Loading...
HomeMy WebLinkAboutAgenda Item - 2001-05-01 - Number 5.2.2 - 5.2.2 CITY OF LAKE OSWEGO 05/01/01 AGENDA REPORT SUMMARY MEETING DATE: May 1, 2001 SUBJECT: Award of a Public Improvement Contract for Construction of the 2001 Street Maintenance Slurry Seals Project (Work Order 1152 - Phase 2) RECOMMENDED MOTION: Move to award a public improvement contract for the construction of the 2001 Street Maintenance Slurry Seals Project, to Blackline, Inc. in the amount of$64,236.29. EST. FISCAL ATTACHMENTS: NOTICED (Date): IMPACT: $64,236.29 • Schoening Council Report dated April 17, 2001 STAFF COST: • List of Project Streets Ordinance no.: N/A BUDGETED: Resolution no.: N/A Y X N Previous Council FUNDING SOURCE: consideration: No Street Fund CITY ENGINEER CITY M NAGER 2 OI Date Date 3 5 H:\Kathy_g\WO\1152\1152_Phase 2\Agenda Summary.doc ``4r of oaf Osw�CO CITY OF LAKE OSWEGO COUNCIL REPORT OREGO$ TO: Douglas J. Schmitz, City Manager FROM: Mark Schoening, City Engineer PREPARED BY: George Dwire, Construction Supervisor SUBJECT: Recommendation of Bid Award for Construction of the 2001 Street Maintenance Slurry Seals Project DATE: April 17, 2001 Action The City Council is requested to award a public improvement contract to Blackline Inc. in the amount of$64,236.29 for the 2001 Street Maintenance Slurry Seals Project. Introduction This Contract requires Council award in order to comply with the City and State contracting and purchasing procedures. Discussion At 11:45 a.m., on Thursday, April 12,2001, the City of Lake Oswego opened bids for the above referenced project. Two bids were received with the apparent low bid being submitted by Blackline,Inc. The bidders and the amount of their bids are tabulated below: Bidder Bid Blackline, Inc. $64,236.29 Asphalt Maintenance Associates $64,548.45 Engineer's Estimate $79,969.72 3 Council Report April 17, 2001 Page 2 of 2 Based upon a review of the bids by staff, the bid submitted by Blackline Inc. was deemed responsive and responsible. Alternatives The alternatives are to: 1) award the contract or 2) reject all bids and re-bid the project. Conclusion City staff prepared the bidding documents for this project in accordance with the City's requirements for public improvement contracts. The bidding process was conducted in accordance with the City's public contracting procedures. Staff, therefore, recommends that Council award the contract to Blackline Inc. in the amount of$64,236.29. H\14thyg\WO\I 152\I 152_Phase 2\Council Report doc 3S Project Streets Pavement Management Slurry Seals 1. Princeton Court- All 2. Cascara Lane - All 3. Parkview Drive - All 4. 8th Street - A Avenue to Evergreen Road 5. 4th Street - A Avenue to Evergreen Road 6. C Avenue - 1st Street Alley east to end 7. B Avenue - 4th Street to State Street 8. Foothills Drive - Oswego Pointe Drive to Foothills Road 9. Westridge Drive — cul-de-sac 10. Woodsman Court - All 11. Wall Street - Robb Street to Greentree Road 12. Scott Court - All 13. Quail Court - All 14. Essex Court - All 15. Windsor Court - All 16. Westminster Drive - Westridge Drive to Buckingham Terrace 17. Westminster Drive - Westridge Drive to end 18. Dover Way - All 19. Lamont Way - Bryant Road to Lakeview Blvd 20. Waxwing Street - All 21. Waxwing Circle - All 22. Waxwing Way - All 23. Wood Duck Street - All 24. Wood Duck Circle - All 25. Wood Duck Way - All 39