HomeMy WebLinkAboutAgenda Packet - 1995-06-01 PM• AGENDA
CITY OF LAKE OSWEGO
CITIZENS' BUDGET COMMITTEE
Council Chambers
380 A Avenue
Lake Oswego, Oregon 97034
June 1, 1995
5:30 P.M.
I. Call to Order
II. Roll Call
• III. Approval of Minutes -- May 18, 1995
IV. Citizen Comment
V. Street Financing
VI. Review of 1995-97 Budget Process
VII. Adjournment
• TRANSPORTATION PROJECTS FINANCING
Maintenance Projects Total $ 5,389,000
Assumed Bond Issuances:
July 1,1996 $ 2,727,000
July 1,1998 $ 2,662,000
1996-97 1997-98 1998-99 1999-2000
Estimated Annual Debt Service $278,000 $278,000 $549,000 $549,000
Gross Property Taxes Required $ 309,000 $ 309,000 $ 610,000 $ 610,000
(90%)
Projected Assessed Value $ 3,465,022 $ 3,742,000 $ 4,041,000 $ 4,364,000
(Thousands of Dollars)
Projected Tax Rate $ 0.09 $ 0.08 $ 0.15 $ 0.14
(per$1,000 of Real Market Value)
Improvement Projects Total $ 6,239,000
Assumed Bond Issuances:
July 1,1996 $ 3,119,500
July 1,1998 $ 3,119,500
•
1996-97 1997-98 1998-99 1999-2000
Estimated Annual Debt Service $318,000 $318,000 $635,000 $635,000
Gross Property Taxes Required $ 353,000 $ 353,000 $ 706,000 $ 706,000
(90%)
Projected Assessed Value $ 3,465,022 $ 3,742,000 $ 4,041,000 $ 4,364,000
(Thousands of Dollars)
Projected Property Tax Rate $ 0.10 $ 0.09 $ 0.17 $ 0.16
(per$1,000 of Real Market Value)
Combined Property Tax Rate Impact
1996-97 1997-98 1998-99 1999-2000
Maintenance Projects $ 0.09 $ 0.08 $ 0.15 $ 0.14
Improvement Projects $ 0.10 $ 0.09 $ 0.17 $ 0.16
TOTAL $ 0.19 $ 0.17 $ 0.32 $ 0.30
$.01 of the Tax Rate Generates: $ 34,650 $ 37,420 $ 40,410 $ 43,640
. Annual Property Taxes on a
$200,000 Property $ 38.00 $ 34.00 $ 64.00 $ 60.00
•
TRANSPORTATION PROJECTS
Maintenance
(In Thousands of Dollars)
1995-96 1996-97 1997-98 1998-99 1999-2000 Total
Overlays/Reconstruction
Maintenance Overlays 60 63 67 70 73 333
Kruse Way Overlay 1,305 1,305
Lakeview Blvd Overlay 743 743
Bryant Rd Overlay 260 260
Laurel Overlay 148 148
Lake Forest Dr Overlay 117 117
N.Shore/N.Shore Cir.Overlay 175 175
S Durham St.Construction 48 48
Bickner St.Reconstruction 26 26
Childs Rd.Overlay 308 308
Pilkington Rd.Overlay 183 183
Chapin Way Overlay 88 88
Oak Street Reconstruction 396 396
Oakridge 76 76
Washington Ct. 150 150
Fosberg 210 210
Douglas Way Overlay 118 118
Twin Fir Rd.Overlay 484 484
Carman Dr.Overlay 140 140
Pathways
Chapin Rd./Cherry Lane 81 81
TOTAL $ 1,365 $ 292 $ 1,070 $ 1,529 $ 1,133 $ 5,389
•
TRANSPORTATION PROJECTS
Improvements
(In Thousands of Dollars)
1995-96 1996-97 1997-98 1998-99 1999-2000 Total
Roadways
Neighborhood Traffic
Management Devices $ 45 $ 50 $ 55 $ 60 $ 65 $ 275
Intersections
McVey/South Shore 388 388
III
State/Terwilliger 1,180 1,180
Kea Signals 550 550
Kruse Way/Westlake 120 120
State&A,State&McVey 556 556
Roadways
A Avenue 2,490 2,490
Kruse Transit 360 360
Pathways
Childs 120 120
Melrose 40 40
South Shore 45 45
Carman 100 100
Wheel Chair Ramps 15 15
TOTAL $ 753 $ 966 $ 4,275 $ 180 $ 65 $ 6,239
III
IMPROVEMENT PROJECTS OPTIONS
(In Thousands of Dollars)
Option A Option B
A Avenue $ 2,490 A Avenue $ 2,490
Pathways 320 State/McVey/A 556
Pathways 320
TOTAL $ 2,810
TOTAL $ 3,366
Property Tax Rate
Impact $0.09 $0.11
Option C Option D
All except A Avenue $ 3,429 McVey/S.Shore $ 388
Pathways 320 Kruse/Westlake 120
State/McVey/A 556
TOTAL $ 3,749 A Avenue 2,490
Pathways 320
TOTAL $ 3,874
111
Property Tax Rate
Impact $0.12 $0.13
Option E Option F
A Avenue $ 2,490 A Avenue $ 2,490
State/McVey/A 556 McVey/S.Shore 388
State/Terwilliger 1,180 Kruse Transit 360
Pathways 320 State/McVey/A 556
State/Terwilliger 1,180
TOTAL $ 4,546 Pathways 320
TOTAL $ 5,294
Property Tax Rate
Impact* $0.15 $0.17
Option G
All Improvements $ 6,239
Property Tax Rate
Impact* $0.20
* Options E,F,and G would probably involve two separate issues separated by
111
two to three years,reducing the initial and peak tax rate impact from that shown.
``�{OF LAKE OS wFCO
Public Works Department
MEMORANDUM
OREGO$
TO: Tom Coffee, Asst. City Manager
FROM: Jerry Baker, City Engineer
RE: Proposed Transportation Improvement Projects for Bond issue
DATE: June 1, 1995
TRANSPORTATION IMPROVEMENTS
• INTERSECTIONS
A Avenue Improvement: This is a continuation of the demonstration street
project to improve A Avenue from State Street to 3rd Street. A Avenue has
moderate rutting, deteriorating asphalt that has been overlaid many times over
the year to the point that the street and sidewalk need to be regraded and
adjusted. This will require that the drainage system be redesigned. First and
Second Streets will be signalized for pedestrian safety and shoppers'
convenience. Work will include engineering, demolition, grading, paving, traffic
signals and channelization. *$2,490,000
*Total project cost with LORA, SDC and water participation is $2,700,000.
State Street
State and A: Improvement includes the installation of one additional right turn
lane to the northbound approach of A Avenue. This will improve the operation
of the existing traffic signal and alleviate some of the congestion on A Avenue.
The cost includes engineering, demolition, a new traffic signal, curb and sidewalk
work, and some grade work on A Avenue.
111
Page 1 of 3
S
State and McVey: Improvement consists of adding two opposing left turn lanes
on Highway 43 at McVey to solve a safety problem. Left turn accidents occur at
rate of about 6 to 10 per year. The cost includes engineering, street widening,
bridge widening, traffic signal modernization.
Total City participation of State Street projects $556,000
This amount is 30% of project cost. State has committed 50% and Clackamas
County will provide 20% of the project.
South Shore and McVey: Improvement consists of reconstruction of the
intersection and the installation of a traffic signal. This intersection is congested
and it is very difficult to enter the stream of traffic on McVey from South Shore.
This project was projected to be installed in conjunction with commercial
development of Grimm's Corner to obtain the right-of-way necessary for the
addition of traffic lanes and rechannelization. Work includes engineering, street <<
demolition, right-of-way acquisition, traffic signal, channelization. $388,000
Kerr Parkway Traffic Signals: This project includes traffic signal installation
at Kerr and Touchstone and Kerr and Lower McNary. The signals will create
gaps in the traffic stream on Kerr and allow side street traffic access to occur.
Left turn lanes will also be installed on Kerr Parkway. The project will include
. engineering, right-of-way acquisition, traffic signals, channelization, and paving
at intersections. $550,000
Terwilliger/Hwy. 43: This project consists of the reconstruction of the
intersection and a traffic signal. A major traffic safety issue will be the addition
of a left turn lane for traffic from Highway 43 onto Terwilliger. Work includes
engineering, demolition, rock excavation, grading, traffic signal, paving, and
channelization. $1,180,000
Kruse Way and Westlake Drive: This improvement would allow a right turn
lane from Kruse Way onto Westlake. The project would improve the safety of
the intersection by removing the potential of a rear end collision from vehicles
slowing to make a right turn. This project would include engineering right-of-
way acquisition, grading, signal changes, and paving. $120,000
PATHWAY CONNECTIONS
Chapin/Cherry Lane Pathway (Chapin Way to Hallinan School): This
pathway is along Cherry Lane and will be used as a school route and a way for
children and adults to access the school playground. Some drainage work along
. the road will be necessary to provide enough pathway walking width. This
project should be done in conjunction with the Chapin Street overlay project. $81,000
Page 2 of 3
. Melrose (Bunick to 300' east): The project is on the south side of Melrose. It
connects completed pathways on either side. It is a school route and will
connect to the park from the school. $40,000
South Shore (Westview to Blue Heron): This pathway will enable the Blue
Heron residents to access the South Shore pathway at a crossing at an all-way
stop. $45,000
Carman Drive (Waluga to Quarry): This pathway will be on the east side of
Carman Drive. It will complete the circular route or loop around Waluga path.
It will enable the young students from lake Grove Elementary to use this path as
a school route and a route to Waluga Park. $100,000
Childs Road Pathway (Canal Road to Sycamore): This pathway will connect
the sidewalk of the Childs Road Canal Bridge to a Rivergrove pathway that ends—
at Sycamore. It will improve pedestrian access to Bryant Park. This project
should be done in conjunction with the Childs Road overlay project. $120,000
Wheel Chair Ramps: This project would construct 30 ramps at various
locations in the city(commercial areas). --- $15,000
• OTHER IMPROVEMENTS
Kruse Way Transit Improvements: This project would help implement the
Kruse Way Traffic Management Program. Presently, buses use the right-turn
lanes for a bus pull out. Far side bus pullouts would allow buses to move out of
the moving lane of traffic to load passengers. There are nine high priority
locations on Kruse Way(shown on attached map). $360,000
NTAB's Annual Project List: These projects will include traffic management
devices approved by the Neighborhood Traffic Advisory Board. They are
typically speed bumps, traffic circles, chicanes, curb extensions, etc. The amount
included is for the 5 year projected expenditures shown in the CIP. $275,000
JB/kaa
Attachment
c:\winword\pw\jeny_b\TNTRSCTN.DOC
10
Page 3 of 3
41
z
-iSri...... ...._:.....‘..... ....\\
LEGEND: i
Melrose
=BUS S
TRANSFTOP ER POINT
a
Ct
) •••Vt.
• * •
• •
3 •
•
#:
n '.• + .,n
/D .. .. ....• . Cor
• . 1,4
T Kruse Way
• *
•
/9. •. •. .
�n • '^ Meadows :' :•
: o
• co •
Bonito •
• a„
Figure 10
Suggested Future Transit Service
11/
Current Pathway Proposals
June 1, 1995
Street Improvement Length Cost
Melrose/ Sidewalk 313 If $40,000
Westview*/ Pathway 500 If $100,000
South Shoret Pathway at request of neighborhood 540 if $45,000
(Westview to Blue association - path on other side of
Heron) South Shore
Upper*t Original pathway route still wanted 1,650 1f $85,000
(Reese to Bryant) by LGNA
Carman Drive.; On Pathway Master Plan - lack of 1,800 if $100,000
(Waluga to Quarry) funds
Greentree* Connect existing sidewalks to South 685 If $80,000
(Cherry Crest to Shore, some storm.
Greentree Estate)
A Avenue/ Completes all of A Avenue sidewalk 150 If $9,000
Glenmorrie* Connects Marylhurst to Cherry to 250 If $12,500
(at Cherry) Chapin School at Hallinan, school
route
* Completes Transit Route
-1- Neighborhood Association Request
+ Completes Pathway Loop
PATHWAYS.DOC