EXP CLDI RS RAWSEWAGE ≥ 4 0 0 SUB SST ENC WS (GRAVITY) O w z m PVC EMB CLDI 0 1-o ENC WS m O O Q o SST FW FIRE WATER ≥ 4 BUR C900 PVC SUB o w z c!)≤ 3 EXP GLDI ≤ 3 EXP SST w O Q 2 0 BF BIOLOGICAL FOAM CPVC GR GRIT ≥ 4 EXP - J DZ SST EXP 0 Q p o 0 ≥4 SUB CLDI RAW SEWAGE w J } 22° HDPE RS/P BUR CLDI Y H m.< IND GS GRIT SLURRY ALL EXP (PUMPED) ≥ 4 J U i CLDI GLDI ENC EXP WS IND BUR HDPEI Z C SUB ≤ 3 SST EXP IND PVC-DWV o BW BACKWASH >4 CLDI IND SS SANITARY SEWER ≤ 3PVC u_ 0 BUR HDPE CLDI BUR HDPE ° WS ML MIXED LIQUOR EXP WS ≤ 10 PVC D CLDI WS ≥ 4 BUR HDPE SD STORM DRAIN BUR PVC ENC CLDI > 10 WS SUB CLDI RC CD CONDENSATE DRAIN ALL ALL PVC-DWV ENC WS ≤ 3 ALL SST W IND MLR MIXED LIQUOR RETURN ≥ 4 SUB CLDI CLDI HDPE SD/P STORM DRAIN BUR HDPE J D DRAIN ALL ENC PVC-DWV (PUMPED) ≥ 4 (PLUMBING) IND SUB O CLDI BUR Zi SODIUM EXP CPVC _ ENC Q (/) = 1- IND PVC NAOCL HYPOCHLORITE ALL SUB O z U U W EXP CPVC PVC TUBING U) W ≤ 3 BUR CONTAINED all O Etfin i BUR U) ' PVC IND, EXP ' z ENC STL 0_ NG NATURAL GAS ≤ 2 ENC IND CLDI AERATION BASIN BUR PE DEW DEWATERING EXP WS IND CLDI PVC-DWV BUR WS ≤ 3 EXP D ≥4 HDPE PD PLANT DRAIN CLDI PVC-DWV ENC WS BUR PVC CLDI ≥ 4 HDPE SUB WS EXP SST ≤ 3 VERIFY SCALE EXP FRP BUR PVCBAR IS ONE INCH ON SST ORIGINAL DRAWING. FA FOUL AIR ALL EXP o 1„ IND SST PD/P PLANT DRAIN (PUMPED) _ SUB CLDI DATE MARCH 2026 ≥ 4 PROJ BJO0152J ENC DWG 01-G-0005 BUR HDPE SHEET 5 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 12:57:27 PM 1 I 2 I 3 I 4 I 5 I 6 PIPING SCHEDULE PIPING SCHEDULE w > L w w L LEGEND SERVICE SIZE (IN.)1 INSTALLATION2 PIPE MATERIAL3 LEGEND SERVICE SIZE (IN.)1 INSTALLATION2 PIPE MATERIAL3 w I E J IND IND < SST ≤ 3 SST co EXP EXP o U) BUR SST IND O z o A HDPE ENC SST WAS WASTE ACTIVATED EXP CLDI 0 u) O < 3 SLUDGE v U IND PVC ≥ 4 SUB > Q BUR CLDI C° EXP CPVC HDPE BUR PVC ENC CLDI a ENC PVC IND COP > o Q i>_- SE SECONDARY EFFLUENT IND CLDI IND - w w POTABLE CPVC w 0 0 CLDI W1 ≤ 3 EXP - Et Q EXP WATER T WS BUR HDPE >- H o Co wz — WS ENC PVC -0 4 - 54 BUR CLDI HDPE HW HOT WATER ≤ 3 IND COP z w 0 Y cn Oz CLDI HOT WATER < IND 5 U Z Q QI- ENC HW3 (NON-POTALBE) 3 COP 0 w STL EXP O U wH SUB CLDI COP w m o> TW TEPID WATER ≤ 3 IND c CPVC — WS w 54 - 63 BUR OH HDPE 2 ° PVC w 0 SECONDARY EFFLUENT WS IND D- SE/WW WET WEATHER ALL BUR CLDI COP (DI- HDPE EXP a -w B <0 IND ≤ 3 SUB SST C.) Tr CL ≤ 3 SST u) zw EXP HDPE I 2 LI = o CLDI BUR PVC w Y o z IND O H WS W3 PLANT WATER SUB PVC <0 CLDI IND CLDI u9 6 TERTIARY FILTER EXP Oz o 0 Z TFE EFFLUENT WS EXP CLDI z z wcc ≥4 CLDI HDPE ?L, ENC ≥ 4 w o WS BUR CLDI a = O � z — CLDI C900 PVC w < o Wu) BUR HDPE ENC CLDI O a > 0 w I U w w O WS ~ m O u) off PROCESS O w O <8 XX/D DRAIN co > z — ° w w O Q Dz XX/OF PROCESS OVERFLOW u) w u 0< SAME MATERIAL O Q 81) PROCESS ALL ALL AS PIPE BEING w J O} o 0 XX/SAM SAMPLING SERVED J a H PROCESS/ z C XX/V PLUMBING VENT D O 0 NOTES: o w U) D 1. SYMBOLS 4. JOINT TYPES W < LESS THAN BA: BARBED ≤ LESS THAN OR EQUAL TO BR: BRAZED > GREATER THAN FL: FLANGED ≥ GREATER THAN OR EQUAL TO GR: GROOVED HS: HUB AND SPIGOT 2. INSTALLATION HU: HUBLESS W J EXP: EXPOSED (OUTDOOR) MJ: MECHANICAL JOINT WITH RESTRAINT D IND: INDOOR PO: PUSH ON JOINT WITH RESTRAINT - SUB: SUBMERGED PRJ: PROPRIETARY RESTRAINED JOINTAI u) N BUR: BURIED SG: SWAGED Q ENC: ENCASED OR BENEATH STRUCTURES SL: SOLDERED O w U U W SW: SOLVENT WELDED V w O U) W 3. MATERIALS TH: THREADEDCCI O Et Cin _ C900: AWWA C900 PVC W: WELDED, PLASTIC FUSION, OR FRP (n CELDI: CERAMIC EPDXY-LINED DUCTILE IRON '' z CISP: CAST IRON SOIL PIPE 5. INSULATION AND HEAT TRACING REQUIRED ON ALL EXPOSED OUTDOOR W CLDI: CEMENT-LINED DUCTILE IRON PIPING 6" AND SMALLER. OMIT INSULATION AND HEAT TRACING ON PIPING CL COP: COPPER LOCATED IN HEATED SPACES, EXCEPT WHERE INDICATED ON THE CPE: CORRUGATED POLYETHYLENE DRAWINGS. INSULATION AND/OR HEAT TRACING REQUIRED ON EXPOSED CPVC: CHLORINATED POLYVINYL CHLORIDE PIPING GREATER THAN 6" WHERE INDICATED ON THE DRAWINGS. WHERE FRP: FIBERGLASS REINFORCED PLASTIC EXPOSED PIPING TRANSITIONS TO BURIED PIPING, EXTEND INSULATION D GALV: GALVANIZED STEEL TO FROST DEPTH. REFER TO SPECIFICATION SECTION 40 42 13 GLDI: GLASS-LINED DUCTILE IRON SUPPLEMENT 1 FOR PIPING INSULATION REQUIREMENTS AND PIPE HDPE: HIGH-DENSITY POLYETHYLENE INSULATION SERVICE TYPE DEFINITION. REFER TO SPECIFICATION HDPE TUBING: HIGH-DENSITY POLYETHYLENE TUBING SECTION 40 05 33 FOR HEAT TRACING REQUIREMENTS. PE: POLYETHYLENE PP: POLYPROPYLENE 6. FOR UNPAINTED PIPING OR INSULATED PIPING, COLOR IS LABEL COLOR. VERIFY SCALE PTFE: POLYTETRAFLUOROETHYLENE SAFETY COLORS AS DEFINED BY ASME A13.1. PVC: POLYVINYL CHLORIDE BAR IS ONE INCH ON PVC-DWV: PVC DRAIN WASTE VENT 7. PROCESS VENT, OVERFLOW, AND DRAIN PIPING SHALL BE AS ORIGINAL DRAWING. o 1" PVC TUBING: BRAIDED REINFORCED PVC TUBING SCHEDULED FOR THE ASSOCIATED SERVICE UNLESS OTHERWISE NOTED. DATE MARCH 2026 RC: REINFORCED CONCRETE STL: CARBON STEEL 8. THIS IS PRELIMINARY DESIGN CRITERIA THAT MAY CHANGE DURING DETAILED PROJ BJO0152J SST: STAINLESS STEEL DESIGN. DWG 01-G-0006 WS: WELDED FABRICATED STEEL SHEET 6 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 12:56:57 PM 1 I 2 I 3 I 4 I 5 I 6 0 AREA CLASSIFICATION AND MATERIALS SELECTION TABLE AREA CLASSIFICATION AND MATERIALS SELECTION TABLE w Lt w CO w FACILITY ROOM /AREA LOCATION DESIGNATION NFPA 820 CLASSIFICATION 2020 NFPA 820 REFERENCE FACILITY ROOM /AREA LOCATION DESIGNATION NFPA 820 CLASSIFICATION 2020 NFPA 820 REFERENCE L H I ELECTRICAL ROOM INDOOR, DRY UNCLASSIFIED N/A SCUM PIT WET, CORROSIVE, UNCLASSIFIED TABLE 6.2.2, ROW 4D E 10 ADMINISTRATION BUILDING LAB ROOM INDOOR DRY UNCLASSIFIED NA SUBMERGED Q co OFFICE SPACE INDOOR, DRY UNCLASSIFIED N/A CLARIFIER AREA BELOW COVERS OUTDOOR, WET, UNCLASSIFIED TABLE 5.2.2, ROW 16CN CORROSIVE co GARAGE INDOOR, DRY UNCLASSIFIED N/A 0 z o A 12 MAINTENANCE SHOP CLARIFIER AREA ABOVE COVERS OUTDOOR, WET UNCLASSIFIED TABLE 5.2.2, ROW 16 O Q STORAGE INDOOR, DRY UNCLASSIFIED N/A 0 Y O SLUDGE STORAGE TANKS INDOOR, WET, CORROSIVE, CLASS 1, DIVISION 1 TABLE 6.2.2, ROW 10A ABOVE GRADE OUTDOOR, WET UNCLASSIFIED NEC 500 INTERIOR HAZARDOUS >- Q m CLASS 1, DIVISION 1 ABOVE GRADE 3 FEET OR LESS WET, CORROSIVE, FIGURE A.4.2(b) EXTERIOR OF SLUDGE STORAGE FROM HATCHES OR VENTS HAZARDOUS GROUP D 40 CLARIFIERS TANK 3 FEET OR LESS FROM WET, CORROSIVE, CLASS 1, DIVISION 1, FIGURE A.4.2(b) HAZARDOUS GROUP D CLASS 1, DIVISION 20 INFLUENT PUMP STATION ABOVE GRADE 3 TO 5 FEET FROM WET, CORROSIVE, HATCHES OR VENTS 2, a w HATCHES OR VENTS HAZARDOUS GROUP D FIGURE A.4.2(b) a o EXTERIOR OF SLUDGE STORAGE Q WET, CORROSIVE, CLASS 1, DIVISION 2, WET WELL, ROCK TRAPS, WET, CORROSIVE, CLASS 1, DIVISION 1, GROUP TANK 3 TO 5 FEET FROM FIGURE A.4.2(b) (1 w m TABLE 4.2, ROW 14A HATCHES OR VENTS HAZARDOUS GROUP D w o 0 JUNCTION BOX HAZARDOUS D Y Et o Da¢ PUMP ROOM INDOOR, WET UNCLASSIFIED TABLE 6.2.2, ROW 9B 0 =w AREAS WITHIN 3 FEET OF FANS, i-o 22 ODOR CONTROL - OUTDOOR, WET, m cn z FLEX CONNECTIONS, DAMPERS, CLASS 1, DIVISION 2 TABLE 4.2.2, ROW 18C o , WET, CLASS 1, DIVISION 2 .- FLANGES, AND VESSELS o l ELECTRICAL ROOM INDOOR, DRY UNCLASSIFIED NEC 500 z ct E ABOVE GRADE OUTDOOR, WET UNCLASSIFIED NEC 500 — 0 Y n 2 ABOVE GRADE 3 FEET OR LESS WET, CORROSIVE, CLASS 1, DIVISION 2, AREA ABOVE PROCESS LIQUID w . g z 23 STORM DRAIN PUMP STATION FROM HATCHES OR VENTS HAZARDOUS GROUP D FIGURE A.4.2(b) C I- LEVEL UP TO 18INCHES ABOVE CU cn w TANK WALL, EXTENDING 181N OUTDOOR, WET, w �I- STORMWATER PUMP STATION WET, CORROSIVE, CLASS 1, DIVISION 2, CLASS I, DIV 2 TABLE 5.2.2, ROW 7, 22 50 FILTRATION HORIZONTALLY FROM OUTSIDE CORROSIVE, HAZARDOUS °J° °� WET WELL HAZARDOUS GROUP D TABLE 4.2, ROW 4 WALL AND 18 IN ABOVE GRADE I- o OUT TO 10 FEET HORIZONTALLY I- 1215 ELECTRICAL ROOM INDOOR DRY UNCLASSIFIED NEC 500 w o 2_ WET, CORROSIVE, PUMP ROOM INDOOR, WET UNCLASSIFIED TABLE 4.2.2, ROW 16 i INTERIOR OF CHANNELS CLASS 1, DIV 1 TABLE 5.2.2, ROW 2A HAZARDOUS01- ABOVE CHANNEL COVERS OUTDOOR, WET UNCLASSIFIED TABLE 5.2.2, ROW 26 a z w B 55 UV DISINFECTION a o SCREENING AREA WITHIN 10 IN CHANNELS BELOW COVERS SUBMERGED, WET,... UNCLASSIFIED TABLE 5.2.2, ROW 26 z co a ct OUTDOOR, WET, a FEET OF EQUIPMENT OR OPENCLASS 1, DIV 2 TABLE 5.2.2, ROW 2C Q z w CHANNEL. CORROSIVE 60 SOLIDS LOADOUT BAY/ POLYMER AREA INDOOR, WET, HAZARDOUS CLASS I, DIV 2 TABLE 6.2.2, ROW 10B a DI 25 HEADWORKS AND GRIT F w b w =} H SCREENING GREATER THAN 10 Q o a OUTDOOR, WET, FEET FROM EQUIPMENT OR CORROSIVE UNCLASSIFIED TABLE 5.2.2, ROW 2C I o CHANNEL. O � GRIT PUMPING INDOOR, WET UNCLASSIFIED TABLE 6.2.2, ROW 2 Z ct o 0 a zz LOAD OUT INDOOR, WET, CORROSIVE UNCLASSIFIED TABLE 6.2.2, ROWS 1 AND 2 z o ABOVE GRADE OUTDOOR, WET UNCLASSIFIED NEC 500 0 0I 0� ABOVE GRADE 3 FEET OR LESS WET, CORROSIVE, CLASS 1, DIVISION 1, <— FIGURE A.4.2(b) w (/)o FROM HATCHES OR VENTS HAZARDOUS GROUP D F- w w O g 28 PLANT DRAIN PUMP STATION ABOVE GRADE 3 TO 5 FEET FROM WET, CORROSIVE, CLASS 1, DIVISION 2, 6 O w HATCHES OR VENTS HAZARDOUS GROUP D FIGURE A.4.2(b) m O i o a O U) z~ O <0 WET, CORROSIVE, CLASS 1, DIVISION 1, O w z .2, ROW 14A C.0 Y w z HAZARDOUS GROUP D w O Q ma Lu AREA ABOVE LIQUID LEVEL AND INDOOR, WET, CORROSIVE, O Q O 22 CLASS 1, DIVISION 1 TABLE 5.2.2, ROW 7A AND 8 BELOW HARD COVER HAZARDOUS Y -i >- PIPE GALLERY INDOOR, WET UNCLASSIFIED TABLE 9.1.1.1.1, ROW 2C o ~ 30 AERATION BASINS AREAS ABOVE HARD COVER OUTDOOR, WET UNCLASSIFIED NA H z C "J 2 SCUM PITS INDOOR, WET, CORROSIVE, CLASS 1, DIVISION 1 TABLE 6.2.2, ROW 4C o HAZARDOUS O w 0 32 ODOR CONTROL AREAS WITHIN 3 FEET OF FANS, OUTDOOR, WET, w FLEX CONNECTIONS, DAMPERS, CLASS 1, DIVISION 2 TABLE 4.2.2, ROW 18C D AERATION AND SOLIDS HAZARDOUS FLANGES, AND VESSELS ELECTRICAL ROOM INDOOR, DRY UNCLASSIFIED NA O 35 BLOWER FACILITY Z BLOWER ROOM OUTDOOR, WET UNCLASSIFIED NA Q Z O NOTES: A - Q J 1. CLASSIFICATION FOR EXISTING AREAS NOT INDICATED ON THIS TABLE HAVE NOT BEEN DETERMINED. O W _ ≤ ANY WORK DONE IN AREAS NOT LISTED ON THIS TABLE SHALL BE SUBMITTED TO ENGINEER FOR REVIEW. EC) O u_ W 2. FOR INSTRUMENT ENCLOSURE RATINGS AND MATERIALS, SEE INSTRUMENT LIST AND SPECIFICATION SECTION 41 91 00, INSTRUMENTATION AND CONTROL COMPONENTS. al (D D C]) Q 3. NEMA 4X ENCLOSURES SHALL BE 316 SST, UNO. r, CL Q 2 4. JUNCTION BOXES, PULL BOXES AND WIREWAYS MAY BE NEMA 4X IN CLASS I DIVISION 2 SPACES. U 5. THIS IS PRELIMINARY DESIGN CRITERIA THAT MAY CHANGE DURING DETAILED DESIGN. Q ABBREVIATIONS: W AL ALUMINUM Et CGD COMBUSTIBLE GAS DETECTOR Q D EMT ELECTRICAL METALLIC TUBING FE FIRE EXTINGUISHER FAS FIRE ALARM SYSTEM FDS FIRE DETECTION SYSTEM FRP FIBERGLASS REINFORCED PLASTIC H HYDRANT VERIFY SCALE NA NOT APPLICABLE BAR IS ONE INCH ON PVC POLYVINYL CHLORIDE ORIGINAL DRAWING. o 1" RGS RIGID GALVANIZED STEEL SST SST DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0009 SHEET 7 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/24/2026 7:48:17 AM 1 I 2 I 3 I 4 I 5 I 6 GENERAL SHEET NOTES a > INSTRUMENT IDENTIFICATION LINE LEGEND 1. COMPONENTS AND PANELS SHOWN WITH A SINGLE ASTERISK (* ) ARE TO BE PROVIDED AS PART OF A CC PACKAGE SYSTEM. co INSTRUMENT IDENTIFICATION LETTERS TABLE iH CD 2. COMPONENTS AND PANELS SHOWN WITH A DOUBLE -J FIRST-LETTER SUCCEEDING-LETTERS PRIMARY PROCESS (CLOSED CONDUIT, PARALLELING LINES ASTERISK (�I(* ) ARE TO BE PROVIDED UNDER DIVISION 26, ELECTRICAL. PROCESS OR MODIFIER READOUT OR READOUT OR READOUT OR DASHED LINE INDICATES o EXAMPLE SYMBOLS LETTER INITIATING VARIABLE PASSIVE FUNCTION PASSIVE FUNCTION PASSIVE FUNCTION ALTERNATE FLOW STREAM) 4 4 THIS IS A STANDARD LEGEND. THEREFORE, NOT ALL OF c, A A ANALYSIS (+) ALARM SECONDARY PROCESS (2) �m m� 3(2) 3 THIS INFORMATION MAY BE USED ON THE PROJECT. o z o B BURNER, COMBUSTION USER'S CHOICE (*) USER'S CHOICE (*) USER'S CHOICE (*) _ BYPASS PROCESS I I COMPONENTS AND PANELS SHOWN WITH A SINGLE o_ c © FIRST LETTER(S) _��___ Q Y SUCCEEDING LETTER(S) C USER'S CHOICE (*) CONTROL ---- -Pm- PROCESS (OPEN CHANNEL) (A) (B) 4. FILLED IN DIAMOND ( *) ARE TO BE PROVIDED BY THEOZONE SYSTEM Q D DENSITY (S.G.) DIFFERENTIAL �_-- PANEL PROCUREMENT IPACKAGE.ER AS RT OF THE CONTROL m CLARIFYING ABBREVIATIONS,/- (A) TOTAL OF 2 SIGNALS E VOLTAGE PRIMARY ELEMENT, POWER SUPPLY UNITS INDICATED BY A SINGLE UNFILLED UNIT PROCESS NUMBER SENSOR ANALOG SIGNAL (B) 3 TYPICAL SETS OF BB/— (4 TO 20 mAdc, ETC.) 2 SIGNALS EACH. 5. DIAMOND (0) ARE TO BE PROVIDED BY THE OZONE FLOW RATE RATIO -- --�--F- SYSTEM SUPPLIER AS PART OF THE POWER SUPPLY > u_ ITXX F (FRACTION) DISCRETE TOTAL OF 6 SIGNALS. UNIT PROCUREMENT PACKAGE. Q ° (ON/OFF, ETC.) LLLUU � USER'S CHOICE (*) GLASS, GAUGE GATE // // // PNEUMATIC SIGNAL CONNECTING LINES 0 z w Gom VIEWING DEVICE X X X FILLED SYSTEM SIGNAL 4‘ 4'SET LETTER (USED WHEN Q Lii THERE ARE MULTIPLE DEVICES H HAND (MANUAL) HIGH HYDRAULIC SYSTEM SIGNAL I I ~o WITH THE SAME UNIT NUMBER) o 0I CURRENT (ELECTRICAL) INDICATE o DATA LINKS Uo J POWER SCAN Iz >N UNIT NUMBER I >N TIME, TIME SCHEDULE TIME RATE CONTROL STATION BUILDING OR u) i _i o K OF CHANGE FACILITY BOUNDARY NON-CONNECTING LINES > O Q IS LOOP NUMBER P w PACKAGE SYSTEM o< Et w L LEVEL LIGHT PILOT (PILOT) LOW EQUIPMENT Q H M MOTION MOMENTARY MIDDLE, INTERMEDIATE — TYPICAL BREAK z °w rY N TORQUE USER'S CHOICE (*) USER'S CHOICE (*) USER'S CHOICE (*) EC ETHERNET (COPPER) Q Cl- LLJ O USER'S CHOICE (*) ORIFICE, RESTRICTION PACKAGE SYSTEM HH DIGITAL SYSTEM INTERFACES - w G S S C S P PRESSURE, VACUUM POINT (TEST) CONNECTION 0 -w B A ANALOG INPUT WHERE X = QUANTITY INTEGRATE, Z Q TOTALIZE INTERFACE SYMBOLS A = ALARM R RADIATION RECORD OR PRINT _I Z E V ANALOG OUTPUT Y ui O H = MAINTAINED S SPEED, FREQUENCY SAFETY SWITCH Di Lu =° T TEMPERATURE TRANSMIT S WA Mlif PROCESS INTERFACE Q M = MOMENTARY o Z o e O X DISCRETE INPUT U MULTI VARIABLE MULTI FUNCTION MULTI FUNCTION MULTI FUNCTION o 0 s = STATUS z G_H VIBRATION, VALVE, DAMPER, co DISCRETE OUTPUT V MECHANICAL ANALYSIS LOUVER WA D SIGNAL INTERFACE O o o Z X W WEIGHT, FORCE WELL Z o -LU NETWORKED X UNCLASSIFIED (*) X AXIS UNCLASSIFIED (*) UNCLASSIFIED (*) UNCLASSIFIED (*) CO 0 COMMUNICATIONS EVENT, STATE Y AXIS RELAY, COMPUTE, W SOURCE UNIT PROCESS NO. (1 OR 2 DIGITS) o Z — INTERFACE Y OR PRESENCE CONVERT QMa- PROFINET OR P/B (PROFIBUS) A INTERFACE NO. (2 DIGITS) H O o POSITION Z AXIS DRIVE, ACTUATOR, Z Z UNCLASSIFIED FINAL D DESTINATION DRAWING NO. O O 'I LLI o CONTROL ELEMENT m O (1) 0H S SOURCE DRAWING NO. O O 0 Qo w Z TABLE BASED ON THE INSTRUMENTATION, SYSTEMS, AND AUTOMATION SOCIETY (ISA) STANDARD. Lu 0 o J o w w (+) WHEN USED, EXPLANATION IS SHOWN ADJACENT TO INSTRUMENT SYMBOL. SEE ABBREVIATIONS AND LETTER SYMBOLS. INTERFACE TO Y O o w O (*) WHEN USED, DEFINE THE MEANING HERE FOR THE PROJECT. Di/ OR FROM PROCESS / O < �° w _i H CJ EXTERNAL TO PROJECT Q U Q J co H Z C PROCESS OR SIGNAL 2 1 0 LINE CONTINUATION O f o GENERAL INSTRUMENT OR SPECIAL CASES TRANSDUCERS N=1,2,3,ETC O FUNCTIONAL SYMBOLS \ / A ANALOG I CURRENTCC YL 00 D DIGITAL P PNEUMATIC / \1 ON AND OFF EVENT FIELD MOUNTED / --- \ LIGHTS E VOLTAGE PF PULSE FREQUENCY �_/ F FREQUENCY PD PULSE DURATION SELF CONTAINED VALVE & ° 00 H HYDRAULIC R RESISTANCE EQUIPMENT TAG NUMBERS z i O BACK-OF-PANEL HS UN_ - ___. MOUNTED (OPERATOR ON OFF HAND SWITCH, II"INACCESSIBLE) Q �_/ MAINTAINED CONTACT .c a Z O z SWITCH (CONTROLLED EXAMPLE ARV AIR RELEASE VALVE � O 06 W PANEL MOUNTED DEVICE WILL RESTART AAA-FPLLDS ___/ (OPERATOR ON RETURN OF POWER I/P BAL RV AIR AND VACUUM RELEASE VALVE Illiir w Q 0_ACCESSIBLE) SS AFTER POWER FAILURE). (F-1-if CCw A = ISA IDENTIFIER BFV BUTTERFLY VALVE ' � J CURRENT TO PNEUMATIC F = FACILITY NUMBER CV CHECK VALVEill) MCC MOUNTED HS STOP-START HAND SWITCH �/ TRANSDUCER (BACK OF P = PROCESS NUMBER DV DIAPHRAGM VALVE rY �� MOMENTARY CONTACT PANEL, IN A FLOW LOOP) L = LOOP NUMBER E EJECTOR co SWITCHES (CONTROLLED D = DEVICE NUMBER FCV FLOW CONTROL VALVE z S = SEC DEVICE NUMBER GGATE DEVICE WILL NOT RESTART GV GATE VALVE SCADA FUNCTION ON RETURN OF POWER LCV LEVEL CONTROL VALVE AFTER POWER FAILURE). M MECHANICAL EQUIPMENT D NV NEEDLE VALVE OIU OPERATOR INTERFACE UNIT P PUMP PCV PRESSURE CONTROL VALVE PSE RUPTURE DISK NTS PSV PRESSURE RELIEF VALVE VERIFY SCALE PV PLUG VALVE T TANK BAR IS ONE INCH ON TCV TEMPERATURE CONTROL VALVE ORIGINAL DRAWING. 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 01-G-0021 SHEET 8 FILENAME: 01-G-0021.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:57 AM 1 I 2 I 3 I 4 I 5 I 6 a w VALVE SYMBOLS MISCELLANEOUS SYMBOLS PUMP AND COMPRESSOR SYMBOLS w CO w CC CO H C E J J Q -><H GATE PRESSURE RELIEF LE 120V o K SIGHT GLASS 120 VOLT,60 HZ POWER NOTE:XX:AS ADJUSTABLE SPEED N CS-1 CONSTANT SPEED (SINGLE SPEED) m A �� KNIFE GATE ' ' AIR AND/OR VACUUM RELEASE �� 480V CS-2 CONSTANT SPEED (TWO SPEED) j o BUTTERFLY I DIAPHRAGM SEAL 480 VOLT, 60 HZ POWER Q z 0 REGULATED SIDE 0 �� GLOBE PRESSURE CONTROL CENTRIFUGAL PUMP SUBMERSIBLE SUMP PUMP m Q (DRY PIT) (Jo( -1)80— BALL II f BLIND FLANGE ANNULAR DIAPHRAGM SEAL V �4 MULTI-PORT VALVES XX �� 'I--► PROGRESSIVE CAVITY PUMP �� VEE- BALL (BALL VALVE SHOWN. FOR OTHERv4' CENTRIFUGAL WET PIT AXX > o �� PLUG VALVE TYPES, APPROPRIATE AIR GAP RUPTURE DISK (PRESSURE) XX PUMP OR TURBINE PUMP < >- VALVE SYMBOL SHOWN. ) K1 - SEAT PORT ARROWS INDICATE FLOW PATTERN. O m ECCENTRIC PLUG �/ (CENTRIFUGAL)SEAT PORTS ARE IMPLIED BY COMPRESSOR CENTRIFUGAL cn °o VENT TO ATMOSPHERE CHEMICAL FEED PUMP XX H w Q -1/\1- DIAPHRAGM INDICATED FLOW PATTERN. M RUPTURE DISK (VACUUM) O XX � � O° TELESCOPE COMPRESSOR (PISTON) o —MI— PINCH � �z AERATOR PIG INSERT POINT DIAPHRAGM PUMP 0 Q XX XX z >N NEEDLE S SAMPLE O u O CT) J2 ��� SWING CHECK o MUD �-fOR N PIG CATCH POINT 8GEAR PUMP OR BLOWER BLOWER OR FAN W 0 oQ vf--) PLUG (POSITIVE DISPLACEMENT) O (CENTRIFUGAL) H -z Q H --1<C) H BALL CHECK XX XX z °w rY RECEPTACLE MIXER c a-w ��� PERESTALTIC EJECTOR w oHI- ~ CHEMICAL FEED PUMP -) LU o SELF CONTAINED GATE SYMBOLS A M ELECTRIC MOTOR co~ AIR SUPPLY o col— w B COMPOSITE SAMPLER a o U SLUICE [ ] FABRICATED SLIDE SD (DIPPER TYPE) TPRESSURE GAUGE LINE SIZE AND MATERIAL IDENTIFICATION U Q a D J Zw Di BUTTERFLY SHEAR COMPOSITE SAMPLER w \," =o SS TONE TRANSMITTER FLAP (SUCTION TYPE) X NO. X (FOR REFERENCE ONLY. SEE SITE AND MECHANICAL DRAWINGS) o az PIPE DIAMETER g o TV TV CAMERA X TONE RECEIVER IN INCHES 0 o Q O ACTUATOR SYMBOLS NO. X 24"-RW S z zz z o n XX PNEUMATIC DIAPHRAM E Z 7 RADIO ANTENNA VOICE COMMUNICATION FLOW STREAM ID -/f 0 w o SPRING-OPPOSED, SINGLE OR ELECTRIC MOTOR WITH POSITIONER . POINT o= "ON" TIME DELAY za Qz DOUBLE ACTING A ON-TD B.„...)( B "ONT X-SEC. z o f X-SEC A'B' FTER A "ON". TV TV MONITOR O w XX PNEUMATIC CYLINDER O o� SINGLE OR DOUBLE ACTING T MANUAL INSTANT "OFF". A O =m ACTUATED BY ONE INPUT "OFF" TIME DELAY AND C_ LOGIC ELEMENT: FLOW STREAM IDENTIFICATION p 00 O o 0 A OFF-TD B B "OFF" X SEC. B� IF A AND NOT B THEN C O o w Z° Txx Txx X-SEC AFTER A "OFF". O INSTANT "ON" > Q E w ELECTRIC MOTOR ELECTROHYDRAULIC A w O w . . J CHFL CHEMICAL CONVEYANCE WATER C LOGIC ELEMENT: CHW CHEMICAL FLUSHING WATER O Q O> o ca I B OR IF A OR B THEN C CS CAUSTIC SOLUTION, CONCENTRATED Q LLJJ U i s Iii XX NOTE: CSD CAUSTIC SOLUTION, DILUTE SOLENOID ON LOSS OF PRIMARY POWER (PNEUMATIC, ELECTRICAL INTERLOCK. SEE S ON/OFF RELAY. INPUT IS CWR COOLING WATER RETURN (OPEN LOOP) OR CWS COOLING WATER SUPPLY (OPEN LOOP) co OR HYDRAULIC) CONTROL DIAGRAMS CONNECTED TO OUTPUT D, DR DRAIN z C XX: FO =FAIL OPEN I R WHEN SWITCHING SIGNAL DW DILUTION WATER LLI XX FC =FAIL CLOSED IS PRESENT. FS FIRE SPRINKLER WATER o H FLP=FAIL TO LAST POSITION FW FINISHED WATER LL HYDRAULIC S SWITCHING SIGNAL GCWR GENERATOR COOLANT WATER RETURN (CLOSED LOOP) o A SWITCHING RELAY. INPUT GCWS GENERATOR COOLANT WATER SUPPLY (CLOSED LOOP) D S C MEMORY ELEMENT R GOX GASEOUS OXYGEN Et B R WITH DOT IS CONNECTED HF HYDROFLUORIC ACID, CONCENTRATED PRIMARY ELEMENT SYMBOLS S= SET , R= RESET TO OUTPUT WHEN SWITCHING HFD HYDROFLUORIC ACID, DILUTE SIGNAL IS PRESENT HWR HEATING WATER RETURN HWS HEATING WATER SUPPLY X PURGE SET OTHER INPUT IS CONNECTED LOX LIQUID OXYGEN X : W = WATER TO OUTPUT WHEN SWITCHING N2 NITROGEN a \/ ULTRASONIC A = AIR SIGNAL IS NOT PRESENT. O2 OXYGEN PARSHALL FLUME Hr\jl ® FLOWMETER O3 OZONE MI z SEEO F Of FLUSHING CONNECTION O3S OZONE SOLUTION OU N lig3 OF OVERFLOW p WEIR M ELECTROMAGNETIC OG OFF GAS Q O O FLOWMETER XX AIR SET OW OZONATED WATER z — Z R1 OZONE REACTOR R1 O OU — o6 W PROPELLER OR XX= SUPPLY PRESSURE R5 OZONE REACTOR R5 Q 0_ Ur �,�® ORFICE PLATE IN PSIG. HOSE ADAPTOR RW RAW WATER TURBINE METER SA SAMPLE CV w W n S if SEAL WATER SET SBD SODIUM BISULFITE, DILUTE rill) J -amr-1-10.- FLOW TUBE pE �� GI-Pi SBS SODIUM BISULFITE, CONCENTRATEDrY DENSITY METER SD STORM DRAIN H FILTER/ - I-of SH SODIUM HYPOCHLORITE, CONCENTRATED co \--_---/ REGULATOR/ SHD SODIUM HYPOCHLORITE, DILUTE i H PITOT-STATIC GAUGE SET SIGHT GLASS UW UTILITY WATER LE V VENT I LEVEL (ULTRASONIC) FLEXIBLE CONNECTOR .' W1 NO.1 (POTABLE) WATER D FFLCPLLLX W2 NO.2 (NONPOTABLE) WATER -� D kilo- VORTEX METER �� r PANEL CONTINUED rj \ �� ON SAME OR OTHER Fl ROTAMETER TOOPULSATION DAMPENER A DRAWING ROTAMETER ° LEVEL (BUBBLER TUBE) PANEL OUTLINE NTS PANEL NAME VERIFY SCALE '•'•'° FILTER LTE R ❖.•. BAR IS ONE INCH ON —Morifil—D.- THERMAL FLOW METER LS LEVEL (FLOAT) ORIGINAL DRAWING DATE FEBRUARY 2026 PROJ BPO0152J DWG 01-G-0022 SHEET 9 FILENAME: 01-G-0022.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:58 AM 1 2 3 4 5 6 SYMBOL DESCRIPTION SYMBOL DESCRIPTION SYMBOL DESCRIPTION SYMBOLS DESCRIPTION O ONE-LINE DIAGRAM-1 ONE-LINE DIAGRAM-2 CONTROL DIAGRAM-1 CONTROL DIAGRAM-2 > L _ w U) LIJ << n >> DRAWOUT AIR CIRCUIT BREAKER, LOW VOLTAGE « >> DRAWOUT POWER CIRCUIT BREAKER, MEDIUM VOLTAGE 0 0 PUSH-BUTTON SWITCH, MOMENTARY CONTACT, CAPACITOR u) H NORMALLY OPEN i 0 n CIRCUIT BREAKER, THERMAL MAGNETIC TRIP SHOWN, <-�- I I H> NON DRAWOUT FUSED SWITCH, MEDIUM VOLTAGE n I n PUSH-BUTTON SWITCH, MOMENTARY CONTACT, I BATTERY 400 3 POLE, UNO 400 225 NORMALLY CLOSED Q co n CIRCUIT BREAKER, STATIC TRIP UNIT, SENSOR AMP «�� I I H �> DRAWOUT FUSED SWITCH AND CONTACTOR, MEDIUM 0 PUSH-BUTTON SWITCH, MAINTAINED CONTACTS WITH 0, ,I2 LIMIT SWITCH, NORMALLY OPEN, CLOSES AT END CN AS AT TRIP AND FRAME RATINGS SHOWN, 3 POLE, UNO 400 225 VOLTAGE -- MECHANICAL INTERLOCK V� OF TRAVEL m A AF or AF « > DRAWOUT FUSED SWITCH AND VACUUM CONTACTOR, OQ6 LIMIT SWITCH, NORMALLY CLOSED, OPENS AT END > O o /1 400 225 MEDIUM VOLTAGE OF TRAVEL Q Y O CIRCUIT BREAKER, MAGNETIC TRIP ONLY, O 100/M TRIP RATING SHOWN, 3 POLE, UNO O 3 POSITION SELECTOR SWITCH MAINTAINED CONTACT >- Q < DRAWOUT VACUUM CONTACTOR, MEDIUM VOLTAGE o TEMPERATURE SWITCH, OPENS ON TEMPERATURE RISE m -c-"---I I I I- CIRCUIT BREAKER WITH CURRENT LIMITING FUSES, MEDIUM VOLTAGE CABLE STRESS CONE TYPE O TEMPERATURE SWITCH, CLOSES ON TEMPERATURE RISE 400 400 TRIP AND FUSE RATING INDICATED, 3 POLE, UNO TERMINATION, OPEN TERMINATOR OR ELBOW OFF HAND REMOTE SELECTOR SWITCH - MAINTAINED CONTACT - CHART o IDENTIFIES OPERATION WHEN NEEDED FOR CLARITY w i>_- FLOAT°S) SWITCH, NORMALLY OPEN, CLOSES ON Q -I I I SWITCH - LOAD BREAK, GROUP OPERATED, I- W U) FUSED SWITCH, SWITCH AND FUSE CURRENT RATING POSITION DESCENDING LEVEL 0_ m 400 225 MEDIUM VOLTAGE w o O INDICATED, 3 POLE, UNO CKT HAND OFR - CLOSED CONNOTE m CL Q il 1 _ X O - OPEN CONTACT O Q = -, 100 SWITCH, CURRENT RATING INDICTED, 3 POLE, UNO �� p p 2 O O X O FLOAT SWITCH, NORMALLY OPEN, CLOSES ON = o — SWITCH W/ARCING HORNS, MEDIUM VOLTAGE RISING LEVEL �o wI= I II FUSE, CURRENT RATING AND QUANTITY INDICATED >N 60(3) DISCONNECTING FUSE SOLID MATERIAL, z w MEDIUM VOLTAGE OHO TOGGLE SWITCH, ON OFF TYPE PRESSURE SWITCH, NORMALLY CLOSED, OPENS ON O Y o RISING PRESSURE > O zQ 1 SWITCH - HOOK STICK OPERATED, SINGLE POLE, ON OFF O PRESSURE SWITCH, NORMALLY OPEN, CLOSES ON W o z �OC� MAGNETIC STARTER WITH OVERLOAD, MEDIUM VOLTAGE RISING PRESSURE Q i- NEMA SIZE INDICATED, FVNR UNO m Q - c �'1 FUSE EXPULSION, HOOK STICK OPERATED, O p SELECTOR SWITCH, ON OFF TYPE O FLOW SWITCH, CLOSES ON INCREASED FLOW 0_ LJ VFD ELECTRONIC STARTERS/SPEED CONTROL SINGLE POLE, MEDIUM VOLTAGE I o H RVSS - REDUCED VOLTAGE SOFT STARTER wo O O FLOW SWITCH, OPENS ON INCREASED FLOW i VFD = AC VARIABLE FREQUENCY DRIVE _ D_ DC = DC ADJUSTABLE SPEED DRIVE O GROUND SWITCH, GANG OPERATED i RVAT = REDUCED VOLTAGE AUTO TRANSFORMER TYPE O n MUSHROOM HEAD PUSHBUTTON SWITCH NGR NEUTRAL GROUND CURRENT LIMITING RESISTOR p Z W B RVRT = REDUCED VOLTAGE REACTOR TYPE Q o -O TERMINAL BLOCK LUG \ / z (,)d,� J Q A INDICATING LIGHT, PUSH-TO-TEST, LETTER RES CALIBRATING RESISTOR < ZLLJ • DELTA CONNECTION -0, INDICATES COLOR H o CABLE BUS OR CONNECTION POINT pw w (GD TACHOMETER GENERATOR ~ z a CI K KEY INTERLOCK '4 WYE GROUNDED CONNECTION, SOLID GROUND A INDICATING LIGHT - LETTER INDICATES COLOR Q o i \ A - AMBER G - GREEN S - STROBE Z 0_Q B - BLUE R - RED o SURGE ARRESTER (GAP TYPE) WYE NEUTRAL GROUND RESISTOR OR IMPEDANCE C CLEAR W (I) z WHITE GFS GROUND FAULT SENSOR z z R or Z CONNECTION z o ( 10 CAPACITOR - KVAR INDICATED, 3 PHASE ETM ELAPSED TIME METERC&D o w w 0 02 FLASHER 0 Z 86 RELAY OR DEVICE, FUNCTION NUMBER AS INDICATED • M • MOTOR STARTER CONTACTOR COIL u_ Q o 30 AC MOTOR, SQUIRREL CAGE INDUCTION - I I SEALED CONTACT O 0 u) HORSEPOWER INDICATED • CRx • CONTROL RELAY, X INDICATES NUMERICAL ORDER > 0 w = m IN CIRCUIT 50:5 F CURRENT TRANSFORMER, ZERO SEQUENCE, RATIO riV BUZZER co o OO co O 0 o G GENERATOR, KW/KVA RATING SHOWN AND QUANTITY INDICATED • TDR • TIME DELAY RELAY, X INDICATES NUMERICAL ORDER O w w H z (1) X IN CIRCUIT Co Y z w 500/625 POTENTIOMETER w O Q D z SV SOLENOID VALVE,X INDICATES NUMERICAL ORDER w w Q VS 800/1200:5 Y O o m BUSHING CURRENT TRANSFORMER, MULTI RATIO X IN CIRCUIT O V ANALOG METER WITH SWITCH - SCALE RANGE SHOWN AND QUANTITY INDICATED Y Q _ V = VOLTAGE KW = KILOWATTS (3) I I CONTACT - NORMALLY OPEN RESISTOR U H 0-600V A = AMPERAGE KVAR = KILOVARS PF = POWER FACTOR MO MOTOR OPERATOR, BREAKER OR SWITCH H C / CONTACT - NORMALLY CLOSED Z D 4-elBLOWN FUSE INDICATOR O EUM ENERGY MOUNTING UNIT DPM 0-I=IH li=l- DEVICE o DIGITAL POWER METER (MULTIFUNCTION) MRP MOTOR PROTECTION RELAY w D 0 )i TIME DELAY RELAY CONTACT, NORMALLY OPEN, COAXIAL CABLE L Q UTILITY REVENUE METER HS HAND SWITCH, ESTOP Jl CLOSES WHEN ENERGIZED AND TIMED OUT °T° TIME DELAY RELAY CONTACT, NORMALLY CLOSED, BREAKER SHUNT TRIP, 120VAC COIL, ENERGIZE TO OPENS WHEN ENERGIZED AND TIMED OUT MULTICONDUCTOR SHIELDED CABLE GROUND ST REMAIN CLOSED = O TIME DELAY RELAY CONTACT, CLOSES WHEN ENERGIZED, OPENS WHEN ENERGIZED AND TIMED OUT 15 KVA DPM DIGITAL POWER METER 480-120/240V I TIME DELAY RELAY CONTACT, OPENS WHEN ENERGIZED, DUPLEX RECEPTACLE 11 J 1 PH �M�J CLOSES WHEN ENERGIZED AND TIMED OUT U TRANSFORMER, SIZE, VOLTAGE RATINGS, I AI AND PHASE INDICATED X% O Lqj EE REACTOR, INPUT OR OUTPUT OUL-O MOTOR SPACE HEATER l.Jd_AJ 0 V w U O SHIELDED ISOLATION TRANSFORMER O) RELAY WITH MECHANICAL LATCH CIS Co w LLI J DV/DT DV/DT OUTPUT FILTER O TERMINAL BLOCK, REMOTE ') J w 480-120V 3EPOTENTIAL TRANSFORMER, VOLTAGE RATING 0 TERMINAL BLOCK, INTERNAL FULLWAVE DIODE BRIDGE (AC TO DC) AND QUANTITY INDICATED -< )- (3) >-D FUSED TERMINAL BLOCK CURRENT TRANSFORMER, RATIO(100:5) AND D 100:5 E(3) QUANTITY INDICATED (3) NOTES: THERMISTOR I II FUSE, RATING INDICATED 1. THESE ARE STANDARD LEGEND SHEETS, SOME SYMBOLS AND ABBREVIATIONS 4 CONNECTION POINT TO EQUIPMENT SPECIFIED IN OTHER MAY APPEAR ON THE LEGEND AND NOT ON THE DRAWINGS. , �T DIVISIONS. RACEWAY, CONDUCTOR AND CONNECTION ����'"' j 12" - 1' 0" IN THE DIVISION 2. FOR ADDITIONAL ABBREVIATIONS OF OTHER DIVISIONS (HVAC, MECHANICAL, AND TRANSFORMER, CONTROL POWER - STRUCTURAL/ARCHITECTURAL) SEE OTHER LEGENDS. �rWl VERIFY SCALE XKV 120V -s •--i I I MEDIUM VOLTAGE SURGE ARRESTOR 3. COMPONENTS AND PANELS SHOWN WITH A SINGLE ASTERISK (*) ARE TO BE BAR IS ONE INCH ON ORIGINAL DRAWING. PROVIDED AS PART OF A PACKAGE SYSTEM. THERMOCOUPLE 0 1" SPD SURGE PROTECTION DEVICE 4. COMPONENTS AND PANELS SHOWN WITH A DOUBLE ASTERISK (**) ARE TO BE DATE MARCH 2026 PROVIDED UNDER DIVISION 26, ELECTRICAL. PROJ BJO0152J DWG 01-G-0023 SHEET 10 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/25/2026 10:15:37 AM 1 I 2 I 3 I 4 I 5 I 6 0 w cc w w cc H I E J J cd O (N CO CO A 0Z ° O Q Y O 0 >- < m Y --I I I I --41 > o L 1. 11I Q wL.Lj 036 I I 1 I Ma< w =LL � � - I I 1 Yo 1 . I I IOf 7 Tlt , l 5N N_ I Z CtCC w Q Y �O 1 ! - > U zQ 7 1 - w J °Z 1. 1 m w I- woCe ��_ [I I / 0E aw rr I , Luo I- ll-r I strati �_ I - 1_ l I I °n 1 o Zw Be 0 - _ 7 I 1 1 I - Z I m zw w Q I w = � 1 I � �� Irtfttivt. t 1 I I'- w �, w° F I I Luz I I Z I_ I I I ', 1111 ._ o1_ I .� I 11 '� z a zZ• • 11 r' 1 CO Ce 1 . . --1:_r? ' I I w0 i I :06 zQ w m�- III m O 0 $ a > O H-. O J : Q I u) w u_ o� O O OM .f,' w Q H =O Q U ~ � J i H Z C W 2 w 0 W U) D W CC O z CI J_ D m 11 z Adi z O o E V w z Et ( m H r7 z 2 a Q 0 D N— VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0050 SHEET 11 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/23/2026 8:04:10 AM 1 I 2 I 3 I 4 I 5 I 6 0 w > cc w (/) w cc Cn H I E J J cd O N CO CO A _ 1 .-uli . •-. • ... - 0_ zO L. ..1 _ • • • Q O U • J • 1 � .rte v / , `is' le r. 4 I-..1'.. , �.1 ,', ! ' ' l i j` - � 4. >- Q m Y ! ,. ftr i a __ _ � 111 119 i- .4,4 Q , '! Et .. L.LJo O � '� d Q I . W 2 IL Ho lemriPill' co U Q I r� - - 1• ) z w� 6 ,I IIIILIPII. _ W y o¢ ......___,.3,1 1. J-_ IM W (H! mw~Ce or r", r .rlir ' cono�Zpwr ��,, coNTRo . o zw B _ t STORAGE J Et ±; w Q CC 4 , • I M Z LLI i_ct ELECT JAN RR3 H _>- 0 Z SERVER <<O 0 O 2 o LOBBYiiiii.hinrIRR2 zCe zO w ow(o� a. I. I I • A 1,4 (, w w O W =m , 0 O zo I A _ a w O H , V „ 1IN I I � OJQ _ _ W LL U 1 ' O O p CO - I 1 IIII _I COfist FE ' EiPI' . I ROO NI ti‘. 1 z a i v MI!CH WOI BEA1 P OO LLJ CO 0rF �- ir Q F ,- r- CC lk___" . . 4 _ ___ _ o . lir - \ Vl z miaz 0 o z V W z Ct al w r7 co z 2 a Q 0 D N- VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0051 SHEET 12 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/23/2026 8:17:45 AM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc H I E J J cd O N CO CO A 0 Z O O Q Y O O >- < m Y O w O O a Et W a0 CO w� HO Y cnz — O U~ N z Ct CC 0 cwn2 \� > U Z¢ � W O Z �. � mwI- \ cn wH O - wO c ~H p Zw B • Maifl0a1 wzw I .a W cn = c } Qo z - O C) a Z 0< O zZ , I j ct z00 �41111, ?w w0 0_ Z Qz H ww 0 a - LU 0 w =m O > z0 O O <0 Z W iiiim 0 zci) LU L.L.I U) <jO J Dz U) W LL U O O Sm Y Q H w6 Q U H - J H z C I w 2 D U O 0 w O w U) D w 0 z 0 J_ D 1 m Aiii C) W Oz V W O w z w r7 F- z Q 2 N N- D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0052 SHEET 13 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/23/2026 8:19:23 AM 1 I 2 I 3 I 4 I 5 I 6 0 w > cc w w cc H z O E J J cd O (N CO CO > Z o A O _ - Q Y O _t - O .e >- < _.. __ m Y 0 Li_ d O a ~ 1 aOU . W 2 LL — w- Y —WI-- z _ O UQ N Z 2 dir 1r r -N,111 __. _. Q Y WO rI �� � w U `Q r' r✓ t 'r w ni- J O � � A w l-c6-Li r � o rr , • wo ci_ i_ l_ p Zw • B ,_ Luzo f m a�_ ir iIt >p \iih1/4\14041‘1110H,. e. - E E W w O iii cn oz J ce LL z o c. 13- Zz \..) ‘ r 10CP 0. u9 6<, \� � Cr . cow < — + z0 •� -J� J (7w , 1 I azz J r. QZ I- ww , 0 o 0 w =m 4 Et O 0 zHH �1 0 o Qo ° w W zczi) f6 W Q � o Iry r • 0 LI Q o Sm Y Lu Q � =o Q U H - li t 0 z C w rD O w O w U) CC Z 0 D m — 11). ° W o z Z V W 0 CC w z w w r7 F z Q 2 N N— D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0053 SHEET 14 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 11:11:24 AM 1 2 3 4 5 6 0 w > L w w cc H I E MOTOR INFLUENT JUNCTION ACTUATED STRUCTURE N FOUL AIR MOTOR ROCK TRAP GATE m , TYP o Z o A ACTUATED MANHOLE ". ° Q Y O GATE _ O Tv., >_ Q Nliriftimmium--6-- . .-•,..... - -- Oillilli • ' wWETWELL 1 AND 2Q NS'cli PUMP PIPING AND — — fl w ei• LLJ � �Q VALVES 1 la �o 1% iLL c�z _o w � U Q N_ • Y �I • ,� Z t \I • w (n W • � 'ter ���`~ ! '� ` ELL � � : 4 )4. O TO HEADWORKS • t - 1r 4 ,__ . . w ; PE 4.44 • --- • . . DH Ail\ -� `' �.jorpe 0 zU z � B \ 4, i �` 1 ii\ J Q o f _ � . wQa \, - t : CO z w v w 2 it /�r / w w ~o ice_ , ) , 0‘... ' I Q U) p z H CC , ,.,,,,e. r , , , ,_ „ : .. . ...•›,'N\N„,, ____ ,_ ,, 'N'NN --- ,\---,c.......-------------\--dl - : .., ,t,„ �' „,„ , ,.. z.. 4, , **1 - - - % 4 „ozzz0:zo- w i . . _ 0 - - . , filk Wd AIR INTAKE Wu) O a . O w = w - m 0 O > ❑ � w O Qo H let 5z O ( - - Oil : I ' CD LLI ° J Dz - i, Jl w LL J - - O Q O o,co 14r (Th ' NI U Hg c) H z C w 2 - TRYON CREEK U O IL Allv .. CO PUMP PIPING O 1W - . Li_ O 4,--4` AN D VALVES I' ,' - 4 ' Z RECIRCULATION Q LINE FOR ~ MAINTENANCE V� o_ Aii ° 2 o z E ha a --milaill* CC r' w D J LL Z 0 N D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0054 SHEET 15 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 4/1/2026 8:10:10 AM 1 I 2 I 3 I 4 I 5 I 6 0 W > cc W W cc H I O E J J co O (N CO CO A O Z O O Q Y O O >- < m Y PUMPS I WETWELL 1 0 > W Q i i Wco W W m 00 [Q W -) wHo Y Cz o W E ROCK TRAP z 0N = o Y �0 i = QII > 0 zQ w oz J W U)H .4 CD w i WOE ., O W WH0PUMPS ~ ilj w _ -_ inc � � B - - - . J p ti `,.` wo- w Z lIllr____4‘'1/4 0 WO W O W II LIJ H CC Q <0 - E 1INFLUENT JUNCTION —z o I - -, STRUCTURE ° u9 W z a O z wW z0 1M wO . 4e \ z - Q i- QW LLJ 0) 0 ow O w = m m o Ho o O w O Qo z 111 • .I LIJ O � DZ (n W w O O O am III w =O J H z C _ W 2 D 0 WETWELL 2 4f: ROCK TRAP LIJ • W CC z • O *ilia A F Q .. •• .. I co VI 0_ .0 2 0 E Va CC Lu z Z r, w D J LL Z TRYON CREEK WETWELL PUMPS 0 N D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0055 SHEET 16 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 1:24:09 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc H c_ ROTARY DRUM THICKENER J Q O N CO CO O A IIIIIIIIIIIIIIIIIIIN O Z > O Q 0,,,„„„4,„,„,„..4.0,... .._ _..., < 00, ,„„ imili„,„,„„„iii >_ co Y elftimmis W.'— 0 0°i 'Aimig Mitt a GRIT WASHEREt Cci '' ------ HORIZONTAL CONVEYOR Q . i0404:0°.. 1 1 ": i • -....,,,... ' w CL co O o — , or ,, _ - ---t - . I Ycnz VIIIIIIo I wp_ 1 SCREENS UQ N Z w� O pz 41\ • !„.,i. r, 4Pri 1 .. iti Lw U r 'f m w i- w_ w0� ce - - - I, , w0� ,.. MI.4 • 164. =I- , , _ , - '0 . IP ~. ; . w ,_ _ , z_ _ a _Lu •B ti • r , _ �� Zo lot'A" m \\ / , W z_W r W 2 / W W Illik Ilk:,.. ...,.,, , e d i r l r ry_ Y , =,rte Z U) Oa •:.. ...r t 1• (nL.0 J Qz ��y�'j1����1` `�\.� 0 iii 1 CO •`= 0 I— ````````� O Ur O ZQ~O ```��,f. O W zc� • w — i ���` W O J 2 m ~, u) W W Ow — O O pm Y Q H =0 Q U ~ � J z C w D U O 0 Li_ O w OCO Z tY w J 0 Z Q CO Ill a Rz ° w Cl) V O v, CC z c '1 o 0 Q w I D i L() N VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0056 SHEET 17 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 1:58:06 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc H I E SLUDGE STORAGE TANKSzs N CO CO O z n> O Q Y O U GRIT EFFLUENT CHANNEL m Y O > w GRIT BASIN HEADCELL Q wCO w oo U) 0Q m w4 —3 W Ho — z o wE U Q illr Z w � O Y �o iMil • (7) i w U o¢ Et J Z N W �� 111111116 eDp w H . . ) in wO> Et O u) wp ww H •r" IL z � W' U " O B zo z J :0 W Qa CD • w zw � �O GRIT PUMP W `D _ } � (n oz Q F "� Eo —z o IP --...momMilliiiiii II H �o wo N o z Qz Wo lhiiillMmwm..._ u_ i— ww O a fl w LULU m O � Ho� y 0 O O Qo in O a H O Y zw w - 11 W O D Z Do ow,- fiX 1-1 W LL 0< w0 . , ._ 1,,,i, i O Y O o m U sail • I z 7' o p Mn fIlk Ill o w ammo • Z - Q -EadroilailMillill&- Illir - 0 I — 2 z _, o ° w V 0z co ROLL OFF CONTAINER SCREEN CHANNELS Cti w ') O 0 Q w I D i L() N VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0057 SHEET 18 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 11:44:57 AM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc H I E J J cd O (N CO CO A 0 Z O O Q Y O O > Q CONCRETE COVERS WITH ACCESS t, ' r o HATCHES FOR MAINTENANCE ACCESS ___ r - --_L ,E...., . Q o If.:. ,IJ j 1'1 T. / 1�_ I !/.i �.� ct Min - ill' rlan! u�Z jct N 1 i \t k.D I*1 . O l&151 O 1 jegiciP041: 1 I 6*:nr-' / C7.* :& (7) 2 -I il \ 1 t4.646 ...:, .0•00.04...... .,,r, j\.... ..1.141641 ...../...91 � W W H ! fP 4 w o ct. 1,,i - -.4 (,,) 0, ___.-f-: .-,,., , r, i k. — ....,.�` O , wO C ►� 21 ro.t.44r J - • H • .k tB �1 .7i • .> _i ct w a� Z v 1•1W w 414141%ra< • / 1i. E El - r - w (9w___ ‘4g. g - 0 ---1 . < . w< ,_,,, ...., <0 ��. ___ , ..yes 4. .. , .4% — Z Oce- 41/4 6 1 Op. u9 0 Z ` `f it U ,` p ZZ • �, I '� ` w o , _ J • �' , -- f— co d `/// Q Z u) , . , O oD G • - O w 200 'NI .. m O co O H N . a W> O QO F O > W Z(n . O DQ % u) LJJ L_ U k // O Q O 8o W J >- wU Q U I Jn•C , r- .. D O O AIR PIPING, TYP w CO w cn Z ) __ _ . PIPE RACK SUPPORTIll m mia z Z Oc? V Z HCC Lu Ct r' w w Q 0 co D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0058 SHEET 19 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 1:59:43 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc BIOLOGICAL FOAM CLARIFIER SPLITTER EFFLUENT CHANNEL BIOLOGICAL FOAM co _ PIT BOX PIT J Q cd O N U) CO z O A � I O A Y O Q . O 0 > w W O a i CL W • . • w 00 AERATED ZONE 5 1 ) • . . • m w� • LLJ it -_Z — o wE O • • A j N z W 0 Y �2 QH L>LI O Zo J Z in (6 H [o w l— W irycn o d W w w � O AERATED ZONE 4 H Z° i- W =- 1111 !Mili B — IIIPIIHi 0 Zcol- Ct J W Qa • • • CO _cC LLJ Z w c I • r ' T‘;._, w T r . Q o . CC <O AERATED ZONE 3 o 0 II 0 w _ _ - .II=I.-i. W Q o Lij • O OW S) SELECTOR o w = m ZONES1 -4 ~° • O O Qo z O W zw U . .II Y W O J 0 Dz u) W w O(n O O am Y Q =o Q U � � J Z C w ° O - I L O d w D tYW I ' ) -''IlligliMOMMIIII ‘4r1L.Dlee' Cliialaillilifiliglialifft if ' --- ---- - - . . . . . . _ „awsjo 7 t . E IiIIIII � _ >> �1� Q _ -,- = o z z cci 111 � � � 11 �O Q LI O FF . CO W Q i r, w Q 0 PIPE GALLERY D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0059 SHEET 20 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 2:04:50 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > Ct w w CO CO H I E J J co O (N CO O A 0 z o 0 O Y < O O > Q 00 Y - lk, Zit BIOLOGICAL FOAM PIT w Q i i w w EL U) 0_Q Yw10 �z _o wE REMOVABLE COVERS z Lt C FOR MAINTENANCE ACCESS ° 1 -JH � _ > zQ 4IIIIIIIIII%%%0. w oz Et J W co, DQ w H -� in w0 Ur E dw u) OH + Z /../.. LL O / 0 Zw B z `�-� may,' W4414%Ill , , / DO W zw o # . w 0 w z 44414%‘ ,,,4iill ' lliiiiiiiiilipDiHp7- illbP.-....io, ... H co O Q o HL <O —� 0_I- O (1) O� O 0 zz �♦ 7IIIIIIIIP,.. - - �oww0•1 . D2� z Q - s W Q o I- Wu) a lirk. - Ct O w = m _ EFFLUENT DROP BOX ° 0 o o w z� -1, .- �j` __4,0 . w..„„„ W 0 < o r W LL 8Q O Y O om REMOVABLE COVERS H Li*IDHIDD, ♦ Q Y J I- iQ J U FOR MAINTENANCE ACCESS H z C w O O . w i. O w D "14- / Il likk N• 411P/_ w z Ct minE_ o IY fl Vw 0 Q w r7 o co RETURN ACTIVATED SLUDGE PUMP, TYP D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0060 SHEET 21 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 2:06:42 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc H o EFFLUENT DROP BOX RETURN ACTIVATED SLUDGE PUMP E J J Q O 4 CO N W O Z O A V* 1 :• ....'---..'-'..'-'-'-..-1-• -Ol > O Q .. .. t• .• f• Q Y O 1 ' U • LAUNDERS m Y v- r— EL— i rm. 1”P w � O ■ w wwm 1 I Eat mum on � o0 uIIIiIl . cn 0_Q m w � w �O ' r w ~ UQ Z L p = JO 1111.111 I ■ w O Oz J w (4 i- mwH LLI O I (Y w 1 u) wH 0 H � zI • ,i ll s • I 1 2 1 I C i L i . D- _ ■ IC Z U . . i I W LIJ Cl- Lrj z; i . l' ' Li j w ii. I I � $o Q ° Q l<1 < 0 �o N: O O 1Q 1 Zcn �w O Zz_I ' I ill II y►e wz or: f. 4 H NW It LL U)o i- < w 4 • ' O o� pL�LI = m p �o co O O O Qo S lilLa."114 i I O w z( lil1IlII w J 20 1 D 11 I 0 w LL UQ O Y O om I w Q } UO a , � \I c� z w U C a � O 0 0 6, , 0 w O w ., 1 CO LLJ, \1 \ ..e — 2. i lirl_.fili lir / Irt . ! 1.-- ..._ 1* I \ iminilliii. \ in Ct -- --, I i •- r , . .lii MP lr min (.9• o w fl V O < 0 r7 0 BIOLOGICAL FOAM PIT D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0061 SHEET 22 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 2:07:29 PM 1 I 2 I 3 I 4 I 5 I 6 0 w > L w w cc co H I E J J Q cd O N CO CO A O Z O O Q Y O I O EFFLUENT CHANNEL DISK FILTERS m Y 0 > W a H w w oo U) 0_Q [Q W -, wHo w _O W E UQ Z E O Y u° = Q H > U ZQ w oz CC J W4( H - _ - _ ._ _- -_--__-__ _ m WI- c _ �� _ _ _ _ _ - _ _ _ Ur d W W H O �' _ I§ -�-T Z B . ‘INI! AI:\ . ' ' _ _ _ __ __. __ • _--_,.... - ..,- .. . „„ in Z LE 4.�`lk No NI. L N. Ni. •i♦'♦'`o,♦'�/,.0.\S♦/7\`7\6�0��� w (r w ` Or .00. ii / / / / ii / / .� idid � � o LLJ H � / /v/v. ilk N. N.de 449 de de /♦/\fN/♦/�/t/♦ �/♦/��,♦s�/�d�.d`d♦ o O N. N. N. ♦ t N. N. N. < or IN./r ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ -doe doe dr ooe se se sir 0_ I-- ‘‘ IIIIIIII. 11, `r♦f♦/♦/\/�t/♦/♦/♦/♦/♦/♦/♦/♦/`t/ 4110 NN, Nhr / / I, / / / S / / I / v / zo �� ►' � e j Irper/♦v`�/ej de j♦Or Ir u?w v'���/`vim/♦/�N. /`t/t/ o 49 40 z z ���''`�� INFLUENT CHANNEL LL <o . I.\ se H LLJ O) .�. O O CD LE LE w 1 CO O m O o o ff 1� w O Q � O w I- 0 u) ICI Z I' Y w -LU U)Ow. O Y O S m • .' ‘ / I , : H ICI l-1 C W N rir\\ 0 O• , LLJ ' -' ‘N 0, .. , . I . . ' 4 \ ,V\‘. \\Nilire in,,,,,,,,, O , . _ -- !. . ,. ... (....D .. . . ... o z V Z J ct LL PUMP GALLERY '' o Lo D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0062 SHEET 23 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 2:08:29 PM 1 I 2 I 3 I 4 I 5 I 6 0 W > L W W cc co H FILTER EFFLUENT I E J Q co O N co m A _ - • _ -- , -- - - _ — - • - . - WEIR, TYP ≥ Z . Q � o co 2 Fey ►i r�.� + r .• _ 10 _;.r o Q { , CL am < mw-' -- :.7 > W Io co z — 1 _ w H U Q - . , - N_ — • Z (2 CC . O Y U)O . • , U) I ¢H .. - w O U Z¢ J Z 1 LU W wH DISK FILTER, TYP E a= • o1- I- . wO / / l ----'.1......... .n..... I— I— Ce o Zw B - _a -'iNIIIMEMEINNINIIIIftia, • • Zo Q ct ...„„„„„,... .....,_ _ m a a� a� O w =o H (/) o Z �O•— V O pa \ . 9IMIIIMI NEMII= Ili , , Z oCe � w IIIIMINIMEMI II w O 0 2 �� t•� 1 Q Z �� .; r I- w co W . x �; !1 O w zm . O . O > H O a O O <O ' - O w IZ U Y z(L)w O < � o w w 0< O Y O m p • w Q >- =O • Q U H - . J•3 - 1 ., , ' - . _ ` (n " r . • • - z z ■ Lli I y D U • 3 O U- 0 Y • t ��M��S `r��M �M)r w " ---. v tY •-r�r. ► NM _ - - - PUMPS, TYP z Vli O .0:r. • o w 12 - V I, a J CIS w LL ti -��_ r' • - , . • . of o Lo D PUMP GALLERY VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0063 SHEET 24 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 2:09:34 PM 1 I 2 I 3 I 4 I 5 I 6 0 w L w w cc H I E CANOPY FOR CONTROLS cd N CO CO Z O A Q Y O O >- Q CO Y 0 w d t a Et W a0 CO w< HO . cnZ O 7-IIII-1 U~ Q N Z ft CC O Y cwn0 0 z? i=iiNit W OZ -� WI• II17 :-.6.171:17-1141H °r�������1� I— I— illIP°6246 . - . . 2 1 il .tit, ,\‘ w coo_ -_ 1 I a . .4 .4ww Z2 4A41141111 -i--z.IF,ri.,:frrP fill hir- x .-, .- - --- $ LLI y -1- , (,) az . .< ,_,:, 7- •,2 4, , Z• cn H _ , • .,_•,_ !.- ,, W w0 0_ 0� Z Q CO H H O z0 0 0 p Qo z OO Y H UV CHANNELS w o J � o u) w u_ o� O Q O ao CONTROL PANELS Y J i- E< 0 H - J H z c w D 0 0 O w 0 w U) D w Z O H row U All C.0 Oz V w z al w cC o r7 > D V) V) D VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 01-G-0064 SHEET 25 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/GEN_RVT2024.rvt PLOT DATE/TIME: 3/31/2026 12:00:08 PM 1 2 3 4 5 6 � /7/711)14.):1 )% 1 GENERAL NOTES / o 1. EXISTING GRADE CONTOURS ARE SHOWN AT 1 FOOTw\ CONTOUR INTERVAL. wco / cc / \ 2. ELEVATIONS ARE BASED ON NGVD 29 VERTICAL =o\ DATUM. E / NO SHEET KEYNOTES20 - INFLUENT PUMP STATIONN 14I.Ju) 21 - ODOR CONTROL `� / 1. NONEoA 22 - IPS ELECTRICAL BUILDING / , 1111111 O p-.; • IEXISTING TRYON CREEK � � } Q 2s PUMP STATION / o /�� °0Y 3p 2 p/,,3� 3 � �/ �` ��� I i� J . SEWEF DROP STRUCTURE `'� \ g/ _ .A1 , �������Aiiimilmii wry/ Q it CC 60 - TRUCK LOADOUT 3• � ���-�Id, H -o / -....../ i I 'Milk i44 IC"' 1:41111 -A;r � '1 w w� trAll</-- O ��N4slii4_ 1 ( (‘I\' n/ a Y -Z I 0 ••••.__ 4 _ ` //* EFFLUENT JUNCTION STRUCTURE I I Z W Tom- 2 rio-r ----- --- 1 Pc ----'' -- -'-- _ � \ i > � (In: o 26 - ODOR CONTROL 1�— Iti ��\ --�-i � Imo`�� �' �; � w o El 12 - MAINTENANCE iii ihul �„ ► ���, wr cCE BLDG ;-� r =��ii����: �,��Tr,,--- 5 ILij, '� o� IIIIIIIIIIIIHDo I�/ wo o1IW -�► 25 - HEADWORKS/SOLIDS HANDLING •� I, / // Li �_ 'Mg , // • III �,�� II �� �i 1 ' col—a -w B TA 50 I I — n a( ' k flf w z // 111111 w O ,,, Z w O t. I • ,.- , LL.T...„—I ---L ---____._____...---. 41He, ,,u__ . _ �I Z :.! 55 - UV _� 27 - ELECTRICAL BUILDING 50 - DISINFECTION I _o �litlp.---. au)_, AND GENERATORS FILTRATION o I 1 �1� `. -...., • • • • •I4 P Q z \\ �� (,)0_ w cwn , i il k O 11:\ a)C3)C) :2 O cn \ , \70, 0 0 O aZ LU I o z: . . 6 ,NA..-.."' . o o Ua O CO � 1lir . i-u:vim 1 35 - BLOWER CANOPYC I 1 A ) Jpir i • •I ` o 40 - CLARIFIERS i IL . . . • I " Iii0 0 \m44:.' `� °II30 - AERATIONI BASINS fl 1 I It 1iii I il 41 pir ilwio..... ---_,„,„liiH . 1 LLI 1 N\ksii‘N C55 \N Illti 1 1 I i 1) 1 4:'I -- 0 it--1 I i k-411- I 1 lThil %-II - , \vi 1 A _...iil,'""- 30 7N1 ._..;,..„----1 ,. .. ., . ;00iiiijorilligilgal-s.... -Ilk 1 la i ADMINISTRATION c~-n JAi . N ‘IlkS44Diaitikii ! BLDGoreovidigi 00 ___ -- -,_- ___\ , : - 1.1-411*:N's up, i� � i.r I IIIIQ _____Ar----. 1014 e• ..,,,„. s„,.0-- ‘ ..-- _-- _ ..,--- e..: ' . T.,__ ,,..„.... —...... ___, .. ..*,,,-.._,..„,,,-,,,, , vial „....,_,____„_:,,,,,,;.:0,,,_„. .„,_ _ 4,,„_., ..„..., ,,,,IlI / / [ :) pi/ nT•i i i *11410 ,„,01,1,041,— r i I ' 1.1 s f _.,.. \ 1 7II cciilitl,4ss, t i' "ti ( _ _ <,q4 ,0> / °P N CD1 - 50 VERIFY SCALE L= I I 1� BAR IS ONE INCH ON CC L1� 1 MAIN ENTRANCE I I �� ORIGINAL DRAWING. Ilit / I ' 0 50 100 150 0 1itiff I I i ■■■■■■■■■■ DATEMARCH2026 1'‘ - ... 1 , 1"= 50' PROJ BPO0152J Ida Art \ \ IIDWG 05-C-2001 gal/A .- / SHEET FILENAME: 05-C-2001.dwg PLOT DATE: PLOT TIME: 1 2 3 4 5 6 lityli, � GENERAL NOTES / o 1. EXISTING GRADE CONTOURS ARE SHOWN AT 1 FOOTwICONTOUR INTERVAL. w/ ro 2. ELEVATIONS ARE BASED ON NGVD 29 VERTICALcc cc� � � DATUM. �/ N O SHEET KEYNOTES20 - INFLUENT PUMP STATION 51 • J' CN / % NEW UPSTREAM LAKE OSWEGO JUNCTION STRUCTURE mA 22 - IPS E ECTR OR BUILDING1 `� \ (FACILITY 17) WILL BE INSTALLED OVER THE EXISTING > Z24-INCH AND 36-INCH SEWERS AS PART OF DESIGNIlillia O X �� PACKAGE 2. THE LAKE OSWEGO DROP STRUCTURE Q U/ -- */ � i144/ 1 1 (FACILITY 18)AND EXISTING 36-INCH INTERCEPTOR EXISTING TRYON CREEK STRUCTURE FACILITY 18A WILL BE COMPLETED AS WELL } Q i PUMP STATION o /�`' ( ) °0Y 3 2 /,, AS THE48 INCH PIPELINE FROMFACILITY17TO FACILITY 18. 323/ / � ,, �� p� �� FLOWSWILLTHENBEROUTEDTOTHEEXISTING/ �� SEWER DROP STCTURE ��'\ CONNECT TO HEADWORKS THROUGH THE 24-INCH PIPELINE WHILE � �� / , I Ai/ siivr�� �`� � EXISTING �� �i/ FACILITY 17 AND FACILITY 18A TIE-INS ARE COMPLETED.�� • �'���� � WILLAMETTEi �' I PORTLAND RS \�� � ��/ WHEN THE WORK IS COMPLETE, FLOWS WILL BE ABLE TO Qo i,.� ��� L INTERCEPTOR '� � FLOW THROUGH EITHER THE 24-INCH OR 48-INCH / 36-INCH ce � FA, TYP. � `� � �� ' FLOW PATHS TO GET TO THE EXISTING HEADWORKS. CC w Homo / 60 - TRUCK LOADOUT n�1 ��'` ' r /I I "" I ,�i � � CONNECTTOWHEN THE LOWWTF IS COMPLETE, STOP LOGS WILL BEmaQ♦• %, ire `` .. w0/ CONNECT TO NEW , RS TONEW � � A EXISTING REMOVED AND ALL FLOWS WILL BE ROUTED OT THE NEW w ,��_ � � �� � � INFLUENT PUMP STATION THROUGH THE 48-INCH � �z LAKEOSWEGO � o �� � � TRYONCREEKPS �� ' OUTFACE Y �z �� � DROP STRUCTURE % �' ��� � .„ di �' � � CONNECTION AT FACILITY AND THE DROP IN FACILITY 18. ui o / FACILITY 18A WILL BE DEMOLISHED ALONG WITH TEH �l�-.i (///,..W ../____„__________ i__..../ '�� ' EFFLUENT JUNCTION STRUCTURE I UNUSED ABOVE GRADE PIPING. Z RS TO IPS ;Z % . z -I i 26 - ODOR CONTROL � - - ALLI�� iiiisi��_ �, ifif ° NlllllN /l/ /IIIII� fail E � lillik ���i���o �► ���,.. .. D�� Q U)I- Lii 12 - MAINTENANCE BLDG ��a,, 0 =��in���: �� ,� = f c �i Ce i� Milvii 7 1 �� �,, ` ------. 4-.1%.11-14.1 1, L w a e �e • �I -v ; ,�- • I I I„,, �r 25 - HEADWORKS/SOLIDS HANDLING -y 'llaM k �7 , ?H RS TO �.�t *- '46. ��,' IC "® HEADWORKS ..•' \ _.1� ��I 1 Cz Et It a -w B LAKE OSWEGO RS, 1915 MIL II ilk FE TO EXISTING \ D Zuj CONNECT TO NEW LAKE 91 s - � - I OUTFALL w z zo OSWEGO UPSTREAM I iIIIII JUNCTION STRUCTURE ILI I1I/' - a oa TFE TO • 41 p° BW TO GRITL o _ � EFFLUENTUVA �,hL 0 111111 oa �. 55 - UV 27 - ELECTRICAL BUILDING ■�' AB/WW TO 50 - it ;o '1 FILTRATION �� wo AND GENERATORSi//huh FILTERS III in i I 1 0 1 ��.. I10 Qz ip IABI TO AI ill '- ���_ w w BASINS I 'C\, <O SE/WW L.IFTWI&Iell ii • o° O o cn II 41_- =-\ TO UV m O a o 1 \) WAS TO ®\ -1 i i_-z �' w`� .? I 1 piO co o m \\1/4ii\h\iiii, !Ilizi- SE TO RAS TO A .ii‘k\ ' FILTERS BASINS Ivo 35 - BLOWER CANOPY o/IIII40 - CLARIFIERS `W3 LOOP � % 30 - AERATION IL BASINS w PW/FWQ J ‘01W Aftvilft t Lo o Loom ( ML TO LOOP 0,611.111 �,�., � CLARIFIERS 7�>� �—` 30 /c: .. : 6i N i J. 55 , iiriiiiiiiiiiiii,,,,,,,,,, ...iiiiiiiis_lik --. ail cl_ il It _ mssiiip-m; ...- I ,.., 0:01„,, „----" ,---<0.:00 -7,,,,,------iii - /-z- , I, _-, ,, IA _, z cl_ . A — c.) 0 I110 - JO 1 NA r 1 so NW LLJ ADMINISTRATION L c �i' CONNECT TO CITY WAT Q BLDGA �� Sl*� �II t LINE, TYP. 2 LOCATIONS /I / �` al �� llt C �� RELOCATED I I :4I14k rim) 11 I IllI k 00 • ���' , STORM §‘, ii • Q �� - ��� '%% i SEWER i Et i I LLJ / i I O D „nr....„.105194-0::::15 ,;, - - 'I* 0 �W camWI . �!' CONNECT TO CITY ��� N LINE STN LINE AT � G EXISTING MANHOLE cktrgo,, CONNECT TO � r / 'NIIIIIIIIIi\ > CITY GAS LINE / N 1" = 50' VERIFY SCALE / I 1� BAR IS ONE INCH ON ttittitil 1 MAIN ENTRANCE I / �� CD ORIGINAL DRAWING. IWj I , ' ltalt 100150 I ,���,I �� I / = ■■■■■■■■■■ DATE MARCH 2026 I - �h�I� II 1"= 50' PRODBPO0152J �NAL \ \ II DWG 05-C-2002 I I SHEET �A I FILENAME: 05-C-2002.dwg PLOT DATE: PLOT TIME: 1 I 2 I 3 I 4 I 5 I 6 PLC d w > IY w w IY I- I(0 E J J Q vi N O N CO A j 0 Z o Q 0 >- Q 00 a > w D_ 0 Q H Z Lu w o Oa m U) �O I aO < wa LL O O Qz LL-O -< Z IY- O uwj 2 J 0 W U zQ H (w Q wI-I z or: ct aw w OH HH ZD RS FIT RS/P w o �% DI- i112 a ZU B TO SCREENINGS z o RS Q Z w O W w FROM WETWELL 2 ~ _▪} FORCEMAIN DRAIN/BYPASS o Q o Z O 0 l� in in in cn z u) Ov a zz zo o W J w O 0_ Z QZ U- W Q i 0 2D \I- \I- \I- \ Q >w 2m O H m O Cl) OH O 0 0 Q8 Q w i=z 0 Y z cn w— �f O L L Q Y Q p m < >0 �O LIJ _i H =o Q (7) H- z 7 7 7 H Z LU C 2 D 0 PI PI ( PI ( PI � o D w CC Z V O J I- LSH LT f Q — "ill O wig o 0- J i JTSH TSH TSH TSH 9 � �ode Wsi RSMOISTMOIST MOIST MOISTXSH - 480V 480V 480V 480V 1 z W XSH XSH XSH M M M M w Z FROM INFLUENT * * * * 11 JUNCTION STRUCTURE w CW �S \ W �S C �S \ W �S LT Z LL INFLUENT INFLUENT INFLUENT INFLUENT Z WETWELL 1 WETWELL 1 WETWELL 1 WETWELL 1 D PUMP 1 PUMP 2 PUMP 3 PUMP 4 NTS VERIFY SCALE INFLUENT WETWELL 1 BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0001 SHEET 28 FILENAME: 09-1-0001.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:36 AM 1 I 2 I 3 I 4 I 5 I 6 PLC d w > ly w w IY I- I0 E J J Q vi O N CO A j 0 Z o Q 0 >- Q 00 a > U- D_ O Q H w Z � o a Om U) �O I aO < wa LL �O a Qz LL-O C.)<I- - Z IY-O 0 Y L. 2 J2 W U zQ D H (z a wI- Z O� cc aw w OH HH zD RS >.< RS/P FITA A A * j o 112 ✓ (Z)L.) g FORCEMAN TO SCREENINGS a z DRAIN/BYPASS LINE Y <O TO WETWELL 1 U Q a Q Z W W w 0 LUa rx §o O ao D_ D_ D_ z 0 Ov a U) U) U) z z H z Qz — U- m Q O a p w =m m O u) al- 0 0 0 Q8 O Iil w i=z O z cn O u_ 0a Y Q o m J >- mO LIJ H =o Q U H J Z Z Z iii z C LU D U PI PI PI u_ o w W D w CC Z O J LSH LT f ~ Q — ill C)61- u) N o 0- J Q J TSH TSH TSH RZ - W RS MOIST OK MOIST >K MOIST >K Q XSH 480V XSH 480V XSH 480V gillii w H W FROM INFLUENT * M * M * M ' ? Z JUNCTION STRUCTURE W C J \ J \ J w AS w AS W AS LT Z LL Z INFLUENT INFLUENT INFLUENT - WETWELL 2 WETWELL 2 WETWELL 2 D PUMP 1 PUMP 2 PUMP 3 NTS VERIFY SCALE INFLUENT WETWELL 2 BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0002 SHEET 29 FILENAME: 09-I-0002.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:38 AM 1 I 2 I 3 I 4 I 5 I 6 PLC a w > J 0) J CC CO H O E J J Q IrS O N U) PD 00 z o A Q u FROM WASHER O COMPACTORS } 0 00 PD/P illia".4 FA FROM FILTRATE AND SUMP PUMPS E 1 TO ODOR Q o HS LR TYPICAL OF 5 SLR CONTROL z ry O om 120V OSC 480V OSC Q w o (H2)O M HS �o- AS o z INFLUENT C 480V OC Q o SAMPLER1411 illi HS HS z N 480V NSHH) MAS 480V = J° M �/ X M w U zQ ct �z < Ur n n 1 = 0 r z °- w * LIT (LIT) woI-SD/P Iu • u 1 w o LSH I SCREEN SCREEN 1 CHANNEL 1 COARSE SCREEN 1 CHANNEL 1 I FROM STORM - 1 INFLUENT GATE EFFLUENT GATE I o z w B WATER PS L J Z r . U LR 1 LR E PD/P HS I K 1 S J w= w Y w0 FROM PLANT OSC I OSC Q o Q DRAIN PS HS 1 n ' ' n c..--is) o Q�o OC I z °- t . RS/P HS U U HS ci zz o a a zz FROM INFLUENT 480V M I M 480V z o PUMP STATION o LU o C D. CJ GR / o z= L L : z u_ m C r o ] ��� C ] TO GRIT H O o v 1 CONCENTRATORS 6z O w =m n n CO c 0 o CO o° 0 w 0 ~ w ° Y Z�, I U U w o J �z (ti) Y O o m �z I o� w Q O,o L i .it, 0 I--) LSH I i c.,; I C — —K*I— 2 O O n n CONTINUED ON GRIT o CONCENTRATORS U) w D w U U cL Z I O L J J Q r 1 ° I- — % RS/P I OU D z n n LIT O z ow (n Z FROM INFLUENT PUMP STATION I U U LLI H w U 1 LSH ZS CC 12 u..i U rill) H u) Z L i w z D U- z D PD TO PLANT DRAIN PUMP STATION NTS VERIFY SCALE SBAR IS ONE INCH ON AS ORIGINAL DRAWING. nq ZS TO WASHER ° v. PD COMACTORS DATE FEBRUARY 2026 Of, O GLR PROJ BPO0152J TO HEADWORKS HS HS HS SUMP PUMPS �J I M DWG 09-1-0003 480V SHEET 30 FILENAME: 09-I-0003.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:39 AM 1 I 2 I 3 I 4 I 5 I 6 PLC a w w CO w CC CO H 2 O E J J Q IrS O N 0) CO A > z ° o_ O LR Q U O c--IS } m OSC c--IS) OC o LR ZS FA HS 480V / Q ry z w • OSC TO ODOR CONTROL O� °o / HS �� ~ �0 - J t Fl ' Q ,I L6 A \ OC z ZS w° C.)<I- - 480V M - p Y UJ o 2 JI IS w U zQ W3 :_l_.> Q o z w z °� FROM UTILITY Q CL LIJ 2 WATER SYSTEM in OH Hi- -) zD wp D1- IC COI- Q _Z w B QO U Q E 42" ABI/WW D ABI/WW r4' J w= w Y w0 TO FILTERS o o Q LR go HS LR z H \OSC HS \ z o zz ( i!) J �osC I GS / zo o OC 1___, S LU ZS > TO GRIT PUMPS a o GRIT CONCENTRATOR 1 z ZS <- M H <,, O ov, 480V M n o w =m 480V > ~ ABI m O o° LI ABI GATE 1 O , o z zw TO AERATION w ..... J o LR w w �Q CONTINUED FROM HS p Y O o m INFLUENT SCREENS LR ( ) Y Q 0 _° ( HS/) \ �/OSC Q U HSOSC J H (CS) CwC ZS U oc o ZS o M 0 FROM SCREENS w M 480V ABI Y/ w r CC 480V iThk H TO AERATION ABI GATE 2 GS 7+ � J o TO GRIT PUMPS H GRIT CONCENTRATOR 2 zz Q _ Yill Ct I- 0 z w to) o 0 U 03z � Qz w O III w O H I- A A A A z Ct PD D FROM WASHER/COMPACTOR 12 PD WAS NTS FROM WASHER/COMPACTOR 2 -40 VERIFY SCALE PD FROM SLUDGE BAR IS ONE INCH ON 2 LOADOUT PUMPS ORIGINAL DRAWING. 0 1"441 FROM GRIT WASHER 1 BW DATE FEBRUARY 2026 PD 4 PROJ BPO0152J FROM FILTERS DWG 09-1-0004 FROM GRIT WASHER 2 SHEET 31 FILENAME: 09-I-0004.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:44 AM 1 I 2 I 3 I 4 I 5 I 6 PLC d w > IY w w IY I- I(0 E J J Q vi N O N CO A j 0 Z O Q 0 >- Q 00 a > w D_ O Q H z w . o a Om U) �O I aO < wa LL O O Qz u_-- C.)<1- Z IY- (0 O uwj 2 J O 5W U oQ H (w Q wI-I Z �� * GS w woi- ' i-i- zD w0 FROM GRIT PUMPS FA D~ ct Z� B OM GRIT WASHER 1 CS AGITATOR DRIVE TO ODOR CONTROL <° U as� Q Z W T W Y w0 _} O LUa Q0 �o f a_o O Z a pa cs GRIT CLASSIFIER 1 _ ?z AUGER DRIVE z(/),: / PI w 1 w0 I0= o� Z S Qz u)o o wu w 0 W 2m OSC I � ~ a 0 0 Q Ho HS O 5 Q wo LLJ J O LL O Q M �O Y O om 480V . W _i - `�O Q U H4 J iii C PI Lu O n 7 D El GR :. O 0 O W XX 3 w FI TO DUMPSTER D w CC FROM UTILITY WATER SYSTEM J O fl lin Z O _ XI c) GRIT WASHER 1 o W J CLASSIFIER 0z 0 � U - I I O Q a 0_ L PACKAGE SYSTEM) w F- ' r) V u) z D 7 PD NTS TO GRIT BASIN VERIFY SCALE INFLUENT CHANNEL BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" II PD DATE FEBRUARY 2026 PROJ BPO0152J TO GRIT BASIN DWG 09-1-0005 EFFLUENT CHANNEL SHEET 32 FILENAME: 09-I-0005.dwg PLOT DATE: 3/23/2026 PLOT TIME: 9:46 AM 1 I 2 I 3 I 4 I 5 I 6 PLC d w > IY w U w IY I- I0 E J J Q vi N O N CO A j z o Q 0 O >- Q co a DEW o_ 0 1 A A A A Q 0 W TO AERATION O o m BASINS 0 I— aU < wa LL O 0 Qz U O UQ I- Z IY- M o 1 _i° LR LR 480V 5 o z3 HS ) Q1SISC w �� w °z / 0 0 0 < w1 --\OSC ` _ ,� HS ) HS ) �� — ct z a w / / w �\ ��OC ��LR < oi- ZT ZS z W 2_ 480V 480VQ,--IS) \ SC n n D I- M M HS ��� , • , u u u o (in_ zo B Lu T n \OC Z ABI FIT fl Y ¢� / ZT• I Q Z LLI FROM HEADWORKS L I Y =° 0 LUa a0 CCU_ SEL 1 SEL 4 z [L i-O Z u) Oa LR _ 0 zz HS z o ZO o _w OSC w ociS) oz Qz C U_ Qo ZS O on � C7 D 480V 0 w =m M � ~ 0 O � o° 0 0 0 Q~ O w w _(2480V7 0 w- Ow u_ as 0 AER 1 AER 2 AER 3Y O o 200 w J iii J 480V a-N vi 1 • 1 i- ...../ z C LR 2 S U 0 QOSC 0 rHS w l\ CC OC ZS QLLI 480V M F- J V ° a ini-OZ D o UJ SEL 2 SEL 3 Dia0 Q 0 J LR z - i U c.--IS) Sc 03 Qlid i= wfiz0- O .---AL..---AL. W H c--IS) Q rill) m ZT i- z 480V .----AIL, - Z O M Q D RAS (:2-) � �� �� 480V LLB Q FROM CLARIFIERS NTS VERIFY SCALE V BAR IS ONE INCH ON ORIGINAL DRAWING. TO OTHER AERATION BASINS 7 ML o 1" DATE FEBRUARY 2026 TO CLARIFIERS PROJ BPO0152J DWG 09-1-0006 SHEET 33 FILENAME: 09-I-0006.dwg PLOT DATE: 3/31/2026 PLOT TIME: 11:31 AM 1 I 2 I 3 I 4 I 5 6 PLC GENERAL SHEET NOTES d w 1. BASINS 2 AND 4 WILL NOT HAVE DO PROBES. w W w IY W H E J J Q vi N O N CO A j z o Q 0 C) O >- Q 00 a > w D_ 0 Q H O w O am 0 LR F a°Ill < w Q HS =LL o — XOSC o (I)Z QS) o -a Z IY- FIT O Y w o (n _ _i= ZT w5 O Z a H (w M Q �I- = or 480V z a w < LL 0 _ zD Q UJo 112 a Zw B ¢° U T03- <> n n <C, z w O 0 0 0 DO ��DO Y wo (ri) AIT i i>_ Q wa arx §o I-'i: SEL 1 SEL 4 Z o °z zo o W J w Q 0= 0� Z QZ U- W 0 O ou) 0 Lij LULU AER 1 AER 2 AER 3 0 > =o m O Cl) OH O 0 0 aH O w i_o O Y Z czn w- Y O om O W J H �o Q U 1-4 J SEL 2 SEL 3 vi i- Z LU C 2 D 0 0 0 Li_ O o o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o w o o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 o o o o o o o o o o o o o o o o o W V v v V V V V V V v v �/ V v �/ w 11 A A c, /� J r TO OTHER AERATION BASINS i O Q In z O Z - LR LR LR LR LR p J Qs.)osc ( HS ) HS ) Oosc HS Z 0 � V \ / / O�\OSC \OSC OSC p 06 (F-Ls) HS (I--LS) c.--IS) c.--1..S) Q Z L .------, M ZS ZS ZS ZS ZS ' Q M M M M M z W 480V 480V 480V 480V 3 480V Q FIT FIT FIT FIT FIT D a o_ a_ a_ a_ NTS Q Q Q Q VERIFY SCALE * ALP ALP ► ► ALP ► BAR IS ONE INCH ON ORIGINAL DRAWING.0 1" FROM BLOWERS DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0007 SHEET 34 FILENAME: 09-I-0007.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:49 AM 1 I 2 I 3 I 4 I 5 6 PLC GENERAL SHEET NOTES d w 1. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS w ON NUMBER OF CONNECTIONS BETWEEN Lu SECONDARY EFFLUENT CHANNEL AND FILTER cc INFLUENT CHANNEL. H o 2. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS ON NUMBER OF CONNECTIONS BETWEEN FILTER Q EFFLUENT CHANNEL AND UV INFLUENT CHANNEL. N 0 N CO A a z o ii>Q 0 U >- Q m SECONDARY a CLARIFIER NO. 1 > o < >- MS w z w • O O13-co' i— aU < wa 2LL g :z - * I I wo UQ FROM PLANT II z w 5 UTILITY WATER I I p Y u,o z J < > U H °z } } 480V i- 7 z } -p... = orI ► _Mo._ M � aw wI < > ' HP' w °F- zD RASal Nal FIT D o I- 1r < > ' AS TO AERATION o Z B RAS PUMP 1 BASINS Y <o -IIIIImP- C) as 1r 7 azw Y w 0 < > �� w} MS Q 0Z ( 1r < > ' } I I } I I } Z I I z 0 oa SECONDARY -I�-� SE _ �� BIOFOAM oz o COLLECTOR < NO. 1A > ' SHEAR PIN SLUDGDARY TO PLANT DRAIN E o= - �� �� 480V CS COLLECTOR Q z 480V YS NSH NO. 1A Q o 7 M 7 M ~ O o u) 7+ NW. .., OCO o W o'IM° Il 0 LU o Z_o FROM AERATION w O Q L o BASINS / I I �z I — o Q o oe w MS I I ,' Y - Q J c } } } — ww Z ( _Mo._ D 7 7 AMID' O < > HMI.' IL w U) SE % Q CC w 0 -IIIIII.- � TO UV INFLUENT 0- CHANNEL < > s I-IIIIIP- _imp_ - -r , VI z * } I } I } ~ ° W ( 1r < > 1- I IEt ii LL I I Q SECONDARY O zz J0 7 COLL 'OAM ECTOR SLUDGE SECONDARY ILI Q J < NO. 1 B > SHEAR PIN COLLECTOR (10 z 0 480V I.) ›- YS NSH 480V CS NO. 1B Li] 7 M V * * M < > SE cnEt z 0 ~ TO FILTER Z INFLUENT CHANNEL 0 0 D W W NTS VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0008 SHEET 35 FILENAME: 09-I-0008.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:50 AM 1 I 2 I 3 I 4 I 5 6 PLC GENERAL SHEET NOTES d W 1. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS w ON NUMBER OF CONNECTIONS BETWEEN SECONDARY EFFLUENT CHANNEL AND FILTER ly INFLUENT CHANNEL. H E 2. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS ON NUMBER OF CONNECTIONS BETWEEN FILTER Q EFFLUENT CHANNEL AND UV INFLUENT CHANNEL. N 0 N CO A a z o ii>Q 0 O > Q m 480V-\ o HOA LCP > o HS i- FAIL-/- �� ��LR \ ___,5)N \,..---..,/ \,___.,5)N •.---.9N �--.HOA ZO Li OA OIT YL YL YL YL HS oHS o-/- Q._--IS) i \ i \ i \ i \ < Wg HW - A 4. I I I 11111 I �o L J, J, w_ I I I 11111 I �1TURB -a I 1 I 11111 I (AIT) >N 0 o I u II I I s.I I I I 1 "POWER" TO SOLIDS 1 zl- 0 T "MSC" w v o< or: Oo z aw LR LIT LSH < o1- HS ( AE ) Iwo DI- (FI f OSC / \ WSII II II II II II II o Z w B ?OC U T03- (ZS) — — J Zw W= fyi- SE M F F .--'116... � Y =Lu o 480V -----4116.. p o a FROM SECONDARY — — §o EFFLUENT CHANNEL O z Z 2 o:12C1-z zo FILTER w J INFLUENT W o CHAMBER o� EFFLUENT <- FILTER BASIN CHAMBER O w o O ww :61-c0 Q O O �wO LU w 1_ Ai CONTINUED TO E co w O Q 20 OTHER FILTERS m m m m m m m m TFE w UQ O Y a co O W J F- =0 ao Y =Q TO UV INFLUENT Q U ~ > CHANNEL I- o M Z C \�' 2 FV 0 CD CO M 00 Y ` W 0 FV IL CO M LIJ > FV o M o U J > M fl O J FV VI z Q o U oci_ ) M o o z ,,,_ 0 O <z - F- 4.1 i2c'es i M \,„..---„, TE pM w u_ FV P IVT w W '� H J LLFIT Z D AS BACKWASH PUMP M M 480V 480V NTS BW BW4. VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. U U TO GRIT EFFLUENT 0 1" CHANNEL DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0009 SHEET 36 FILENAME: 09-I-0009.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:50 AM 1 I 2 I 3 I 4 I 5 6 PLC GENERAL SHEET NOTES 0 w 1. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS w ON NUMBER OF CONNECTIONS BETWEEN co SECONDARY EFFLUENT CHANNEL AND FILTER INFLUENT CHANNEL. _ O E 2. REFER TO PROCESS FLOW DIAGRAM FOR DETAILS ON NUMBER OF CONNECTIONS BETWEEN FILTER Q EFFLUENT CHANNEL AND UV INFLUENT CHANNEL. N 0 N (/) CO A z o Q u O O 120V_\ 120UPS_\ >- Q m CCM UV SCC (SYSTEM CONTROL CENTER) 0 e a o z w 0 Dom Q wQ PDC I o H LL o z — o POWER DISTRIBUTION I w o CD I- 4.. z >N 0 UVI UVI UVI O u O 0 0 0 0 0 0 0 0 0 0 0 0 0 o AIT AIT AIT 120VAC I w U o< LCP cc Ct w 480V LOW LEVEL Q CONTROL BOX z ° ry HSC LR w w LL 1 HYDRALIC SYSTEM HS Q o~ CENTER 9OC �UVI � UVI � UVI -) wII o HS 1 / - _ I I I - 1 II COI- / I I I I 0 -w B OC /ZS I I I - I Y Z O co n 480V UV DISINFECTION UV DISINFECTION UV DISINFECTION I FINGER J z w TFE FIT LAMP BANK A LAMP BANK B LAMP BANK C I I WEIRS Y ct i_ LSL (TYP) w Y =o Q FROM FILTER H I ❑ Q o EFFLUENT CHANNEL LR I LR z o"( HS i^ I Q-ID zz ( o a❑ zz - OC I � \ C z� HS o pC w I UC wo DI ZS I ZS a Z El n U- O w u) M FE > 0 w ' M DE 480V U I U 0 > O 480V m O C o CS ,n, I ,/;�, ❑ w 0 Q o p IJ H z U I— U p > z cn 120VAC I w0 -I 2 Dz UPS LI LT I SS �� w w O Q AIT FIT ',. O Q O o 0 I / �� ��UVT I TO OUTFACE U ~a I O ( iY AE I Z i , Z C AE j e SE/SAM I o I I 0 I LLI I _.•44H)80__ AE)_[)81_ CC UV SAMPLE PUMP -40 ® r z z O O IA ❑ UJ Q aW OU z -LL U o a_ SE z � OP- IF! a FROM SECONDARY rill) > EFFLUENT CHANNEL cc co D ti . D CONTINUED TO OTHER UV CHANNELS NTS VERIFY SCALE / BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" TO INFLUENT PUMP STATION DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0010 SHEET 37 FILENAME: 09-I-0010.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:51 AM 1 I 2 I 3 I 4 I 5 I 6 PLC d w > IY w w IY I- I0 E J J Q vi N O N CO A j z o Q 0 C) O > Q co a > w D_ O < H z w o Oa m U) �O I a0 ...._< w a t O Qz LL-O -a Z IY- O Y uwj 0 2 J2 W U zQ ESTOP i o I- OC HS (LI) z aw HS PS w o O M * zD AS * 2 _ D H SSL NPW W3 �* Do- * Z o B <� U Q(3- * .H, WA_► ROTARY* Y w= BOOSTER A DRUM A w Y PUMP 1 AS } SSL o o rx < iyo * z °i- f. WAS * Z u) 0< WAS ROTARY - zzCM) zz FROM RDT ' AS DRUM B zo o FEED PUMPS W-Jo V 0= O� Z Qz POL ROTARY DRUM* u_ a- m o * THICKENER 1 O w u) FROM POLYMER POLYMER ��ESTOP O O ww MIXING VALVE HS p =m m O W O° o 0 0 Qo C z u)O w LLI w- O LL 0< L PACKAGE SYSTEM O < � O 0 W J F- 2V Q U H<4 iii Z LU C I- -I D U 0 0 Li_ 0 w D w CC ESTOP �* OC HS LT M HS ( PS * J C ) M AS V 5 U NPW SSL H SIC 11) O 0- W3 _>* F- 0 * WAS M ROTARY* O I BOOSTER C� DRUM A p PUMP 2 /�� � AS 1 z ( SSL) 014 < o_ \ / w z rill) W WAS *. IP' _ i�WA� ROTARY* z U FROM RDT DRUM B - I I- FEED PUMPS AS * D POL ill \ Ow ROTARY DRUM* * THICKENER 2 7. NTSFROM POLYMER POLYMER , ESTOP MIXING VALVE HSIlrVERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. L PACKAGE SYSTEM 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0011 SHEET 38 FILENAME: 09-1-0011 PLOT DATE: 3/25/2026 PLOT TIME: 8:53 AM 1 I 2 I 3 I 4 I 5 I 6 PLC d w > rI w w ct co I- I E J J vi N O N CO A j 0 Z 0 Q O >- Q 00 r 1 A u- m O Q H c, —� o 0co �o I— H aU < wa H— Z w 0u)z L.uO UQ Z II- O W S z J2 > U Z� PDIT 1 Lii I- o z �1 I wil DPI z oil w o� F-, zD wO D_ DPI I PIT (0 1- PIT M p —w B CARBON ¢ ABSORBER U ::o a • W Y w0 _O 11110.- O 0 �a \ ODOR CONTROL o HEADWORKS FROM PREFILTER = FAN z o W �� Z o 0 U Oa \i/ - zO w J W O O= L ACOUSTIC ENCLOSURLI o Qz u_7QQ O on 7 —D&I— i— o O w =m O 1 m O C o° L PACKAGE SYSTEM]I Z 2 o 0 0 Q O O w i2z w- 1 O LL O< O o u) A O Q �o W J F U QU I-4 I J iii C 2 D U Z 0 w O Ili D LL i CC I S DPI C DT)\ p I ILI O c�F- ,_ ODPI PIT Q 0 z O M R — O J CARBON oZf Q ABSORBER Q U (,_< O >_ ����'\O , , 0 , \ 0 ODOR CONTROL\— c PREFILTER — FAN Z \i/ L ACOUSTIC ENCLOSURLI 7 7 -Dill- NTS VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. L PACKAGE SYSTEM]I 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0012 SHEET 39 FILENAME: 09-I-0012.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:54 AM 1 I 2 I 3 I 4 I 5 6 GENERAL SHEET NOTES LU 1. THIS DRAWING SHOWS ULTIMATE CONFIGURATION w AT CONCLUSION OF 65 MGD IMPROVEMENTS. LU H J J N N U) CO A Z 0 • O < Y O 50-PLC-001 50-PLC-002 50-PLC-003 50-PLC-004 50-FPP-001 25-RIO-001 25-RIO-002 0 \ 00 Y FILTER 1 PLC FILTER 2 PLC FILTER 3 PLC FILTER 4 PLC UV PLC HEADWORKS RIO HEADWORKS RIO 0 > U- a 0 Q Zw� s- o H oO LUQ =w O Qz Uj O —< Z O Y cwi) 2 J' W U zQ H �z Q UiH = ory z �w < U-2 w OH HH zD w0 �2 10-NIP-001 12-NIP-001 25-NIP-001 col- 0 zw B Y ao ADMIN BUILDING MAINTENACE BUILDING HEADWORKS BUILDING U <°- SERVER ROOM ELECTRICAL ROOM ELECTRICAL ROOM Q z w J Di LLJ Y w O } O Uw< Qry gO z 0 fl 0 zz <- _ Q❑ O LU(/) O z 0 >w =m H O O C/) o 0 0 OO Q H w ijZ z cn w- W• 0O J o LJJ U Q Q Y a) LU Q H O 0 H Q J I- H z C 2 0 0 a U_ 0 L1.1 U) 35-NIP-001 40-NIP-001 w BLOWER BUILDING CLARIFIER BUILDING ELECTRICAL ROOM ELECTRICAL ROOM J 2 a Z O la0 Q Z O a to) Q CDH O z H W z D 35-SWGR-001 35-GEN-001 30-RIO-001 30-RIO-002 SWITCHGEAR GENERATOR MASTER MASTER CONTROLLER AERATION RIO 1 AERATION RIO 2 CONTROLLER NTS VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE FEBRUARY 2026 PROJ BPO0152J DWG 09-1-0013 SHEET 40 FILENAME: 09-I-0013.dwg PLOT DATE: 3/25/2026 PLOT TIME: 8:55 AM 1 I 2 I 3 I 4 I 5 I 6 w w w I I J I W N CO I U) Z 0 A , > 0 < Q YO I U I I >- co Q I I I I I a I z Q 5 om I W co a.0 O J m d Q Q , w ED O 1Ha I- O I W' (i)0 I W I 0 U W , N Q I 0 Y � ° � I 5 0 zQ I Iw oz m wH or Q o� I o w = PNL I off 22-XFMR-001-01 o 45 KVA I § 480-208Y/120V I Z a w g , z ' Qo MBS Z Q� I Qa z = I Lyj PNL PNL ~ I Z I a O N UPS I Q o " I 6<L CV co o zo0- zz o m o c) 0 o o I zo � U I c2w I o_ Q aQ z � o0 N ' Y a0 I O � � I Qz O w I I p a I m o > 00 H a w O Qo W z(L) 0 < i W LL 0 Y 0 a 9 W Q > =o I J H � H C w O U I I I u_ O I w w I I I I 2 I c11). E Ct Q C� co m UQ Q o o V < U III ctsIII z ') 2 J J 0 W Il'l z O ONE-LINE DIAGRAM NTS 12" = VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 10-E-6001 SHEET 41 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/010-E_RVT2024_DBO0152J.rvt PLOT DATE/TIME: 3/24/2026 3:59:31 PM 1 I 2 I 3 I 4 I 5 I 6 0 Lu FROM FROM 27-SWGR-001-01 27-SWGR-001-01 LE BUS A BUS B L 0) , -`, H I E 22-SWBD-001-01 • • , Q cd 1000 AT I 1000 AT I N DPM 1200 AF ) K DPM 1200 AF K o A ALSIG i ALSIG 0 O Y O 3Q BUS A, 1200A, 480V, 3PH, 3W, 65KAIC 1000:53 i n 1000:5 BUS B, 1200A, 480V, 3PH, 3W, 65KAIC m Q I I K 80 ) 80 ) 20 ) 600 ) 600 ) 200 ) 175 ) 225 ) 225 ) 30 ) 175 ) 175 ) 600 20 ) 20 ) 80 ) I o LSIG LSIG LSIG LSIG 800A LSIG ) w I I 3-POLE SWITCH I Q o - SPD w Hui �Oc m wC El CL3 Etw ¢ w = H O — I `�0 wI= � E z —-—- -—-—-—-—- -—- -—- -—- -—- -—-—- -—- -—-—- -—-—-—-—-—-—-—-—-—-— -—-—-—-—-—-—- -—- -—-—-—-—-—-—-—-—-—-—-—- 0 Y cn Oz 250A ( 1 Q H (65 KAIC) > O zQ W < 0)w (3 POLE) Q ow 15M 15M ) 15M ) C° w H i • O i - o__ AFD AFD 1 AFD AFD AFD AFD �___ __ AFD AFD AFD 1 1 AFD zD � H Ct Cr)O a - w B PNL z z L 22-XFMR-001-01 < z LTJ 45 KVA H I- LuL 480-208Y/120V Lu w _° 40 40 15 335 335 70 70 70 70 335 15 5 40 Q ct MBS cc° —z oco p O 6Q co J 2 PNL PNL N N z o o z 0_ 2 Q 0_ < N co z a_ -cc DW I� co r o in UPS W D_ W N IL W 2 Z O W J WM W ,_ 0_ co WS 7i" CV � O 2O 2O w 2 O 2 O 2 O 2 O ' ' J J �� O co Oi r cj Ch N cV 0_ O D_ O W O O m O D_ N 0 I W Cn Y o W O ' 9 ch I- ' I- i I- O WO Eto Zo Ho H ' � o � o N o o Z � ZW Za � N o W � QZ — W' O Ud o zW ZW ZW zW om o O W2 Lu W2 Xo 2 CCo u_ wo Uo_ Z � Uz W2 W2 W2 Lu o O Om JD J > » m Uo_ cn � � o- Cl_ -I 0_ Z D 2 0 g 0D O Q Jii Jri JEL J � JU W ' Li_Z ) Z WD Z 0 2 ww } � } � OIL Wo u_ o u_ o u_ o aQ aQ Z2 ? � ? � ? � Ow � 2 � O > 0 W 2m - in > o_ a o_ 0 o � °' � � ON ZN ZN ZN Z- N NN NY NO ON DWON CC pp O 0H NN (N c0 NO I- N- 0 0 8 O Qo LU O > W z(L) j 0 < : ¢ W u_ 8 p O a m W Q > co I= 1 < Q U H— -, J ui H z C "J 2 D 0 0 0 LL 0 w CO D w L ONE-LINE DIAGRAM NTS 2 z Q Ill 0 Jct 0 < h .()Q c- ro 0_ LLJ CC H z III - ') _ -I -I u III 11 1 z Z O D 12" = 1'-0" VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 20-E-6001 SHEET 42 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/020-E_RVT2024_BPO0152J.rvt PLOT DATE/TIME: 3/31/2026 11:46:49 AM 1 I 2 I 3 I 4 I 5 I 6 I--- ----7 o 600A 12 47k I USERC METER CC CC SIMILAR TO I W ■ COLUMBIA BLVD. W I 00000000000000000000 W O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 u) 0 0 • 27-GEN-001-01 ; 27-GEN-001-02 ; • 27-GEN-001-03 ; • 27-GEN-001-04 ; o 1200:5 I ; 600kW/750 kVA ; ; 600kW/750 kVA ; ; 600kW/750 kVA ; ; 600kW/750 kVA ! c7 --J GENERATOR MASTER ; 480V, 3PH, .8 PF ! ; 480V, 3PH, .8 PF ! ; 480V, 3PH, .8 PF ! ; 480V, 3PH, .8 PF ! a -- --- CONTROL PANEL ' ; ; `° G i G I I G i I O ; o MAIN XFMR co m ' i • i i p Z A - I - Q 12.47KV-480Y/277V � O 800 ; 800 ) ; 800 ) ; 800 ) Q Y i . i i i Q m ---------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------ • 27-SWGR-001-01 I 0 a u_ 1 . Q i- . I— wcd i m �Q i IY W ' 52-UA /� i 2 o _ ! cn0 5000AT > 0 LLCt i ALSIG5000AF ° DPM 52-G1 52-G2 52-G3 52-G3 • w N 3-POLE ° 800AT ) 800AT ) 800AT ) 800AT ) ; z = u)o 1200AF 1200AF 1200AF 1200AF - U Q vo ALSIG ALSIG ALSIG ALSIG w g z 5000AF 3-POLE 3-POLE 3-POLE 3-POLE I Q 4000:5 5000AF SWITCH _ o E SWITCH 3 POLE . Q BUS A, 5000A, 480V, 3PH, 3W, SCCR 100K c <E 3 POLE-- > BUS B, 5000A, 480V, 3PH, 3W, SCCR 100K � �� BUS G, 5000A, 480V, 3PH, 3W, SCCR 100K I O o I- •-../ \--/ I Z o ; W O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 = i- 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 O O V 1 I- 0 0 O 0 0 0 0 o O 0 0 I 12 a Z W B ! ^ ^ n HMI co n o n O n ° . Qo 0 0 0 0 H 1 fCi Q WWa - 52-22SA 52-25A 52-35A 52-27MB o 52-27SB 52-22SB . w i 1000AT / 0 3000AT / K2 2000AT / 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 = 1000AT �K1 3000AT K2 1000AT ; W H w O / =r 3000AF 1200AF 1200AF 3000AF 2000AF 0 0 0 H 1200AF i Q o Q LSIG K1 0 LSIG LSIG AUTOMATIC TRANSFER W ALSIG ALSIG LSIG i p i—r 3-POLE 0 3-POLE 3-POLE CONTROLLER 3-POLE 3-POLE 3-POLE i °ct z °i= Z p 0 D_ 0 0 ; zz 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ; u)D_ ZO ._._._._._._._._._._._._._._._.i._._._._._._._._.y._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._.1._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._._! 7)J ' WO p Z Z O O (7) O (7) p O (Ns O O I- W w ‘CS O O Q O OI > 0 0n p � a m H ct O w =m mi— m a 0 i � J m i-0 cw5 u) 2 ti NQ a O O Qo N Q ti ti c., ti N LL O W z NW N N O N ° C7 > Y Zcn OW O O H O OH0- O J ?o H CO W u_ 0 Q O Y O om Y Q H =0 U ~, J I- Z C W 2 D 0 0 O I U- O W D Q W CC NN GEN O METER SPD FDR ATC FDR ATC Q 0 MAIN FDR TIE FDR TIE GEN W 5000A 5000A 5000A o Q J 4 Ai J 1 U_ LU FDR FDR GEN Pa crjEt z Q ~ o U al w BLANK BLANK GEN '� w J J W N— w O O / ��/1 L.L_ D U) ti N ONE-LINE DIAGRAM NTS 12" = 1-0" VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 27-E-6001 SHEET 43 Autodesk Docs://US OR BPO0152J_Lake Oswego_DBO WWTF/010-E_RVT2024_DBO0152J.rvt PLOT DATE/TIME: 3/24/2026 3:59:31 PM 1 I 2 I 3 I 4 I 5 I 6 TO 27-SWGR-001-01 TO 27-SWGR-001-01 0 BUS A BUS B > _------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ w • '1 ''41g......, W • ! U) • _ O c7 DPM DPM a 06 ! i! 1000:5co / A ! K1 1000:5 3 \ O o z0 m O ! 27-MCC-001-01 ! > a mBUS A, 1000A, 480V, 3PH, 3W, SCCR 100K «��� BUS A, 1000A, 480V, 3PH, 3W, SCCR 100K Q co O 1000A U I SWITCH ONLY I I , z m g co z 7M ) 7M ) 50M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 50M ) 50M ) 15 ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 30 ) 30 )225 ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15M ) 15 ) 15M ) 15M ) 15M ) 15M ) 7M ) 50M ) 15M ) 15M ) Q O LSIG ~<\ > Z � D ! 1 1 2 AFD AFD AFD AFD AFD AFD 2 2 11 II 1 1 1 1 1 1 SPD SPD1 1 1 1 1 1 1 1z AFD AFD AFD AFD 1 2 11 1 1 Z p 0 o AFD AFD F R ! OO w 0 co Q LL Et w I- i O H w m W U O i i w c9O W , m wQ Ct W� CC O 0< Q z ct ct p Y IE,u)O (W 1 _, w U 0_ Q 0)'- m W I- - u_ !Y O� 5 5 10 5 5 5 5 5 5 25 25 5 5 5 5 5 10 5 5 O w2 -, oI- Z� CO r W O ›- a a D- Q to M r Ln co r o' >- d r W W W W W LZLI a M W r ZU B < Mo co o o W � Luc," wQ Win Wm Wr_ CC � O 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 o N NN o w 0 z X (n r- ,n O ' CC O 0 o CC o 0 ' 0 o IW- O w H 0 N 9 O c� a o' U X w X Zp � coo u o cno u) O wE O1 o) O Qo WC] Qp ..ct wag (o °- W > O IYo wc) [to WO WO WO cc CCD wwz I CL d wi- CC2a 2OL CCZU Qcn Q (W Qcn Qcn Qco Q (n CL 0- W W W _W -CL _CC _C� CC CC Cr Cr CC C� C Cr W > O cW oQ o O O co MW MW r rW r rW NW NW NW NW d- W d' W � W d- W N N OCZU U' , ~ W U � � � � � UO ,n O � O � O � O � O � O � Hc� I- ch r chW X W W X X X X N Q Ocv W =r (nCLN 2CLN (nUN UN UN UN UN UN UN (WN coN r ZX Z_ ZX ZX zX Z_ x zX Z_ X ZX Z_ ZX Z_ ZX Z_ ZX Z_ Z Z Z Z UO ,n UN p W NM W W W W › (n UN O (W (n (W (n (n CT) (W CT) (n (n CT) (n CT) (W (W (n p Q Q m CO NO N 0 H NO 0_ O m � c? m co p m N O m r pmt' O m C'' O Q N O m r O m r O m N O Q M O 00 '71- p Q T- c? CON O Q M O m � N D CC O „ O W' c ct o„ , c Q QO O M M j M - ° r r m r N N N m N �' m ' m ' O OL U U ' () ' U ' CL X 0_,� OL r z O r Z p r Z p r Z p r— z ct r Z p r Z p r Z p r Z p r Z p r Z p r Z p r Z p r Z p Z O 4z r., of C CO O O (n O co O cn X z G o _O O O o p O _O o O O O_ o p O O_ O O_ O O o O O O o O 9Q O O 9Q d G o O O o w 2 o � O XQU XQU X1- (~j XQU XQU XQU XQU XQU XQU X_ Qiw _>< QU _XQiw _xQU XQW XQU XQw � O (ow U � U ( U pt oz wa2 a OQ LL QW QW Qw QW QW QLLI QW QW Qw 2 � J � � J 2CC � 2 � J � CCJ 2 � J 2Q' J CLW � � C ZZ O � pW W OW W pW W OW W CCJ CCJ � CCJ CCJ 2w _, , , , , , , , p Qcn Q (o Q (n Q (n , MmWW OWW oww OWW OWW OWW OWW OWW OWW OWW OWW OWW O - O6 O � p , O6 U � in u)(t MQ (W coMQ (n MQ (W coMQfn MQ (n MQ (W MQ (n MQ (W MQ (n MQ (n MQ (n MQ (n MQ (W MQ (n MQ (W MQ (n Mm UN UN UN UN cndN Z0 CT W w0 a 2 o� Z Q- W coo Qw W H Wu) O ! 35-MCC-001-01 ; Ct O w w 27-MCC-001-01 BUS A, 1000A, 480V, 3PH, 3W, SCCR 100K ; Q I BUS A, 1000A, 480V, 3PH, 3W, SCCR 100K , O O w i 0 op p o i- W co I I I o W 0 <o O o 50M 50M ) 30M ) 7M 7M ) 40 40 , 50 15M 25 25 25 , 40 , 50 , 50 , 7M , 7M 50M ) 15M ) 15M ) Q z i 50M ) 7M ) 7M ) 7M ) 7M ) 50 ) 40 ) 25 ) 25 ) 25 ) 15M ) 50 ) 40 ) 40 ) 30M ) 50M ) 15M ) O , `s w cn Z w O < ! O J Dz Q I— > Q ! I co W LL p< 1 1 1 1 1 AFD AFD AFD II AFD AFD AFD AFD AFD AFD 1 1 2 1 1 1 z O z 1 1 1 1 1 AFD AFD 2 1 ! O Q O am R i O m AFD AFD AFD 1 AFD AFD AFD 1 Y J =o U Q H ct w z ! Q U '� pw O W U J O iii C ! i W ! i w 0 O O I LL O w U) 2 w CC NQN Q 1 1 20 5 5 20 1 1 25 0 C w 7 N anan Z QZ E U J 25 25 10 1 1 20 20 20 5 10 10 10 20 25 25 O o r r r �, N CC N 1 1 25 20 10 10 10 20 20 20 a N 25 wr _ Q r r OCV co � N Oo 5 10 w O m W > o ct ,f- o_ o � o r0 do CCU > o Ho Q Z O V U O z ' CCoo 2 . Uo � o 2a CCo z . Q U CC CC O O c\I CC g d r O U ~ 2 a O U U cK Et N n H ,- Z W L7 cn a Q co � a H � � 8 O O a N pW ' w J O CL r N a2 2et i ,n U r N I— M J 1 W W Q D D C 7 N U' N C N U N >> U D W Z I I 2 2 r J J W r r H CL CL N O N O N O N w J CL 2 2 Q (W N w J J r J J N LL r Z Z � � X p � po Z Z_ NO oU zQ Do � � o9 29 po o � ao C:) 0- 0_ c" CL ',SO- Mp r0 co r Jr 0_ O � r � r CLr Or U' M Or J U' N CL CC (NI NN J N ra O O O og OU oU 9 O O O O O O O ON oW 9 o N r r Ch M r NM Nr O X rX X QLf Xo X OU X Ln NX �' pN N M Z .- 1 QO QO O W O � OCL OCL I_ H0_ X w WX W X Oo � O 2O rN ON O O WX (N W W X O 90- O Q O o O o CL W X I- o a o o a o pd pCL CL2 � W � W OL2 a2 pi Qwa > 1 > X a 1 J u- CL ow O � JQ pX > " > , F- � X zo a2 o_ 2 OL2 CCU U a W d wW wW w � w Jw w Wn- Wa W0- a CL ct O � 2D M � gQ oa U 2 2Q JL. JLL 2D 2D U > H2 Q' w � 2 U' O2 p LT_— Q2 2 w � � , 2 2I- 2 W 2 Qa Q D DO a 0_ I-1- OUQ OUQ 0- CO 0_ (/) � WO OD OD WD 0 � oW � � OE JE pD QD WD 0 � � D MHO D CL m (n 0_ p Z � CO p J p p O - O O J O O Q O O 1 J J Q Qai Q ' � a JCL � � J � JO Jp U UQ JO JCL l- CL Q �- l- 0- (WOOL OOL O' Q pQ O' O Qa D OLN CLN X00 d- 0 d- O d- CC •71- FY N mco o ao cc co (n co cnC° � O og of (WTI Jo Do CC � m QOo a ACC .7r cc .1- co 0- CV I`OM Et � o � U � U u) co CC co mco OM N ONE-LINE DIAGRAM NTS 12" = 1-0" VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 27-E-6002 SHEET 44 Autodesk Docs://US OR BPO0152J_Lake Oswego_DBO WWTF/010-E_RVT2024_DBO0152J.rvt PLOT DATE/TIME: 3/24/2026 3:59:33 PM 1 2 3 4 5 6 FROM FROM 0 27-SWGR-001-01 27-SWGR-001-01 w BUS A BUS A w L , (/) H I _ 27SWBD00101----------------------------------------------------------------------------------------------------------------------------------7 c2 • • ' Q co DPM DPM o U) CO A -� '-i•-, o I p z > O Q 0- U BUS A 3000A 480V 3PH, 3W, 100KAIC 3000:53 2500:53 BUS B, 3000A, 480V, 3PH, 3W, 100KAIC v O nQ I- - - - K2 1 I I I m 60 ) 60 ) 600 ) 600 ) 600 ) 30 ) 30 ) 225 ) 400 l 400 1 400 ) 400 ) 400 ) 225 )30 ) 600 ) 600 ) 225 ) 80 ) 60 ) 225 LSIG LSIG LSIGI LSIGI LSIG l LSIG / LSIG 3000A LSIG LSIG / 3-POLE SWITCH LSIG LSIG LSIG LSIG LSI r a o < i � co w O:mO w CL L w ¢ Q w 2 �O i 0_W' wH ------ --------------------- --- --- ----- --- --- --------- --------------------------------- ---- --- --- ----------------- --------- - - UQ Z CC E 400A 0 ° (65 KAIC) 5 a z Q (3 POLE) W o w --- Q (w o_ w \4 l4 i \ Q AFD AFD AFD AFD 0 ti ti ^' I 225 MOB 225 AFD \ i } >- AFD AFD I PNL 225A BUS I AFD AFD PNL 225A BUS -, O H J >- O < J i 42 POLE , 42 POLE w O Q >- < co > 5I I I _ W 0000 OO cco0 W - I !Y wU B z 7i- co � o PNL 7I- co z - i p w O IA 12-XFMR-001-01 45KVA I I O 12-XFMR-001-01 Z O Q o 25-XFMR-001-01 Q o hi i 480V 208Y/120V I i\6 45KVA z u)0_ • O O 480V-208Y/120V J Q H o 75 KVA D O I --- a z = J U) 480-208Y/120V J I I I W o � Q � Q ' in = z 30 30 300 300 300CoH PNL PNL o MBS PNL HO O in 300 300 I PNL 40 30 PNL I p H Et <O 0 0 q o CO I ' _z w U U C� > > oCD z PNL PNL Q N L----------- O 6� 0 0in cr) I I z Q = L---- No Z p z z CC CCL 2 o_ r . o UPS -N'S ,_ o w w w O Q o ? N o �_ o z �o O > > > O Q N N O O O J Z N O D w � � O O O w' w' � � � � OQ No (,) Y0 O m m Q XQ � � � j 0I CO CO m H 0_ O O O Z J LL x m 0_ D CO O 0- D 0- D 0 2 YO YO r QZ H x 2 � � z CO 0_ 0_ J ZQ J ZQ J o co O m 0- 0 W X Z 0_ O — n �CO � w 0_ m � ma � � oU n w z � � 0_ � in 0 D O Qco o > 6 > 6 ZQ 0- Q z � Qo DQ ? O 1 = 2 Din Din - �n � > 0- W � o_ E? J Q 0 w = m ww I- N r- Q 2 O OW 0_ Z O O HO NN Nco No ZO chQp 0_ J m Q OH QCO � o Q in O ¢° W Z O N O W 0 < D H u) W L_ 8cn Q Y O Om W ›- coO i = < U ~ � w H Z C "J 2 D O O O w O w Q w L V ONE-LINE DIAGRAM Q NTS w V� 0 J z o UJ o � _ w co zc' D z V g U � acts III ', w J I W , L.L., O CD � M W D U) ti N 12" = 1-0" VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 27-E-6003 SHEET 45 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/010-E_RVT2024_DBO0152J.rvt PLOT DATE/TIME: 3/24/2026 3:59:35 PM 1 I 2 I 3 I 4 I 5 I 6 d w > r w co w cr co I- I0 c7 I J Q I I o Ico o 0 I A I > Z o < C9 0z z I Q Yo 0 I ›- < 5 5I m m I m I J J Q I O 0 I i- o I a ' U . U ' > o J O J 0 ' < I I w9 w z coo Z 2 I H W m w 28 • cn Q O O IY w I i- N I- N < 2 IL CO — I 225A � o (50 KAIC) O< ' 5N (3 POLE) I z ct ct OI Y m° I! % o ' w0 I ; MAINTENANCE BYPASS I >- (w ---------' ATS I co w 0 I- I c < I E,_w O w= -) 0~ Z 50-PNL-001-01 I w 0 225 C� 225A, 480V, 3PH, 3W, 30 KAIC I cC z l- B Zw z w � 60 ) 60 ) 60 ) 60 ) 20 ) I J Q 0_ z= I I I- Lij�o ' w =>- I t oz I Q 0 r ctO I I O C7 0 Z 2 O, Filter Control Filter Control Filter Control Filter Control O zz co ct Panel Panel Panel Panel I z 0 w A 50-XFMR-001-01 I a 0i `",,`"'"" 15 KVA I a — 480-208Y/120V I Q Z � wo ct O 0 20 5 20 5 20 5 20 5 OI-0 PNL I m O 0 0 0 w O Qo Io zz O > Y zcn 0_ E> I O < oT D O O o o om o rig M CO CO 0- N- di- ,__,'I" N I Q �0 I d �' ' f 2 N 11 O 1 2 N 9i rl 2 N 9i I Y J i 1< � � � Jo Hwo Ho JQo wo JQo � o o < O 1� J _ _ o pp Li [1- � cK LL 2 � > ii LI > � 2 W > ZU ' _ _ _ I- z w Qo (Yo Qd 0 ( O0- Y YVa Yp d _ _ Qo (q � = Qo (n . Q I C , OmLn Oun Omer, El OmLn ES OmLn EiL9 Lo � I 0 0 I LL 0 '------------------------------------------------------------J w CO D w CC 2 Q LO) _i i2 < 0 Ai z O < p Q � o V i2 U III GIL L z ONE-LINE DIAGRAM '7 w iii 12" = 1'-0" z O D 12" = 1-0" VERIFY SCALE BAR IS ONE INCH ON ORIGINAL DRAWING. 0 1" DATE MARCH 2026 PROJ BJO0152J DWG 50-E-6001 SHEET 46 Autodesk Docs://US OR_BPO0152J_Lake Oswego_DBO WWTF/050-E_RVT2024.rvt PLOT DATE/TIME: 3/24/2026 4:03:54 PM Jacobs _ __ _ _. _ _ . _ ... _ _ _.... -•.• . . . � t. . • ',-::" , ,..: ' ' 0 ii i+, ,.cc .... r. 1.- ' _.__ , lI I Ill :., 4»+ BSc, i tiffs w 4 IC t ' v - r t _ .,,,,3 m A Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emainine Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Lake Oswego BAFO 260817 1380 1380 14-Sep-26 30-Jan-32 Milestones :59 1359 13-Oct-26 30-Jan-32 A3520 Notice of Award 0 0 13 Oct-26' • No;fce of Award A3530 Project Kickoff Meeting 2 2 02-Nov-26 03-Nov-26 I Project Kickdff Meeting A5810 Notice to Proceed 0 0 02-Nov-26* • Notice to Proceed A6000 Construction Complete 0 0 29-Nov-30 H ♦ Construction Complete A6250 Substantial Completion 0 0 21-Apr-31 • Substantial Completion A6001 Project Acceptance Date 0 0 01-Aug-31 • ProjectAcceptance Date A6260 Scheduled Acceptance Date 0 0 01 Sep 31" ♦ Scieduled Acceptance Date A6280 Anal Completion 0 0 30-Jan-32 : • ;Final Completion Engineering, Design, Preconstruction 443 443 14-Sep-26 28-Jun-28 DELIVERABLE MILESTONES Imiu Mli_ 02-Nov-26 07-Jun-28 A3540 DP1 -90%Demolition Package Complete 0 0 02-Nov-26 • DP1 =90%Demolition Package;Compete A6240 DP1 -100%Demolition Package Complete 0 0 11-Dec-26 • DP1 100%Demolition Package Complete A3560 DP2-30%Storm/Sewer Reroute 0 0 22-Feb-27 •DP 30%St 2 orm/Sew route er Re A3570 DP2-100%Storm/Sewer Reroute 0 0 16-Mar-27 • DIP2'.-:100%Stotm/SeWeyr Reroute : : : A3630 DP5-Main Plant Package-Conceptual Design Complete(30%Design) 0 0 20-Apr-27 • 0P5 Main Plant;Paokage:Gonkptual;l es'gn Complete(30%Design) A6230 DP4-Early Concrete Package-Conceptual Design Complete(30%Design) 0 0 20-Apr-27 ♦:DP4-Early Concrete Package-'Conceptual Design Complete(30%Design) A3580 DP3-90%Deep Foundation Design Package 0 0 27-May-27 ♦ DP3-90%Deep Foundation Design Package A3590 DP3-100%Deep Foundation Design Package 0 0 16-Aug-27 • Dpi 100%Deep';Foundation Design package A3640 DP5-Main Plant Package-Intermediate Design Complete(60%Design) 0 0 13-Sep-27 • DP5-Maui Plant Package-Intermediate Design Complete(6 )?Dersign) A3610 DP4-90%Early Concrete Package Complete 0 0 21-Dec-27 ; •,DP4-9Q%early,Concrete Package Complete; A3650 DP5-Main Plant Package-Detail Design Complete(90%Design) 0 0 02-Feb-28 :♦ DR5-Main:Plant Package Detail Design'Complete t90%Design) A3620 DP4-100%Early Concrete Package Complete 0 0 23-Mar-28 • DP4 100%Early Concrete Package Complete A3660 DP5-Main Plant Package-Contract Documents Complete(100%Design) 0 0 07-Jun-28 DP5 Main Plant Package Contract'Documents Co mplete(100%Design) ENGINEERING,DESIGN,PRECONSTRUCTI. 14-Sep-26 07-Jun-2 ON-CALL CONTRACT 20 14-Sep-26 9-Oct-2 A6010 Building HAZMAT Investigations 20 20 14 -26" 09-Oct-26 0 Building HAZMAT IhUe tiga#iart5 A6020 Kickoff Demoliiton Permit 1 1 14 -26" 14-Sep-26 I Kickoff Derpol'iton Permit P1 -DEMOLITION PACKAGE 119 15-Sep-2 A3800 DP1 Engineering for Permit Application(Complete Form) 20 20 15-Sep-26 12-Oct-26 DR1 Engineeririg for PerrnitApplication(Complete Form) A3900 DP1 -Demolition Permit-Submit to Client(Handoff to Permitting) 0 0 02-Nov-26 • DP1 Demolition Permit Submit to CI'ent(Hand;off to Permitting) A5830 Preconstruction Bird Survey(Closer to Bird Window) 5 5 22-Feb-27 26-Feb-27 I Preconstruction Bind Survey(Closer to Bird Window) ; I DP2-STORM/SEWER REROU = •7 02-Nov-26 Mar-2 DP2-30%Storm/Sewer Reroute 81 81 02-Nov-26 22-Feb-27 A4060 DP2-Storm/Sewer Reroute 30%Engineering(Locates,Potholing,Survey) 80 80 02-Nov-26 19-Feb-27 NM QP2-Storm/Sewer Reroute 30%Engineering(Locates,PothQl rig,:SUNey) L A4160 I DP2-30%Storm/Sewer Reroute-Submit to Client(Handoff to Permitting) 1 1 I 22-Feb-27 I 22-Feb-27 I DP2.-30%Storm/Sewer Reroute-Submit to Client(Handoff to Permitting) DP2-100%Storm/Sewer Reroute 6 6 09-Mar-27 16-Mar-27 A4180 DP2-Storm/Sewer 100%Engineering 5 5 09-Mar-27 15-Mar-27 DP2 Storm /sewer 100%Engineering A4300 DP2-100%Storm/Sewer Reroute-Submit to Client(Handoff to Permitting) 1 1 16-Mar-27 16-Mar-27 I DP2 100%Storm Sewer Reroute Submit'to Client'(Hendoff to Permitt rtg) ■ HOR THWO DP3-90%Deep Foundations 149 149 02-Nov-26 27-May-27 : • • • • •• : • A4310 DP3-Deep Foundations/Shoring/Early Earthwork 90%Engineering 148 148 02-Nov-26 26-May-27 p Deep Foundations/Shoring/Early Earthwork 90%Engineering kA4430 DP3-90%Design-Submit to Client(Handoff to Permitting) 1 1 27-May-27 27-May-27 ! DP3 90%Design_Submit to Client(Handoff to Permitting MIM Actual Work Critical Remaining Work Page 1 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emainine Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q DP3-100%Deep Foundation ..miii AIM 30-Jul-27 13-Aug-27 r A4490 DP3 Deep Foundations 100%Engineering 10 10 30-Jul-27 12-Aug-27 I DP3-deep f=oundations 100%Engineering . . I A4550 DP3-100%Deep Foundation-Submit to Client(Handoff to Permitting) 1 1 13-Aug-27 13-Aug-27 I DP3-100%Deep FoUlndation-Submit to CI ent(Handoff to Permitting) DP4- . ' - .• • - IDP4-90%Early Concrete Package 106 106 27-Jul-27 21-Dec-27 A4680 DP4-Early Concrete Package 90%Engineering(Requires DP5 60%) 105 105 27-Jul-27 20-Deo-27 DR4 Early Concrete Package 90%Engireerin9(Requires DP5 60°/) A4800 DP4-90%Early Concrete Package-Submit to Client(Handoff to Permitting) 1 1 21-Dec-27 21-Dec-27 t D -90%P4 Early Concrete Package-Submit to C4ent(Handoff to Permitting) DP4-100%Early Concrete Package 23 23 22-Feb-28 23-Mar-28 • A4860 DP4-Early Concrete Package 100%Engineering 22 22 22-Feb-28 22-Mar-28 I DP4-Early Concrete Padtage 100%Ehgiheerlhg A4980 DP4-100%Early Concrete Package-Submit to Client(Handoff to Permitting) 1 1 23-Mar-28 23-Mar-28 DP4-100%Early ConciMta Package-Sugmit to CI'ent(Handoff t4 Permitting) • Conceptual Design(30%Design) 02-Nov-26 20-Apr-27 A4990 DP5-30%Engineering 80 80 02-Nov-26 19-Feb-27 DP5-30%Engineering A5000 DP5-30%Process Input Cutoff 0 0 22-Feb-27 DP5-30%Process Input Cutoff ■ A5010 DP5-30%Engineering Input to Model cutoff 0 0 15-Mar-27 • DP5 r 30%Ehgirteering:Input to Mbdet bUtbff A5020 DP5-Modeling Cutoff 0 0 06-Apr-27 • 0P5,-Modeling'Cutoff ' A5030 DP5-Engineering(Drawings and Specs)Cutoff 0 0 20-Apr-27 ♦••DP5-Engineering(Drawings and Specs)Cutoff Intermediate Design(60%Design) 104 104 20-Apr-27 13-Sep-27 A5140 DP5-60%Engineering 70 70 20-Apr-27 26-Jul-27 II DP5-60%i ngineenng • A5150 DP5-60%Process Input Cutoff 0 0 27-Jul-27 I ♦ DP5-60%Prbbess Input Cutoff A5160 DP5-60%Engineering Input to Model cutoff 0 0 12-Aug-27 • DP5.60%,Engineering Input to Model cutoff ° P5 odeli 'g Cutoff.. ...... ..... • .. .. • ........ ■ A5170 DP5-60/°Modeling Cutoff 0 0 30-Aug-27 • D 60%Modeling A5180 DP5-60%Engineering(Drawings and Specs)Cutoff 0 0 13-Sep-27 • DP5 60%Engineering(Drawings and Specs)Cutoff Detailed Design(90%Design) 102 102 13-Sep-27 02-Feb-28 • A5290 DP5-90%Engineering 62 62 13-Sep-27 07-Dec-27 M: DP5-90%Eng neerihg :: A5300 DP5-90%Process Input Cutoff 0 0 08-Dec-27 • DP5-00%PrgceSs Input Cutoff • A5310 DP5-90%Engineering Input to Model cutoff 0 0 29-Dec-27 • DP5-90%Engineering Input to Model cutoff A5320 DP5-90%Modeling Cutoff 0 0 19-Jan-28 • DP5-90%Modeling Cutoff • A5330 DP5-90%Engineering(Drawings and Specs)Cutoff 0 0 02-Feb-28 • t)P5-90%Engineering(Drawings and Specs)Cutoff Contract Documents(100%Design) 46 46 05-Apr-28 07-Jun-28 A5500 DP5-100%Engineering 45 45 05-Apr-28 06-Jun-28 aE [P5 t 100%°Fngine?ring A5630 DP5-100%Submit to Client 1 1 07-Jun-28 07-Jun-28 I DP5 100%Submit to Client PE- ' - . I LAND USE PERMI 27-Oct-2. • A3670 Land Use Permit-Submit Pre-Application Meeting Request 4 4 27-Oct-26 30-Oct-26 I Land Use Permit-Submit Pre-Application Meeting Request A6140 Land Use Permit-City Review of Pre-Application Meeting Request 20 20 02-Nov-26 27-Nov-26 1 Land Use Permit jcitY Review of PM-Application Meeting',Request A6220 Land Use Permit-Pre-Application Conference 1 1 30-Nov-26 30-Nov-26 I Larid Use Permit PteApplicatibn Conference A5890 Land Use Permit-Finalize Site Plan(See 30%Design) 0 0 11-Dec-26 ♦ Lend Use Permit-Finel'ze Site Plan(See 30%Design) A6150 Land Use Permit-Neighborhood Meeting 1 1 14-Dec-26 14-Dec-26 I Land Use Permit-Neighborhood'Meeting A6160 Land Use Permit-Draft Application 24 24 15-Dec-26 28-Jan-27 ■ :Land Use Permit-Draft Application :: A6170 Land Use Permit-Application Submittal 10 10 29-Jan-27 11-Feb-27 1] Land Use Permit-Application Submittal A6180 Land Use Permit-Completeness Letter 21 21 12-Feb-27 12-Mar-27 0 Land Use Permit-Completeness Letter A6190 Land Use Permit-Response to Completeness 14 14 15-Mar-27 01-Apr-27 b Land Use Permit-Response t4 Completeness A6200 Land Use Permit-Deemed Complete 1 1 02-Apr-27 02-Apr-27 I Land Use Permit-Deemed Complete A6210 Land Use Permit-Anal Decision 63 63 05-Apr-27 01-Jul-27 O Land Use Permit:-Final Decision DP1 -DEMOLITIO Actual Work Critical Remaining Work Page 2 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emaininc Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration QQQQQQOOOQQQQQQQQOOOOQQOOOOQQQOOQQQOOOQQQQQQ A3920 DP1 City of Lake Oswego Demolition/SWMP Permit Review 30 30 02-Nov-26 11-Dec-26 ID DP1:-City of Lake Oswego Demolition/SWMP Permit Review A3720 DP1 -City of Lake Oswego Demolition/SWMP PermitAppoval 0 0 I 11-Dec-26 ♦ DP1 -City of Lake Oswego Demolition/SWMI PermitAppoval DP2-STORM/SEWER REROU : 21 21 — 23-Feb-2 A6070 DP2-Storm/Sewer Reroute Permit Review, 1st Review and Comments 10 10 23-Feb-27 08-Mar-27 1 DP2 Storm•/SeV r Reroute Permit Review, 1st Revievu arid Comments P Storm/Sower rout w,end Review a p pp e Permit R A6080 DP2-Storm/Sewer Reroute Permit Review,2nd Review and Approval 5 5 17-Mar-27 23-Mar-27 I Di* Re �A DP3-DEEP FOUNDATIONS/SHORING/EARLY EARTHWOR - -'I•- 7 A4450 DP3-Deep Foundations/Shoring/Early Earthwork Permit Review 1st Review and Commer 45 45 28-May-27 29-Jul-27 • DP3-Deep Foundations/Shoring%;Early EarthWOrk Permit Review 1st Review and Comments A3750 DP3-Deep Foundations/Shoring/Early Earthwork Permit Review 2nd Review and Approva 6 6 16-Aug-27 23-Aug-27 1, DP3 Deep Foundations/:Shoring I Early Earthwork,Permit Review;2nd Review and:Approval - ' -'pr-28 : : :: : : :. : :: : : : A4820 DP4-Early Concrete Permit Review, 1st Review and Comments 45 45 21-Dec-27 21-Feb-28 ■ DP4 H Early Concrete Permit Review 1st Review and Comments A4830 DP4-Early Concrete Permit Review,2nd Review and Approval 10 10 23-Mar-28 05-Apr-28 I DP4,Early Concrete Permit Review,2nd Review and.Approval 'I P5-MAIN PLANT PACKAGE-BUILDING PERM! 106 106 02-Feb-28 28-Jun-28 A5460 DP5 Main Design Package Review, 1st Review and Comments 45 I 45 L 02-Feb-28 04-Apr-28 In DP5 Main Design Package Review, 1st Rev'ewand Comments A5480 DP5-Main Design Package Review,2nd Review and Approval 15 15 08-Jun-28 28-Jun-28 DR5 Main Design Package Review,2nd Review and Approval Construction 1318 1318 11-Dec-26 30-Jan-32 Milestones 305 02-Dec-30 30-Jan-3 PH2-28 Construction Work Complete o 0 02-Dec-30 • Construction Work Complete A5870 Holiday and Weather Buffer 30 30 03-Jul-31 01-Aug-31 I Hblidey and Weather Buffer PH2-29 Punchlist&Closeout 130 130 01-Aug-31 30-Jan-32 NM Punchlist&Closeout A6270 Acceptance Date 0 0 01-Aug-31 ♦ Acceptance Date Demolition and Investigations Dec-26 23-Aug-27 I Milestones Dec 26 11-Dec-26 A6030 DP1 -Demolition/SWMP Permit Approval(Duplicate) 0 0 11-Dec-26 ♦ DPI-Demolition/SWMP Permit Approval(Qupl'cate) Site Clearing and Demolition 1- - 'pr-27 A6040 Mobilization 10 10 11-Dec-26 05-Jan-27 1 Mobilization PH2-38 SWMP 10 10 06-Jan-27 19-Jan-27 II SWMP PH2-42 Utility Safe Off, Removal,Relocation 15 15 06-Jan-27 26-Jan-27 p Utility Safe Off, Removal,.R Iggtipn PH2-43 Temporary Fence and Gates 10 10 06-Jan-27 19-Jan-27 II Temporary Fence and Gates PH2-40 Tree Removal 5 5 20-Jan-27 26-Jan-27 I Tree Removal PH2-37 Clear/Grub 10 10 27-Jan-27 09-Feb-27 I Par./Grub PH2 9 Facility Demolition 40 40 27-Jan-27 23-Mar-27 • Facility Defnblit on PH2-41 Site Demolition 15 15 24-Mar-27 13-Apr-27 Site Demolitign Earthwork Subcontracto •- 11-May-27 • • • • • • :: A6050 Geotechnical/Subsurface Investigations(Soils,Rock) 20 20 14-Apr-27 11-May-27 I Geotechnical/Subsurface Investigations(Soils,Rock) • Hazardous Mals 3-Aug-27 7 : : PH2-47 I Hazardous Soils Investigation 60 60 14-Apr-27 06-Jul-27 CI Hazardous So Is Investigation 4 PH2-48 I Hazardous Soils Remediation(If/As Needed) 34 34 07-Jul-27 23-Aug-27 p Hazardous Soils Remediation;(If/As Needed) Deep Foundations and Earthwo 17-Mar-27 05-Apr-28 41 Milestones L 23-Mar-27 23 Aug A6060 DP2-Storm/Sewer Relocation Permit Approval(Duplicate) 0 0 23-Mar-27 • p' R?' -Storm I Sewer Re ocation Permit Approval(Dup icate) A6090 DP3 Deep Foundations/Shoring/Early Earthwork Permit Approval(Duplicate) 0 0 23-Aug-27 DP3-Deep Foundations/Shoring/Early Earthwork Perm itApp(oval(Duplicate) A6100 DP3-Temporary Construction Office Permit Approval 0 0 23-Aug-27 DP3 temporary Construction Office Permit Approval Earthwork Subcontractor A1460 Storm/Sewer Relocations(Coordinate with Investigations) 114 114 17-Mar-27 23-Aug-27 Stbmi/Sewer Relb tibns(Cbbrdiriate 4h:Invest gation5) A1470 Structural Excavation/Blasting/Rock Removal/Shoring/Dewetering 162 162 24-Aug-27 05-Apr-28 Structural Sxcavatign/Blasting/Rock Removal/Shoring/;Qewatering Actual Work Critical Remaining Work Page 3 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emainine Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) QOOOQQOOOQQQOOOQQQOOOQQQQOOQQQOOQQQOOOQQQQQQ A1510 Temporary Facilities/Utilities 40 40 24-Aug-27 18-Oct-27 ❑ Temporary Facilities/Utilities I Deep Foundations Subcontractor Allik AIMIL62 24-Aug-27 05-Apr-28 , A5840 Mobilization 5 5 24-Aug-27 30-Aug-27 I Mobilization PH2-76 Clarifiers 95 95 31-Aug-27 10-Jan-28 •'Clarfbr5 PH2-77 Filters/UV 25 25 31-Aug-27 04-Oct-27 Filters/UV PH2-78 Influent Pump Station 20 20 05-Oct-27 01-Nov-27 Influent Pump Station PH2-79 Headworks/Solids 25 25 02-Nov-27 06-Dec-27 Headworks/Solids PH2-80 Electrical Building 25 25 07-Dec-27 10-Jan-28 ■ leotrical Building PH2-81 Contingency on Drilling(Completed before Early Concrete) 62 62 11-Jan-28 05-Apr-28 Cbhtingertcy bn Drill rfg(Completbd before Early Concrete) Main Constructi• 648 24-Mar-28 18-Sep-301 Milestones 59 05-Apr-28 9 Jun-28 A6110 Deep Foundations Complete(Duplicate) 0 0 05-Apr-28 * Deep Foundafgns Complete(Duplicate) A6120 Site Earthwork/Shoring/Rock Removal/Dewatering Ready for Priority Concrete 0 0 05-Apr-28 • Site Earthwdrk/'Shoring/Rock Removal/Dewatenng Ready for Priority Concrete PH2-87 DP4-100%Sealed Design, Early Concrete 0 0 06-Apr-28 ♦ DP4-100,°Lo;Sealed Design,Early Concrete PH2-88 DP5-100%Sealed Design, Main Design 0 0 29-Jun-28 ♦',DP5-100%Sealed Design, Main Design " re le -Jun-28 18 Se = , PH2-94 I Yard Piping(TBE) 340 340 29-Jun-28 17-Oct-29 Yard Piping(TBE) A6130 Final Site Grading and Landscaping(TBE) 80 80 30-May-30 18-Sep-30 =1 :Final Site Grading and Landscaping(TW Administration Buildi , 299 08-Sep-2: H A1680 Facility 10-Administration Building-Earthwork/Grading/Underslab 30 30 08-Sep-28 20-Oct-28 • Facility 10-Administration Building-Earthwork/Grading/Underslab A1690 Facility 10-Administration Building-Concrete 40 40 20-Oct-28 14-Dec-28 ■ Facility 10-Administration Building-Concrete A1700 Facility 10-Administration Building-Insulated Precast Wall Panels 10 10 15-Dec-28 28-Dec-28 U Facility 10-Administration Building-Insulated Precast Wall Panels A1710 Facility 10-Administration Building-Precast HPC 5 5 29-Dec-28 04-Jan-29 I Fadlity 10-Adhiihiatration Building r Pietast HPC A1730 Facility 10-Administration Building-Built-Up Roofing 20 20 05-Jan-29 01-Feb-29 I Facility 10-Administration Building Built-Up Roofing A1740 Facility 10-Administration Building-Openings 20 20 02-Feb-29 01-Mar-29 IJ Facility 10-Administration Building:Openings y din -• -A1750 Facility 10-Building Dried In 0 0 02-Mar-29 ♦ Facilit 10 Buil d i rig Dried in A1760 Facility 10-Administration Building-Building Trades 80 80 02-Mar-29 21-Jun-29 Il Facility 10=Administration Building-Building Trades A1770 Facility 10-Administration Building-Plumbing 100 100 02-Mar-29 19-Jul-29 0 Facility 10 Administration Building-Plumb ng A1780 Facility 10-Administration Building-HVAC 100 100 02-Mar-29 19-Jul-29 I' ' I Facility 10 iAdminiStration Building-HVAC A1790 Facility 10-Administration Building-Electrical 120 120 17-May-29 31-Oct-29 [ Facility 10 Administration Building-Electrical A1800 Facility 10-Administration Buidling-Ready for Commissioning 0 0 01-Nov-29 •♦ Facility 10 Admin'stration Buid ling-Ready for Commissioning aintenance Building 219 ' 03-Nov 2 A1810 Facility 12-Maintenance Building-Earthwork/Grading/Underslab 30 30 03-Nov-28 15-Dec-28 ■ Facility 12-Maintenance Building-Earthwork/Grading./Undersiab A1820 Facility 12-Maintenance Building-Concrete 15 15 15-Dec-28 04-Jan-29 0 Facility 12-Maintenance BUildin'g-Concrete A1830 Facility 12-Maintenance Building-Insulated Precast WaI Panels 10 10 05-Jan-29 18-Jan-29 II Facility 12-Maintenance Building, Insulated Precast WaI Pari i$ A1840 Facility 12-Maintenance Building-Precast HPC 10 10 19-Jan-29 01-Feb-29 0 Facility 12-Maintenance'Building H Precast'HPC A1860 Facility 12-Maintenance Building-Built-Up Roofing 20 20 02-Feb-29 01-Mar-29 I Facility 12-Maintenance Building-Built-Up Roofing A1870 Facility 12-Maintenance Building-Openings 20 20 02-Mar-29 29-Mar-29 • ,Facility 12-Maintenance Building-Openings A1880 Facility 12-Building Dried In 0 0 30-Mar-29 ♦ Facility 12-Building Dried Iii A1890 Facility 12-Maintenance Building-Building Trades 60 60 30-Mar-29 21-Jun-29 • Facility 12-,Maintenance Building Building Trades A1900 Facility 12-Maintenance Building-Plumbing 80 80 30-Mar-29 19-Jul-29 W Facility 12 Maintenance Building-P umbing A1910 Facility 12-Maintenance Building-HVAC 80 80 30-Mar-29 19-Jul-29 W Facility 12 Maintenance Building-HVAC A1920 Facility 12-Maintenance Building-Electrical 80 80 17-May-29 05-Sep-29 i=l Facility 12 Maintenance Building-Electrical A1930 Facility 12-Maintenance Building-Ready for Commissioning 0 0 06-Sep-29 • Facility 12.-Maintenance Building-Ready for Commissioning • Influent • :: • •• • • • • • • .. A1970 Facility 20-Influent Pump Station-Concrete 150 150 24-Mar-28 19-Oct-28 r 1 Facility 20-Influent Pump Station y Concrete MIM Actual Work Critical Remaining Work Page 4 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emaininc Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) QOOOQQOOOQQQOOOQQQOOOQQQOOOQQQOOQQQOOOQQQQQQ A1980 Facility 20-Influent Pump Station-Painter 50 50 11-Aug-28 19-Oct-28 O Facility 20-Influent Pump Station-Painter A1990 Facility 20-Influent Pump Station-Structural Backfill 15 15 20-Oct-28 09-Nov-28 I Facility 4 Influent pump Station-Structural Backfill A2000 Facility 20-Influent Pump Station-Metals 20 20 20-Oct-28 16-Nov-28 I Facility 20_Influent Pump Station-Metals A2010 Facility 20-Influent Pump Station-Process Mechanical 60 60 17-Nov-28 08-Feb-29 IC Facility 20-Influent Pump Station-Process'Mechanical A2020 Facility 20-Influent Pump Station-Insulation 20 20 12-Jan-29 08-Feb-29 0 Facility 20-Influent Pump Station-Insulation A2030 Facility 20-Influent Pump Station-Painter 20 20 09-Feb-29 08-Mar-29 0 Facility 20-Influent Pump Station-Painter A2040 Facility 20-Influent Pump Station-Electrical 80 80 17-May-29 05-Sep-29 'I=I Facility 20-Influent Pump Station-Electrical A2050 Facility 20-Influent Pump Station-Ready for Commissioning 0 0 06-Sep-29 ♦ Facility 20-Inf uent Pump Station-Ready for Comnriss on rig A2190 Facility 22-Odor Control 1 -Process Mechanical 40 40 17-May-29 11-Jul-29 I Fadlity 22 Odor control 1 -Process Mechanical A2200 Facility 22-Odor Control 1 - Electrical 40 40 12-Jul-29 05-Sep-29 • Facility 22-Odor Control 1 - Electrical r-tormwater Pump Statio i 18-Oct-291 A2210 Yard Pipe Tie 1 1 i 18-Oct-29 18-Oct-29 I Yard Pipe Tie A2220 Facility 28-SDPS-Process Mechanical 20 20 19-Oct-29 15-Nov-29 I; Facility 20-SDPS-Process Mechanical A2230 Facility 28-SDPS-Electrical 30 30 19-Oct-29 29-Nov-29 ■ Facility 28-SDPS-EteCttit al • ks/S• i•- -an. in• 06Apr 5-Oct-29 • A2240 Facility 25-Headworks/Solids-Concrete 225 225 06-Apr-28 14-Feb-29 DINIIIII Facility 25 t Headwork$I$olicIS'QQncr tq A2250 Facility 25-Campbell Manor-Painter 120 120 31-Aug-28 14-Feb-29 Facility 25 Campbell Manor-Painter A2270 Facility 25-Campbell Manor-Metals 40 40 18-Jan-29 14-Mar-29 El Facility 25;Campbell Manor-Metals A2260 Facility 25-Campbell Manor-Structural Backfill 20 20 15-Feb-29 14-Mar-29 0 Facility 25;Carript el,l Manor-Stnietural Backfill A2280 Facility 25-Campbell Manor-Process Mechanical 130 130 15-Mar-29 12-Sep-29 I I Fat;ility 25_Campbell Manor' Process Mechanical A2310 Facility 25-Campbell Manor-Electrical 160 160 15-Mar-29 24-Oct-29 I ' ' ' I Facility 25 Campbell;Manor-Electrical A2290 Facility 25-Campbell Manor-Insulation 20 20 16-Aug-29 12-Sep-29 0 Facility 25 Campbell Manor H Insulation A2300 Facility 25-Campbell Manor-Painter 20 20 13-Sep-29 10-Oct-29 0 Foci ity 25-Campbell Manor-Painter A2320 Facility 25-Campbell Manor-Ready for Commissioning 0 0 25-Oct-29 11:Facility 25-Campbell Manor-Ready for Commissioning or Control 2 A2460 Facility 26-Odor Control 2-Earthwork/Grading/Underslab 10 10 22-Dec-28 05-Jan-29 0 Facility 26 Odor Control 2-EarthtMlrk/Grad rig/Underslab A2470 Facility 26-Odor Control 2-Concrete 10 10 05-Jan-29 18-Jan-29 I Facility 26 Odor Cqntrpl 2 cQngrgte A2480 Facility 26-Odor Control 2-Process Mechanical 30 30 17-May-29 27-Jun-29 0 Facility 26 Odor Control 2 Process Mechanics A2490 Facility 26 Odor Control 2-Electrical 30 30 17-May-29 27-Jun-29 1 Facility 26 Odor Control 2-Electrical Main Electrical Building r 18-Jan-29 30-May-30- I A2500 Facility 27-Main Electrical Building-Concrete 20 20 18-Jan-29 14-Feb-29 0 Facility 27-Main Electrical Building-Concrete A2510 Facility 27-Main Electrical Building-Insulated Precast Wal Panels 15 15 15-Feb-29 07-Mar-29 I Facility 27-Main Electrical Building-Insulated Precast Wal Panels A2520 Facility 27-Main Electrical Building-Precast HPC 10 10 08-Mar-29 21-Mar-29 I Facility 27-Main Electrical,$gilding-Precast-IPC „„ ..„ ..._„ - A2540 Facility 27-Main Electrical Building-Built-Up Roofing 20 20 22-Mar-29 18-Apr-29 I: Facility 27 Main Electrical Roofing Building-Built-Up oofing A2550 Facility 27-Main Electrical Building-Openings 20 20 19-Apr-29 16-May-29 I Facility 27-Main Electrical Bui ding-Openings A2560 Facility 27-Building Dried In 0 0 17-May-29 • Facility 27=Building Dried'in A2590 Facility 27-Main Electrical Building-HVAC 80 80 17-May-29 05-Sep-29 0 FaCility27;-Main Electrical Build ng-HVAC A2610 Facility 27-Main Electrical Building-Electrical 270 270 17-May-29 29-May-30 IIIIIIIIIMI Facility 2t";Main Electrical$wilding-Electrical A2620 Facility 27-Main Electrical Building Ready for Commissioning 0 0 30-May-30 • Facility 27-Main Electrical Building-Ready- y din for Commissioning Generators A2630 Facility 27a-Generators-Earthwork/Grading/Underslab 10 10 05-Jan-29 19-Jan-29 0 Facility 27a-Generators-Earthwork/Grading/Unders ab 1 A2640 Facility 27a-Generators-Concrete 10 10 19-Jan-29 01-Feb-29 Facilify'27a Generators ';Concrete A2650 Facility 27a-Generators-Electrical 30 30 17-May-29 27-Jun-29 O Facility 27a-Generators-Electrical Plant D A2660 Yard Pipe Tie 1 1 18-Oct-29 18-Oct-29 I Yard Pipe Tte MIM Actual Work II- Critical Remaining Work Page 5 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original temainin$ Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) QQQOQQQQQQQQQQQQQQQQQOOOOOOOOOOOQQQQQQQQQOQQ A2670 I Facility 28-PDPS-Process Mechanical 20 20 19-Oct-29 15-Nov-29 I: Facility 28-PDPS-Process Mechanical A2680 Facility 28-PDPS-Electrical 30 30 19-Oct-29 I 29-Nov-29 ■ Facility,2$-PDPS:-Electrical Aeration Basins 560 06-Apr-28 30-May-30 A2690 Facility 30-Aeration Basin-Concrete 280 280 06-Apr-28 02-May-29 Facil ty 30-Aeration Basin=Cdr Crete A2700 Facility 30-Aeration Basin-Precast HPC 10 10 19-Apr-29 02-May-29 d Facility 30-Aeration Basin Precast HPC A2710 Facility 30-Aeration Basin-Painter 100 100 03-May-29 19-Sep-29 1♦ Facility 30'7Aeration Basin-Painter A2740 Facility 30-Aeration Basin-Process Mechanical 150 150 17-May-29 12-Dec-29 il Facility'30-Aeration Basin_Process Mechanical A2730 Facility 30-Aeration Basin-Metals 40 40 26-Jul-29 19-Sep-29 • Facility 3;U Aeration basin'-:Metals A2720 Facility 30-Aeration Basin-Structural Backfill 20 20 20-Sep-29 17-Oct-29 • 30:Fatuity' Aeratibh'Basin-Structural:Ba- Ckfil A2770 Facility 30-Aeration Basin-Electrical 180 180 20-Sep-29 29-May-30 111111111 Facility 30 Aeration Basin;-Blectrical A2750 Facility 30-Aeration Basin-Insulation 20 20 15-Nov-29 12-Dec-29 II Facility;30-Aeration Basin-Insulation A2760 Facility 30-Aeration Basin-Painter 20 20 13-Dec-29 09-Jan-30 0 Facility 30-Aeration Basin-.Painter A2780 Facility 30-Aeration Basin-Ready for Commissioning 0 0 30-May-30 ♦ Facility 30 Aeration basin Deady for Commissioning Blower Building A2800 Facility 35-Blower Building-Insulated Precast WaI Panels 10 10 03-May-29 16-May-29 I Facility 3.5.BlO er Building 7 Insulated Precast WaI Panels A2810 Facility 35-Blower Building-Precast HPC 5 5 17-May-29 23-May-29 I Faclity 35 L;Blpwer Bu'Iding PrecastHPQ A2830 Facility 35-Blower Building-Built-Up Roofing 15 15 24-May-29 13-Jun-29 O• Facility 35-Blower Building-Built-Up Roofing A2840 Facility 35-Blower Building-Openings 15 15 14-Jun-29 04-Jul-29 1 Facility 35-Blower Building-Openings A2850 Facility 35-Building Dried In 0 0 05-Jul-29 • Facility 35-building Dried In A2880 Facility 35-Blower Building-HVAC 20 20 05-Jul-29 01-Aug-29 1 Facil ty 35-blower Building-HVAC A2890 Facility 35-Blower Building-Process Mechanical 40 40 05-Jul-29 29-Aug-29 Facility 35-Blov r Building,-Process Mechanical A2900 Facility 35-Blower Building-Electrical 40 40 05-Jul-29 29-Aug-29 U] Facility -Blower Building-Electrical pr-30 A2910 Facility 40-Clarifiers-Concrete 250 250 15-Feb-29 30-Jan-30 Facility 40-Clarifers-Concrete A2940 Facility 40-Clarifiers-Metals 30 30 20-Dec-29 30-Jan-30 IF Facility 40-Clarifiers-Metals A2920 Facility 40-Clarifiers-Precast HPC 10 10 17-Jan-30 30-Jan-30 0 Facility 40-Clarifiers-Precast HPC A2930 Facility 40-Clarifiers-Structural Backfill 15 15 31-Jan-30 20-Feb-30 D Facility 40-,Clarifiers-Structural Backf II A2950 Facility 40-Clarifiers-Process Mechanical 60 60 31-Jan-30 24-Apr-30 O Facility 40-Clarifiers-Process Mechanical A2980 Facility 40-Clarifiers-Electrical 60 60 31-Jan-30 24-Apr-30 li Facility 40-Clarifiers-:Electrical A2960 Facility 40-Clarifiers-Insulation 20 20 28-Mar-30 24-Apr-30 13 Facility 40-Clarifiers-.Insulation A2970 Facility 40-Clarifiers-Painter 20 20 28-Mar-30 24-Apr-30 0 Fac lity 40-Clarifiers-Painter A2990 Facility 40-Clarifiers-Ready for Commissioning 0 0 25-Apr-30 ♦ Facility 40-Clarifiers-Ready for Commiss onipg A3010 Facility 50-Truck Loadout-Earthwork/Grading/Underslab 20 20 05-Apr-29 03-May-29 0 Faci ity 50:Truck Loadout-Earthwork I Grading/Underslab A3020 Facility 50-Filters-Concrete 148 148 03-May-29 26-Nov-29 O Facility.50.-Fitters-Concrete A3040 Facility 50-Filters-Painter 20 20 27-Nov-29 24-Dec-29 III Facility 50-':Filters-Painter A3060 Facility 50-Filters-Metals 30 30 27-Nov-29 07-Jan-30 ❑ Facility 50-Filters-Metals A3070 Facility 50-Filters-Process Mechanical 60 60 27-Nov-29 18-Feb-30 C] Facility 50 Filters-Process MePhartica ..... ... .... acilit Electrical A3100 Facility 50-Filters-Electrical 80 80 27-Nov-29 18-Mar-30 I] :Facility 50 Filters;Ele rical A3080 Facility 50-Filters-Insulation 20 20 22-Jan-30 18-Feb-30 0 Facility 50-Filters-Insulation A3090 Facility 50-Filters-Painter 20 20 19-Feb-30 18-Mar-30 0 Facility 50 Filters-Painter A3110 Facility 50-Filters-Ready for Commissioning 0 0 19-Mar-30 ♦.Facility 50-F Iter5-Ready fbt Commissioning UV Disinfectio . .. . . . . . . . . . A3120 Facility 55-UV Disinfection-Earthwork/Grading/Underslab 20 20 05-Apr-29 03-Ma -29 I Facility 55-UV Disinfection�Earthwork Y Y /Grading/tJnclerslab 03-May-29 Facility 55-UV Disinfection-Concrete A3130 Facility 55-UV Disinfection-Concrete 131 131 01-Nov-29 � , A3170 Facility 55-UV Disinfection-Metals 20 20 02-Nov-29 29-Nov-29 . !.Facility 55-UV Disinfection-Metals. Actual Work Critical Remaining Work Page 6 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emaininl Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) QQQQQQQQQQQQQQQQQQQQQOOQQOOOQOOOOOOQQQQQQQQQ A3180 Facility 55-UV Disinfection-Process Mechanical 40 40 02-Nov-29 27-Dec-29 ❑ Facility 55-:UV Disinfection Process Mechanical: A3190 Facility 55-UV Disinfection-Insulation 20 20 30-Nov-29 27-Dec-29 0 Facility 55-UV Disinfection Insulation A3210 Facility 55-UV Disinfection-Electrical 129 129 30-Nov-29 29-May-30 Facil ty 55-UV Disinfection Elect riCal A3200 Facility 55-UV Disinfection-Painter 10 10 28-Dec-29 10-Jan-30 . Facility 55-U,V Qisirf ection-Painter A3220 Facility 55-UV Disinfection-Ready for Commissioning 0 0 30-May-30 • Facility 55-UV Disinfection-Ready for Commissioning Truck Loa•o ,orma •pera ion •- -• A3230 Facility 60-Truck Loadout-Earthwork/Grading/Underslab 20 20 05-Jan-29 02-Feb-29 0 Faci ity 60-Truck Loadout-Earthwork/Grading/Underslab A3240 Facility 60-Truck Loadout-Concrete 40 40 02-Feb-29 29-Mar-29 IQ Facility 60-Truck Loadout'-Concrete A3250 Facility 60-Truck Loadout-Insulated Precast Wall Panels 10 10 30-Mar-29 12-Apr-29 I Facility 60-'fiudk Load Out- rlSulated Precast Wal Panels A3260 Facility 60-Truck Loadout-Precast HPC 5 5 13-Apr-29 19-Apr-29 I Facility 60-TrUck Loadout-Precast H PC A3280 Facility 60-Truck Loadout-Built-Up Roofing 15 15 20-Apr-29 10-May-29 0 Facility 60:Truck Loadout-Built-Up Roofing A3290 Facility 60-Truck Loadout-Openings 15 15 11-May-29 31-May-29 0 Facility 60-Truck Loadout-Openings A3300 Facility 60-Building Dried In 0 0 01-Jun-29 • FORS/60-Budding Dried In A3340 Facility 60-Truck Loadout-Process Mechanical 40 40 01-Jun-29 26-Jul-29 ❑ Facility 60-Truck Lbadolt-Process n/i .nah Cal A3350 Facility 60-Truck Loadout-Electrical 40 40 01-Jun-29 26-Jul-29 k] Fapfty 60-Truck Lgadout-Electrical A3360 Facility 60-Truck Loadout-Ready for Commissioning 0 0 27-Jul-29 • Facility 60-Truck Loadout-Ready for Commissioning Truck Loadout(Flooded O•-rati• A3370 Facility 61 -Emergency Truck Loadout-Earthwork/Grading/Underslab 10 10 16-Mar-29 30-Mar-29 I Facility 61 -Emergency Truck Loadout-Earthwork/Grading/Underslab A3380 Facility 61 -Emergency Truck Loadout-Concrete 10 10 30-Mar-29 12-Apr-29 I Facility 61 -Emergency Truck Loadout-Concrete A3390 Facility 61 -Truck Loadout-Process Mechanical 20 20 17-May-29 13-Jun-29 0 Facility 61 -Th i k Lbadbut 7 Prtdass M'edhanida A3400 Facility 61 -Emergency Truck Loadout-Electrical 30 30 17-May-29 27-Jun-29 U Facility 61 -Emergency Thick Loadout i Flecrjcal Commissioning & Startup 285 285 30-May-30 02-Jul-31 • Clean Water Testing-Functional&Systems Testing 30-May-30 21-Apr-31 A5860 Construction Buffer 132 132 30-May-30 29-Nov-30 Construction Buffer A3410 Temporary Recirculation Loop Online 0 0 29-Nov-30 • Temporary Recirculation Loop Online A3420 Headworks(Screening/Grit) 15 15 02-Dec-30 20-Dec-30 I HeadWOrks(Saeening/Grit) A3430 Influent Pump Station 10 10 23-Dec-30 03-Jan-31 I ,Influent Pump;Staticrt A3440 Storm WaterPump Station 5 5 06-Jan-31 10-Jan-31 I Storm woo r Pump Station A5660 UV Disinfection 15 15 06-Jan-31 24-Jan-31 0 UV Disinfedtbri A3450 Blowers 15 15 13-Jan-31 31-Jan-31 I Blower's A5670 W3 Pumps 5 5 27-Jan-31 31-Jan-31 I W3 Pumps A3460 Submersible Mixers 5 5 03-Feb-31 07-Feb-31 I Suprrlersible Mixers A5680 Sludge Mixing Pumps 5 5 03-Feb-31 07-Feb-31 I Slu' e Mixing puMps 4 A3470 Fine Bubble Diffusers 5 5 10-Feb-31 14-Feb-31 I Fine Bubble Diffusers A5690 Sludge Load Out Pumps 5 5 10-Feb-31 14-Feb-31 I Sludge Load O;ut'Pumps 4 A3480 Plant Drain Pump Station 5 5 17-Feb-31 21-Feb-31 I Plant Drain Pump station A5700 Thickening(RDT Feed,RDT Polymer) 15 15 17-Feb-31 07-Mar-31 0 Thigkening(ROT Feed RWT Polymer) A3490 Odor Control System 5 5 24-Feb-31 28-Feb-31 I Odor•Control System 4 A3500 Biofoam Pumps 5 5 03-Mar-31 07-Mar-31 I Biofoam Pumps A5640 Secondary Clarifiers 5 5 03-Mar-31 07-Mar-31 I Secondary Clarifiers 4 A3510 RAS Pumps 5 5 10-Mar-31 14-Mar-31 I RAS Pumps A5650 Disk Filters 15 15 10-Mar-31 28-Mar-31 I Disk Filters A5710 Hypo Feed Pumps 5 5 10-Mar-31 14-Mar-31 I: Hypo Feed Pumps A5720 Full Plant Loop Testing 16 16 31-Mar-31 21-Apr-31 I Fu I Plant Loop Testing Performance Testillw A5780 Odor Control 3 3 26-May-31 28-May-31 I c dor Control MIM Actual Work Critical Remaining Work Page 7 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Lake Oswego Wastewater Treatment Plant Project Best-and-Final Proposal Update, August 18, 2027 18-Aug-26 18:16 Activity ID Activity Name Original 2emaininl Start Finish 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Duration Duration ) Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 11 A5790 UV 15 15 26-May-31 13-Jun-31 ',UV A5800 Filters 3 3 I 26-May-31 I 28-May-31 I I filters Process Startup&Acceptance Testing 72 22-Apr-31 02-Jul-31 A5730 Haul Sludge from Tryon Creek 7 7 22-Apr-31 28-Apr-31 I Haul S Udge from Tryon Creek A5880 Testing Readiness 0 0 22-Apr-31 ♦ Testing Reading A5740 Acclimation/Fine Tunning 25 25 29-Apr-31 23-May-31 Acclimation/Fihe Tunning --------- ---------------- A5750 15 Day Acceptance Test 30 30 24-May-31 22-Jun-31 II 15 Day Acceptance Test A5760 Compile Data&Submit AT Report 10 10 23-Jun-31 02-Jul-31 I Compile ID*&,S;u;bmitATReport Actual Work Critical Remaining Work Page 8 of 8 TASK filter:All Activities Remaining Work • • Milestone ©Oracle Corporation Jacobs _ __ _ _. _ _ . _ ... _ _ _.... -•.• . . . � t. . • ',-::" , ,..: ' ' 0 ii i+, ,.cc .... r. 1.- ' _.__ , lI I Ill :., 4»+ BSc, i tiffs w 4 IC t ' v - r t _ .,,,,3 m A DRAFT COMMISSIONING PLAN 1 . INTRODUCTION This Commissioning Plan outline has been developed as part of the City of Lake Oswego's Design- Build Operate Maintain proposal package fora new wastewater treatment facility. This document will serve as the basis of the commissioning estimate, as it relates to the testing activities required prior to performing the Acceptance Test. Portions of the Preliminary Draft have already been developed while other portions remain in outline or example form. The status of each section of the document is provided in Table 1-1. Table 1-1.Preliminary Draft Startup and Commissioning Plan Section Status Section Status Written Plan Draft complete;minor updates anticipated for the Final Draft Plan. Attachment-Commissioning Checklist complete;standard for utilized on all Jacobs' • -Buil updates anticipated for Checklist Final Draft Plan. Attachment B:Manufacturer's Form complete;standard form utilized on all Jacobs'Design-Builds.No updates anticipated for the Final Certificate of Proper Installation Draft Plan. Attachment C:Mechanical Functional Example(from another project)included to indicate level of detail to be provided.Forms for any equipment Test Forms to be developed by DBOM Contractor will be included in the Final Draft Plan.Note major systems(e.g.,UV I. IL system)will follow plans developed by the Suppliers. Attachment D:I&C Commissioning Example from another project is included to indicate level of detail to be provided.Project-specific database Database Reports will be included as part of Final Draft Plan. Attachment E:Systems Test Forms Example from another project to indicate level of detail to be provided.Remaining rms to be developed ` as part of Final Draft Plan. Attachment F:Commissioning Log template complete;standard form utilized on all Jacobs'Design-Builds.Log will be filled out for each Tracking Log piece of process equipment for the Final Draft Plan. Attachment G:Equipment Example from another project is included to indicate level of detail to be provided.Forms for any equipment Performance Test Forms to be developed by DBOM Contractor will be included in the Final Draft Plan.Note major systems(e.g.,UV system)will follow plans developed by the Suppliers. Attachment H:Commissioning Issues Log template complete;standard form utilized on all Jacobs Design-Builds. Log The Final Draft of the Commissioning Plan will be developed during the Construction Phase of the Project and submitted no later than 150 days prior to commencing any commissioning activities in the field.The Final Startup and Commissioning Plan will be submitted following receipt of any comments from the City.Testing activities in the field (i.e.,functional testing)will not commence until the Final Commissioning Plan is accepted by the City. Note that the City will complete their review of the Final Draft of the Commissioning Plan and provide comments to the DBOM Contractor within the timeframes described in Agreement Appendix 6 paragraph 3.3.Testing will not occur prior to approval of the Final Commissioning Plan from the City. 1.1 Overview The Lake Oswego Wastewater Treatment Facility(LOWWTF) Project(Project)will provide the City of Lake Oswego (City)with a new greenfield WWTF. Flows currently treated at the Tryon Creek Wastewater Treatment Plant(TCWTP)will be rerouted to the new WWTF. Major project components include: • Influent Pump Station 111 DRAFT COMMISSIONING PLAN • Headworks • Aeration Basins • Clarifiers • Filtration • Ultraviolet(UV) Disinfection • Sludge Thickening • Sludge Storage • Odor Control • Chemical Feed Systems The Project is being delivered via the DBOM Agreement for the Design, Construction, Operation, and Maintenance of the Lake Oswego Wastewater Treatment Plant(DBOM Agreement) by Jacobs Project Management Co. (DBOM Contractor). Commissioning is the process for achieving,validating,and documenting the performance of the total Project and its systems to meet the design needs and requirements of the City. Commissioning consists of Planning, Pre-Commissioning, Functional Testing, Process Startup,and Acceptance Testing phases. 1.2 Purpose of the Plan This Commissioning Plan (Plan) provides the approach to complete startup and commissioning of the Project.This Plan is intended to serve as a guide for Project personnel on how the Project and its sub-systems will be tested prior to the Acceptance Test. The purpose of this Plan is to: • Define the phases within the startup and commissioning process to demonstrate a fully functioning plant and to meet the conditions to start the Acceptance Test. • Identify activities required to be performed during startup and commissioning. • Define the methods by which such activities are to be carried out, evaluated, recorded,and/or approved. Completion of pre-commissioning activities will be required prior to the start of testing in each area.As such, pre- commissioning activities are discussed within this Plan as well. This Plan is not intended to cover conditions of performing or passing the Acceptance Test(which is detailed in a separate plan), but rather to ensure the LOWWTF is ready to begin the Acceptance Test. 1.3 Objectives of Startup and Commissioning The overall objectives of the startup and commissioning phase are to: • Achieve compliance with relevant principles of safety, environment,schedule, and community as the team prepares for and implements the duties related to commissioning. • Demonstrate that the individual components, systems, and subsystems have been properly installed and are operating in accordance with the requirements of the DBOM Agreement, including manufacturer's written requirements. • Adequately plan and complete all activities required to confirm the functionality and integration of the whole of the Project prior to initiation of the Acceptance Test. • Fully train operations staff prior to the commencement of Process Startup and the Acceptance Test. • Successfully complete the Acceptance Test. 1.4 Phases of Commissioning In order to meet the objectives established above,the whole of commissioning has been divided into the following key areas: Planning, Pre-Commissioning, Functional Testing, Process Startup,and Acceptance Testing.The sequence of commissioning activities is depicted in Figure 1-1, and a brief description of each phase is described in Table 1-2. Further detail of each phase is discussed in Section 3 of this Plan. I 2 I DRAFT COMMISSIONING PLAN Pre- Functional Process Acceptance Planning Commissioning Testing Startup Test » O&M input » Witness factory >> Manufacturer » Seeding All flow directed during design testing Certifications » Transition influent through the new • Develop planning » Electrical circuit » Mechanical flows from Tryon WWTF documents testing checks Creek to the Continuous and detailed » Perform visual » Instrument new WWTF 15-day test checklists observations and calibrations » Biological startup Final • Finalize initial checks » Network and stabilization demonstration commissioning >> Complete Pre- configuration » Verify process of Performance sequencing and Commissioning » PLC/SCADA performance Guarantees schedule checklists communications » Control system » Submittal reviews » Systems Testing fine tuning (i.e.,software logic testing) Figure 1-1 Startup and Commissioning Approach Table 1-2.Commissioning Phases Commissioning Phase Description Planning The planning phase of commissioning will consist largely of developing the Startup and Commissioning Plan(this Plan)and the Acceptance Test Plan,which include scheduling,resourcing,and identifying tools and procedures to be utilized for each area of focus;developing detailed testing plans;providing commissioning reviews of design documents and construction submittals;and monitoring progress over the course of startup and commissioning.This phase also includes setup of the I&C Commissioning Database for tracking software integration activities and development of control loops based on the process control narratives. Pre-Commissioning Pre-commissioning activities(i.e.,activities completed prior to construction handover to the commissioning team)will be performed primarily by the construction team and manufacturers or vendors where applicable. These activities will be witnessed as necessary by the commissioning team to ensure that equipment and areas are ready for commissioning. Functional Testing Tests to demonstrate the installed equipment or system meets the requirements as specified and that the equipment functions as an entire system in accordance with the design requirements.This phase encompasses mechanical checkouts,instrumentation and controls checkouts,and equipment performance testing as required by the specifications.For planning and tracking purposes,this period has been broken into sub-components:Mechanical Functional Testing,I&C Functional Testing,and Equipment Performance Testing.I&C Functional Testing is further broken down into Component Acceptance Testing, Communications Infrastructure Testing,and Systems Testing. Mechanical Functional Testing A sub-component of Functional Testing.Mechanical functional testing will consist of functional inspections and mechanical testing of individual equipment to demonstrate that the component is installed correctly and functions as intended. I&C Functional Testing A sub-component of Functional Testing.Testing of communications infrastructure consisting of Component Acceptance Testing,Communications Infrastructure Testing,and Systems Testing. Component Acceptance Testing A sub-component of I&C Functional Testing.Testing of instruments and communications hardware for proper installation,calibration,and adjustment on loop-by-loop and component-by-component basis. 131 DRAFT COMMISSIONING PLAN Commissioning Phase Description Communications Infrastructure A sub-component of I&C Functional Testing.Testing of network communications,IP addressing,and Testing uninterruptable power supply(UPS)systems. Systems Testing A sub-component of Functional Testing.Individual process units and systems are independently evaluated to confirm basic functionality and controls are performing as designed(including both manual and automatic controls).Following successful testing of each system,the entire Project is tested in the same manner,including extensive Supervisory Control and Data Acquisition(SCADA)system control testing. Equipment Performance Testing A sub-component of Functional Testing.Testing required by the specifications to demonstrate performance of the equipment under process(or simulated process)conditions.Units are evaluated while operated under treatment(or simulated treatment)conditions to verify complete process capability and controls(when applicable)are functioning as designed.Equipment performance testing as required by the individual equipment specifications may be performed prior to,during,or after Process Startup depending on the test requirements. Process Startup Process Startup will begin upon successful completion of Functional Testing.During this time influent flow will be introduced into the process.Unit processes are evaluated while being operated in full treatment mode to confirm the process capability and controls are functioning as designed.During this time,the split flow between the new and existing treatment infrastructure as needed as finalized in the transition plan. Acceptance Test The Acceptance Test(discussed in a separate plan)will demonstrate the overall performance of the Project and will be witnessed and accepted by the City.This is the final testing activity required to achieve Acceptance and Substantial Completion for the Project. k 4 DRAFT COMMISSIONING PLAN 2. SAFETY The DBOM Contractor is committed to ensuring the complete safety of all individuals who have access to the Project. For the full construction and commissioning periods,the Project will be operated under the construction safety and induction procedures as documented in the site-specific Health and Safety Plan (HSP).After construction and Acceptance Testing,the Project will be operated under long-term O&M safety procedures. Safety and security of employees,subcontractor personnel,visitors,the environment, and assets are primary considerations for any action performed as part of the Project.Commissioning duties, properly planned and implemented, should be incident free. 2.1 Site Safety Training Site safety induction training will be provided to individuals involved in the startup and commissioning period.All persons requiring access to perform work on the construction site will be required to attend the site induction training. In addition,all personnel on site during commissioning will be introduced to the specific risks during the startup and commissioning phase. 2.2 AHAs and PTSP An Activity Hazard Analysis(AHA) will be completed for commissioning activities,as required by the HSP.A Pre-Task Safety Plan (PTSP) is to be completed daily in conjunction with the AHAs. Daily PTSPs are completed by the Commissioning Manager(or his/her designee)and briefed with the commissioning team to review the hazards posed and required hazard control procedures for each day's planned activities. During the daily commissioning meeting,the Commissioning Manager will review the PTSP with the rest of the team. Participants in the day's activities will sign off on the form that they have received the briefing. Particular attention shall be paid to chemical hazards, electrical safety, lock-out/tag-out, and confined space requirements during commissioning. 2.3 Site Access and Security Site security will follow security requirements established and followed during the construction phase.This Project is a controlled site.Access to the site by all approved personnel will be via the construction entrance unless otherwise directed by the DBOM Contractor. During the commissioning phase, all site security protocols will be adhered to by all members of the commissioning team.The Commissioning Manager will ensure that all members of the commissioning team are briefed on security and that each team member is aware of proper security and safety procedures. 151 DRAFT COMMISSIONING PLAN 3.COMMISSIONING SCHEDULE The commissioning schedule will be divided into the major phases noted in Section 1.4 above.The phases are divided between each main area (or process)to be commissioned. In general, pre-commissioning of each area (or process) occurs after completion of process mechanical work and electrical installation and testing for that area (or process).Once each area (or process) has a completed pre-commissioning checklist and is turned over to the commissioning team,the next major phase is to complete functional testing. Functional testing (both mechanical and I&C testing)will occur to verify equipment mechanical and control system functionality.Once functional testing activities have been completed on an area (or process) basis, Process Startup for the major processes will commence.Once Process Startup has been completed, commissioning will continue with a formal Acceptance Test per the DBOM Agreement. Equipment performance testing as required by the individual equipment specifications may be performed prior to, during, or after Process Startup depending on the test requirements. In some cases,the testing can occur on an area (or process) basis without interaction with other facilities. In cases where there is interaction, such as pumps moving large quantities of water from one facility to another,this has been taken into account in sequencing of the commissioning activities. The commissioning schedule has been incorporated into the overall project master schedule to guide the project for major commissioning activities.A look ahead schedule(discussed below)will provide the daily details of testing activities when the commissioning phase commences. The commissioning sequence has been developed considering the availability of the equipment on site and availability of resources for commissioning of equipment in a parallel and logical sequence for commissioning activities.This master schedule is a living document that is updated monthly.The project master schedule will be submitted to the City each month. The project scheduler will maintain the commissioning schedule and update it based on information from the Commissioning Manager. 3.1 Work Hours Testing activities will extend beyond normal working hours.Testing activities may occur around the clock seven days per week,as necessary.Testing activities are not considered construction activities, but rather operational activities, and therefore do not fall within working hours stipulated for construction working hours. 3.2 Look Ahead Schedule When commissioning activities commence,a three-week look ahead commissioning schedule will guide commissioning activities.The three-week look-ahead commissioning schedule will be distributed and discussed during routine commissioning progress meetings with the City.This schedule and the meeting will serve as official notification to the City for confirmation of scheduled activities including testing. 3.3 Updates to Startup and Commissioning Schedule The startup and commissioning schedule is based on the current construction schedule.Should the construction schedule change,the commissioning schedule may be modified as a result. 161 DRAFT COMMISSIONING PLAN 14. ROLES AND RESPONSIBILITIES This section of the Plan defines the roles and responsibilities for all activities required for commissioning.The commissioning team will consist of commissioning staff from process, mechanical, electrical, construction, and controls backgrounds, and dedicated commissioning tradespersons. 4.1 Team Organization The DBOM Contractor will be responsible for planning of all commissioning activities in the field and overseeing the execution of all commissioning activities.The DBOM Contractor will remain wholly responsible for and provide the staff to conduct all commissioning activities. The Onsite Commissioning Manager will Lead commissioning activities for the whole of the Project. However, a full commissioning team will assist the Commissioning Manager in Leading and carrying out the various activities identified for the commissioning phase of the Project. Note that some team members may have dual roles on the Project, including roles within the construction and commissioning teams. 4.2 Roles and Responsibilities The roles and responsibilities of the various Commissioning Team members are discussed in Table 4-1 below and the O&M Team member responsibilities are described in Table xx. Table 4-1.Commissioning Team Roles Role Responsibilities Regional Director of Commissioning • Overall responsibility of quality control of commissioning activities. (offsite;onsite only for critical • Responsible for coordinating commissioning staff support needs for commissioning of the Project. commissioning activities) • Oversees the development of the commissioning plans and documents. • Provides oversight of all commissioning related documents and document control. • Ensures that DBOM Agreement compliance obligations related to commissioning are met. • Indirectly supervises the commissioning staff via the Commissioning Manager. • Engages in issues resolution if necessary. • Provides additional support to the commissioning team as needed. Onsite Commissioning Manager • Manages the commissioning team and all aspects relating to the development and implementation of (onsite full time during the commissioning program. commissioning) • Coordinates the activities of the commissioning team. • Responsible for commissioning related safety paperwork and ensuring the work is performed safely in the field. • Receives all site related correspondence concerning commissioning activities. • Coordinates and oversees the specific testing activities of the commissioning team. • Coordinates all the specialist or technical advisers required from the engineering team,different suppliers,and subcontractors. • Responsible for the planning and coordination of vendor activities. • Works directly with the O&M staff and City of Portland to ensure seamless handover to operations staff prior to Process Startup and Acceptance Testing. • Reports to the Design-Build Manager and the Regional Director of Commissioning. Commissioning Leads • Plans and coordinates all assigned process/area commissioning testing activities. (onsite full time during • Works directly with the integration team to complete systems testing for each process/sub-process. commissioning) • Responsible for ensuring systems are operating to provide functionality necessary for the operating plant. • Reports to the Onsite Commissioning Manager. Process Engineer • Responsible for ensuring the new equipment and processes provide the process functionality necessary (onsite full time during for the operating plant. commissioning) • Responsible for the day-to-day direction during the Process Startup phase. • Reports to the Onsite Commissioning Manager. DRAFT COMMISSIONING PLAN Role Responsibilities Senior Technical Consultants • Assist and advise the commissioning team of technical guidance during commissioning activities. (offsite;onsite only for critical • Develop and/or review test plans for commissioning activities. commissioning activities) • Provide design-theory training to O&M staff. • Work directly with the Regional Commissioning Director to ensure overall quality control of the commissioning phase. Programming Team • Develops project software standards,graphics,and software code. (onsite full time during • Performs and documents the Factory Software Acceptance Test. commissioning) • Performs network configuration. • Oversees testing related to I&C systems including,but not limited to: — Verifying instrument installations — Performing instrument calibrations — Verifying IP addressing and I/O checks to the PLCs — Loop/component inspection tests — Local and remote control verification of individual equipment,process areas,and the facility — Systems Testing • PID tuning. • Supports training to O&M staff on SCADA items. • Organizes and manages all I&C Commissioning Database test documentation until submitted to the Onsite Commissioning Manager • Reports to the Onsite Commissioning Manager. Project Scheduler • Incorporates commissioning activities into the overall master schedule. (offsite) • Assists in tracking commissioning activity progress and updating the Commissioning Schedule. • Reports to the Design-Build Manager. Table 4-1.O&M Team Roles Role Responsibilities O&M Manager • Oversees and manages the O&M staff for long term operations. • Assigns O&M staff to assist in facility and process leads in equipment,systems,and process testing as assigned. • Prepares the operations phase workplans and deliverables. • Responsible for reviewing training manuals through the construction submittal review process. • Coordinates vendor training with commissioning team and startup of various equipment and systems. • Attends O&M training sessions. • Participates and/or witnesses testing as desired. • Reports to Regional Director of Operations. O&M Staff • Witnesses and participates in commissioning activities as assigned. • Develops operations phase plans and reports under the direction of the Operations Manager. • Attends O&M training sessions. • Reports to the Operations Manager. 8 DRAFT COMMISSIONING PLAN 15.STARTUP AND COMMISSIONING ACTIVITIES AND TESTING The commissioning phase will consist of planning activities, pre-commissioning verifications,functional testing, Process Startup, and the Acceptance Test.The overall sequence of the commissioning phase is depicted in Figure 1-1. Further description of all commissioning related activities is provided below. 5.1 Planning Activities 5.1.1 Description of Activities The planning phase of commissioning will consist of developing the Commissioning Plan (this Plan), Acceptance Testing Plan,and detailed functional and equipment performance testing plans to support commissioning activities. Construction submittals received during the planning phase will provide important review milestones for the commissioning team. Designated Commissioning Team members will review these submittals, along with other designated reviewers from the engineering team, during the construction submittal review process. It is the responsibility of the Commissioning Manager to ensure that all planning documents are adequately prepared in advance of performing commissioning activities and are available to all commissioning team members. 5.1.2 Documentation During the planning phase,the following documents will be developed and submitted to the City for review and approval: • Commissioning Plan (this document),which will cover pre-commissioning,functional testing, equipment performance testing,and Process Startup activities • Acceptance Test Plan (separate plan) It is the responsibility of the Regional Commissioning Director to ensure that all City-required documents are adequately prepared in accordance with the DBOM Agreement requirements and are submitted, reviewed, updated as necessary, and approved by the City. 5.2 Pre-Commissioning Activities 5.2.1 Description of Activities The following Pre-Commissioning activities will be completed at the factory by the manufacturer prior to equipment delivery to the site: • Equipment Factory Acceptance Test[EFAT]—EFAT testing will be completed at the factory for specific equipment or systems as identified in the individual equipment specifications. Factory testing in general will consist of equipment or motor functional and/or performance testing, software demonstrations testing,and/or hydrostatic testing. EFATs must be completed prior to equipment delivery onsite with results submitted and reviewed through the construction submittal review process. • Factory Software Acceptance Test[FSAT]—The FSAT will be completed at the factory for the whole of the Project. The FSAT will encompass function block and graphical object tests, HMI functions, manual controls,and automatic controls provided by the programming team.The FSAT will be performed by the programming team. Upon successful delivery of the FSAT and approval through the construction submittal review process,the Programmable Logic Controls(PLCs) and SCADA components will be delivered to the site. Once equipment has been factory tested and delivered to site, installation of equipment and systems will be completed by the Construction Team before being turned over to the Commissioning Team. Parts of work may be incomplete when testing begins;for example,temporary guard rails may be used instead of permanent guard rails. Pre-Commissioning will include inspections to ensure areas are ready for Functional Testing. Before commencing testing in the field, initial validation that a component or area is ready for testing will occur through the applicable subcontractors responsible for its installation,followed by validation from the Design Builder.This step ensures that construction is complete and the applicable equipment and components are ready to be tested.The inspection process is documented in the Pre- Commissioning Checklist(Attachment A). w 191 DRAFT COMMISSIONING PLAN As part of Pre-Commissioning and prior to equipment suppliers arriving onsite, electrical systems checks will be performed when required including insulation resistance tests, continuity tests on grounding systems, direct current(DC) high potential tests on high-voltage cables, etc.The services of a third-party testing company will be provided by the electrical subcontractor to perform electrical system tests. Plans and reports related to electrical systems testing are not documented in the Pre-Commissioning Checklist, but rather will be submitted and reviewed through the construction submittal review process. However,the Pre-Commissioning Checklist does contain a box for verification that this testing is complete to ensure that this is carried out prior to commencing Functional Testing for the area. At a minimum,the following conditions must be met for commissioning readiness: • Construction completed as necessary to provide working equipment with safety features in working order. • Equipment, piping, electrical wiring, and instrumentation associated with the area/component are installed. • Water containing structures have passed a water tightness test. • Leakage tests and piping pressure tests have been completed and any leaks repaired. • Equipment, piping, and water containing structures have been cleaned. • Tagging,signage, pipe labels, panel identification, and wiring identification completed to the extent necessary to identify items being tested.Temporary tagging will be permissible. • Factory testing completed and documentation received and verified. • Individual equipment manufacturers' O&M Manuals have been submitted and preliminarily approved,which include testing and commissioning procedures. • Safety devices are installed,fully functional,adjusted,and tested. • Pre-Commissioning Checklists signed off and turned into the Commissioning Manager. Pre-vendor site visit activities may occur and include activities such as initial cycling of valves or rotation checks for motors as necessary to be adequately prepared for the equipment vendors. Construction and pre-commissioning completion of areas and support systems is a phased approach and may be staggered throughout the Project as equipment and systems become ready. 5.2.2 Documentation Equipment factory testing activities will be documented in Factory Test Reports where required by the specifications and will be prepared and submitted by the manufacturer or subcontractor as applicable. Factory Test Reports will be submitted and reviewed through the standard construction submittal process. Software factory testing activities will be documented in the I&C Commissioning Database. Field Pre-Commissioning will be documented via a Pre-Commissioning Checklist prepared jointly by the Construction and Commissioning Teams.The turnover process will include a detailed walk down to verify each system/subsystem is complete to the point where the system/subsystem can be safely energized and put into initial operation. Items identified during the walk down which would prevent the system from being either safely energized or put safely into initial operation will prevent the system from being accepted by the Commissioning Manager.These items will be corrected by the Construction Team and given immediate attention for resolution. Other items requiring attention, specifically items that would allow safely energizing or operating the equipment,will be noted on the Commissioning Issues Log and scheduled for completion.This list will be included in the checklist at the time the system/subsystem is transferred from Construction to Commissioning. Final documentation of Pre-Commissioning will include the signed Pre-Commissioning Checklist.A copy of the signed documents will be stored in both hard copy and electronic formats. It is the responsibility of the Construction Superintendent to ensure accurate and complete documentation is provided via the Pre-Commissioning Checklist. I10I DRAFT COMMISSIONING PLAN 5.3 Functional Testing Activities 5.3.1 Description of Activities Functional testing will include mechanical testing, I/O checks, obtaining the Manufacturer's Certificate of Proper Installation, and field testing to ensure that equipment within a system or sub-system is properly installed, is capable of safe operation, and that associated control circuits are operational.This phase will generally consist of some dry running equipment and some wet running equipment using "clean"water. Functional testing activities that will be performed in the field by the commissioning team include both Mechanical Functional Testing and I&C Functional Testing. Mechanical Functional Tests will be performed in the field by the commissioning team and often the manufacturer.Activities to be performed as part of this testing include: • Verification that equipment is properly installed in accordance with the manufacturer's written requirements. • Verification that equipment functions as intended and meets the requirements identified in the specification. • Verification that equipment safety features are properly installed;that it is free of debris, can be freely moved, is properly aligned;that grease and oil or lubrication are applied as required;and that support systems such as seal water are available for normal operation. • Checking rotating machinery for correct direction of rotation and for freedom of moving. • Testing pumps, motors,and variable frequency drives(VFDs)to verify pump performance and operation over the full operating range from minimum head/flow up to maximum head/maximum capacity. • Ensuring that limit switches are properly set. • Cycling valves manually open and closed to confirm freedom of movement. • Cycling valves locally full open and closed. • Operate local control panels in Local Mode, testing control panel and equipment operation in accordance with the procedures. Mechanical Functional Tests will include any Functional Testing requirements of the individual specification sections. Mechanical Functional Tests will generally be completed dry or with clean water from the City's potable water supply. I&C Functional Tests will be performed in the field by the commissioning and integration teams.Activities to be performed as part of this testing include: • Communications Infrastructure Tests [CIT]—CITs will be performed on site to demonstrate Ethernet and other network communication testing,failover testing, IP addressing verification, and UPS performance verification.CITs will be performed in the field by the integration, programming,and commissioning teams. • Component Acceptance Test[CAT]—CATs,will be performed in the field by the integration, programming, and commissioning teams.Activities to be performed as part of the CATs include: — Verification that I/O connections to the SCADA system are properly terminated and initiating the PLC for the subject equipment. — Verifying PLC software for that equipment on a control loop by control loop basis,where possible manually operating instruments or alternatively generating instrument signals to see that they record correctly and that alarms are generated and recorded. — Verifying that interlocks preventing equipment operation under certain conditions function properly; checking the operating sequence features and set points. — Instrument calibrations and scaling will be performed and make required adjustments and control point settings where applicable. When Mechanical Functional Testing, CITs, and CATs have been completed for a process/sub-process and applicable Manufacturer's Certificates of Installation have been completed, Systems Testing will then commence for the process/sub- process.Systems Tests will include: I11I DRAFT COMMISSIONING PLAN • Verification that the subject process/sub-process is functional and capable of serving its required purpose. In general, this will be conducted under"wet" conditions using clean water as appropriate and will include both manual and automatic control. • Verification of discrete, contained sections of the equipment and control system performance under conditions as close as possible to the actual operating conditions in order to demonstrate that the systems function as intended. • Confirming all software systems and subsystems for the Project including full PLC/SCADA interface checking. Systems testing will be completed in a sequential order within the process/sub-process so that at the end of the systems tests,the full process/sub-process operation has been demonstrated. Site commissioning, programming,and integration team members will jointly perform these tests,with the supervision of the manufacturer's representative where required by the project specifications. Once systems testing has been substantially complete for a process,the systems integrator will continue to tune the process and overall facility controls as additional processes/sub-processes are brought online. Functional testing will be performed on all equipment/trains during this phase. Functional testing may be performed concurrently or staggered as staff,vendors,and ancillary equipment are available. In addition,some functional testing activities may occur concurrently with pre-commissioning activities for an area as necessary to support the overall commissioning schedule. Onsite functional testing activities will be led by commissioning staff and supported by construction staff as necessary. Following completion of functional testing,the DBOM Contractor will have completed the necessary requirements to commence the Process Startup Phase and Acceptance Testing. 5.3.2 Documentation The following documents will be developed as part of functional testing. • Mechanical functional testing will be documented through Manufacturer's Certificates of Proper Installation and the completion of Mechanical Functional Test Forms.The Manufacturer's Certificate of Proper Installation template is located in Attachment B.Mechanical Functional Test Forms are located in Attachment C. • The CIT and CAT I&C functional testing will be documented through the I&C Commissioning Database. I&C Commissioning Database Reports are included in Attachment D. • Systems testing will be documented through the I&C Commissioning Database and the completion of Systems Testing Forms.The completed Systems Test Forms will clearly show the tests carried out and the results, in addition to confirming that the system is ready for use. I&C Commissioning Database Reports are included in Attachment D. Systems Test Forms are located in Attachment E. Functional testing status will be documented and tracked through the Commissioning Tracking Log (CTL).The Commissioning Tracking Log has been included as Attachment F. 5.4 Equipment Performance Testing Activities 5.4.1 Description of Activities Equipment performance testing may be performed on individual pieces of equipment or on systems when specified by individual equipment specifications. Equipment performance testing will verify proper performance under actual operating conditions. Individual equipment or systems will be operated to verify equipment performance criteria.This may include activities such as verification of water pumping rate tests against operating curves; power drawn;time taken to move from position A to B;water pressure;etc. Equipment performance testing may be completed with clean water from the plant's potable water system during Functional Testing or with actual process solids or fluids depending on the specified requirements. If equipment performance testing can be completed with clean test water,testing may be completed during the Functional Testing phase. However, if equipment performance testing for equipment or systems requires actual process flows(wastewater, sludge, odor, etc.),then equipment performance testing will be completed during or after Process Startup of the process/sub-process. 1121 DRAFT COMMISSIONING PLAN Equipment performance testing required for the Project will be identified in the CTL along with whether this testing will be completed with test water or with process flow. In some cases, equipment performance testing may be completed after the Acceptance Test due to vendor-specific requirements or to test conditions that require running the facility under abnormal conditions to achieve maximum design conditions. 5.4.2 Documentation Generally, Equipment Performance Test Plans will be required to be provided by individual equipment manufacturers for each equipment performance test when specified for major equipment and systems. Smaller equipment,such as single pumps, may only require an Equipment Performance Test Report documenting results.Testing for these items will be documented in an Equipment Performance Test Form. Equipment Performance Test Forms are provided in Attachment G. Equipment Performance Test Plans provided by the manufacturer or subcontractors will be submitted and reviewed through the standard construction submittal review process prior to performing the testing. Equipment performance testing activities will be documented in Equipment Performance Test Forms and Reports prepared and submitted by the manufacturer or subcontractor as applicable. Equipment Performance Test Reports will be submitted and reviewed through the standard construction submittal process. 5.5 Support Systems Testing 5.5.1 Description of Activities In addition to the treatment processes,support systems that must be commissioned include: • HVAC Systems • Service Water Systems • Standby Power • Fire Protection Systems • Fire Detection Systems • Security Systems 5.5.2 Documentation Generally,test plans for support systems will be provided by individual system suppliers for each system when specified.Test plans will be submitted and reviewed through the standard construction submittal process prior to performing the testing. The same testing activities will be documented in test reports prepared and submitted by the manufacturer or subcontractor as applicable. 5.6 Process Startup 5.6.1 Description of Activities Once final systems testing has occurred, chemicals will be delivered and influent wastewater will be introduced to the new processes for process treatment.The initial phase of Process Startup will include seeding and acclimation of the Aeration Basins. Process and controls will also be tuned sufficiently to meet regulatory requirements during this phase. Assumptions during this phase include: • A minimum of 28,000 pounds of solids inventory are required to seed the LOWWTFAeration Basins. Seed sludge will be provided by TCWTP for seeding of the new Aeration Basins in the form of waste activated sludge(WAS)at no cost to the DBOM Contractor. WAS will be transferred to the LOWWTF for a period of up to 72 hours to limit the seed sludge age prior to the influent flow cutover from the TCWTP to LOWWTF. It is anticipated that the required solids inventory cannot be transferred during 72 hours of wasting from the TCWTP. The remaining solids inventory will be transferred by pumping the contents of the TCWTP Aeration Basins and Secondary Clarifier blankets to the LOWWTFAeration Basins during the influent flow cutover. - It is assumed that 8,000 pounds of solids inventory will need to be trucked to the LOWWTF in addition to the solids inventory available from the TCWTP. The DBOM Contractor will be responsible for trucking seed WAS if required to meet the required solids inventory at the time of seeding the LOWWTF. I13I *.4 DRAFT COMMISSIONING PLAN • The DBOM Contractor will provide a minimum of 7 days'notice to BES prior to when seeding is to begin. • The DBOM Contractor will be responsible for moving the seed sludge between facilities.BES will allow DBOM Contractor access to the TCWTP for trucks and/or temporary pumps/piping to transfer the seed sludge. • The influent flow cutover from the TCWTP to the LOWWTF is based on the following assumptions: - TCWTP Aeration Basins will be drained by BES to the Tryon Creek Pump Station and discharged to the LOWWTF Influent Pump Station. - Thickened primary sludge will be removed from the Primary Sludge Thickeners by BES,Primary Clarifier blankets will be removed from the clarifiers, no sludge blanket contents rNo thickened primary sludge will go to LOWWTF. Following draining of the Aeration Basins, the remaining Primary Clarifier Sludge Thickener contents will be drained by BES to the Tryon Creek Pump Station and discharged to the LOWWTF Influent Pump Station. - Secondary Clarifier blankets will be transferred to the LOWWTF as part of seeding.removed from the clarifiers, no sludge blanket contents will go to LOWWTF. Following draining of the Primary Clarifiers, the remaining Secondary Clarifier contents will be drained by BES to the Tryon Creek Pump Station and discharged to the LOWWTF Influent Pump Station. - The majority of the No contents of the Chlorine Contact Basin contents will be used for washdown of the TCWTP basins. Basin washdown liquid will be tested to confirm there is no chlorine residual prior to discharging to the LOWWTF.Any remaining Chlorine Contact Basin contents will be dechlorinated prior to being drained to the Tryon Creek Pump Station and discharged.:will be scnt to the LOWWTF to avoid transferring chlorinated water. The DBOM Contractor is not responsible for draining the Chlorine Contact Basins. - All solids will be hauled offsite for disposal,including contents of the Gravity Thickeners and Digesters. The DBOM Contractor is not responsible for hauling or disposal of the TCWTP solids. - BES will operate permanently installed equipment at the TCWTP to support seeding, draining basins, or transferring basin contents to the LOWWTF. BES is responsible for all BES standard process outage steps required to support Jacobs' connection of temporary pumps/piping,such as but not limited to BES operations support, lock out tag out,moving grating, turning valves, etc. - BES will be responsible for salvaging the TCWTP equipment and securing electrical power to the TCWTP. • The DBOM Contractor will be responsible for any temporary pumping and piping systems required to transfer basin contents faster than the Tryon Creek Pump Station can drain the existing basins, if considered necessary by the DBOM Contractor. • The DBOM Contractor is not responsible for odors and/or noise originating from the TCWTP. • The DBOM Contractor may divert up to 500,000 gallons per day of raw sewage during seeding to provide nutrients for seed sludge prior to the influent flow cutover from the TCWTP. The DBOM Contractor will be responsible for moving raw sewage during seeding. BES will allow DBOM Contractor access for trucks and/or temporary pumps/piping to transfer raw sewage, as well as BES standard process outage steps that will require operations support, lock out tag out, moving grating, turning valves, etc. • All influent flow will be cutover at one time from the TCWTP to the LOWWTF immediately following the 72-hour seeding period. TCWTP will be offline at this point, and DBOM Contractor is not responsible for any decommissioning activities. Once the LOWWTF has been initially seeded and influent wastewater flows are introduced to the Facility, a stabilization period will be required to fully acclimatize the biological processes. This acclimation period will be required in order to meet performance goals. - If it is required to return flow to the TCWTP due to the inability to treat flows at the LOWWTF, the DBOM Contractor will be responsible for costs associated with reseeding the TCWTP. BES will be responsible for operation of the TCWTP as the DBOM Contractor would neither hold the license to operate the facility or have staff trained to operate the facility. • Seeding and Process Startup may be delayed if a rainstorm is occurring or forecasted to occur within the first 7 days of commencement of seeding and introduction of wastewater to the LOWWTF. The delay will minimize the risk of seed inventory being washed out during the rain event.Should a storm occur or be forecasted during this period, and the activity is on the I14I DRAFT COMMISSIONING PLAN critical path for completion by the Substantial Completion date, the DBOM Contractor shall be entitled to adjustment in Contract Price and/or Contract Time. • A grace period will be granted from DEQ during the first 14 days following the flow cutover for BOD and TSS daily limits and removal efficiency requirements. • The DBOM Contractor may use offline basins at the LOWWTF to provide emergency storage if necessary to meet permit requirements. • The DBOM Contractor will provide a minimum of 7 days'notice to BES prior to the start of hauling sludge from the LOWWTF to Columbia Boulevard Wastewater Treatment Plant. The following sections will be provided in the final plan to further detail the activities of this phase: 5.6.2 Seeding 5.6.3 Flow Introduction and Phasing 5.6.4 Influent Diversion 5.6.5 Effluent Management 5.6.6 System Stabilization 5.6.7 Permit Management 5.6.8 Documentation 5.7 Acceptance Testing Activities 5.7.1 Description of Activities When the DBOM Contractor believes that the new LOWWTF processes are optimized and operating within the performance criteria in the DBOM Agreement,an Acceptance Test will be performed to demonstrate that the various components and systems of the Project will perform as a complete facility.At this point,the Operations Manager and his O&M staff will be in the lead role and the commissioning team will provide direction and support. During Acceptance Testing,the O&M staff will operate the LOWWTF under normal operations protocols for operating and maintaining the facilities.These procedures are outlined in a separate Acceptance Test Plan. 5.7.2 Documentation An Acceptance Test Plan (separate from this Commissioning Plan)will be developed to support and document the Acceptance Test activities. Included in this document will be an Acceptance Test Daily Report Template which will be developed and submitted on a daily basis during the test.These reports outline the previous day's operating parameters, activities, and test results.These daily reports will be combined into a final Acceptance Test Report at the conclusion of the test. I15I DRAFT COMMISSIONING PLAN 6. Procedures 6.1 I&C Commissioning Database The I&C Commissioning Database will be used to document instrumentation and controls testing during commissioning.The database includes testing plans and documentation that are organized in a modular fashion with a hierarchy based upon major process areas and PLCs.This top-down hierarchy will bore down eventually to all component level devices, equipment, or hardware which requires testing.The associated testing forms will be structured such that they can be robed back up to provide a complete testing support package that is tied to each major process area or PLC. The I&C Commissioning Database is used to document control system commissioning activities, including the input/output list, loop checks, and systems testing.A copy of the reports provided in the I&C Commissioning Database are provided in Attachment D.This is a living database that will continue to be developed and refined throughout the commissioning phase. In addition,the l&C Commissioning Database tool will be used for quality and completion tracking for control system testing. The commissioning team can review test reports generated by the database on a regular basis to stay apprised of testing progress and schedule. 6.2 Commissioning Tracking Log A CTL(Excel spreadsheet)will be maintained and communicated to all commissioning team members.The purpose of the CTL is to keep track of the status and progress of the commissioning activities.The CTL template is provided in Attachment F. The CTL spreadsheet will be updated weekly.The Commissioning Manager will maintain the CTL; however,the log will be stored so that all team members can view the status of the log as needed. 6.3 Commissioning Issues Log A commissioning issues log will be maintained and communicated to all commissioning team members.The purpose of the issues log is to keep track of all commissioning-related issues requiring attention and/or an action.A copy of the commissioning issues log template is provided in Attachment H. The Commissioning Manager will maintain the commissioning issues log; however,the log will be stored so that all team members can view the status of the log as needed. 6.4 Design Clarifications Any changes to the design resulting from commissioning activities should be managed through the design change process, by issuing a design change notice for approval through the engineering team. 6.5 Vendor Operations & Maintenance Manuals The commissioning team will maintain equipment manufacturers' installation, operation,and maintenance instruction manuals that will be available in the field during testing and related activities. 6.6 Communications The purpose of communications procedures is to ensure that all commissioning team members, management, subcontractors,and City staff that are involved in the commissioning of the Project provide and receive appropriate communications related to commissioning. 6.6.1 Communication Procedures The commissioning team will utilize different formats for communicating project information.Whenever possible,face-to- face communication is encouraged. If critical decisions are made during this verbal discussion, a written memorandum or e- mail should be sent to all core commissioning team participants and other team members involved summarizing the discussion and conclusions. E-mail messages will also be used as a means of Project communication. E-mail messages should be brief and concise.All commissioning team members with a need to know should be copied on the e-mail message, especially when issues affecting their work are addressed. Subject headings should include facilities,areas,functions, etc.as necessary. '� I16I DRAFT COMMISSIONING PLAN Internal memorandums will be utilized to address specific project issues requiring the attention of internal staff. External memorandums will be used to for communication between the DBOM Contractor and the City and between the DBOM Contractor and any external agency in connection with the commissioning.All Project memorandums, internal and external, will be kept as Project documentation. A variety of meetings will be held in accordance with the Project scope of work. Whenever possible, agendas and notices will be provided in advance to invited attendees. • Weekly Progress"Look-Ahead"Meetings.Weekly commissioning meetings will be scheduled with the DBOM Contractor and the City once regular commissioning activities commence if desired by the City.The meetings will provide updates to the progress of commissioning activities, give a look ahead for upcoming commissioning activities, and address any issues or commissioning-related concerns. • Daily Commissioning Team Meetings. Each day,a meeting will be held with the DBOM Contractor commissioning team to discuss the day's commissioning activities.All commissioning team leads are required to attend.Other commissioning team members will be requested to join as needed. • Other Meetings.Other meetings will be conducted as necessary to address specific areas of concern as they arise. 6.6.2 City Interaction The City will have various roles throughout the commissioning phase. Primary communication with the City will be through the Commissioning Manager and Design-Build Manager during the weekly meetings.Any communication related to commissioning between other team members and the City will be copied to the Commissioning Manager and the Design- Build Manager.All correspondence with the City will be copied and filed into the Project files. I17I DRAFT COMMISSIONING PLAN 7. Utilities During the Functional Testing Phase, potable water from the City's potable water supply will be utilized for clean water testing.This water will be supplied by the City at no cost to the DBOM Contractor.Temporary connections will be implemented and used to fill tanks, basins,and piping as needed for testing. Equipment performance testing may be completed with clean water from the City's potable water systems during Functional Testing or with actual process solids or fluids depending on the specified requirements.The DBOM Contractor will be responsible for any temporary components required to move testing water. Clean water used for Functional Testing may be discharged to the TCWTP after clean water testing is complete. virna 1181 DRAFT COMMISSIONING PLAN Attachment A Pre-Commissioning Checklist DRAFT COMMISSIONING PLAN PRE-COMMISSIONING CHECK LIST AREA/SYSTEM: The following activities should be checked and verified to document handover from construction to commissioning. Unsatisfactory items that are critical to performing testing safely must be corrected prior to handover. Unsatisfactory items that are not critical to performing testing must be documented in the handover punch list, and testing may commence. Item Yes No N/A Initials Date General Verifications Construction complete according to the P&IDs as required to commence testing: concrete complete,piping installed,pipe supports installed,equipment installed and ❑ ❑ powered,and instruments installed and powered.Note architectural components or other features that do not impact startup do not have to be completed. Leak testing completed satisfactorily for all water holding basins. ❑ ❑ ❑ Applicable O&M manuals reviewed,complete,and available onsite. ❑ Area clean and safe for work. ❑ ❑ ❑ Grating,safety rails,and walkways installed. Lock-Out-Tag-Out is in place per FSI if required for mechanical or electrical isolation. n ❑ ❑ Mechanical Verifications Utilities are properly connected to commence testing: • Utility water ❑ ❑ • Potable water ❑ ❑ • Service air ❑ ❑ • HVAC ❑ ❑ • Safety showers ❑ ❑ • Natural gas ❑ ❑ ❑ Leak and pressure testing completed satisfactorily for all piping systems. ❑ ❑ ❑ Leak testing completed for pneumatic controls and instrument air piping. ❑ ❑ Flanges and gaskets tight and checked for leakage.Inspect screwed joints for leakage. n ❑ ❑ Screwed joints and mating devices checked for leakage. ❑ ❑ Pipe supports and seismic bracing installed. ❑ ❑ ❑ Item Yes No N/A Initials Date Downstream piping reviewed for potential water hammer during initial startup. ❑ ❑ ❑ Low point drains connected to drain piping and routed to appropriate drainage ❑ ❑ ❑ collection system. Hand valves in place,positioned for proper flow direction,and freely open/close by ❑ ❑ hand. Motor valves in place,positioned for proper flow direction,and freely open/close by ❑ ❑ ❑ hand. Air release valves and blowoff vents installed. Rust preservatives,oils,and temporary protective coverings removed from equipment. 20 DRAFT COMMISSIONING PLAN Lubrication/coolant flushed and recharged.Recharge only with lubricant ❑ ❑ ❑ recommended by manufacturer. Fuel flushed,filled,and available. ❑ ❑ ❑ Packing installed loose,seals,o-rings,and miscellaneous seals checked and adjusted. Rotation direction arrows installed and pointing in correct direction. ❑ ❑ ❑ Alignment to manufacturer's tolerances of equipment complete(only if alignment not completed by vendors). Adjust V-belt tension and variable pitch sheaves. ❑ ❑ ❑ Mounting apparatus,bolts,etc.properly installed and tightened.Temporary supports n ❑ ❑ and other foreign objects removed. Shaft guards installed(or available for installation during startup with manufacturer). n ❑ ❑ Safety devices and equipment are installed,fully functional,adjusted,and tested(or ❑ ❑ ❑ available for installation during startup with manufacturer). Electrical/I&C Verifications Third party electrical tests and adjustments have been completed. ❑ ❑ ❑ Power is available to equipment and instruments. ❑ ❑ ❑ PLCs installed,wired,pulled,and terminated. ❑ ❑ ❑ Fiber-optic Network installed and tested. ❑ ❑ ❑ Point to point checks have been satisfactorily completed from the equipment/device n ❑ ❑ to the PLC. Commissioning Verifications Walkthrough with commissioning team has been completed. ❑ ❑ ❑ Commissioning punch list items have been documented. ❑ ❑ ❑ If any of the above are marked"NO",provide explanation or comment and details of any agreed action: Comments: Certification:This document certifies that the construction and installation of the area/system and its associated equipment complies with the Specifications and Contract documents,regulatory requirements(where applicable),and that this area/system is ready to commence commissioning. Verified by Construction Team: Name: Date: Signature: Approved by Commissioning Manager: Name: Date: Signature: 21 DRAFT COMMISSIONING PLAN Attachment B Manufacturer's Certificates of Proper Installation DRAFT COMMISSIONING PLAN MANUFACTURER'S CERTIFICATE OF PROPER INSTALLATION Owner: Project: Contract Number: Specification Section: Equipment/System: Tag Number(s): Serial Number(s): I hereby certifythat the above-referenced equipment/system has been: Yes No NA nri n Installed in accordance with Manufacturer's recommendations. nn n S- erviced with proper initial lubricants. nn n E- lectrical and mechanical connections meet quality&safety standards. nn n A- l applicable safety equipment has been properly installed. nn n Operated and rotates in the proper direction. nn n Correct rotation verified and properly aligned/adjusted as necessary. nn n Tested for vibration and meets requirements. nn n Equipment as installed is ready to be operated by others and will reliably perform the function for which it is intended. n n n Initial Volts (V) and Amps (A) recorded: Phi (A-B): V A Ph2 (B-C): V A Ph3 (A-C): V A Comments: I,the undersigned Manufacturer's Representative, hereby certify that I am(i)a duly authorized representative of the manufacturer, (ii)empow ered by the manufacturer to inspect,approve,and operate his equipment and (iii)authorized to make recommendations required to assure that the equipment furnished by the manufacturer is complete and operational, except as may be otherwise indicated herein. I further certify that all information contained herein is true and accurate. Representative: Manufacturer: Signature: Date: 23 DRAFT COMMISSIONING PLAN Attachment C Mechanical Functional Test Forms 24 DRAFT COMMISSIONING PLAN MECHANICAL FUNCTIONAL TEST FORM Form Number: FT-12 Specification Name: Submersible Pumps Specification Section: 44 42 56.04 Equipment Description: Tag Number: Serial Number: Specification Requirements • Conduct on each pump in accordance with HIS 11.6. • Test complete assemblies for correct rotation,proper alignment and connection,and quiet operation. • Measure flow output using plant instrumentation and storage volumes. • Test fora continuous 1-hour period. • Provide a test report in accordance with HIS 14.6 and 11.6. Pre-Requisites ❑ All construction debris has been removed ❑ Clean water is available for testing ❑ Downstream valve(s)or gate(s)are set appropriately to direct water released during testing to desired final destination ❑ Final destination for water pumped during testing is ready to receive flow ❑ VFD has been started up and programmed(if applicable) Functional Test Procedures 1. Verify manual operation of the pump by demonstrating local pump controls.Note any items that are N/A for the pump being tested. ❑ For pumps with a VFD,pump START/STOP from the VFD ❑ For pumps with a VFD,pump speed control from the VFD ❑ Pump LOCAL-OFF-REMOTE switch ❑ Pump ON status ❑ For pumps with a VFD,pump speed control from the handswitch ❑ Pump FAULT status ❑ Pump HIGH TEMP indicator status ❑ Pump MOISTURE indicator status ❑ Pump E-STOP status(verify equipment stops when engaged) ❑ Pump RESET status ❑ Operation is smooth and quiet ❑ Flow is apparent using the discharge PIT,FIT,or wetwell drawdown volume ❑ Other: ❑ N/A Items: 2. Start the pump and adjust to the primary duty point.Document operating parameters at the primary duty point. ❑ Flow(gpm): ❑ TDH(ft): ❑ Suction Level(ft): ❑ Water Surface EL: ❑ Discharge Pressure(psig): ❑ Amperage,A: ❑ Amperage,B: ❑ Amperage,C: ❑ Voltage,AB: ❑ Voltage,BC: ❑ Voltage,AC: ❑ Pump Speed(Hz): ❑ Pump Speed(rpm): ❑ Noise(dBa): 25 DRAFT COMMISSIONING PLAN 3. Start the pump and adjust to the secondary duty point(if specified).Document operating parameters at the secondary duty point. ❑ Secondary Duty Point N/A(not specified)-move to next step ❑ Flow(gpm): ❑ TDH(ft): ❑ Suction Level(ft): ❑ Water Surface EL: ❑ Discharge Pressure(psig): ❑ Amperage,A: ❑ Amperage,B: ❑ Amperage,C: ❑ Voltage,AB: ❑ Voltage,BC: ❑ Voltage,AC: ❑ Pump Speed(Hz): ❑ Pump Speed(rpm): ❑ Noise(dBa): 4. Operate the pump for a continuous 1-hour run.Did the pump operate continuously and without malfunction? ❑ Start Date and Time: ❑ End Date and Time: ❑ Yes ❑ No 5. Supplement this form with any vendor-required test forms. Comments Does this equipment meet Functional Testing requirements? El Yes El No Sign-Off Design-Builder: Signature: Date: City Representative: 26 DRAFT COMMISSIONING PLAN Attachment D &C Commissioning Database Reports 27 DRAFT COMMISSIONING PLAN Nampa,Idaho Check Out Status Report Nampa Group F 10 Type Zero State One State PLC Panel No. Rack Slot Point Address SAT 3610031 Air Scour Cross-Over Valve To Filtration DI Closed 450PLC0001 00 03 05 3610031FV_CLSO E DI Opened 450PLC0001 00 03 06 3610031FV_OPND E DI Local Remote 450PLC0001 00 03 07 3610031FV_REM E DO Close Command 450PLC0001 00 07 02 3610031FV_CLS E DO Open Command 450PLC0001 00 07 03 3610031FV_OPN E 3610032 Alr Scour Cross-Over Valve To Post Aeration DI Closed 450PLC0001 00 06 00 3610032FV_CLSD E DI Opened 450PLC0001 00 06 01 3610032FV_OPND E DI Local Remote 450PLC0001 00 06 02 3810032FV_REM E DO Close Command 450PLC0001 00 08 02 3610032FV_CLS Q DO Open Command 450PLC0001 00 08 03 3610032FV_OPN Q 3611001 Filter Alr Scour Blower 1 AOE Speed Command 450PLC0001 00 00 00 3611001BLWR_SPDCTL E AIE Speed Feedback 450PLC0001 00 00 00 3611001BLWR_SPDFBK E AIE Amps 450PLC0001 00 00 00 3611001PMP_AMPS E DIE Normal High Temp 450PLC0001 00 00 00 3611001TSHB_HIGH 2 DIE Off Running 450PLC0001 00 00 00 3611001BLWR ON E DOE Off Run Command 450PLC0001 00 00 00 3611001BLWR RUN E DIE Normal High Pressure 450PLC0001 00 00 00 3611001PSH_HIGH Q DIE Local Remote 450PLC0001 00 00 00 3611001BLWR_REM Q DIE Normal Fault 450PLC0001 00 00 00 36110018LWR_FAULT Q DIE Normal High Temp 450PLC0001 00 00 00 3611001TSHA_HIGH E DI Normal High Differential Pro 450PLC0001 00 03 03 3611001PDSH_HIGH E Al Pressure 450PLC0001 00 09 04 3611001PIT_PRESS Q 3611002 Filter Air Scour Blower 2 DIE Local iliril., 450PLC0001 00 00 00 3611002BLWR_REM E DIE Off Kt.rr rai 450PLC0001 00 00 00 3611002BLWR_ON E 211 October 2024 r.L,t of 13 1 i28I DRAFT COMMISSIONING PLAN Attachment E Systems Test Form I29I DRAFT COMMISSIONING PLAN Nampa, Idaho Systems Test Nampa Croup F Filtration/Filterl Loop Number Description ORT ST 3501010 Filter 1 Action: With the filter,ri offline mode and filtration availubie press the Onire request button Set Me Step Fad Tamer Low so that the Verification Process experiences a step failure. Result: SCADA alarm indicates the correct step failure description Initials: SJR Comment. Data: 6'2.2024 Action: Press Inc Bypass On button in the Backwash Available.Popup white overall backwash availability is not satisfied Result: The System bypasses all availabety conditions for Backwashes Overall Availability indicates backwashes are Initials: SJR avaMblo Comment: Date: 6.''2/2024 Action: FILT-While in Filtration request the tiller to transition crone Result: The hater transitions ofnne by closing the valves dunng the olnne transition step. Initials: BWC Comment: pate: 62:2024 Action: CBW-Cause the filter to enter a clean backwash while a dean backwash is available Wat for the filter to complete a random amount of steps in clean backwash and press the abort button Result: The Clean backwash is atoned immediately and transitions offline after stopping the NaOCI pump and BW pump if Initials: BwC they are furring. Comment Date: 6''2/2024 Action: BWP-While a filter is in Backwash Prep.press the backwash prep abort button. Result: Backwash Prep is aborted and the filter is placed offline Initials: SJR Comment: Date: 6.2:2024 Action: BW- lest a random failure state for backwashes by reducing the process step failure Maim time SP Result: The backwash is paused when the failure occurs.An alarm becomes active intormng operators of the failure that Initials: l3wc occurred A backwash.Air Scour or Dosing pump is never left running when the failure occurs The appropriate ptmps are restarted when the play button is pressed Comment* Date: 62.'2024 Action: Enable an automatic backwash condition and satisfy its requirement by charging its setpoint Result: Thn filter is added to the backwash queue and displays backwash pending Initials: SJR Comment: Date: 6/2/2024 Action: Initiate a clean backwash with the Filtration Settings Popup clean backwash request button While a dean backwash is not available. Result: The filter remains in filtration Button is disabied Initials: BWC Comment: Date: 6/2/2024 Action: Test functionality of pause.play,and skip step function at venous steps while filer is bac kwashng or dean backwashing Result: Buttons function as intended When the pause button is pressed and a pump or blower is running the backwash is Initials. s.:R reverted to the step at which that pump or blowier was started The skip button skips past a step and the pause button stops the backwash al the current step or reverts to a step what a blower/Pump is called to run fix that sequence Comment: Date: 6.2:2024 I I I)ci ember 21121 rage a of ex I30 � DRAFT COMMISSIONING PLAN Attachment F Commissioning Tracking Log 31 DRAFT COMMISSIONING PLAN Lake Oswego Wastewater Treatment Facility COMMISSIONING TRACKING LOG FUNCTIONAL TESTING DRY/CLEAN WATER TESTING CLEAN WATER OR PROCESS FLUID TESTING Equipment Name Equipment Spec Name Spec P&ID or Manufacturer/Rep Pre-Commissioning MCOPIs Mechanical Functional Testing Equipment Performance Testing Notes Number Section Drawing No. Checklist Required Scheduled Completed Required Form ID Scheduled Completed Required Form ID Scheduled Completed L L L L L IL NR=Not Required MCOPI=Manufacturer's Certificate of Proper Installation FT=Functional Testing EPT=Equipment Performance AT=Acceptance Testing Illk may be conducted during the dry/clean water FT phase testing EPT includes both clean water and process fluid testing components Notes: 1.I&C components of Functional Testing(Component Acceptance Testing.Communications Infrastructure Testing)will be tracked through the MC Commissioning Database. 2.Systems Testing will be tracked through the I&C Commissioning Database in addition to the forms noted. 3.Milestone and Acceptance Testing requirements and completion will be tracked through a separate log. 32 DRAFT COMMISSIONING PLAN IAttachment G Equipment Performance Test Form I33 � DRAFT COMMISSIONING PLAN D.C.TILLMAN AWPF PROJECT EQUIPMENT PERFORMANCE TEST FORM Form Number: PT-01 Specification Name: Submersible Pumps Specification Section: 44 42 56.04 Equipment Description: MF Backwash Waste Pumps Tag Number: AWT-1504-8061/213 Serial Number: Specification Requirements • Conduct on each pump as specified in Section 01 91 14,Equipment Testing and Facility Startup. • Perform under simulated operating conditions at full rated speed. • Adjust operating conditions in order to obtain flow and head performance readings for five operating points per tested operating speed. • Test Records and Report:Prepare and submit a complete test report along with the test records.Record pump serial number,acceptance grade,flow,head, temperature,current,and voltage data. • Note:Pump functional and performance testing may be conducted together. Pre-Requisites ❑ All construction debris has been removed ❑ Clean water supply is available for testing under operating pressure conditions ❑ Downstream valve(s)or gate(s)are set appropriately to direct water released during testing to desired final destination ❑ Final destination for water released during testing is ready to receive flow ❑ Pipelines have been cleaned ❑ Suction and discharge valves are in correct positions Performance Test Procedures 1. Start the pump at 100%speed.Wait for readings to stabilize,then document parameters in the pump performance table. 2. Ramp the pump speed down to its minimum.Wait for readings to stabilize,then document parameters in the pump performance table. 3. Pick 3 points at approximately even intervals between min and max speed and operate the pump at each,waiting for reading to stabilize before recording.Document parameters in the pump performance table. 4. Plot selected points on the pump curve for comparison to expected performance and attach to this form. Comments Does this equipment meet Performance Testing requirements? ❑ Yes ❑ No Sign-Off Design-Builder: Signature: Date: City Representative: 34 DRAFT COMMISSIONING PLAN Pump Performance Table-MFF-1501-8061 Serial Number: Suction Discharge Amps(A) Voltage(V) Pump Motor Operating Flow TDH Pump Bearing Point ID (gpm) (feet) Level Pressure A B C A-B A-C B-C Speed Bearing Temp(F) (feet) (PSI) (rpm) Temp(F) Design Duty 1,500 35.6 -- -- TBD TBD TBD 480 480 480 1,200 Point 1 2 3 4 5 Pump Performance Table-MFF-1501-8062 Serial Number: Operating Flow TDH Suction Discharge Amps(A) Voltage(V) Pump Motor Pump Bearing Point ID (gpm) (feet) Level Pressure A B C A-B A-C B-C Speed gearing Temp(F) (feet) (PSI) (rpm) Temp(F) Design Duty 1,500 35.6 -- -- TBD TBD TBD 480 480 480 1,200 -- -- Point 1 2 3 4 5 Pump Performance Table-MFF-1501-8063 Serial Number: Operating Flow TDH Suction Discharge Amps(A) Voltage(V) Pump Motor Pump Bearing Point ID (gpm) (feet) Level Pressure A B C A-B A-C B-C Speed gearing Temp(F) (feet) (PSI) (rpm) Temp(F) Design Duty 1,500 35.6 -- -- TBD TBD TBD 480 480 480 1,200 -- -- Point 1 2 3 4 5 Notes: • Flowdetermined by discharge flowmeter(AWT-FIT-8071) • Discharge pressure determined by each pump's dedicated discharge PI • TDH calculated from suction level within the Backwash Equalization Tank and discharge pressure values i 35 DRAFT COMMISSIONING PLAN Attachment H Commissioning Issues Log 36 DRAFT COMMISSIONING PLAN Print Date: COMMISSIONING ISSUES LOG Project No: STATUS: CATEGORY(CAT): Project Name: Closed-Work Complete A Items required to complete immediate commissioning activities Site Location: On-going-Work In Progress B Items required to complete before Acceptance Testing Discipline:All Open-Work Yet to Commence C Items not critical for commissioning/operation Details Origin Progress Verification E Target Actual m Raised Raised Responsible Comments Area System/Equipment Description CAT Party Status Completion Completion Design-Builder By Date Date Date 1 Select Select 2 Select Select 3 Select Select 4 Select Select 5 Select Select 6 Select Select 7 Select Select 8 Select Select 9 Select Select 10 Select Select 11 Select Select 12 Select Select 13 Select Select 14 Select Select 15 Select Select 16 Select Select 17 Select Select 18 Select Select 19 Select Select 20 Select Select 37 DRAFT COMMISSIONING PLAN 38 DRAFT ACCEPTANCE TEST PLAN I 1 . INTR0DUCTI0N This Acceptance Test(AT) Plan outline has been developed as part of the City of Lake Oswego's Design-Build Operate Maintain proposal package for a new wastewater treatment facility. This document will serve as the basis of the commissioning estimate, as it relates to the Acceptance Test. This outline includes minimum requirements for the Acceptance Test, and additional details will be provided as part of the Final Plan. Portions of the plan have already been developed in complete (e.g., Section 1) while other portions remain in outline form with notes on critical assumptions in blue font(e.g., Section 2). The complete AT Plan will be developed during the Construction Phase of the Project. Additional Assumptions and Clarifications for the commissioning estimate (i.e., testing required prior to Acceptance Testing) have also been provided elsewhere as part of the cost proposal. 1.1 Overview The Lake Oswego Wastewater Treatment Facility(LOWWTF) Project(Project)will provide the City of Lake Oswego (City)with a new greenfield WWTF. Flows currently treated at the Tryon Creek Wastewater Treatment Plant will be rerouted to the new LOWWTF. Major project components include: • Influent Pump Station • Headworks • Aeration Basins • Clarifiers • Filtration • Ultraviolet(UV) Disinfection • Sludge Thickening • Sludge Storage • Odor Control • Chemical Feed Systems The Project is being delivered via the DBOM Agreement for the Design, Construction, Operation, and Maintenance of the Lake Oswego Wastewater Treatment Plant(DBOM Agreement) by Jacobs Project Management Co. (DBOM Contractor). A formal Acceptance Test(AT) will demonstrate compliance of the Project with the Performance Guarantees detailed herein. The purpose of this Acceptance Test Plan (AT Plan) is to provide a sequenced, clear plan for the AT for the Project. 1.2 Commencement of Acceptance Test Prior to commencing the AT,the following activities must be performed: • Substantial Completion has been achieved (DBOM Agreement Article 6.1.D.1). • The Acceptance Test Plan has been submitted and approved in writing by the City(DBOM Agreement Article 6.1.D.2). • The DBOM Contractor has notified the City in writing with a minimum notice of 30 days of the expected initiation of the Acceptance Test(DBOM Agreement Article 6.1.C). • The DBOM Contractor has certified in writing to the City that it is ready to begin Acceptance Testing at least 10 days prior to the actual commencement of any Acceptance Testing (DBOM Agreement Article 6.1.C). 111 DRAFT ACCEPTANCE TEST PLAN • The DBOM has received specific authorization from applicable Governmental Bodies necessary to commence Acceptance Tests and has provided evidence of such authorization to the City(DBOM Agreement Article 6.1.D.3). • The Company has certified that it has complied with the pre-Acceptance Testing requirements of Appendix 8 of the Service Contract(DBOM Agreement Article 6.1.D.4). Note that it is anticipated that the Governmental Bodies will not require approval of the Acceptance Test Plan, and therefore this will not be a requirement for commencing the Acceptance Test unless indicated otherwise by any Governmental Body. 1.3 Acceptance Test Plan Requirements and Submittal Timeline The DBOM Contractor will prepare and submit the following to the City: • Draft of the AT Plan at least 150 calendar days prior to the commencement of ODEQ requiring such plan or commencement of Commissioning (DBOM Agreement Article 6.1.A). • Final AT Plan following receipt of the City's comments on the Draft AT Plan. Note that the City will complete their review of the Draft AT Plan and provide comments to the DBOM Contractor within the timeframes described in Agreement Appendix 6 paragraph 3.3.Testing will not occur prior to approval of the Final AT Plan from the City. The AT Plan addresses several topics identified in the DBOM Agreement.These items, along with a cross reference of where they can be found within this document, are provided in Table 1-1. Table 1-1.Acceptance Test Plan Requirements and Cross-References Acceptance Test Plan Requirement Acceptance Test Plan Reference All procedures to be used(DBOM Agreement Article 6.1.6). Section 2,3 All specific measurements to be made(DBOM Agreement Article 6.1.6). Section 3,Attachment A and B Proposed usage of permanent and temporary instrumentation(DBOM Agreement Article 6.1.B). Section 2.3 •rganization of the test team(DBOM Agreement Article 6.1.B). Section 5 Testing schedule(including the estimated date,time and duration of each test)(DBOM Agreement Article Section 2.1 6.1.B). Operating and maintenance schedule during testing(DBOM Agreement Article 6.1.6). Section 2. Acceptance Test Protocol:Duration,frequency of monitoring,and analytical methods for proving that the Section 2.1,3.1-3.3 Project meets all guaranteed effluent quality parameters(BOD,TSS,disinfection,etc.)(DBOM Agreement Appendix 8.4). Reliability Demonstration:A plan to demonstrate continuous,uninterrupted operation of the entire facility, Section 2.2 including testing the functionality of redundant equipment(DBOM Agreement Appendix 8.4). Failure and Retesting Plan:Clearly defined triggers for Acceptance Test failure and the subsequent Section 4 corrective actions,retesting procedures,and revised schedule(DBOM Agreement Appendix 8.4). I 2 I DRAFT ACCEPTANCE TEST PLAN 2.ACCEPTANCE TEST OPERATIONAL PROCEDURES This section of the AT Plan will describe the general operational procedures that will be utilized to conduct the AT. 2.1 Test Schedule This section of the AT Plan describes the planned time of year for the testing. Assumptions include: • The duration of the AT will be 15 days. • The AT will occur when the prerequisites in Section 1.2 are met. Commencement of the AT is not limited by the time of year (AT can occur during either the Dry Weather or Wet Weather Season). - At the time of cost proposal, the anticipated time of year for the AT is the 2031 Wet Weather Season. • City will provide an instantaneous minimum influent flow of 1 MGD to the LOWWTF for the duration of the AT. 2.2 Equipment and Systems to be Operated This Section will describe the permanent systems that will be utilized to perform the AT;systems will be summarized in table format(Tables 2-1). Example processes are provided. Additional Assumptions: • A process startup period prior to starting the AT is included in the project schedule to verify process performance and fine tune controls prior to starting the AT and will be detailed in the Transition and Phasing Plan. • In general, the AT will include all major systems listed in Section 1.1. • Where multiple basins or trains are present(e.g.Aeration Basins, Clarifiers, Filters, UV Disinfection), the Final AT Plan will coordinate which are planned to be run during the AT. The design flows and loads will be demonstrated to the extent possible by minimizing the number of online trains during the AT. Standby basins or trains will be brought online throughout the AT only as required by influent flows and loads exceeding the design capacity of a single train. • To maximize process stability,it is anticipated that the online Aeration Basins and Clarifiers will not be rotated during the AT. All basins and equipment will undergo Functional and Systems Testing during clean water testing to demonstrate that the installed equipment meets the design requirements and functions as an entire system. This testing is sufficient to provide confidence that all units of the same process(i.e., all Aeration Basins)will provide similar treatment. • Where like equipment exists(e.g., Influent pumps,screening channels), equipment shall be rotated throughout the AT so that each piece of equipment is demonstrated. Where like equipment exists, but is dedicated to an offline basin(e.g., RAS pump dedicated to an offline Clarifier), the equipment will not be run as part of the AT. • The Rotary Drum Thickener(RDT)Feed Pumps, RDTs, Sludge Storage Tanks,Sludge Storage Tank Mixing and Transfer Pumps will be operated as required by the process. • Process setpoints will be discussed during each daily AT meeting.Adjustments to the process setpoints may be made throughout the day based on field conditions at the discretion of the DBOM Contractor. • Systems will be operated in automatic control where designed based on the final control narratives. The DBOM Contractor will direct which control modes to use when there are multiple control modes(e.g.,flow pace vs dose pace for chemical systems). • The DBOM Contractor's process instrumentation and controls systems(PICS)team may make optimizations to the control system during the AT(modify PID tuning or minor control modifications based on operator preference and input). Control modifications may require brief downtime of specific PLCs(i.e., less than 30 minutes)to download programming modifications to the PLC(s)or other similar PLC modifications. Planned PLC downloads shall not constitute a failure of the AT. 131 DRAFT ACCEPTANCE TEST PLAN Table 1-1.Example-Equipment to be Operated During the AT Process Total#of Installed Units #Units in Service During AT Notes Influent Pump Station 6 Varies Pumps sequence on/off and ramp automatically as required to maintain a wet well level.Rotate Lead/Lag to allow all pumps to run during the AT. Clarifiers 4 2 Anticipated number of Clarifiers required during AT. Additional Clarifiers to be brought online only when influent flows and loads exceed the design capacity of the online Clarifiers.Online Clarifiers will not be rotated during the AT. RAS Pumps 4 2 Pumps ramp automatically based on plant flow pacing.Pumps associated with offline Clarifiers are not run during the AT. 2.3 Temporary Components If any temporary components or instrumentation are required for the AT, the requirements will be summarized here. No temporary components are anticipated at the time of the cost proposal based on the procedures identified herein. 2.4 Influent Flows and Loads Influent Flows and Loads Assumptions: • Many design conditions cannot be demonstrated during the AT due to limitations in the influent(i.e., there is no ability to control influent flows and loads). • The AT will be conducted with the actual flows and loads available at the time of the AT. The DBOM Contractor will not adjust the influent flows and loads to support testing. • The design flows and loads will be demonstrated to the extent possible by minimizing the number of online trains during the AT. • LOWWTF Influent Characteristics are established in the Agreement. Failure to meet a Performance Guarantee when influent characteristics are outside of the established envelope shall not constitute a failure of the AT. 2.5 Operating and Maintenance Schedule For the AT,the Project will be operated continuously. Operating requirements will be as written in the specific vendor O&M Manuals.These manuals(in at least draft form)will be in possession of the DBOM Contractor and available to the team at all times during the AT.Maintenance scheduling during the AT will be programmed into the computerized maintenance system, and maintenance activities will be action based on set intervals or run hours as recommended by the manufacturers. 2.6 Procedures for Testing Standby Power Proper operation of the electrical power automatic transfer will be conducted as described in the Commissioning Plan.This test may be performed prior to, during, or following the Acceptance Test. If the test is conducted prior to the Acceptance Test, it may be performed with clean water in the temporary recirculation loop.The DBOM Contractor will notify the City prior to performing the testing.The City may witness this testing at their discretion. Power loss will occur by opening the main breaker from the Utility on Switchgear 35-SWGR-001-01,which provides power to the LOWWTF.When power is lost, equipment installed at the LOWWTF will stop but controls will continue to operate on UPS. The LOWWTF will then be brought back online on generator power. On return to utility power,standby power will remain online for a preset adjustable time to ensure utility power is stable.As with the initial power loss,all equipment will drop offline on transfer back to utility power. Instrumentation and controls will be maintained on UPS,and the LOWWTF will be systematically brought back online. 141 DRAFT ACCEPTANCE TEST PLAN 3.ACCEPTANCE TESTING PROCEDURES FOR DEMONSTRATING COMPLIANCE This section of the AT Plan will describe the reporting and sign-off requirements during the AT. 3.1 Performance Guarantees The Performance Guarantees are listed in Attachment B, and the allowable LOWWTF influent flows and loads are listed in Attachment A. Influent flows and loads outside of the noted flows and loads would trigger relief from the Performance Guarantees. 3.2 Parameters to be Monitored The AT will demonstrate that the Project meets the Performance Guarantees. This Section of the AT Plan describes what analyses will be conducted and how results of these analyses will be used to demonstrate compliance with the Performance Guarantees. Attachment B lists the parameters and frequency for those parameters to determine compliance during the AT. Assumptions: • The DBOM Contractor will use analyses completed for regulatory compliance to demonstrate compliance with the Performance Guarantees. • Additional sampling required to demonstrate compliance with the Performance Guarantees beyond that normally completed for regulatory compliance will be completed by the DBOM Contractor. The DBOM Contractor will transport these samples to a subcontracted state-certified third-party lab for analyses. • 24-hour composite samples for monitoring influent loading will be collected at the permanently installed automatic composite sampler upstream of the Headworks Coarse Screens. • 24-hour composite samples for demonstrating compliance with the Performance Guarantees will be collected at the permanently installed automatic composite sampler downstream of the UV Disinfection process. • Daily grab samples to demonstrate compliance with the E.Coli Performance Guarantees will be collected from within the UV Channel adjacent to the effluent weir. One UV Channel will be sampled per day. If multiple UV Channels are online at the time of sampling, the selected UV Channel for sampling will rotate daily. 3.3 Sampling and Analysis Procedures The DBOM Contractor will perform sample collection and analysis as identified in Sections 3.2 and Attachment B.Analytical methods will be EPA-approved methods or in accordance with the Standard Methods for Examination of Water and Wastewater. In the event that a particular parameter does not have a method approved by the State, methods currently approved by EPA will be used. The City may accompany the DBOM Contractor in sample collection and analysis at their discretion. 3.3.1 Third Party Laboratory Sampling • A state accredited laboratory will be utilized for any third-party lab analysis performed by the DBOM Contractor. 3.3.2 Additional City Samples The City may desire to analyze additional samples outside of Performance Guarantee samples. If the City would like to collect their own samples,the City may accompany the DBOM Contractor at any time on their normal sampling rounds. If the City would like to take samples outside of the normal sampling rounds of the DBOM Contractor,then a DBOM Contractor representative may accompany the City in collection of their own samples. It is assumed that the City will employ their own quality control procedures in sample collection and analysis when collecting additional samples.The City shall provide notification to the DBOM Contractor during the Daily AT Meetings so that it can be coordinated accordingly.Only those samples collected and analyzed for compliance by the DBOM Contractor as noted in Attachment B will be used for determining compliance with the Performance Guarantees and acceptance of the AT. 151 DRAFT ACCEPTANCE TEST PLAN 3.4 Reporting 3.4.1 Daily Reports Throughout the AT, Daily Reports will be developed by the DBOM Contractor and submitted to the City within 24 hours of each day of testing.The City will appoint a City AT Lead, and this role will provide notification to the DBOM Contractor within 24 hours of receipt of the Daily Reports if they determine that the day represented by the report was successful or was unsuccessful. For instance,for a test day that runs from Monday 8:00 a.m.to Tuesday 8:00 a.m.,the Daily Report will be submitted to the City no later than Wednesday at 8:00 a.m.The City will then provide review and sign-off of the Daily Report no later than 24 hours following receipt of the Daily Report. Daily reports will include a list of acceptance criteria and whether or not they were met for the day, continuous monitoring results in the form of SCADA trends, laboratory results, and sign-off fields for the DBOM Contractor and City representatives. Laboratory samples may not be available on a daily basis like the online instrumentation data. Laboratory results will be included in the new Daily Reports as results become available. It is understood that review of the Daily Reports only includes information that is available within the report and lagging laboratory information will be reviewed as part of subsequent reports. 3.4.2 Acceptance Test Report An AT Report will be provided to the City with the test results following completion of the AT.The DBOM Contractor will complete the AT Report and certify that the AT has been successfully completed within 10 days of completion of the AT (DBOM Agreement Article 6.1.F). It is understood by all parties that some laboratory testing results may be outstanding at this time due to laboratory turn-around time.Any outstanding laboratory analysis will be submitted once received for final documentation. The following information related to the Project will be provided as part of the report(DBOM Agreement Article 6.1.F): • The Acceptance Tests conducted; • The results of the Acceptance Tests; • The level of satisfaction of the Acceptance Standards;and • The level of satisfaction of all Acceptance Conditions set forth in the DBOM Agreement. The City will provide notice within 10 business days following receipt of the Acceptance Test report whether to issue the Acceptance Certificate(DBOM Agreement Article 6.3.A). 161 DRAFT ACCEPTANCE TEST PLAN 4. RESPONSE PROCEDURES This section of the AT Plan will summarize the process to be followed when unanticipated test conditions are encountered. As is the case with all projects, some unanticipated test conditions will be experienced during the AT. Failures are defined herein as either non-critical failures or critical failures. Each of these is further discussed in the subsections below.When an unanticipated test condition is experienced,the issues resolution matrix on Figure 4-1 will be used to determine the path forward. 4.1 Influent Flows and Loads Should the DBOM Contractor fail to meet the Performance Guarantees because the LOWWTF influent flows and loads are outside of the allowable influent identified in Attachment A,the AT will be paused until the water quality comes back into compliance with the Performance Guarantees.At that point,the AT will resume.The time spent successfully meeting Performance Guarantees prior to the LOWWTF influent flows and loads change will be counted toward the overall AT duration requirement. Per Article 9.1 of the DBOM Agreement, influent quality outside of the allowable influent identified in Attachment A will be considered a Relief Event. If the raw wastewater influent contains toxic substances at any time that materially and adversely affect the biological activity or the ability of the Project to meet the Performance Guarantees,then any associated impacts or costs will be the responsibility of the City. 4.2 Non-Critical Failures A non-critical failure is generally a condition that does not invalidate an ongoing test.More specifically,the ability to convey process flows and meet the requirements of the Performance Guarantees is not interrupted. Equipment failures where standby equipment starts in its place such that treatment remains within the Performance Guarantees will not constitute a failure or a pause of the AT. In the case of a non-critical failure,the DBOM Contractor's staff will follow normal procedures to identify and perform corrective maintenance. It may be determined that a non-critical failure is not able to be fully corrected prior to completion of the AT due to spare parts not being in stock and requiring a long lead time, equipment needing to be sent back to the factory, or a number of other reasons. For equipment that fails prior to or during the AT that cannot be corrected prior to the completion of the AT, equipment will be repaired, and its proper operation will be verified upon return to service in accordance with the Project warranty requirements and procedures. Any equipment failures and repairs will be documented by the DBOM Contractor through the maintenance management system. 4.3 Critical Failures A critical failure is one that results in the inability to treat process flows to meet the Performance Guarantees.A critical failure will require a pause in, or a restart of,the AT. In the case of a critical failure,the City and DBOM Contractor will evaluate each instance of a major issue on a case-by-case basis to determine whether a pause or a termination of the Acceptance Test is prudent based on the issue. It may be determined that a failure may not be able to be fully corrected within the testing period as a result of spare parts not being in stock and requiring a long lead time, equipment needing to be sent back to the factory, or a number of other reasons. In these cases, it may be possible to extract specific components from the AT and to perform a separate 10-day test on the failed components only as a prerequisite to Final Completion. 171 DRAFT ACCEPTANCE TEST PLAN 4.4 Decision Process for Unanticipated Test Conditions When an unanticipated test condition is experienced,the issues resolution matrix in Figure 4 1 will be utilized to determine the path forward.There may be cases where the AT is paused while an issue is evaluated and corrected. In these cases,the City and DBOM Contractor will evaluate the failure and determine the acceptable duration of the pause, reasonably assess the importance of the failure, and finalize any requirements to resume the test. The City and the DBOM Contractor will coordinate to determine the best course of action based on the nature of the issue that resulted in the pause. Issue is identified All flow can continue to be treated and meet the Performance Guarantees DBOM Contractor YES NO Issue reported reports issue to Q l immediately to City NON-CRITICAL FAILURE CRITICAL FAILURE both parties V Exceedance in Performance Guarantees is due Continue AT to out of compliance influent I Pause AT until influent is in City and DBOM compliance,Performance YES NO Guarantees are in compliance, Q D Contractor meet to and/or parties agree on modified discuss corrective Performance Guarantees action plan V Plan allows for Resume AT" separate test of failed component(s) V YES NO DBOM Contractor corrects conditions and testing resumes when Performance DBOM Contractor Guarantees are Resume AT performs separate met test for Final Completion (identified items only) V City disposition on Legend if AT continues AT=Acceptance Test from pause or restarts at Day 1 Notes Resume AT 1)Time prior to issue counted towards overall test period 41110 Figure 4 1. Decision Process for Unanticipated Test Conditions 181 DRAFT ACCEPTANCE TEST PLAN I .ORGANIZATION OF TEST TEAM This section of the AT Plan defines the roles and responsibilities for activities during the AT. 5.1 Overview During the Acceptance Test the DBOM Contractor's staff will be responsible for the operation of the Project.The Operations Manager will operate and maintain the Project components in accordance with this Plan.The Commissioning Manager will be available for the duration of the AT and will provide guidance and support for the AT.The following sections discuss the shift coverage during the AT and the roles and responsibilities of the team members. 5.2 DBOM Contractor Staff This section will identify the specific roles and responsibilities of the DBOM Contractor and its subcontractors. Preliminary roles and responsibilities are identified in Table 5 1. These responsibilities may be adjusted between individuals as more individuals are assigned to specific roles. Table 5 1.Roles and Responsibilities During the AT Role Name Responsibilities DBOM Manager Michelle Green • Overall responsibility for the Project. • Ensures delivery of the Project through design,construction,installation,commissioning,and operations handover is seamless. • Engages in issues resolution during the AT if necessary. Commissioning Director Alex Yoffie • Responsible for coordinating commissioning staff support needs for the AT. • Develops or oversees the development of the AT Plan and Reports. • Ensures that Agreement compliance obligations related to the AT are met. • Indirectly supervises the commissioning staff via the Onsite Commissioning Manager. • Provides additional support to the commissioning team as needed. • Engages in issues resolution during the AT if necessary. Onsite Commissioning TBD • Primary contact for providing oversight to the O&M staff in the operations and maintenance Manager of the Project components. • Manages and coordinates the activities of the commissioning team and commissioning activities. • Receives all site related correspondence concerning testing activities. • Coordinates specialist or technical advisers required from the engineering team,different suppliers,and subcontractors. • Oversees subcontractors providing maintenance activities. • Coordinates corrective maintenance if necessary. Process Engineer • Attends daily meetings. _ma • Provides technical guidance to onsite team for troubleshooting and optimization. • Coordinates updates to Operations and Maintenance Plan as necessary based on AT results. • Assists in technical issues resolution as necessary. Senior Technical Bill Leaf • Assists and advises the commissioning team of technical guidance during the AT. Consultant DRAFT ACCEPTANCE TEST PLAN Role Name Responsibilities Commissioning Lead TBD • Attends daily meetings. • Monitors performance of Project for duration of the AT. • Develops the Daily Reports and AT Report. • Assists in technical issues resolution as necessary. • Provides other support to the Onsite Commissioning Manager or Senior Technical Consultant as needed. PICS Lead TBD • Monitors control system and instrumentation performance during AT. • Coordinates with commissioning team to obtain required documentation of AT activities. • Responds to questions from the operations and maintenance staff regarding the controls. • Coordinates corrective actions to the control system when necessary. O&M Project Manager TBD • Responsible for operations and maintenance of the Project • Supervises operations and maintenance staff • Coordinates with the commissioning manager on operations and maintenance decisions • Works with the Commissioning Manager to identify and resolve AT issues • Responsible for regulatory reporting • Attend daily AT meetings • Reviews plant performance on a daily basis,including weekends for the duration of the AT Operations Supervisor TBD • Reports to the O&M Project Manager • Manage operations staff and oversee day-to-day operations • Assist the O&M Project Manager in identifying and resolving operational issues • Provide operational redundancy Maintenance Supervisor TBD • Reports to the O&M Project Manager • Manage maintenance staff and oversee day-to-day maintenance activities • Maintain the computerized maintenance management system • Schedule preventative maintenance tasks • Maintain the equipment spare parts inventory • Maintain spare parts storage areas • Assist on various equipment repairs and maintenance activities • Oversee SCADA/PLC maintenance O&M Staff TBD(multiple) • Reports to the Operations and Maintenance Supervisors • Operations staff will perform operational tasks,basic laboratory testing,and housekeeping tasks • Maintenance staff will be responsible for repairs to equipment and treatment components and entering completed work orders into the computerized maintenance system I&C Maintenance TBD • Reports to the O&M Project Manager Technician • Performs instrument calibrations,preventative maintenance,and repairs related to instrumentation and controls • Enters completed work orders into the computerized maintenance system Laboratory Support Staff TBD • Collects,handles,and tracks samples from designated locations in the field. • Fills out and handles chain of custody documents. • Delivers or ships samples to a pre-designated laboratory. • Conducts lab analyses in the onsite laboratory. • Maintains lab results in spreadsheet format. During the AT,the DBOM Contractor shall provide the following staff FTEs based on the cost proposal: • Commissioning Manager during normal work hours and on the weekends(Monday through Sunday 7:00 a.m.to 4:00 p.m.)for a total of 1.6 FTE. • Commissioning Lead during normal work hours and on the weekends(Monday through Sunday 7:00 a.m.to 4:00 p.m.) fora total of 1.6 FTE. 10 DRAFT ACCEPTANCE TEST PLAN • Process Engineer onsite for 1.0 FTE during weekdays. • Laboratory Support Staff onsite during normal work hours and on the weekends as needed to support sampling and analyses to demonstrate compliance with the Performance Guarantees. • O&M Project Manager onsite for 1.0 FTE during normal work hours. • I&C Maintenance Technician onsite for 1.0 FTE during normal work hours. • Operations and maintenance staff per the Staffing Plan. • A list of 24-hour"on call" representative supervisory persons for hours when DBOM Contractor staff is not onsite. In addition, during the AT the DBOM Contractor will: • Perform corrective maintenance should any issues arise and provide results to the City. • Provide necessary craft, labor, or supplier assistance, in the event of an emergency equipment failure requiring immediate attention (emergency is defined as a failure of function which precludes the further operation of a critical segment of, or the whole of,the Project). 5.3 City AT Lead During the AT, City staff will observe the performance and operation of the Project at their discretion.The City will appoint a City AT Lead,who is authorized to make decisions on behalf of the City related to the testing.The City AT Lead will be responsible for the following activities: • Monitoring and observing the AT at their discretion. • Attending the Daily AT meetings. • Reviewing and signing off on Daily Reports within 24 hours of receipt. • Reviewing and approving the Final AT Report. 5.4 Communication Protocols This section will describe general communication procedures and decision-making protocols should issues arise. 5.4.1 Internal Communication Internal communication protocols will be briefly described here. 5.4.2 Communication with the City All formal communication should be copied to the Onsite Commissioning Manager and the City's AT Lead.Any requests that have the potential to change scope or schedule must be communicated to both the DBOM Manager and the City's Project Manager. 5.4.3 Communication with Regulatory Agencies The DBOM Contractor will be responsible for compiling regulatory reports required by permits.The DBOM Contractor will be responsible for preparing, signing, and submitting all sampling and testing results and monthly discharge monitoring reports. 5.4.4 Daily Acceptance Test Meetings Assumptions: • Daily AT Meetings will take place each day of the AT. Prior day activities and results will be reviewed and discussed. Objectives for the upcoming day will be reviewed and discussed. • At least one City staff member(and/or designated representative)with decision making authority will be present at the Daily AT Meetings. 1111 DRAFT ACCEPTANCE TEST PLAN 5.4.5 Decision Making Protocols In general, operational decisions will be determined on a daily basis by the DBOM Contractor's commissioning and O&M staff. However, on nearly every project, issues arise,and there may be differences of opinion among the team members as to how to resolve these issues. If there are differences between the City's and DBOM Contractor's interpretation of the contractual requirements as it relates to quality or Performance Guarantees, it may be necessary to engage other staff in the decision- making process. In this case,the AT decision ladder in Table 5 2 will be followed to help move the issue to resolution. Table 5 2.Acceptance Testing Decision Ladder Step DBOM Contractor DB DBOM Contractor O&M City 1 Day-to-Day Discussions AT Team(Commissioning Manager,construction AT Team(O&M leads,lab staff) City onsite staff staff,commissioning leads,senior technical consultant) 2 Issues Identification and'ommissioning Director(Alex Yoffie) O&M Manager City's AT Lead Initial Resolution 3 Issues Resolution DBOM Manager(Michelle Green) O&M Regional Manager(Paul City(TBD) DB Regional Manager(Ashley Currey) Rehault) During the AT, it will be necessary to resolve issues in a timely manner. If issues cannot be resolved at each step, they should be escalated to the next level as soon as possible, but within no more than 24 hours. 12 DRAFT ACCEPTANCE TEST PLAN ATTACHMENT A ALLOWABLE INFLUENT FLOWS AND LOADS I REFER TO APPENDIX 4, TABLE 4-1 OF THE AGREEMENT DRAFT ACCEPTANCE TEST PLAN ATTACHMENT B PERFORMANCE GUARANTEES I REFER TO APPENDIX 13, TABLE 13-1 OF THE AGREEMENT .3 14 Attachment 9A Preliminary Schedule of Values A C D I E F G H I ITEM ITEM DESCRIPTION SCHEDULED WORK COMPLETED MATERIALS TOTAL BALANCE RETAINAGE NO. NO. OF WORK VALUE PREVIOUS THIS PRESENTLY COMPLETED AND % TO (IF VARIABLE APPLICATIONS PERIOD STORED STORED TO DATE (G/C) FINISH RATE) (D+E+F) (C-G) 5% Design-Builder Mobilization $ 11,088,631.87 $ - $ - $ - 11,088,631.87 $ - Design-Builder Mobilization $ 11,088,631.87 $ - $ $ - $ - 0% $ 11,088,631.87 $ - Engineering and Design $ 15,023,872.62 $ - $ - $ - $ 0% $ 15,023,872.62 $ - Engineering and Design Labor $ 14,179,972.62 $ - $ - B - $ - 0% $ 14,179,972.62 $ - Engineering and Design Expenses $ 843,900.00 $ - $ - B - $ - 0% $ 843,900.00 $ - Preconstruction $ 2,335,372.00 $ - $ - $ - $ 0% $ 2,335,372.00 $ - Preconstruction Labor $ 2,192,200.00 $ - $ - $ - $ - 0% $ 2,192,200.00 $ - Preconstruction Expenses $ 143,172.00 $ - $ - $ - $ - 0% $ 143,172.00 $ - Design-Builder General Conditions for Construction $ 27,381,160.00 $ - $ - $ - $ 0% $ 27,381,160.00 $ - General Conditions Labor $ 18,651,160.00 $ - $ - $ - $ - 0% $ 18,651,160.00 $ - General Conditions Expenses $ 8,730,000.00 $ - $ - $ - $ - 0% $ 8,730,000.00 $ - Design-Builder Engineering Services During Construction $ 8,972,017.91 $ - $ - $ - $ 0% $ 8,972,017.91 $ - Engineering Services During Construction Labor $ 8,336,667.91 $ - $ - $ - $ - 0% $ 8,336,667.91 $ - Engineering Services During Construction Expenses $ 635,350.00 $ - $ - $ - $ - 0% $ 635,350.00 $ - Design-Builder Integration and Programming $ 11,256,15t60 $ - $ - $ - $ 0% $ 11,256,151.60 $ - Integration and Programming Labor $ 6,333,094.11 $ - $ - $ - $ - 0% $ 6,333,094.11 $ - Integration and Programming Expenses $ 4,923,057.49 $ - $ - $ - $ - 0% $ 4,923,057.49 $ - Design-Builder Commissioning and Startup $ 6,134,455.57 $ - $ - $ - $ 0% $ 6,134,455.57 $ - Design-Builder Commissioning and Startup Labor $ 4,942,728.12 $ - $ - $ - $ - 0% $ 4,942,728.12 $ - Design-Builder Commissioning and Startup Expenses $ 1,191,727.45 $ - $ - $ - $ - 0% $ 1,191,727.45 $ - Purchase Agreements $ 26,950,448.96 $ - $ - $ - $ 0% $ 26,950,448.96 $ - Purchase Agreements Expenses $ 26,950,448.96 $ - $ $ - $ - 0% $ 26,950,448.96 $ - Construction Subcontracts $ 201,309,482.53 $ - $ - $ - $ 0% $ 201,309,482.53 $ - Mobilization $ 10,376,777.45 $ - $ - $ - $ - 0% $ 10,376,777.45 $ - Expenses $ 190,932,705.08 $ - $ - $ - $ - 0% $ 190,932,705.08 $ - Bonds,Insurance,Taxes,Permits $ 2,922,397.57 $ - $ - $ - $ 0% $ 2,922,397.57 $ - Bonds,Insurance,Taxes,Permits Expenses $ 2,922,397.57 $ - $ $ - $ - 0% $ 2,922,397.57 $ - Desi•n-Builder Fee $ 27,908,284.19 $ - $ $ - $ 0% $ 27,908,284.19 $ - Design-Builder Fee Expenses $ 27,908,284.19 $ - $ $ - $ - 0% $ 27,908,284.19 $ - Design-Builder Contingency and Escalation $ 28,338,790.65 $ - $ $ - $ 0% $ 28,338,790.65 $ - Design-Builder Contingency and Escalation Expenses $ 28,338,787.65 $ - $ - $ - $ - 0% $ 28,338,787.65 $ - Owner Escalation $ 13,500,000.00 $ - $ $ - $ 0% $ 13,500,000.00 $ - Owner Escalation Expenses $ 13,500,000.00 $ - $ - $ - $ - 0% $ 13,500,000.00 $ - Attachment 9B Maximum Drawdown Schedule $18,000,000.00 $450,000,000.00 $16,000,000.00 $400,000,000.00 $14,000,000.00 $350,000,000.00 $12,000,000.00 $300,000,000.00 $10,000,000.00 $250,000,000.00 $8,000,000.00 $200,000,000.00 $6,000,000.00 $150,000,000.00 $4,000,000.00 $100,000,000.00 $2,000,000.00 $50,000,000.00 IIII � III � Ii Lc) I� n n n n n CO CO 00 00 CO 00 01 01 01 01 01 01 O O O O O O ci r-I a--I ci ri r-I N N N N N N N N N N N N N N N N N N N N M M M M M M M cr1 M M M M M O c0 c0 c0 N O c0 c0 c0 A• 0) O c0 c0 c0 0) O CO co m A' 0) O c0 c0 c0 0) O ca Z 22A A v) z 7 2 2 A z722Aul, 2 7 2 2 2 7 2 2 N INTERVAL CUMULATIVE Month Interval Cumulative Month Interval Cumulative Nov-2026 $ 1,143,124 $ 1,143,124 Jul-2029 $ 9,024,002 $ 307,245,998 Dec-2026 $ 2,173,494 $ 3,316,618 Aug-2029 $ 8,404,020 $ 315,650,018 Jan-2027 $ 7,272,580 $ 10,589,198 Sep-2029 $ 6,431,775 $ 322,081,793 Feb-2027 $ 4,627,243 $ 15,216,441 Oct-2029 $ 7,909,892 $ 329,991,685 Mar-2027 $ 4,163,391 $ 19,379,832 Nov-2029 $ 7,363,943 $ 337,355,628 Apr-2027 $ 3,519,075 $ 22,898,908 Dec-2029 $ 6,487,260 $ 343,842,888 May-2027 $ 3,949,181 $ 26,848,088 Jan-2030 $ 4,514,628 $ 348,357,516 Jun-2027 $ 4,952,545 $ 31,800,633 Feb-2030 $ 3,919,185 $ 352,276,701 Jul-2027 $ 5,983,476 $ 37,784,108 Mar-2030 $ 3,335,814 $ 355,612,515 Aug-2027 $ 6,439,427 $ 44,223,536 Apr-2030 $ 3,520,134 $ 359,132,648 Sep-2027 $ 4,399,791 $ 48,623,327 May-2030 $ 3,465,413 $ 362,598,062 Oct-2027 $ 6,284,744 $ 54,908,071 Jun-2030 $ 3,090,349 $ 365,688,411 Nov-2027 $ 8,769,744 $ 63,677,816 Jul-2030 $ 3,023,860 $ 368,712,271 Dec-2027 $ 10,174,605 $ 73,852,421 Aug-2030 $ 2,719,721 $ 371,431,991 Jan-2028 $ 10,663,469 $ 84,515,890 Sep-2030 $ 1,986,510 $ 373,418,501 Feb-2028 $ 10,948,789 $ 95,464,679 Oct-2030 $ 1,956,950 $ 375,375,452 Mar-2028 $ 13,608,714 $ 109,073,393 Nov-2030 $ 1,441,707 $ 376,817,158 Apr-2028 $ 11,394,265 $ 120,467,657 Dec-2030 $ 1,621,748 $ 378,438,906 May-2028 $ 13,166,669 $ 133,634,326 Jan-2031 $ 990,557 $ 379,429,463 Jun-2028 $ 13,403,391 $ 147,037,717 Feb-2031 $ 633,845 $ 380,063,309 Jul-2028 $ 14,135,834 $ 161,173,551 Mar-2031 $ 631,972 $ 380,695,280 Aug-2028 $ 17,021,976 $ 178,195,527 Apr-2031 $ 512,993 $ 381,208,273 Sep-2028 $ 13,975,613 $ 192,171,140 May-2031 $ 474,674 $ 381,682,947 Oct-2028 $ 14,125,289 $ 206,296,429 Jun-2031 $ 407,808 $ 382,090,755 Nov-2028 $ 12,813,875 $ 219,110,304 Jul-2031 $ 342,606 $ 382,433,361 Dec-2028 $ 13,911,835 $ 233,022,138 Aug-2031 $ 124,821 $ 382,558,183 Jan-2029 $ 13,827,594 $ 246,849,732 Sep-2031 $ 121,836 $ 382,680,019 Feb-2029 $ 10,352,702 $ 257,202,434 Oct-2031 $ 127,638 $ 382,807,656 Mar-2029 $ 11,509,045 $ 268,711,478 Nov-2031 $ 104,431 $ 382,912,087 Apr-2029 $ 10,520,438 $ 279,231,916 Dec-2031 $ 127,638 $ 383,039,725 May-2029 $ 10,227,750 $ 289,459,666 Jan-2032 $ 81,341 $ 383,121,065 Jun-2029 $ 8,762,330 $ 298,221,996 3.4 OPERATIONS AND MAINTENANCE (O&M) PLAN 13.4.1 OPERATIONAL PROCEDURES AND PROTOCOLS Developing and implementing comprehensive and thoughtful O&M management plans establishes the foundation and expectations for performance, and they work best with an integrated team approach. Our general system management philosophy leverages the full breadth of our resources to cost-efficiently deliver performance excellence. Exhibit 3.4.1-1 summarizes this philosophy and the overall procedures and protocols we apply to all the facilities we operate. EXHIBIT 3.4.1-1.Jacobs O&M Management Philosophy Ensure the health of the workforce, compliance with OSHA and other safety Provide environmental compliance regulations,and expertise for and internal auditing certifications asset/data security and management for permit report preparation for Commitment to assist the n regulatory agencies City as a trusted partner through superior customer Health, service while closely Safety,and Compliance and Reporting collaborating to find Security efficiencies in-or-out of our Customer Document w' scope of services Service treatment strategies Operations and process control with Management client access,enabling optimization of systems Commitment to Jacobs' Core work with the City and Community Involvement O&M local community leaders Asset • to enhance the City's Management Management Tools to expedite system implementation image and give back to System the communities in which y and integration that we live and work Administrative optimizes asset Management performance, Sampling and minimizes and Lab implementation time CRobust and proven Financial approach for real-time Management Human Support best 8 performance analysis, Resources practices and award-winning process improvement quality assurance/quality and reporting control(QA/QC)as O Continuous monitoring of requested by the City Offer competitive costs using innovative wages and benefits,superior trending,optimization,and training and career advancement reporting tools to control opportunities to attract and schedule and cost retain a highly-qualified and motivated workforce OMFS_OPM_100_01 7 1 3.4 Operations and Maintenance This proposal summarizes our approach to developing a comprehensive O&M Management Plan that addresses all elements needed to meet the City's and Jacobs' performance requirements. Geographic Director of Operations Shawn Moffitt will provide regional support to Geographic Manager of Operations Travis Capson as he and the O&M Supervisor Tony Benavidez tailor the plan to the final operating and maintenance conditions following facility completion and commissioning.The O&M Supervisor will implement the plan and review it annually, revising it as needed to reflect new equipment or changing conditions. Exhibit 3.4.1-2 summarizes the plan components. EXHIBIT 3.4.1-2.O&M Plan Elements to be prepared by Jacobs O&M PLAN ELEMENTS TO DRIVE PROTOCOLS AND PROCESSES FOR PERFORMANCE EXCELLENCE • Management Oversight and QA/QC • Maintenance of Essential Data and Records • Standard Operating Procedures(SOPs) • Communications and Reporting Plan • Plant Operations including Process Control Procedures • Risk Management Plan • Compliance Monitoring, Sampling, Laboratory/ • Staffing and Training Plan Testing,and Reporting Plan • Subcontractor/Vendor Management • Residuals(Biosolids)Management Plan • Financial Management and Annual Budget Preparation • Odor Control Plan (including response plan) • Safety Program and Plan • SCADA • Security Plan • Noise Control Procedures • Emergency Response/Disaster Recovery Plan • Asset Management Plan (including CMMS Plan) • Hazardous Materials Plan • Major Maintenance/Repair/Replacement Plan • Spill Prevention Control and Counter Measures Plan (with 30-year lifecycle detail) • Sustainability Plan • Information Technology and Operations Technology(OT)/SCADA 2 3.4 Operations and Maintenance 3.4.2 ORGANIZATIONAL CHART AND COMMUNICATIONS PROTOCOLS Organizational Chart Jacobs' O&M organizational structure for the Lake Oswego Wastewater Treatment Facility(WWTF) operations (Exhibit 3.4.2-1) reflects our staffing approach, shaped by extensive experience delivering similar services at comparable facilities.The organization and reporting lines are designed to provide the coverage and accountability required for safe, compliant,and reliable operations. The O&M Supervisor will serve as the primary point of contact for City staff and will coordinate day-to-day communications, issue resolution,and escalation across the Jacobs team. Roles, responsibilities,staffing approach,and license management are described in Section 3.4.8,Staffing Plan and License Management. EXHIBIT 3.4.2-1.Jacobs'O&M Team Organization O&M SUPERVISOR (Grade IV) ADMINISTRATIVE ASSISTANT REGIONAL (0.30) ENGINEERING SUPPORT (0.20) OPERATIONS SUPERVISOR/LEAD MAINTENANCE SUPERVISOR/LEAD LABORATORY ANALYST (GRADE IV) (1) (1) O&M TECH GRADE III MAINTENANCE (FRONT OF WEEK) TECHNICIAN (2) (1) O&M TECH GRADE III REGIONAL ELECTRICAL/ (BACK OF WEEK) I&C TECHNICIAN (1) (0.50) Full-time Onsite Team O&M TECH GRADE II Regional Resources to (FLOATING SHIFT) Support the Project (1) When Required V 3 3.4 Operations and Maintenance Communication Protocols ANNUAL INNOVATION WORKSHOP Jacobs will establish a collaborative,transparent TO DRIVE CONTINUOUS IMPROVEMENT communication framework that supports safe, compliant, and efficient operations for the City. From Day One,our team Jacobs will convene an Annual Innovation Workshop focused will maintain clear points of contact, routine coordination on strengthening the partnership and advancing continuous forums,and defined escalation pathways so issues are improvement.This session will bring together the City addressed quickly and decisions are documented and stakeholders,our onsite O&M team,and three Jacobs subject executed consistently. matter experts selected to match current priorities.Together,we will review the prior year's performance and accomplishments, Effective communication is critical to mutual success. identify improvement opportunities,and agree on goals and We encourage day-to-day coordination between the innovations that support the City's evolving needs and long- City and onsite Jacobs staff to enable timely decision- term vision.This annual forum reinforces accountability, making at the appropriate level and prompt attention to maintains momentum,and ensures the team remains focused operating, maintenance, and compliance needs.Jacobs will on future needs and emerging trends while delivering reliable proactively share operational insights, recommendations, day-to-day performance. and improvement opportunities to build confidence, sustain performance, and support the City's priorities. In addition to frequent informal coordination, our program includes structured meetings to review plant performance, compliance status, maintenance execution, and planned work on major unit processes.As reflected in Exhibit 3.4.2-2, these forums typically include weekly, monthly, and quarterly check-ins, each with defined objectives, required participants, and documented action items. Our O&M Supervisor Tony Benavidez will lead day-to-day coordination and ensure decisions and action items are tracked to closure, with regional management support from Geographic Manager of Operations Travis Capson and Geographic Director of Operations Shawn Moffitt as needed. EXHIBIT 3.4.2-2.Summary of Jacobs'Communications Plan to Ensure a Collaborative, Transparent Partnership WHEN WHAT in WHO Day-to-Day Meetings& »Open exchange of information to ensure »Jacobs O&M Supervisor Discussions transparency and collaboration and O&M Team Weekly Weekly » Review the previous week's events »Jacobs O&M Supervisor Meeting » Discuss future week plans and O&M Team » Document decisions Monthly Monthly » Progress update and collaboration »The City/Jacobs Reviews » Review process performance O&M Supervisor » Review maintenance performance » Review CIP and impact to operations Quarterly Quarterly » Review quarterly progress »Jacobs Regional Management Business » Discuss future objectives and opportunities »The City/Jacobs Review for continuous improvement O&M Supervisor Annual Annual » Review prior year's accomplishments »Jacobs Executive Team Innovation while establishing new goals and » External Jacobs Utility Experts Workshop objectives for the following year to »City's Leadership Team ensure continuous improvement »The City/Jacobs O&M Supervisor 121_005NWD 7 141 3.4 Operations and Maintenance Reporting Reporting is a key component of our transparency and communications approach. Our detailed reporting procedures are described in Section 3.4.15 Operating Reports. During finalization of the O&M Plan,we will align the Communication Plan with the Agreement requirements and the City's preferences, including meeting cadence, deliverables, documentation protocols, and escalation expectations. Public Communications (Operations Period) During Operations, Jacobs will support the City's public communications objectives through a disciplined, responsive,and well-documented approach.The City will remain the lead for external/public-facing communications;Jacobs will provide timely technical information, operational context,and recommended response actions to support the City's messaging and decision-making. Points of Contact and Availability.Jacobs will designate a primary communications contact and backup(s)to support urgent operational communications.All media inquiries and interview requests will be routed to the City's designated lead communications contact.Jacobs will not issue public statements, releases, or public-facing materials related to WWTF operations without the City's review and approval. Inquiry and Complaint Intake and Response.Jacobs will support a clear process for receiving and responding to public inquiries and complaints related to WWTF operations(e.g., odors, noise, light, spills, or other service concerns).As directed by the City,Jacobs will: • Support established intake channels(phone, email,and mailing address). • Acknowledge and begin response actions within 2 hours for urgent issues(including odors, spills, leaks/breaks, noise/light concerns,and emergencies)and within 24 hours for all other inquiries. • Coordinate closely with the City on response messaging, corrective actions,and follow-up communications. Documentation,Tracking,and Reporting.Jacobs will maintain a written log of material public inquiries, complaints, and related communications, including date/time received, issue category,actions taken, response status,and closeout.We will elevate urgent matters immediately,transmit logs to the City at the required frequency, and summarize trends, recurring issues,and corrective actions in routine operations reporting. Annual Communications Plan Maintenance.Jacobs will review the operations-focused public communications procedures at least annually with the City to confirm contacts, escalation pathways, response expectations, reporting formats,and approval protocols remain current. v I 5 I 3.4 Operations and Maintenance 3.4.3 STANDARD OPERATING PROCEDURES FOR ALL EQUIPMENT AND TREATMENT PROCESSES Our comprehensive,thoughtful process control strategy provides the focal point for all operational activities.The Jacobs team will design our process control plans to avoid process upsets and maintain high-quality, steady-state operations. Operating strategies will be audited and updated annually. During each review cycle, we'll explore opportunities for innovation and make adjustments as needed.At all times,the current process control plan will be fully documented. Development of the Process Control Strategy The process control strategy will consider plant design, influent characteristics, treatment parameters, performance goals, and permit requirements. From there, our operators and technical specialists will develop a strategy that will best meet required performance while maintaining efficient operations.The strategy will identify critical aspects of the treatment process, detail how unit processes will be monitored and controlled, and establish our strategic and tactical approaches to achieve treatment goals efficiently and reliably. Our onsite team will stay on target through weekly process control meetings that include all staff. During those meetings, the team will review performance over the previous week, make process control adjustments, discuss maintenance concerns, and plan for upcoming activities.We will also plan for special circumstances like extreme weather, construction activities, or other outside services in these meetings. Results will be documented and posted for all staff.The weekly meetings are critical to improving communication, planning, and performance. Jacobs' Suite of Process Tools for Performance Excellence Based on our extensive experience and best practices, we have developed a robust suite of tools, summarized in Exhibit 3.4.3-1, to support the process control strategy. EXHIBIT 3.4.3-1.Jacobs'Tools for Operational,Process,and Compliance Success Built on Best Practices and Decades of Experience PROVEN OPERATIONS PLAN DESCRIPTION BENEFIT TO THE CITY PLANS UPCPs outline our operations road map,establish the Documented procedures and process targets shared with key performance and parameters we track,drive process the City,management,O&M,and laboratory staff confirm UNIT PROCESS adjustments,direct continuous improvement,and clearly a common purpose and goal.The detailed information CONTROL PROCEDURES(UPCPS) establish lines of communication and control.UPCPs also provided maximizes efficiency and minimizes potential for provide the detail needed for operators and maintenance errors and downtime. personnel to make informed decisions. The Sampling Plan includes a well-thought-through and A properly written and implemented sample plan is understood list of sampling locations,a sampling map,and critical to the compliant and efficient operation of a SAMPLING PLAN parameters to be sampled at each location.It also identifies facility.Reliable,accurate data starts with representative methods to be used,proper chain of custody techniques,and sampling to achieve effective solids balances proper preservation procedures. and process control. Data collection will be driven by the Sampling Plan and will Direct access to the data management software will allow be collected through lab analysis or online instrumentation the City to"mine"the database for specific data.Regular and entered manually or directly from SCADA.Jacobs will reports will provide the City with a quick summary of how DATA MANAGEMENT install and use Hach WIMS to allow for the use of Jacobs' the plant and individual unit processes are performing. process control system(PCS). Exporting data into our PCS will allow additional assurances by allowing our regional support staff to analyze data and trends to assist the onsite operations staff in real time decisions and to drive optimization. 6 3.4 Operations and Maintenance PROVEN OPERATIONS PLAN DESCRIPTION BENEFIT TO THE CITY PLANS SOPs make sure that safe work practices and consistent Development of SOPs is an ongoing process.Critical SOPs operations of equipment and systems are implemented will be developed first,and new SOPs will be developed STANDARD OPERATING and followed by O&M staff.SOPs typically contain as required.SOPs ensure consistent and standard PROCEDURES(SOPS) precautionary safety steps followed by startup,shutdown, procedures are followed to ensure staff safety,operations and routine monitoring of the equipment,as well as the performance,and equipment reliability. detailed information needed to complete the work properly, safely,and efficiently. One of the most effective ways to maintain control of the Round sheets are printed out daily through the CMMS treatment process and operational equipment is to perform and completed by the operator at least daily or twice a daily,or more frequent,rounds of the Plant.Daily round day,as necessary.Unusual observations are recorded sheets consist of readings,observations,and preventive on the round sheet and the data is uploaded into the OPERATOR maintenance tasks that give early warning of potential CMMS.Unusual observations or readings are reported ROUND SHEETS process upsets or problems with equipment.That allows immediately to the operations supervisor so that the staff to make process adjustments or create work orders to appropriate action can be taken. proactively correct the issue.Operator round sheets also identify housekeeping and safety actions to keep the Plant safe,clean,and in showcase condition. Our SIT is used by operations staff to monitor and track A key element of compliance is ensuring that samples and process and compliance sampling and analysis requirements. analyses are performed at the locations and frequencies This tool is developed and implemented at the start of each outlined in the permit and Scope of Work.The SIT SAMPLE year;as samples are taken and analyzed in-house or sent to a provides the necessary quality assurance to make sure TRACKING TOOL(STT) third-party laboratory,samples are checked off by the person that nothing is missed by the onsite team. who has pulled the samples and then checked off the same day by a second independent party to ensure that all process and compliance samples are taken as per requirements. Unit Process Control Plan (UPCP) A key component of our operational strategy includes the development of the UPCP for each process and includes focus points and key performance indicators(KPIs).We will ensure the Lake Oswego WWTF's UPCPs meet or exceed permit limitations, avoid process upsets, maintain steady-state operations, and produce a high-quality effluent and biosolids product. With assistance from our regional technical specialist,the operating strategies will be audited and updated annually. Our innovative Companywide Process Control System (CPCS)tool automatically reviews process and compliance data from the wastewater and then evaluates process control parameters against set targets.The objective is to make sure that our O&M staff have the right tools to efficiently evaluate and operate each unit of the treatment plant.The CPCS report scores each project every week, measuring how close each team is to achieving their controllable process targets, and reports are automatically emailed to project staff, regional process and management teams, and senior leadership. At the Lake Oswego WWTF project,the CPCS reports are reviewed by both the O&M Supervisor Tony Benavidez and Geographic Manager Travis Capson. Our regional technical specialists will engage with the onsite team weekly and together they evaluate the performance metrics and develop a corrective action plan to address any concerns. Our CPCS is an unmatched process monitoring system, and an example of a weekly wastewater CPCS Report is shown in Exhibit 3.4.3-2. 7 3.4 Operations and Maintenance 3.4.4 SCADA MANAGEMENT APPROACH Jacobs will manage the Facility SCADA/ICS as a critical operational asset—keeping control systems available,secure, maintainable, and standardized while executing upgrades and integrations in a way that minimizes operational risk and downtime.Our SCADA management approach will span master planning through design, integration,testing,and operational handoff,with tight coordination among operations, maintenance, design, and construction teams to maintain the level of service during implementation—especially in live facilities. Systems Integration and Instrumentation Configuration Control, Jacobs maintains in-house capabilities to execute Change Management, and Backups instrumentation and systems integration work for water Jacobs will implement disciplined SCADA operational and wastewater facilities, ranging from SCADA master practices that document and control all SCADA/ICS changes, planning studies through full systems integration.Our maintain recoverability,and preserve auditability.Our SCADA integration teams understand how SCADA systems, management workflow will include: instruments,and OT networks function as a unified control environment, including the cybersecurity and remote access • Change request and screening (reason, scope,affected considerations that must be built into modern systems. assets/tags/screens, operational risk, and rollback needs) • Technical review and operational coordination To execute controls and integration work efficiently (operations/maintenance/design-build interface, cutover and consistently,Jacobs maintains relationships, sales windows,and hold points) agreements,and licensing for PLC and SCADA programming . Test planning (offline/bench testing where feasible;field across major municipal suppliers.We will scale delivery validation steps;acceptance criteria) using qualified platform partners and third-party integrators . Approval and implementation (authorized personnel when needed—while maintaining Jacobs-led governance, only;controlled access) standards, quality control,and single-point accountability . "As-left"backup and version tracking (programs, for performance and documentation. configurations, and HMI changes captured immediately after implementation) Governance, Coordination, and City Alignment • Documentation updates(tag database/I/O lists, Jacobs will manage SCADA as an integrated program narratives, network/architecture diagrams,alarm and will coordinate phasing across concurrent design- setpoints,and any revised operating guidance) build, startup,and O&M activities to prevent conflicts and • Post-change verification (confirm key control functions, protect reliability.We will maintain routine coordination alarms,and trends perform as intended) with the City(as applicable)to support transparency,timely In addition to post-change"as-left" backups,Jacobs will decision-making,and alignment with the O&M Plan and maintain scheduled backups and documented recovery contract requirements. procedures for SCADA/ICS components(including servers/ VMs, PLC programs/configuration,and HMI applications).We Standards-first Execution will also perform restore verification on a defined cadence to Jacobs will establish and enforce SCADA/ICS standards confirm recoverability and reduce operational risk. that define: hardware/software baselines;tag naming conventions; PLC configuration standards; HMI graphics City Access to SCADA Records and Auditability conventions; historian and reporting standards;OT Jacobs will maintain SCADA records in a form capable configuration standards;and OT network architecture of audit and will make SCADA records available to the requirements.This standards first approach drives City consistent with records/access expectations in the consistent implementation, improves maintainability, O&M Plan.At a minimum,Jacobs will maintain and make accelerates troubleshooting, and reduces lifecycle risk. available:configuration and change logs; backup/restore logs; user/access listings and access change history;alarm Reliability and Risk history and alarm performance outputs; historian/trend Management for Live Systems exports used for operating reports;and documentation updates associated with modifications(tag lists, narratives, Jacobs will sequence upgrades to preserve continuous operations, using staged implementation and and relevant drawings/diagrams). commissioning plans that protect system integrity while introducing upgrades and new scope. For mission-critical functions,we will incorporate redundancy/failover where appropriate and implement rollback-ready cutover planning to reduce operational risk. 181 3.4 Operations and Maintenance Alarm Management and Operational Usability Jacobs will manage alarms to support Asset and effective operator response and Maintenance consistent plant performance.Our approach will include alarm priority Management definitions, nuisance alarm reduction Continuous Applications Simulation practices(e.g.,appropriate deadbands/ Imaging S` Applications time delays where appropriate), and and GIS 3- 6. periodic alarm performance review Applications � to improve situational awareness and reliability.Alarm response expectations and escalation triggers will be SCADA Business documented in operator-facing guidance Surveillance Dashboard and incorporated into training and and Security PLATFORM shift turnover practices. Applications p Reporting Applications Diagnostics and performance reporting. Jacobs will provide routine alarm and , •� I trend reporting to support process analysis and optimization.We will also Energy Remote produce diagnostics reporting that and Process and Mobile identifies issues, recommended corrective Optimization Operations actions,and critical spare parts(where Applications applicable)to reduce mean time to repair Laboratory 1113 and improve system reliability. Management Testing,commissioning,acceptance, Systems App and Exit Testing support.Jacobs will manage a structured testing and commissioning pathway that includes test planning, execution, documentation of results, and functional verification of tags, alarms,and integrated system behavior. During implementation we will support submittal review, RFI/change management,and construction testing to verify system performance and support the broader commissioning and acceptance testing requirements. For Exit Testing, Jacobs will explicitly support SCADA-related test planning and deliverables by: • documenting SCADA system monitoring and control functions relevant to the Exit Test Procedures and Standards;and • providing the City a list of real-time data fields that will be available during Exit Testing,aligned with the City's needs for transparency,verification,and independent review. SCADA Support Jacobs recognizes SCADA as essential to compliance, reliable operations, and process optimization,and we will manage SCADA as part of the overall O&M system documented in the final O&M Plan for City review and approval.As an integrated O&M and engineering firm, Jacobs typically self-performs SCADA system integration for the plants we operate—enabling effective collaboration between design and operations teams and ensuring operational usability is built into the solution. Where third parties support discrete tasks,Jacobs will retain standards enforcement, quality control, documentation requirements, and acceptance verification. 191 3.4 Operations and Maintenance Mobile Solutions Jacobs will implement secure, operationally practical mobile capabilities that support field rounds,faster response,and improved situational awareness—while maintaining appropriate access controls, governance,and auditability consistent with Facility cybersecurity and security requirements. Communications and Telemetry Jacobs will help ensure reliable communications between plant and remote assets using fit-for-purpose telemetry and communications approaches(e.g., private networks, radio, cellular,satellite, leased-line, or other methods as appropriate).Our approach will prioritize availability, maintainability,and cybersecurity-aligned connectivity for critical operational data. Advanced SCADA Applications Software Jacobs will manage SCADA as part of a broader operational ecosystem,supporting integration with plant operations practices and,where appropriate, maintenance and reporting systems.We will also deploy and/or configure advanced SCADA applications where they add value—such as improved alarm management,workflow support, and enhanced reporting—so operators receive actionable information and the City has reliable operational visibility consistent with operating report and records/access expectations. Cybersecurity Jacobs will incorporate cybersecurity into OT architecture and SCADA management, consistent with the Contract Standards and the DBOM Agreement requirements. Our approach will include defense-in-depth practices such as OT network segmentation; role-based access/least privilege; controlled remote access; logging and event review;and coordinated patch/ vulnerability management to avoid unplanned disruptions.We will maintain accurate, current records of cybersecurity- relevant configurations and access controls for City review, and we will coordinate cybersecurity actions with operations to protect availability and compliance. 1 10 1 3.4 Operations and Maintenance 3.4.5 ODOR CONTROL PROCEDURES Jacobs will implement and maintain a comprehensive odor control program focused on proactive monitoring, disciplined operational practices, rapid response to odor conditions,and continuous improvement.The program is designed to protect public health and worker safety, minimize off-site odor impacts,and maintain positive relationships with the surrounding community.Jacobs will operate the facility in compliance with all applicable odor-related laws and contract requirements and in a manner that satisfies the Odor Guarantee, preventing odors from creating Odor Incidents except during verified Relief Events. Odor control practices are structured to ensure continuous compliance with the Odor Guarantee and to minimize the risk of Odor Incidents through proactive operations, rapid response,and documented corrective actions. Routine Monitoring and Inspections Odor control practices will include active management of residuals handling and storage durations to minimize Operations staff will routinely monitor the facility for odors, odor generation. Residuals management practices will including hydrogen sulfide(H2S)and other nuisance odors, be evaluated routinely to confirm they remain protective using portable monitoring equipment and direct sensory of odor control objectives under varying operational and observations. Operators will conduct regular patrols of odor- seasonal conditions. generating process areas, building interiors, and the facility perimeter to identify potential odor conditions. During Good housekeeping practices will be emphasized as a periods of elevated odor potential,such as warm weather foundational element of odor control.Operators will operations, residuals handling activities, or maintenance verify that doors and hatches remain closed as required, work, monitoring frequency will be increased as appropriate. ventilation systems are operating properly,and no abnormal Operations staff are authorized to initiate immediate accumulation of solids, debris, or odorous materials is operational adjustments or notify facility management when present within process areas or buildings. potential odor conditions are identified. All monitoring activities will be documented in odor Odor Complaint Response inspection logs, including time,weather conditions,wind In the event of an odor complaint,Jacobs will respond speed and direction, observed odor characteristics, and promptly by dispatching operations staff to the reported any measured H2S concentrations.Odor monitoring location. If odors are present,staff will document odor records will be retained as part of the facility's operational intensity, character, duration,and prevailing meteorological records and made available to the City in accordance conditions and will make all attempts to interview the with the DBOM Agreement. complainant to gather additional information regarding the frequency and timing of odor occurrences.Where Operational Controls and Preventive Measures appropriate, odor complaints and preliminary findings will be escalated to facility management and coordinated Jacobs will actively manage operational conditions that with the City consistent with DBOM Agreement influence odor generation, including dissolved oxygen communication requirements. levels, sludge handling and storage practices, return and waste sludge operations,and housekeeping within odor- Concurrently,an immediate review of facility operations generating areas.Operators will routinely inspect sludge will be initiated to identify potential sources or processing and handling areas to verify that odor control contributing operational conditions.Corrective actions and odor-reducing practices are properly implemented and will be implemented as necessary to mitigate odors and function as intended. Detection of septic or abnormal odors do a follow-on review of the event with staff to analyze will prompt immediate operational evaluation and corrective opportunities to prevent a future occurrence.Jacobs will action, such as modifying aeration rates,adjusting sludge document all odor complaints, investigations,findings, handling schedules, or implementing other process control and corrective actions and will submit them to the City in measures.These operational responses are designed to accordance with the DBOM Agreement. address both immediate odor conditions and underlying process drivers to minimize recurrence and maintain compliance with applicable odor performance requirements. v 111 3.4 Operations and Maintenance Performance Tracking, Reporting, and Continuous Improvement Jacobs will track odor monitoring data, complaint records, and operational trends to evaluate the effectiveness of odor control practices and to identify opportunities for improvement. Monthly odor control practices reporting will summarize odor complaints, investigations, response actions, compliance with odor control operating practices, as required by the DBOM Agreement.Trend analysis will be used to identify emerging conditions that could lead to Odor Incidents and to implement proactive adjustments before complaints or violations occur. Jacobs acknowledges the City's right to conduct odor monitoring and inspections,with or without prior notice, and will cooperate fully with any such activities. Through consistent monitoring, disciplined operations, responsive corrective actions, and transparent reporting, Jacobs will maintain an effective odor control program that minimizes impacts to the surrounding community and supports reliable, compliant facility operations.This approach ensures that odor control remains an integrated, enforceable element of Long-term DBOM performance rather than a reactive or complaint-driven activity. v 112 3.4 Operations and Maintenance 3.4.6 NOISE CONTROL PROCEDURES Jacobs will implement and maintain a proactive noise control program focused on monitoring, preventive operational practices, prompt response to complaints, and continuous improvement.The program is designed to minimize off-site noise impacts, protect worker safety, and maintain compliance with applicable noise regulations and contract requirements while supporting reliable facility operations. Noise control procedures will also support compliance with applicable DBOM Agreement performance requirements, including any noise-related standards or guarantees established for long-term facility operations. Routine Noise Monitoring and Inspections Noise Complaint Response Operations staff will routinely observe and monitor facility In the event of a noise complaint,Jacobs will respond noise conditions during normal operations, maintenance promptly by reviewing facility operations at the time of the activities,and residuals handling events. Operators will reported event and,where appropriate, dispatching staff to conduct regular inspections of major noise-generating assess conditions.Jacobs will document the nature of the equipment and operational areas to verify that equipment complaint,the time and duration of the reported noise,and is functioning properly and that no abnormal or excessive any operational activities occurring at the facility during that noise conditions are present. Operations staff are period.Where warranted,Jacobs will elevate the issue to authorized to initiate immediate operational adjustments or facility management and coordinate with the City regarding maintenance follow-up when abnormal or excessive noise findings, response actions,and any required follow-up. conditions are identified. An immediate review of operating conditions will be During activities with higher noise potential,such as conducted to identify potential noise sources or contributing equipment testing, maintenance work, or truck loading and factors. Corrective actions will be implemented as necessary unloading, operators will remain attentive to noise levels to mitigate noise. Noise complaints, investigations, and and operational practices. Observations will be documented response actions will be documented and included in routine as part of routine operational logs, including the nature of operational reporting as required by the DBOM Agreement. the activity,time of day, and any unusual noise conditions Corrective actions will focus on both immediate mitigation identified. Noise-related observations and findings will be and long-term prevention of similar noise conditions. maintained as part of the facility's operational records and made available to the City upon request in accordance Performance Tracking and with the DBOM Agreement. Continuous Improvement Operational Controls and Preventive Measures Jacobs will periodically review noise-related observations, complaint records,and operational trends to evaluate Jacobs will manage operational practices to minimize noise the effectiveness of noise control practices.Where generation, particularly during early morning, evening, or monitoring results or complaint patterns indicate the other noise-sensitive periods. Preventive measures will need for improvement,Jacobs will implement appropriate include maintaining equipment in good working order, operational adjustments and management practices to promptly addressing mechanical issues that may increase maintain compliance with applicable noise standards and noise levels,and sequencing operational activities to limit minimize community impacts. Lessons learned from noise- cumulative noise impacts where practicable. Particular related reviews will be incorporated into operating practices, emphasis will be placed on operational practices that maintenance planning, and staff training as appropriate. reduce noise impacts during periods most sensitive to the surrounding community. Jacobs acknowledges the City's right to monitor facility noise levels and will cooperate fully with any monitoring Residuals handling and hauling activities will be managed or inspection activities conducted by the City or its to minimize unnecessary noise, including controlling representatives.Through consistent oversight, disciplined idling, loading practices, and truck movements on site. operational practices, and responsive corrective actions, Housekeeping practices will also be emphasized to reduce Jacobs will maintain an effective noise control program that noise associated with loose materials, equipment vibration, supports compliance, protects the surrounding community, or unsecured components. and aligns with the City's expectations for long-term facility operations. 1 13 1 3.4 Operations and Maintenance 3.4.7 REGULATORY COMPLIANCE: TESTING & LABORATORY PROTOCOL Environmental Compliance p Jacobs' Environmental Compliance Program for the Lake 99.98% Oswego WWTF is built on a disciplined, repeatable framework that integrates ethics,standardized processes, laboratory Jacobs' environmental excellence, auditing, and transparent reporting to deliver compliance record is 710 predictable regulatory compliance. unmatched in the industry Jacobs'objective for the City will be to achieve predictable, 157_00923M uninterrupted regulatory compliance at the WWTF while protecting public health,the environment, and the City's assets.Jacobs will tailor and fully implement an Environmental Compliance Program specific to Lake Oswego, its NPDES permit, industrial contributors, biosolids operations,and all applicable federal, state,and local regulatory requirements. Jacobs will operate with integrity and transparency and will be fully accountable for the accuracy, completeness,and timeliness of all compliance activities and reporting.Through disciplined execution, proactive oversight,and open communication, Jacobs will support the City's objective of operating the WWTF in full compliance with all environmental statutes, regulations, permits,and reporting obligations. Jacobs' Environmental Compliance Program is a proven framework designed to: 4 Generate consistent compliance with all applicable environmental laws, regulations, permits, and public health standards 4 Provide early identification of conditions or trends requiring attention, including escalation to Jacobs' regional or corporate technical specialists when appropriate 4 Produce accurate,traceable, and legally defensible compliance data and records This program will provide the City with confidence that regulatory risks are actively managed and that compliance decisions are supported by reliable, defensible information. druinfili,` 0_ r I, a S 'r, - ,;•''';%...';h• y Iw1f' •• ir. t 6 iii- • ,y�X' 4.„ . ;,-,--,,t.. • .s �f : _,4".....10. ..- .; r . wt « tiYf •.rt s dY rcr ..„.,,,,,, ,,...• ..,� v-„, ;err : 4. ... 1 r i .. J _� _ • +, _-,,,; �w fr " •. ..',,.;,-%-: i � / r . _ • a: 7 14 3.4 Operations and Maintenance Regulatory Expertise and Support Jacobs'environmental compliance professionals bring decades of experience supporting municipal wastewater utilities nationwide.This team has deep expertise in the Clean Water Act, NPDES permitting,the Emergency Planning and Community Right-to-Know Act(EPCRA), biosolids management, laboratory compliance,and stormwater regulations. Jacobs maintains established working relationships with regulators at the federal, state, and local levels, including the Oregon Department of Environmental Quality(DEQ).These relationships will support clear communication,timely issue resolution, and effective advocacy on behalf of the City.This depth of expertise will be provided as part of Jacobs' base O&M services. OUR SIX-POINT COMPLIANCE PROGRAM 99.98%Compliance Is the Result of a Disciplined System,Not a Statistic rA •Oregon DEQ and EPA compliant sampling+ Jacobs'Six-Point Compliance Program - proven QA/QC protocols integrates ethics,standardized •Cross-functional teams for lab,reuse, stormwater,biosolids processes,laboratory excellence, data integrity,auditing,and SOPS AND PROCESS CONTROL EXPERTISE transparent reporting to deliver defensible permit Consistency and precision at every operations stage. 41) •Immediate compliance and e-Reporting support the City's 491 submission and permit zero excursion goal. COMPLIANCE TRANSPARENCY violation alerts TRAINING&TOOLS AND REPORTING •Real-time data feeds on the City's Empowering our people to Insight into your system, web based dashboard ■30,000 hours oftraining protect the environment. visibility you can provided in the last 99.98% count on. 3 years alone •Standardized tools, COMPLIANCE tracking systems,and Maintained through rigorous evaluation matrices process control,defensible 414 data,and daily vigilance from certified experts. ■Internal baseline and ongoing audits drive improvement CULTURE OF AUDITS AND PROJECT ETHICS MONITORING We do the right thing— I, Constant improvement •Transparency in even when no one i et through independent all regulatory is watching. sow, validation. communications •Reporting culture ,59.009235 OVERSIGHT AND guided by honesty SUPPORT BY and defensibility GLOBAL EXPERTS ■20+dedicated O&M Compliance Compliance strength &Reporting SMEs driven by ongoing oversight andsupporr. •Support for permit interpretation, training,rapid response,and future preparedness v 115 3.4 Operations and Maintenance Compliance Execution: Tracking, Incident Response, Reporting, and Dashboards Mitigation, and Accountability Jacobs will maintain a transparent,auditable compliance While Jacobs' objective is uninterrupted compliance,we system that consolidates operational, laboratory, and recognize that rare instances of permit excursions may maintenance data into a single defensible record for the occur due to factors such as extreme weather, industrial City. Hach WIMS, or equivalent software package,will discharges, or equipment failure. be used as the primary compliance data management platform and will be integrated with Lake Oswego's We'll respond to any non-compliance event at the WWTF SCADA and CMMS systems. with transparency, urgency, and professionalism. Our response will include: Compliance data will be validated daily,trended monthly, and summarized quarterly for joint review with the City. • Immediate assessment of the situation Interactive dashboards will visualize permit performance, • Deployment of necessary resources to return the approaching limits,and parameter trends while linking facility to compliance results to process conditions, maintenance activities, • Identification and implementation of corrective and events.Automated alerts will be configured to flag and preventive actions approaching permit limits, missed samples, or abnormal • Mitigation of environmental impacts through prompt trends to allow early operational intervention. cleanup and restoration • Accurate and timely notification and reporting to the All regulatory reports including DMRs, Monthly Operating Oregon DEQ,the City, and other stakeholders, as required Reports, biosolids and residuals reports, industrial Our team can draw on regional and corporate technical pretreatment summaries, and air permit documentation resources as needed to support onsite staff in resolving will be prepared in the City's established formats and complex processes or compliance challenges.We will submitted 100%on time and in full compliance with maintain critical equipment lists,vendor contacts,and Oregon DEQ's requirements. response resources to allow for rapid access to additional Calibration records, chain-of-custody documentation,and support when required. supporting compliance materials will be maintained in a Jacobs will address regulatory fines or penalties in secure, SharePoint-based electronic document management accordance with the allocation of responsibility set forth system accessible to authorized City and Jacobs personnel. in the DBOM Agreement. All compliance records,supporting documentation,and regulatory correspondence will be maintained in accordance Excursion Management with Appendix 18—Reports and Records, including audit- and Root Cause Analysis ready retention and availability requirements. Jacobs will use its Preliminary Excursion Guide,an internal Managing Regulatory Changes compliance tool applied on Jacobs-operated O&M projects, g g g y g to support the identification, documentation, investigation, Our team will actively monitor proposed and emerging and resolution of any actual or suspected instance of regulatory changes that could affect the WWTF.When regulatory non-compliance at the WWTF. new or revised regulations are proposed,Jacobs will evaluate potential impacts on treatment processes, We will document each event and subject it to a formal root monitoring requirements,staffing, capital investments, cause analysis.To fully understand contributing factors and and operating costs. to implement corrective actions that prevent recurrence,we will conduct a structured review involving environmental We can provide the City with early guidance on anticipated compliance specialists,technical experts,and management. changes, including concise summaries of regulatory Findings and corrective actions will be documented,tracked, requirements, operational implications,and potential capital and verified to completion. needs.Where appropriate,Jacobs will support the City in discussions with regulators to confirm that requirements are Laboratory Management and clearly understood and implementation expectations are Compliance Reporting reasonable and technically sound.This proactive approach will allow the City to plan and budget effectively well in Because permit compliance begins in the laboratory,Jacobs advance of regulatory deadlines. will implement a comprehensive laboratory management program to support the City.Jacobs will perform all sampling, analysis, and reporting necessary to comply with Oregon DEQ and federal requirements, either through onsite laboratory services or qualified third-party laboratories when appropriate and cost-effective. v I16I 3.4 Operations and Maintenance Testing & Laboratory Protocol Jacobs will implement and maintain a comprehensive LABORATORY COMPLIANCE TOOLS testing and laboratory program to support regulatory FOR "PERFECT COMPLIANCE AND compliance, process control, performance verification, PERFECT REPORTING" and accurate reporting. Laboratory procedures will be — conducted in accordance with all applicable federal, state, "`� ��1 • and permit requirements and will align with the Project's performance guarantees and Operations and Maintenance Plan. Laboratory data will directly support compliance /mss determinations under the applicable NPDES permits and verification of the Project's Effluent Performance Guarantees established in the DBOM Agreement, including documentation used to demonstrate compliance and avoid performance guarantee liquidated damages. • Comprehensive Training Program:At project startup and throughout operations,we will provide both Laborator Standards and Analytical Methods on- site and online training sessions to ensure that all staff y y are fully versed in regulatory compliance,operational operational All sampling and analytical activities will be performed protocols,and data integrity best practices. using the most current versions of USEPA-approved • Permit Evaluation Tool:This tool provides an in-depth review of permit requirements,helping methods, 40 CFR Part 136,the EPA Method Update Rule the O&M Supervisor and staff to identify and fully (MUR), and Standard Methods for the Examination of Water understand compliance obligations. and Wastewater.Jacobs' Compliance&Reporting (C&R) • Comprehensive Sampling and Monitoring Plan: Team will establish site-specific laboratory procedures Our plan combines all required monitoring and standard operating procedures(SOPs)and will train details into a single,accessible document that laboratory and operations staff on proper sampling includes monitoring locations,deadlines,specific protocols for different sample types(stormwater, techniques,analytical methods, quality control requirements, biosolids,residuals),and is reviewed annually to capture and safety practices. any updates. • Sample Tracking Tool:To maintain timely and accurate Laboratory analyses will be performed using a combination sampling,this tool provides a record of all sampling of in-house process testing and certified commercial events with built-in oversight layers,ensuring compliance laboratory services,as appropriate,to meet permit with both state and federal regulations. requirements, holding times,and analytical complexity. • Project SharePoint Site:All compliance tools,SOPs, Jacobs will confirm that all permit-required analyses and reference documents are accessible to staff through are conducted using approved methods and within a dedicated SharePoint site,ensuring easy access to required detection limits. essential information and supporting transparency. 141 0l1BWE,1 2 Sampling, Chain of Custody, and Sample Handling Jacobs will implement strict sampling and chain-of-custody protocols for all in-house and externally analyzed samples. Chain-of-custody records will document sample collection, preservation, handling,transport, and analysis to ensure traceability and data integrity.Samples will be preserved,stored,and transported in accordance with permit requirements, approved methods, and laboratory SOPs. An in-plant laboratory and operations logbook will be used to track samples from collection through final analysis and reporting.Samples requiring off-site analysis will be transported by courier or approved delivery methods to ensure compliance with holding time and preservation requirements. Quality Assurance and Quality Control A robust Quality Assurance (QA)and Quality Control(QC) program will be implemented to ensure the accuracy, precision, and defensibility of all laboratory data. QC procedures will include, as applicable, method blanks, laboratory control samples, duplicates, matrix spikes, matrix spike duplicates, reference standards, and split samples.All QC results will be evaluated against established acceptance criteria prior to data reporting. Jacobs will utilize standardized QC tracking and statistical tools to monitor analytical performance, identify trends, and detect potential issues. If QC results fall outside established control limits,analyses will be halted,the cause investigated, and corrective actions implemented prior to resuming testing.Samples will be reanalyzed as necessary to ensure valid and defensible results. v X 17 1 3.4 Operations and Maintenance Instrumentation, Audits, Reporting, and Calibration, and Maintenance Continuous Improvement Laboratory equipment, online analyzers, and plant Jacobs' C&R Team will perform regular internal audits of instrumentation will be calibrated and maintained in laboratory procedures, data quality, and reporting practices. accordance with manufacturer recommendations, Blind performance evaluation studies, including Discharge regulatory requirements, and Jacobs' internal standards. Monitoring Report(DMR) QA studies,will be conducted Calibration activities will be documented in calibration periodically to verify laboratory proficiency and compliance. logbooks and electronic records.When calibration results indicate performance outside acceptable limits, corrective Jacobs' Compliance&Reporting (C&R)Team will maintenance will be performed promptly. coordinate directly with City staff and regulatory agencies, as appropriate,to support permit reporting, Discharge Preventive maintenance procedures will be established Monitoring Report(DMR)submittals,audit responses, and for laboratory and analytical equipment and integrated regulatory inquiries related to laboratory data. into the computerized maintenance management system (CMMS).Annual third-party calibration and verification of Laboratory performance, QA/QC results, and audit findings select instruments will be performed as required to maintain will be reviewed routinely to identify opportunities for compliance and data integrity. improvement.Corrective and preventive actions will be documented and tracked to resolution.Jacobs will Redundant analytical capability will be maintained coordinate closely with operations staff to ensure laboratory through backup laboratory instruments and access to results are effectively used for process optimization and certified commercial laboratories to ensure uninterrupted compliance assurance. compliance monitoring during equipment outages, peak flow conditions, or emergency events. Laboratory Safety and Chemical Hygiene Laboratory Information Jacobs will implement a site-specific Laboratory and Management and Data Control Chemical Hygiene Plan (LCHP)to protect laboratory personnel and ensure compliance with OSHA and applicable Jacobs will utilize a Laboratory Information Management safety regulations.The LCHP will address chemical handling, System (LIMS)and associated data management tools to storage, labeling, disposal, safety equipment,training,and track laboratory results, quality control data, and permit emergency response procedures. Laboratory safety training monitoring requirements. Laboratory data will be reviewed, will be provided to all applicable personnel,and Safety Data verified, and validated prior to reporting.All original raw Sheets(SDS)will be maintained and readily accessible. data, calibration records, bench sheets, electronic files, and final reports will be retained in accordance with regulatory requirements and the recordkeeping, access, and retention provisions of the DBOM Agreement. Laboratory records will be maintained in a controlled document management system to support regulatory inspections, audits,and City review. Data security, backup procedures, and access controls will be implemented to protect the integrity and confidentiality of laboratory information. v 1 18 1 3.4 Operations and Maintenance 3.4.8 STAFFING PLAN AND LICENSE MANAGEMENT O&M Staffing Plan Jacobs understands the City's DBOM delivery model requires an adequately staffed, consistently qualified O&M team that can sustain compliance, reliability, safety,and responsiveness across a 3O-year term.Our staffing plan meets the contract standards and all applicable regulatory requirements, including Oregon DEQ requirements, and reflects our commitment to managing the facilities to a high standard. Exhibit 3.4.8-1 summarizes our proposed staffing for the Lake Oswego Wastewater Treatment Facility(LOWWTF) and explains our reasoning for each position and totals. It also shows a comparison to the Tryon Creek Wastewater Treatment Plant(TCWTP)staffing levels to provide further insight to our staffing levels. Our staffing levels and project organization, shown previous in Exhibit 3.4.2-1 under Section 3.4.2 Organizational Chart and Communication Protocols,were developed based on Jacobs' extensive wastewater treatment O&M experience and building staffing structures that are resilient to absences,turnover,and unusual operating conditions—without sacrificing compliance,asset reliability, or responsiveness. Exhibit 3.4.8-2 provides additional data on other comparable facilities in the region to further demonstrate the basis for our proposed staffing levels. EXHIBIT 3.4.8-1.Summary of Jacobs Proposed Staffing Approach with Comparison to TCWTP Staff LAKE OSWEGO COMPARISON ROLE WWTF COMMENT TO TCWTP* Based on Jacobs'experience at similar facilities,the size and criticality of the LOWWTF warranted a full-time O&M Supervisor to O&M SUPERVISOR 1.0 0.3 oversee operations.The TCWTP has a Manager overseeing TCWTP, City of Portland Ops Support&Special Ops. SUPERVISOR/OPS SUPERVISOR 1.0 1.0 SHIFT OPERATORS 4.0 Proposed level of staffing reflects Jacobs'experience at similar 4.0 facilities.TCWTP operations staffing is similar. RELIEF/FLOATING OPERATOR 1.0 1.0 Maintenance will be a critical element to preserving the value of MAINTENANCE SUPERVISOR 1 O the City's significant investment in the LOWWTF and warrants a 0.0 full-time onsite maintenance staff to address both preventive and immediate maintenance needs. We will have one full-time onsite staff and they will be supported MILLWRIGHTS/MAINTENANCE TECH 1.0 as needed by Jacobs'regional support team.This was a similar 2.0 past approach at TCWTP. This position will be provided as needed by other Jacobs &C/ELECTRICAL SUPPORT As-needed projects in the region,which is a similar approach at TCWTP.We As-needed anticipate 0.5 FTE for LOWWTF. Laboratory analysis is sent to other City of Portland facilities at LABORATORY ANALYST 1.0 TCWTP.We've included this position due to its critical nature for ** regulatory compliance. This position will be provided as needed by other Jacobs ADMIN SUPPORT As-needed projects in the region,which is a similar approach at TCWTP.We ** anticipate 0.3 FTE for LOWWTF. This position will be provided as needed by other Jacobs projects ENGINEERING SUPPORT As-needed in the region,which is a similar approach at TCWTP.We anticipate ** 0.2 FTE for LOWWTF. AUTO EQUIPMENT OPERATOR 0.0 This effort is assumed to be contracted out,but may be insourced 1.0 over the course of the contract term. TOTAL PROPOSED ONSITE STAFF 10.0 TCWTP includes Relief Operator&Apportioned Manager I 9.3 *TCWTP staffing numbers are based on feedback from Portland BES staff. **These positions are provided as needed by staff from other City of Portland facilities. 7 19 3.4 Operations and Maintenance EXHIBIT3.4.8-2.Staffing Level Benchmarks for Other Similar Facilities in the Region Used to Help Establish Jacobs'Staffing at LOWWTF TOTAL ONSITE FACILITY/REFERENCE PROCESS TYPE FTE AVG FLOW(MGD) FTE/MGD NOTES TYPICAL OREGON Conventional Activated Sludge 5-12 5-15 0.7-1.0 WEF/PNCWA SECONDARY WWTP benchmarks ADVANCED SECONDARY+ Secondary+Filtration+UV 6-15 5-15 1.0-1.4 Higher automation, UV(OREGON) lab,compliance HILLSBORO BNR,UV,Biosolids z25 z20 21 25 Based on ROCK CREEK WRF publicly reported staffing EUGENE RRF Advanced Secondary,UV z14 z12 21.15 Comparable regulatory environment SALEM RIVERBEND BNR,Filtration,UV z30 z22 21.35 Complex process, wet-weather focus WILSONVILLE WWTF Contact Stabilization,Filtration,UV, 2:8 z4.0 z2.0 Complex process, Digestion,Dewatering,Drying biosolids reuse 6.5 Larger and (Projected Avg Life Flow) X1.53 more equipment Lake Oswego WWTF Advanced Secondary+Filters+UV 10 for average design flow 14.7 -0.68 Below Oregon benchmark (Design Flow-Max Month) range for design flow We will document our proposed staffing plan in the final O&M Plan submittal, including an organization chart, defined roles/ responsibilities, and communications protocols consistent with requirements in Appendix 1O of the sample agreement. Shift Schedule We will formalize shift schedules collaboratively with the City to align coverage with process demands, regulatory requirements, and the City's expectations for responsiveness.While the final schedule will be confirmed through that joint planning process,Jacobs anticipates generally staffing the facilities 8 hours per day, seven days per week,with designated on- call personnel available after hours to respond to alarms, upsets, and call-outs to maintain effective 24-hour coverage, 7 days per week. Exhibit 3.4.8-3 illustrates our proposed shift staffing and certification coverage. EXHIBIT 3.4.8-3.Summary of Jacobs Proposed Shift Schedule to Be Finalized in Collaboration with the City CERTIFIED DEQ SUPERVISOR/ OPERATOR SHIFT SUPERVISOR SHIFT/PERIOD ONSITE STAFFING COVERAGE ROLES PRIMARY FOCUS COMPLIANCE NOTES SUNDAY-THURSDAY O&M Tech III(4) Grade III onsite, I Designated Process ops, Exceeds minimum AND no qualified staff DEQ Supervisor maintenance, DEQ supervision TUESDAY-SATURDAY after 4:30 PM (Grade IV) sampling,reporting requirements 7:00 AM-3:30 PM MONDAY-FRIDAY Ops Manager-IV Grade III onsite, Shift Supervisor Operations, Compliant via Ops Sup.-IV no qualified staff (Grade IV overlap) monitoring, Grade III+ 8:00 AM-4:30 PM Main Sup. after 4:30 PM adjustments available Grade IV Main Tech(1) Lab Analyst WEEKDAY-REMOTE No routine Remote Grade III/IV Designated SCADA monitoring, Allowed— onsite staff available Supervisor alarms supervisor after 4:30 PM on-call not required onsite FRIDAY-MONDAY O&M Tech II(1) Grade III onsite, Supervisor Permit sampling, Meets no qualified staff available inspections OAR 340-049 6:30AM-5:00 PM after 4:30 PM remotely requirements WET WEATHER/UPSET OT call-in Grade III or IV onsite Supervisor on site Hydraulic/process Staffing to be as required or remote response escalated per conditions 1 v 20 3.4 Operations and Maintenance License Management - Jacobs provides broad career development options that improve retention and build bench strength Jacobs will implement a structured License Management through cross-training and succession planning. Program to ensure(1)the project is continuously staffed with appropriately licensed/certified personnel, O&M Staff Training Program and (2) individual operators and maintenance staff have clear pathways to obtain, maintain, and upgrade Jacobs recognizes a strong training program is essential licenses and certifications. to long-term performance, compliance, and staff retention—especially for a new facility transitioning from commissioning into steady-state operations.We Contractual and Compliance Drivers will submit a final personnel training program at the Jacobs acknowledges that the DBOM Agreement requires Substantial Completion stage as part of the final O&M Plan that all O&M personnel be qualified and meet state licensing to document key programs and systems(including staffing and certification requirements and includes administrative and license management)that depend on trained staff for consequences for"failure to maintain proper certification compliant execution. as required by any Governmental Body," reinforcing the importance of proactive,auditable license control. Jacobs' Training Approach for Lake Oswego We offer staff comprehensive training programs that How Jacobs will Manage combine technical instruction, regulatory awareness, and Licensing and Certifications professional development. From onboarding to advanced Jacobs will implement a structured, auditable License skill-building, our approach includes classroom sessions, Management Program grounded in our wastewater O&M field exercises, e learning,and simulation based training— expertise and industry best practices to ensure continuous ensuring our team will be equipped to manage both routine compliance and dependable coverage. Our approach operations and unexpected events. emphasizes proactive planning, clear accountability,and Our training plan will be role-based, competency-driven, consistent documentation so the City can be confident and aligned to the contract standards,with a strong focus the project is always supported by properly licensed and on safety, compliance, and operational discipline. Drawing qualified personnel. Our approach will: from proven programs at Jacobs'similar wastewater facility • Rigorous screening and credentialing will ensure all projects,Jacobs will implement: personnel assigned to the project hold and maintain • Individual Training Assessments to tailor learning plans appropriate Oregon certifications applicable to to each employee's experience and role, closing gaps their role. For all new staff,we will conduct detailed efficiently and supporting advancement. credential verification and ensure full compliance with • Structured learning paths covering safety, ethics, required staffing specifications. operations, quality, certification,and compliance, delivered • Establish a project license matrix by role, shift coverage, through a blend of classroom, on-the-job training,and and contingency needs(e.g.,vacation/sick coverage), e-learning. Exhibit 3.4.8-4 summarizes our typical mapped to Oregon certification requirements and any job training topics,which will be tailored to individualized function certifications required by manufacturers,safety and site-specific training needs.Our many local, regional, programs, or regulatory programs. and technical support resources and SMEs enable us • Track licenses,renewals,and continuing education in a to address all project training needs onsite—providing centralized system with automated reminders, supervisor knowledge transfer necessary to develop their skills and review,and documented compliance checks. elevate performance for the Lake Oswego facilities. • Plan staffing and coverage to protect compliance • Early compliance"crash course"and ongoing refreshers by ensuring required licensed staff are scheduled for to standardize regulatory data gathering, reporting normal and abnormal conditions(events, outages, or practices, equipment checks, and accountability— emergency response). reinforcing a culture of"do it right every time." • Support operator advancement and retention through • Maintenance skills development and reliability training, structured incentives and support, consistent with including predictive maintenance techniques and CMMS Jacobs'standard approach on other O&M programs: best practices delivered by experienced resources,with — Jacobs covers the cost of training/preparation and encouragement and support for CMRT certification. exam fees and supports career advancement for • Ongoing professional development and cross-training operators-in-training progressing to full certification. to build redundancy across key functions,strengthen — Jacobs promotes maintenance reliability certifications retention, and support succession planning. such as Certified Maintenance Reliability Technician (CMRT) and provides hands-on training in predictive maintenance disciplines(vibration analysis, alignment, oil analysis, CMMS best practices, ultrasound,troubleshooting). v I21I 3.4 Operations and Maintenance EXHIBIT 3.4.8-4.Summary of Typical Staff Training Topics TYPICAL JACOBS O&M TRAINING TOPICS OPERATIONS STAFF » Plant-specific Process Control Testing and Monitoring >> Check Sheets/Operator Duties »Weekly Process Control Meetings » NPDES Permit » Operations Strategy » Monitoring Process KPIs by Observing Data Trends » Solids Handling Operations and Optimization >> UPCP Development » Logbook and Status Exchange >> Optimization Plan(chemical,process,electrical,sludge) » SOP Development » Site-specific Odor Control System Operations and Monitoring » Data Management MAINTENANCE STAFF » CMMS/Completing Work Orders » Motor Current Analysis—Predictive Maintenance >>Vibration Analysis » Inventory Control » Equipment Calibration » Pump Repairs and PM Tasks » Infrared Thermography for Electrical Staff » Reliability Assessment »Arc Flash for Electrical Staff ALL STAFF »General Health and Safety Awareness »Annual NPDES Permit Training » Safe Driving » Spill Response • Fall Protection » Globally Harmonized System(GHS) >> First Aid&CPR » Crane Safety >> OSHA 10-hour » Fire Prevention » Electrical Safety and Lockout/Tagout Prevention »Teamwork » Chemical Safety(Hazard Communication) » Contract Synopsis(KPI) » PPE and Safety Equipment Use »Workplace Violence »Job Safety Analysis(JSA) » Sexual Harassment,Cultural Sensitivity,and Ethics » Confined Space SELECTED STAFF >> Health&Safety Management for Managers » Supervisor and Management Training JACOBS UNIVERSITY • 225 Courses Online on Business Skills,Computer >> Leading People Desktop Training,and IT Topics » Persuasive People Speaking » Leadership/Management, Project Management, » Global Leadership Team Mentor Program and Business Risk Mitigation » Project Management Fundamentals 103 007V2M Training Deliverables and Integration with Project Phases Our training program will be structured to support: • Commissioning/startup and transition into steady operations, ensuring operators and maintenance staff understand equipment, SOPs, alarms/interlocks,and emergency actions. • Long-term sustainment, including refresher training, competency checks, license renewal support,and continuous improvement updates as procedures and equipment evolve. I22 3.4 Operations and Maintenance 3.4.9 EMERGENCY RESPONSE AND DISASTER RECOVERY PLAN Prevention of and Response to Emergencies JACOBS EMERGENCY REPORTING HOTLINE Keeping our employees and community partners safe is our highest priority and an integral part of our culture. Jacobs maintains a 24/7 emergency reporting Jacobs takes the responsibility of emergency preparedness hotline,giving the City,staff and residents seriously, and our team brings the City personal experience immediate access to resources trained to in successfully managing a wide range of emergency respond quickly and effectively to emergencies situations. Emergency response procedures are designed to and significant customer services issues. prioritize protection of public health and safety, minimize environmental impact, and support continued compliance with NPDES permit requirements and DBOM Agreement Elements of Our Emergency Response Plan performance standards to the extent practicable under emergency conditions. Jacobs commits to operating and maintaining the City's facilities and utilities under emergency operating conditions. We have extensive experience in the development and We will review current emergency operations plans and deployment of Emergency Response Plans(ERPs).A well- develop a comprehensive emergency operations plan with practiced and rehearsed emergency contingency plan reliability and communication features that enhance safety, equips our staff to prevent hazardous situations, minimize response,and communications.(Exhibit 3.4.9-1).The ERP disruptions,and restore service quickly and safely while will be fully integrated with Jacobs' Continuity of Operations protecting human life,the water supply,and managed assets. (COO) planning to ensure sustained compliance, staffing The ERP details the response, recovery,and remediation continuity, and uninterrupted facility operations during processes for each type of anticipated emergency. short-term and long-duration emergency conditions. Successful emergency responses begin with awareness Our ERP will include staff training in procedures and and preparation.To the best of our ability,we will assess appropriate use of emergency equipment, as well as critical the magnitude of the event before it occurs. Plant staff will coordination procedures with the City and local agencies. review UPCPs to confirm process equipment availability and Drawing on our extensive experience with severe weather, knowledge of process control parameters.Additional staff such as hurricanes,winter storms,and flooding, our ERP will will be staged as needed based on the expected significance lay out the immediate response to threats with a focus on of the event, drawing from our local staff. During the event, protecting lives and assets. It will address recovery protocols we will continuously monitor systems and processes for so once the danger has passed, no time will be lost.At a operational performance and will deploy once the health minimum, our ERP will include: and safety of the staff has been confirmed. • Maintaining 24-hour emergency response capability We are also prepared to quickly respond to unexpected for equipment failure, process upsets, power loss, and catastrophic loss events with our local dedicated staff, weather-related events regional support staff,and subcontractors. In the event of • Maintaining standby power and contingency any emergency,the most senior Jacobs employee on site will pumping capabilities call our 24-Hour Incident Reporting Hotline and additional • Immediate notification to the City of any event that may personnel will immediately be available to assist.Jacobs impact permit compliance, public safety,facility integrity, will quickly mobilize to respond to emergencies pertaining or performance guarantees, consistent with DBOM to the operation of the WWTF and the components of the Agreement notification requirements system we operate. During any emergency event,Jacobs • Participating in local and regional emergency response will implement a defined incident command structure with coordination as applicable clear authority, roles,and escalation protocols to ensure timely decision-making, coordination with the City,and effective response execution. We will maintain coordination with local fire and emergency response agencies by providing site-specific hazard information, emergency contacts,and facility access details, and by aligning our Emergency Response Plan with applicable local incident command and notification protocols. I23I 3.4 Operations and Maintenance EXHIBIT 3.4.9-1.Key Elements in the ERP EVENT JACOBS'APPROACH CHEMICAL SPILL RESPONSE Individual safety data sheets(SDS)will guide proper clean-up and control measures. ASSET/EQUIPMENT Identification of asset conditions,critical assets,and acquiring spare equipment that may be placed in FAILURE RESPONSE inventory so emergency replacements can be made. FIRE RESPONSE Plant staff will be trained on fire prevention and fire suppression,and local and regional maintenance staff will be available for equipment/facility recovery operations. Properly certified and qualified regional staff will be available to support local personnel in the event of regional flooding.During flood conditions,Jacobs'technical support staff will focus on hydraulic and FLOOD RESPONSE process stabilization strategies consistent with facility design limitations,including solids management, flow balancing,and protection of biological treatment processes.Response actions will prioritize maintaining permit compliance within the operational capabilities of the facility and accelerating recovery once flows subside. PANDEMIC/HEALTH A comprehensive employee health program,including mental/emotional health.Regional staff will be EMERGENCY RESPONSE available to assist with O&M during extreme events,and an emergency staffing plan will help maintain safe operation under reduced staffing if required. Continuous monitoring and evaluation of trends to proactively identify potential upsets.Response will include immediate additional testing to identify atypical contaminants,jar testing,and process optimization,which may be required based on changed water quality conditions.Conduct comprehensive influent water quality PROCESS FAILURE RESPONSE testing to detect possible contamination.Procurement resources will be available to remedy chemical shortages.Jacobs technical resources will be leveraged to identify the issue and assist in the development of the recovery plan.Response actions will prioritize protection of effluent quality and minimizing the potential for reportable noncompliance or performance deductions within the operational capabilities of the facility. POWER FAILURE RESPONSE Generator startup procedures;sustained plant operations until utility power is restored. An emergency contact list with site numbers will be posted at each worksite and will include project EMERGENCY contacts,such as the plant manager;the safety manager;the Public Safety Department;police,fire,and TELEPHONE NUMBERS ambulance for surrounding communities;emergency(911)and non-emergency numbers;area hospitals;and serious incident reporting and crisis management. EMERGENCY If emergency equipment is a rental item or provided as a specialty service by a vendor,agreements for EQUIPMENT INVENTORY 24/7 service will be put in place in advance. An effective COO confirms uninterrupted operations during immediate needs,such as a pandemic, CONTINUITY OF OPERATIONS and plans for longer range needs,such as retirement or promotions.The COO will focus on roles and (COO)PLAN responsibilities,notification requirements,subcontractor guidelines,quarantine guidelines,exposure reporting,and travel requirements,and will identify resources,both internal and external,to respond to staffing augmentation needs. PIPELINE FAILURE/ Train field crews on a comprehensive response plan for the various types of pipeline failure to guide them BLOCKAGES in appropriate response,whether it's bypassing,isolating,or venting/flushing and/or rodding sections. O&M Supervisor will communicate condition to the City and provide updates as appropriate. Local and Regional Resources for Diversified Emergency Response Jacobs' Invaluable In a major emergency, it's wise not to have"all your eggs in one basket."A large Regional Resources for event such as a wildfire or earthquake can result in fierce competition for operators, Emergency Response maintenance personnel, contractors, and materials.We bring the City diversified support, with regional and national resources that we routinely deploy to support At the request of the City of projects across the country. Waterbury,Connecticut,during a water supply emergency in When emergencies exceed local capacity,we deploy specialized crews with experience 2019,Jacobs staff(including in critical pump replacements, pipe repair, generator failure, and SCADA restoration. Regional Director Kevin Dahl), These teams have responded to major emergency events across the country and are mobilized and engaged with trained to act under pressure while adhering to safety and regulatory protocols. the City at no cost to help troubleshoot water supply Having a diversified response capability prevents over-reliance on a single resource restrictions and offer solutions. pool—a vital advantage during widespread regional incidents where labor and 145_009I3M materials are in high demand. 24 3.4 Operations and Maintenance Proven Emergency Preparedness High Flow/Severe Weather Event and Response for the Planning and Staffing Most Challenging Situations Jacobs management and on-call staff monitor the online weather services daily,and any significant forecasted Jacobs is the preeminent emergency response firm and weather events are discussed with project staff well in a FEMA Disaster Response and Recovery contractor.Our advance. Depending on the severity of the event,we regional team has successfully prepared for and managed will implement a high-flow plan built on our extensive a wide range of emergencies and will support our onsite experience with wet weather events in the region. teams with regional O&M and consulting resources to handle any challenge presented.We are extreme weather Pre-planning for weather events focuses on protecting and experts and have received awards and kudos from clients as preserving the integrity of the WWTF during wet weather we've kept their systems in operation.As a certified FEMA flows,which can exceed eight times the average daily dry contractor,we also bring the City deep access to specialized weather flow rate.These activities include: skills, contractors,and materials to handle any challenge. • Building solids in the aeration basins to reduce the probability of washout from the clarifiers Emergency Response Times and High Flow/ • Bringing filters online to enhance robustness of treatment. Severe Weather Event Staffing • Increasing solids hauling ahead of a storm to ensure capacity is available for peak solids loading Emergency Response Management is involved to some extent in every emergency Our emergency hotline and alarm service provide event. On-call staff must discuss emergency calls and automated routing of all calls to our answering service and corrective actions with the management team,verifying the team's on-call and management cell phones based on a all aspects of the call are reviewed and proper corrective priority list.This system will keep calling until a real person actions are completed. During high flow events or confirms the issue and that they are responding. emergency conditions,the team will prioritize protection of effluent quality, prevention of NPDES permit exceedances, Two on-call team members will initiate a response to alarms, and minimization of risk to public health, property, and and an operator will be dispatched upon notification.A the receiving waters. staff member will document calls for the Jacobs team and allow reporting to City staff upon request.The local Minimizing Overtime During police and fire departments will also receive our on-call Emergency or High Flow Events phone list in case a resident calls them with a sewer-related emergency condition. Though overtime is necessary at times for responses to emergencies, it will be closely controlled. Every effort will Should more significant or immediate emergency response be made to accomplish tasks during routine plant hours. measures be needed, Jacobs can mobilize O&M staff and Overtime is only approved by managers,who will review other professionals from our other local operations and all call-ins at the time of the calls and document them in regional resources to address these needs. required reports. If a severe weather event is predicted, management may assign personnel to provide 24/7 Defined response times and escalation protocols are coverage schedules, restructuring straight-time during structured to reduce the risk of permit exceedances, severe wet weather, hurricanes, or heavy snow events. environmental impact, and service disruptions during Our planning includes determining which personnel are emergency conditions. needed for specific emergencies, confirming we address the emergency appropriately while helping prevent unnecessary overtime. I25 3.4 Operations and Maintenance 3.4.10 HAZARD ANALYSIS AND CRITICAL CONTROL POINTS (HACCP) Jacobs will implement and maintain a formal Hazard Analysis and Critical Control Points(HACCP) program as an integral component of our Operations and Maintenance Plan in accordance with Section 3.4.10 of the REP. Our HACCP framework provides a structured, proactive methodology for identifying operational risks, establishing measurable control points, and preventing process failures that could impact effluent compliance,odor performance, residuals management, or overall facility reliability. The purpose of our HACCP program is simple: prevent non-compliance before it occurs. Rather than relying on reactive troubleshooting,Jacobs applies disciplined process control principles that continuously monitor and manage operational risk at the system level. Process Hazard Identification Monitoring, Verification, and Corrective Action At the outset of operations,Jacobs will conduct a structured Continuous monitoring of CCPs will be achieved through a evaluation of all treatment processes,solids handling combination of SCADA data, laboratory results, operator systems,and critical support systems.This evaluation will field observations, and trending analysis. Supervisory staff identify conditions or events that could reasonably result in will routinely review process data to verify that control points effluent exceedances, biological process instability, nutrient remain stable and that corrective actions,when required,are removal failures, odor incidents, residuals management implemented promptly and effectively. non-compliance, or loss of operational reliability. If a control limit deviation occurs, operators will immediately Each identified hazard will be evaluated for likelihood, implement predefined corrective measures designed potential severity, and detectability. By systematically to restore stability. Each deviation and response will be assessing risk across the facility,we establish a clear documented and evaluated to confirm effectiveness.Where understanding of where process control is most critical and appropriate, root cause analysis will be performed to where operational discipline must be most rigorous. strengthen preventive measures and reduce recurrence risk. Verification activities will include periodic review of Critical Control Points and Operational Limits monitoring procedures, calibration of instrumentation, and For each significant risk identified,Jacobs will define evaluation of response effectiveness.This layered approach specific Critical Control Points(CCPs).A CCP represents ensures that the HACCP program remains active, relevant, an operational parameter that must remain within defined and performance-driven rather than static documentation. limits to ensure continued regulatory compliance and performance guarantee adherence. Integration with Performance Guarantees These control points will be established using process The HACCP program directly supports the operational engineering principles, historical operating data, permit obligations and performance guarantees outlined in the requirements, and manufacturer performance guidance. DBOM Agreement. By maintaining disciplined control of Operational limits will be defined conservatively to critical process parameters, Jacobs reduces the likelihood provide early warning indicators well before regulatory of effluent non-compliance,sustained odor conditions, or thresholds are approached.This margin of control allows residuals handling deficiencies. operators to stabilize processes before performance guarantees are at risk. This structured linkage between process control and contractual performance requirements ensures that daily Control limits will be clearly documented and incorporated operations remain aligned with long-term regulatory into standard operating procedures. Operators will and performance commitments. HACCP serves as the understand not only the target operating range, but also operational backbone that protects water quality, public the response actions required if a parameter begins to trend health, and the City's regulatory standing. toward an unacceptable condition. v I26I 3.4 Operations and Maintenance Continuous Improvement Commitment to The HACCP program will not remain static over the term Proactive Process Management of the Agreement.Jacobs will review and update hazard Jacobs' HACCP program reflects our commitment to assessments at least annually and whenever operational disciplined, data-driven operations. By systematically conditions change, including changes in influent identifying hazards, defining critical control points, characteristics, regulatory requirements, equipment monitoring performance,and implementing timely performance, or process configuration. corrective action,we will maintain stable operations and protect compliance under all operating conditions. Lessons learned from process upsets, near misses, or operational trends will be incorporated into updated This proactive approach ensures that the Lake Oswego hazard analyses and revised control strategies.Through this WWTF is operated with rigor,transparency,and continuous improvement approach,the HACCP framework accountability—delivering reliable performance and long- evolves alongside the facility, maintaining effectiveness term protection of the City's investment. throughout the full O&M term. 4i y s F' / s r aws - F dl� • • _ F. • • 7 v I27I 3.4 Operations and Maintenance 13.4.11 SAFETY PLAN Safety First: A Culture of Accountability and Prevention Jacobs will deliver a comprehensive safety program for the City that is grounded in personal accountability,visible leadership, and proactive hazard prevention. Our BeyondZero®safety philosophy will guide day-to-day decision-making and reinforce a work environment where every employee is empowered—and expected—to identify hazards and act before they result in injury, damage, regulatory noncompliance, or disruption of service. Based on Jacobs' understanding of the Lake Oswego WWTF and its advanced biological nutrient removal processes, membrane systems, chemical storage and dosing systems, solids handling, electrical distribution,and pump station operations, we will implement disciplined, risk-based safety practices that support reliable and compliant operations throughout the O&M period.This approach will protect plant staff,subcontractors,visitors, and the surrounding community while safeguarding City assets and the environment. Our objective is clear and uncompromising:zero injuries,zero incidents,and zero harm. Jacobs' industry-leading safety performance is supported by proven systems, comprehensive training, and transparent reporting. Jacobs will implement a structured, enterprise-level safety management system to document inspections, incident reporting, corrective actions, and trend analysis.Safety data will be tracked electronically and reviewed routinely by site and regional leadership to identify emerging risks and drive continuous improvement.Training records, certifications, and compliance documentation will be maintained in a centralized learning management system and made available to the City upon request throughout the term. Jacobs will apply structured hazard identification and risk analysis to all WWTF activities, including treatment operations, laboratory work,solids handling, chemical management, maintenance, electrical systems,and confined space entry. Findings will be directly integrated into standard operating procedures, preventive maintenance planning, and daily work execution. Jacobs outperforms industry averages in these top safety categories Recordable Incident Rate(RIR) DART or Lost Time Injury Rate(LTIR) 5-Year Average* 5-Year Average* 0.62 Jacobs is 60% BETTER 0.20 Jacobs is than Industry Average 72% BETTER V V than Industry Average BOA 9 FIN Industry Jacobs Industry Jacobs Average Average *2018-2022 data from BLS OMFS_SAF_lOO Industry` Safety Management System and Required Plans Jacobs' Safety Management System will comply with Oregon OSHA,applicable federal OSHA regulations, and all DBOM Agreement requirements.Within 30 days of Notice to Proceed,we will submit a site-specific Safety Plan for City review and approval that will include,at a minimum: • confined space entry • housekeeping standards • lockout/tagout procedures • daily pre-task planning/AHAs/safe work permitting • arc-flash hazard analysis • contractor safety coordination, expectations,and oversight • chemical handling and storage • emergency response • fall protection • spill prevention and site security protocols • gas detection (fixed/portable), calibration, documentation The Safety Plan will designate an appropriately certified safety professional with a minimum of five years of construction safety experience to develop and sign the Project Site-specific Health and Safety Plan. v 1 28 1 3.4 Operations and Maintenance Leadership, Roles, and Integration Safety leadership will be embedded in Jacobs' onsite management TYPICAL SAFETY TRAINING structure throughout the O&M period.The O&M Supervisor will hold overall accountability for safety performance and will serve as MAINTENANCE STAFF the primary point of contact with the City.A designated Safety Lead •NFPA 70E will implement the Safety Plan, conduct inspections, coordinate •Training on Overhead Cranes, Forklifts, training, manage documentation, and lead incident investigations. and Aerial Lifts Supervisors will conduct daily safety briefings, ensure proper permitting and hazard controls are in place prior to work activities,and verify compliance with established procedures. Safety •General Health and Safety Awareness responsibilities will be clearly defined for all staff, reinforcing that •Fall Protection safety is a core operational requirement—not a parallel program. •First Aid&CPR Jacobs and the City will jointly review safety performance, • JElectrical Safety and Lockout/Tagout incidents, and corrective actions during regular operations and •Chemical Safety(Hazard Communication) performance meetings to reinforce transparency,accountability, •PPE and Safety Equipment Use and continuous improvement. •Job Safety Analysis Training and Workforce Engagement •Confined R Space •Spill Response Employees assigned to the Lake Oswego WWTF will complete •Fire Prevention required regulatory and site-specific safety training prior to •Workplace Violence performing work.Training will address confined space entry, •Sexual Harassment,Cultural Sensitivity,and Ethics lockout/tagout,fall protection, respiratory protection, hazard communication, emergency response, electrical safety, and first SELECTED STAFF aid/CPR.Job-specific and facility-specific modules will supplement • core requirements, and refresher training will be completed Health&Safety Management for Managers annually and tracked electronically. Jacobs will reinforce safety awareness through daily shift start-up discussions, routine safety observations, and HOW DO WE DO IT? leadership safety walks.All personnel will have stop-work authority and will be TRAINING AND ESTABLISHED CULTURE expected to exercise it whenever unsafe SKILL DEVELOPMENT OF ACCOUNTABILITY conditions are observed. We empower our teams with the knowledge Staff are empowered to speak up if they see and tools to navigate potential hazards, unsafe practices,allowing everyone to feel How We creating a workforce that is proficient and comfortable raising concerns without fear safety conscious at every step. of repercussion. Deliver a Safe Operation ROBUST SAFETY PROTOCOLS INSPIRING SAFETY Jacobs' safety culture is sustained We perform regular safety audits,hazard COMMUNICATION through engaged leadership,disciplined assessments,and real-time monitoring to Staff volunteer to share simple daily procedures, and shared accountability identify and address potential risks. messages focused on our culture of caring, across the organization. distributed to all O&M staff,often reflecting ENGAGED LEADERSHIP on deeply personal events. Our approach empowers teams with Our projects are supported by regional and the knowledge and tools to recognize national safety leaders.Each leader actively STAFF RECOGNITION and mitigate hazards before they engages with their teams to reinforce safety AND REWARD escalate.We perform regular safety messages,provide on-the-job and industry Behind every incident-free year is a team audits and risk assessments. Regional training,listen as concerns arise,and of dedicated professionals who prioritize and national safety leaders actively motivate teams to work safely. safety in their daily operations.Our people support the site team, reinforcing are the heartbeat of our success.We expectations and providing ongoing regularly seek out industry safety awards training. Staff are encouraged to raise and host project parties to foster a sense of concerns without fear of repercussion, accomplishment and reinforce our desired and incident-free performance is safe behaviors. recognized and reinforced. 136_00923M 7 v 1 29 3.4 Operations and Maintenance Incident Reporting, Auditing, and Continuous Improvement Jacobs will comply fully with City notification and reporting requirements for all incidents, near misses, and hazardous conditions. City representatives will be notified immediately of serious incidents.Written summaries will follow, including root cause analysis and clearly defined corrective actions.All findings will be documented and reviewed jointly with the City as part of routine operational meetings. Supervisors will conduct routine field inspections,and management will review safety performance metrics monthly to evaluate trends and corrective action effectiveness.A comprehensive annual safety audit of the facility will be performed,with findings documented, prioritized, and tracked to verified closure. 13.4.12 SECURITY PLAN Jacobs will protect the Lake Oswego Wastewater Treatment Facility, its personnel, its infrastructure,and its information systems through a comprehensive, site-specific Security Plan integrated into our daily operations.Security, like safety, is not a standalone document—it is an operational discipline embedded in our culture, reinforced through training, leadership accountability,and continuous oversight. Our Security Plan will comply with Section 3.4.12 of the RFP and all applicable DBOM Agreement requirements and Appendices.More importantly, it will reflect Jacobs'commitment to protecting public health, maintaining regulatory compliance,and safeguarding City assets throughout the full term of the Agreement. Leadership Accountability and Culture Security performance begins with leadership.The O&M Supervisor will have direct responsibility for implementation and annual review of the Security Plan, ensuring it remains current with evolving risks, regulatory expectations,and City standards. Security performance will be tracked, documented,and discussed with the same rigor as safety and environmental compliance. Every employee and subcontractor will understand that protection of the facility and its systems is a core responsibility.We will cultivate a culture in which situational awareness,vigilance, and prompt reporting of concerns are expected behaviors. This"culture of safety and security" ensures that risks are identified early and addressed decisively. Physical Security Jacobs will maintain a secure operating environment through disciplined access control and layered physical security measures.All facility gates,access points, buildings, and critical process areas will remain secured when not actively attended. Access will be restricted to authorized personnel with verified credentials, and visitor management procedures will require sign-in, identification,and appropriate escort. During transition and commissioning,we will evaluate physical security features to confirm functionality and identify opportunities for enhancement. We will coordinate, as appropriate,with the City and local law enforcement agencies to support incident response, emergency preparedness,and threat awareness. Our approach emphasizes deterrence, detection, and rapid response to protect both the facility and the surrounding community. SCADA and Cybersecurity Protection of process control systems is essential to reliable wastewater operations.Jacobs will implement cybersecurity practices that safeguard SCADA, operational technology(OT),and supporting information systems in alignment with City standards and DBOM Agreement requirements, including applicable cyber liability provisions. System access will be governed by role-based permissions, secure authentication protocols, and controlled administrative privileges. Network segmentation between business systems and process control networks will be maintained to reduce exposure risk. Updates and security patches will be applied in coordination with the City to ensure both system integrity and operational stability. Cybersecurity awareness will be reinforced through employee training to reduce human-factor vulnerabilities.Any suspected cyber incident will be immediately reported, investigated, documented, and resolved in accordance with established emergency response procedures. 130 3.4 Operations and Maintenance Incident Reporting and Emergency Integration Security procedures will be fully integrated with the Emergency Response and Disaster Recovery Plan required under Section 3.4.9.Clear protocols will address facility lockdown, evacuation,threat response, and business continuity to ensure protection of personnel and uninterrupted compliance with permit requirements. All security incidents including unauthorized access,vandalism,theft, cyber events, or credible threats will be reported immediately to facility leadership and the City. Each event will be investigated to determine root cause, corrective actions will be implemented,and records will be maintained in compliance with the Agreement's reporting and documentation requirements. Training and Continuous Improvement Security awareness training will be incorporated into employee onboarding and reinforced through periodic refresher sessions. Staff will be trained in access control procedures, suspicious activity recognition, cybersecurity best practices, and emergency protocols.Training records will be maintained in accordance with the Agreement. Jacobs will conduct periodic security assessments to evaluate the effectiveness of physical and cyber safeguards. Findings will be documented and addressed through corrective action plans.Through proactive evaluation and disciplined implementation,we will continuously strengthen the facility's security posture. The Lake Oswego WWTF will be a critical piece of public infrastructure serving the community for decades.Jacobs will protect it with the same commitment, discipline, and accountability that define our safety culture—ensuring a secure, resilient,and reliable operation throughout the life of the DBOM Agreement. 31 3.4 Operations and Maintenance 3.4.13 MEETINGS AND CITY ACCESS TO RECORDS AND I ADMINISTRATIVE SPACE Jacobs will partner with the City through a disciplined,transparent governance approach that supports timely decisions, efficient coordination,and full accountability. Our team will establish a clear meeting cadence and communication structure aligned to the City's preferences, ensuring that the right stakeholders are engaged at the right time and that decisions, action items,and commitments are documented and tracked to closure.Jacobs will also respond promptly to City information needs, including written priority requests, consistent with contract requirements. Meetings at least six(6)years after termination, and Jacobs will preserve original hard copy records wherever practical(or Jacobs will participate in and support a structured program true copies where originals are impracticable), consistent of meetings throughout the contract term.This includes an with contract requirements. Upon termination (or earlier initial coordination/kickoff meeting to confirm goals, roles, upon City request), Jacobs will deliver records to the City communication protocols,and near-term priorities,followed in the manner and location specified by the City, consistent by recurring progress meetings to review performance, with the Agreement.Jacobs will coordinate with the City discuss upcoming activities, identify risks, and resolve issues. regarding any record disposition process required by the As a starting point(to be aligned with City preferences), Agreement, including providing notice and honoring the Jacobs anticipates: (1) routine operations and coordination City's election to retain records when applicable. meetings, (2) monthly performance and reporting reviews, and (3) periodic strategic/leadership reviews focused Where applicable, Jacobs will comply with public records on risk, upcoming major maintenance activities, and requirements and will coordinate with the City on handling continuous improvement. requests in a manner consistent with applicable law and contract requirements. We will also support focused workshops and as-needed meetings for key topics, including operational coordination, Administrative Space performance and reporting reviews, and escalation discussions when issues require management attention. Jacobs will coordinate with the City regarding administrative Jacobs will attend City meetings as reasonably requested workspace needs and access during contract performance. with adequate advance notice. For each meeting,Jacobs will We will work within facility access and security protocols to prepare or contribute to agendas, capture key outcomes ensure appropriate access to necessary administrative space, and decisions, and maintain an action-item log with owners consistent with operational data gathering and performance and due dates to ensure follow-through and accountability. reviews.At a minimum,Jacobs will provide reasonable Meeting outputs will include meeting minutes(or notes), access to meeting space for contract-related discussions(as a decision log where applicable,and an updated action/ available),and will coordinate access to basic administrative risk/issue register. needs(e.g.,workspace, connectivity, and printing/scanning support where available)for City representatives performing We discuss our approach to meeting cadence and oversight activities onsite.Site access will be managed in collaboration in Section 3.4.2 Organizational Chart and accordance with facility safety and security requirements Communications Protocols. (e.g., orientation, PPE, badging/visitor procedures,and escort requirements as applicable). City Access to Records When onsite space is limited or not required, Jacobs Jacobs will maintain complete,well-organized records will support virtual collaboration and hybrid working associated with contract performance and will make them arrangements to maintain responsiveness and efficiency available to the City in a timely manner upon request. while still meeting the City's expectations for availability, Our approach emphasizes strong document control, coordination,and oversight. traceability,and audit readiness.Jacobs will maintain records in a form capable of audit and,where applicable, in chronological order, and will make such records available for City inspection during normal business hours upon reasonable notice. Jacobs will support City review, inspection,and audit needs by maintaining project records in an orderly and retrievable manner, providing appropriate access for authorized representatives, and ensuring records can be produced efficiently when needed. Records will be retained for the duration of the Contract Term and for 132 3.4 Operations and Maintenance 3.4.14 COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM (CMMS) PLAN Jacobs will provide and operate a CMMS as the authoritative system of record for asset inventory, maintenance planning and execution, materials/spare parts, purchasing support,and maintenance reporting.The CMMS will ensure reliable, compliant, and cost-effective maintenance delivery; provide complete,auditable work history(including item-by-item repair and replacement history);support repair-versus-replace decision-making;and provide the City with transparent visibility to maintenance performance and asset condition over the Term. CMMS Delivery, Ownership, and Lifecycle Support Jacobs will implement,configure,administer,and maintain the CMMS for the Project for the duration of the Term, including upgrades and vendor support coordination.Jacobs will maintain configuration control so the CMMS remains current as assets are added, modified, or retired, and will ensure continuity of service and data integrity throughout operations. Preventive Preventive Maintenance Schedule Maintenance Plan Maintenance CMMSPerformance Reports Corrective Computerized Maintenance Review Maintenance Plan Maintenance Asset Performance Management Capital Planning Inventory System Activity Inventory Status 123_005NWD Required CMMS capabilities At a minimum,the CMMS will: • Maintain asset-level records and complete item-by-item repair and replacement history. • Schedule, execute, monitor,and control predictive, preventive, and corrective maintenance programs. • Support monitoring of routine operational activities and convert exceptions to work requests where appropriate. • Issue and manage work orders and support purchase order processes aligned with maintenance and inventory needs. • Manage spare parts and materials inventory, including traceability to assets,work orders, and purchasing records. • Produce exception reports, equipment status reports, and repair priority reports to support operational governance and performance monitoring. • Be kept current as Project assets change and support orderly documentation and data transfer at handback. Asset Hierarchy and Alignment with the Project Registry Jacobs will structure assets within the CMMS using a consistent hierarchy(e.g.,facility/area/system/asset/component)and will align asset identifiers and naming conventions with the Project Registry requirements.We will document standards in an Asset Data Dictionary and apply controlled processes to add new assets and retire replaced/removed assets while preserving historical records for lifecycle traceability. v 1 33 1 3.4 Operations and Maintenance Work Management(Work Orders Reporting, Dashboards, and City Transparency and Purchasing Support) Jacobs will use the CMMS to provide the City real-time, Jacobs will operate a defined,auditable workflow within read-only access to CMMS records and dashboards. the CMMS that includes: Standard reporting will include: • Work identification/intake:operator rounds, inspections, • PM compliance and overdue PM exceptions alarms/alerts, and condition-based findings. • Work order backlog, age,and priority • Screening and prioritization: risk-based prioritization • Equipment status(including out-of-service/ with emphasis on safety, regulatory compliance, limited service assets) reliability,and criticality. • Repair priority lists and critical work visibility • Planning: labor and craft assignment, parts/materials, • Inventory exceptions(e.g.,stockouts/critical spares) LOTO and permit requirements, and step-by-step job plan Jacobs will also provide CMMS data replication/exports to linkage where applicable. the City in agreed machine-readable formats at defined • Scheduling:weekly and daily schedules coordinated with intervals and upon request to support governance, operations to minimize disruption and optimize availability. auditability,and handback. • Execution and closeout:as-found/as-left condition, failure/cause information as appropriate, labor and Interfaces and Document Linkage materials capture,and attachment of supporting documentation (e.g., photos,test results, certificates). Where beneficial and feasible, Jacobs will configure • Purchasing support:CMMS-driven requests/PO interfaces to support efficient work identification and support for maintenance materials and replenishment closeout(e.g., alarm/event-driven work requests and based on inventory controls(e.g., min/max and reorder condition-based inputs)and will link asset records and work points), coordinated with the City's purchasing/finance orders to key documents(SOPs, manuals,vendor cut sheets, processes as applicable. test records). Interface scope, directionality,frequency,and test/validation approach will be defined during mobilization Preventive, Predictive, and in coordination with the City. Corrective Maintenance Control Jacobs will develop and maintain a PM library based on Data governance and quality controls original equipment manufacturer(OEM) recommendations, Jacobs will apply role-based access,audit trails, and asset criticality, regulatory requirements, and operating standard data entry requirements to ensure consistent work history. Predictive/condition-based findings will be tracked documentation and reporting integrity.We will perform and will generate work orders based on defined triggers. routine quality checks(e.g., asset data completeness, Corrective maintenance will be managed through prioritized work order closeout quality, PM library integrity, inventory work orders, backlog controls,and repeat-failure review to accuracy) and implement corrective actions to maintain improve reliability and reduce emergency work. CMMS reliability as a management tool. Implementation, training, and transition During construction,Jacobs will establish the CMMS environment; load and validate the asset hierarchy, PM library, and inventory;configure reporting and user roles;and provide role-based training for operations, maintenance, and City users.Jacobs will maintain continuity of CMMS operation and provide complete CMMS data and documentation exports to support handback and transition at the end of the Term. I34 3.4 Operations and Maintenance 3.4.15 OPERATING REPORTS Transparent, Accurate, and Timely Reporting Daily Operating Reports Jacobs will prepare and submit operating reports in Jacobs will maintain structured daily operating logs accordance with the DBOM Agreement and applicable documenting influent and effluent flows, process control permit requirements. Reports will accurately document parameters, chemical usage, equipment status, alarm facility performance, regulatory compliance status, activity, and any operational events affecting performance. maintenance activities, and other required operational data These logs will be reviewed by supervisory staff each shift within the timeframes specified in the Agreement. and used to verify process stability, regulatory compliance, and equipment reliability. Our reporting processes will integrate SCADA data, laboratory results,and maintenance records into structured Daily operating data will be electronically captured to ensure deliverables consistent with contractual and regulatory accuracy,traceability,and audit readiness. Daily operational reporting obligations. data will be continuously available to the City through real-time system access consistent with Section 8.10 Regulatory Compliance Reporting of the DBOM Agreement. Jacobs will prepare and submit all required regulatory This approach ensures continuous oversight rather than reports in accordance with the facility's NPDES permit, retrospective reporting. Oregon ODEQ requirements,and all applicable Contract Standards.This includes preparation and submittal of Monthly, Quarterly, and Annual Reports Discharge Monitoring Reports(DMRs), biosolids reporting, permit communications and reports,and any additional Jacobs will provide monthly and quarterly operations regulatory submittals required under Section 8.11 reports in accordance with Section 8.11 of the of the DBOM Agreement. DBOM Agreement and Appendix 10(Operation and Maintenance Requirements). ALL regulatory reporting will undergo internal quality review prior to submission.Jacobs' compliance specialists will verify Monthly reports will summarize: data accuracy, confirm sampling and analytical results, and • Influent and effluent performance trends ensure timely submission.The City will receive copies of all • Compliance status relative to permit limits regulatory reports concurrent with agency submittal. • Chemical and energy consumption Jacobs will promptly provide the City copies of any • Biosolids production and handling material default notices, regulatory correspondence, or • Maintenance activities and equipment reliability permit-related communications received or transmitted in • Maintenance logs and CMMS documentation consistent connection with O&M Services, consistent with Section 8.11 with Contract Standards of the DBOM Agreement. • Safety performance metrics • Odor control activities and community If a non-compliance event occurs,Jacobs will immediately response (as applicable) notify the City in accordance with Contract Standards and • Performance Guarantee tracking,where applicable provide written documentation describing the event, root Jacobs will furnish the Annual O&M Report within 90 cause, corrective actions, and preventive measures. days after the end of each Contract Year, consistent with Jacobs will also provide any Default Reports required under Section 8.11 of the DBOM Agreement.The Annual Report Section 8.11 of the DBOM Agreement promptly upon will include a comprehensive summary of operational receipt or issuance. performance, compliance history, maintenance and asset condition, energy and chemical optimization initiatives, capital improvement recommendations, and continuous improvement efforts. 1 35 1 3.4 Operations and Maintenance Data Management and Transparency Continuous Improvement Through Reporting Jacobs will maintain all operating, maintenance, laboratory, Operating reports will serve not only as compliance performance, and compliance records in accordance deliverables, but as management tools.Jacobs will use trend with Appendix 18—Reports and Records. Records will analysis and performance metrics to identify opportunities be retained in chronological order, maintained in a for optimization, cost control, reliability improvement, and form capable of audit, and preserved for the duration risk reduction.Through disciplined reporting,structured data of the DBOM Agreement and for at least six years management,and collaborative review with the City,Jacobs following termination. will maintain a high-performing, compliant,and resilient wastewater treatment operation throughout the DBOM term. Operational data will be managed through an integrated digital framework that includes: • SCADA for real-time operational monitoring • Laboratory Information Management Systems (LIMS)for analytical data • Computerized Maintenance Management System (CMMS) for maintenance records and asset histories • Secure electronic document management systems for regulatory and contractual reporting The City will have real-time, continuous read-only electronic access to operating, maintenance,and performance data, with hard-copy reproduction capability, consistent with Section 8.10 of the DBOM Agreement.Jacobs will ensure that all sampling data, maintenance logs, performance metrics,and asset records are accurate, current, and readily accessible for City review, audit, and inspection. Data integrity controls will include supervisory review, calibration verification, system backups,and role-based access controls to ensure data accuracy, cybersecurity protection, and compliance with Contract Standards. v I36I 3.4 Operations and Maintenance 3.4.16 OPERATION AND MAINTENANCE INSPECTIONS I AND QA/QC Jacobs will implement a layered inspection and quality assurance program that verifies the project is operated, maintained, repaired,and replaced in accordance with the DBOM Agreement's Contract Standards including Good Operation and Maintenance Practice.The program combines(1) routine operating and maintenance inspections to help identify and reduce unforeseen issues, (2)formalized internal QA/QC oversight that verifies compliance and drives corrective action,and (3)full transparency and support for City inspections and reviews. Routine O&M Inspections City Inspection Support and The onsite Jacobs team will perform structured inspections Inspection Readiness at frequencies appropriate to asset criticality and Jacobs will cooperate fully with City inspections and manufacturer and regulatory requirements, including: reviews and will support: • Shift/daily operator rounds using defined checklists • Annual Maintenance Inspections(City option with for process performance,alarms, safety and security 15 days' notice), including access to the project observations, housekeeping, and abnormal conditions. and relevant records. • Weekly/monthly maintenance checks to verify • Full-scale inspections and reviews beginning on the third equipment condition, lubrication, alignment/belt/ anniversary of the Acceptance Date and every three years chain condition, abnormal vibration/temperature/ thereafter(City option with 30 days' notice), including noise, electrical and instrument condition,and readiness concurrent review of relevant data, records, and reports. of standby equipment. • Unscheduled inspections at any time, including access • Predictive maintenance condition inspections(e.g., to relevant records,without transferring any maintenance vibration,thermography, oil analysis,and other condition responsibility from Jacobs to the City. indicators as applicable)to identify degradation early and convert"findings" into planned work. To make inspections efficient and transparent,Jacobs • Post-maintenance and return-to-service inspections will maintain an "inspection readiness" package for City to confirm work quality, proper configuration,and review that is defined in advance and mutually agreed by operational readiness. the City and Jacobs as part of the O&M Plan/CMMS to reporting alignment.The package will consist of standard, Inspection Documentation, repeatable data extracts and summaries that provide a prudent"snapshot in time"view of maintenance compliance Follow-Through, and Reporting and asset condition,such as CMMS extracts for PM/PdM Inspection findings will be documented in the CMMS and/ completion, corrective work order status/aging, recurring or approved electronic forms and will result in actionable issues, spare parts/inventory status(as applicable),asset work orders with priority,target completion, and closeout condition summaries,and Major Maintenance/Repair/ evidence.Jacobs will maintain inspection records in a Replacement status.Where additional datasets are manner that supports efficient City oversight and aligns with requested for a particular inspection, Jacobs will coordinate the contract requirement for City access to maintenance with the City to confirm scope,format,and timing and will documentation through the CMMS. Inspection outputs provide supplemental information to the extent available (e.g., open findings, corrective action status,trends,and in the CMMS and project records without disrupting safe, risk-significant conditions)will be summarized through compliant operations. the operating reports and other reporting processes established for the project. Jacobs will develop and maintain a standardized template for this package during mobilization/transition,and will review and confirm the agreed datasets,formats, and Integration with the Major Maintenance, delivery cadence with the City as part of finalizing the O&M Repair, and Replacement Plan Plan and CMMS reporting approach. Inspection results will directly support the required asset inspection protocol and reporting protocol within the Major Maintenance, Repair,and Replacement Plan.Asset condition observations and corrective maintenance history will be used to refine repair/replacement timing, improve planning, and justify schedule adjustments when warranted. 1 37 1 3.4 Operations and Maintenance Remediation Planning and Closeout If the City identifies deficiencies following reports, inspections, or reviews and requests a plan of remediation,Jacobs will promptly develop and submit a remediation plan that demonstrates how the project will be brought back into compliance and will execute the plan upon City acceptance.Jacobs understands that deficiencies identified by the City are limited to:(1) project structures below the minimum structural integrity and functionality ratings(3 or greater)defined in Appendix 15 of the Agreement and (2) items that could directly affect project performance and are vital to successful operation consistent with good operation and maintenance practice as described in the Agreement. In-House Procedures to Provide Accuracy, Integrity, and Quality Control In addition to the routine inspections above and the City's inspection rights, Jacobs will apply its established O&M Quality Assurance and Quality Control(QA/QC)audit process to independently verify compliance and drive continuous improvement across safety, operations, maintenance, documentation, and management systems.This includes developing and implementing a comprehensive QA/QC Plan that supplements the routine O&M inspection program described above. The plan will describe the methods, process, and measurements used to verify quality and compliance with contractual requirements during the project. Results will be reported to the City via various methods as described above in Section 3.4.15—Operating Reports in this proposal. EXHIBIT 3.4.16-1.Example of Jacobs'Audit Process to Ensure QA/QC Oversight of the Project "\ STEP STEP STEP ' STEP 1 2 3 4 PREPARATION ONSITE EVALUATION ACTION PLAN ASSESSMENT •Audit team sends information •Field assessments,staff •Review information provided for •O&M Supervisor begins request to O&M Supervisor interviews,and review of completeness and accuracy corrective tasks •Alerts go to Compliance Team project records •Compile field observations •Proof of task completion logged and regional O&M technical •Schedule follow-up within •Review meeting with O&M to internal Jacobs Corrective support of upcoming audit three weeks to discuss results Supervisor and Geographic Action Plan database •O&M Supervisor provides Manager •Reminders and progress checks preliminary info for review •Draft action plan to correct at 30,60,90 days deficiencies if needed •Audit close out when all tasks are recorded as completed/resolved Jacobs' O&M projects are regularly audited through a EXHIBIT 3.4.16-2.Dedicated Team of Jacobs Experts Help Perform process that we have developed and refined over our Our Annual Quality Audits O&M group's 40-year history and illustrated in ANNUAL QUALITY AUDIT Exhibit 3.4.16-1. Through this rigorous QA/QC process, new projects are audited six months after start-up,then the frequency of follow-up audits is determined by the project's score across O&M and management areas. Our quantifiable, Compliance repeatable QA/QC process leads to actionable results. Team A dedicated QA/QC team, illustrated in Exhibit 3.4.16-2, investigates 70 specific topics with a focus on contractual requirements and how the project measures against them. Some typical topics include training, project documentation, Audit Regional succession planning, communication plans, inventory, Team Manager CMMS maintenance,work order schedule status, sampling LOCAL plan status, process control plans, data management, and ci TEAM business and budget management. Regional Regional Maintenance Process Specialist Specialist OMFS_QAQC_100 7 v 1 38 1 3.4 Operations and Maintenance 13.4.17 MAJOR REPAIR AND REPLACEMENT PLAN Jacobs recognizes that the City is making a major long-term investment in a new WWTF,and we will protect that investment through a disciplined asset management approach centered on preservation, reliability,and lifecycle value. Our maintenance philosophy emphasizes proactive reinvestment in assets through preventive and predictive maintenance,timely major maintenance, repair, and replacement, and a commitment to the planned Major Maintenance, Repair,and Replacement (MMRR)spending needed to sustain performance and condition over the full term.Accordingly,Jacobs will deliver and maintain a living MMRR Plan that preserves long-term reliability,durability,and regulatory compliance and ensures the project is returned to the City at the end of the term without significant deferred overhaul or immediate replacement needs. The MMRR Plan is the management framework that drives the Project's Major Maintenance,Repair and Replacement Schedule(the detailed,year-by-year schedule maintained over the Term) and provides clear line-of-sight from asset condition and performance to scoped,executed work and documented results. Jacobs'approach is built around the Agreement's allocation of responsibility:Jacobs will perform all Major Maintenance, Repair and Replacement required under the Contract Standards, including work that may be characterized as "major" or "capital" in nature. City approval is not required unless the work constitutes a Capital Modification under Article 11.Jacobs' compensation for MMRR is through the Service Fee.The Plan therefore focuses on disciplined lifecycle planning, risk-based timing,and auditable documentation to avoid surprises and protect end-of-term condition. The Plan integrates: Project Registry(authoritative asset inventory and identity control) CMMS (authoritative system of record for work history, cost, condition evidence, and reporting) Condition assessment and inspections (routine and periodic) Major work planning and execution controls (scope, outage coordination,procurement/ long-lead management) City transparency(reports, dashboards, and schedule change control via CAM) Governance and Continuous Maintenance.Jacobs will manage the MMRR Plan through defined roles and routine City touchpoints: • O&M Supervisor:accountable for Plan delivery, resources, and City coordination • Maintenance Manager/Planner:maintains the schedule baseline;scopes and plans major work packages; coordinates procurement/outages • Reliability/Asset Management Lead: leads condition assessment methods,failure analysis,and remaining useful life (RUL) reviews • CMMS/Asset Data Lead: maintains registry, CMMS alignment,work history quality, and reporting integrity • City Representatives:participate in reviews and provide approvals when required by the Agreement(e.g., certain schedule deferrals) The Plan will be maintained as a living baseline.Jacobs will update it using asset condition findings,work history, OEM guidance, duty-cycle changes,and obsolescence/lead-time considerations. Plan updates and schedule changes are version- controlled so that decisions remain transparent and auditable over the Term. 13.4.17.1 ASSET INVENTORY/REGISTRY Jacobs will develop and maintain a Project Registry that serves as the authoritative inventory of major assets and supports lifecycle planning and handback evaluation.The Registry will align to the CMMS hierarchy(facility/area/ system/asset/component)and will define population boundaries(in-scope equipment and structures), inclusions/ exclusions,and data ownership. Asset records will include, as applicable: unique asset number/ID, location, manufacturer/model, installation/commissioning references, criticality, duty cycle, design/service life assumptions, RUL inputs/outputs, replacement value basis, condition assessment references,and linkage to key documentation (manuals, cut sheets,test records). Registry identity will be synchronized with the CMMS to maintain a single source of truth for asset identification and history. 1 39 1 3.4 Operations and Maintenance Baseline and lifecycle control. Following Acceptance, Execution planning.Jacobs will use the schedule to drive Jacobs will establish the baseline inventory and supporting a rolling look-ahead process that confirms scope definition, documentation needed to demonstrate compliance over outage coordination, long-lead procurement planning,and time and to support future evaluations.Assets replaced constructability/operability considerations so major work or removed will be dispositioned through configuration is delivered safely and efficiently without compromising control to preserve history,traceability,and auditable performance or compliance. records for handback. Scheduled maintenance and adjustment rules.Jacobs I 3.4.17.2 ASSET may choose to accelerate work. However, if Jacobs seeks to delay scheduled maintenance for any component whose IDENTIFICATION METHODOLOGY value exceeds the agreed threshold,Jacobs will first request Jacobs will apply consistent asset identification standards City approval.The request will include documentation aligned with the Project Registry and CMMS. Each asset will showing that the work completed so far, combined with the be assigned a unique identifier using a consistent naming revised future schedule,will maintain or improve the overall convention;field labeling (e.g.,tags and,where beneficial, maintenance, repair,and replacement standard established barcode/QR)will support accurate identification during by the baseline schedule.Jacobs will document all such inspections, maintenance,and inventory management. changes in a Contract Administration Memorandum (CAM) and will work with the City to identify schedule changes A configuration management process will control needed to address or anticipate technical obsolescence. identifiers from commissioning through operations to prevent duplicates and ensure continuity of history. New Risk allocation reminder.Schedule acceleration or or replaced assets will be added through controlled delay does not change the timing of the City's payment workflows; retired assets will retain their historical record obligations for the MMRR component,and Jacobs bears the and a clear disposition. risk associated with deviations from the schedule. Decision framework(repair vs.renew vs.replace).Jacobs I 3.4.17.3 ASSET USEFUL LIFE will apply a consistent decision framework based on ASSUMPTIONS AND CALCULATIONS criticality, condition, RUL, lifecycle cost,safety/regulatory impact, redundancy and outage constraints, maintainability, Jacobs will document useful life and remaining useful and obsolescence/lead-time risk. Decisions and their life(RUL)assumptions using a structured method that technical basis will be documented and retained in considers OEM guidance, industry practice,actual duty the CMMS/Plan record. cycle, operating environment, redundancy/rotation strategy, historical reliability,and asset criticality. Condition End-of-term condition targets.The schedule and decisions assessment findings and work history will validate or adjust will be managed to support the Agreement's end-of-term assumptions over time. condition requirements, including required condition expectations for Project Structures and the required All life assumptions and changes that materially affect the aggregate useful life outcomes for Project Equipment,with 30-year schedule will be recorded in a controlled register particular attention to specified critical equipment groups. with version history.This ensures schedule changes remain technically defensible and fully traceable. I 3.4.17.5 ASSET REPAIR DATA 3.4.77.4 ASSET REPAIR MANAGEMENT METHODOLOGY I AND REPLACEMENT The CMMS will be the system of record for all work history INTERVALS AND SCHEDULE supporting major repair and replacement decisions.Major work records will capture scope,as-found/as-left condition, Jacobs will develop and maintain the detailed relevant failure/cause information where appropriate, Major Maintenance, Repair and Replacement Schedule labor/materials, contractor/vendor documentation, (see Cost Submittal Section 4.6)that identifies major testing/commissioning results,and supporting evidence repair, overhaul, renewal, and replacement activities (e.g., photos, inspection reports).Standard closeout by asset/system for each year of the Term.The requirements and periodic quality reviews will be applied to schedule will be the baseline for planning, execution, maintain record integrity. documentation, and City oversight. Jacobs will conduct periodic reliability reviews to identify repeat failures and chronic"bad actors,"validate preventive and predictive maintenance effectiveness,and adjust repair/ replacement timing using documented evidence. Findings will feed Plan updates and targeted mitigation strategies to reduce emergency work and protect end-of-term condition. 1 v I40I 3.4 Operations and Maintenance 13.4.17.6 CMMS INTERFACES 13.4.17.8 REPORTING PROTOCOL The MMRR Plan will define the interfaces and linkages Jacobs will provide reporting that gives the City clear needed to support timely work identification and defensible visibility from asset condition to decisions,scheduled work, lifecycle decisions, including (as applicable): inspection/ execution status, and documentation. Reporting will include: condition monitoring inputs, alarm/event-driven work request triggers where appropriate, document management • Schedule status(planned vs. executed major work and linkage,and coordination with purchasing/finance upcoming activities) processes. Interface scope, directionality,validation/testing • Multi-year visibility of planned major work and emerging approach,and change control will be established during risks/constraints(e.g., obsolescence, long-lead items) mobilization and managed through configuration control. • Risk tracking for emergent conditions and critical deferrals • Post-work closeout summaries for major events(scope, I 3.4.17.7 ASSET INSPECTION PROTOCOL outage management, QA/QC, lessons learned) Report formats and cadence will be finalized during Jacobs will implement an inspection and condition mobilization to align with City preferences and contract assessment protocol that informs major repair/replacement administration requirements. decisions and supports City oversight, including: • Routine operational observations and rounds Spare and Replacement Parts • Planned maintenance inspections Support for Major Work • Condition-based monitoring where applicable Jacobs will maintain a parts and materials strategy that (e.g.,vibration,thermography, oil analysis, ultrasound, motor diagnostics) supports major repairs and replacements, including • Periodic deeper assessments for major identification of critical spares and long-lead replacement assets and structures components, linkage of parts to asset bill of materials (BOMs)where applicable, and kitting/planning to support Inspection findings will be documented and retained and outage execution.Where required,Jacobs will support will generate work orders and,where warranted, schedule the inventories and valuations associated with spare parts adjustments or interim mitigations to protect safety, and consumables in accordance with the Agreement's compliance,and operability. evaluation requirements. Coordination with City inspections.Jacobs will cooperate with City inspection rights and support efficient review by maintaining current records, reports,and supporting evidence and making them available for City review consistent with the Agreement. X41 3.4 Operations and Maintenance 3.4.18 PRELIMINARY RESIDUALS MANAGEMENT PLAN Purpose and Compliance Basis Sludge processing/conditioning.Jacobs will thicken sludge to well within BES'2%-7%total solids criteria prior to Jacobs will manage Project residuals to ensure safe, transport to Columbia Boulevard and will manage sludge compliant, reliable handling,transport, and disposition quality to support acceptance consistency(including total while minimizing odors,spills,and community impacts.This solids and other applicable acceptance parameters). Preliminary Residuals Management Plan will be refined and incorporated into the final O&M Plan for City review and Grit/screenings/scum conditioning.Jacobs will handle approval and implemented consistent with Applicable Law, and transport grit/screenings/scum to prevent leakage; Contract Standards, and the DBOM Agreement(including materials will be dried, non-putrescible, and no drippings residuals performance requirements). will be permitted from transport vehicles. Residuals are defined as Sludge,Scum,and Grit and Odor control(residuals-focused).Jacobs will integrate Screenings.Jacobs will manage residuals monitoring/ residuals handling and load-out with the Project's odor testing,transport, disposal, and reporting consistent with management practices(as applicable to the final facilities) applicable requirements. by minimizing exposure time, maintaining containment where provided,and implementing corrective actions when Residuals Streams and Quantities odors are identified. If odor testing indicates abnormal odors,Jacobs will develop and implement a corrective Jacobs will manage each residual stream as an end-to-end action plan for City review and comment. operating system,from collection through handling and storage, processing and conditioning, load-out,transport, Hauling, Disposal and disposal or beneficial use,and documentation.Jacobs will plan and control sludge hauling to meet Columbia Beneficial Use Interfaces Boulevard receiving constraints.: Resources and controls.Jacobs will provide, by ownership, lease, subcontract, or otherwise,the vehicles, equipment, Jacobs will also adjust residuals operations for seasonal wet/ dry variability, process changes, influent upsets,thickening and qualified drivers needed to perform residuals transport, and will manage load-out,transport,and unloading to equipment performance. prevent blowing, spilling, or leakage. Collection, Handling, Storage, Processing/ Sludge:Jacobs will transport sludge to Columbia Boulevard Conditioning, and Odor Control when acceptance requirements are met. If Columbia Boulevard is unavailable under contract-defined conditions, Jacobs will operate residuals collection, conveyance, Jacobs will implement the alternative disposal pathway storage, processing,and load-out using the Facility's systems using a Qualified Residuals Disposal Facility. (e.g., pumps, piping, chutes, hoppers/containers, holding tanks)to prevent leaks, spills,and offsite impacts.Jacobs Grit/screenings/scum:Jacobs will transport grit, will comply with DBOM requirements governing residuals screenings,and scum to an Acceptable Disposal Site in storage/stockpiling and will manage staging and load-out to accordance with Applicable Law and contract requirements. comply with contractual odor criteria. Documentation and coordination.Jacobs will maintain Housekeeping and spill/leak prevention.Jacobs will shipping documentation, including manifests, bills of lading, maintain clean handling areas(washdown, drainage and receipts,and will coordinate City signature requirements control, inspections), use covered/contained handling as only to the extent required by Applicable Law. appropriate to prevent tracking and windblown material, maintain spill kits, execute immediate containment/ cleanup during transfers,and train staff/haulers on transfer SOPs and spill response. v I42I 3.4 Operations and Maintenance Monitoring, Sampling, Metering/ Upset and Contingency Planning Weighing, and Recordkeeping Equipment outages.Jacobs will maintain contingency Sampling/monitoring.Jacobs will develop a Residuals procedures for residuals equipment outages, including Sampling Plan(locations,frequency, methods, operational adjustments, use of available storage within preservation/holding, analytical methods)for City approval contract limits, and rental/temporary equipment as needed and will provide/install/operate/maintain samplers as to maintain removal and manage odor potential. needed per the approved plan. Consistent with contract Hauling disruptions.Jacobs will maintain hauling flexibility requirements,the City will collect samples from the through scheduling controls, qualified resources, and samplers in accordance with the approved sampling and alternate disposal pathways consistent with the DBOM reporting plan.Jacobs will support chain-of-custody, documentation, and data packaging. Agreement(including use of a Qualified Residuals Disposal Facility when Columbia Boulevard is unavailable under Recordkeeping.Jacobs will maintain residuals logs/records contract-defined conditions). (quantities, manifests, nonconformances, corrective actions) Spills/releases.Jacobs will prevent unauthorized releases; in an orderly, retrievable,auditable form and provide if one occurs, Jacobs will complete required notifications/ information to the City upon request. reporting, promptly notify the City,and arrange cleanup 9, P p Y Y, 9 and proper disposal consistent with Applicable Law Maintenance and Reliability and the DBOM Agreement. for Residuals Equipment Jacobs will implement proactive PM/CM for residuals- Reporting and Continuous Improvement related equipment(e.g.,thickening systems, pumps, Routine reporting.Jacobs will report residuals volumes, hoppers/containers, load-out equipment, polymer/ weights/measures,and compliance status through the chemical feed as applicable, controls/instrumentation). monthly operations reporting framework and provide Work will be planned and tracked in the CMMS(PM libraries, supporting manifests/records upon request. failure tracking, history),and maintenance records will be available for City review. Optimization.Jacobs will continuously improve residuals performance to maximize sludge solids concentration to Critical spares/contingency readiness.Jacobs will identify reduce hauled volume where feasible without violating residuals-critical spares and implement redundancy/ acceptance constraints, improve housekeeping and minimize contingencies appropriate to the final design and risk(e.g., odor potential at handling areas, reduce spill/leak risk standby equipment, rental options, expedited procurement, during load-out and transit, and improve hauling efficiency pre-qualified hauling alternates). within receiving constraints and City-approved routes. Health and Safety Jacobs will execute residuals operations under the Project Safety Plan and applicable safety requirements, emphasizing confined space hazards, bioaerosols/pathogens and hygiene controls, chemical handling (as applicable),traffic control at load-out/haul interfaces, PPE, lockout/tagout,and task-specific training. v I43I Attachment 106 Major Maintenance, Repair and Replacement Schedule Asset Grouping Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Yr 10 Total PUMPs 0 0 0 0 0 0 0 0 0 1,541,916 1,541,916 BLOWERS 0 0 0 0 0 0 0 0 0 0 0 SCREENS 0 0 0 0 0 0 0 0 0 484,009 484,009 GRIT 0 0 0 0 68,306 0 0 0 0 379,537 447,843 AERATION 0 0 0 0 0 0 0 0 0 0 0 CLARIFIERs 0 0 0 0 203,949 0 0 0 0 509,872 713,821 DISK_FILTERs 0 0 0 0 212,921 0 317,553 0 0 711,118 1,241,592 UV_DISIN 0 0 0 0 0 0 0 0 0 160,521 160,521 HVAC 0 0 0 0 0 0 0 0 0 0 0 I RDTs 0 0 0 0 0 0 0 96,552 0 166,842 263,394 I ODOR 0 0 0 83,811 0 0 0 83,811 0 0 167,622 I VALVEs 0 0 0 0 0 0 0 0 0 0 0 I GATEs 0 0 0 0 0 0 0 0 0 0 0 I PIPING 0 0 0 0 0 0 0 0 0 0 0 VFDs 0 0 0 0 0 0 0 0 0 308,729 308,729 ELEC_GEAR 0 0 0 0 55,000 0 0 0 0 270,000 325,000 GENERATORs 0 0 0 0 0 0 0 0 0 201,108 201,108 LCPs 0 0 0 0 0 0 0 0 0 0 0 PLCs 0 0 0 0 0 0 0 30,293 0 0 30,293 SCADA 0 0 0 0 0 0 0 27,021 0 0 27,021 TANKs 0 0 0 0 0 0 0 0 0 0 0 BLDGs 0 0 0 0 0 0 0 0 0 94,800 94,800 STRUCTs 0 0 0 0 0 0 0 0 0 0 0 SITE 0 0 0 0 0 0 0 0 0 0 0 Totals 0 0 0 83,811 540,176 0 317,553 237,677 0 4,828,452 6,007,668 1 Appendix D:Resumes Michelle Green, PE, DBIA, DBOM Project Manager Michelle has a proven track record of delivering holistic design, - ±' engineering, and construction services and improvements for wastewater plants, while ensuring programmatic elements such as permitting, stakeholder engagement, and agency coordination contribute to project success. As a skilled project manager and process lead, she understands what is required to deliver successful wastewater projects in the Northwest. Professional Profile Firm Name Jacobs Michelle has extensive experience delivering large capital water and wastewater treatment projects using design-build(DB)and design-build-operate(DBO)delivery. Years of Experience She is a strong communicator especially adept at promoting collaborative interface 32 between clients,and design,construction,and operations teams.Michelle also develops and promotes best practices for use in implementation of successful collaborative Education delivery projects. BS,Civil Engineering, Iowa State Representative Projects University Engineering Manager.Wilsonville Wastewater Treatment Plant(WWTP)DBO. Registrations Wilsonville,Oregon.Michelle managed the engineering and permitting team throughout Professional Engineer(PE); the duration of this operate-design-build-operate(ODBO)project—the first delivered in Design-Build Institute of America Oregon.The project involved extensive reuse and incorporation of existing facilities,and (DBIA) major construction on an incredibly constrained site.Michelle interfaced with Jacobs construction and operations teams to facilitate project delivery,including development of construction sequencing to allow continuous operation and permit compliance during construction.Developed extensive startup strategies to transition from existing unit processes to new facilities as they came online in a staggered fashion.Managed design team support,including onsite quality assurance staff,throughout construction. Relevance to Lake Oswego:DBO WWTP of a similar size in Oregon. Project Manager.Grants Pass Water Reclamation Facility(WRF)Phase Upgrade Progressive Design-Build(PDB).Grants Pass,Oregon.Michelle managed the entire scope of PDB services for this$25M wastewater rehabilitation.The project included headworks, odor control,and gravity thickening improvements;a new primary clarifier and aeration basin;and the complete replacement of electrical and supervisory control and data acquisition systems within the facility.The project significantly upgraded the city's 6-mgd WRF,improving reliability of treatment.It was built safely,with 118,000 onsite workhours without a lost time incident.Michelle was responsible for collaboration and integration between city management/operations staff and Jacobs design/construction staff, completing the project within an aggressive schedule(23 months)and 1%under the final budget.Relevance to Lake Oswego:PDB WRF of a similar size in Oregon. Project Executive/Commercial Lead.Nampa WWTP Phase 2 PDB.Nampa,Idaho.This $150M PDB project implemented extensive upgrades at the city's existing WWTP to increase capacity and meet new discharge water quality requirements.As Commercial Lead,Michelle guided the delivery team in risk management,contingency development and guaranteed maximum price development.As Project Executive,interfaced with City leadership,including Mayor,City Councilor,and Design Review Committee to discuss project challenges and develop execution strategies that met city's performance and financial goals.Relevance to Lake Oswego:PDB WWTP. 1 Appendix D:Resumes Procurement Lead.San Juan Lateral Water Treatment Plant DBO.Shiprock, New Mexico.Michelle led procurement for this recently awarded$267M project,which will provide a sustainable water supply for approximately 250,000 people in 43 Navajo chapters.Jacobs will design and build the 18.8-mgd WTP,provide commissioning of the entire San Juan Lateral distribution system,and up to 2-years of operations and maintenance of the WTP and Lateral.Michelle managed design,construction,and operations,teams throughout the procurement in development of technical concepts,construction approaches,and contract price.Over the course of 8 months and several proprietary meetings with Reclamation,Michelle led interface with Reclamation and was responsible for aligning Jacobs'best value proposal with their goals and preferences.Relevance to Lake Oswego:DBO WWTP. DB Procurement Lead and Project Sponsor.Stanislaus Regional Water Supply Project.Ceres,California.Michelle led procurement for this $195M fixed-price DB project.Improvements include a new raw water pump station, 1/2-mile 48"raw water transmission main, 15-mgd surface water treatment plant(expandable to 30-mgd),and 12 miles of 30"and 42"finished water transmission mains.During the 2-year procurement period,Michelle managed process,design,construction, procurement,and legal teams in development of technical concepts,construction approaches,contract price,and commercial terms.She led interface with client and final negotiation of contract after selection.Supported the team as project sponsor,accountable to client general manager and owner's advisor,throughout project execution to see that Jacobs team delivered as promised.Relevance to Lake Oswego:DB water supply project. Facility Plan Lead.Tryon Creek Wastewater Treatment Plant(TCWTP)Facilities Plan.Portland,Oregon.Michelle led all technical work for development of an updated facilities plan for the TCWTP.This work included development of system design criteria and evaluation of existing treatment systems,development,and evaluation of whole-plant alternatives to define 30-year plan for the facility.The recommended 10-year CIP included phased improvements designed to address aging infrastructure,manage 25-year storm flows through the facility,improve performance and system resiliency during high river levels,expand the plant site to improve interface with the neighborhood and improve effluent water quality.Michelle served as engineering liaison to the 10-member Community Advisory Committee comprising Lake Oswego and Portland representatives.Relevance to Lake Oswego:WWTP in Portland,Oregon. Project Manager.Oak Lodge Water Reclamation Facility Improvements.Oak Grove,Oregon.Michelle led engineering,preconstruction, and construction phase services for this two-phase$61M program.Jacobs provided facility planning,predesign,final design, construction-phase engineering services,supervisory control and data acquisition(SCADA)system integration,startup support,and training services scope for an invasive retrofit within the existing site footprint.Provided ongoing process support and training during initial year of operation.The project was delivered ahead of schedule and on budget,with no construction related permit violations during construction.Relevance to Lake Oswego:WWTP in Oregon. CM/GC Advisor.Columbia Boulevard Wastewater Treatment Plant(CBWTP)Secondary Treatment Expansion Program(STEP). Portland,Oregon.Jacobs is the designer for this$500M project at the city's main wastewater facility.Provided strategic input to BES, design and program support teams to support successful CM/GC execution.Michelle is responsible for advising the Jacobs team on interface with the CM/GC,specifically related to risk analyses and management.Relevance to Lake Oswego:WWTP expansion in Portland,Oregon. Owner's Advisory Services,Strategic Advisor.Michelle regularly supports owner's advisory teams on their first PDB projects, including the development of robust,viable procurements and contracts.She provides strategic input during Phase 1 activities,with a specific focus on development of project-first risk allocations to reduce project costs and set up successful outcomes,GMP review,and Phase 2 Contract Price negotiations. Projects include the Tri-City WRF Outfall PDB Project in Clackamas County,and the Upper Tualatin Interceptor PDB Improvements Project in Hillsboro.Relevance to Lake Oswego:Owner's advisory for PDB water projects. v 2 Appendix D:Resumes Kristen Jackson, PE, Engineering Design Manager Kristen brings a unique, diverse perspective to water and wastewater treatment. Leveraging her construction expertise, communication skills and organizing capabilities, Kristen is a natural leader, driving \VW integration of her design teams to create constructible wastewater treatment solutions. Professional Profile Kristen brings extensive project management and design experience in large and small Firm Name wastewater treatment projects,specializing in liquids treatment,hydraulic and process Jacobs modeling,and energy analysis to develop efficient,high-quality processes and systems. Kristen also brings experience in construction project management and scheduling,as Years of Experience well as alternative delivery methods,such as design-build(DB),construction manager/ 18 general contractor,and public-private partnerships(P3s). Education Representative Projects MS,Civil and Environmental Outfall Designer.Wilsonville Wastewater Treatment Plant(WWTP)Design-Build- Engineering, University of Operate(DBO).Wilsonville,Oregon.This$88M($44M capital and$2.4M yearly O&M California, Davis;BS,Civil for 20 years)DBO project updated and expanded the city's aging sewage treatment Engineering,Santa Clara plant.The scope included 2.5-mgd to 4-mgd immediate expansion,with future expansion University capabilities to 7-mgd that will produce Class A biosolids for land application.Kristen supported the project's outfall design.Relevance to Lake Oswego:DBO WWTP of a similar Registrations size in Oregon. Professional Engineer(PE) Facility Lead.Grants Pass WRP Phase 2 Upgrade.Grants Pass,Oregon.This$25M progressive design-build(PDB)project significantly upgraded the City's 6-mgd water restoration plant to improve treatment reliability.Kristen worked collaboratively with the city to implement improvements at the existing facility,while maintaining operations throughout the invasive construction activity.She was process lead for design of rehabilitation of the gravity thickener including coordination for temporary thickening operations during construction.She also managed services during construction and coordinated field efforts with engineering staff to solve construction issues.Kristen also managed startup and commissioning of major equipment components,including functional and performance testing. Relevance to Lake Oswego:PDB WWTP in Oregon. Technical Reviewer and Ash Study Lead.Westside and Marine Park WWTP.Vancouver, Washington. Jacobs is operating the city's 28.26-mgd Westside WWTP, 16.1-mgd Marine Park WWTP, 1.7-mgd Industrial Lagoon Treatment Facility,and eight lift stations. We also implemented a$24M DB upgrade to the city's supervisory control and data acquisition system and programmable logic controls.Kristen provided technical review of the preliminary design documents to include in the lenders'technical advisor report highlighting technical risks for potential lenders to prepare their financing commitments and led an ash study for the facility.Relevance to Lake Oswego:Operation and maintenance(O&M)and DB for WWTPs in the Pacific Northwest. 3 Appendix D:Resumes Technical Reviewer.Lenders'Technical Advisor Lake Oswego Wastewater P3 Project.Portland,Oregon.Responsible for providing technical review of the preliminary design documents to include in the lenders'technical advisor report highlighting technical risks for potential lenders to prepare their financing commitments.Relevance to Lake Oswego:Knowledge of Lake Oswego's wastewater needs and alternative delivery opportunities. Facility Lead.Columbia Boulevard Wastewater Treatment Plant(CBWTP)Secondary Treatment Expansion Program(STEP).City of Portland, Bureau of Environmental Services(BES).Portland,Oregon.STEP includes the design of two new 145-foot-diameter secondary clarifiers,associated disinfection for the clarifiers,along with a combination of projects in proximity or operationally connected, including a completely new biosolids co-thickening and dewatering facility and biosolids storage and loading facility.The project includes demolition of aging facilities,modifications to remote boilers,replacement of the medium voltage system,design of non- process facilities,and ground improvements for new facilities.The project design budget is$29M.Kristen was the facility lead for design of the new secondary clarifiers, return activated sludge(RAS)pump station,mixed liquor pumping system,and associated disinfection for the new clarifiers.Coordinated hydraulics analysis and was quality manager and safety coordinator for a portion of the project. Led alternatives analysis and process mechanical design,and managed discipline coordination for the secondary clarification system. Relevance to Lake Oswego:Design of new WWTP facilities in Portland,Oregon. Project Engineer.Kellogg Water Pollution Control Plant(WPCP)Outfall Improvements.Clackamas County,Oregon.Kristen provided construction management services for an outfall extension project at the Kellogg WPCP,including management of submittals,RFIs,work change directives,permitting,schedule,and budget.The project included construction of the new outfall pipe and extensive field studies, dilution analysis,and support for District coordination with DEG to improve the facility's mixing zone.Relevance to Lake Oswego:Outfall improvements at a WPCP in Oregon. Design Manager.CBWTP Wet Weather Clarifier and Sodium Hypochlorite System Modifications.Portland,Oregon. Responsible for day-to-day management of project tasks,client,and 14 subconsultant's primary point of contact.Manages the daily activities of the design team, including driving detailed design schedule,weekly briefing with the design team,facilitating interdisciplinary decision making,documenting change,and ensuring quality of each individual deliverable.Relevance to Lake Oswego:Design of new WWTP facilities in Portland,Oregon. Project Manager/Process Engineer.WWTP Anaerobic Digestion and Cogeneration Expansion Project.Gresham,Oregon. Kristen was responsible for the project's preliminary design,which included additional liquid organic waste receiving infrastructure,digestion capacity expansion,gas treatment system analysis,cogeneration,biosolids management,new boilers,and production of renewable natural gas.The project also included an update to the previous business case evaluation from the feasibility study to perform financial analysis that can be used for proceeding with funding the implementation phase of the project,including capital costs,feedstocks,and renewable energy revenues.Relevance to Lake Oswego:Design of new WWTP in Oregon. Project Manager.WWTP Gravity Belt Thickener Replacement Project.Gresham,Oregon.Project manager and quality manager for the design and services during construction project for the replacement of three gravity belt thickeners with three rotary drum thickeners for co-thickening of waste activated sludge and primary sludge from the blend tank.Project also included replacement of thickened sludge pumps and new instrumentation.Relevance to Lake Oswego:Design services during construction for new WWT facilities in Oregon. Project Engineer.WWTP Master Plan Update 2017.Gresham,Oregon.The master plan update included development of a liquids treatment plan with flexibility to adapt to a variety of potential regulatory scenarios,evaluation of alternatives to defer construction of a third anaerobic digester,investigation of Class A biosolids options,assessment of options for use of excess biogas and/or heat generated from the existing combined heat and power system,and updates of the capital improvement plan to reflect the results of the master plan update.Evaluated entire plant energy usage to identify energy sinks.Kristen analyzed plant data for flows and loads projections updates,process modeling update,alternatives evaluation for digestion alternatives,and analysis of plant energy consumption. Relevance to Lake Oswego:Evaluation of WWTP for improvements in Oregon. 4 Appendix D:Resumes Enrique Ramos, Design-Build Manager Enrique brings over three decades of construction leadership for more than $640M worth of water and wastewater design-build(DB) / and design-build-operate (DBO)projects, many with more than 100 onsite staff Professional Profile Enrique manages large-scale electrical, mechanical,and civil construction projects. Specializing in at-risk and design-build water and wastewater infrastructure projects, Firm Name his career features more than 70 projects with a total value of more than$800M.His Jacobs expertise extends to all aspects of delivering quality construction projects on time and on budget,including contract negotiation,subcontracting,estimating,and scheduling Years of Experience for water and wastewater treatment plants. 40 Representative Projects Education Construction Manager.Wilsonville Wastewater Treatment Plant(WWTP)Design- Mechanical Engineering Build-Operate(DBO).Wilsonville,Oregon.This DBO project expanded the plant from Coursework, University of 2.5-mgd to 4-mgd,with future expansion capabilities to 7-mgd,and produces Class A Massachusetts biosolids for land application. It also replaced and upgraded most remaining portions of the original plant first constructed in the early 1970s.Jacobs operates this plant Registrations while the improvements are built and tested and will continue operation until 2027. N/A While serving as construction manager on this expansion project, Enrique and his team addressed a lack of space within the footprint of the operating facility while meeting the requirement to keep the facility operational.This required complex planning to safely schedule and engage multiple work crews concurrently,while also implementing a construction sequence that removed existing centrifuges and temporarily hauled biosolids offsite for processing.Relevance to Lake Oswego:DBO WWTP of a similar size in Oregon. Construction Manager.Spokane County Regional Water Reclamation Facility(RWF) DBO Project.Spokane,Washington.Spokane County's new 8-mgd,$131.7M WRF was designed and constructed to meet future population growth,eliminate septic tank service,and reduce phosphorous discharge to the Spokane River.Jacobs was the prime DBO firm with a single point of responsibility for this project,completed 7 months early,and is currently operating and maintaining the facility for 20 years.Enrique was responsible for all aspects of construction delivery,including oversight of more than 550,000 direct hire and subcontractor work hours encompassing 9,600 cubic yards of structural concrete and 40,000 linear feet of yard pipe.Safety performance was also excellent,with zero days away/restricted time incidents during 30+months of construction.The Spokane project won a 2012 Design-Build Institute of America National Award in the Water/Wastewater category.Relevance to Lake Oswego:DBO WRF of similar size in the Pacific Northwest. 5 Appendix D:Resumes Construction Manager.Nampa WWTP Phase 2 Progressive Design-Build(PDB).Nampa, Idaho.This$189M project increased the capacity of the city's WWTP by 50 percent.The project included full-service design engineering,with services during construction, systems integration,construction upgrades,startup,and commissioning.The project provided liquids improvements through a new aeration basin structure, new secondary clarifier,recoating of existing secondary clarifier mechanisms and the expansion and upgrade of return activated sludge pump station,provided new tertiary filters,a new ultraviolet(UV)disinfection facility,new plant water pump station,new reuse pump station and two new outfalls(National Pollutant Discharge Elimination System and Class A Recycled Water). Upgrades also included a new medium voltage plant wide electrical system upgrade including full load emergency back-up power generation.The mile long reuse pipeline including micro-tunneling under the Union Pacific Railroad train yard is a key feature of the project.It will deliver Class A recycled water to mitigate the high demand for agricultural and municipal irrigation water.At startup,an expected 11 million gallons of recycled water per day will be introduced into the Phyllis Irrigation Canal during the critical summer months when irrigation water demands are at their highest,thereby reducing the impact to our valuable water reserves.The project's acceptance test was completed 2 months ahead of schedule.Relevance to Lake Oswego:PDB WWTP. Construction Manager.Woodland-Davis Water Supply Project DBO.Woodland,California.Jacobs served as the design-builder and is currently operating this$146M, 30-mgd WTP and 15 miles of pipelines.A key challenge was meeting the owner's requirement to provide a demonstrated savings of 10 percent on a net present value basis.The two other shortlisted teams withdrew from the procurement,which required a collaborative approach between Jacobs and the owner to develop an open-book process for demonstrating that the targeted net present value savings was achieved via fair and competitive pricing.Enrique served as construction manager for this project and provided leadership to overcome several challenges.A primary challenge was construction of the raw water intake,which was performed under a traditional design-bid-build contract by a third-party contractor.When completion of the intake fell behind schedule, Enrique led the Jacobs team in installing temporary raw water pumps to supply river water for startup and commissioning of the new facility.This work-around for the raw water supply helped the project achieve substantial completion 3 months ahead of schedule.Relevance to Lake Oswego:DBO WTP. Assistant Construction Manager.Twin Oaks Valley Water Treatment Plant DBO Project.San Diego County Water Authority.San Diego, California.Responsible for onsite management of construction activities of a 100-mgd water treatment facility for the San Diego County focusing on safety and quality while meeting schedule milestones.Oversaw superintendents and subcontractors to ensure consistency in daily communications and completion of scheduled tasks.Relevance to Lake Oswego:DBO WTP. Construction Manager.San Jose-Santa Clara Regional Wastewater Facility Headworks DB.City of San Jose.San Jose,California. This$127M DB project included construction of a new Headworks 3,making minor improvements to existing Headworks 2, decommissioning the existing aging Headworks 1,and making improvements to the influent conveyance facilities.The facilities will be capable of treating current flows and extreme peak hour wet weather design condition of 2040 of 396-mgd.Relevance to Lake Oswego: DB WWTP. Project Manager.San Jose-Santa Clara Regional Wastewater Facility Cogeneration Progressive Design-Build.City of San Jose.San Jose,California.This new$95M cogeneration facility uses internal combustion engine-driven generators with a biogas conditioning system to generate 14 megawatts(MW)of electricity while complying with the California Bay Area Air Quality emissions limits.Enrique was engaged from the beginning of design and was responsible for the management,construction,start-up and commissioning of the facility while closely coordinating with the San Jose WWTP management and operations.Relevance to Lake Oswego:DB project constructed in close coordination with San Jose WWTP management and operations. 6 Appendix D:Resumes Jose Castro, Construction QA/QC Manager Jose has extensive experience with field inspections and sampling, as well as overseeing laboratory testing of critical processes, systems, and equipment, so that the delivered project meets client expectations and regulatory requirements. Professional Profile Jose brings 22 years of experience in construction and engineering and has a working knowledge of construction management,inspection,and supervision for major public Firm Name infrastructure projects. He is experienced in geotechnical inspections,field material sampling and laboratory testing and works diligently to keep client expectations in Jacobs mind at all times.He is proficient in AutoCAD and excels at project execution from project inception to completion and closeout. Years of Experience 28 Representative Projects Education WTP Lead Inspector.Stanislaus Regional Water Authority(SRWA)Water Treatment Civil Engineering,Universidad Plant(WTP).Hudson,California.Jose served as part of the design-build team Autonoma de Baja California in charge of the design and construction of the$195M project to provide high- quality drinking water to the cities of Turlock and Ceres. In this role,he observed Registrations subcontractors'field activities;coordinated and scheduled third-party inspections; N/A reviewed third-party weekly reports;maintained progress photos in filing system; performed QC field observations and concrete pre-placement inspections;prepared and published daily construction reports and weekly field activities;observed and reported field safety issues,including supervision of subcontractors'periodic equipment rotations;and prepared and followed up on the project's final punch list. Relevance to Lake Oswego:Onsite supervision of DB WTP construction. Construction Inspector.Calexico West Land Port of Entry(LPOE)Phase 1 Expansion and Reconfiguration.Calexico,California.The$120M, Phase 1 LPOE expansion and modernization program at Calexico West LPOE consisted of three southbound POV lanes and a southbound bridge over the New River; 10 northbound POV inspection lanes with primary and secondary inspection canopies;booths and inspection equipment;and a new headhouse and site work to accommodate inspection facilities on the sloping site.Jose's responsibilities included daily observation of contractor field activities;coordinating field activities of third-party inspectors;preparing and publishing daily construction reports;maintaining photograph files for construction progress;preparing and posting a safety plan of actions;preparing and publishing safety observation reports;participating in QA/QC meetings;preparing and submitting non-conformance notices;keeping track of construction open items; and reviewing/transitioning requests for information(RFIs)and submittals into an electronic project management system.Relevance to Lake Oswego:Onsite construction supervision of complex infrastructure project. v 7 Appendix D:Resumes Senior Construction Inspector.All-American Canal.Imperial Irrigation District.Winter Haven,California. Responsibilities included daily operations of the QA/QC process as part of the management team.Responsible for conducting surveillance and inspection of civil elements of the work,including earthwork structures,trimming,concrete lining,and surveying.Reported to the QA/QC manager for the concrete lining of the All-American Canal,with an estimated constructed value of$230M.Instrumental in the inspection of the approximately 30 million cubic yards of excavation,construction of 23 miles of the 150-foot-wide concrete-lined canal,and associated dewatering,transitions,metering facilities,maintenance road and drainage,and wetlands mitigation construction.Interacted with the U.S.Bureau of Reclamation, U.S. Border Patrol,and the San Diego County Water Authority to ensure there would be no disruption in the supply of 3.1 million acre-feet of water per year,and minimal disruption of hydroelectric power production during construction. Relevance to Lake Oswego:Onsite construction supervision of complex infrastructure project. Quality Control Specialist.Mojave Generating Station Ash Canyon Storm Repair Project.Southern California Edison. Laughlin, Nevada.This project consisted of the repair of the eroded areas along the storm drainage system.Jose was responsible for maintaining a daily log of construction and inspection activities;preparing daily and weekly progress reports;preparing and distributing agenda for team meetings;verifying accuracy of repair dimensions;inspecting contractor work to ensure that procedures and materials comply with plans and specifications;reporting directly to the Edison construction and engineering departments transferring contractor change orders,submittals, RFIs and other information related to the project;reviewing and commenting on contractor submittals, RFIs and change orders before transferring to Edison engineering department;and inspecting equipment,tools,and working conditions to ensure safety of workers repairing eroded areas along the storm drainage system.Jose also inspected personal protective equipment (PPE)and reviewed open trench best management practices.Relevance to Lake Oswego:Onsite construction supervision of complex infrastructure project. Quality Control Specialist.Tunnel Rehabilitation Project.Southern California Edison. Kern County,California.This$14M project consisted of the repair of floors,walls,and ceiling of the 16-mile tunnel.Jose was responsible for maintaining a daily log of construction and inspection activities;preparing weekly progress reports;preparing and publishing weekly agenda for team meetings;verifying accuracy of dimensions of structural installations and layouts;inspecting and overseeing contractor work to ensure that procedures and materials comply with plans and specifications;and reporting directly to the Edison engineering department regarding contractor change orders,submittals, RFIs and diverse information related to the project.Relevance to Lake Oswego:Onsite construction supervision of complex infrastructure project. Construction Inspector.San Ysidro LPOE Phase 3.San Ysidro,California.Jose's responsibilities included inspecting contractor's field activities, updating daily construction reports,maintaining construction progress photos in a filing system,observing and reporting field safety issues, reviewing RFIs,and updating the redline log.Relevance to Lake Oswego:Onsite construction inspection. v 8 Appendix D:Resumes Daniel Black, Operation and Maintenance Manager Daniel brings more than 25 years of experience in the operations and maintenance of water and wastewater facilities, pump stations, collection systems, and public works. He focuses on operational control strategies, maintenance, safety, and team development. Professional Profile Daniel has managed municipal water and wastewater operations across multiple Firm Name facilities,including a Grade IV wastewater treatment plant and satellite treatment Jacobs and collection systems.His experience includes supervising and training operations Years of Experience teams,overseeing daily facility operations and budgets,and supporting regulatory compliance for NPDES,drinking water,and land application permits.He was named 25 Idaho PNCWA Operator of the Year in 2023 and has served as secretary,vice president, and president of the Southeast Idaho Operator Section. Education High School Diploma Representative Projects » College of Southern Idaho- Project Manager.Jacobs,Twin Falls,Idaho.2022—Present.Daniel manages a 9-mgd Diesel Tech wastewater treatment facility that includes a Grade IV IFAS activated sludge plant. He » Operator 10®Training leads a team of 19 full-time employees.Relevance to Lake Oswego:Management of » Wastewater Treatment wastewater facility operations and staff. Volumes I and II,Advanced Operations Supervisor.Jacobs,Twin Falls,Idaho.2020-2022.Daniel supervised Treatment and Water operations of the City of Twin Falls wastewater treatment plant and the City of Hansen's Distribution. satellite drinking water and wastewater facilities.He helped train new employees, » Utility Management. develop operator policies and daily tasks,and supported reporting and regulatory Wastewater Collections. compliance for NPDES and drinking water permits.Relevance to Lake Oswego: » University of California, Supervision of wastewater and drinking water operations,staff training,and permit Sacramento,California compliance. » U.S.Army 63H MOS—Track Project Manager.Jacobs,The Dalles,Oregon.2019-2020.Daniel managed Vehicle Repair operations across three facilities:a Grade IV wastewater treatment plant in The Dalles, Registrations a Grade II wastewater treatment plant and Grade I collection system in Mosier,and a Grade II wastewater treatment plant and Grade I collection system in Biggs Junction. » Idaho Grade IV Wastewater He managed eight full-time employees across the facilities.Relevance to Lake Treatment Oswego:Management of multiple wastewater treatment and collection facilities. » Idaho Grade II Wastewater Operator 1.Jacobs,Twin Falls,Idaho.2017-2019.Daniel operated the City of Twin Collection Operator Falls wastewater treatment plant and the City of Hansen's satellite drinking water and » Idaho Grade II Water wastewater facilities.He operated and maintained treatment processes on a rotational Distribution Operator basis, helped train employees and develop operator policies and daily tasks,and » Idaho Wastewater Land supported regulatory reporting and permit compliance.Relevance to Lake Oswego: Application Direct operation and maintenance of wastewater and drinking water facilities. » Idaho Grade I Laboratory Analyst 3 Appendix D:Resumes Class III Operator/Public Works Director.City of Bellevue,Bellevue, Idaho.2011-2016. Daniel oversaw the city's water,wastewater, streets, parks,and buildings and grounds departments,including daily operations,employees,and budgets.As Responsible Charge Operator, he was responsible for a Class III membrane wastewater treatment plant,a Class II drinking water distribution system,and a Class II wastewater collection system. He prepared annual budgets,supported federal grant work to upgrade city services,and worked with Idaho DEQ to maintain permit compliance. Relevance to Lake Oswego: Leadership of municipal water and wastewater operations, public works, budgeting,and regulatory compliance. Water and Wastewater Operator/Public Works Director.City of Wendell,Wendell, Idaho.2007-2011.Daniel oversaw the city's water,wastewater,streets,and buildings and grounds departments,including daily operations,employees,and budgets.As Responsible Charge Operator, he was responsible for a Class II lagoon wastewater treatment system,a Class II drinking water distribution system, and a Class II wastewater collection system. He prepared annual budgets and worked with Idaho DEQ to maintain compliance with wastewater land application and drinking water permits.Relevance to Lake Oswego: Leadership of municipal water and wastewater systems and permit compliance. Operator 2.CH2M HILL OMI/Jacobs,Twin Falls, Idaho.2001-2007.Daniel operated and maintained the City of Twin Falls wastewater treatment plant and the City of Hansen's satellite drinking water and wastewater facilities.He operated treatment processes on a rotational basis, helped train employees and develop operator policies and daily tasks,and supported regulatory reporting and permit compliance.Relevance to Lake Oswego:Hands-on operation and maintenance of wastewater and drinking water facilities. d 4 Appendix D:Resumes Matt Smith, CSP, CHST, STSC, Safety Officer As Jacobs' Western Regional Health, Safety, and Environment (HSE)Manager for at-risk delivery, Matt leads construction safety programs for general contracting and design-build projects across multiple states. He brings deep knowledge of federal and state occupational safety and health regulations and is experienced in applying these requirements across diverse project environments. t Matt is a proactive safety leader who emphasizes training, communication, and planning. He works closely with project teams Firm Name to build safety awareness, verifying that personnel understand Jacobs critical risks, regulatory requirements, and the importance of Years of Experience effective safety planning to achieve zero-incident performance. 23 Professional Profile Education Matt has more than 21 years of experience in construction health and safety, including BS,Occupational Safety and over 10 years serving as an HSE manager on large water and wastewater infrastructure Health,Columbia Southern projects exceeding$100M.He has extensive expertise in OSHA compliance and University implementing safety programs for complex,multi-discipline construction projects. His hands-on background enables him to effectively collaborate with field personnel Registrations and develop practical,implementable safety solutions.Matt specializes in preparing Certified Safety Professional and reviewing detailed task hazard analyses(THAs)and integrating appropriate HSE (CSP);Construction Health and controls to comply with regulatory requirements,client standards,and project-specific Safety Technician(CHST);Safety procedures. Train Supervisor,Construction Matt's experience across design-build-operate and design-build-operate-maintain (STS-C) (DBO/DBOM)delivery models provides him with a strong understanding of the safety considerations required across all phases of project execution,from design through construction and into operations.His attention to detail and commitment to continuous improvement result in consistent, high-performing safety programs that protect workers,the public,and the environment. Representative Projects H&S Manager.Spokane County Regional County Water Reclamation Facility(WRF) DBO.Spokane,Washington.$127M DBO project for a new 8-mgd regional water reclamation facility.Jacobs provided design, permitting,construction,and long-term operations services.The facility significantly improved regional treatment capacity, supported population growth,and reduced phosphorus discharges to the Spokane River.Matt served as H&S manager, responsible for implementing and maintaining compliance with Jacobs'health and safety program,OSHA requirements,and injury management and reporting protocols. He led site-wide safety planning,training,and performance monitoring across all phases of construction.Under Matt's leadership, the project achieved over 600,000 work hours with zero lost-time incidents and a recordable incident rate approximately 85%below industry average,demonstrating exceptional safety performance on a complex DBOM project.Relevance to Lake Oswego: Demonstrates ability to lead safety on a DBO WRF of similar size in the Pacific Northwest. 11 Appendix D:Resumes H&S Manager.Grants Pass WRF Phase Upgrade Progressive Design-Build(PDB).Grants Pass,Oregon.PDB project to expand and upgrade an existing WRF,including construction of a new aeration basin,blowers,and secondary clarifier;rehabilitation of existing treatment processes;and upgrades to electrical and control systems.The project included early work packages and phased construction to maintain ongoing operations.Matt was responsible for implementing project-specific safety programs,confirming OSHA compliance, and managing incident prevention,reporting,and training across all construction activities.The project achieved over 156,000 work hours with zero lost-time incidents during nearly 2 years of construction and received Jacobs'Excellence in Safety Award for outstanding safety performance.Relevance to Lake Oswego:Experience managing safety on a WRF of a similar size in Oregon under a collaborative delivery model,including work at an operating facility with phased construction. Safety Manager.Agua Nueva WRF DBO.Pima County,Arizona.$158M DBO project involving construction of a new 32-mgd WRF, including multiple process facilities, pipelines,basins,and tanks to replace an existing wastewater treatment plant.Matt led implementation of comprehensive H&S programs,confirming compliance with OSHA standards,corporate safety requirements,and project-specific procedures.His responsibilities included safety planning,audits,training,and injury management and reporting.The project achieved over 1 million work hours with zero lost-time incidents and a recordable incident rate approximately 90%below industry average,reflecting best-in-class safety performance on a large-scale DBOM project.Relevance to Lake Oswego:Demonstrates ability to manage safety across multi-phase construction and long-term operational integration for a DBO WRF. Safety Manager.Northern Treatment Plant(NTP)DB,Metro Wastewater Reclamation District.Brighton,Colorado.DB project for a new 24-mgd wastewater treatment plant serving the northern Denver metropolitan area.The facility includes preliminary and primary treatment,advanced biological treatment,tertiary filtration,and UV disinfection,with discharge to the South Platte River. Construction involved approximately 83,000 CY of concrete, 1 million CY of earthwork,and installation of a slurry wall system to isolate groundwater.Matt served as safety manager,responsible for implementing and maintaining compliance with Jacobs'health and safety standards,OSHA requirements,and injury management and reporting systems.He led safety planning,audits,training,and field oversight across all major construction activities.Under Matt's leadership,the project achieved over 2 million work hours with zero lost-time incidents and a recordable incident rate approximately 90%below industry average.The project received Jacobs'Excellence in Safety Program(ESP)Award,reflecting performance aligned with OSHA's Voluntary Protection Program(VPP)standards.Relevance to Lake Oswego: Demonstrates Matt's ability to manage safety on high-risk DB WWTP and deliver exceptional outcomes on treatment plant projects comparable in complexity to Lake Oswego. H&S Manager.San Jose-Santa Clara Regional Wastewater Facility Headworks DB.City of San Jose.San Jose,California.$127M DB project,including construction of a new Headworks 3 facility,upgrades to Headworks 2,decommissioning of Headworks 1, and improvements to influent conveyance systems at an active wastewater treatment facility.Matt was responsible for confirming compliance with OSHA and Cal OSHA standards and leading the implementation of project-specific safety programs.His work included subcontractor prequalification,safety audits and inspections,and development and enforcement of site-wide health and safety procedures. Relevance to Lake Oswego: Demonstrates experience delivering safety on an active DB WWTP with complex phasing,tie-ins, and operational constraints. H&S Manager.San Jose-Santa Clara Regional Wastewater Facility Cogeneration PDB.City of San Jose.San Jose,California.This new$95M cogeneration facility uses internal combustion engine-driven generators with a biogas conditioning system to generate 14 megawatts(MW)of electricity while complying with the California Bay Area Air Quality emissions limits.Matthew's role included verifying adherence to OSHA and Cal OSHA standards and more.His work included pre-qualification,audits,inspections,and health and safety program development and implementation.Relevance to Lake Oswego:Experience delivering safety within an operating wastewater facility,requiring close coordination with plant operations. Regional H&S Manager.Houston Northeast Water Purification Plant(NEWPP)Expansion Project.Houston,Texas.$1.7B PDB project to expand a 320-mgd water purification plant,supporting regional growth and reducing groundwater dependency.One of the largest water infrastructure projects in the United States.As Regional H&S Manager,Matt oversaw implementation of safety programs across the project,confirming compliance with Jacobs'safety standards,OSHA regulations,and project-specific requirements.He led safety culture initiatives,performance monitoring,and continuous improvement efforts across multiple work fronts and contractors.The project has achieved over 2.1 million work hours without a lost-time incident,demonstrating sustained, large-scale safety performance. Relevance to Lake Oswego:Demonstrates leadership of safety programs on large,complex, multi-contractor progressive design- build projects. 12 OE`A eo s4 � n u � c City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 Schedule of Materials Direct Cost Buyout Date Line F IA (August 2026) Description I UNIT I QTY UC $ 71,516,769 1 ALL Generators Quote included. EA 4.00 $ 345,930.25 $ 1,383,721 TBD 2 ALL Architectural/Structural Precast SF 50,635.00 $ 69.00 $ 3,480,545 TBD 3 Miscellaneous Metals 17 ALL Aluminum Covers SF 1,566.00 $ 184.07 $ 288,260 TBD 18 Building Trades(Specialties, Furnishings, Flooring,Drywall,Etc.) 32 ALL Membrane Roofing SF 17,147.00 $ 55.00 $ 943,085 TBD 33 Doors and Frames 34 Overhead Coiling Doors 35 Paintings and Coatings BLS Index ID:PCU3255103255107 See below $ 3,045,921 TBD F/A QTY 1=architectural painting,QTY 2=pipe painting/labeling/stenciling,QTY 3=CRC System 1,QTY 4=CRC System 2,QTY 5=CRC System 3 5 Site 10 Administration Building 12 Maintenance Building 17 Lake Oswego Upstream Junction Structure 18 Lake Oswego Drop Structure 19 City of Portland Drop Structure 20 Influent Pump Station 21 Odor Control(IPS/PDS) 23 Stormwater Pump Station 25 Headworks/Solids Storage/Solids Pumping 26 Odor Control(LODS,Headworks,Solids,Aeration Basin, Filters) City of Lake Oswego Page 1 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing Ads � o OPFGO'. City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 27 Main Electrical Building and Generators 28 Plant Drain Pump Station 30 Aeration Basins 35 Blower Building 40 Clarifiers 41 RAS Pumping 50 Filters 52 TBD 55 UV 56 Plant Effluent Junction Structure 60 Truck Loadout(Normal) 59 ALL Pre-Engineered Metal Buildings 8-10%every 3 months per supplier SF 11,867.00 $ 180.00 $ 2,135,560 TBD 60 Cranes 61 Plumbing 75 HVAC 97 ALL Deep Foundations All three reporting slight increase in rot EA 635.00 $ 7,876.94 $ 5,001,859 TBD 98 Landscaping City of Lake Oswego Page 2 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing OE`A eo s4. � n u c 0,E00. City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 99 Tapani-Labor(Earthwork,Yard Pipe,Concrete) 100 Tapani-Construction Equipment 101 Tapani-Materials 102 Rebar Reinforcing Steel LB 9,881,890.00 $ 0.70 $ 6,917,323 TBD 103 Tlock Liner SF 32,281.00 $ 35.00 $ 1,129,835 TBD 104 Lumber/Form Products SF 1,277,958.00 $ 1.60 $ 2,044,733 TBD 105 Steel Pile Cap Protection EA 511.00 $ 1,100.00 $ 562,100 TBD 106 Readymix Concrete CY 30,194.00 $ 270.69 $ 8,173,214 TBD 107 Grout CY 485.00 $ 225.00 $ 109,125 108 PVC Waterstop LF 45,240.00 $ 12.50 $ 565,375 TBD 109 Precast Concrete LB 1,216,262.00 $ 0.34 $ 413,529 TBD 110 Aggregates-2027 TN 111 Aggregates-2028 TN 50,000.00 $ 30.00 $ 1,500,000 TBD 112 Aggregates-2029 TN 60,000.00 $ 27.00 $ 1,620,000 TBD 113 Aggregates-2030 TN 33,590.00 $ 30.00 $ 1,007,700 TBD 114 HDPE Pipe&Fittings LB 393,420.00 $ 2.00 $ 786,839 TBD 115 PVC Pipe&Fittings LB 116,430.00 $ 1.50 $ 174,626 TBD 116 Ductile Iron Pipe&Fittings LB 405,100.00 $ 3.20 $ 1,296,543 TBD 117 Cathodic Protection LOC 56.00 $ 1,968.75 $ 110,250 TBD 118 Asphalt Paving TN 3,334.00 $ 132.00 $ 440,088 TBD 119 Fencing LF 4,050.00 $ 62.50 $ 253,125 TBD 120 Offroad Diesel-2026 GAL 121 Onroad Diesel-2026 GAL 122 Gas-2026 GAL 123 Offroad Diesel-2027 GAL 30,000.00 $ 4.00 $ 120,000 TBD City of Lake Oswego Page 3 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing OE`A eo s4. � n u c 0,E00. City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 124 Onroad Diesel-2027 GAL 24,000.00 $ 4.00 $ 96,000 TBD 125 Gas-2027 GAL 17,500.00 $ 4.00 $ 70,000 TBD 126 Offroad Diesel-2028 GAL 30,000.00 $ 4.00 $ 120,000 TBD 127 Onroad Diesel-2028 GAL 20,000.00 $ 4.00 $ 80,000 TBD 128 Gas-2028 GAL 15,000.00 $ 4.00 $ 60,000 TBD 129 Offroad Diesel-2029 GAL 30,000.00 $ 4.00 $ 120,000 TBD 130 Onroad Diesel-2029 GAL 20,000.00 $ 4.00 $ 80,000 TBD 131 Gas-2029 GAL 15,000.00 $ 4.00 $ 60,000 TBD 132 Offroad Diesel-2030 GAL 17,500.00 $ 4.00 $ 70,000 TBD 133 Onroad Diesel-2030 GAL 10,050.00 $ 4.00 $ 40,200 TBD 134 Gas-2020 GAL 6,000.00 $ 4.00 $ 24,000 TBD 135 Harder-Labor(Process Mechanical) 136 Harder-Construction Equipment 137 Harder-Materials To be further detailed. 138 DUCTILE IRON FITTINGS EA 1,739.00 $ 1,929.42 $ 3,690,791 TBD 139 DUCTILE IRON MISC EA 33.00 $ 0.01 $ 0 TBD 140 DUCTILE IRON PIPE EA 6,292.00 $ 239.86 $ 1,660,085 TBD 141 DUCTILE IRON SLEEVES EA 96.00 $ 4,257.84 $ 449,628 TBD 142 DUCTILE IRON SUPPORTS EA 3,288.00 $ 349.32 $ 1,263,403 TBD 143 DUCTILE IRON TESTING EA 5,869.00 $ 0.01 $ 82 TBD 144 DUCTILE IRON VALVES EA 247.00 $ 14,713.43 $ 3,997,639 TBD 145 EQUIP EQUIP EA 228.00 $ 55.82 $ 14,000 TBD 146 EQUIP FORMWORK EA 30.15 $ 57.26 $ 1,899 TBD 147 EQUIP GROUT EA 133.70 $ 57.26 $ 8,422 TBD 148 EQUIP MISC EA 2,782.00 $ 75.54 $ 231,180 TBD City of Lake Oswego Page 4 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing 0,4‘)4;:,4 � n ut.I.F, c City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 149 FIXTURES FIXTURES EA 115.00 $ 1,360.45 $ 172,097 TBD 150 FRP FITTINGS EA 389.23 $ 0.01 $ 5 TBD 151 FRP MISC EA 5.00 $ 0.01 $ 0 TBD 152 FRP PIPE EA 1,755.00 $ 0.01 $ 25 TBD 153 FRP SUPPORTS EA 608.00 $ 449.98 $ 300,944 TBD 154 FRP VALVES EA 5.00 $ 0.01 $ 0 TBD 155 HDPE FITTINGS EA 10.00 $ 22.78 $ 251 TBD 156 HDPE PIPE EA 252.00 $ 5.37 $ 1,490 TBD 157 HDPE SUPPORTS EA 1.00 $ 63.62 $ 70 TBD 158 HDPE TESTING EA 30.00 $ 0.01 $ 0 TBD 159 HDPE VALVES EA 7.00 $ 2,665.88 $ 20,527 TBD 160 PVC FITTINGS EA 264.00 $ 99.41 $ 28,869 TBD 161 PVC MISC EA 3.00 $ 2,734.09 $ 9,022 TBD 162 PVC PIPE EA 2,416.00 $ 7.31 $ 19,423 TBD 163 PVC SUPPORTS EA 86.00 $ 663.62 $ 62,779 TBD 164 PVC TESTING EA 2,082.00 $ 0.01 $ 29 TBD 165 PVC VALVES EA 55.00 $ 5,419.23 $ 327,863 TBD 166 SS PIPE FITTINGS EA 521.62 $ 1,304.25 $ 748,350 TBD 167 SS PIPE MISC EA 686.00 $ 0.01 $ 10 TBD 168 SS PIPE PIPE EA 2,675.00 $ 219.82 $ 646,823 TBD 169 SS PIPE SUPPORTS EA 710.00 $ 946.56 $ 739,266 TBD 170 SS PIPE TESTING EA 2,311.00 $ 0.01 $ 32 TBD 171 SS PIPE VALVES EA 81.00 $ 2,320.60 $ 206,765 TBD 172 STEEL RACKING HDG RACKS EA 45.00 $ 16,542.44 $ 818,851 TBD City of Lake Oswego Page 5 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing OE`A eo s4 � n u c 0,E00. City of Lake Oswego WWTF Project BAFO,August 18,2026 08/01/26 173 CEI-Labor(Electrical) 174 CEI-Construction Equipment 175 CEI Materials 176 Detail on second tab-too many rows to include here. LS 1.00 $ 11,163,430.00 $ 11,163,430 TBD City of Lake Oswego Page 6 of 6 WWTF Project DESIGN-BUILD-OPERATE PROPOSAL Escalation Pricing LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material* Material Unit Cost SITE P2,20'-Pole mt.,Single head LED,20'pole 18.00 $ 12,744 $ 708 P3,20'-Pole mt., Double head,90*LED,20'pole 8.00 $ 45,328 $ 5,666 METERED 15KV SW 1.00 $ 156,250 $ 156,250 4000KVA MV XFMR 1.00 $ 250,000 $ 250,000 600KW DIESEL GENSET-OFCI 4.00 $ - $ - 1"GRC 5.00 $ 22 $ 4 1 1/4"GRC 40.00 $ 260 $ 6 2"GRC 40.00 $ 394 $ 10 1"GRC MYERS HUB W/G 1.00 $ 12 $ 12 1 1/4"GRC MYERS HUB W/G 4.00 $ 54 $ 14 2"GRC MYERS HUB W/G 8.00 $ 180 $ 22 1 1/4"GRC COUPLING 4.00 $ 55 $ 14 1"GRC STRUT CLAMP 2.00 $ 2 $ 1 1 1/4"GRC STRUT CLAMP 8.00 $ 8 $ 1 2"GRC STRUT CLAMP 24.00 $ 32 $ 1 3"GRC STRUT CLAMP 64.00 $ 105 $ 2 5"GRC STRUT CLAMP 8.00 $ 46 $ 6 1"GRC CUT&THREAD 1.00 $ - $ - 1 1/4"GRC CUT&THREAD 4.00 $ - $ - 2"GRC CUT&THREAD 8.00 $ - $ - 1 1/4"PVC/CTD 90 ELBOW 44.00 $ 1,568 $ 36 1"PVC BURIED 100.00 $ 44 $ 0 1 1/4"PVC BURIED 2,200.00 $ 1,408 $ 1 2"PVC BURIED 1,320.00 $ 1,214 $ 1 3"PVC BURIED 2,640.00 $ 4,673 $ 2 4"PVC BURIED 13,325.00 $ 32,513 $ 2 5"PVC BURIED 240.00 $ 828 $ 3 1"PVC FEM ADAPTER 1.00 $ 1 $ 1 1 1/4"PVC FEM ADAPTER 22.00 $ 48 $ 2 2"PVC FEM ADAPTER 8.00 $ 22 $ 3 1"PVC COUPLING 4.00 $ 3 $ 1 1 1/4"PVC COUPLING 44.00 $ 56 $ 1 2"PVC COUPLING 32.00 $ 66 $ 2 3"PVC COUPLING 48.00 $ 288 $ 6 4"PVC COUPLING 168.00 $ 1,407 $ 8 5"PVC COUPLING 8.00 $ 171 $ 21 1 PVC EXPANSION CPLG 1.00 $ 24 $ 24 2 PVC EXPANSION CPLG 8.00 $ 302 $ 38 3 PVC EXPANSION CPLG 16.00 $ 1,090 $ 68 4 PVC EXPANSION CPLG 20.00 $ 2,092 $ 105 1"PVC END BELL 1.00 $ 11 $ 11 * Note: References to"Total Material"are to be interpreted as"Direct Cost(August 2026)"for purposes of subsection 7.3(B)(3) of the DBOM Agreement. LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1 1/4"PVC END BELL 22.00 $ 290 $ 13 2"PVC END BELL 8.00 $ 123 $ 15 3"PVC END BELL 32.00 $ 615 $ 19 4"PVC END BELL 232.00 $ 4,316 $ 19 5"PVC END BELL 8.00 $ 290 $ 36 1"PVC CONDUIT PLUG 1.00 $ 2 $ 2 2"PVC CONDUIT PLUG 8.00 $ 15 $ 2 3"PVC CONDUIT PLUG 32.00 $ 75 $ 2 4"PVC CONDUIT PLUG 232.00 $ 682 $ 3 5"PVC CONDUIT PLUG 8.00 $ 31 $ 4 PVC CEMENT(1-QUART) 83.00 $ 3,771 $ 45 2"x3"BASE SPACER 277.00 $ 543 $ 2 3"x3"BASE SPACER 528.00 $ 1,172 $ 2 4"x3"BASE SPACER 2,665.00 $ 6,103 $ 2 5"x3"BASE SPACER 48.00 $ 133 $ 3 1/2"S/S SADDLE WASHER 215.00 $ 290 $ 1 1/4"S/S WASHER 44.00 $ 33 $ 1 3/8"S/S WASHER 1,466.00 $ 1,686 $ 1 1/4"S/S NUT 22.00 $ 6 $ 0 1 5/8"S/S CHANNEL 2,850.00 $ 57,342 $ 20 1/4-20x1" BOLT(SS) 22.00 $ 12 $ 1 3/8-16x1" BOLT(SS) 1,466.00 $ 1,891 $ 1 1/2-13x1" BOLT(SS) 430.00 $ 624 $ 1 1/2-13x2" BOLT(SS) 68.00 $ 345 $ 5 3/8"SS SPRING NUT 1,466.00 $ 13,986 $ 10 1/2"SS SPRING NUT 430.00 $ 4,085 $ 10 STRUT L-JOINER(SS) 108.00 $ 8,583 $ 79 CORNER ANGLE(SS) 549.00 $ 43,629 $ 79 DBL POST BASE(SS) 108.00 $ 30,888 $ 286 #10XHHW 1,650.00 $ 644 $ 0 #14XHHW 11,840.00 $ 2,250 $ 0 #10 XHHW 460.00 $ 179 $ 0 #8XHHW 2,640.00 $ 1,822 $ 1 #6 XHHW 7,260.00 $ 7,623 $ 1 #110 XHHW 2,220.00 $ 7,082 $ 3 #300MCM XHHW 6,660.00 $ 57,276 $ 9 #350MCM XHHW 6,720.00 $ 69,619 $ 10 #6 BARE-CU 220.00 $ 183 $ 1 #410 BARE-CU 6,240.00 $ 42,370 $ 7 #4/0/1C 15KV CU SHLD 133% 240.00 $ 3,156 $ 13 1-H CRIMP LUG#6 BLUE 22.00 $ 107 $ 5 BURIED UTILITY TAPE(3"x1000') 1.00 $ 215 $ 215 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost WIRE MARKER 312.00 $ 624 $ 2 CABLE TAG 204.00 $ 1,020 $ 5 1"X 3"PHENOLIC NAME PLATE 8.00 $ 36 $ 5 2"X 4"PHENOLIC NAME PLATE 1.00 $ 5 $ 5 CONDUIT MEASURING TAPE 13,059.00 $ 409 $ 0 1/4"POLYROPE 2,640.00 $ 297 $ 0 3/8"POLYROPE 12,560.00 $ 3,517 $ 0 # 10 WIRE TERM-POWER 74.00 $ - $ - #1/0 WIRE TERM-POWER 24.00 $ - $ - #300 MCM TERM-POWER 72.00 $ - $ - #350 MCM TERM-POWER 96.00 $ - $ - #14 WIRE TERM-CONTROL 128.00 $ - $ - 410 LDBRK ELB 200A/15KV 2.00 $ 404 $ 202 #410 15KV HV TERMINATION 2.00 $ 918 $ 459 36"AL SOLID TRAY 3"D 2,580.00 $ 247,886 $ 96 36"AL SLD HORZ90 ELB 18.00 $ 7,650 $ 425 36"AL SLD HORZ T SECT 18.00 $ 7,650 $ 425 36"AL SLD VRT90 INSIDE 30.00 $ 12,750 $ 425 36"AL SLD VRT90 OUTSIDE 30.00 $ 12,750 $ 425 36"AL SOLID COVER 2,580.00 $ 38,700 $ 15 36"AL SLD HOR90 ELB COVER 18.00 $ 720 $ 40 36"AL SLD HOR T SECT 18.00 $ 720 $ 40 36"AL SLD VRT90 INSIDE COVER 30.00 $ 1,200 $ 40 36"AL SLD VRT90 OUTSIDE COVER 30.00 $ 1,200 $ 40 36"AL TRAY WALL FLANGE 60.00 $ 22,500 $ 375 AL TRAY EXPANSION JOINT 30.00 $ 5,010 $ 167 3-1/4"SOLID STRUT S/S 2,688.00 $ 101,580 $ 38 1/2 ANCHOR S/S 713.00 $ 16,492 $ 23 1/2" LOCK WASHER S/S 68.00 $ 145 $ 2 1/2" FENDER WASHER S/S 283.00 $ 603 $ 2 GEN TESTING 4.00 $ - $ - GEN COMMISSIONING 4.00 $ - $ - 518"x10'CU CLAD GRD ROD 22.00 $ 1,013 $ 46 5/8 GRD ROD CLAMP 22.00 $ 113 $ 5 CADWELD 4/0 CABLE TEE/WYE 12.00 $ - $ - #150 CADWELD METAL 12.00 $ 321 $ 27 CONC TEST WELL 22.00 $ 2,530 $ 115 CONC TEST WELL COVER 22.00 $ 990 $ 45 FUSE HOLDER 66.00 $ 1,584 $ 24 20'STEEL POLE(INCLUDED W/FIXTURE PRICE) 22.00 $ - $ - 3030-LA(2'X2'X2') 10.00 $ 7,710 $ 771 CAT6 WP CABLE 740.00 $ 324 $ 0 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost CAT6 TERM 8.00 $ 32 $ 4 Copper Link Test Category 6 4.00 $ - $ - 12-24-FO CABLE PREP-UNFILLED 32.00 $ 972 $ 30 24-48-FO CABLE PREP-FANOUT 10.00 $ 304 $ 30 LC FO TERM-ANAEROBIC 864.00 $ 6,972 $ 8 CONDUIT TAGS 234.00 $ 2,340 $ 10 Cable Tray>Strut-Clamp 645.00 $ 3,864 $ 6 SPYDER BOX W/CORD 25.00 $ 32,425 $ 1,297 DUCTBANKRACKANCHOR 1,185.00 $ 11,850 $ 10 3"FIBERGLASS 36"SWEEP 48.00 $ 7,759 $ 162 4"FIBERGLASS 36"SWEEP 324.00 $ 65,662 $ 203 5"FIBERGLASS 48"SWEEP 12.00 $ 4,923 $ 410 CUT UTILITIES BACK TO 5FT FROM SITE BOUNDARY 4.00 $ - $ - 1"FIBERGLASS 90 4.00 $ 216 $ 54 2"X12"R FIBERGLASS 90 32.00 $ 2,126 $ 66 WIRE TESTING(PER CONDUCTOR) 100.00 $ - $ - SMFO-12STR 4,875.00 $ 3,169 $ 1 SMFO-48STR 1,735.00 $ 10,913 $ 6 1-1/4"HDPE INTERDUCT 26,805.00 $ 27,609 $ 1 TEMP TRAILER POWER 12.00 $ 54,000 $ 4,500 10 ADMIN BLDG A-2x4 LED Troffer w/whip 47.00 $ 16,779 $ 357 AE-2x4 LED Troffer w/em ballast and whip 17.00 $ 15,895 $ 935 B-4'Wrap,Surface Mt. 7.00 $ 1,253 $ 179 BE-4'Wrap, Surface M.t w/Em Ballast 2.00 $ 1,154 $ 577 C-6"Recessed Downlight 4.00 $ 1,864 $ 466 D-Vanity Fixture,Wall Mt. 3.00 $ 1,545 $ 515 F-6"Recessed Down Light,Wet Location 9.00 $ 2,871 $ 319 G-18"Under Cabinet Light 3.00 $ 957 $ 319 W-Exterior Wall Pack 7.00 $ 4,298 $ 614 WE-Exterior Wall Pack w/Em. Ballast 3.00 $ 2,313 $ 771 X-Exit Sign,Wall Mt. 8.00 $ 3,728 $ 466 XC-Exit Sign,Ceiling Mt. 3.00 $ 1,032 $ 344 10-PNL-001-01 225A 480V 1.00 $ 22,986 $ 22,986 10-UPS-001-01 UPS 8KVA 208/120V W/MBS 1.00 $ 36,405 $ 36,405 10-MBS 30A($$included with UPS) 1.00 $ - $ - 10-XFMR-001-01 45KVA 480-208/120V 1.00 $ 3,595 $ 3,595 10-PNL-001-02 125A 208/120V 1.00 $ 4,066 $ 4,066 10-PNL-001-03 60A 208/120V 1.00 $ 3,956 $ 3,956 3/4"EMT 3,280.00 $ 2,755 $ 1 1"EMT 500.00 $ 710 $ 1 1 1/4"EMT 60.00 $ 146 $ 2 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 2"EMT 10.00 $ 35 $ 3 3/4"EMT STL COMP CONN 368.00 $ 2,675 $ 7 1"EMT STL COMP CONN 64.00 $ 689 $ 11 1 1/4"EMT STL COMP CONN 12.00 $ 330 $ 27 2"EMT STL COMP CONN 4.00 $ 186 $ 46 3/4"EMT STL COMP CPLG 352.00 $ 1,365 $ 4 1"EMT STL COMP CPLG 20.00 $ 116 $ 6 1 1/4"EMT STL COMP CPLG 6.00 $ 78 $ 13 3/4"EMT STRAP 1-H 230.00 $ 132 $ 1 1"EMT STRAP 1-H 8.00 $ 5 $ 1 1 1/4"EMT STRAP 1-H 6.00 $ 6 $ 1 2"EMT STRUT CLAMP 2.00 $ 6 $ 3 1-IN INSULATING BUSHING 12.00 $ 7 $ 1 2-IN INSULATING BUSHING 6.00 $ 11 $ 2 4-IN INSULATING BUSHING 6.00 $ 45 $ 7 3/4"GRC 60.00 $ 182 $ 3 1 1/2"GRC 5.00 $ 37 $ 7 3/4"GRC MYERS HUB W/G 12.00 $ 111 $ 9 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 3/4"GRC COUPLING 9.00 $ 62 $ 7 1 1/4"GRC COUPLING 4.00 $ 55 $ 14 1 1/2"GRC COUPLING 1.00 $ 18 $ 18 3/4"GRC T CONDULET 10.00 $ 206 $ 21 3/4" COVER 10.00 $ 50 $ 5 3/4"NEOPRENE GASKET 10.00 $ 43 $ 4 3/4"GRC 90 ELBOW 8.00 $ 157 $ 20 1 1/4"GRC 90 ELBOW 8.00 $ 343 $ 43 3/4"STEEL LOCKNUT 8.00 $ 5 $ 1 1 1/4"STEEL LOCKNUT 8.00 $ 11 $ 1 3/4"INS STL GRD BUSHING 11.00 $ 65 $ 6 1"PLASTIC BUSHING 34.00 $ 17 $ 0 3/4x 1/2 RED BUSHING 10.00 $ 43 $ 4 3/4"GRC STRUT CLAMP 12.00 $ 9 $ 1 1 1/2"GRC STRUT CLAMP 1.00 $ 1 $ 1 3/4"GRC CUT&THREAD 4.00 $ - $ - 1 1/2"GRC CUT&THREAD 1.00 $ - $ - 1"PVC BURIED 60.00 $ 26 $ 0 1 1/4"PVC BURIED 60.00 $ 38 $ 1 3/4"PVC T.A. 8.00 $ 8 $ 1 1 1/4"PVC T.A. 8.00 $ 14 $ 2 1 1/4"PVC FEM ADAPTER 4.00 $ 9 $ 2 3/4"PVC COUPLING 16.00 $ 9 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1 1/4"PVC COUPLING 16.00 $ 20 $ 1 3/4"ALUMINUM FLEX 182.00 $ 247 $ 1 3/4"STR FLEX CONN 17.00 $ 48 $ 3 1/2"LT FLEX 40.00 $ 34 $ 1 3/4"LT FLEX 17.00 $ 23 $ 1 1 1/2"LT FLEX 5.00 $ 20 $ 4 1/2"LT STRAIGHT CONN 10.00 $ 73 $ 7 3/4"LT STRAIGHT CONN 5.00 $ 53 $ 11 1 1/2"LT STRAIGHT CONN 1.00 $ 43 $ 43 1/2"LT 90DEG CONN 10.00 $ 124 $ 12 3/4"LT 90DEG CONN 5.00 $ 96 $ 19 1 1/2"LT 90DEG CONN 1.00 $ 88 $ 88 3/8"S/S CONCRETE ANCHOR 90.00 $ 826 $ 9 1/2"S/S CONCRETE ANCHOR 40.00 $ 925 $ 23 1/2"S/S SADDLE WASHER 45.00 $ 61 $ 1 1/4"S/S WASHER 46.00 $ 35 $ 1 3/8"S/S WASHER 237.00 $ 273 $ 1 1/2"S/S WASHER 80.00 $ 170 $ 2 1/2"S/S NUT 80.00 $ 98 $ 1 1/2"S/S ALL THREAD 250.00 $ 2,175 $ 9 1 5/8"S/S CHANNEL 190.00 $ 3,823 $ 20 3/8-16x1" BOLT(SS) 153.00 $ 197 $ 1 1/4"SS SPRING NUT 36.00 $ 167 $ 5 3/8"SS SPRING NUT 45.00 $ 429 $ 10 STRUT L-JOINER(SS) 72.00 $ 5,722 $ 79 CORNER ANGLE(SS) 18.00 $ 1,430 $ 79 #10 XHHW 120.00 $ 47 $ 0 #12 XHHW 14,076.00 $ 3,660 $ 0 #10XHHW 1,131.00 $ 441 $ 0 #6 XHHW 400.00 $ 420 $ 1 #1 XHHW 100.00 $ 260 $ 3 #410 BARE-CU 625.00 $ 4,244 $ 7 18/3 LVT STAT CABLE 60.00 $ 18 $ 0 RG-6/U CABLE 50.00 $ 13 $ 0 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 RED WIRE NUT 703.00 $ 128 $ 0 WIRE MARKER 500.00 $ 1,000 $ 2 1"X 3"PHENOLIC NAME PLATE 6.00 $ 27 $ 5 POLYTWINE 450.00 $ 6 $ 0 # 12 WIRE TERM-POWER 604.00 $ - $ - # 10 WIRE TERM-POWER 76.00 $ - $ - # 6 WIRE TERM-POWER 32.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost # 1 WIRE TERM-POWER 8.00 $ - $ - 4x1-1/2"SQ BOX COMB KO 221.00 $ 449 $ 2 4x2-1/8"SQ BOX COMB KO 115.00 $ 291 $ 3 4"SQ BLANK COVER 185.00 $ 122 $ 1 4"SQ 1G PL-RING 1/2"RISE 73.00 $ 83 $ 1 4"SQ 1G PL-RING 3/4"RISE 39.00 $ 51 $ 1 4"SQ 2G PL-RING 1/2"RISE 8.00 $ 9 $ 1 4"SQ 2G PL-RING 3/4"RISE 5.00 $ 10 $ 2 4"SQ 1-TOGGLE SWITCH COVER 1.00 $ 3 $ 3 4-11/16x2-1/8"SQ BOX COMB KO 8.00 $ 33 $ 4 4-11/16x2-1/8"SQ BOX 1"KO 4.00 $ 20 $ 5 4-11/16x2-1/8"SQ BOX 1-1/4"KO 2.00 $ 14 $ 7 4-11/16"SQ BLANK COVER 8.00 $ 12 $ 1 4-11/16"SQ 1G PL-RING 1/2"RISE 2.00 $ 8 $ 4 1G MAS-BOX 2-1/2"DEEP 4.00 $ 100 $ 25 GROUND SCREW W/INSUL#12 LEAD 37.00 $ 149 $ 4 24x20x 9 NEMA1 CABINET 1.00 $ 290 $ 290 S3825 RECT DUP REC PLT 4.00 $ 400 $ 100 B4233 2G DEEP ADJ FLOOR BOX 4.00 $ 1,092 $ 273 SB3084 2G RECT CARPET FLANGE 4.00 $ 702 $ 176 S2425 RECT COMM PLT 4.00 $ 243 $ 61 18"AL LADDER TRAY 6R 3D 50.00 $ 1,249 $ 25 18"AL LADD HORZ90 ELB 4.00 $ 783 $ 196 36"AL SOLID TRAY 3"D 180.00 $ 17,294 $ 96 36"AL SLD HORZ90 ELB 2.00 $ 850 $ 425 36"AL SLD VRT90 INSIDE 4.00 $ 1,700 $ 425 36"AL SLD VRT90 OUTSIDE 4.00 $ 1,700 $ 425 36"AL SLD HOR90 ELB COVER 2.00 $ 80 $ 40 36"AL SLD VRT90 INSIDE COVER 4.00 $ 160 $ 40 36"AL SLD VRT90 OUTSIDE COVER 4.00 $ 160 $ 40 18"AL TRAY CABLE DROP-OUT 4.00 $ 1,088 $ 272 18"AL TRAY WALL FLANGE 4.00 $ 2,265 $ 566 36"AL TRAY WALL FLANGE 4.00 $ 1,500 $ 375 AL TRAY DIVIDER 90.00 $ 1,080 $ 12 AL TRAY EXPANSION JOINT 2.00 $ 334 $ 167 4"x4"WIREWAY 2'PC 1.00 $ 58 $ 58 4"WW END PLATE 2.00 $ 41 $ 20 20A 120-277V S/P SW(SG) 20.00 $ 101 $ 5 20A 120-277V 3/W SW(SG) 2.00 $ 10 $ 5 WATTSTOPPER BZ-100 120/277VAC POWER PACK 3.00 $ 99 $ 33 W-500A CEILING OCCUPANCY SENSOR 3.00 $ 367 $ 122 WA-200 120/277V AUTO WALL SW 10.00 $ 895 $ 90 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost WA-200 120/277V AUTO WALL SW 1.00 $ 90 $ 90 20A 125V GFI DUP REC(SG) 11.00 $ 109 $ 10 30A 250V 3W 1 PH REC(SG) 1.00 $ 10 $ 10 20A 125V DUPLEX REC(SG) 60.00 $ 270 $ 5 1G DECOR PLATE PLASTIC 10.00 $ 12 $ 1 1G PLASTIC SWITCH PLATE 12.00 $ 9 $ 1 2G PLASTIC SWITCH PLATE 4.00 $ 6 $ 2 2G S/S SWITCH PLATE 1.00 $ 2 $ 2 1G S/S DUP REC PLATE 40.00 $ 36 $ 1 2G S/S 2xSINGLE REC PLATE 8.00 $ 44 $ 5 1G S/S 1.937"DIAM REC PLATE 1.00 $ 10 $ 10 1G S/S GFCI WALL PLATE 11.00 $ 15 $ 1 CCTV OUTSIDE-WALL CAMERA 2.00 $ 3,600 $ 1,800 CCTV CAMERA WALL BRACKET 2.00 $ 50 $ 25 CARD READER W/CONTROL 2.00 $ 9,000 $ 4,500 1 5/8"SLOTTED STRUT S/S 425.00 $ 8,551 $ 20 3-1/4"SOLID STRUT S/S 113.00 $ 4,270 $ 38 3/8"SPRING NUT S/S 74.00 $ 706 $ 10 #6-8 PL ANCHOR W/SCREW(3/16) 28.00 $ 3 $ 0 3/8"WEDGE ANCHOR S/S 36.00 $ 330 $ 9 1/2"WEDGE ANCHOR 18.00 $ 44 $ 2 1/2 ANCHOR S/S 27.00 $ 625 $ 23 3/8-16x1" BOLT S/S 102.00 $ 132 $ 1 1/2-13x2" BOLT S/S 4.00 $ 20 $ 5 3/8-16 HEX NUT S/S 28.00 $ 15 $ 1 1/2-13 HEX NUT S/S 90.00 $ 110 $ 1 3/8" FLAT WASHER S/S 36.00 $ 41 $ 1 3/8" LOCK WASHER S/S 224.00 $ 258 $ 1 1/2" LOCK WASHER S/S 4.00 $ 9 $ 2 3/8" FENDER WASHER S/S 112.00 $ 129 $ 1 1/2" FENDER WASHER S/S 49.00 $ 104 $ 2 #6x 3/8"S-TAP SCREW F/H 150.00 $ 11 $ 0 #6x 1/2"S-TAP SCREW F/H 15.00 $ 2 $ 0 #10x 3/4"S-TAP SCREW F/H 16.00 $ 3 $ 0 #10x1" S-TAP SCREW F/H 6.00 $ 1 $ 0 #6x 3/8"S-TAP SCREW P/H 8.00 $ 1 $ 0 #8x 3/4"S-TAP SCREW P/H 52.00 $ 6 $ 0 #10x 3/4"S-TAP SCREW P/H 20.00 $ 3 $ 0 #10x1" S-TAP SCREW P/H 430.00 $ 55 $ 0 TY-526M T&B TY-RAP(11") 102.00 $ 36 $ 0 TY-528M T&B TY-RAP(14") 100.00 $ 84 $ 1 WIRE HANGER&HILTI SHOT 341.00 $ 42 $ 0 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 350 M/STUD BOX SUPP 60.00 $ 42 $ 1 766 FAR SIDE BOX SUPP 70.00 $ 32 $ 0 MFS ADJ BOX SUPPORT 10.00 $ 22 $ 2 MSF STUD BOX SUPPORT 26.00 $ 50 $ 2 4Z34 DROP WIRE CLIP 30.00 $ 24 $ 1 CS812 STUD ATTACH ASSEMBLY 52.00 $ 49 $ 1 K-8 KON CLIP(1/2") 9.00 $ 5 $ 1 K-12 KON CLIP(3/4") 232.00 $ 127 $ 1 K-16 KON CLIP(1") 25.00 $ 24 $ 1 4ACS T-BAR BOX SUPP 64.00 $ 71 $ 1 512 T-BAR BOX HANGER 24" 3.00 $ 40 $ 13 517A HI-HAT T-BAR HANGER 25.00 $ 386 $ 15 4WN WING NUT 74.00 $ 32 $ 0 20A 4P 600V LIGHTING CONTACTOR(1) 2.00 $ 1,184 $ 592 24HR SPST 277V TIME SW 1.00 $ 274 $ 274 120V PHOTOCONTROL K4141 1.00 $ 13 $ 13 BPB TESTING 2.00 $ - $ - BPB COMMISSIONING 2.00 $ - $ - 30A/250V 1P FUSIBLE NEMA1 5.00 $ 1,042 $ 208 30A/250V 3P FUSIBLE NEMA1 5.00 $ 978 $ 196 30A/250V 3P FUSIBLE NEMA3R 4.00 $ 1,065 $ 266 30A/600V 3P NON FUS NEMA1 1.00 $ 200 $ 200 15A 250V RK1 TD FUSE 27.00 $ 531 $ 20 XMER TESTING 1.00 $ - $ - XMER COMMISSIONING 1.00 $ - $ - 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 GRND SCR W/12SOL PIGTAIL 192.00 $ 70 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 2/C#12 6'FIXTURE WHIP 103.00 $ 26 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 22.00 $ - $ - Core Drill layout 4.00 $ - $ - WALL SLEEVE 2" 4.00 $ 84 $ 21 CAT6 CABLE 5,500.00 $ 1,375 $ 0 CAT6 MODULE 48.00 $ 34 $ 1 CAT6 MODULE 24.00 $ 39 $ 2 CAT6 CABLE 58.00 $ 15,660 $ 270 Copper Link Test Category 6 29.00 $ - $ - CONDUIT TAGS 5.00 $ 50 $ 10 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost FA SYSTEM PER SQ FT 5,164.00 $ 9,626 $ 2 CABLE TRAY PASS-THRU GND LUG 18.00 $ 378 $ 21 Cable Tray>Strut-Clamp 45.00 $ 270 $ 6 SEISMIC BRACE 22.00 $ 5,830 $ 265 UPS TEST&COMMISSIONG 1.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 25.00 $ - $ - Retractable Power Reel with Quad Industrial Receptacle,20 Amp, 115 Volt 3.00 $ 1,985 $ 662 INSTALL SERVER ROOM RACKS AND COMMISIONING 1.00 $ 50 $ 50 SLEEVE 4" 3.00 $ 342 $ 114 SLEEVE 2" 3.00 $ 156 $ 52 SLEEVE 1" 6.00 $ 237 $ 39 CAT HP2 J HOOK W MFC WIRE HUNG 51.00 $ 351 $ 7 4 Element Access Control Cable 18-04+22-3P+22-02+22-04 Plenum Yellow 500.00 $ 508 $ 1 INSTALL ACCESS CONTROL PANEL 1.00 $ 5,400 $ 5,400 AV ADD FOR CONFERANCE ROOM 1.00 $ 5,000 $ 5,000 49.2'HDMI Cable 2.00 $ 142 $ 71 36"SLOPED TRAY COVER-LF 90.00 $ 2,250 $ 25 STRAIGHT SECT.COVERS 36"W-LF 90.00 $ 4,050 $ 45 12 MAINT SHOP B-4'Wrap,Surface Mt. 1.00 $ 179 $ 179 D-Vanity Fixture,Wall Mt. 1.00 $ 515 $ 515 W-Exterior Wall Pack 7.00 $ 4,298 $ 614 WE-Exterior Wall Pack w/Em. Ballast 3.00 $ 2,313 $ 771 E-Em.Bug-eye 5.00 $ 1,820 $ 364 H-Highbay LED, Damp Loc.,Suspended 32.00 $ 5,632 $ 176 XD-Exit Sign,Wall Mt, Damp Location 2.00 $ 352 $ 176 12-PNL-001-01 225A 480V 1.00 $ 12,197 $ 12,197 12-XFMR-001-01 45KVA 1.00 $ 3,595 $ 3,595 12-PNL-001-02 125A 208/120V 1.00 $ 4,385 $ 4,385 2"EMT 10.00 $ 35 $ 3 2"EMT STL COMP CONN 4.00 $ 186 $ 46 2"EMT STRUT CLAMP 2.00 $ 6 $ 3 3/4"GRC 2,661.00 $ 8,089 $ 3 1"GRC 370.00 $ 1,635 $ 4 1 1/2"GRC 5.00 $ 37 $ 7 2"GRC 60.00 $ 590 $ 10 3/4"GRC MYERS HUB W/G 3.00 $ 28 $ 9 1"GRC MYERS HUB W/G 8.00 $ 93 $ 12 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 2"GRC MYERS HUB W/G 4.00 $ 90 $ 22 3/4"GRC COUPLING 1.00 $ 7 $ 7 1 1/2"GRC COUPLING 1.00 $ 18 $ 18 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/4"GRC ERICKSON CPLG 8.00 $ 146 $ 18 1"GRC ERICKSON CPLG 2.00 $ 45 $ 22 3/4"GRC LB CONDULET 17.00 $ 278 $ 16 1"GRC LB CONDULET 2.00 $ 49 $ 25 3/4"GRC T CONDULET 68.00 $ 1,397 $ 21 1"GRC T CONDULET 6.00 $ 187 $ 31 3/4" COVER 54.00 $ 272 $ 5 3/4"NEOPRENE GASKET 54.00 $ 231 $ 4 3/4"STEEL LOCKNUT 58.00 $ 33 $ 1 3/4"INS STL GRD BUSHING 17.00 $ 101 $ 6 2" INS STL GRD BUSHING 4.00 $ 46 $ 12 3/4x 1/2 RED BUSHING 42.00 $ 180 $ 4 1 x 3/4 RED BUSHING 6.00 $ 47 $ 8 3/4" 1-H MALL STRAP 3.00 $ 7 $ 2 3/4"GRC STRUT CLAMP 231.00 $ 179 $ 1 1"GRC STRUT CLAMP 46.00 $ 41 $ 1 1 1/2"GRC STRUT CLAMP 1.00 $ 1 $ 1 2"GRC STRUT CLAMP 5.00 $ 7 $ 1 3/4"CLAMP BACK 3.00 $ 5 $ 2 3/4"2-H STEEL STRAP 84.00 $ 41 $ 0 3/4"xCLOSE NIPPLE 6.00 $ 28 $ 5 3/4"GRC CUT&THREAD 153.00 $ - $ - 1"GRC CUT&THREAD 9.00 $ - $ - 1 1/2"GRC CUT&THREAD 1.00 $ - $ - 2"GRC CUT&THREAD 3.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 31.00 $ - $ - 2"GRC 90 FIELD BEND 2.00 $ - $ - 1/2"LT FLEX 168.00 $ 143 $ 1 3/4"LT FLEX 5.00 $ 7 $ 1 1 1/2"LT FLEX 5.00 $ 20 $ 4 1/2"LT STRAIGHT CONN 42.00 $ 307 $ 7 3/4"LT STRAIGHT CONN 1.00 $ 11 $ 11 1 1/2"LT STRAIGHT CONN 1.00 $ 43 $ 43 1/2"LT 90DEG CONN 42.00 $ 520 $ 12 3/4"LT 90DEG CONN 1.00 $ 19 $ 19 1 1/2"LT 90DEG CONN 1.00 $ 88 $ 88 3/4"STEEL FLEX 48.00 $ 71 $ 1 3/4"STL FLEX CONN 32.00 $ 109 $ 3 1/4"S/S CONCRETE ANCHOR 4.00 $ 30 $ 7 3/8"S/S CONCRETE ANCHOR 49.00 $ 450 $ 9 1/2"S/S SADDLE WASHER 63.00 $ 85 $ 1 1/4"S/S WASHER 82.00 $ 62 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8"S/S WASHER 194.00 $ 223 $ 1 3/8"S/S NUT 34.00 $ 18 $ 1 3/8"S/S ALL THREAD 63.00 $ 275 $ 4 1/2"S/S ALL THREAD 125.00 $ 1,088 $ 9 1 5/8"S/S CHANNEL 163.00 $ 3,280 $ 20 1/4-20x1" BOLT(SS) 4.00 $ 2 $ 1 1/4-20X2" BOLT(SS) 11.00 $ 15 $ 1 3/8-16x1" BOLT(SS) 183.00 $ 236 $ 1 1/4"SS SPRING NUT 20.00 $ 93 $ 5 3/8"SS SPRING NUT 63.00 $ 601 $ 10 STRUT L-JOINER(SS) 100.00 $ 7,947 $ 79 CORNER ANGLE(SS) 50.00 $ 3,974 $ 79 #14 XHHW 640.00 $ 122 $ 0 #10 XHHW 120.00 $ 47 $ 0 #12 XHHW 9,854.00 $ 2,562 $ 0 #10XHHW 3,636.00 $ 1,418 $ 0 #6 XHHW 555.00 $ 583 $ 1 #4 XHHW 375.00 $ 559 $ 1 #1 XHHW 100.00 $ 260 $ 3 #310 XHHW 1,365.00 $ 7,043 $ 5 #410 XHHW 1,125.00 $ 7,279 $ 6 #4 BARE-CU 6.00 $ 8 $ 1 #410 BARE-CU 713.00 $ 4,841 $ 7 #2 MECH-LUG 2.00 $ 4 $ 2 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 RED WIRE NUT 364.00 $ 66 $ 0 RED WIRE NUT 20.00 $ 8 $ 0 WIRE MARKER 316.00 $ 632 $ 2 CABLE TAG 12.00 $ 60 $ 5 1"X 3"PHENOLIC NAME PLATE 3.00 $ 14 $ 5 CONDUIT MEASURING TAPE 36.00 $ 1 $ 0 POLYTWINE 135.00 $ 2 $ 0 # 12 WIRE TERM-POWER 412.00 $ - $ - # 10 WIRE TERM-POWER 40.00 $ - $ - # 6 WIRE TERM-POWER 10.00 $ - $ - # 4 WIRE TERM-POWER 2.00 $ - $ - # 1 WIRE TERM-POWER 8.00 $ - $ - #3/0 WIRE TERM-POWER 6.00 $ - $ - #4/0 WIRE TERM-POWER 6.00 $ - $ - #24 WIRE TERM-CONTROL 16.00 $ - $ - #22 WIRE TERM-CONTROL 32.00 $ - $ - #18 WIRE TERM-CONTROL 8.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 4x1-1/2"SQ BOX COMB KO 7.00 $ 14 $ 2 4x2-1/8"SQ BOX COMB KO 64.00 $ 162 $ 3 4"SQ BLANK COVER 27.00 $ 18 $ 1 4"SQ 1G PL-RING 1/2"RISE 41.00 $ 46 $ 1 4"SQ 1G PL-RING 3/4"RISE 2.00 $ 3 $ 1 GROUND SCREW W/INSUL#12 LEAD 61.00 $ 246 $ 4 FD 1GANG BOX 9.00 $ 285 $ 32 FD 2GANG BOX 4.00 $ 228 $ 57 1G FS/FD SW COVER-STAMPED 1.00 $ 7 $ 7 2G TOGGLE SWITCH-STAMPED CVR 4.00 $ 42 $ 11 A-SE12x12x6 SCR CVR NEMA1 1.00 $ 63 $ 63 36"AL SOLID TRAY 3"D 250.00 $ 24,020 $ 96 36"AL SLD HORZ90 ELB 2.00 $ 850 $ 425 36"AL SLD HORZ T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE 2.00 $ 850 $ 425 36"AL SLD VRT90 OUTSIDE 2.00 $ 850 $ 425 36"AL SLD HOR90 ELB COVER 2.00 $ 80 $ 40 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 2.00 $ 80 $ 40 36"AL SLD VRT90 OUTSIDE COVER 2.00 $ 80 $ 40 36"AL TRAY WALL FLANGE 8.00 $ 3,000 $ 375 AL TRAY DIVIDER 125.00 $ 1,500 $ 12 AL TRAY EXPANSION JOINT 2.00 $ 334 $ 167 4"x4"WIREWAY 2'PC 1.00 $ 58 $ 58 4"WW END PLATE 2.00 $ 41 $ 20 20A 120-277V S/P SW(SG) 5.00 $ 25 $ 5 20A 120-277V 3/W SW(SG) 8.00 $ 40 $ 5 WA-200 120/277V AUTO WALL SW 1.00 $ 90 $ 90 20A 125V GFI DUP REC(SG) 28.00 $ 279 $ 10 30A 250V 3W 1 PH REC(SG) 1.00 $ 10 $ 10 1G S/S SWITCH PLATE 2.00 $ 2 $ 1 2G S/S DUP REC PLATE 7.00 $ 13 $ 2 1G S/S 2.109"DIAM REC PLATE 1.00 $ 3 $ 3 1G S/S GFCI WALL PLATE 21.00 $ 29 $ 1 CCTV OUTSIDE-WALL CAMERA 2.00 $ 3,600 $ 1,800 CCTV CAMERA WALL BRACKET 2.00 $ 50 $ 25 CARD READER W/CONTROL 2.00 $ 9,000 $ 4,500 1 5/8"SLOTTED STRUT S/S 634.00 $ 12,756 $ 20 3-1/4"SOLID STRUT S/S 156.00 $ 5,895 $ 38 3/8"SPRING NUT S/S 121.00 $ 1,154 $ 10 #6-8 PL ANCHOR W/SCREW(3/16) 12.00 $ 1 $ 0 3/8"WEDGE ANCHOR S/S 10.00 $ 92 $ 9 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/2"WEDGE ANCHOR 38.00 $ 93 $ 2 1/2 ANCHOR S/S 35.00 $ 810 $ 23 1/4"DRILL&TAP F/SCREW 2.00 $ - $ - 3/8-16x1" BOLT S/S 151.00 $ 195 $ 1 1/2-13x2" BOLT S/S 4.00 $ 20 $ 5 3/8-16 HEX NUT S/S 32.00 $ 17 $ 1 1/2-13 HEX NUT S/S 125.00 $ 153 $ 1 3/8" FLAT WASHER S/S 36.00 $ 41 $ 1 3/8" LOCK WASHER S/S 289.00 $ 332 $ 1 1/2" LOCK WASHER S/S 4.00 $ 9 $ 2 3/8" FENDER WASHER S/S 158.00 $ 182 $ 1 1/2" FENDER WASHER S/S 67.00 $ 143 $ 2 #6x 1/2"S-TAP SCREW F/H 6.00 $ 1 $ 0 #8x 1/2"S-TAP SCREW P/H 444.00 $ 54 $ 0 #10x1" S-TAP SCREW P/H 12.00 $ 2 $ 0 #14x1-1/4"S-TAP SCREW P/H 43.00 $ 10 $ 0 TY-524M T&B TY-RAP(5") 166.00 $ 53 $ 0 TY-525M T&B TY-RAP(7") 498.00 $ 119 $ 0 TSGB16 BOX BRACKET 29.00 $ 160 $ 6 517A HI-HAT T-BAR HANGER 1.00 $ 15 $ 15 20A4P 600V LIGHTING CONTACTOR(1) 1.00 $ 592 $ 592 24HR SPST 277V TIME SW 1.00 $ 274 $ 274 120V PHOTOCONTROL K4141 1.00 $ 13 $ 13 BPB TESTING 2.00 $ - $ - BPB COMMISSIONING 2.00 $ - $ - 30AI250V 1P NON FUS NEMA1 19.00 $ 4,174 $ 220 30A/600V 3P NON FUS NEMA1 1.00 $ 200 $ 200 XMER TESTING 1.00 $ - $ - XMER COMMISSIONING 1.00 $ - $ - 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 GRND SCR W/12SOL PIGTAIL 7.00 $ 3 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 FIXTURE HOOK 64.00 $ 640 $ 10 2/C#12 6'FIXTURE WHIP 7.00 $ 2 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 3.00 $ - $ - CAT6 CABLE 758.00 $ 190 $ 0 CAT6 CABLE 8.00 $ 2,160 $ 270 Copper Link Test Category 6 4.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost CONDUIT TAGS 6.00 $ 60 $ 10 CABLE TRAY PASS-THRU GND LUG 25.00 $ 525 $ 21 Cable Tray>Strut-Clamp 63.00 $ 377 $ 6 SEISMIC BRACE 38.00 $ 10,070 $ 265 SEISMIC-SUPPORT ARM 16.00 $ 880 $ 55 WIRE TESTING(PER CONDUCTOR) 17.00 $ - $ - 4 Element Access Control Cable 18-04+22-3P+22-02+22-04 Plenum Yellow 140.00 $ 142 $ 1 INSTALL ACCESS CONTROL PANEL 1.00 $ 5,400 $ 5,400 FIXTURE DEFLECTION CABLE 64.00 $ 2,240 $ 35 36"SLOPED TRAY COVER-LF 125.00 $ 3,125 $ 25 STRAIGHT SECT.COVERS 36"W-LF 125.00 $ 5,625 $ 45 20 INFLUENT PUMP STATION P2,20'-Pole mt.,Single head LED,20'pole 6.00 $ 4,248 $ 708 20-LCP-001 20x20x10 NEMA 4X-OFCI 1.00 $ - $ - 20-INF-LCS OFCI 7.00 $ - $ - 20-LCP-002 20x20x10 NEMA 4X-OFCI 1.00 $ - $ - 1"GRC 380.00 $ 1,680 $ 4 3"GRC 800.00 $ 15,376 $ 19 1"GRC MYERS HUB W/G 13.00 $ 151 $ 12 3"GRC MYERS HUB W/G 20.00 $ 1,164 $ 58 1"GRC COUPLING 12.00 $ 119 $ 10 3"GRC COUPLING 40.00 $ 2,970 $ 74 1"GRC LB CONDULET 4.00 $ 99 $ 25 3"GRC LB CONDULET 10.00 $ 2,327 $ 233 1" COVER 4.00 $ 28 $ 7 1"NEOPRENE GASKET 4.00 $ 23 $ 6 1" INS STL GRD BUSHING 4.00 $ 27 $ 7 1 x 1/2 RED BUSHING 4.00 $ 34 $ 8 1"GRC STRUT CLAMP 42.00 $ 37 $ 1 3"GRC STRUT CLAMP 1,630.00 $ 2,664 $ 2 3/4"EYS-26 (C-H) 2.00 $ 56 $ 28 3/4"x8"ECGJH-28 (C-H) 13.00 $ 2,997 $ 231 1"x8"ECGJH-38 (C-H) 8.00 $ 3,542 $ 443 3/4"GRC CUT&THREAD 26.00 $ - $ - 1"GRC CUT&THREAD 35.00 $ - $ - 3"GRC CUT&THREAD 60.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 16.00 $ - $ - 3"GRC 90 FIELD BEND 50.00 $ - $ - 3/4"PVC COATED GRC 520.00 $ 3,546 $ 7 1"PVC COATED GRC 200.00 $ 1,766 $ 9 3"PVC COATED GRC 400.00 $ 13,560 $ 34 3/4"PVC/CTD KO HUB CONN 26.00 $ 1,825 $ 70 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"PVC/CTD KO HUB CONN W/G 15.00 $ 1,126 $ 75 3"PVC/CTD KO HUB CONN W/G 20.00 $ 5,664 $ 283 3/4"PVC/CTD GRC CPLG 26.00 $ 185 $ 7 1"PVC/CTD GRC CPLG 11.00 $ 102 $ 9 3"PVC/CTD GRC CPLG 20.00 $ 1,125 $ 56 3/4"PVC COATED LB FORM 7 13.00 $ 931 $ 72 1"PVC COATED LB FORM 7 4.00 $ 383 $ 96 3"PVC COATED LB FORM 7 10.00 $ 5,783 $ 578 1"PVC COATED T FORM 7 4.00 $ 638 $ 159 1"PVC/CTD 90 ELBOW 12.00 $ 348 $ 29 3/4"PVC/CTD 1-H STL STRAP 78.00 $ 1,172 $ 15 1"PVC/CTD STRUT STRAP 30.00 $ 530 $ 18 3"PVC/CTD STRUT STRAP 830.00 $ 22,020 $ 27 3/4"PVC/CTD CLAMPBACK 78.00 $ 1,771 $ 23 3/4"EYS-26 PVC/CTD 13.00 $ 1,448 $ 111 1"EYS-36 PVC/CTD 6.00 $ 763 $ 127 3"EYS-86 PVC/CTD 10.00 $ 4,686 $ 469 1"PVC BURIED 180.00 $ 79 $ 0 1"PVC FEM ADAPTER 24.00 $ 35 $ 1 1"PVC COUPLING 6.00 $ 5 $ 1 3/8"S/S CONCRETE ANCHOR 312.00 $ 2,864 $ 9 3/8"S/S SADDLE WASHER 4.00 $ 6 $ 2 1/2"S/S SADDLE WASHER 28.00 $ 38 $ 1 1/4"S/S WASHER 24.00 $ 18 $ 1 3/8"S/S WASHER 302.00 $ 347 $ 1 1/4"S/S NUT 6.00 $ 2 $ 0 3/8"S/S NUT 12.00 $ 6 $ 1 1/2"S/S ALL THREAD 55.00 $ 479 $ 9 1 5/8"S/S CHANNEL 234.00 $ 4,708 $ 20 1/4-20x1" BOLT(SS) 6.00 $ 3 $ 1 3/8-16x1" BOLT(SS) 92.00 $ 119 $ 1 3/8"SS SPRING NUT 32.00 $ 305 $ 10 STRUT L-JOINER(SS) 44.00 $ 3,497 $ 79 CORNER ANGLE(SS) 41.00 $ 3,258 $ 79 #10 XHHW 450.00 $ 176 $ 0 #10 XHHW 234.00 $ 91 $ 0 #8XHHW 1,200.00 $ 828 $ 1 #6 XHHW 400.00 $ 420 $ 1 #6 BARE-CU 60.00 $ 50 $ 1 #410 BARE-CU 458.00 $ 3,110 $ 7 #10/3C W/G TRAY CABLE TC-ER 390.00 $ 772 $ 2 3/0-3+GRD VFD TC-ER CABLE 600.00 $ 28,110 $ 47 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 373/3+GRD VFD TC-ER CABLE 900.00 $ 70,704 $ 79 #14/3C FCC SHLD 910.00 $ 801 $ 1 #14/7C FCC SHLD 910.00 $ 1,729 $ 2 #6/3C W/G SHLD VFD CABLE TC-ER 330.00 $ 3,062 $ 9 1-H CRIMP LUG#6 BLUE 6.00 $ 29 $ 5 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 WIRE MARKER 544.00 $ 1,088 $ 2 CABLE TAG 116.00 $ 580 $ 5 CONDUIT MEASURING TAPE 1,972.00 $ 62 $ 0 POLYTWINE 1.00 $ 0 $ 0 # 10 WIRE TERM-POWER 62.00 $ - $ - # 8 WIRE TERM-POWER 24.00 $ - $ - # 6 WIRE TERM-POWER 52.00 $ - $ - # 1 WIRE TERM-POWER 24.00 $ - $ - #3/0 WIRE TERM-POWER 48.00 $ - $ - #350 MCM TERM-POWER 72.00 $ - $ - #14 WIRE TERM-CONTROL 364.00 $ - $ - 10x10x 6"LCF-BOX NEMA4 1.00 $ 64 $ 64 FD 1GANG BOX 4.00 $ 127 $ 32 36"AL SOLID TRAY 3"D 110.00 $ 10,569 $ 96 36"AL SLD HORZ90 ELB 2.00 $ 850 $ 425 36"AL SLD HORZ T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE 4.00 $ 1,700 $ 425 36"AL SLD VRT90 OUTSIDE 4.00 $ 1,700 $ 425 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 4.00 $ 160 $ 40 36"AL SLD VRT90 OUTSIDE COVER 4.00 $ 160 $ 40 36"AL TRAY WALL FLANGE 8.00 $ 3,000 $ 375 AL TRAY DIVIDER 55.00 $ 660 $ 12 AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 20A 120-277V D/P SW(SG) 4.00 $ 38 $ 10 DS32 FS SWITCH COVER 4.00 $ 29 $ 7 1 5/8"SLOTTED STRUT S/S 422.00 $ 8,491 $ 20 3-1/4"SOLID STRUT S/S 69.00 $ 2,608 $ 38 3/8"SPRING NUT S/S 158.00 $ 1,507 $ 10 3/8"WEDGE ANCHOR S/S 80.00 $ 734 $ 9 1/2"WEDGE ANCHOR 26.00 $ 64 $ 2 1/2 ANCHOR S/S 88.00 $ 2,035 $ 23 1/2"PLATED T-ROD 150.00 $ 308 $ 2 3/8-16x1" BOLT S/S 166.00 $ 214 $ 1 1/2-13x2" BOLT S/S 36.00 $ 183 $ 5 3/8-16 HEX NUT S/S 8.00 $ 4 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/2-13 HEX NUT S/S 130.00 $ 159 $ 1 3/8" FLAT WASHER S/S 16.00 $ 18 $ 1 3/8" LOCK WASHER S/S 130.00 $ 150 $ 1 1/2" LOCK WASHER S/S 36.00 $ 77 $ 2 3/8" FENDER WASHER S/S 249.00 $ 286 $ 1 1/2" FENDER WASHER S/S 139.00 $ 296 $ 2 5/8"x10'CU CLAD GRD ROD 6.00 $ 276 $ 46 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS W/CVR 2.00 $ 92 $ 46 5/8 GRD ROD CLAMP 6.00 $ 31 $ 5 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 CONC TEST WELL 6.00 $ 690 $ 115 CONC TEST WELL COVER 6.00 $ 270 $ 45 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 FUSE HOLDER 18.00 $ 432 $ 24 20'STEEL POLE(INCLUDED W/FIXTURE PRICE) 6.00 $ - $ - 3030-LA(2'X2'X2') 2.00 $ 1,542 $ 771 3/4 EFS218 1G D/P SW XPL 2.00 $ 248 $ 124 CONDUIT TAGS 138.00 $ 1,380 $ 10 CABLE TRAY PASS-THRU GND LUG 11.00 $ 231 $ 21 Cable Tray>Strut-Clamp 28.00 $ 168 $ 6 SEISMIC BRACE 26.00 $ 6,890 $ 265 SS STANCHION 9.00 $ 6,750 $ 750 LCP/LCS ORT/SAT TESTING 9.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 298.00 $ - $ - 3"X 24"EXGJH EXP FLX COUP 10.00 $ 53,000 $ 5,300 36"SLOPED TRAY COVER-LF 55.00 $ 1,375 $ 25 STRAIGHT SECT.COVERS 36"W-LF 55.00 $ 2,475 $ 45 21 ODOR CONTROL FOR IPS 1"GRC 80.00 $ 354 $ 4 1"GRC MYERS HUB W/G 2.00 $ 23 $ 12 1"GRC COUPLING 4.00 $ 40 $ 10 1"GRC LB CONDULET 2.00 $ 49 $ 25 1" COVER 2.00 $ 14 $ 7 1"NEOPRENE GASKET 2.00 $ 11 $ 6 1"GRC STRUT CLAMP 10.00 $ 9 $ 1 1"x8"ECGJH-38 (C-H) 2.00 $ 886 $ 443 1"GRC CUT&THREAD 26.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 8.00 $ - $ - 1"PVC COATED GRC 280.00 $ 2,472 $ 9 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"PVC/CTD KO HUB CONN W/G 10.00 $ 750 $ 75 1"PVC/CTD GRC CPLG 10.00 $ 92 $ 9 1"PVC COATED LB FORM 7 2.00 $ 192 $ 96 1"PVC/CTD STRUT STRAP 36.00 $ 636 $ 18 1"EYS-36 PVC/CTD 6.00 $ 763 $ 127 #410 BARE-CU 500.00 $ 3,395 $ 7 #14/12C THHN TRAY CABLE 280.00 $ 748 $ 3 #6/3+GRD VFD TC-ER CABLE 190.00 $ 1,763 $ 9 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 WIRE MARKER 108.00 $ 216 $ 2 CABLE TAG 4.00 $ 20 $ 5 # 10 WIRE TERM-POWER 4.00 $ - $ - # 6 WIRE TERM-POWER 12.00 $ - $ - #14 WIRE TERM-CONTROL 96.00 $ - $ - 3/8-16x1" BOLT S/S 8.00 $ 10 $ 1 3/8-16 HEX NUT S/S 8.00 $ 4 $ 1 3/8" FLAT WASHER S/S 16.00 $ 18 $ 1 3/8" LOCK WASHER S/S 8.00 $ 9 $ 1 TY-526M T&B TY-RAP(11") 48.00 $ 17 $ 0 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 CONDUIT TAGS 24.00 $ 240 $ 10 WIRE TESTING(PER CONDUCTOR) 56.00 $ - $ - 22 IPS ELECTRICAL BLDG 22-PNL-001-01 225A 480V 1.00 $ 14,233 $ 14,233 22-XFMR-001-01 45KVA 480-208/120V 1.00 $ 5,232 $ 5,232 22-UPS-001-01 UPS 8KVA 208/120V W/MBS 1.00 $ 36,405 $ 36,405 22-MBS 30A($$included with UPS) 1.00 $ - $ - 22-PNL-001-03 125A 208/120V 1.00 $ 4,268 $ 4,268 22-SWBD-001-01 1200A 480V 5-SECT 1.00 $ 214,411 $ 214,411 600HP AFD 600A 3.00 $ 168,008 $ 56,003 70HP AFD 200A 4.00 $ 36,281 $ 9,070 30HP AFD 60A 3.00 $ 15,000 $ 5,000 20HP MOTOR STARTER 2.00 $ 977 $ 488 5HP MOTOR STARTER 1.00 $ 435 $ 435 3/4"GRC 20.00 $ 61 $ 3 1"GRC 240.00 $ 1,061 $ 4 1 1/2"GRC 5.00 $ 37 $ 7 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 2 1/2"GRC 120.00 $ 2,024 $ 17 3"GRC 400.00 $ 7,688 $ 19 3/4"GRC MYERS HUB W/G 8.00 $ 74 $ 9 1"GRC MYERS HUB W/G 12.00 $ 139 $ 12 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 2 1/2"GRC MYERS HUB W/G 12.00 $ 534 $ 44 3"GRC MYERS HUB W/G 20.00 $ 1,164 $ 58 3/4"GRC COUPLING 1.00 $ 7 $ 7 1"GRC COUPLING 12.00 $ 119 $ 10 1 1/2"GRC COUPLING 1.00 $ 18 $ 18 3"GRC COUPLING 40.00 $ 2,970 $ 74 3"GRC LB CONDULET 4.00 $ 931 $ 233 3/4"INS STL GRD BUSHING 1.00 $ 6 $ 6 2 1/2" INS STL GRD BUSHING 12.00 $ 228 $ 19 1 x 1/2 RED BUSHING 12.00 $ 101 $ 8 3/4"GRC STRUT CLAMP 4.00 $ 3 $ 1 1"GRC STRUT CLAMP 30.00 $ 27 $ 1 1 1/2"GRC STRUT CLAMP 1.00 $ 1 $ 1 2 1/2"GRC STRUT CLAMP 24.00 $ 36 $ 1 3"GRC STRUT CLAMP 830.00 $ 1,357 $ 2 1/2"x8"ECGJH-18 (C-H) 9.00 $ 1,715 $ 191 3/4"GRC CUT&THREAD 4.00 $ - $ - 1"GRC CUT&THREAD 36.00 $ - $ - 1 1/2"GRC CUT&THREAD 1.00 $ - $ - 2 1/2"GRC CUT&THREAD 12.00 $ - $ - 3"GRC CUT&THREAD 40.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 18.00 $ - $ - 2 1/2"GRC 90 FIELD BEND 12.00 $ - $ - 3"GRC 90 FIELD BEND 34.00 $ - $ - 1"PVC COATED GRC 150.00 $ 1,325 $ 9 1"PVC/CTD KO HUB CONN W/G 6.00 $ 450 $ 75 1"PVC/CTD GRC CPLG 6.00 $ 55 $ 9 1"PVC COATED T FORM 7 9.00 $ 1,435 $ 159 1"PVC/CTD STRUT STRAP 19.00 $ 336 $ 18 1"EYS-36 PVC/CTD 3.00 $ 382 $ 127 3/4"LT FLEX 5.00 $ 7 $ 1 1 1/2"LT FLEX 5.00 $ 20 $ 4 3/4"LT STRAIGHT CONN 1.00 $ 11 $ 11 1 1/2"LT STRAIGHT CONN 1.00 $ 43 $ 43 3/4"LT 90DEG CONN 1.00 $ 19 $ 19 1 1/2"LT 90DEG CONN 1.00 $ 88 $ 88 3/8"S/S CONCRETE ANCHOR 100.00 $ 918 $ 9 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8"S/S WASHER 100.00 $ 115 $ 1 1 5/8"S/S CHANNEL 100.00 $ 2,012 $ 20 1/2-13x2" BOLT(SS) 80.00 $ 406 $ 5 CORNER ANGLE(SS) 40.00 $ 3,179 $ 79 #10 XHHW 425.00 $ 166 $ 0 #6 XHHW 640.00 $ 672 $ 1 #1 XHHW 430.00 $ 1,118 $ 3 #210 XHHW 3,030.00 $ 12,090 $ 4 #310 XHHW 660.00 $ 3,406 $ 5 #350MCM XHHW 990.00 $ 10,256 $ 10 #400MCM XHHW 9,090.00 $ 107,444 $ 12 #4 BARE-CU 18.00 $ 24 $ 1 #14/12C THHN TRAY CABLE 210.00 $ 561 $ 3 #10/3C W/G TRAY CABLE TC-ER 55.00 $ 109 $ 2 #6/3+GRD VFD TC-ER CABLE 275.00 $ 2,552 $ 9 #2 MECH-LUG 6.00 $ 11 $ 2 LAMINATED DISCONNECT LABEL 3.00 $ 17 $ 6 WIRE MARKER 252.00 $ 504 $ 2 CABLE TAG 12.00 $ 60 $ 5 1"X 3"PHENOLIC NAME PLATE 33.00 $ 149 $ 5 CONDUIT MEASURING TAPE 400.00 $ 13 $ 0 POLYTWINE 30.00 $ 0 $ 0 # 10 WIRE TERM-POWER 28.00 $ - $ - # 6 WIRE TERM-POWER 70.00 $ - $ - # 1 WIRE TERM-POWER 20.00 $ - $ - #2/0 WIRE TERM-POWER 12.00 $ - $ - #3/0 WIRE TERM-POWER 24.00 $ - $ - #350 MCM TERM-POWER 36.00 $ - $ - #400 MCM TERM-POWER 36.00 $ - $ - #14 WIRE TERM-CONTROL 72.00 $ - $ - 1 5/8"SLOTTED STRUT S/S 233.00 $ 4,688 $ 20 3/8"SPRING NUT S/S 168.00 $ 1,603 $ 10 3/8"WEDGE ANCHOR S/S 108.00 $ 991 $ 9 1/2"WEDGE ANCHOR 20.00 $ 49 $ 2 1/2 ANCHOR S/S 134.00 $ 3,099 $ 23 1/2"PLATED T-ROD 200.00 $ 411 $ 2 1/4"DRILL&TAP F/SCREW 6.00 $ - $ - 3/8-16x1" BOLT S/S 174.00 $ 224 $ 1 1/2-13x2" BOLT S/S 4.00 $ 20 $ 5 3/8-16 HEX NUT S/S 12.00 $ 6 $ 1 1/2-13 HEX NUT S/S 100.00 $ 122 $ 1 3/8" LOCK WASHER S/S 72.00 $ 83 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/2" LOCK WASHER S/S 84.00 $ 179 $ 2 3/8" FENDER WASHER S/S 288.00 $ 331 $ 1 1/2" FENDER WASHER S/S 184.00 $ 392 $ 2 TY-525M T&B TY-RAP(7") 2,424.00 $ 580 $ 0 TY-526M T&B TY-RAP(11") 42.00 $ 15 $ 0 BPB TESTING 2.00 $ - $ - BPB COMMISSIONING 2.00 $ - $ - XMER TESTING 1.00 $ - $ - XMER COMMISSIONING 1.00 $ - $ - CONDUIT TAGS 93.00 $ 930 $ 10 SEISMIC BRACE 20.00 $ 5,300 $ 265 VFD/AFD TESTING/COMMISSIONG 10.00 $ - $ - UPS TEST&COMMISSIONG 1.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 125.00 $ - $ - 23 STORM WATER PS 23-SWPS-LCS 3.00 $ - $ - 23-LCP-011 20x20x10 NEMA 4X-OFCI 1.00 $ - $ - 1"GRC(GALV)(EXPOSED) 200.00 $ 884 $ 4 1"GRC MYERS HUB W/G 5.00 $ 58 $ 12 1 x 1/2 RED BUSHING 4.00 $ 34 $ 8 1"GRC STRUT CLAMP 28.00 $ 25 $ 1 1/2"x8"ECGJH-18 (C-H) 3.00 $ 572 $ 191 3/4"x8"ECGJH-28 (C-H) 7.00 $ 1,614 $ 231 1"x8"ECGJH-38 (C-H) 3.00 $ 1,328 $ 443 3/4"GRC CUT&THREAD 14.00 $ - $ - 1"GRC CUT&THREAD 26.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 6.00 $ - $ - 3/4"PVC COATED GRC 280.00 $ 1,910 $ 7 1"PVC COATED GRC 165.00 $ 1,457 $ 9 3/4"PVC/CTD KO HUB CONN 14.00 $ 983 $ 70 1"PVC/CTD KO HUB CONN W/G 16.00 $ 1,201 $ 75 3/4"PVC/CTD GRC CPLG 14.00 $ 99 $ 7 1"PVC/CTD GRC CPLG 7.00 $ 65 $ 9 3/4"PVC COATED LB FORM 7 7.00 $ 501 $ 72 1"PVC COATED T FORM 7 3.00 $ 478 $ 159 3/4"PVC/CTD 1-H STL STRAP 42.00 $ 631 $ 15 1"PVC/CTD STRUT STRAP 27.00 $ 477 $ 18 3/4"PVC/CTD CLAMPBACK 42.00 $ 954 $ 23 3/4"EYS-26 PVC/CTD 7.00 $ 780 $ 111 1"EYS-36 PVC/CTD 9.00 $ 1,145 $ 127 1"PVC BURIED 573.00 $ 252 $ 0 1"PVC FEM ADAPTER 10.00 $ 15 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"PVC COUPLING 26.00 $ 22 $ 1 1 PVC EXPANSION CPLG 7.00 $ 169 $ 24 1"PVC 90 ELBOW 9.00 $ 34 $ 4 1"PVC END BELL 6.00 $ 66 $ 11 1"PVC CONDUIT PLUG 12.00 $ 18 $ 2 PVC CEMENT(1-QUART) 5.00 $ 227 $ 45 2"x3"BASE SPACER 72.00 $ 141 $ 2 3/8"S/S CONCRETE ANCHOR 135.00 $ 1,239 $ 9 3/8"S/S WASHER 144.00 $ 166 $ 1 1 5/8"S/S CHANNEL 72.00 $ 1,449 $ 20 #10 XHHW 165.00 $ 64 $ 0 #6 XHHW 495.00 $ 520 $ 1 #410 BARE-CU 200.00 $ 1,358 $ 7 #10/3C W/G TRAY CABLE TC-ER 1,815.00 $ 3,594 $ 2 #6/3+GRD TRAY CABLE TC-ER 1,782.00 $ 8,126 $ 5 #14/3C FCC SHLD 490.00 $ 431 $ 1 #14/7C FCC SHLD 490.00 $ 931 $ 2 #14/12C FCC SHLD(FLAG) 2,250.00 $ 4,275 $ 2 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 WIRE MARKER 400.00 $ 800 $ 2 CABLE TAG 52.00 $ 260 $ 5 CONDUIT MEASURING TAPE 1,011.00 $ 32 $ 0 POLYTWINE 18.00 $ 0 $ 0 # 10 WIRE TERM-POWER 36.00 $ - $ - # 6 WIRE TERM-POWER 36.00 $ - $ - #14 WIRE TERM-CONTROL 340.00 $ - $ - 1/2 ANCHOR S/S 16.00 $ 370 $ 23 3/8-16x1" BOLT S/S 8.00 $ 10 $ 1 1/2-13x2" BOLT S/S 16.00 $ 81 $ 5 3/8-16 HEX NUT S/S 8.00 $ 4 $ 1 3/8" FLAT WASHER S/S 16.00 $ 18 $ 1 3/8" LOCK WASHER S/S 8.00 $ 9 $ 1 1/2" LOCK WASHER S/S 16.00 $ 34 $ 2 1/2" FENDER WASHER S/S 16.00 $ 34 $ 2 TY-524M T&B TY-RAP(5") 363.00 $ 116 $ 0 TY-525M T&B TY-RAP(7") 425.00 $ 102 $ 0 3/4"x10'CU CLAD GRD ROD 1.00 $ 42 $ 42 GRD ROD WELLS W/CVR 1.00 $ 46 $ 46 3/4 GRD ROD CLAMP 1.00 $ 7 $ 7 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 CONDUIT TAGS 50.00 $ 500 $ 10 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost SS STANCHION 4.00 $ 3,000 $ 750 LCP/LCS ORT/SAT TESTING 4.00 $ - $ - 1"FIBERGLASS 90 10.00 $ 541 $ 54 WIRE TESTING(PER CONDUCTOR) 206.00 $ - $ - 25 CAMPBELL MANOR(HEADWORKS,SOLIDS STORAGE,SOLIDS iiill W-Exterior Wall Pack 3.00 $ 1,842 $ 614 WE-Exterior Wall Pack w/Em. Ballast 5.00 $ 3,855 $ 771 XD-Exit Sign,Wall Mt, Damp Location 5.00 $ 880 $ 176 El -Em.Bug-eye, Damp Location 8.00 $ 1,408 $ 176 EX2-Em. Bug-eye,Cl D2 Location 4.00 $ 14,728 $ 3,682 J-4'Enclosed Ind. LED,Suspended 14.00 $ 37,506 $ 2,679 K-4'Enclosed Ind.LED, Damp Loc., Suspended 43.00 $ 159,616 $ 3,712 P4, 16'-Pole mt., Double head, 180*LED, 16'pole 14.00 $ 79,324 $ 5,666 OFCI PLC-25 HEADWORKS 1.00 $ - $ - OFCI PLC-25 HEADWORKS RIO 1 1.00 $ - $ - OFCI PLC-25 HEADWORKS RIO 2 1.00 $ - $ - 25-LCP-001 20x20x10 NEMA 4X-ISP 1.00 $ - $ - 25-HW-LCS 27.00 $ - $ - 25-ISP-001 20x20x10 NEMA4X 1.00 $ - $ - 3/4"EMT 40.00 $ 34 $ 1 3/4"EMT STL COMP CONN 4.00 $ 29 $ 7 3/4"EMT STL COMP CPLG 5.00 $ 19 $ 4 3/4"EMT STRAP 1-H 5.00 $ 3 $ 1 3/4"GRC 3,305.00 $ 10,047 $ 3 1"GRC 390.00 $ 1,724 $ 4 2"GRC 10.00 $ 98 $ 10 3/4"GRC MYERS HUB W/G 172.00 $ 1,588 $ 9 1"GRC MYERS HUB W/G 3.00 $ 35 $ 12 2"GRC MYERS HUB W/G 4.00 $ 90 $ 22 3/4"GRC COUPLING 163.00 $ 1,121 $ 7 3/4"GRC ERICKSON CPLG 8.00 $ 146 $ 18 1"GRC ERICKSON CPLG 6.00 $ 134 $ 22 3/4"GRC LB CONDULET 7.00 $ 114 $ 16 1"GRC LB CONDULET 6.00 $ 148 $ 25 3/4"GRC T CONDULET 107.00 $ 2,199 $ 21 1"GRC T CONDULET 18.00 $ 560 $ 31 3/4" COVER 105.00 $ 528 $ 5 1" COVER 18.00 $ 126 $ 7 3/4"NEOPRENE GASKET 105.00 $ 448 $ 4 1"NEOPRENE GASKET 18.00 $ 103 $ 6 3/4"GRC 90 ELBOW 288.00 $ 5,651 $ 20 3/4"INS STL GRD BUSHING 226.00 $ 1,345 $ 6 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/4x 1/2 RED BUSHING 222.00 $ 954 $ 4 3/4"GRC STRUT CLAMP 665.00 $ 516 $ 1 1"GRC STRUT CLAMP 49.00 $ 43 $ 1 2"GRC STRUT CLAMP 2.00 $ 3 $ 1 1"EYS-316 (C-H) 6.00 $ 205 $ 34 3/4"EYS-26 (C-H) 28.00 $ 788 $ 28 3/4"x8"ECGJH-28 (C-H) 98.00 $ 22,590 $ 231 3/4"xCLOSE NIPPLE 7.00 $ 32 $ 5 3/4"GRC CUT&THREAD 503.00 $ - $ - 1"GRC CUT&THREAD 15.00 $ - $ - 2"GRC CUT&THREAD 2.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 37.00 $ - $ - 3/4"PVC COATED GRC 5,090.00 $ 34,714 $ 7 3/4"PVC/CTD KO HUB CONN 148.00 $ 10,390 $ 70 3/4"PVC/CTD GRC CPLG 191.00 $ 1,356 $ 7 3/4"PVC COATED LB FORM 7 20.00 $ 1,432 $ 72 3/4"PVC COATED T FORM 7 108.00 $ 14,409 $ 133 3/4"PVC/CTD 90 ELBOW 102.00 $ 2,580 $ 25 3/4"PVC/CTD 1-H STL STRAP 120.00 $ 1,802 $ 15 3/4"PVC/CTD STRUT STRAP 802.00 $ 9,063 $ 11 3/4"PVC/CTD CLAMPBACK 120.00 $ 2,725 $ 23 3/4"EYS-26 PVC/CTD 98.00 $ 10,918 $ 111 1/2"LT FLEX 287.00 $ 245 $ 1 3/4"LT FLEX 95.00 $ 129 $ 1 1/2"LT STRAIGHT CONN 88.00 $ 643 $ 7 3/4"LT STRAIGHT CONN 32.00 $ 337 $ 11 1/2"LT 90DEG CONN 88.00 $ 1,088 $ 12 3/4"LT 90DEG CONN 30.00 $ 576 $ 19 1/4"S/S CONCRETE ANCHOR 10.00 $ 75 $ 7 3/8"S/S CONCRETE ANCHOR 144.00 $ 1,322 $ 9 1/2"S/S CONCRETE ANCHOR 72.00 $ 1,665 $ 23 1/2"S/S SADDLE WASHER 73.00 $ 99 $ 1 1/4"S/S WASHER 58.00 $ 44 $ 1 3/8"S/S WASHER 197.00 $ 227 $ 1 1/2"S/S WASHER 72.00 $ 153 $ 2 1/4"S/S NUT 7.00 $ 2 $ 0 1/2"S/S ALL THREAD 145.00 $ 1,262 $ 9 1 5/8"S/S CHANNEL 4.00 $ 80 $ 20 1/4-20x1" BOLT(SS) 17.00 $ 9 $ 1 1/4-20X2" BOLT(SS) 4.00 $ 5 $ 1 3/8-16x1" BOLT(SS) 223.00 $ 288 $ 1 1/2-13x2" BOLT(SS) 72.00 $ 366 $ 5 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/4"SS SPRING NUT 14.00 $ 65 $ 5 3/8"SS SPRING NUT 77.00 $ 735 $ 10 STRUT L-JOINER(SS) 116.00 $ 9,219 $ 79 CORNER ANGLE(SS) 66.00 $ 5,245 $ 79 #12 XHHW 774.00 $ 201 $ 0 #10 XHHW 516.00 $ 201 $ 0 #10 XHHW 5,430.00 $ 2,118 $ 0 #6 BARE-CU 70.00 $ 58 $ 1 #410 BARE-CU 863.00 $ 5,860 $ 7 #14/7C THHN TRAY CABLE 10,045.00 $ 16,574 $ 2 #10/3C W/G TRAY CABLE TC-ER 13,840.00 $ 27,403 $ 2 #14/3C FCC SHLD 1,710.00 $ 1,505 $ 1 #14/5C FCC SHLD 80.00 $ 108 $ 1 #14/7C FCC SHLD 1,550.00 $ 2,945 $ 2 #10/3C W/G SHLD VFD CABLE TC-ER 2,050.00 $ 7,790 $ 4 1-H CRIMP LUG#6 BLUE 7.00 $ 34 $ 5 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 RED WIRE NUT 270.00 $ 111 $ 0 LAMINATED DISCONNECT LABEL 1.00 $ 6 $ 6 WIRE MARKER 1,766.00 $ 3,532 $ 2 CABLE TAG 504.00 $ 2,520 $ 5 1"X 3"PHENOLIC NAME PLATE 18.00 $ 81 $ 5 CONDUIT MEASURING TAPE 1,000.00 $ 31 $ 0 POLYTWINE 164.00 $ 2 $ 0 # 12 WIRE TERM-POWER 165.00 $ - $ - # 10 WIRE TERM-POWER 675.00 $ - $ - #24 WIRE TERM-CONTROL 32.00 $ - $ - #22 WIRE TERM-CONTROL 24.00 $ - $ - #18 WIRE TERM-CONTROL 6.00 $ - $ - #14 WIRE TERM-CONTROL 1,290.00 $ - $ - 4x1-1/2"SQ BOX COMB KO 1.00 $ 2 $ 2 4"SQ 1-TOGGLE SWITCH COVER 1.00 $ 3 $ 3 GROUND SCREW W/INSUL#12 LEAD 10.00 $ 40 $ 4 24x20x 9 NEMA1 CABINET 1.00 $ 290 $ 290 FS 2GANG BOX 3.00 $ 128 $ 43 FD 1GANG BOX 33.00 $ 1,047 $ 32 1G FS/FD BLANK COVER-STAMPED 1.00 $ 6 $ 6 2G BLANK-STAMPED COVER 3.00 $ 20 $ 7 A-1212CHNFSS 12x12x6 4X 4.00 $ 3,568 $ 892 36"AL SOLID TRAY 3"D 290.00 $ 27,863 $ 96 36"AL SLD HORZ90 ELB 0.00 $ - 36"AL SLD HORZ T SECT 0.00 $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 36"AL SLD VRT90 INSIDE 4.00 $ 1,700 $ 425 36"AL SLD VRT90 OUTSIDE 4.00 $ 1,700 $ 425 36"AL SLD HOR90 ELB COVER 0.00 $ - 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 4.00 $ 160 $ 40 36"AL SLD VRT90 OUTSIDE COVER 4.00 $ 160 $ 40 36"AL TRAY WALL FLANGE 4.00 $ 1,500 $ 375 AL TRAY DIVIDER 145.00 $ 1,740 $ 12 AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 4"x4"WIREWAY 2'PC 1.00 $ 58 $ 58 4"WW END PLATE 2.00 $ 41 $ 20 20A 120-277V S/P SW(SG) 3.00 $ 15 $ 5 20A 120-277V 3/W SW(SG) 6.00 $ 30 $ 5 DS32 FS SWITCH COVER 2.00 $ 14 $ 7 DS128 FS WP SWITCH COVER 6.00 $ 399 $ 67 CCTV OUTSIDE-WALL CAMERA 4.00 $ 7,200 $ 1,800 CCTV CAMERA WALL BRACKET 4.00 $ 100 $ 25 CARD READER W/CONTROL 3.00 $ 13,500 $ 4,500 1 5/8"SLOTTED STRUT S/S 859.00 $ 17,283 $ 20 3-1/4"SOLID STRUT S/S 181.00 $ 6,840 $ 38 3/8"SPRING NUT S/S 223.00 $ 2,127 $ 10 3/8"DROP IN ANCHOR S/S 86.00 $ 644 $ 7 3/8"WEDGE ANCHOR S/S 96.00 $ 881 $ 9 1/2"WEDGE ANCHOR 48.00 $ 117 $ 2 1/2 ANCHOR S/S 210.00 $ 4,857 $ 23 1/2"PLATED T-ROD 185.00 $ 380 $ 2 12 FIXTURE SUSPENSION CABLE 342.00 $ 38 $ 0 SUSPENSION CABLE END CONNECTORS 228.00 $ 36 $ 0 1/4-20X2" BOLT S/S 24.00 $ 13 $ 1 3/8-16x1" BOLT S/S 247.00 $ 319 $ 1 1/2-13x2" BOLT S/S 128.00 $ 650 $ 5 1/4-20 HEX NUT S/S 24.00 $ 112 $ 5 3/8-16 HEX NUT S/S 24.00 $ 13 $ 1 1/2-13 HEX NUT S/S 238.00 $ 290 $ 1 1/4" FLAT WASHER S/S 24.00 $ 18 $ 1 3/8" FLAT WASHER S/S 32.00 $ 37 $ 1 1/4" LOCK WASHER S/S 24.00 $ 18 $ 1 3/8" LOCK WASHER S/S 293.00 $ 337 $ 1 1/2" LOCK WASHER S/S 200.00 $ 426 $ 2 3/8" FENDER WASHER S/S 342.00 $ 393 $ 1 1/2" FENDER WASHER S/S 294.00 $ 626 $ 2 #10x1" S-TAP SCREW P/H 6.00 $ 1 $ 0 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/4x2-1/2"LAG BOLT 10.00 $ 4 $ 0 TY-524M T&B TY-RAP(5") 3,128.00 $ 997 $ 0 20A 4P 600V LIGHTING CONTACTOR(1) 2.00 $ 1,184 $ 592 24HR SPST 277V TIME SW 1.00 $ 274 $ 274 120V PHOTOCONTROL K4141 1.00 $ 13 $ 13 30A/600V 3P NON FUS NEMA4X 1.00 $ 4,234 $ 4,234 5/8"x10'CU CLAD GRD ROD 7.00 $ 322 $ 46 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS W/CVR 2.00 $ 92 $ 46 5/8 GRD ROD CLAMP 7.00 $ 36 $ 5 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 CONC TEST WELL 7.00 $ 805 $ 115 CONC TEST WELL COVER 7.00 $ 315 $ 45 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 FUSE HOLDER 21.00 $ 504 $ 24 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 5.00 $ - $ - 16'STEEL POLE(INCLUDED W/FIXTURE PRICE) 7.00 $ - $ - Core Drill(LAYOUT ONLY) 2.00 $ - $ - WALL SLEEVE 2" 2.00 $ 42 $ 21 3/4 EFS218 1G D/P SW XPL 2.00 $ 248 $ 124 CAT6 CABLE 350.00 $ 88 $ 0 CONDUIT TAGS 615.00 $ 6,150 $ 10 CABLE TRAY PASS-THRU GND LUG 29.00 $ 609 $ 21 Cable Tray>Strut-Clamp 73.00 $ 437 $ 6 SEISMIC BRACE 48.00 $ 12,720 $ 265 S/S 1/2"CONDUIT DRAIN 143.00 $ 19,415 $ 136 SS STANCHION 29.00 $ 21,750 $ 750 PLC ORT/SAT TESTING 3.00 $ - $ - LCP/LCS ORT/SAT TESTING 29.00 $ - $ - VFCI-TJB 14.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 890.00 $ - $ - 1/2X12 EXGJH EXP FLX COUPLING 26.00 $ 4,930 $ 190 4 Element Access Control Cable 18-04+22-3P+22-02+22-04 Plenum Yellow 280.00 $ 284 $ 1 INSTALL ACCESS CONTROL PANEL 1.00 $ 5,400 $ 5,400 FIXTURE DEFLECTION CABLE 114.00 $ 3,990 $ 35 36"SLOPED TRAY COVER-LF 145.00 $ 3,625 $ 25 STRAIGHT SECT.COVERS 36"W-LF 145.00 $ 6,525 $ 45 26 ODOR CONTROL(LODS,HEADWRKS,SS,&SP) P1 -Pole Mt., Single head LED, 10'pole 4.00 $ 3,968 $ 992 3/4"GRC 90.00 $ 274 $ 3 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"GRC 110.00 $ 486 $ 4 3/4"GRC MYERS HUB W/G 3.00 $ 28 $ 9 1"GRC MYERS HUB W/G 6.00 $ 69 $ 12 1"GRC COUPLING 2.00 $ 20 $ 10 3/4"GRC ERICKSON CPLG 1.00 $ 18 $ 18 3/4"GRC LB CONDULET 0.00 $ - 3/4"GRC T CONDULET 2.00 $ 41 $ 21 1"GRC T CONDULET 2.00 $ 62 $ 31 1" COVER 2.00 $ 14 $ 7 1"NEOPRENE GASKET 2.00 $ 11 $ 6 1" INS STL GRD BUSHING 4.00 $ 27 $ 7 1 x 1/2 RED BUSHING 10.00 $ 84 $ 8 1 x 3/4 RED BUSHING 2.00 $ 16 $ 8 3/4"GRC STRUT CLAMP 11.00 $ 9 $ 1 3/4"EYS-26 (C-H) 4.00 $ 113 $ 28 1"EYS-36 (C-H) 2.00 $ 74 $ 37 1/2"x8"ECGJH-18 (C-H) 6.00 $ 1,143 $ 191 3/4"x8"ECGJH-28 (C-H) 2.00 $ 461 $ 231 1"-3/4"RE32 REDUCER 2.00 $ 9 $ 4 3/4"GRC CUT&THREAD 4.00 $ - $ - 1"GRC CUT&THREAD 28.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 4.00 $ - $ - 1"PVC COATED GRC 120.00 $ 1,060 $ 9 1"PVC/CTD KO HUB CONN W/G 20.00 $ 1,501 $ 75 1"PVC/CTD GRC CPLG 8.00 $ 74 $ 9 1"PVC COATED T FORM 7 6.00 $ 957 $ 159 1"PVC/CTD 90 ELBOW 2.00 $ 58 $ 29 1"PVC/CTD STRUT STRAP 24.00 $ 424 $ 18 1"EYS-36 PVC/CTD 12.00 $ 1,526 $ 127 1"PVC BURIED 460.00 $ 202 $ 0 1"PVC FEM ADAPTER 8.00 $ 12 $ 1 1"PVC COUPLING 15.00 $ 13 $ 1 1 PVC EXPANSION CPLG 8.00 $ 193 $ 24 1"PVC END BELL 12.00 $ 132 $ 11 1"PVC CONDUIT PLUG 8.00 $ 12 $ 2 PVC CEMENT(1-QUART) 2.00 $ 91 $ 45 2"x3"BASE SPACER 38.00 $ 74 $ 2 1"LT FLEX 0.00 $ - 3/4"LT STRAIGHT CONN 0.00 $ - 3/4"LT 90DEG CONN 0.00 $ - 3/8"S/S CONCRETE ANCHOR 12.00 $ 110 $ 9 3/8"S/S SADDLE WASHER 4.00 $ 6 $ 2 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/2"S/S SADDLE WASHER 23.00 $ 31 $ 1 1/4"S/S WASHER 8.00 $ 6 $ 1 3/8"S/S WASHER 59.00 $ 68 $ 1 1/2"S/S ALL THREAD 45.00 $ 392 $ 9 1 5/8"S/S CHANNEL 4.00 $ 80 $ 20 3/8-16x1" BOLT(SS) 75.00 $ 97 $ 1 3/8"SS SPRING NUT 27.00 $ 258 $ 10 STRUT L-JOINER(SS) 36.00 $ 2,861 $ 79 CORNER ANGLE(SS) 19.00 $ 1,510 $ 79 #10 XHHW 180.00 $ 70 $ 0 #10 XHHW 221.00 $ 86 $ 0 #8 XHHW 840.00 $ 580 $ 1 #410 BARE-CU 613.00 $ 4,162 $ 7 #14/12C FCC SHLD(FLAG) 2,340.00 $ 4,446 $ 2 #6/3C W/G SHLD VFD CABLE TC-ER 480.00 $ 4,454 $ 9 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 RED WIRE NUT 21.00 $ 9 $ 0 WIRE MARKER 300.00 $ 600 $ 2 CABLE TAG 8.00 $ 40 $ 5 CONDUIT MEASURING TAPE 380.00 $ 12 $ 0 POLYTWINE 4.00 $ 0 $ 0 # 12 WIRE TERM-POWER 12.00 $ - $ - # 10 WIRE TERM-POWER 16.00 $ - $ - # 6 WIRE TERM-POWER 12.00 $ - $ - #14 WIRE TERM-CONTROL 288.00 $ - $ - GROUND SCREW W/INSUL#12 LEAD 4.00 $ 16 $ 4 10x10x 6"LCF-BOX NEMA4 1.00 $ 64 $ 64 36"AL SOLID TRAY 3"D 90.00 $ 8,647 $ 96 36"AL SLD HORZ90 ELB 0.00 $ - 36"AL SLD HORZ T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE 0.00 $ - 36"AL SLD VRT90 OUTSIDE 0.00 $ - 36"AL SLD HOR90 ELB COVER 0.00 $ - 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 0.00 $ - 36"AL SLD VRT90 OUTSIDE COVER 0.00 $ - 36"AL TRAY WALL FLANGE 4.00 $ 1,500 $ 375 AL TRAY DIVIDER 45.00 $ 540 $ 12 AL TRAY EXPANSION JOINT 2.00 $ 334 $ 167 1 5/8"SLOTTED STRUT S/S 274.00 $ 5,513 $ 20 3-1/4"SOLID STRUT S/S 56.00 $ 2,116 $ 38 3/8"SPRING NUT S/S 82.00 $ 782 $ 10 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8"WEDGE ANCHOR S/S 40.00 $ 367 $ 9 1/2"WEDGE ANCHOR 14.00 $ 34 $ 2 1/2 ANCHOR S/S 24.00 $ 555 $ 23 1/2"PLATED T-ROD 50.00 $ 103 $ 2 3/8-16x1" BOLT S/S 90.00 $ 116 $ 1 1/2-13x2" BOLT S/S 16.00 $ 81 $ 5 3/8-16 HEX NUT S/S 8.00 $ 4 $ 1 1/2-13 HEX NUT S/S 86.00 $ 105 $ 1 3/8" FLAT WASHER S/S 16.00 $ 18 $ 1 1/2" FLAT WASHER S/S 16.00 $ 34 $ 2 3/8" LOCK WASHER S/S 86.00 $ 99 $ 1 1/2" LOCK WASHER S/S 16.00 $ 34 $ 2 3/8" FENDER WASHER S/S 131.00 $ 151 $ 1 1/2" FENDER WASHER S/S 48.00 $ 102 $ 2 TY-524M T&B TY-RAP(5") 96.00 $ 31 $ 0 TY-525M T&B TY-RAP(7") 38.00 $ 9 $ 0 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 10'STEEL POLE(INCLUDED W/FIXTURE PRICE) 4.00 $ - $ - 3/4 EFS218 1G D/P SW XPL 4.00 $ 496 $ 124 CONDUIT TAGS 22.00 $ 220 $ 10 CABLE TRAY PASS-THRU GND LUG 9.00 $ 189 $ 21 Cable Tray>Strut-Clamp 23.00 $ 138 $ 6 SEISMIC BRACE 14.00 $ 3,710 $ 265 S/S 1/2"CONDUIT DRAIN 2.00 $ 272 $ 136 1"FIBERGLASS 90 16.00 $ 866 $ 54 WIRE TESTING(PER CONDUCTOR) 144.00 $ - $ - 36"SLOPED TRAY COVER-LF 45.00 $ 1,125 $ 25 STRAIGHT SECT.COVERS 36"W-LF 45.00 $ 2,025 $ 45 27 MAIN ELECTRICAL BLDG W-Exterior Wall Pack 5.00 $ 3,070 $ 614 WE-Exterior Wall Pack w/Em. Ballast 2.00 $ 1,542 $ 771 X-Exit Sign,Wall Mt. 2.00 $ 932 $ 466 E-Em.Bug-eye 2.00 $ 728 $ 364 H-Highbay LED, Damp Loc.,Suspended 12.00 $ 2,112 $ 176 J-4'Enclosed Ind. LED,Suspended 14.00 $ 37,506 $ 2,679 E2-Em.Bug-eye,Wet Location 4.00 $ 21,220 $ 5,305 GEN CONTROL PANEL-OFCI 1.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 35-SWGR-001-01 5000A 480V 1.00 $ 1,331,141 $ 1,331,141 ATS 250A 3P 480V 1.00 $ 26,988 $ 26,988 40-PNL-001-01 225A 480V 1.00 $ 13,222 $ 13,222 ATS 225A 3P 480V 1.00 $ 26,988 $ 26,988 GEAR-STUDIES 1.00 $ 21,286 $ 21,286 GEAR-TRAINING 1.00 $ 21,000 $ 21,000 GEAR-START UP 1.00 $ 121,672 $ 121,672 GEAR-FAT 1.00 $ 12,795 $ 12,795 GEAR SPARE PARTS 1.00 $ 60,896 $ 60,896 27-MCC-001-01 1000A 42'W- 1-SECT(25 TOTAL) 25.00 $ 809,706 $ 32,388 27--SWBD-001-01 3000A 5-SECT 1.00 $ 374,991 $ 374,991 30HP AFD 60A 3.00 $ 15,000 $ 5,000 40HP AFD 80A 1.00 $ 6,000 $ 6,000 300HP AFD 600A 5.00 $ 280,014 $ 56,003 400A ATS 65KAIC 1.00 $ 35,706 $ 35,706 27-PNL-001-01 400A 480V 1.00 $ 22,986 $ 22,986 75KVA XFMR NEMA 1 1.00 $ 5,059 $ 5,059 27-PNL-001-02 225A 208V 1.00 $ 4,066 $ 4,066 27-UPS-001-01 UPS 8KVA 208/120V W/MBS 1.00 $ 36,405 $ 36,405 27-MBS 30A($$included with UPS) 1.00 $ - $ - 27-PNL-001-03 125A 208/120V 1.00 $ 4,268 $ 4,268 3/4"GRC 536.00 $ 1,629 $ 3 1"GRC 270.00 $ 1,193 $ 4 1 1/2"GRC 5.00 $ 37 $ 7 2"GRC 40.00 $ 394 $ 10 3"GRC 530.00 $ 10,187 $ 19 3/4"GRC MYERS HUB W/G 26.00 $ 240 $ 9 1"GRC MYERS HUB W/G 9.00 $ 104 $ 12 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 2"GRC MYERS HUB W/G 4.00 $ 90 $ 22 3"GRC MYERS HUB W/G 50.00 $ 2,909 $ 58 3/4"GRC COUPLING 11.00 $ 76 $ 7 1"GRC COUPLING 8.00 $ 79 $ 10 1 1/2"GRC COUPLING 1.00 $ 18 $ 18 2"GRC COUPLING 4.00 $ 92 $ 23 3"GRC COUPLING 6.00 $ 445 $ 74 3/4"GRC ERICKSON CPLG 3.00 $ 55 $ 18 1"GRC ERICKSON CPLG 1.00 $ 22 $ 22 3/4"GRC LB CONDULET 0.00 $ - 1"GRC LB CONDULET 1.00 $ 25 $ 25 3/4"GRC T CONDULET 33.00 $ 678 $ 21 1"GRC T CONDULET 4.00 $ 125 $ 31 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/4" COVER 33.00 $ 166 $ 5 1" COVER 4.00 $ 28 $ 7 3/4"NEOPRENE GASKET 33.00 $ 141 $ 4 1"NEOPRENE GASKET 4.00 $ 23 $ 6 3/4"GRC 90 ELBOW 16.00 $ 314 $ 20 3/4"INS STL GRD BUSHING 11.00 $ 65 $ 6 2" INS STL GRD BUSHING 4.00 $ 46 $ 12 3" INS STL GRD BUSHING 50.00 $ 1,243 $ 25 3/4x 1/2 RED BUSHING 47.00 $ 202 $ 4 3/4"GRC STRUT CLAMP 60.00 $ 47 $ 1 1"GRC STRUT CLAMP 34.00 $ 30 $ 1 1 1/2"GRC STRUT CLAMP 1.00 $ 1 $ 1 2"GRC STRUT CLAMP 8.00 $ 11 $ 1 3"GRC STRUT CLAMP 18.00 $ 29 $ 2 3/4"GRC CUT&THREAD 41.00 $ - $ - 1"GRC CUT&THREAD 20.00 $ - $ - 1 1/2"GRC CUT&THREAD 1.00 $ - $ - 2"GRC CUT&THREAD 8.00 $ - $ - 3"GRC CUT&THREAD 56.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 25.00 $ - $ - 2"GRC 90 FIELD BEND 4.00 $ - $ - 3"GRC 90 FIELD BEND 50.00 $ - $ - 1/2"LT FLEX 132.00 $ 113 $ 1 3/4"LT FLEX 15.00 $ 20 $ 1 1 1/2"LT FLEX 5.00 $ 20 $ 4 1/2"LT STRAIGHT CONN 47.00 $ 343 $ 7 3/4"LT STRAIGHT CONN 5.00 $ 53 $ 11 1 1/2"LT STRAIGHT CONN 1.00 $ 43 $ 43 1/2"LT 90DEG CONN 47.00 $ 581 $ 12 3/4"LT 90DEG CONN 1.00 $ 19 $ 19 1 1/2"LT 90DEG CONN 1.00 $ 88 $ 88 3/8"S/S CONCRETE ANCHOR 46.00 $ 422 $ 9 1/2"S/S SADDLE WASHER 263.00 $ 355 $ 1 1/4"S/S WASHER 8.00 $ 6 $ 1 3/8"S/S WASHER 699.00 $ 804 $ 1 1/2"S/S ALL THREAD 263.00 $ 2,288 $ 9 1 5/8"S/S CHANNEL 8.00 $ 161 $ 20 1/4-20X2" BOLT(SS) 4.00 $ 5 $ 1 3/8-16x1" BOLT(SS) 695.00 $ 897 $ 1 1/2-13x2" BOLT(SS) 184.00 $ 935 $ 5 3/8"SS SPRING NUT 271.00 $ 2,585 $ 10 STRUT L-JOINER(SS) 420.00 $ 33,377 $ 79 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost CORNER ANGLE(SS) 131.00 $ 10,411 $ 79 #14 XHHW 240.00 $ 46 $ 0 #10 XHHW 84.00 $ 33 $ 0 #10 XHHW 2,275.00 $ 887 $ 0 #6 XHHW 400.00 $ 420 $ 1 #4 XHHW 120.00 $ 179 $ 1 #3 XHHW 285.00 $ 522 $ 2 #1 XHHW 100.00 $ 260 $ 3 #410 XHHW 360.00 $ 2,329 $ 6 #250MCM XHHW 1,020.00 $ 7,609 $ 7 #400MCM XHHW 5,780.00 $ 68,320 $ 12 #500MCM XHHW 9,015.00 $ 132,881 $ 15 #4 BARE-CU 66.00 $ 88 $ 1 #410 BARE-CU 1,313.00 $ 8,915 $ 7 #10/3C W/G TRAY CABLE TC-ER 865.00 $ 1,713 $ 2 #6/3+GRD VFD TC-ER CABLE 165.00 $ 1,531 $ 9 #4/3+GRD THHN TRAY CABLE 55.00 $ 389 $ 7 #14/3C FCC SHLD 0.00 $ - #14/7C FCC SHLD 0.00 $ - #2 MECH-LUG 22.00 $ 39 $ 2 RED WIRE NUT 36.00 $ 7 $ 0 RED WIRE NUT 42.00 $ 17 $ 0 LAMINATED DISCONNECT LABEL 2.00 $ 11 $ 6 WIRE MARKER 368.00 $ 736 $ 2 CABLE TAG 87.00 $ 435 $ 5 1"X 3"PHENOLIC NAME PLATE 124.00 $ 558 $ 5 CONDUIT MEASURING TAPE 333.00 $ 10 $ 0 POLYTWINE 35.00 $ 0 $ 0 # 12 WIRE TERM-POWER 84.00 $ - $ - # 10 WIRE TERM-POWER 87.00 $ - $ - # 8 WIRE TERM-POWER 2.00 $ - $ - # 6 WIRE TERM-POWER 50.00 $ - $ - # 4 WIRE TERM-POWER 10.00 $ - $ - # 3 WIRE TERM-POWER 6.00 $ - $ - # 1 WIRE TERM-POWER 8.00 $ - $ - #4/0 WIRE TERM-POWER 12.00 $ - $ - #250 MCM TERM-POWER 12.00 $ - $ - #400 MCM TERM-POWER 68.00 $ - $ - #500 MCM TERM-POWER 114.00 $ - $ - #14 WIRE TERM-CONTROL 0.00 $ - 4x1-1/2"SQ BOX COMB KO 4.00 $ 8 $ 2 4"SQ 1G PL-RING 1/2"RISE 4.00 $ 5 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost GROUND SCREW W/INSUL#12 LEAD 4.00 $ 16 $ 4 FD 1GANG BOX 10.00 $ 317 $ 32 1G FS/FD BLANK COVER-STAMPED 2.00 $ 11 $ 6 1-IN COND TRAY CLAMP 10.00 $ 885 $ 88 3-IN COND TRAY CLAMP 6.00 $ 2,168 $ 361 36"AL SOLID TRAY 3"D 1,050.00 $ 100,884 $ 96 36"AL SLD HORZ90 ELB 6.00 $ 2,550 $ 425 36"AL SLD HORZ T SECT 12.00 $ 5,100 $ 425 36"AL SLD VRT90 INSIDE 12.00 $ 5,100 $ 425 36"AL SLD VRT90 OUTSIDE 12.00 $ 5,100 $ 425 36"AL SLD HOR90 ELB COVER 6.00 $ 240 $ 40 36"AL SLD HOR T SECT 12.00 $ 480 $ 40 36"AL SLD VRT90 INSIDE COVER 12.00 $ 480 $ 40 36"AL SLD VRT90 OUTSIDE COVER 12.00 $ 480 $ 40 36"AL TRAY WALL FLANGE 24.00 $ 9,000 $ 375 AL TRAY DIVIDER 175.00 $ 2,100 $ 12 AL TRAY EXPANSION JOINT 24.00 $ 4,008 $ 167 20A 120-277V 3/W SW(SG) 4.00 $ 20 $ 5 DS32 FS SWITCH COVER 2.00 $ 14 $ 7 DS128 FS WP SWITCH COVER 2.00 $ 133 $ 67 1 5/8"SLOTTED STRUT S/S 2,636.00 $ 53,036 $ 20 3-1/4"SOLID STRUT S/S 656.00 $ 24,790 $ 38 3/8"SPRING NUT S/S 546.00 $ 5,209 $ 10 #6-8 PL ANCHOR W/SCREW(3/16) 8.00 $ 1 $ 0 3/8"WEDGE ANCHOR S/S 192.00 $ 1,763 $ 9 1/2"WEDGE ANCHOR 118.00 $ 288 $ 2 1/2 ANCHOR S/S 313.00 $ 7,240 $ 23 1/2"PLATED T-ROD 130.00 $ 267 $ 2 12 FIXTURE SUSPENSION CABLE 84.00 $ 9 $ 0 SUSPENSION CABLE END CONNECTORS 56.00 $ 9 $ 0 1/4"DRILL&TAP F/SCREW 22.00 $ - $ - 1/4-20X2" BOLT S/S 8.00 $ 4 $ 1 3/8-16x1" BOLT S/S 582.00 $ 751 $ 1 1/2-13x2" BOLT S/S 52.00 $ 264 $ 5 1/4-20 HEX NUT S/S 8.00 $ 37 $ 5 3/8-16 HEX NUT S/S 58.00 $ 31 $ 1 1/2-13 HEX NUT S/S 590.00 $ 720 $ 1 1/4" FLAT WASHER S/S 8.00 $ 6 $ 1 3/8" FLAT WASHER S/S 14.00 $ 16 $ 1 1/4" LOCK WASHER S/S 8.00 $ 6 $ 1 3/8" LOCK WASHER S/S 832.00 $ 957 $ 1 1/2" LOCK WASHER S/S 236.00 $ 503 $ 2 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8" FENDER WASHER S/S 835.00 $ 960 $ 1 1/2" FENDER WASHER S/S 564.00 $ 1,201 $ 2 #10x1" S-TAP SCREW P/H 8.00 $ 1 $ 0 TY-525M T&B TY-RAP(7") 1,413.00 $ 338 $ 0 TY-526M T&B TY-RAP(11") 1,734.00 $ 609 $ 0 SWG TESTING 1.00 $ - $ - SWG COMMISSIONING 1.00 $ - $ - MCC TESTING 25.00 $ - $ - MCC COMMISSIONING 25.00 $ - $ - BPB TESTING 1.00 $ - $ - BPB COMMISSIONING 1.00 $ - $ - 30A/600V 3P NON FUS NEMA4X 2.00 $ 8,469 $ 4,234 TRANSFER SW TESTING 2.00 $ - $ - TRANSFER SW COMMISSIONING 2.00 $ - $ - GRND SCR W/12SOL PIGTAIL 4.00 $ 1 $ 0 FIXTURE HOOK 24.00 $ 240 $ 10 2/C#12 6'FIXTURE WHIP 4.00 $ 1 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - CONDUIT TAGS 133.00 $ 1,330 $ 10 CABLE TRAY PASS-THRU GND LUG 105.00 $ 2,205 $ 21 Cable Tray>Strut-Clamp 263.00 $ 1,575 $ 6 100'LED STRING 25.00 $ 5,500 $ 220 200A TEMP POWER SKID 6.00 $ 72,000 $ 12,000 SEISMIC BRACE 118.00 $ 31,270 $ 265 VFD/AFD TESTING/COMMISSIONG 9.00 $ - $ - UPS TEST&COMMISSIONG 1.00 $ - $ - SS STANCHION 1.00 $ 750 $ 750 35-SWGR-REMOTE HMI (INCUDED IN SWGR PRICE) 1.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 86.00 $ - $ - FIXTURE DEFLECTION CABLE 52.00 $ 1,820 $ 35 36"SLOPED TRAY COVER-LF 0.00 $ - STRAIGHT SECT.COVERS 36"W-LF 1,050.00 $ 47,250 $ 45 MV XFMR 3.00 $ 180,000 $ 60,000 200A CRANE TEMP PWR 2.00 $ 5,000 $ 2,500 ASSURED GROUNDING 40HRS/QTR 16.00 $ - $ - 28 PLANT DRAIN PS Illmil 28-PDPS-LCS 3.00 $ - $ - 28-LCP-011 20x20x10 NEMA 4X-OFCI 1.00 $ - $ - 1"GRC 290.00 $ 1,282 $ 4 1"GRC MYERS HUB W/G 5.00 $ 58 $ 12 1 x 1/2 RED BUSHING 4.00 $ 34 $ 8 1"GRC STRUT CLAMP 34.00 $ 30 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1/2"x8"ECGJH-18 (C-H) 3.00 $ 572 $ 191 3/4"x8"ECGJH-28 (C-H) 7.00 $ 1,614 $ 231 1"x8"ECGJH-38 (C-H) 3.00 $ 1,328 $ 443 3/4"GRC CUT&THREAD 14.00 $ - $ - 1"GRC CUT&THREAD 26.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 6.00 $ - $ - 3/4"PVC COATED GRC 280.00 $ 1,910 $ 7 1"PVC COATED GRC 165.00 $ 1,457 $ 9 3/4"PVC/CTD KO HUB CONN 14.00 $ 983 $ 70 1"PVC/CTD KO HUB CONN W/G 16.00 $ 1,201 $ 75 3/4"PVC/CTD GRC CPLG 14.00 $ 99 $ 7 1"PVC/CTD GRC CPLG 7.00 $ 65 $ 9 3/4"PVC COATED LB FORM 7 7.00 $ 501 $ 72 1"PVC COATED T FORM 7 3.00 $ 478 $ 159 3/4"PVC/CTD 1-H STL STRAP 42.00 $ 631 $ 15 1"PVC/CTD STRUT STRAP 27.00 $ 477 $ 18 3/4"PVC/CTD CLAMPBACK 42.00 $ 954 $ 23 3/4"EYS-26 PVC/CTD 7.00 $ 780 $ 111 1"EYS-36 PVC/CTD 9.00 $ 1,145 $ 127 1"PVC BURIED 463.00 $ 204 $ 0 1"PVC FEM ADAPTER 10.00 $ 15 $ 1 1"PVC COUPLING 26.00 $ 22 $ 1 1 PVC EXPANSION CPLG 7.00 $ 169 $ 24 1"PVC 90 ELBOW 9.00 $ 34 $ 4 1"PVC END BELL 6.00 $ 66 $ 11 1"PVC CONDUIT PLUG 12.00 $ 18 $ 2 PVC CEMENT(1-QUART) 5.00 $ 227 $ 45 2"x3"BASE SPACER 60.00 $ 118 $ 2 3/8"S/S CONCRETE ANCHOR 156.00 $ 1,432 $ 9 3/8"S/S WASHER 165.00 $ 190 $ 1 1 5/8"S/S CHANNEL 84.00 $ 1,690 $ 20 #10 XHHW 165.00 $ 64 $ 0 #6 XHHW 495.00 $ 520 $ 1 #410 BARE-CU 200.00 $ 1,358 $ 7 #10/3C W/G TRAY CABLE TC-ER 2,070.00 $ 4,099 $ 2 #6/3+GRD TRAY CABLE TC-ER 2,040.00 $ 9,302 $ 5 #14/3C FCC SHLD 490.00 $ 431 $ 1 #14/7C FCC SHLD 490.00 $ 931 $ 2 #14/12C FCC SHLD(FLAG) 1,920.00 $ 3,648 $ 2 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 WIRE MARKER 400.00 $ 800 $ 2 CABLE TAG 52.00 $ 260 $ 5 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost CONDUIT MEASURING TAPE 902.00 $ 28 $ 0 POLYTWINE 21.00 $ 0 $ 0 # 10 WIRE TERM-POWER 36.00 $ - $ - # 6 WIRE TERM-POWER 36.00 $ - $ - #14 WIRE TERM-CONTROL 340.00 $ - $ - 1/2 ANCHOR S/S 16.00 $ 370 $ 23 3/8-16x1" BOLT S/S 8.00 $ 10 $ 1 1/2-13x2" BOLT S/S 16.00 $ 81 $ 5 3/8-16 HEX NUT S/S 8.00 $ 4 $ 1 3/8" FLAT WASHER S/S 16.00 $ 18 $ 1 3/8" LOCK WASHER S/S 8.00 $ 9 $ 1 1/2" LOCK WASHER S/S 16.00 $ 34 $ 2 1/2" FENDER WASHER S/S 16.00 $ 34 $ 2 TY-524M T&B TY-RAP(5") 414.00 $ 132 $ 0 TY-525M T&B TY-RAP(7") 464.00 $ 111 $ 0 3/4"x10'CU CLAD GRD ROD 1.00 $ 42 $ 42 GRD ROD WELLS WI CVR 1.00 $ 46 $ 46 3/4 GRD ROD CLAMP 1.00 $ 7 $ 7 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 CONDUIT TAGS 50.00 $ 500 $ 10 SS STANCHION 4.00 $ 3,000 $ 750 LCP/LCS ORT/SAT TESTING 4.00 $ - $ - 1"FIBERGLASS 90 10.00 $ 541 $ 54 WIRE TESTING(PER CONDUCTOR) 206.00 $ - $ - 30 AERATION BASINS WE-Exterior Wall Pack w/Em. Ballast 2.00 $ 1,542 $ 771 X-Exit Sign,Wall Mt. 4.00 $ 1,864 $ 466 H-Highbay LED, Damp Loc.,Suspended 16.00 $ 2,816 $ 176 P2,20'-Pole mt.,Single head LED,20'pole 2.00 $ 1,416 $ 708 E2-Em.Bug-eye,Wet Location 4.00 $ 21,220 $ 5,305 P3,20'-Pole mt., Double head,90*LED,20'pole 8.00 $ 45,328 $ 5,666 P4,20'-Pole mt., Double head, 180*LED,20'pole 6.00 $ 3,918 $ 653 30-AB-LCS 3.00 $ - $ - 3/4"GRC 1,218.00 $ 3,703 $ 3 1"GRC 1,595.00 $ 7,050 $ 4 1 1/2"GRC 10.00 $ 73 $ 7 3/4"GRC MYERS HUB W/G 43.00 $ 397 $ 9 1"GRC MYERS HUB W/G 4.00 $ 46 $ 12 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 3/4"GRC COUPLING 21.00 $ 144 $ 7 3/4"GRC ERICKSON CPLG 3.00 $ 55 $ 18 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"GRC ERICKSON CPLG 7.00 $ 156 $ 22 3/4"GRC LB CONDULET 0.00 $ - 1"GRC LB CONDULET 7.00 $ 173 $ 25 3/4"GRC T CONDULET 36.00 $ 740 $ 21 1"GRC T CONDULET 9.00 $ 280 $ 31 3/4" COVER 36.00 $ 181 $ 5 1" COVER 9.00 $ 63 $ 7 3/4"NEOPRENE GASKET 36.00 $ 154 $ 4 1"NEOPRENE GASKET 9.00 $ 51 $ 6 3/4"GRC 90 ELBOW 3.00 $ 59 $ 20 3/4"INS STL GRD BUSHING 676.00 $ 4,023 $ 6 1" INS STL GRD BUSHING 215.00 $ 1,449 $ 7 3/4x 1/2 RED BUSHING 36.00 $ 155 $ 4 1 x 1/2 RED BUSHING 1.00 $ 8 $ 8 3/4" 1-H MALL STRAP 4.00 $ 9 $ 2 3/4"GRC STRUT CLAMP 33.00 $ 26 $ 1 1"GRC STRUT CLAMP 281.00 $ 249 $ 1 3/4"CLAMP BACK 4.00 $ 7 $ 2 3/4"EYS-26 (C-H) 2.00 $ 56 $ 28 3/4"x8"ECGJH-28 (C-H) 2.00 $ 461 $ 231 3/4"GRC CUT&THREAD 509.00 $ - $ - 1"GRC CUT&THREAD 129.00 $ - $ - 1 1/2"GRC CUT&THREAD 2.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 33.00 $ - $ - 3/4"PVC COATED GRC 6,470.00 $ 44,125 $ 7 1"PVC COATED GRC 10.00 $ 88 $ 9 3/4"PVC/CTD KO HUB CONN 217.00 $ 15,233 $ 70 1"PVC/CTD KO HUB CONN W/G 1.00 $ 75 $ 75 3/4"PVC/CTD GRC CPLG 430.00 $ 3,053 $ 7 1"PVC/CTD GRC CPLG 1.00 $ 9 $ 9 3/4"PVC COATED LB FORM 7 215.00 $ 15,392 $ 72 1"PVC COATED T FORM 7 1.00 $ 159 $ 159 1 1/2"PVC/CTD 90 ELBOW 1.00 $ 44 $ 44 3/4"PVC/CTD 1-H STL STRAP 862.00 $ 12,947 $ 15 1"PVC/CTD STRUT STRAP 4.00 $ 71 $ 18 3/4"PVC/CTD CLAMPBACK 862.00 $ 19,576 $ 23 3/4"EYS-26 PVC/CTD 2.00 $ 223 $ 111 1 1/2"PVC BURIED 200.00 $ 148 $ 1 1 1/2"PVC FEM ADAPTER 2.00 $ 2 $ 1 1 1/2"PVC COUPLING 7.00 $ 4 $ 1 1/2"LT FLEX 72.00 $ 61 $ 1 3/4"LT FLEX 95.00 $ 129 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"LT FLEX 3.00 $ 8 $ 3 1/2"LT STRAIGHT CONN 18.00 $ 132 $ 7 3/4"LT STRAIGHT CONN 20.00 $ 211 $ 11 1"LT STRAIGHT CONN 1.00 $ 16 $ 16 1/2"LT 90DEG CONN 18.00 $ 223 $ 12 3/4"LT 90DEG CONN 18.00 $ 345 $ 19 1"LT 90DEG CONN 1.00 $ 39 $ 39 3/8"S/S CONCRETE ANCHOR 30.00 $ 275 $ 9 1/4"S/S WASHER 30.00 $ 23 $ 1 3/8"S/S WASHER 686.00 $ 789 $ 1 1/2"S/S WASHER 113.00 $ 241 $ 2 1/4"S/S NUT 9.00 $ 3 $ 0 1 5/8"S/S CHANNEL 4.00 $ 80 $ 20 1/4-20x1" BOLT(SS) 9.00 $ 5 $ 1 3/8-16x1" BOLT(SS) 698.00 $ 900 $ 1 1/2-13x1" BOLT(SS) 113.00 $ 164 $ 1 3/8"SS SPRING NUT 230.00 $ 2,194 $ 10 STRUT L-JOINER(SS) 452.00 $ 35,920 $ 79 #14 XHHW 320.00 $ 61 $ 0 #10 XHHW 699.00 $ 273 $ 0 #10 XHHW 2,232.00 $ 870 $ 0 #8 XHHW 5,260.00 $ 3,629 $ 1 #6 BARE-CU 90.00 $ 75 $ 1 #410 BARE-CU 2,413.00 $ 16,384 $ 7 #14/7C THHN TRAY CABLE 45,780.00 $ 75,537 $ 2 #10/3C W/G TRAY CABLE TC-ER 6,720.00 $ 13,306 $ 2 #10/3C W/G TRAY CABLE TC-ER 43,280.00 $ 85,694 $ 2 #10/3C W/G SHLD VFD CABLE TC-ER 775.00 $ 2,945 $ 4 #4/3+GRD VFD TC-ER CABLE 400.00 $ 5,080 $ 13 1-H CRIMP LUG#6 BLUE 9.00 $ 44 $ 5 4/0 HYPRESS 2-HOLE LUG 30.00 $ 568 $ 19 RED WIRE NUT 48.00 $ 9 $ 0 RED WIRE NUT 63.00 $ 26 $ 0 WIRE MARKER 1,872.00 $ 3,744 $ 2 CABLE TAG 1,454.00 $ 7,270 $ 5 CONDUIT MEASURING TAPE 148.00 $ 5 $ 0 POLYTWINE 918.00 $ 13 $ 0 # 12 WIRE TERM-POWER 68.00 $ - $ - # 10 WIRE TERM-POWER 385.00 $ - $ - # 8 WIRE TERM-POWER 2.00 $ - $ - # 4 WIRE TERM-POWER 6.00 $ - $ - #14 WIRE TERM-CONTROL 3,052.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 4x1-1/2"SQ BOX COMB KO 4.00 $ 8 $ 2 4"SQ 1G PL-RING 1/2"RISE 4.00 $ 5 $ 1 GROUND SCREW W/INSUL#12 LEAD 6.00 $ 24 $ 4 16x16x 6"LCF-BOX NEMA4 1.00 $ 614 $ 614 FD 1GANG BOX 8.00 $ 254 $ 32 36"AL SOLID TRAY 3"D 1,130.00 $ 108,570 $ 96 36"AL SLD HORZ90 ELB 0.00 $ - 36"AL SLD HORZ T SECT 6.00 $ 2,550 $ 425 36"AL SLD VRT90 INSIDE 4.00 $ 1,700 $ 425 36"AL SLD VRT90 OUTSIDE 4.00 $ 1,700 $ 425 36"AL SLD HOR90 ELB COVER 0.00 $ - 36"AL SLD HOR T SECT 6.00 $ 240 $ 40 36"AL SLD VRT90 INSIDE COVER 4.00 $ 160 $ 40 36"AL SLD VRT90 OUTSIDE COVER 4.00 $ 160 $ 40 36"AL TRAY WALL FLANGE 4.00 $ 1,500 $ 375 AL TRAY DIVIDER 565.00 $ 6,780 $ 12 AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 20A 120-277V 3/W SW(SG) 4.00 $ 20 $ 5 DS128 FS WP SWITCH COVER 4.00 $ 266 $ 67 1 5/8"SLOTTED STRUT S/S 2,540.00 $ 51,105 $ 20 3-1/4"SOLID STRUT S/S 706.00 $ 26,680 $ 38 3/8"SPRING NUT S/S 280.00 $ 2,671 $ 10 BEAM CLAMP P-2676(1/2") 113.00 $ 3,349 $ 30 #6-8 PL ANCHOR W/SCREW(3/16) 8.00 $ 1 $ 0 3/8"WEDGE ANCHOR S/S 280.00 $ 2,570 $ 9 1/2 ANCHOR S/S 153.00 $ 3,539 $ 23 1/4-20X2" BOLT S/S 8.00 $ 4 $ 1 3/8-16x1" BOLT S/S 344.00 $ 444 $ 1 1/2-13x2" BOLT S/S 12.00 $ 61 $ 5 1/4-20 HEX NUT S/S 8.00 $ 37 $ 5 3/8-16 HEX NUT S/S 64.00 $ 34 $ 1 1/2-13 HEX NUT S/S 565.00 $ 689 $ 1 1/4" FLAT WASHER S/S 8.00 $ 6 $ 1 3/8" FLAT WASHER S/S 124.00 $ 143 $ 1 1/4" LOCK WASHER S/S 8.00 $ 6 $ 1 3/8" LOCK WASHER S/S 516.00 $ 593 $ 1 1/2" LOCK WASHER S/S 12.00 $ 26 $ 2 3/8" FENDER WASHER S/S 560.00 $ 644 $ 1 1/2" FENDER WASHER S/S 295.00 $ 628 $ 2 #10x1" S-TAP SCREW P/H 8.00 $ 1 $ 0 TY-524M T&B TY-RAP(5") 10,124.00 $ 3,227 $ 0 TY-525M T&B TY-RAP(7") 147.00 $ 35 $ 0 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost TY-526M T&B TY-RAP(11") 80.00 $ 28 $ 0 5/8"x10'CU CLAD GRD ROD 9.00 $ 414 $ 46 3/4"x10'CU CLAD GRD ROD 20.00 $ 849 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 5/8 GRD ROD CLAMP 9.00 $ 46 $ 5 3/4 GRD ROD CLAMP 20.00 $ 134 $ 7 GRND SCR W/12SOL PIGTAIL 4.00 $ 1 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 CONC TEST WELL 9.00 $ 1,035 $ 115 CONC TEST WELL COVER 9.00 $ 405 $ 45 YGHP29C2 250-#2 FIG 6 30.00 $ 1,517 $ 51 GAR3905BU 5" IPS 6.00 $ 1,950 $ 325 FIXTURE HOOK 32.00 $ 320 $ 10 FUSE HOLDER 27.00 $ 648 $ 24 2/C#12 6'FIXTURE WHIP 4.00 $ 1 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - 20'STEEL POLE(INCLUDED W/FIXTURE PRICE) 9.00 $ - $ - 3/4 EFS218 1G D/P SW XPL 2.00 $ 248 $ 124 CONDUIT TAGS 916.00 $ 9,160 $ 10 CABLE TRAY PASS-THRU GND LUG 113.00 $ 2,373 $ 21 Cable Tray>Strut-Clamp 226.00 $ 1,354 $ 6 S/S 1/2"CONDUIT DRAIN 19.00 $ 2,580 $ 136 SS STANCHION 3.00 $ 2,250 $ 750 LCP/LCS ORT/SAT TESTING 3.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 885.00 $ - $ - FIXTURE DEFLECTION CABLE 32.00 $ 1,120 $ 35 36"SLOPED TRAY COVER-LF 1,130.00 $ 28,250 $ 25 STRAIGHT SECT.COVERS 36"W-LF 0.00 $ - 35 BLOWER BLDG W-Exterior Wall Pack 5.00 $ 3,070 $ 614 WE-Exterior Wall Pack w/Em. Ballast 2.00 $ 1,542 $ 771 X-Exit Sign,Wall Mt. 2.00 $ 932 $ 466 E-Em.Bug-eye 2.00 $ 728 $ 364 H-Highbay LED, Damp Loc.,Suspended 12.00 $ 2,112 $ 176 J-4'Enclosed Ind. LED,Suspended 14.00 $ 37,506 $ 2,679 E2-Em.Bug-eye,Wet Location 4.00 $ 21,220 $ 5,305 OFCI PLC-35 BLOWER 1.00 $ - $ - OFCI PLC-35 BLOWER RIO 1 1.00 $ - $ - OFCI PLC-35 BLOWER RIO 2 1.00 $ - $ - 35-BLWR-LCP-VFCI 5.00 $ - $ - 1"EMT 30.00 $ 43 $ 1 2"EMT 70.00 $ 244 $ 3 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"EMT STL COMP CONN 2.00 $ 22 $ 11 2"EMT STL COMP CONN 4.00 $ 186 $ 46 1"EMT STL COMP CPLG 3.00 $ 17 $ 6 2"EMT STL COMP CPLG 7.00 $ 144 $ 21 1"EMT STRUT CLAMP 4.00 $ 5 $ 1 2"EMT STRUT CLAMP 9.00 $ 28 $ 3 2"EMT 90 FIELD BEND 6.00 $ 18 $ 3 3/4"GRC 1,256.00 $ 3,818 $ 3 1"GRC 110.00 $ 486 $ 4 3"GRC 600.00 $ 11,532 $ 19 3/4"GRC MYERS HUB W/G 36.00 $ 332 $ 9 1"GRC MYERS HUB W/G 1.00 $ 12 $ 12 3"GRC MYERS HUB W/G 40.00 $ 2,327 $ 58 3/4"GRC COUPLING 30.00 $ 206 $ 7 3"GRC COUPLING 80.00 $ 5,939 $ 74 3/4"GRC ERICKSON CPLG 3.00 $ 55 $ 18 1"GRC ERICKSON CPLG 1.00 $ 22 $ 22 3/4"GRC LB CONDULET 0.00 $ - 1"GRC LB CONDULET 1.00 $ 25 $ 25 3/4"GRC T CONDULET 33.00 $ 678 $ 21 1"GRC T CONDULET 4.00 $ 125 $ 31 3/4" COVER 33.00 $ 166 $ 5 1" COVER 4.00 $ 28 $ 7 3/4"NEOPRENE GASKET 33.00 $ 141 $ 4 1"NEOPRENE GASKET 4.00 $ 23 $ 6 3/4"GRC 90 ELBOW 30.00 $ 589 $ 20 3/4"INS STL GRD BUSHING 30.00 $ 179 $ 6 3/4x 1/2 RED BUSHING 47.00 $ 202 $ 4 3/4"GRC STRUT CLAMP 88.00 $ 68 $ 1 1"GRC STRUT CLAMP 14.00 $ 12 $ 1 3"GRC STRUT CLAMP 90.00 $ 147 $ 2 3/4"GRC CUT&THREAD 51.00 $ - $ - 1"GRC CUT&THREAD 4.00 $ - $ - 3"GRC CUT&THREAD 80.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 13.00 $ - $ - 3"GRC 90 FIELD BEND 50.00 $ - $ - 2"PVC CONDUIT PLUG 4.00 $ 7 $ 2 1/2"LT FLEX 132.00 $ 113 $ 1 3"LT FLEX 30.00 $ 316 $ 11 1/2"LT STRAIGHT CONN 47.00 $ 343 $ 7 3"LT STRAIGHT CONN 10.00 $ 3,718 $ 372 1/2"LT 90DEG CONN 47.00 $ 581 $ 12 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3"LT 90DEG CONN 10.00 $ 5,877 $ 588 3/8"S/S CONCRETE ANCHOR 217.00 $ 1,992 $ 9 1/2"S/S SADDLE WASHER 170.00 $ 230 $ 1 1/4"S/S WASHER 8.00 $ 6 $ 1 3/8"S/S WASHER 580.00 $ 667 $ 1 1/2"S/S ALL THREAD 340.00 $ 2,958 $ 9 1 5/8"S/S CHANNEL 119.00 $ 2,394 $ 20 1/4-20X2" BOLT(SS) 4.00 $ 5 $ 1 3/8-16x1" BOLT(SS) 450.00 $ 581 $ 1 3/8"SS SPRING NUT 174.00 $ 1,660 $ 10 STRUT L-JOINER(SS) 272.00 $ 21,616 $ 79 CORNER ANGLE(SS) 101.00 $ 8,026 $ 79 #14 XHHW 240.00 $ 46 $ 0 #10 XHHW 84.00 $ 33 $ 0 #14 XHHW 880.00 $ 167 $ 0 #10XHHW 1,650.00 $ 644 $ 0 #1 XHHW 1,050.00 $ 2,730 $ 3 #350MCM XHHW 3,150.00 $ 32,634 $ 10 #410 BARE-CU 1,200.00 $ 8,148 $ 7 #10/3C W/G TRAY CABLE TC-ER 625.00 $ 1,238 $ 2 373/3+GRD VFD TC-ER CABLE 1,150.00 $ 90,344 $ 79 #14/3C FCC SHLD 575.00 $ 506 $ 1 #14/7C FCC SHLD 575.00 $ 1,093 $ 2 4/0 HYPRESS 2-HOLE LUG 4.00 $ 76 $ 19 RED WIRE NUT 36.00 $ 7 $ 0 RED WIRE NUT 42.00 $ 17 $ 0 WIRE MARKER 360.00 $ 720 $ 2 CABLE TAG 92.00 $ 460 $ 5 CONDUIT MEASURING TAPE 1,010.00 $ 32 $ 0 # 12 WIRE TERM-POWER 84.00 $ - $ - # 10 WIRE TERM-POWER 51.00 $ - $ - # 1 WIRE TERM-POWER 40.00 $ - $ - #350 MCM TERM-POWER 120.00 $ - $ - #14 WIRE TERM-CONTROL 172.00 $ - $ - 4x1-1/2"SQ BOX COMB KO 4.00 $ 8 $ 2 4"SQ 1G PL-RING 1/2"RISE 4.00 $ 5 $ 1 GROUND SCREW W/INSUL#12 LEAD 4.00 $ 16 $ 4 FD 1GANG BOX 8.00 $ 254 $ 32 1-IN COND TRAY CLAMP 20.00 $ 1,769 $ 88 36"AL SOLID TRAY 3"D 680.00 $ 65,334 $ 96 36"AL SLD HORZ90 ELB 4.00 $ 1,700 $ 425 36"AL SLD HOR90 ELB COVER 4.00 $ 160 $ 40 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 36"AL TRAY WALL FLANGE 8.00 $ 3,000 $ 375 AL TRAY DIVIDER 170.00 $ 2,040 $ 12 AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 20A 120-277V 3/W SW(SG) 4.00 $ 20 $ 5 DS32 FS SWITCH COVER 2.00 $ 14 $ 7 DS128 FS WP SWITCH COVER 2.00 $ 133 $ 67 1 5/8"SLOTTED STRUT S/S 1,714.00 $ 34,486 $ 20 3-1/4"SOLID STRUT S/S 425.00 $ 16,061 $ 38 3/8"SPRING NUT S/S 334.00 $ 3,186 $ 10 #6-8 PL ANCHOR W/SCREW(3/16) 8.00 $ 1 $ 0 3/8"WEDGE ANCHOR S/S 80.00 $ 734 $ 9 1/2"WEDGE ANCHOR 85.00 $ 208 $ 2 1/2 ANCHOR S/S 158.00 $ 3,655 $ 23 1/2"PLATED T-ROD 165.00 $ 339 $ 2 12 FIXTURE SUSPENSION CABLE 84.00 $ 9 $ 0 SUSPENSION CABLE END CONNECTORS 56.00 $ 9 $ 0 1/4-20X2" BOLT S/S 8.00 $ 4 $ 1 3/8-16x1" BOLT S/S 356.00 $ 459 $ 1 1/2-13x2" BOLT S/S 32.00 $ 163 $ 5 1/4-20 HEX NUT S/S 8.00 $ 37 $ 5 3/8-16 HEX NUT S/S 22.00 $ 12 $ 1 1/2-13 HEX NUT S/S 423.00 $ 516 $ 1 1/4" FLAT WASHER S/S 8.00 $ 6 $ 1 3/8" FLAT WASHER S/S 30.00 $ 35 $ 1 1/4" LOCK WASHER S/S 8.00 $ 6 $ 1 3/8" LOCK WASHER S/S 548.00 $ 630 $ 1 1/2" LOCK WASHER S/S 32.00 $ 68 $ 2 3/8" FENDER WASHER S/S 482.00 $ 554 $ 1 1/2" FENDER WASHER S/S 285.00 $ 607 $ 2 #10x1" S-TAP SCREW P/H 8.00 $ 1 $ 0 TY-525M T&B TY-RAP(7") 70.00 $ 17 $ 0 TY-528M T&B TY-RAP(14") 460.00 $ 387 $ 1 3/4"x10'CU CLAD GRD ROD 8.00 $ 340 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 8.00 $ 54 $ 7 GRND SCR W/12SOL PIGTAIL 4.00 $ 1 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 6.00 $ 303 $ 51 GAR3905BU 5" IPS 1.00 $ 325 $ 325 FIXTURE HOOK 24.00 $ 240 $ 10 2/C#12 6'FIXTURE WHIP 4.00 $ 1 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost CAT6 CABLE 800.00 $ 200 $ 0 CAT6 WP CABLE 220.00 $ 96 $ 0 CAT 6 MODULE 10.00 $ 7 $ 1 CAT6 TERM 10.00 $ 40 $ 4 Copper Link Test Category 6 10.00 $ - $ - CONDUIT TAGS 116.00 $ 1,160 $ 10 CABLE TRAY PASS-THRU GND LUG 34.00 $ 714 $ 21 Cable Tray>Strut-Clamp 85.00 $ 509 $ 6 SEISMIC BRACE 85.00 $ 22,525 $ 265 SS STANCHION 5.00 $ 3,750 $ 750 PLC ORT/SAT TESTING 3.00 $ - $ - LCP/LCS ORT/SAT TESTING 5.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 180.00 $ - $ - FIXTURE DEFLECTION CABLE 52.00 $ 1,820 $ 35 36"SLOPED TRAY COVER-LF 510.00 $ 12,750 $ 25 STRAIGHT SECT.COVERS 36"W-LF 170.00 $ 7,650 $ 45 40 CLARIFIERS/SLUDGE/PUMP ROOM W-Exterior Wall Pack 4.00 $ 2,456 $ 614 X-Exit Sign,Wall Mt. 2.00 $ 932 $ 466 EX2-Em. Bug-eye,C1D2 Location 7.00 $ 25,774 $ 3,682 K-4'Enclosed Ind.LED, Damp Loc., Suspended 8.00 $ 29,696 $ 3,712 P4, 16'-Pole mt., Double head, 180*LED, 16'pole 4.00 $ 22,664 $ 5,666 E2-Em.Bug-eye,Wet Location 1.00 $ 5,305 $ 5,305 P1 -Pole Mt., Single head LED, 10'pole 14.00 $ 13,888 $ 992 KE-4'Enclosed Ind. LED, Damp Loc.,Suspended w/Em Ballast 2.00 $ 4,198 $ 2,099 MX2-4'Enclosed LED, C1D2 Location 15.00 $ 5,835 $ 389 WX2-Exterior Wall Pack, Cl D2 4.00 $ 1,556 $ 389 40-CLFR-LCS 20.00 $ - $ - 3/4"GRC 1,440.00 $ 4,378 $ 3 1"GRC 575.00 $ 2,542 $ 4 1/2"GRC MYERS HUB W/G 4.00 $ 36 $ 9 3/4"GRC MYERS HUB W/G 27.00 $ 249 $ 9 1"GRC MYERS HUB W/G 12.00 $ 139 $ 12 3/4"GRC COUPLING 6.00 $ 41 $ 7 1"GRC COUPLING 7.00 $ 69 $ 10 3/4"GRC ERICKSON CPLG 10.00 $ 183 $ 18 1"GRC ERICKSON CPLG 1.00 $ 22 $ 22 3/4"GRC LB CONDULET 13.00 $ 212 $ 16 1"GRC LB CONDULET 1.00 $ 25 $ 25 3/4"GRC T CONDULET 44.00 $ 904 $ 21 1"GRC T CONDULET 7.00 $ 218 $ 31 3/4" COVER 26.00 $ 131 $ 5 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1" COVER 7.00 $ 49 $ 7 3/4"NEOPRENE GASKET 26.00 $ 111 $ 4 1"NEOPRENE GASKET 7.00 $ 40 $ 6 1"GRC 90 ELBOW 1.00 $ 31 $ 31 3/4"INS STL GRD BUSHING 156.00 $ 928 $ 6 1" INS STL GRD BUSHING 60.00 $ 404 $ 7 3/4x 1/2 RED BUSHING 39.00 $ 168 $ 4 1 x 1/2 RED BUSHING 6.00 $ 51 $ 8 1 x 3/4 RED BUSHING 5.00 $ 39 $ 8 3/4"GRC STRUT CLAMP 138.00 $ 107 $ 1 1"GRC STRUT CLAMP 60.00 $ 53 $ 1 1/2"EYS-116 (C-H) 4.00 $ 93 $ 23 3/4"EYS-216 (C-H) 29.00 $ 789 $ 27 1"EYS-316 (C-H) 2.00 $ 68 $ 34 3/4"EYS-26 (C-H) 5.00 $ 141 $ 28 1/2"xCLOSE NIPPLE 4.00 $ 14 $ 4 3/4"xCLOSE NIPPLE 18.00 $ 83 $ 5 3/4"GRC CUT&THREAD 170.00 $ - $ - 1"GRC CUT&THREAD 46.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 43.00 $ - $ - 3/4"PVC COATED GRC 1,440.00 $ 9,821 $ 7 1"PVC COATED GRC 25.00 $ 221 $ 9 3/4"PVC/CTD KO HUB CONN 48.00 $ 3,370 $ 70 1"PVC/CTD KO HUB CONN W/G 1.00 $ 75 $ 75 3/4"PVC/CTD GRC CPLG 96.00 $ 682 $ 7 1"PVC/CTD GRC CPLG 1.00 $ 9 $ 9 3/4"PVC COATED LB FORM 7 48.00 $ 3,436 $ 72 1"PVC COATED T FORM 7 1.00 $ 159 $ 159 3/4"PVC/CTD 1-H STL STRAP 192.00 $ 2,884 $ 15 1"PVC/CTD STRUT STRAP 4.00 $ 71 $ 18 3/4"PVC/CTD CLAMPBACK 192.00 $ 4,360 $ 23 1/2"LT FLEX 132.00 $ 113 $ 1 3/4"LT FLEX 30.00 $ 41 $ 1 1"LT FLEX 28.00 $ 73 $ 3 1/2"LT STRAIGHT CONN 33.00 $ 241 $ 7 3/4"LT STRAIGHT CONN 11.00 $ 116 $ 11 1"LT STRAIGHT CONN 1.00 $ 16 $ 16 1/2"LT 90DEG CONN 33.00 $ 408 $ 12 3/4"LT 90DEG CONN 11.00 $ 211 $ 19 1"LT 90DEG CONN 1.00 $ 39 $ 39 3/8"S/S CONCRETE ANCHOR 20.00 $ 184 $ 9 1/4"S/S WASHER 30.00 $ 23 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8"S/S WASHER 600.00 $ 690 $ 1 1/2"S/S WASHER 100.00 $ 213 $ 2 1/4"S/S NUT 2.00 $ 1 $ 0 1/4-20x1" BOLT(SS) 2.00 $ 1 $ 1 3/8-16x1" BOLT(SS) 626.00 $ 808 $ 1 1/2-13x1" BOLT(SS) 100.00 $ 145 $ 1 1/4"SS SPRING NUT 6.00 $ 28 $ 5 3/8"SS SPRING NUT 200.00 $ 1,908 $ 10 STRUT L-JOINER(SS) 400.00 $ 31,788 $ 79 #12 XHHW 450.00 $ 117 $ 0 #10 XHHW 846.00 $ 330 $ 0 #10XHHW 1,796.00 $ 700 $ 0 #8 XHHW 6,070.00 $ 4,188 $ 1 #6 BARE-CU 32.00 $ 27 $ 1 #410 BARE-CU 2,250.00 $ 15,278 $ 7 #14/7C THHN TRAY CABLE 17,850.00 $ 29,453 $ 2 #10/3C W/G TRAY CABLE TC-ER 3,015.00 $ 5,970 $ 2 #10/3C W/G TRAY CABLE TC-ER 5,300.00 $ 10,494 $ 2 #6/3C W/G SHLD VFD CABLE TC-ER 2,800.00 $ 25,984 $ 9 1-H CRIMP LUG#6 BLUE 2.00 $ 10 $ 5 4/0 HYPRESS 2-HOLE LUG 30.00 $ 568 $ 19 RED WIRE NUT 192.00 $ 79 $ 0 WIRE MARKER 568.00 $ 1,136 $ 2 CABLE TAG 279.00 $ 1,395 $ 5 CONDUIT MEASURING TAPE 75.00 $ 2 $ 0 POLYTWINE 298.00 $ 4 $ 0 # 12 WIRE TERM-POWER 180.00 $ - $ - # 10 WIRE TERM-POWER 158.00 $ - $ - # 6 WIRE TERM-POWER 30.00 $ - $ - #24 WIRE TERM-CONTROL 8.00 $ - $ - #22 WIRE TERM-CONTROL 16.00 $ - $ - #18 WIRE TERM-CONTROL 4.00 $ - $ - #14 WIRE TERM-CONTROL 952.00 $ - $ - 4x1-1/2"SQ BOX COMB KO 2.00 $ 4 $ 2 4"SQ 1G PL-RING 1/2"RISE 2.00 $ 2 $ 1 GROUND SCREW W/INSUL#12 LEAD 10.00 $ 40 $ 4 FD 1GANG BOX 16.00 $ 508 $ 32 1-IN COND TRAY CLAMP 2.00 $ 177 $ 88 36"AL SOLID TRAY 3"D 1,000.00 $ 96,080 $ 96 36"AL SLD HORZ90 ELB 2.00 $ 850 $ 425 36"AL SLD HORZ T SECT 6.00 $ 2,550 $ 425 36"AL SLD VRT90 INSIDE 4.00 $ 1,700 $ 425 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 36"AL SLD VRT90 OUTSIDE 4.00 $ 1,700 $ 425 36"AL SLD HOR90 ELB COVER 2.00 $ 80 $ 40 36"AL SLD HOR T SECT 6.00 $ 240 $ 40 36"AL SLD VRT90 INSIDE COVER 4.00 $ 160 $ 40 36"AL SLD VRT90 OUTSIDE COVER 4.00 $ 160 $ 40 36"AL TRAY WALL FLANGE 4.00 $ 1,500 $ 375 AL TRAY DIVIDER 500.00 $ 6,000 $ 12 AL TRAY EXPANSION JOINT 6.00 $ 1,002 $ 167 20A 120-277V D/P SW(SG) 5.00 $ 48 $ 10 DS128 FS WP SWITCH COVER 5.00 $ 333 $ 67 1 5/8"SLOTTED STRUT S/S 2,200.00 $ 44,264 $ 20 3-1/4"SOLID STRUT S/S 625.00 $ 23,619 $ 38 3/8"SPRING NUT S/S 200.00 $ 1,908 $ 10 BEAM CLAMP P-2676(1/2") 100.00 $ 2,964 $ 30 #6-8 PL ANCHOR W/SCREW(3/16) 4.00 $ 0 $ 0 3/8"DROP IN ANCHOR S/S 50.00 $ 375 $ 7 3/8"WEDGE ANCHOR S/S 200.00 $ 1,836 $ 9 1/2 ANCHOR S/S 205.00 $ 4,742 $ 23 12 FIXTURE SUSPENSION CABLE 150.00 $ 17 $ 0 SUSPENSION CABLE END CONNECTORS 100.00 $ 16 $ 0 1/4-20X2" BOLT S/S 16.00 $ 8 $ 1 3/8-16x1" BOLT S/S 276.00 $ 356 $ 1 1/2-13x2" BOLT S/S 136.00 $ 691 $ 5 1/4-20 HEX NUT S/S 16.00 $ 74 $ 5 3/8-16 HEX NUT S/S 76.00 $ 40 $ 1 1/2-13 HEX NUT S/S 556.00 $ 678 $ 1 1/4" FLAT WASHER S/S 16.00 $ 12 $ 1 3/8" FLAT WASHER S/S 136.00 $ 156 $ 1 1/2" FLAT WASHER S/S 56.00 $ 119 $ 2 1/4" LOCK WASHER S/S 16.00 $ 12 $ 1 3/8" LOCK WASHER S/S 476.00 $ 547 $ 1 1/2" LOCK WASHER S/S 136.00 $ 290 $ 2 3/8" FENDER WASHER S/S 400.00 $ 460 $ 1 1/2" FENDER WASHER S/S 330.00 $ 703 $ 2 #10x1" S-TAP SCREW P/H 4.00 $ 1 $ 0 TY-524M T&B TY-RAP(5") 2,204.00 $ 702 $ 0 TY-525M T&B TY-RAP(7") 42.00 $ 10 $ 0 5/8"x10'CU CLAD GRD ROD 2.00 $ 92 $ 46 3/4"x10'CU CLAD GRD ROD 20.00 $ 849 $ 42 GRD ROD WELLS W/CVR 2.00 $ 92 $ 46 5/8 GRD ROD CLAMP 2.00 $ 10 $ 5 3/4 GRD ROD CLAMP 20.00 $ 134 $ 7 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost GRND SCR W/12SOL PIGTAIL 2.00 $ 1 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 CONC TEST WELL 2.00 $ 230 $ 115 CONC TEST WELL COVER 2.00 $ 90 $ 45 YGHP29C2 250-#2 FIG 6 30.00 $ 1,517 $ 51 GAR3905BU 5" IPS 6.00 $ 1,950 $ 325 48"2LAMP EXPLOSION PROOF FIX. (INCLUDED IN FIXTURE PIRICE) 15.00 $ - $ - FUSE HOLDER 6.00 $ 144 $ 24 2/C#12 6'FIXTURE WHIP 2.00 $ 1 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - 10'STEEL POLE(INCLUDED W/FIXTURE PRICE) 14.00 $ - $ - 16'STEEL POLE(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - Core Drill(LAYOUT ONLY) 9.00 $ - $ - WALL SLEEVE 2" 9.00 $ 189 $ 21 3/4 EFS218 1G D/P SW XPL 5.00 $ 620 $ 124 CAT6 CABLE 70.00 $ 18 $ 0 CONDUIT TAGS 229.00 $ 2,290 $ 10 CABLE TRAY PASS-THRU GND LUG 100.00 $ 2,100 $ 21 Cable Tray>Strut-Clamp 200.00 $ 1,198 $ 6 S/S 1/2"CONDUIT DRAIN 12.00 $ 1,629 $ 136 SS STANCHION 20.00 $ 15,000 $ 750 LCP/LCS ORT/SAT TESTING 20.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 252.00 $ - $ - 3/4"OET2 C1 D2 T COND(C-H) 19.00 $ 2,375 $ 125 4 Element Access Control Cable 18-04+22-3P+22-02+22-04 Plenum Yellow 112.00 $ 114 $ 1 FIXTURE DEFLECTION CABLE 20.00 $ 700 $ 35 36"SLOPED TRAY COVER-LF 1,000.00 $ 25,000 $ 25 STRAIGHT SECT.COVERS 36"W-LF 0.00 $ - 50 FILTRATION WE-Exterior Wall Pack w/Em. Ballast 2.00 $ 1,542 $ 771 X-Exit Sign,Wall Mt. 2.00 $ 932 $ 466 E2-Em.Bug-eye,Wet Location 2.00 $ 10,610 $ 5,305 P1 -Pole Mt.,Single head LED, 10'pole 6.00 $ 5,952 $ 992 50-PNL-001-01 225A 480V NEMA 4X 1.00 $ 6,232 $ 6,232 50-XFMR-001-01 15KVA 480-208/120V 3R SS 1.00 $ 8,131 $ 8,131 50-PNL-001-02 225A 208/120V NEMA 4X 1.00 $ 10,445 $ 10,445 50-FILT-GO-NO/GO 3.00 $ - $ - 50-FILT-LCP-VFCI 4.00 $ - $ - 3/4"GRC 320.00 $ 973 $ 3 2"GRC 50.00 $ 492 $ 10 3/4"GRC MYERS HUB W/G 0.00 $ - 2"GRC MYERS HUB W/G 2.00 $ 45 $ 22 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 2"GRC COUPLING 5.00 $ 115 $ 23 3/4"GRC ERICKSON CPLG 4.00 $ 73 $ 18 3/4"GRC LB CONDULET 4.00 $ 65 $ 16 3/4"GRC T CONDULET 10.00 $ 206 $ 21 3/4" COVER 2.00 $ 10 $ 5 3/4"NEOPRENE GASKET 2.00 $ 9 $ 4 2" INS STL GRD BUSHING 2.00 $ 23 $ 12 3/4x 1/2 RED BUSHING 122.00 $ 524 $ 4 3/4"GRC STRUT CLAMP 40.00 $ 31 $ 1 2"GRC STRUT CLAMP 7.00 $ 9 $ 1 3/4"EYS-216 (C-H) 4.00 $ 109 $ 27 3/4"EYS-26 (C-H) 6.00 $ 169 $ 28 3/4"x8"ECGJH-28 (C-H) 120.00 $ 27,661 $ 231 3/4"GRC CUT&THREAD 614.00 $ - $ - 2"GRC CUT&THREAD 5.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 13.00 $ - $ - 2"GRC 90 FIELD BEND 5.00 $ - $ - 3/4"PVC COATED GRC 11,180.00 $ 76,248 $ 7 1"PVC COATED GRC 115.00 $ 1,015 $ 9 3/4"PVC/CTD KO HUB CONN 242.00 $ 16,988 $ 70 1"PVC/CTD KO HUB CONN W/G 10.00 $ 750 $ 75 3/4"PVC/CTD GRC CPLG 481.00 $ 3,415 $ 7 1"PVC/CTD GRC CPLG 5.00 $ 46 $ 9 3/4"PVC COATED T FORM 7 120.00 $ 16,010 $ 133 3/4"PVC/CTD 90 ELBOW 480.00 $ 12,139 $ 25 3/4"PVC/CTD STRUT STRAP 1,396.00 $ 15,775 $ 11 1"PVC/CTD STRUT STRAP 24.00 $ 424 $ 18 3/4"EYS-26 PVC/CTD 120.00 $ 13,369 $ 111 1/2"LT FLEX 8.00 $ 7 $ 1 3/4"LT FLEX 5.00 $ 7 $ 1 1"LT FLEX 5.00 $ 13 $ 3 1/2"LT STRAIGHT CONN 2.00 $ 15 $ 7 3/4"LT STRAIGHT CONN 1.00 $ 11 $ 11 1"LT STRAIGHT CONN 1.00 $ 16 $ 16 1/2"LT 90DEG CONN 2.00 $ 25 $ 12 3/4"LT 90DEG CONN 1.00 $ 19 $ 19 1"LT 90DEG CONN 1.00 $ 39 $ 39 3/8"S/S CONCRETE ANCHOR 14.00 $ 129 $ 9 1/2"S/S SADDLE WASHER 63.00 $ 85 $ 1 1/4"S/S WASHER 14.00 $ 11 $ 1 3/8"S/S WASHER 163.00 $ 187 $ 1 1/2"S/S ALL THREAD 125.00 $ 1,088 $ 9 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8-16x1" BOLT(SS) 177.00 $ 228 $ 1 3/8"SS SPRING NUT 63.00 $ 601 $ 10 STRUT L-JOINER(SS) 100.00 $ 7,947 $ 79 CORNER ANGLE(SS) 63.00 $ 5,007 $ 79 #10 XHHW 294.00 $ 115 $ 0 #10 XHHW 25,028.00 $ 9,761 $ 0 #8 XHHW 2,295.00 $ 1,584 $ 1 #6 XHHW 670.00 $ 704 $ 1 #4 XHHW 370.00 $ 551 $ 1 #410 XHHW 1,110.00 $ 7,182 $ 6 #4 BARE-CU 6.00 $ 8 $ 1 #410 BARE-CU 1,313.00 $ 8,915 $ 7 #14/7C FCC SHLD 20,700.00 $ 39,330 $ 2 #2 MECH-LUG 2.00 $ 4 $ 2 4/0 HYPRESS 2-HOLE LUG 30.00 $ 568 $ 19 RED WIRE NUT 60.00 $ 25 $ 0 WIRE MARKER 2,912.00 $ 5,824 $ 2 CABLE TAG 16.00 $ 80 $ 5 1"X 3"PHENOLIC NAME PLATE 3.00 $ 14 $ 5 POLYTWINE 4.00 $ 0 $ 0 # 12 WIRE TERM-POWER 28.00 $ - $ - # 10 WIRE TERM-POWER 466.00 $ - $ - # 8 WIRE TERM-POWER 24.00 $ - $ - # 6 WIRE TERM-POWER 32.00 $ - $ - # 4 WIRE TERM-POWER 2.00 $ - $ - #4/0 WIRE TERM-POWER 6.00 $ - $ - #14 WIRE TERM-CONTROL 2,520.00 $ - $ - 4x1-1/2"SQ BOX COMB KO 2.00 $ 4 $ 2 4"SQ 1G PL-RING 1/2"RISE 2.00 $ 2 $ 1 GROUND SCREW W/INSUL#12 LEAD 7.00 $ 28 $ 4 FD 1GANG BOX 3.00 $ 95 $ 32 36"AL SOLID TRAY 3"D 250.00 $ 24,020 $ 96 36"AL SLD HORZ90 ELB 0.00 $ - 36"AL SLD HORZ T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE 0.00 $ - 36"AL SLD VRT90 OUTSIDE 0.00 $ - 36"AL SLD HOR90 ELB COVER 0.00 $ - 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 0.00 $ - 36"AL SLD VRT90 OUTSIDE COVER 0.00 $ - 36"AL TRAY WALL FLANGE 8.00 $ 3,000 $ 375 AL TRAY DIVIDER 125.00 $ 1,500 $ 12 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 20A 120-277V S/P SW(SG) 1.00 $ 5 $ 5 DS128 FS WP SWITCH COVER 1.00 $ 67 $ 67 1 5/8"SLOTTED STRUT S/S 810.00 $ 16,297 $ 20 3-1/4"SOLID STRUT S/S 156.00 $ 5,895 $ 38 3/8"SPRING NUT S/S 260.00 $ 2,480 $ 10 #6-8 PL ANCHOR W/SCREW(3/16) 4.00 $ 0 $ 0 3/8"WEDGE ANCHOR S/S 128.00 $ 1,175 $ 9 1/2"WEDGE ANCHOR 44.00 $ 107 $ 2 1/2 ANCHOR S/S 111.00 $ 2,567 $ 23 1/2"PLATED T-ROD 190.00 $ 391 $ 2 1/4"DRILL&TAP F/SCREW 2.00 $ - $ - 1/4-20X2" BOLT S/S 4.00 $ 2 $ 1 3/8-16x1" BOLT S/S 326.00 $ 421 $ 1 1/2-13x2" BOLT S/S 56.00 $ 284 $ 5 1/4-20 HEX NUT S/S 4.00 $ 19 $ 5 3/8-16 HEX NUT S/S 68.00 $ 36 $ 1 1/2-13 HEX NUT S/S 244.00 $ 298 $ 1 1/4" FLAT WASHER S/S 4.00 $ 3 $ 1 3/8" FLAT WASHER S/S 124.00 $ 143 $ 1 1/2" FLAT WASHER S/S 24.00 $ 51 $ 2 1/4" LOCK WASHER S/S 4.00 $ 3 $ 1 3/8" LOCK WASHER S/S 300.00 $ 345 $ 1 1/2" LOCK WASHER S/S 56.00 $ 119 $ 2 3/8" FENDER WASHER S/S 417.00 $ 480 $ 1 1/2" FENDER WASHER S/S 190.00 $ 405 $ 2 #10x1" S-TAP SCREW P/H 4.00 $ 1 $ 0 TY-525M T&B TY-RAP(7") 296.00 $ 71 $ 0 BPB TESTING 2.00 $ - $ - BPB COMMISSIONING 2.00 $ - $ - XMER TESTING 1.00 $ - $ - XMER COMMISSIONING 1.00 $ - $ - 3/4"x10'CU CLAD GRD ROD 20.00 $ 849 $ 42 GRD ROD WELLS W/CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 20.00 $ 134 $ 7 GRND SCR W/12SOL PIGTAIL 2.00 $ 1 $ 0 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 30.00 $ 1,517 $ 51 GAR3905BU 5" IPS 6.00 $ 1,950 $ 325 2/C#12 6'FIXTURE WHIP 2.00 $ 1 $ 0 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - 10'STEEL POLE(INCLUDED W/FIXTURE PRICE) 6.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost Core Drill(LAYOUT ONLY) 2.00 $ - $ - WALL SLEEVE 2" 2.00 $ 42 $ 21 3/4 EFS218 1G D/P SW XPL 6.00 $ 743 $ 124 CONDUIT TAGS 374.00 $ 3,740 $ 10 CABLE TRAY PASS-THRU GND LUG 25.00 $ 525 $ 21 Cable Tray>Strut-Clamp 63.00 $ 377 $ 6 SEISMIC BRACE 44.00 $ 11,660 $ 265 S/S 1/2"CONDUIT DRAIN 120.00 $ 16,292 $ 136 SS STANCHION 7.00 $ 5,250 $ 750 LCP/LCS ORT/SAT TESTING 7.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 1,513.00 $ - $ - 36"SLOPED TRAY COVER-LF 125.00 $ 3,125 $ 25 STRAIGHT SECT.COVERS 36"W-LF 125.00 $ 5,625 $ 45 55 UV DISINFECTION&W3 PUMPS P1 -Pole Mt., Single head LED, 10'pole 7.00 $ 6,944 $ 992 L-4'Enclosed Ind. LED,Wet Loc., Suspended w/Em Ballast 6.00 $ 2,580 $ 430 55-300kva Nema 3R SS XFMR 480-480/277V 3.00 $ 115,854 $ 38,618 55-UV PANELS 400A 4X 480/277V 3.00 $ 110,537 $ 36,846 VFCI-UV PDU 3.00 $ - $ - 55-UVD-LCP-001 72X36X18 NEMA 4X-VFCI 1.00 $ - $ - 55-UVD-LCS OFCI 3.00 $ - $ - 55-UVD-LCP-002 20x20x10 NEMA 4X-OFCI 1.00 $ - $ - VFCI-UV SCC 1.00 $ - $ - 55-ISP-001 20x20x10 NEMA 4X 1.00 $ - $ - 3/4"GRC 60.00 $ 182 $ 3 1"GRC 90.00 $ 398 $ 4 3"GRC 120.00 $ 2,306 $ 19 4"GRC 15.00 $ 400 $ 27 3/4"GRC MYERS HUB W/G 0.00 $ - 1"GRC MYERS HUB W/G 10.00 $ 116 $ 12 3"GRC MYERS HUB W/G 6.00 $ 349 $ 58 4"GRC MYERS HUB W/G 6.00 $ 464 $ 77 3"GRC COUPLING 6.00 $ 445 $ 74 4"GRC COUPLING 3.00 $ 298 $ 99 3/4"GRC ERICKSON CPLG 1.00 $ 18 $ 18 3/4"GRC LB CONDULET 1.00 $ 16 $ 16 3/4"GRC T CONDULET 7.00 $ 144 $ 21 3/4" COVER 6.00 $ 30 $ 5 3/4"NEOPRENE GASKET 6.00 $ 26 $ 4 1" INS STL GRD BUSHING 6.00 $ 40 $ 7 3" INS STL GRD BUSHING 6.00 $ 149 $ 25 3/4x 1/2 RED BUSHING 33.00 $ 142 $ 4 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1 x 1/2 RED BUSHING 3.00 $ 25 $ 8 3/4"GRC STRUT CLAMP 8.00 $ 6 $ 1 1"GRC STRUT CLAMP 13.00 $ 12 $ 1 3"GRC STRUT CLAMP 15.00 $ 25 $ 2 4"GRC STRUT CLAMP 3.00 $ 14 $ 5 3/4"EYS-216 (C-H) 1.00 $ 27 $ 27 3/4"x8"ECGJH-28 (C-H) 71.00 $ 16,366 $ 231 3/4"GRC CUT&THREAD 225.00 $ - $ - 1"GRC CUT&THREAD 19.00 $ - $ - 3"GRC CUT&THREAD 12.00 $ - $ - 4"GRC CUT&THREAD 3.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 8.00 $ - $ - 3"GRC 90 FIELD BEND 6.00 $ - $ - 3/4"PVC COATED GRC 4,325.00 $ 29,497 $ 7 1"PVC COATED GRC 90.00 $ 795 $ 9 3/4"PVC/CTD KO HUB CONN 142.00 $ 9,968 $ 70 1"PVC/CTD KO HUB CONN W/G 13.00 $ 976 $ 75 3/4"PVC/CTD GRC CPLG 196.00 $ 1,392 $ 7 1"PVC/CTD GRC CPLG 7.00 $ 65 $ 9 3/4"PVC COATED LB FORM 7 44.00 $ 3,150 $ 72 3/4"PVC COATED T FORM 7 27.00 $ 3,602 $ 133 1"PVC COATED T FORM 7 3.00 $ 478 $ 159 3/4"PVC/CTD 90 ELBOW 108.00 $ 2,731 $ 25 1"PVC/CTD 90 ELBOW 8.00 $ 232 $ 29 3/4"PVC/CTD 1-H STL STRAP 264.00 $ 3,965 $ 15 3/4"PVC/CTD STRUT STRAP 321.00 $ 3,627 $ 11 1"PVC/CTD STRUT STRAP 24.00 $ 424 $ 18 3/4"PVC/CTD CLAMPBACK 264.00 $ 5,995 $ 23 3/4"EYS-26 PVC/CTD 71.00 $ 7,910 $ 111 1"EYS-36 PVC/CTD 6.00 $ 763 $ 127 1"PVC BURIED 1,180.00 $ 519 $ 0 1"PVC FEM ADAPTER 26.00 $ 38 $ 1 1"PVC COUPLING 27.00 $ 23 $ 1 1 PVC EXPANSION CPLG 4.00 $ 97 $ 24 1"PVC END BELL 6.00 $ 66 $ 11 1"PVC CONDUIT PLUG 12.00 $ 18 $ 2 PVC CEMENT(1-QUART) 5.00 $ 227 $ 45 2"x3"BASE SPACER 119.00 $ 233 $ 2 1/2"LT FLEX 24.00 $ 20 $ 1 1"LT FLEX 9.00 $ 24 $ 3 4"LT FLEX 15.00 $ 243 $ 16 1/2"LT STRAIGHT CONN 6.00 $ 44 $ 7 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"LT STRAIGHT CONN 3.00 $ 47 $ 16 4"LT STRAIGHT CONN 3.00 $ 1,288 $ 429 1/2"LT 90DEG CONN 6.00 $ 74 $ 12 1"LT 90DEG CONN 3.00 $ 117 $ 39 4"LT 90DEG CONN 3.00 $ 2,999 $ 1,000 3/8"S/S CONCRETE ANCHOR 308.00 $ 2,827 $ 9 1/2"S/S CONCRETE ANCHOR 12.00 $ 278 $ 23 3/8"S/S SADDLE WASHER 4.00 $ 6 $ 2 1/2"S/S SADDLE WASHER 28.00 $ 38 $ 1 1/4"S/S WASHER 16.00 $ 12 $ 1 3/8"S/S WASHER 126.00 $ 145 $ 1 1/2"S/S WASHER 12.00 $ 26 $ 2 1/2"S/S ALL THREAD 55.00 $ 479 $ 9 1 5/8"S/S CHANNEL 64.00 $ 1,288 $ 20 3/8-16x1" BOLT(SS) 96.00 $ 124 $ 1 1/2-13x2" BOLT(SS) 12.00 $ 61 $ 5 3/8"SS SPRING NUT 86.00 $ 820 $ 10 STRUT L-JOINER(SS) 44.00 $ 3,497 $ 79 CORNER ANGLE(SS) 41.00 $ 3,258 $ 79 POST BASE(SS) 6.00 $ 782 $ 130 #12 XHHW 108.00 $ 28 $ 0 #10 XHHW 315.00 $ 123 $ 0 #10 XHHW 7,660.00 $ 2,987 $ 0 #8XHHW 1,400.00 $ 966 $ 1 #3XHHW 1,320.00 $ 2,416 $ 2 #500MCM XHHW 4,035.00 $ 59,476 $ 15 #410 BARE-CU 1,138.00 $ 7,727 $ 7 #10/3C W/G TRAY CABLE TC-ER 485.00 $ 960 $ 2 #14/3C FCC SHLD 3,080.00 $ 2,710 $ 1 #14/7C FCC SHLD 1,890.00 $ 3,591 $ 2 #14/12C FCC SHLD(FLAG) 2,700.00 $ 5,130 $ 2 #6/3C W/G SHLD VFD CABLE TC-ER 1,455.00 $ 13,502 $ 9 4/0 HYPRESS 2-HOLE LUG 30.00 $ 568 $ 19 RED WIRE NUT 48.00 $ 20 $ 0 WIRE MARKER 1,514.00 $ 3,028 $ 2 CABLE TAG 225.00 $ 1,125 $ 5 1"X 3"PHENOLIC NAME PLATE 22.00 $ 99 $ 5 CONDUIT MEASURING TAPE 3,055.00 $ 96 $ 0 # 12 WIRE TERM-POWER 33.00 $ - $ - # 10 WIRE TERM-POWER 161.00 $ - $ - # 6 WIRE TERM-POWER 18.00 $ - $ - # 3 WIRE TERM-POWER 12.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost #500 MCM TERM-POWER 42.00 $ - $ - #14 WIRE TERM-CONTROL 1,376.00 $ - $ - GROUND SCREW W/INSUL#12 LEAD 8.00 $ 32 $ 4 10x1 Ox 6"LCF-BOX NEMA4 1.00 $ 64 $ 64 FD 1GANG BOX 8.00 $ 254 $ 32 3-IN COND TRAY CLAMP 6.00 $ 2,168 $ 361 36"AL SOLID TRAY 3"D 110.00 $ 10,569 $ 96 36"AL SLD HORZ90 ELB 0.00 $ - 36"AL SLD HORZ T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE 0.00 $ - 36"AL SLD VRT90 OUTSIDE 0.00 $ - 36"AL SOLID COVER 110.00 $ 1,650 $ 15 36"AL SLD HOR90 ELB COVER 0.00 $ - 36"AL SLD HOR T SECT 0.00 $ - 36"AL SLD VRT90 INSIDE COVER 0.00 $ - 36"AL SLD VRT90 OUTSIDE COVER 0.00 $ - 36"AL TRAY WALL FLANGE 8.00 $ 3,000 $ 375 AL TRAY DIVIDER 55.00 $ 660 $ 12 AL TRAY EXPANSION JOINT 4.00 $ 668 $ 167 20A 120-277V D/P SW(SG) 8.00 $ 77 $ 10 DS128 FS WP SWITCH COVER 8.00 $ 533 $ 67 1 5/8"SLOTTED STRUT S/S 422.00 $ 8,491 $ 20 3-1/4"SOLID STRUT S/S 69.00 $ 2,608 $ 38 3/8"SPRING NUT S/S 158.00 $ 1,507 $ 10 3/8"DROP IN ANCHOR S/S 12.00 $ 90 $ 7 3/8"WEDGE ANCHOR S/S 80.00 $ 734 $ 9 1/2"WEDGE ANCHOR 26.00 $ 64 $ 2 1/2 ANCHOR S/S 136.00 $ 3,146 $ 23 1/2"PLATED T-ROD 150.00 $ 308 $ 2 12 FIXTURE SUSPENSION CABLE 36.00 $ 4 $ 0 SUSPENSION CABLE END CONNECTORS 24.00 $ 4 $ 0 3/8-16x1" BOLT S/S 218.00 $ 281 $ 1 1/2-13x2" BOLT S/S 112.00 $ 569 $ 5 3/8-16 HEX NUT S/S 60.00 $ 32 $ 1 1/2-13 HEX NUT S/S 158.00 $ 193 $ 1 3/8" FLAT WASHER S/S 120.00 $ 138 $ 1 1/2" FLAT WASHER S/S 28.00 $ 60 $ 2 3/8" LOCK WASHER S/S 182.00 $ 209 $ 1 1/2" LOCK WASHER S/S 124.00 $ 264 $ 2 3/8" FENDER WASHER S/S 249.00 $ 286 $ 1 1/2" FENDER WASHER S/S 187.00 $ 398 $ 2 TY-524M T&B TY-RAP(5") 97.00 $ 31 $ 0 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost TY-525M T&B TY-RAP(7") 517.00 $ 124 $ 0 TY-526M T&B TY-RAP(11") 54.00 $ 19 $ 0 BPB TESTING 3.00 $ - $ - BPB COMMISSIONING 3.00 $ - $ - XMER TESTING 3.00 $ - $ - XMER COMMISSIONING 3.00 $ - $ - 314"x10'CU CLAD GRD ROD 20.00 $ 849 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 20.00 $ 134 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 30.00 $ 1,517 $ 51 GAR3905BU 5" IPS 6.00 $ 1,950 $ 325 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 6.00 $ - $ - 10'STEEL POLE(INCLUDED W/FIXTURE PRICE) 7.00 $ - $ - 3030-LA(2'X2'X2') 1.00 $ 771 $ 771 Core Drill(LAYOUT ONLY) 0.00 $ - WALL SLEEVE 2" 0.00 $ - CONDUIT TAGS 208.00 $ 2,080 $ 10 CABLE TRAY PASS-THRU GND LUG 11.00 $ 231 $ 21 Cable Tray>Strut-Clamp 28.00 $ 168 $ 6 SEISMIC BRACE 26.00 $ 6,890 $ 265 S/S 1/2"CONDUIT DRAIN 30.00 $ 4,073 $ 136 SS STANCHION 16.00 $ 12,000 $ 750 LCP/LCS ORT/SAT TESTING 6.00 $ - $ - VFCI-UV LAMP BANK 9.00 $ - $ - VFCI-UV LL CONTROL BOX 3.00 $ - $ - 1"FIBERGLASS 90 20.00 $ 1,082 $ 54 WIRE TESTING(PER CONDUCTOR) 800.00 $ - $ - FIXTURE DEFLECTION CABLE 12.00 $ 420 $ 35 36"SLOPED TRAY COVER-LF 55.00 $ 1,375 $ 25 STRAIGHT SECT.COVERS 36"W-LF 55.00 $ 2,475 $ 45 60 SOLIDS LOADING BLDG W-Exterior Wall Pack 4.00 $ 2,456 $ 614 WE-Exterior Wall Pack w/Em. Ballast 2.00 $ 1,542 $ 771 H-Highbay LED, Damp Loc.,Suspended 12.00 $ 2,112 $ 176 EX2-Em. Bug-eye,C1 D2 Location 4.00 $ 14,728 $ 3,682 X2-Exit Sign,Cl D2 Locations 1.00 $ 430 $ 430 OFCI PLC-60 SOLIDS 1.00 $ - $ - 60-RDT-LCS 6.00 $ - $ - TRUCK LOADOUT CONTROL PANEL-VFCI 1.00 $ - $ - 60-SOLIDS-LCS 12.00 $ - $ - 60-SOLIDS-GO-NO/GO 4.00 $ - $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 60-ISP-001 20x20x10 NEMA 4X 1.00 $ - $ - 60-POLYBLEND LCP-VFCI 2.00 $ - $ - SOLIDS LOADING- LCP-VFCI 5.00 $ - $ - SOLIDS-LOADING-LCS 3.00 $ - $ - SOLIDS-LOADING-LCP 2.00 $ - $ - 60-PNL-001-01 480V 225A MCB NEMA 4X 1.00 $ 41,566 $ 41,566 60-XFMR-001-01 45KVA NEMA 3R SS 1.00 $ 8,112 $ 8,112 60-PNL-001-02 208/120V 125A MCB NEMA 4X 1.00 $ 10,349 $ 10,349 3/4"GRC 1,393.00 $ 4,235 $ 3 1"GRC 400.00 $ 1,768 $ 4 1 1/2"GRC 5.00 $ 37 $ 7 2"GRC 40.00 $ 394 $ 10 1/2"GRC MYERS HUB W/G 1.00 $ 9 $ 9 3/4"GRC MYERS HUB W/G 27.00 $ 249 $ 9 1"GRC MYERS HUB W/G 16.00 $ 185 $ 12 1 1/2"GRC MYERS HUB W/G 2.00 $ 27 $ 13 2"GRC MYERS HUB W/G 2.00 $ 45 $ 22 3/4"GRC COUPLING 9.00 $ 62 $ 7 1"GRC COUPLING 8.00 $ 79 $ 10 1 1/2"GRC COUPLING 1.00 $ 18 $ 18 3/4"GRC ERICKSON CPLG 3.00 $ 55 $ 18 3/4"GRC LB CONDULET 13.00 $ 212 $ 16 3/4"GRC T CONDULET 47.00 $ 966 $ 21 1"GRC T CONDULET 8.00 $ 249 $ 31 3/4" COVER 47.00 $ 236 $ 5 1" COVER 8.00 $ 56 $ 7 3/4"NEOPRENE GASKET 47.00 $ 201 $ 4 1"NEOPRENE GASKET 8.00 $ 46 $ 6 3/4"INS STL GRD BUSHING 17.00 $ 101 $ 6 1" INS STL GRD BUSHING 16.00 $ 108 $ 7 2" INS STL GRD BUSHING 2.00 $ 23 $ 12 3/4x 1/2 RED BUSHING 26.00 $ 112 $ 4 1 x 1/2 RED BUSHING 8.00 $ 68 $ 8 1 x 3/4 RED BUSHING 8.00 $ 62 $ 8 3/4"GRC STRUT CLAMP 102.00 $ 79 $ 1 1 1/2"GRC STRUT CLAMP 1.00 $ 1 $ 1 2"GRC STRUT CLAMP 1.00 $ 1 $ 1 1/2"EYS-116 (C-H) 1.00 $ 23 $ 23 3/4"EYS-216 (C-H) 0.00 $ - 3/4"EYS-26 (C-H) 1.00 $ 28 $ 28 1"EYS-36 (C-H) 0.00 $ - 3/4"x8"ECGJH-28 (C-H) 0.00 $ - LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 1"-3/4"RE32 REDUCER 0.00 $ - 1/2"xCLOSE NIPPLE 1.00 $ 4 $ 4 3/4"xCLOSE NIPPLE 10.00 $ 46 $ 5 3/4"GRC CUT&THREAD 54.00 $ - $ - 1"GRC CUT&THREAD 24.00 $ - $ - 1 1/2"GRC CUT&THREAD 1.00 $ - $ - 2"GRC CUT&THREAD 1.00 $ - $ - 1 1/4"GRC 90 FIELD BEND 12.00 $ - $ - 1/2"LT FLEX 76.00 $ 65 $ 1 3/4"LT FLEX 57.00 $ 78 $ 1 1"LT FLEX 40.00 $ 105 $ 3 1 1/2"LT FLEX 5.00 $ 20 $ 4 1/2"LT STRAIGHT CONN 19.00 $ 139 $ 7 3/4"LT STRAIGHT CONN 21.00 $ 221 $ 11 1 1/2"LT STRAIGHT CONN 1.00 $ 43 $ 43 1/2"LT 90DEG CONN 19.00 $ 235 $ 12 3/4"LT 90DEG CONN 21.00 $ 403 $ 19 1 1/2"LT 90DEG CONN 1.00 $ 88 $ 88 3/8"S/S CONCRETE ANCHOR 18.00 $ 165 $ 9 1/2"S/S CONCRETE ANCHOR 8.00 $ 185 $ 23 3/8"S/S SADDLE WASHER 4.00 $ 6 $ 2 1/4"S/S WASHER 40.00 $ 30 $ 1 3/8"S/S WASHER 36.00 $ 41 $ 1 1/2"S/S WASHER 8.00 $ 17 $ 2 3/8"S/S NUT 4.00 $ 2 $ 1 1 5/8"S/S CHANNEL 31.00 $ 624 $ 20 3/8-16x1" BOLT(SS) 78.00 $ 101 $ 1 1/2-13x2" BOLT(SS) 24.00 $ 122 $ 5 1/4"SS SPRING NUT 36.00 $ 167 $ 5 3/8"SS SPRING NUT 36.00 $ 343 $ 10 STRUT L-JOINER(SS) 4.00 $ 318 $ 79 STRUT T-JOINER(SS) 4.00 $ 419 $ 105 CORNER ANGLE(SS) 35.00 $ 2,781 $ 79 POST BASE(SS) 4.00 $ 521 $ 130 #14 XHHW 240.00 $ 46 $ 0 #12 XHHW 15.00 $ 4 $ 0 #10 XHHW 72.00 $ 28 $ 0 #12 XHHW 573.00 $ 149 $ 0 #10XHHW 1,544.00 $ 602 $ 0 #8XHHW 1,400.00 $ 966 $ 1 #6 XHHW 100.00 $ 105 $ 1 #4 XHHW 230.00 $ 343 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost #1 XHHW 100.00 $ 260 $ 3 #410 XHHW 690.00 $ 4,464 $ 6 #410 BARE-CU 1,000.00 $ 6,790 $ 7 #10/3C W/G TRAY CABLE TC-ER 460.00 $ 911 $ 2 #10/3C W/G SHLD VFD CABLE TC-ER 1,380.00 $ 5,244 $ 4 #6/3C W/G SHLD VFD CABLE TC-ER 920.00 $ 8,538 $ 9 4/0 HYPRESS 2-HOLE LUG 30.00 $ 568 $ 19 RED WIRE NUT 54.00 $ 10 $ 0 RED WIRE NUT 21.00 $ 9 $ 0 WIRE MARKER 159.00 $ 318 $ 2 CABLE TAG 60.00 $ 300 $ 5 1"X 3"PHENOLIC NAME PLATE 7.00 $ 32 $ 5 CONDUIT MEASURING TAPE 21.00 $ 1 $ 0 POLYTWINE 21.00 $ 0 $ 0 # 12 WIRE TERM-POWER 90.00 $ - $ - # 10 WIRE TERM-POWER 124.00 $ - $ - # 6 WIRE TERM-POWER 32.00 $ - $ - # 4 WIRE TERM-POWER 2.00 $ - $ - # 1 WIRE TERM-POWER 8.00 $ - $ - #4/0 WIRE TERM-POWER 6.00 $ - $ - #24 WIRE TERM-CONTROL 24.00 $ - $ - #22 WIRE TERM-CONTROL 24.00 $ - $ - #18 WIRE TERM-CONTROL 6.00 $ - $ - GROUND SCREW W/INSUL#12 LEAD 1.00 $ 4 $ 4 12x12x 6"LCF-BOX NEMA4 1.00 $ 68 $ 68 FD 1GANG BOX 15.00 $ 476 $ 32 1G WP DPLX RCPT CVR ALUM 5.00 $ 496 $ 99 A-SE12x12x6 SCR CVR NEMA1 1.00 $ 63 $ 63 20A 125V GFI DUP REC(SG) 5.00 $ 50 $ 10 1 5/8"SLOTTED STRUT S/S 190.00 $ 3,823 $ 20 3/8"SPRING NUT S/S 133.00 $ 1,269 $ 10 3/8"WEDGE ANCHOR S/S 80.00 $ 734 $ 9 1/2"WEDGE ANCHOR 18.00 $ 44 $ 2 1/2 ANCHOR S/S 196.00 $ 4,533 $ 23 1/2"PLATED T-ROD 175.00 $ 360 $ 2 1/4-20X2" BOLT S/S 8.00 $ 4 $ 1 3/8-16x1" BOLT S/S 205.00 $ 264 $ 1 1/2-13x2" BOLT S/S 152.00 $ 772 $ 5 1/4-20 HEX NUT S/S 8.00 $ 37 $ 5 3/8-16 HEX NUT S/S 72.00 $ 38 $ 1 1/2-13 HEX NUT S/S 88.00 $ 107 $ 1 1/4" FLAT WASHER S/S 8.00 $ 6 $ 1 LAKE OSWEGO WWTF 10%ELECTRICAL DESIGN TAKEOFF Description Quantity Total Material Material Unit Cost 3/8" FLAT WASHER S/S 132.00 $ 152 $ 1 1/4" LOCK WASHER S/S 8.00 $ 6 $ 1 3/8" LOCK WASHER S/S 125.00 $ 144 $ 1 1/2" LOCK WASHER S/S 160.00 $ 341 $ 2 3/8" FENDER WASHER S/S 213.00 $ 245 $ 1 1/2" FENDER WASHER S/S 240.00 $ 511 $ 2 TY-524M T&B TY-RAP(5") 598.00 $ 191 $ 0 TY-525M T&B TY-RAP(7") 138.00 $ 33 $ 0 20A4P 600V LIGHTING CONTACTOR(1) 1.00 $ 592 $ 592 24HR SPST 277V TIME SW 1.00 $ 274 $ 274 120V PHOTOCONTROL K4141 1.00 $ 13 $ 13 BPB COMMISSIONING 2.00 $ - $ - 30AI600V 3P NON FUS NEMA4X 4.00 $ 16,938 $ 4,234 XMER TESTING 1.00 $ - $ - XMER COMMISSIONING 1.00 $ - $ - 314"x10'CU CLAD GRD ROD 20.00 $ 849 $ 42 GRD ROD WELLS WI CVR 2.00 $ 92 $ 46 3/4 GRD ROD CLAMP 20.00 $ 134 $ 7 CHATSWORTH 4"X 1/4"X 12"GND BAR ASSEMBLIE 1.00 $ 168 $ 168 YGHP29C2 250-#2 FIG 6 30.00 $ 1,517 $ 51 GAR3905BU 5" IPS 6.00 $ 1,950 $ 325 FIXTURE HOOK 24.00 $ 240 $ 10 EMERGENCY BATTERY BALLAST(INCLUDED W/FIXTURE PRICE) 2.00 $ - $ - Core Drill(LAYOUT ONLY) 0.00 $ - WALL SLEEVE 2" 0.00 $ - 3/4 EFS218 1G D/P SW XPL 1.00 $ 124 $ 124 CAT6 CABLE 266.00 $ 67 $ 0 CONDUIT TAGS 52.00 $ 520 $ 10 SEISMIC BRACE 18.00 $ 4,770 $ 265 S/S 1/2"CONDUIT DRAIN 16.00 $ 2,172 $ 136 SS STANCHION 36.00 $ 27,000 $ 750 PLC ORT/SAT TESTING 1.00 $ - $ - LCP/LCS ORT/SAT TESTING 36.00 $ - $ - VFCI-TJB 2.00 $ - $ - WIRE TESTING(PER CONDUCTOR) 13.00 $ - $ - 4 Element Access Control Cable 18-04+22-3P+22-02+22-04 Plenum Yellow 168.00 $ 171 $ 1 3/4"OET2 C1 D2 T COND(C-H) 1.00 $ 125 $ 125 FIXTURE DEFLECTION CABLE 24.00 $ 840 $ 35 $ 11,163,430 Execution Version TRANSACTION FORM A FORM OF PARENT COMPANY GUARANTY AGREEMENT 4177761.2 047787 [This Page Intentionally Left Blank] 4177761.2 047787 PARENT COMPANY GUARANTY AGREEMENT from JACOBS ENGINEERING GROUP INC. to CITY OF LAKE OSWEGO, OREGON Dated as of , 2026 4177761.2 047787 [This Page Intentionally Left Blank] 4177761.2 047787 TABLE OF CONTENTS Page ARTICLE 1 DEFINITIONS AND INTERPRETATION SECTION 1.1. DEFINITIONS A-2 SECTION 1.2. INTERPRETATION A-2 ARTICLE 2 REPRESENTATIONS AND WARRANTIES OF THE GUARANTOR SECTION 2.1. REPRESENTATIONS AND WARRANTIES OF THE GUARANTOR A-4 ARTICLE 3 GUARANTY COVENANTS SECTION 3.1. GUARANTY TO THE CITY A-6 SECTION 3.2. RIGHT OF CITY TO PROCEED AGAINST GUARANTOR A-6 SECTION 3.3. GUARANTY ABSOLUTE AND UNCONDITIONAL A-6 SECTION 3.4. DEFENSES, SET-OFFS AND COUNTERCLAIMS A-8 SECTION 3.5. WAIVERS BY THE GUARANTOR A-8 SECTION 3.6. PAYMENT OF COSTS AND EXPENSES A-9 SECTION 3.7. SUBORDINATION OF RIGHTS A-9 SECTION 3.8. SEPARATE OBLIGATIONS; REINSTATEMENT A-9 SECTION 3.9. TERM A-10 ARTICLE 4 GENERAL COVENANTS SECTION 4.1. MAINTENANCE OF CORPORATE EXISTENCE A-11 SECTION 4.2. ASSIGNMENT A-11 SECTION 4.3. QUALIFICATION IN OREGON A-11 SECTION 4.4. CONSENT TO JURISDICTION A-11 SECTION 4.5. BINDING EFFECT A-11 SECTION 4.6. AMENDMENTS, CHANGES AND MODIFICATIONS A-12 SECTION 4.7. LIABILITY A-12 SECTION 4.8. NOTICES A-12 SECTION 4.9. ELECTRONIC SIGNATURES A-13 4177761.2 047787 [This Page Intentionally Left Blank] 4177761.2 047787 GUARANTY AGREEMENT THIS GUARANTY AGREEMENT is made and dated as of , 2026, between Jacobs Engineering Group Inc., a corporation organized and existing under the laws of the State of Delaware (together with any permitted successors and assigns hereunder, the "Guarantor"), and the City of Lake Oswego, Oregon (the "City"). RECITALS The City and Jacobs Project Management Co., a corporation organized and existing under the laws of the State of Delaware (the "DBOM Contractor"), have entered into a Design-Build-Operate-Maintain Agreement for the Lake Oswego Wastewater Treatment Facility, dated as of , 2026, as amended from time to time (the "DBOM Agreement"), whereby the DBOM Contractor has agreed to design, construct, commission, acceptance test, operate, maintain and obtain certain governmental approvals for a new wastewater treatment facility in Lake Oswego, Oregon, all as more particularly described therein. The DBOM Contractor is an indirect subsidiary of the Guarantor. Performance by the City and the DBOM Contractor of their obligations under the DBOM Agreement will result in a direct and substantial benefit to the Guarantor. The City will enter into the DBOM Agreement only if, concurrently with its execution and delivery by the DBOM Contractor, the Guarantor guarantees the performance by the DBOM Contractor of all of the DBOM Contractor's Obligations under the DBOM Agreement as set forth in this Guaranty Agreement. In order to induce the execution and delivery of the DBOM Agreement by the City and in consideration thereof, the Guarantor agrees as follows: A-1 4177761.2 047787 ARTICLE 1 DEFINITIONS AND INTERPRETATION SECTION 1.1. DEFINITIONS. For the purposes of this Guaranty, the following words and terms shall have the respective meanings set forth as follows. Any other capitalized word or term used but not defined herein is used as defined in the DBOM Agreement. "Obligations" means the amounts payable by, and the covenants and agreements of, the DBOM Contractor pursuant to the terms of the DBOM Agreement. "Transaction Agreement" means any agreement entered into by the DBOM Contractor or the City in connection with the transactions contemplated by the DBOM Agreement, including the DBOM Agreement, and any supplements thereto. SECTION 1.2. INTERPRETATION. In this Guaranty, unless the context otherwise requires: (1) References Hereto. The terms "hereby", "hereof', "herein", "hereunder" and any similar terms refer to this Guaranty, and the term "hereafter" means after, and the term "heretofore" means before, the date of execution and delivery of this Guaranty. (2) Plurality. Words importing the singular number mean and include the plural number and vice versa. (3) Persons. Words importing persons include firms, companies, associations, general partnerships, limited partnerships, trusts, business trusts, corporations and other legal entities, including public bodies, as well as individuals. (4) Headings. The table of contents and any headings preceding the text of the Articles, Sections and subsections of this Guaranty shall be solely for convenience of reference and shall not constitute a part of this Guaranty, nor shall they affect its meaning, construction or effect. (5) Entire Agreement. This Guaranty constitutes the entire agreement between the parties hereto with respect to the transactions contemplated by this Guaranty. Nothing in this Guaranty is intended to confer on any person other than the Guarantor, the City and their permitted successors and assigns hereunder any rights or remedies under or by reason of this Guaranty. (6) Counterparts. This Guaranty may be executed in any number of original counterparts. All such counterparts shall constitute but one and the same Guaranty. (7) Applicable Law. This Guaranty shall be governed by and construed in accordance with the applicable laws of the State of Oregon. (8) Severability. If any clause, provision, subsection, Section or Article of this Guaranty shall be ruled invalid by any court of competent jurisdiction, the invalidity of any such clause, provision, subsection, Section or Article shall not affect any of the remaining provisions hereof, and this Guaranty shall be construed and enforced as if such invalid portion did not exist provided that such construction and enforcement shall not increase the Guarantor's liability beyond that expressly set forth herein. A-2 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 1 - Definitions and Interpretation (9) Approvals. All approvals, consents and acceptances required to be given or made by any party hereto shall be at the discretion of the party whose approval, consent or acceptance is required. (10) Payments. All payments required to be made by the Guarantor hereunder shall be made in lawful money of the United States of America. A-3 4177761.2 047787 ARTICLE 2 REPRESENTATIONS AND WARRANTIES OF THE GUARANTOR SECTION 2.1. REPRESENTATIONS AND WARRANTIES OF THE GUARANTOR. The Guarantor hereby represents and warrants that: (1) Existence and Powers. The Guarantor is a corporation duly organized, validly existing and in good standing under the laws of the State of Delaware, with the full legal right, power and authority to enter into and perform its obligations under this Guaranty. (2) Due Authorization and Binding Obligation. This Guaranty has been duly authorized, executed and delivered by all necessary corporate action of the Guarantor and constitutes the legal, valid and binding obligation of the Guarantor, enforceable against the Guarantor in accordance with its terms, except to the extent that its enforceability may be limited by bankruptcy, insolvency or other similar laws affecting creditors'rights from time to time in effect and equitable principles of general application. (3) No Conflict. To the best of its knowledge, neither the execution nor delivery by the Guarantor of this Guaranty nor the performance by the Guarantor of its obligations in connection with the transaction contemplated hereby or the fulfillment by the Guarantor of the terms and conditions hereof: (a) conflicts with, violates or results in a breach of any law or governmental regulation applicable to the Guarantor; (b) conflicts with, violates or results in a breach of any term or condition of the Guarantor's corporate charter or by-laws or any order, judgment or decree, or any contract, agreement or instrument to which the Guarantor is a party or by which the Guarantor or any of its properties or assets are bound, or constitutes a default under any of the foregoing; or (c) will result in the creation or imposition of any material encumbrance of any nature whatsoever upon any of the properties or assets of the Guarantor except as permitted hereby. (4) No Approvals Required. No approval, authorization, order or consent of, or declaration, registration or filing with, any Governmental Body is required for the valid execution and delivery of this Guaranty by the Guarantor or the performance of its payment or other obligations hereunder, except as such shall have been duly obtained or made. (5) No Litigation. Except as disclosed in writing to the City, there is no Legal Proceeding, at law or in equity, before or by any Governmental Body pending or, to the best of the Guarantor's knowledge, overtly threatened or publicly announced against the Guarantor, in which an unfavorable decision, ruling or finding could reasonably be expected to have a material and adverse effect on the validity, legality or enforceability of this Guaranty against the Guarantor, or on the ability of the Guarantor to perform its obligations hereunder. (6) No Legal Prohibition. The Guarantor has no knowledge of any Applicable Law in effect on the date as of which this representation is being made which would prohibit the performance by the Guarantor of this Guaranty and the transactions contemplated by this Guaranty. (7) Consent to Agreements. The Guarantor is fully aware of and consents to the terms and conditions of the DBOM Agreement. A-4 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 2-Representations and Warranties of the Guarantor (8) Consideration. This Guaranty is made in furtherance of the purposes for which the Guarantor has been organized, and the assumption by the Guarantor of its obligations hereunder will result in a material benefit to the Guarantor. (9) Applicable Law Compliance. Except as disclosed in writing to the City, the Guarantor does not have knowledge of any material violation of any law, order, rule or regulation with respect to any facilities designed or constructed by the Guarantor, DBOM Contractor or any of their Affiliates. A-53959418.4 047787 CTR 4177761.2 047787 ARTICLE 3 GUARANTY COVENANTS SECTION 3.1. GUARANTY TO THE CITY. The Guarantor hereby absolutely, presently, irrevocably and unconditionally guarantees to the City for the benefit of the City (1) the full and prompt payment when due of each and all of the payments required to be credited or made by the DBOM Contractor under the DBOM Agreement (including all amendments and supplements thereto) to, or for the account of, the City, when the same shall become due and payable pursuant to this Guaranty, and (2) the full and prompt performance and observance of each and all of the Obligations. Notwithstanding the unconditional nature of the Guarantor's obligations as set forth herein, the Guarantor shall have the right to assert the defenses provided in Section 3.4 hereof against claims made under this Guaranty and, for clarification, the limitations on liability set forth in Section 23.6 of the DBOM Agreement and the exceptions to such limitations set forth in Section 23.7 of the DBOM Agreement are applicable to the Guarantor. SECTION 3.2. RIGHT OF CITY TO PROCEED AGAINST GUARANTOR. This Guaranty shall constitute a guaranty of payment and of performance and not of collection, and the Guarantor specifically agrees that in the event of a failure by the DBOM Contractor to pay or perform any Obligation guaranteed hereunder, the City shall have the right to proceed first and directly against the Guarantor under this Guaranty and without proceeding against the DBOM Contractor or exhausting any other remedies against the DBOM Contractor which the City may have. Without limiting the foregoing, the Guarantor agrees that it shall not be necessary, and that the Guarantor shall not be entitled to require, as a condition of enforcing the liability of the Guarantor hereunder, that the City: (1) file suit or proceed to obtain a personal judgment against the DBOM Contractor or any other person that may be liable for the Obligations or any part of the Obligations; (2) make any other effort to obtain payment or performance of the Obligations from the DBOM Contractor other than providing the DBOM Contractor with any notice of such payment or performance as may be required by the terms of the DBOM Agreement or required to be given to the DBOM Contractor under Applicable Law; (3) foreclose against or seek to realize upon any security for the Obligations; or (4) exercise any other right or remedy to which the City is or may be entitled in connection with the Obligations or any security therefor or any other guarantee thereof, except to the extent that any such exercise of such other right or remedy may be a condition to the Obligations of the DBOM Contractor or to the enforcement of remedies under the DBOM Agreement. Upon any unexcused failure by the DBOM Contractor in the payment or performance of any Obligation and the giving of such notice or demand, if any, to the DBOM Contractor and the Guarantor as may be required in connection with such Obligation and this Guaranty, the liability of the Guarantor shall be effective and shall immediately be paid or performed. Notwithstanding the City's right to proceed directly against the Guarantor, the City(or any successor) shall not be entitled to more than a single full performance of the Obligations in regard to any breach or non-performance thereof. SECTION 3.3. GUARANTY ABSOLUTE AND UNCONDITIONAL. The obligations of the Guarantor hereunder are absolute, present, irrevocable and unconditional and shall remain in full force and effect until the DBOM Contractor shall have fully discharged the Obligations in accordance with their respective terms and conditions, and, except as provided in Section 3.4, shall not be subject to any counterclaim, set-off, deduction or defense (other than full and strict compliance with, or release, discharge or satisfaction of, such Obligations) based on any claim that the Guarantor may have against the DBOM Contractor, the City or any other person. Without limiting the foregoing, the obligations of the Guarantor A-6 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 3-Guaranty Covenants hereunder shall not be released, discharged or in any way modified by reason of any of the following (whether with or without notice to, knowledge by, or further consent, of the Guarantor): (1) the extension or renewal of this Guaranty or the DBOM Agreement up to the specified Terms of each agreement; (2) any exercise or failure, omission or delay by the City in the exercise of any right, power or remedy conferred on the City with respect to this Guaranty or the DBOM Agreement except to the extent such failure, omission or delay gives rise to an applicable statute of limitations defense with respect to a specific claim; (3) any permitted transfer or assignment of rights or obligations under the DBOM Agreement or under any other Transaction Agreement by any party thereto, or any permitted assignment, conveyance or other transfer of any of their respective interests in the Project Facilities or in, to or under any of the Transaction Agreements; (4) any permitted assignment for the purpose of creating a security interest or mortgage of all or any part of the respective interests of the City or any other person in any Transaction Agreement or in the Project Facilities; (5) any renewal, amendment, change or modification in respect of any of the Obligations or terms or conditions of any Transaction Agreement; (6) any failure of title with respect to all or any part of the respective interests of any person in the Project Site or the Project Facilities; (7) the voluntary or involuntary liquidation, dissolution, sale or other disposition of all or substantially all the assets, marshalling of assets and liabilities, receivership, insolvency, bankruptcy, assignment for the benefit of creditors, reorganization, moratorium, arrangement, composition with creditors or readjustment of, or other similar proceedings against the DBOM Contractor or the Guarantor, or any of the property of either of them, or any allegation or contest of the validity of this Guaranty or any other Transaction Agreement in any such proceeding (it is specifically understood, consented and agreed to that, to the extent permitted by law, this Guaranty shall remain and continue in full force and effect and shall be enforceable against the Guarantor to the same extent and with the same force and effect as if any such proceeding had not been instituted and as if no rejection, stay, termination, assumption or modification has occurred as a result thereof, it being the intent and purpose of this Guaranty that the Guarantor shall and does hereby waive all rights and benefits which might accrue to it by reason of any such proceeding); (8) except as permitted by Section 4.1 or 4.2 hereof, any sale or other transfer by the Guarantor or any Affiliate of any of the capital stock or other interest of the Guarantor or any Affiliate in the DBOM Contractor now or hereafter owned, directly or indirectly, by the Guarantor or any Affiliate, or any change in composition of the interests in the DBOM Contractor; (9) any failure on the part of the DBOM Contractor for any reason to perform or comply with any agreement with the Guarantor; (10) the failure on the part of the City to provide any notice to the Guarantor which is not required to be given to the Guarantor pursuant to this Guaranty and to the DBOM Contractor as a condition to the enforcement of Obligations pursuant to the DBOM Agreement; A-73959418.4 047787 CTR 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 3-Guaranty Covenants (11) any failure of any party to the Transaction Agreements to mitigate damages resulting from any default by the DBOM Contractor or the Guarantor under any Transaction Agreement; (12) the merger or consolidation of any party to the Transaction Agreements into or with any other person, or any sale, lease, transfer, abandonment or other disposition of any or all of the property of any of the foregoing to any person; (13) any legal disability or incapacity of any party to the Transaction Agreements; or (14) the fact that entering into any Transaction Agreement by the DBOM Contractor or the Guarantor was invalid or in excess of the powers of such party. Should any money due or owing under this Guaranty not be recoverable from the Guarantor due to any of the matters specified in subparagraphs (1) through (14) above, then, in any such case, such money, together with all additional sums due hereunder, shall nevertheless be recoverable from the Guarantor as though the Guarantor were principal obligor in place of the DBOM Contractor pursuant to the terms of the DBOM Agreement and not merely a guarantor and shall be paid by the Guarantor forthwith subject to the terms of this Guaranty. Notwithstanding anything to the contrary expressed in this Guaranty, nothing in this Guaranty shall be deemed to amend, modify, clarify, expand or reduce the DBOM Contractor's rights, benefits, duties or obligations under the DBOM Agreement. To the extent that any of the matters specified in subparagraphs (1) through (6) and (8) through (14)would provide a defense to, release, discharge or otherwise affect the DBOM Contractor's Obligations, the Guarantor's obligations under this Guaranty shall be treated the same. SECTION 3.4. DEFENSES, SET-OFFS AND COUNTERCLAIMS. Notwithstanding any provision contained herein to the contrary, the Guarantor shall be entitled to exercise or assert any and all legal or equitable rights or defenses which the DBOM Contractor may have under the DBOM Agreement or under Applicable Law (other than bankruptcy or insolvency of the DBOM Contractor and other than any defense which the DBOM Contractor has expressly waived in the DBOM Agreement or the Guarantor has expressly waived in Section 3.5 hereof or elsewhere hereunder), and the obligations of the Guarantor hereunder are subject to such counterclaims, set-offs or deductions which the DBOM Contractor is permitted to assert pursuant to the DBOM Agreement, if any. SECTION 3.5. WAIVERS BY THE GUARANTOR. The Guarantor hereby unconditionally and irrevocably waives: (1) notice from the City of its acceptance of this Guaranty; (2) notice of any of the events referred to in Section 3.3 hereof, except to the extent that notice is required to be given as a condition to the enforcement of the Obligations; (3) to the fullest extent lawfully possible, all notices which may be required by statute, rule of law or otherwise to preserve intact any rights against the Guarantor, except any notice to the DBOM Contractor required pursuant to the DBOM Agreement or Applicable Law as a condition to the performance of any Obligation; A-83959418.4 047787 CTR 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 3-Guaranty Covenants (4) to the fullest extent lawfully possible, any statute of limitations defense based on a statute of limitations period which may be applicable to guarantors (or parties in similar relationships)which would be shorter than the applicable statute of limitations period for the underlying claim; (5) any right to require a proceeding first against the DBOM Contractor; (6) any right to require a proceeding first against any person or the security provided by or under any Transaction Agreement except to the extent such Transaction Agreement specifically requires a proceeding first against any person (except the DBOM Contractor) or security; (7) any requirement that the DBOM Contractor be joined as a party to any proceeding for the enforcement of any term of any Transaction Agreement; (8) the requirement of, or the notice of, the filing of claims by the City in the event of the receivership or bankruptcy of the DBOM Contractor; and (9) all demands upon the DBOM Contractor or any other person and all other formalities the omission of any of which, or delay in performance of which, might, but for the provisions of this Section 3.5, by rule of law or otherwise, constitute grounds for relieving or discharging the Guarantor in whole or in part from its absolute, present, irrevocable, unconditional and continuing obligations hereunder. SECTION 3.6. PAYMENT OF COSTS AND EXPENSES. The Guarantor agrees to pay the City on demand all Fees and Costs incurred by or on behalf of the City to enforce observance of the covenants, agreements and obligations contained in this Guaranty against the Guarantor, other than the Fees and Costs that the City incurs in performing any of its obligations under the DBOM Agreement, or other applicable Transaction Agreement where such obligations are a condition to performance by the DBOM Contractor of its Obligations. SECTION 3.7. SUBORDINATION OF RIGHTS. The Guarantor agrees that any right of subrogation or contribution which it may have against the DBOM Contractor as a result of any payment or performance hereunder is hereby fully subordinated to the rights of the City hereunder and under the Transaction Agreements and that the Guarantor shall not recover or seek to recover any payment made by it hereunder from the DBOM Contractor until the DBOM Contractor and the Guarantor shall have fully and satisfactorily paid or performed and discharged the Obligations giving rise to a claim under this Guaranty. SECTION 3.8. SEPARATE OBLIGATIONS; REINSTATEMENT. The obligations of the Guarantor to make any payment or to perform and discharge any other duties, agreements, covenants, undertakings or obligations hereunder shall: (1) to the extent permitted by applicable law, constitute separate and independent obligations of the Guarantor from its other obligations under this Guaranty; (2) give rise to separate and independent causes of action against the Guarantor; and (3) apply irrespective of any indulgence granted from time to time by the City. The Guarantor agrees that this Guaranty shall be automatically reinstated if and to the extent that for any reason any payment or performance by or on behalf of the DBOM Contractor is rescinded or must be otherwise restored by the City, whether as a result of any proceedings in bankruptcy, reorganization or similar proceeding, unless such rescission or A-93959418.4 047787 CTR 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 3-Guaranty Covenants restoration is pursuant to the terms of the DBOM Agreement, or any applicable Transaction Agreement or the DBOM Contractor's enforcement of such terms under Applicable Law. SECTION 3.9. TERM. This Guaranty shall remain in full force and effect from the date of execution and delivery hereof until all of the Obligations of the DBOM Contractor have been fully paid and performed. A-1O3959418.4 047787 CTR 4177761.2 047787 ARTICLE 4 GENERAL COVENANTS SECTION 4.1. MAINTENANCE OF CORPORATE EXISTENCE. (A) Consolidation, Merger, Sale or Transfer. The Guarantor covenants that during the term of this Guaranty it will maintain its corporate existence, will not dissolve or otherwise dispose of all or substantially all of its assets and will not consolidate with or merge into another entity or permit one or more other entities to consolidate with or merge into it unless the successor is the Guarantor; provided, however, that the Guarantor may consolidate with or merge into another entity, or permit one or more other entities to consolidate with or merge into it, or sell or otherwise transfer to another entity all or substantially all of its assets as an entirety and thereafter dissolve if the successor entity(if other than the Guarantor) (a) assumes in writing all the obligations of the Guarantor hereunder and, if required by law, is duly qualified to do business in the State of Oregon, (b) delivers to the City an opinion of counsel to the effect that its obligations under this Guaranty are legal,valid, binding and enforceable subject to applicable bankruptcy and similar insolvency or moratorium laws; and (c) has a net worth at the time of any such transaction at least equal to the net worth of the Guarantor immediately prior to such time. (B) Continuance of Obligations. If a consolidation, merger or sale or other transfer is made as permitted by this Section, the provisions of this Section shall continue in full force and effect and no further consolidation, merger or sale or other transfer shall be made except in compliance with the provisions of this Section. No such consolidation, merger or sale or other transfer shall have the effect of releasing the initial Guarantor from its liability hereunder unless a successor entity has assumed responsibility for this Guaranty as provided in this Section. SECTION 4.2. ASSIGNMENT. Except as provided in Section 4.1, this Guaranty may not be assigned by the Guarantor without the prior written consent of the City. SECTION 4.3. QUALIFICATION IN OREGON. The Guarantor agrees that, so long as this Guaranty is in effect, if required by law, the Guarantor will be duly qualified to do business in the State of Oregon. SECTION 4.4. CONSENT TO JURISDICTION. The Guarantor irrevocably: (1) agrees that any Legal Proceeding related to this Guaranty or to any rights or relationship between the parties arising therefrom shall be solely and exclusively initiated and maintained in federal or State courts located in Clackamas County, Oregon, having appropriate jurisdiction therefor; (2) consents to the jurisdiction of such courts in any such Legal Proceeding; and (3) waives any objection which it may have to the laying of the jurisdiction of any such Legal Proceeding in any such court. SECTION 4.5. BINDING EFFECT. This Guaranty shall inure to the benefit of the City and its permitted successors and assigns and shall be binding upon the Guarantor and its successors and assigns. A-113959418.4 047787 CTR 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 4-General Covenants SECTION 4.6. AMENDMENTS, CHANGES AND MODIFICATIONS. This Guaranty may not be amended, changed or modified or terminated and none of its provisions may be waived,except with the prior written consent of the City and the Guarantor. SECTION 4.7. LIABILITY. It is understood and agreed to by the City that nothing contained herein shall create any obligation of, or right to look, to any director, officer, employee or stockholder of the Guarantor (or any Affiliate of the Guarantor) for the satisfaction of any obligations hereunder, and no judgment, order or execution with respect to or in connection with this Guaranty shall be taken against any such director, officer, employee or stockholder. SECTION 4.8. NOTICES. Procedure. All notices, demands or written communications given pursuant to the terms of this Guaranty shall be: (1) in writing and delivered in person; (2) transmitted by certified mail,return, receipt requested, postage prepaid or by overnight courier utilizing the services of a nationally- recognized overnight courier service with signed verification of delivery; or (3) given by email transmission, if a signed original of the emailed letter or other communication is deposited in the United States mail within two days after transmission. Notices shall be deemed given only when actually received at the address first given below with respect to each party. Either party may, by like notice, designate further or different addresses to which subsequent notices shall be sent. (1) City Notice Address. Notices required to be given to the City shall be addressed as follows: City Manager City of Lake Oswego P.O. Box 369 Lake Oswego, OR 97034 Office Phone Number: 503-635-0215 Email: mbennett@lakeoswego.city with a copy to: City Attorney City of Lake Oswego P.O. Box 369 Lake Oswego, OR 97034 Office Phone Number: 503-635-0225 Email: cao@lakeoswego.city (2) Guarantor Notice Address. Notices required to be given to the Guarantor shall be addressed as follows: Jacobs Engineering Group Inc. 1999 Bryan Street Dallas, TX 75201 Attn: Venk Nathamuni Email: Venk.Nathamuni@Jacobs.com with a copy to: A-123959418.4 047787 CTR 4177761.2 047787 Lake Oswego Wastewater Treatment Facility Guaranty Agreement Article 4-General Covenants Jacobs Engineering Group Inc. 7251 E Bellview Ave. Denver, CO 80237 Attn: Hope Anastasakis, Assistant General Counsel Email: Hope.Anastasakis@Jacobs.com SECTION 4.9. ELECTRONIC SIGNATURES. Any party may execute this Guaranty using an electronic signature in accordance with the Oregon Uniform Electronic Transactions Act (ORS 84.019). An electronic or digital signature will have the same force and effect as original ink signatures. [SIGNATURE PAGE FOLLOWS] A-133959418.4 047787 CTR 4177761.2 047787 IN WITNESS WHEREOF, the Guarantor has caused this Guaranty to be executed in its name and on its behalf by its duly authorized officer as of the date first above written. JACOBS ENGINEERING GROUP INC., as Guarantor By: Name: Title: ACCEPTED AND AGREED TO BY: CITY OF LAKE OSWEGO, OREGON By: Name: Title: 4177761.2 047787 ATTACHMENT 3 RESOLUTION 26-55 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE OSWEGO REVISING FEES AND CHARGES TO FINANCE CAPITAL CONSTRUCTION AND OPERATIONS AND MAINTENANCE OF THE LAKE OSWEGO WASTEWATER TREATMENT FACILITY. WHEREAS, the City of Lake Oswego is currently serviced by the Tryon Creek Wastewater Treatment Plant, which is currently owned and operated by the City of Portland; and WHEREAS, the City has adopted from time to time various fees and charges for wastewater treatment services; and WHEREAS, the City is in the process of replacing the Tryon Creek Wastewater Treatment Plant with a new facility designed to provide reliable service, improve water quality, and withstand seismic and flood events for generations to come; WHEREAS, the City intends to execute a Design-Build-Operate-Maintain contract for Lake Oswego Wastewater Treatment Facility("Project"); and WHEREAS, the City Council has reviewed projected capital, operating, maintenance, debt service, and reserve requirements associated with wastewater treatment services and has determined that existing wastewater utility revenues are insufficient to finance the Project and related utility obligations; and WHEREAS, the City Council finds that an adjustment to wastewater utility rates is necessary and reasonable to ensure the continued provision of reliable wastewater treatment services and to finance the Project; and WHEREAS, the City Council finds that wastewater utility rates should be increased by 28 percent effective July 1, 2027, to finance the capital construction, operation, maintenance, and long-term financial sustainability of the Lake Oswego Wastewater Treatment Facility; and WHEREAS, based on current financial projections used in planning and financing the Project, annual wastewater utility rate increases of approximately 3.9 percent are anticipated beginning July 1, 2028; however, future rate adjustments shall remain subject to review and approval by the City Council, which may modify such rates based on actual costs, revenues, financing requirements, operational needs, and other relevant considerations. NOW,THEREFORE, BE IT RESOLVED by the City Council of the City of Lake Oswego that: Section 1. A 28 percent increase to the City's wastewater utility rates is hereby adopted and shall become operative on July 1, 2027. The City Council further acknowledges that the financial plan for the Lake Oswego Wastewater Treatment Facility assumes annual wastewater utility rate increases of approximately 3.9 percent in fiscal years following the July 1, 2027 rate increase; however, such assumptions are provided solely for planning and financing purposes and do not constitute adoption of future rates. Resolution 26-55 Page 1 of 2 Section 2. The revisions to the fees and charges adopted by this Resolution shall be incorporated into the City's Master Fees and Charges Schedule. Section 3. Effective Date. This Resolution shall take effect upon adoption. The wastewater utility rate increase adopted in Section 1 shall become operative on July 1, 2027. Considered and enacted at the regular meeting of the City Council of the City of Lake Oswego on the 13th day of October 2026 AYES: NOES: EXCUSED: ABSTAIN: Joseph M. Buck, Mayor ATTEST: Laural Hawkins, City Recorder APPROVED AS TO FORM: Erica Tatoian, City Attorney Resolution 26-55 Page 2 of 2